Date: 1/29/2025 Page 1 of 2
PROJECT DESCRIPTION:

PROJECT NO: NIB 21-012CA, 2018-11 PURCHASE ORDER NO: P21893 CONTRACTOR: Pacific HydroTech Corporation Orginal Project Scope JL NO: 69880572 MLD Scope JL NO: 69881572
DESCRIPTION OF CHANGES AND/OR EXTRA WORK:

ITEM U/M QUANTITY UNIT PRICE TOTAL
1 LS 1.00 $168,186.39 $168,186.39
2 LS 1.00 $550,000.00 $550,000.00
3 LS 1.00 $207,440.31 $207,440.31
TOTAL ESTIMATED PRICE FOR THIS CHANGE ORDER: $925,626.70 JUSTIFICATION:

Item 1
Item 2
Item 3
PCO 025 Shoring and Temporary Fencing Rentals
May 2025 - December 2025
Project Shutdown, Pac Hydro continues to accrue costs outside of bid item scope of work on trench shoring and temporary fencing rentals with extended overhead items ($29,634.33 monthly) over a 8 month time span.

In coordination for a reinterment plan, the City requests for Pac Hydro for providing requested field work, equipment to be used, mechanical training, standby pay rates, site facility rentals and schedule of work.

DESCRIPTION
PCO 023 Shoring and Temporary Fencing Rentals
November 2024 - April 2025
Project Shutdown, Pac Hydro continues to accrue costs outside of bid item scope of work on trench shoring and temporary fencing rentals with extended overhead items ($29,634.33 monthly) over a 6 month time span.

A full stop occured September 19, 2022 for Pac Hydro to complete construction bid items and/or City requested site improvements.

PCO 024 Reinterment Plan

CITY OF CORONA
The Contractor is hereby directed to make the herein described changes from the plans and specifications and/or perform the following described work not included in the Plans and Specifications for this project.

WRF3 Sewer Lift Station
Utilities Department
CONTRACT CHANGE ORDER NO. 8
Construct a sewer lift station.

This document shall become an amendment to the Contract and all provisions of the Contract will apply hereto. This Change Order constitutes a complete and final resolution of all claims of the Contract for additional time or additional compensation related to or affected by work that is the subject of this Change Order. Quantities of items other than Lump Sum are not to exceed the amounts indicated.

Date: 1/29/2025 Page 2 of 2
CCO # Amount % Date Approved
1 $9,359.75 0.18%
2 $130,394.49 2.50%
3 $28,082.74 0.54%
4 $318,490.00 6.12%
5 ($27,667.77) -0.53%
6 ($315,900.00) -6.07%
6 $315,567.81 6.06%
7 $315,900.00 6.07%
7 $366,889.32 7.04%
8 $925,626.70 17.77%
Total $2,066,743.04 39.68% Number of days impacting the schedule. $7,274,839.04
Original Completion Date: 2/8/2022 Revised Completion Date: 7/29/2022

8.81%

30.88%
AUTHORIZATION BY CITY:

Recommended for approval by:

Date: __________ ____________________________________________Date: __________ Serena Hinojosa Javier Luna
Project Manager CIP Manager & Assistant Engineer
Approved by:

Date: __________ ____________________________________________Date: __________ Savat Khamphou Tom Moody
Public Works Director & City Engineer Director of Utilties ACCEPTANCE BY CONTRACTOR:

Greg Chehey Project Manager
Accepted by: ______________________________________________Title: ____________________________ (Please print name and title)
Signature: ______________________________________________Date: ____________________________ CCO 69880
CCO 69881
0 MLD Scope
Orginal Project Scope
0 4/4/2023
0 4/4/2023
0 CONTRACT VARIANCE SUMMARY
Revised Contract Amount:

Time Working Days
84 0
6/9/2021
6/23/2021
6/24/2021
87 We, the undersigned Contractor, have given careful consideration to the above described changes and/or extra work and hereby agree that said work is the subject of this Change Order. Quantities of items other than Lump Sum are not to exceed the amounts indicated. 171
Date Started: 01/4/2021
____________________________
____________________________
Original Contract Amount: $5,208,096.00
45 5/5/2021
0 0
7/29/2022

PACIFICHYDROTECHCORPORATION
314 E. 3RD ST, PERRIS, CA 92570
(951) 943-8803 FAX (951) 943-1093
November 14, 2024
City of Corona
755 Public Safety Way
Corona, CA 92880
Attn: Serena Hinojosa
Reference: WRF-3 Lift Station Project
Project No. 2018-11
Subject: Extended Office Overhead
Ms. Hinojosa:

Per the meeting held on June 6th, 2024, PHC has revised the previously sent PCO 022 to extend from November 2024 to end of April 2025.

This PCO will cover the rental items as well asthe following overhead items, and additional items not included in the previously sent PCO 022:
• Project Management & Administration
• Insurance Extensions
• Safety Compliance Visits
PHC proposes the rental part of the change order cover a period of six months (Nov 2024-April 2025). Hopefully by the end of this 6 month period, a newly agreed upon contract price will be executed. See below for the breakout of the monthly overhead, rental items and additional costs.

Extended Office Overhead Costs (Nov 2024 – April 2025):................................. $48,097.89 • Per Month Overhead Costs = $9,619.58
Shoring, Temp Fence & CDWP Rental Costs (Nov 2024 – April 2025): ............... $120,088.50 • Per Month Rental Costs = $20,014.75
Total Rental, Overhead and Additional Costs(Including B&I): .......................... $168,186.39 Per Month Rental & Overhead Costs = $29,634.33
Sincerely,

PACIFIC HYDROTECH CORPORATION
Dustin Chehey Proj. Coordinator

PACIFICHYDROTECHCORPORATION
314 E. 3RD ST, PERRIS, CA 92570
(951) 943-8803 FAX (951) 943-1093
January 29, 2025
City of Corona
755 Public Safety Way
Corona, CA 92880
Attn: Javier Luna
Reference: WRF-3 Lift Station Project
Project No. 2018-11
Subject: PCO 024 – Cost Proposal for Reinternment
Mr. Luna:

In response to your Change Order Request dated January 15, 2025, we are pleased to offer the following proposal for reinternment. Please see below for PHC’s T&M proposal for the Reinternment process.

Since we don't know how long the reinternment process will take, The City and PHC have agreed to an estimated price of $500,000.00 to complete this work. If the process takes longer or shorter than what is noted in the daily rate breakdown below, will adjust accordingly.

This proposal includes a daily rate for assuming that the highlighted items (see attached rate sheet) will be onsite the duration of the project.

Pending the need for any additional equipment these will be marked up on the T&M sheet and noted in PHC’s Daily Log. If any of the highlighted items are either not needed or removed from site, this will also be captured on daily extra work sheets. We would ask that these extra work sheets be signed daily by the City’s representative.

This Daily Rate proposal includes the following:
• Equipment, Labor
• Temp Facilities (Toilets, Office Trailer, Temp Fence) Items that may be required but are not captured in this proposal are as follows:
• MISC Materials
• Any additional services not noted, but may be required Refer to the breakdown below for Mobilization, Estimated Daily Rate, Safety Training, Trucking Export, and Demobilization:

Mobilization Costs: ......................................................................................... $25,000.00 Daily T&M Rate Costs:........................................................................................ $448,000.00 • Totaling the other costs, PHC will have 32 days at $14,000/day to complete the reinterment Safety Training for MLD’s ................................................................................... $1,100.00 Trucking Export Costs: ........................................................................................ $14,375.00 • Estimated 25 Loads @ $500/load per City Request for Reinternment Document.

PACIFICHYDROTECHCORPORATION
314 E. 3RD ST, PERRIS, CA 92570
(951) 943-8803 FAX (951) 943-1093
If trucking goes over or under, the total will be captured in the final T&M sheet.

Demobilization Costs: ........................................................................................ $11,525.00 10% Overage Cost: ............................................................................................. $50,000.00 • To be credited if not used
Total Estimated Reinternment Costs: ................................................................ $550,000.00 Sincerely,

PACIFIC HYDROTECH CORPORATION
Dustin Chehey Proj. Coordinator
EQUIPMENT Qty Total
Foreman Truck $59.15 /hr 1 8.00 hrs 473.20
Backhoe* $86.25 /hr - 8.00 hrs -
Mini Excavator* $54.00 /hr - 8.00 hrs -
Wacker Compactor* $12.25 /hr - 8.00 hrs -
Gradall* $88.50 /hr - 8.00 hrs -
Generator* $17.00 /hr - 8.00 hrs -
Rotohammer* $14.50 /hr - 8.00 hrs -
Excavator $273.50 /hr 1 8.00 hrs 2,188.00
Water Truck $65.00 /hr 1 8.00 hrs 520.00
Forklift* $56.50 /hr - 8.00 hrs -
Loader $238.52 /hr 1 8.00 hrs 1,908.14
Reach Fork* $82.50 /hr - 8.00 hrs -
Grizzly Screen $67.65 /hr 1 8.00 hrs 541.20
Tool Truck $59.15 /hr 1 8.00 hrs 473.20
Subtotal Equipment 6,103.74
LABOR Qty Total
Project Manager* $172.00 /hr $258.00 /hr $344.00 /hr - 1.00 hrs - Asst. Project Manager* $120.00 /hr $180.00 /hr $240.00 /hr - 1.00 hrs - Foreman $130.00 /hr 195 /hr 260 /hr 1 8.00 hrs 1,040.00 Operator $130.00 /hr 195 /hr 260 /hr 2 8.00 hrs 2,080.00 Laborer $104.00 /hr 156 /hr 208 /hr 3 8.00 hrs 2,496.00 Subtotal Labor 5,616.00
RENTALS Qty Total
Insulated Office Container $100.00 /day 1 1.00 day 100.00 Restroom Facilities $25.00 /day 4 1.00 day 100.00
Temporary Fence $10.00 /day 1 1.00 day 10.00
/day - 1.00 day -
Subtotal Rentals 210.00
Subtotal all Daily Costs 11,929.74
Equipment 15% 915.56
Rentals 15% 31.50
Labor 20% 1,123.20
Markup for Equipment and Labor 2,070.26
DAILY TOTAL EXTRA COST 14,000.00
*NOTES - Other equipment and personell not shown may be needed onsite on any given day (rates TBD) MATERIAL Qty Total
BMP's for SWPPP /ls - 1.00 ls -
Security Tape for Excavations /ls - 1.00 ls -
Misc Materials /ls - 1.00 ls -
/ls - 1.00 ls -
Subtotal Material -
SUBCONTRACT Qty Total
Safety Training for MLDs $1,000.00 /ls 1 1.00 ls 1,000.00 /ls - 1.00 ls -
/ls - 1.00 ls -
Subtotal Subcontract 1,000.00
Subtotal Lump Sum Cost 1,000.00
Material 15% -
Subcontract 10% 100.00
Markup 100.00
TOTAL LUMP SUM COST 1,100.00
TRUCKING Qty Total
Estimated 25 Loads $500.00 /load 25 1.00 ls 12,500.00
- 1.00 ls -
- 1.00 ls -
Subtotal Trucking 12,500.00
Trucking 15% 1,875.00
Markup 1,875.00
TOTAL TRUCKING 14,375.00
Units
MARKUP
Units
MARKUP
Straight Time Overtime Double Time
Units
MARKUP
Units
Units
Units

PACIFICHYDROTECHCORPORATION
314 E. 3RD ST, PERRIS, CA 92570
(951) 943-8803 FAX (951) 943-1093
January 29, 2025
City of Corona
755 Public Safety Way
Corona, CA 92880
Attn: Javier Luna
Reference: WRF-3 Lift Station Project
Project No. 2018-11
Subject: Extended Office Overhead
Mr. Luna:

In response to your email dated 1/15/25, PHC has revised the previously sent PCO 023 to extend the overhead change order from May 2025 to end of December 2025 (7 Months).

This PCO will cover the rental items as well asthe following overhead items, and additional items not included in the previously sent PCO 023:
• Project Management & Administration
• Insurance Extensions
• Safety Compliance Visits
PHC proposes that the rental part of the change order will cover seven months (May 2025-Dec. 2025). Hopefully, by the end of this 7-month period, a newly agreed-upon contract price will be executed. See below for the breakout of the monthly overhead, rental items and additional costs.

Extended Office Overhead Costs (May 2025 – Dec 2025):.................................. $67,337.06 • Per Month Overhead Costs = $9,619.58
Shoring, Temp Fence & CDWP Rental Costs (May 2025 – Dec 2025): ............... $140,103.25 • Per Month Rental Costs = $20,014.75
Total Rental, Overhead and Additional Costs(Including B&I): .......................... $207,440.31 Per Month Rental & Overhead Costs = $29,634.33
Sincerely,