1 May 2, 2024
City of Corona
400 S. Vicentia Avenue
Corona, CA 92882
Attn: Mr. Nathan Armendariz
Subject: Budget Amendment Request No. 2 ‐ Construction Management and Inspection Services for the WRCRWA Reclaimed Waterline Project
Dear Mr. Armendariz:
Pursuant to our previous conversation, AKM Consulting Engineers is submitting a budget amendment request for the WRCRWA Reclaimed Waterline Project. The additional budget is being requested due to the Construction Contractor not completing the work within the original contract duration. The following additional budget is requested. This budget amendment proposal assumes that all work on the project will be completed no later than May 17, 2024.
Task Hours Totals
Additional Construction Management ($170/hour) 68 $11,560.00 Additional Construction Inspection ($155/hour) 386 $59,830.00 Additional Project Management ($220/hour) 14 $3,080.00
Total Cost $74,470
Additional Funds Requested: $74,470
Previous Approved Budget: $274,914
New Requested Project Total Budget: $349,384
We appreciate the opportunity to submit this budget amendment request and look forward to being of continued service to the City of Corona. Should you have any questions, please do not hesitate to contact the undersigned.
Very truly yours,
AKM Consulting Engineers
Emin Kayiran
Vice President/Director of Construction Management Services