Date: 5/5/2021 Page 1 of 2
PROJECT DESCRIPTION:
PROJECT NO: NIB 21-012CA, 2018-11 PURCHASE ORDER NO: P21893 CONTRACTOR: Pacific HydroTech Corporation JL NO:
DESCRIPTION OF CHANGES AND/OR EXTRA WORK: No cost extension of contract time of 45 working days.
Cable rail system on top of retaining wall.
Additional layer of CMU block added to retaining wall.
ITEM U/M QUANTITY UNIT PRICE TOTAL
S-1 N/A N/A N/A N/A
S-2 LS 1.00 $8,850.80 $8,850.80
S-3 LS 1.00 $508.95 $508.95
TOTAL ESTIMATED PRICE FOR THIS CHANGE ORDER: $9,359.75
JUSTIFICATION:
S-1
S-2
S-3
CCO # Amount % Date Approved
1 $9,359.75 0.18%
Total $9,359.75 0.18%
$5,217,455.75
Original Completion Date: 2/8/2022 Revised Completion Date: 2/8/2022 Install approximately 20 feet of 8" CMU block on the
northeast section of the retaining wall.
Approximately 20 feet of the new retaining wall was designed to be at the same elevation as the finished surface of the new asphalt pavement whereas the remaining retaining wall will be 8" higher than pavement finish grade. City directed contractor to install an additional 8" course of CMU block over the 20 foot segment of wall to provide a curb around the pavement.
DESCRIPTION
No cost extension of contract time of 45 working days
CONTRACT VARIANCE SUMMARY
During the project bidding phase, City issued Addendum #1 which increased the number of working days from 225 to 270 working days The executed contract with Pacific HydroTech reflects the old 225 workings days whereas 270 working days were granted per the addendum. The project began on January 14, 2021 and project completion date based on 270 workings days is confirmed to be Febuary 8, 2022.
A time extension of 45 working days to complete the project is granted as an administrative adjustment to align with the contract.
See details under Item S-1 below.
Revised Contract Amount:
Time Working Days
Install 225 lineal feet of 3 foot high cable railing along the top of the retaining wall.
CITY OF CORONA
The Contractor is hereby directed to make the herein described changes from the plans and specifications and/or perform the following described work not included in the Plans and Specifications for this project.
WRF-3 Sewer Lift Station
Department of Water and Power
CONTRACT CHANGE ORDER NO. 1
Construct a sewer lift station station.
69880572
45 Date Started: 01/4/2021
This document shall become an amendment to the Contract and all provisions of the Contract will apply hereto. This Change Order constitutes a complete and final resolution of all claims of the Contract for additional time or additional compensation related to or affected by work that is the subject of this Change Order. Quantities of items other than Lump Sum are not to exceed the amounts indicated.
Original Contract Amount: $5,208,096.00
45 5/5/2021
An approximate 200-ft by 30-ft extension of the paved access road is being constructed for access and future communications tower construction. The new 4-foot high retaining wall is being constructed along the edge of the asphalt pavement extension to support the northerly edge of the pavement extension. The City retaining wall standard does not include a railing. Therfore, a fall barrier needs to be be provided as a safety measure along the top of wall where the upper finish grade is accessible by vehicles and personnel. The 3 foot high cable rail system is a Caltrans standard construction detail and will be constructed on top of the retaining wall.
DocuSign Envelope ID: 6141984D-AF0A-4B1E-BD21-7170028BFC17 Date: 5/5/2021 Page 2 of 2
AUTHORIZATION BY CITY:
Recommended for approval by:
Date: __________ ____________________________________________ Date: __________ Steve Patterson Gull Nawaz
Consultant Construction Manager Project Manager
Approved by:
Date: __________ ____________________________________________ Date: __________ Vernon R. Weisman, P.E. Savat Khamphou
Acting Public Works Director & City Engineer
Date: __________
Tom Moody
ACCEPTANCE BY CONTRACTOR:
Greg Chehey Project Manager
Accepted by: _____________________________________________________ Title: ____________________________ (Please print name and title)
Signature: _____________________________________________________ Date: ____________________________ DWP General Manager
District Engineer
We, the undersigned Contractor, have given careful consideration to the above described changes and/or extra work and hereby agree that said work is the subject of this Change Order. Quantities of items other than Lump Sum are not to exceed the amounts indicated.
________________________________________
________________________________________
____________________________________________
DocuSign Envelope ID: 6141984D-AF0A-4B1E-BD21-7170028BFC17 5/6/2021
5/11/2021 5/11/2021
5/11/2021 5/13/2021
5/17/2021
PACIFICHYDROTECHCORPORATION
314 E. 3RD ST, PERRIS, CA 92570
(951) 943-8803 FAX (951) 943-1093
April 5, 2021
City of Corona
755 Public Safety Way
Corona, CA 92880
Attn: Vernon Weisman
Reference: WRF-3 Lift Station Project
Project No. 2018-11
Subject: Proposal for Cable Railing Fence to Retaining Wall AKM Email Dated March 8, 2021
Mr. Weisman:
REV 1: Revised per comments dated 3/26/21. See attached Notes to Reviewer page for PHC responses to these comments.
In response to an AKM email dated March, 8th 2021, The City has requested a proposal to procure and install a new Cable Railing Fence to the CMU retaining wall east of the new driveway. This fence will be per the attached Cal-Trans standard drawing.
Please note that the Cal Trans drawing provided was intended for a cast in place concrete wall, and not a CMU retaining wall. PHC will be grouting the posts into the CMU cells with an embed depth of 12”. This way the posts will be embedded 4" +- into the second course of block. Additionally, there will be a step in the railing height to account for the T.O.W elevation changes. PHC will keep the railing at 3’ from top of block consistent for the entire length of the cable railing fence as shown in the attached New Construction detail.
Please review the proposed lump sum cost below:
Cable Railing Fence to Retaining Wall Total .............................................................. $8,850.80 Scope of work detailed above includes all necessary tax and mark up, including bonds and insurance.
See attached for breakdown, and backup documents.
Sincerely,
PACIFIC HYDROTECH CORPORATION
Dustin Chehey
Project Coordinator
DocuSign Envelope ID: 6141984D-AF0A-4B1E-BD21-7170028BFC17 Pacific Hydrotech Corporation
314 E. 3rd Street
Perris, CA 92570
Phone: (951) 943-8803
Fax: (951) 943-1093
PHC Project Number: C2024
Project Name: WRF3 Lift Station
Change Order: COR 002-R1
Description: Cable Railing Fence to Retaining Wall
NOTES TO REVIEWER
In response to the comments received for the subject change order, PHC offers the following:
• Article 29 of the General Conditions describes the cost of labor will be wages prevailing locally for each craft or type of worker, plus payroll taxes and insurance, health and welfare, pension, vacation, apprenticeship funds, and other direct costs resulting from Federal, State or local laws, as well as assessment or benefits required by lawful collective bargaining agreement. o PHC Response: Noted. Labor rate has been revised to reflect the total direct costs PHC will pay for a Group 4 Laborer. Prevailing wage rate breakdown of all trades will be forward in a separate email for the Owners reference for any future change orders.
• Technical Specification Section 01 22 00 Unit Prices, part 3.44 Stipulated Bid Item A2 - Allowance for Field Orders - Contractor's hourly charge rate for labor, tools and equipment shall not exceed published Caltrans rates of similar labor, tools, and equipment. o PHC Response: Cal Trans Prevailing Wage Rates utilize the breakdown provided in separate email. With these Prevailing Wage Rate breakdown, PHC will also provide the CalTrans equipment rental rates for future reference.
• Please provide certified copies of payroll for review and verification of labor rates. o PHC Response: Noted. Certified Payroll Reports will be forwarded to The City monthly.
• General Conditions Article 29 Change order Work, costs of applicable insurance and bond premiums will be reimbursed at a rate of 1% of the Net Cost of work. Net costs exclude markup. o PHC Response: Noted.
DocuSign Envelope ID: 6141984D-AF0A-4B1E-BD21-7170028BFC17
COST PROPOSAL
(Changed Condition)
Cable Railing Fence Printed: 4/5/2021
Cable Railing Fence to CMU Retaining Wall
PHC Labor
Qty Item Hours Rate Total
2 Laborer 40 $ 72.75 $ 2,910.00
Labor $ 2,910.00
PHC Equipment
Qty Item Hours Rate Total
1 Job Truck 24 $ 25.00 $ 600.00
Equipment $ 600.00
PHC Material
Qty Item UM Rate Total
1 Cable Railing Materials LS $ 4,120.00 $ 4,120.00
Material $ 4,120.00
Subtotal $ 7,630.00
15.0% PHC Markup $ 1,144.50
1.0% Bonds/Ins. $ 76.30
Total for Cable Railing Fence $ 8,850.80
PHC Job: C2024 WRF-3 Lift Station Page 1 of 1
DocuSign Envelope ID: 6141984D-AF0A-4B1E-BD21-7170028BFC17
Addendums (0)
Team West Contracting, proposes to supply and install the following items. Due to volatility of the current supply market, proposal must be signed within 60 days from above date and project must start within 120 days, or a material price increase may occur. We are bondable at 2.5%; however, it is not included in proposal.
Proposed Material and area of work:
1. Furnish Materials Only for Approx. 224 LF of 4’ Cable Railing Proposed Cost: $4,120.00
Per Fence detail, Plans, & Fencing specifications.
Exclusions: Grading, staking, clearing, grubbing, coring, locksets, permits, demolition, mow strip, "V"-track installation, post sleeves & installation, spoils removal, core drilling, saw cutting, backfilling, concrete patching, asphalt patching, painting, temp fence, signs, concrete flat work, electrical, grounding, knox boxes, irrigation, surveying, existing underground pipes & electrical wiring, engineering, shop and field inspections & testing, ADA regulations, payment & performance bonds & fees, waiver of subrogation, excess liability policies and Union agreements.
Eric Negrete
Estimator
Office: (909)421-4450
Cell: (951)522-5192
Signature below will be considered acceptance of above proposal and notice of intent to award so as to begin the preparation of submittals.
Scope of work accepted: Print name: ______________________ initial: _________Date: _________ Job Name: Cable Railing Material
Re: Fencing & Gates
Attn: Estimating
Date: 03-15-2021
Non-Union Company
Lic. # 934352
DIR# 1000633737
Team West Contracting Corporation
2733 Vista Ave, Bloomington, Ca, 92316
* SBE
(909) 421-4450 Phone (909) 421-4471 Fax
DC 4/1/21
DocuSign Envelope ID: 6141984D-AF0A-4B1E-BD21-7170028BFC17 Sht. of
15-033U
5 71
Cable Railing Fence to
be installed to Red
highlighted area only.
DocuSign Envelope ID: 6141984D-AF0A-4B1E-BD21-7170028BFC17 DocuSign Envelope ID: 6141984D-AF0A-4B1E-BD21-7170028BFC17
PACIFICHYDROTECHCORPORATION
314 E. 3RD ST, PERRIS, CA 92570
(951) 943-8803 FAX (951) 943-1093
April 9, 2021
City of Corona
755 Public Safety Way
Corona, CA 92880
Attn: Vernon Weisman
Reference: WRF-3 Lift Station Project
Project No. 2018-11
Subject: Additional Block Course T&M
Mr. Weisman:
On 4/5/21 PHC was directed by AKM to place an additional course of CMU Block (15 total block) at the west most side of the retaining wall.
Please review the proposed T&M cost below:
Additional Block Course T&M.................................................................................. $508.95 Scope of work detailed above includes all necessary tax and mark up, including bonds and insurance.
See attached for breakdown, and backup documents.
Sincerely,
PACIFIC HYDROTECH CORPORATION
Dustin Chehey
Project Coordinator
DocuSign Envelope ID: 6141984D-AF0A-4B1E-BD21-7170028BFC17
COST PROPOSAL
(Changed Condition)
Cable Railing Fence Printed: 4/6/2021
Additional Block Course T&M
PHC Labor
Qty Item Hours Rate Total
5 Laborer 5 $ 72.75 $ 363.75
Labor $ 363.75
PHC Equipment
Qty Item Hours Rate Total
1 Job Truck 1 $ 25.00 $ 25.00
Equipment $ 25.00
PHC Material
Qty Item UM Rate Total
1 MISC Materials LS $ 50.00 $ 50.00
Material $ 50.00
Subtotal $ 438.75
15.0% PHC Markup $ 65.81
1.0% Bonds/Ins. $ 4.39
Total for Cable Railing Fence $ 508.95