Date: 6/23/2021 Page 1 of 2
PROJECT DESCRIPTION:

PROJECT NO: NIB 21-012CA, 2018-11 PURCHASE ORDER NO: P21893 CONTRACTOR: Pacific HydroTech Corporation JL NO:

DESCRIPTION OF CHANGES AND/OR EXTRA WORK: Extra work to perform potholing for new sewer manhole installation.

Extra work to relocate existing utilities for new sewer manhole installation.

ITEM U/M QUANTITY UNIT PRICE TOTAL
1 LS 1.00 $5,532.63 $5,532.63
2 LS 1.00 $22,550.11 $22,550.11
TOTAL ESTIMATED PRICE FOR THIS CHANGE ORDER: $28,082.74 JUSTIFICATION:

Per CCO #2, a time extension of 84 working days was granted to complete shoring installation, dewatering the lift station site, and relocating utilities. The time extension of 45 days granted in CCO#1 corrected an administrative error in the purchase order and did not affect the original completion date. See details below.

Item 1
Item 2
CCO # Amount % Date Approved
1 $9,359.75 0.18%
2 $130,394.49 2.50%
3 $28,082.74 0.54%
Total $167,836.98 3.22% Number of days impacting the schedule. $5,375,932.98
Original Completion Date: 2/8/2022 Revised Completion Date: 6/9/2022

DESCRIPTION
Perform additional potholing in front of the WRF-3 control building to investigate conflicting utilities for new sewer manhole installation.

CONTRACT VARIANCE SUMMARY
The design plans show that the new sewer manhole in front of the WRF-3 control building would be constructed directly over an existing fiber optic line that connects to the WRF-3 SCADA system equipment that is located inside of the control room. Two new locations, east and west of the design location, were selected for relocating the new manhole.

Additional potholing was required at the (2) new locations to investigate if any existing utilities could conflict at the new locations. Potholing the (2) new locations were not covered in contractor's bid.

Revised Contract Amount:

Time Working Days
Relocate conflicting 6" WAS line and (2) electrical
conduits in front of WRF-3 control building to enable new sewer manhole installation.
84 0
6/9/2021
6/23/2021

CITY OF CORONA
The Contractor is hereby directed to make the herein described changes from the plans and specifications and/or perform the following described work not included in the Plans and Specifications for this project.

WRF3 Sewer Lift Station
Department of Water and Power
CONTRACT CHANGE ORDER NO. 3
Construct a sewer lift station.
69880572
84 Date Started: 01/4/2021
This document shall become an amendment to the Contract and all provisions of the Contract will apply hereto. This Change Order constitutes a complete and final resolution of all claims of the Contract for additional time or additional compensation related to or affected by work that is the subject of this Change Order. Quantities of items other than Lump Sum are not to exceed the amounts indicated.

Original Contract Amount: $5,208,096.00
45 5/5/2021
After contractor completed the additional potholing at the (2) new locations where the manhole would be relocated, contractor discovered the following conflicting utilities at the preferred location: a 6" WAS line and (2) electrical conduits.

The longitudinal running utilities would conflict with the perpendicular 12' by 12' trench shoring box which is required to construct the proposed 18 ft deep manhole. Relocating the trench shoring box further away from the conflicting utilities is not possible. Therefore, placement of the trench shoring box into the 18 ft deep excavation necessitates relocating these utilities out of the way.

DocuSign Envelope ID: 40EB683F-6D88-483A-8B45-DD2444E70580 Date: 6/22/2021 Page 2 of 2
AUTHORIZATION BY CITY:

Recommended for approval by:

Date: __________ _________________________________Date: __________ Steve Patterson Gull Nawaz
Consultant Construction Manager Project Manager
Approved by:

Date: __________ _________________________________Date: __________ Vernon R. Weisman, P.E. Savat Khamphou
Acting Public Works Director & City Engineer
Date: __________
Tom Moody
ACCEPTANCE BY CONTRACTOR:

Greg Chehey Project Manager
Accepted by: _______________________________________________ Title: ____________________________ (Please print name and title)
Signature: _______________________________________________ Date: ____________________________ DWP General Manager
District Engineer
We, the undersigned Contractor, have given careful consideration to the above described changes and/or extra work and hereby agree that said work is the subject of this Change Order. Quantities of items other than Lump Sum are not to exceed the amounts indicated.
_____________________________
_____________________________
_____________________________
DocuSign Envelope ID: 40EB683F-6D88-483A-8B45-DD2444E70580 6/23/2021
6/23/2021 6/23/2021
6/23/2021 6/28/2021
6/29/2021

PACIFICHYDROTECHCORPORATION
314 E. 3RD ST, PERRIS, CA 92570
(951) 943-8803 FAX (951) 943-1093
June 4, 2021
City of Corona
755 Public Safety Way
Corona, CA 92880
Attn: Vernon Weisman
Reference: WRF-3 Lift Station Project
Project No. 2018-11
Subject: Proposal for Additional Potholing
AKM Email Dated May 17, 2021 (Revised for follow-up T&M pothole work) Mr. Weisman:

In response to RFI 010.1, The City has requested a proposal for additional potholing to the existing fiber optic line and WAS line.

Per onsite discussion today (5/20/21) PHC will pothole on both sides of the Fiber Optic Line for the most suitable location for the new Manhole, and existing WAS line tie-in point.

After the report of the pothole findings is submitted, The City, AKM, and PHC will discuss best course of action.

After which, PHC will submit the proposal for these conflicting utilities.

Revised cost proposal as follows:

Additional Potholing Total (LUMP SUM).................................................................... $4,662.84 Follow-up Pothole Work performed T&M (worksheet attached) .............................. $869.79 TOTAL Additional Potholing Total............................................................................... $5,532.63 Scope of work detailed above includes all necessary tax and mark up, including bonds and insurance.

See attached for breakdown, and backup documents.

Sincerely,

PACIFIC HYDROTECH CORPORATION
Dustin Chehey
Project Coordinator
DocuSign Envelope ID: 40EB683F-6D88-483A-8B45-DD2444E70580

COST PROPOSAL
(Additional Potholing)
Additional Potholing
(Rev. A)
Printed: 6/4/2021
Additional Potholing
Original Pothole Work at WAS Line
Labor
Qty Item Hours Rate Total
2 Laborer 12 $ 72.75 $ 873.00
Labor $ 873.00
Equipment
Qty Item Hours Rate Total
1 Job Truck 6 $ 25.00 $ 150.00
1 Backhoe 1 $ 46.69 $ 46.69
Equipment $ 196.69
Potholing Service
Qty Item UM Rate Total
1 Ultra Engineering DAY $ 2,950.00 $ 2,950.00
Potholing Service $ 2,950.00
Subtotal $ 4,019.69

15.0% PHC Markup $ 602.95

1.0% Bonds/Ins. $ 40.20
Total for Original Pothole Work at WAS Line $ 4,662.84
Additional Work Performed (T&M Worksheet attached)
Labor
Qty Item Hours Rate Total
1 Foreman/Operator 3 $ 93.50 $ 280.50
1 Laborer 3 $ 72.75 $ 218.25
Labor $ 218.25
Equipment
Qty Item Hours Rate Total
1 Job Truck 3 $ 39.12 $ 117.36
1 Backhoe 3 $ 46.69 $ 140.07
Equipment $ 257.43
Electrical Sub
Qty Item UM Rate Total
1 Mark Maddox LS $ 300.00 $ 300.00
Electrical Sub $ 300.00
Subtotal $ 775.68
Markup for Labor and Equipment 15% $ 71.35
Markup for Electrical Sub 5% $ 15.00

1.0% Bonds/Ins. $ 7.76
Total for Additional Work Performed (T&M Worksheet attached) $ 869.79 GRAND TOTAL EXTRA WORK $ 5,532.63
PHC Job: C2024 WRF-3 Lift Station Page 1 of 1
DocuSign Envelope ID: 40EB683F-6D88-483A-8B45-DD2444E70580

TIME & MATERIALS SHEET
DATE
Job# 25-May-21

NAME S M T W TH F COMMENTS
Roger Morehart 3 Pothole 24’’ gravity sewer line at tie in point Travis Hawkins 3 Pothole 24’’ gravity sewer line at tie in point Mark Maddox 1 Identify 2 electrical conduits

EQUIPMENT S M T W TH F COMMENTS
Truck T-182 3
Backhoe B-23 3 S I g n a t u r e s
C2024
DocuSign Envelope ID: 40EB683F-6D88-483A-8B45-DD2444E70580

PACIFICHYDROTECHCORPORATION
314 E. 3RD ST, PERRIS, CA 92570
(951) 943-8803 FAX (951) 943-1093
June 3, 2021
City of Corona
755 Public Safety Way
Corona, CA 92880
Attn: Vernon Weisman
Reference: WRF-3 Lift Station Project
Project No. 2018-11
Subject: Relocate WAS Line and Electrical for New Sewer Manhole – Rev. A (Eliminated Protecto Lining to Ductile Iron Pipe)
Mr. Weisman:

As agreed during our recent jobsite meeting, PHC proposes to relocate existing 6” WAS line and electrical that will interfere with our shoring at the new starting sewer manhole located just west of the WAS pump station. These relocated utilities will be constructed such that they can remain in continued service for the duration of the WRF3 Sewer Lift Station project. The plan for WAS line relocation is to utilize existing 6” plug valve discharge and continue with restrained ductile iron pipe above ground near existing curb and then down to connect to existing WAS line just east of where the primary electrical duct bank turns to enter the electrical building. A thrust block will be placed against the tie-in to restrain the existing line. There is one (1) active electrical conduit with wiring that will be de-energized and relocated around our proposed excavation in a shallow trench with pull boxes on either end. See attached sketches for proposed layout and additional details.

WAS Line and Electrical Relocation at Sewer Manhole ....................................... $22,550.11 • The ductile iron pipe and fittings are proposed with standard cement mortar lining. • Due to limited availability, ductile pipe/fittings may be combination of std black and red prime coating. • PHC considered alternate materials and discussed with Frank at City of Corona but due to pressure rating and above ground service, we were unable to find a suitable alternative that would provide cost savings. • The pull boxes are proposed as traffic rated of nominal size to receive this one conduit and wiring.

Draining of existing WAS line by City Operations. PHC will need 8hr shutdown of the WAS pumps to make the connections and then minimum over-night to cure thrust block prior to putting the bypass back into service. See attached for breakdown, and backup documents.

Sincerely,

PACIFIC HYDROTECH CORPORATION
Greg Chehey
Project Manager
DocuSign Envelope ID: 40EB683F-6D88-483A-8B45-DD2444E70580 DocuSign Envelope ID: 40EB683F-6D88-483A-8B45-DD2444E70580 PHC Job: C2024 COST PROPOSAL
WAS Line Relocation
Printed: 6/3/2021
WAS Line and Electrical Relocation at Manhole
LABOR
Qty Item Hours Rate Total
1 Foreman 24 $ 93.50 $ 2,244.00
1 Operator 24 $ 93.50 $ 2,244.00
3 Laborer 24 $ 72.75 $ 5,238.00
LABOR $ 9,726.00

EQUIPMENT
Qty Item Hours Rate Total
1 Job Truck 24 $ 39.12 $ 938.88
1 Backhoe 24 $ 46.69 $ 1,120.56
1 Jumping Jack 8 $ 9.32 $ 74.56
EQUIPMENT $ 2,134.00

MATERIAL
Qty Item UM Rate Total
1 DI Pipe and Fittings LS $ 6,639.02 $ 6,639.02
1 Misc Materials LS $ 500.00 $ 500.00
1 Concr Thrust Block LS $ 250.00 $ 250.00
MATERIAL $ 7,389.02
OTHER
Qty Item UM Rate Total
3 Saw Cut AC Pavement Hrs $ 175.00 $ 525.00
1 Dispose Excess Mtl Load $ 250.00 $ 250.00
1 Shoring LS $ 200.00 $ 200.00
OTHER $ 975.00

SUBCONTRACTORS
Qty Item UM Rate Total
1 Mark Maddox Elec. LS $ 1,500.00 $ 1,500.00
SUBCONTRACTORS $ 1,500.00
Subtotal All Items $ 19,249.02
Markup for Labor, Equipment, Material, Other 15.0% $ 3,033.60 Markup for Subcontractors 5.0% $ 75.00
Bonds & Insurance 1.0% $ 192.49
Total for WAS Line and Electrical Relocation at Manhole $ 22,550.11 WAS Line and Electrical Relocation - Rev. A.xlsx WRF-3 Lift Station Page 1 of 1 DocuSign Envelope ID: 40EB683F-6D88-483A-8B45-DD2444E70580

PROPOSAL
5671 GATES ST CHINO, CA - 91710
PHONE: (909)597-7000 | FAX: (909)597-7050
QUOTE DATE EXPIRATION DATE QUOTE NO.
05/28/21 06/27/21 1109204-00
JOB ID PAGE NO.

C2024 1
CUST #: 100021

BILL TO

PACIFIC HYDROTECH CORP
314 E 3RD ST
PERRIS, CA 92570

SHIP TO
PACIFIC HYDRO "WRF-3 LS"
4003 TEMESCAL CANYON RD.

CORONA, CA

INSTRUCTIONS
ATTN: RON

SHIP POINT VIA SHIPPED TERMS
CHINO OUR TRUCK 2% 10TH PROX

CONTACT
PHONE
EMAIL
Ron Harrison
(951)830-9950
[email protected]

LN PRODUCT AND DESCRIPTION ORDERED BO SHIPPED UM PRICE NET AMOUNT Member Since

6 6-8-FF-8H 8 8 EA 3.15 25.20
6X1/8 8H FF CI RUBBER GSKT
7 BN6-B8M-BLUE# 15 15 EA 38.40 576.00
6 150# T316 B8M B/N/W SET W/ BLUE NUTS
8 BF-06 1 1 EA 77.90 77.90
6 DI BLIND FLG
11 MFA-06 7 7 EA 78.40 548.80
6 DI C153 MJXFLG ADAPTER
12 F90-06 4 4 EA 170.80 683.20
6 DI FLG 90
13 F45-06 2 2 EA 151.80 303.60
6 DI FLG 45
14 6FF176# 2 2 EA 1074.70 2149.40
6X17'-6" FXF DI SPOOL
15 6PP176# 2 2 EA 898.70 1797.40
6X17'-6" PXP DI SPOOL
8 Lines Total Qty Shipped Total 41 Total 6161.50
Taxes 477.52
Invoice Total 6639.02