CA\DD\02000.50102\10151745.3
15 (CITY ATTY: 07-17)
CITY’S SIGNATURE PAGE FOR
CITY OF CORONA
MAINTENANCE/GENERAL SERVICES AGREEMENT
WITH SUPERIOR PAVEMENT MARKINGS, INC.
(“AS-NEEDED” STREET STRIPING AND PAVEMENT MARKING MAINTENANCE AND REPAIR SERVICES – RFP 25-014SB)
IN WITNESS WHEREOF, the Parties have entered into this Agreement as of the date first written above.
CITY OF CORONA
Approved By: _________________________
Savat Khamphou
Public Works Director/City Engineer
Reviewed By:
_________________________
Rosalva Ureno
City Traffic Engineer
Reviewed By: _________________________
Yasmin Lopez
Purchasing Manager
Attest:
_________________________
Sylvia Edwards, City Clerk
City of Corona, California
Docusign Envelope ID: FA4D7D98-3EC8-4011-8A5C-299EFCAAEE3E Docusign Envelope ID: 01CDC9ED-79C8-4B81-A1E2-FA9FE74C1668
CA\DD\02000.50102\10151745.3
16 (CITY ATTY: 07-17)
CONTRACTOR’S SIGNATURE PAGE FOR
CITY OF CORONA
MAINTENANCE/GENERAL SERVICES AGREEMENT
WITH SUPERIOR PAVEMENT MARKINGS, INC.
(“AS-NEEDED” STREET STRIPING AND PAVEMENT MARKING MAINTENANCE AND REPAIR SERVICES – RFP 25-014SB)
IN WITNESS WHEREOF, the Parties have entered into this Agreement as of the date first written above.
SUPERIOR PAVEMENT MARKINGS, INC.
a California corporation
By: _________________________
John Matthew Lucas
CEO
By: _________________________
Darren Veltz
CFO
Docusign Envelope ID: FA4D7D98-3EC8-4011-8A5C-299EFCAAEE3E Docusign Envelope ID: 01CDC9ED-79C8-4B81-A1E2-FA9FE74C1668
CA\DD\02000.50102\10151745.3
17 (CITY ATTY: 07-17)
EXHIBIT “A”
SCOPE OF SERVICES
Contractor promises and agrees to furnish to the City all labor, materials, tools, equipment, services, and incidental and customary work necessary to fully and adequately supply the professional as- needed street striping and pavement marking maintenance and repair services are more particularly described herein.
General
The work performed under this Contract shall include the furnishing of all labor, materials, and equipment necessary to perform “as- needed” street striping and pavement markings within the City. All work shall be done in accordance with the latest edition of Caltrans Standard Plans and Specifications, the City of Corona Standard Plans, and The “Greenbook” Standard Specifications for Public Works Construction, and Technical Specifications herein.
Description of Work/Scope of Works:
The type of street striping and related services shall consist of the following:
1. Thermoplastic or paint reflective pavement arrows, centerlines, lane lines, edge lines, bike lanes, stop and yield bars, crosswalks and pavement marking legends
2. Removing of pavement arrows, centerlines, lane lines, edge lines, bike lanes, stop and yield bars, crosswalks and pavement marking legends
3. Re-striping in thermoplastic or paint per existing alignment
4. Placement of raised pavement markers
5. Paint and removal of reflective color curb markings
Specification for Traffic Striping, Pavement Marking, and Curb Marking GREENBOOK 2021 SPECIFICATIONS
214 – TRAFFIC STRIPING, CURB AND PAVEMENT MARKINGS, AND PAVEMENT
MARKERS
Test Reports and Certification – Replace the first sentence with the following:
Prior to delivery of thermoplastic material, the Contractor shall submit to the Engineer certified copies of the manufacturer’s test reports and MSDS in accordance with 3-8 and 7-10.4.3.
Re-Striping
All re-striping and re-painting of existing traffic stripes shall coincide with the original paintings, regardless of other more restrictive requirements of these Special Provisions unless directed by the Engineer.
Removal of Markings
Docusign Envelope ID: FA4D7D98-3EC8-4011-8A5C-299EFCAAEE3E Docusign Envelope ID: 01CDC9ED-79C8-4B81-A1E2-FA9FE74C1668
CA\DD\02000.50102\10151745.3
18 (CITY ATTY: 07-17)
Removing of centerlines, lane lines, raised pavement markers and pavement marking legends shall be accomplished by wet sandblasting or grinding method. Errors made by the Contractor shall be removed at no additional cost to the City. Upon written direction of the City Traffic Engineer, or his assigned staff, pavement markings may be removed by blacking out with black paint.
Preparation
It shall be the responsibility of the Contractor to ensure that, prior to any pavement striping or marking, the surface is clear of all debris.
Traffic Control
The Contractor shall make every effort to assure the safety of vehicular and pedestrian traffic during his operations. The latest edition of the California Manual on Uniform Traffic Control Devices is herein adopted as the minimum safety guidelines. Contractor shall not close any street within the City without first obtaining the approval of the City Engineer.
Thermoplastic Measurement
Thermoplastic traffic stripes will be measured by the units in the bid schedule of each pavement marking type, without deductions for gaps in broken stripes. Each thermoplastic detail that includes multiple stripes such as detail 29 shall be measured as a single linear unit for all four individual stripes as an example.
Thermoplastic Payment
The contract unit prices paid per linear foot for thermoplastic traffic stripes of the patterns designated in this Request for Proposals and per square foot for each pavement marking legend shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all work involved in applying thermoplastic traffic stripes and pavement makings complete in place, including establishing alignment for stripes and layout work, as shown on the plans, as specified in these specifications and the special provisions and as directed by the Engineer. The cost of any necessary raised pavement markers required for any striping detail designated in the Proposal shall be considered to be included in the cost per linear foot for each detail and no separate payment will be made therefore.
Paint Measurement
Painted traffic stripes will be measured by the units in the bid schedule of each pavement marking type, without deductions for gaps in broken stripes. Each painted detail that includes multiple stripes such as detail 29 shall be measured as a single linear unit for all four individual stripes as an example.
Paint Payment
Docusign Envelope ID: FA4D7D98-3EC8-4011-8A5C-299EFCAAEE3E Docusign Envelope ID: 01CDC9ED-79C8-4B81-A1E2-FA9FE74C1668
CA\DD\02000.50102\10151745.3
19 (CITY ATTY: 07-17)
The contract unit prices paid per linear foot for painted traffic stripes of the patterns designated in this Request for Proposal and per square foot for each pavement marking legend shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all work involved in applying painted traffic stripes and pavement makings complete in place, including establishing alignment for stripes and layout work, as shown on the plans, as specified in these specifications and the special provisions and as directed by the Engineer. The cost of any necessary raised pavement markers required for any striping detail designated in the Proposal shall be considered to be included in the cost per linear foot for each detail and no separate payment will be made therefore.
Traffic stripes and pavement markings not designated as thermoplastic shall conform to the provisions of Section 84-3 “Painted Traffic Stripes and Pavement Markings” of the Caltrans Standard Specifications and these Special Provisions.
Only water borne paints will be permitted for use with the City.
Pavement Markers
Pavement markers shall conform to the provisions in Section 85, “Pavement Markers”, of the Caltrans Standard Specifications (latest editions) and these Special Provisions.
Control of Alignment and Layout
Before obliterating (or covering) any pavement delineation that is to be replaced on the same alignment and location, as determined by the Inspector, the pavement delineation shall be referenced by the Contractor, with a sufficient number of control points to reestablish the alignment and location of the new pavement delineation. The references shall include the limits or changes in striping pattern, including one- and 2-way barriers lines, limit lines, crosswalks and other pavement markings. Full compensation for referencing pavement delineation shall be considered included in the contract prices paid for new pavement delineation and no additional compensation will be allowed therefore.
Unless otherwise shown, the Contractor shall re-stripe all pavement delineation to existing locations or as directed by the Engineer.
Traffic stripes shall be painted to the alignment approved by the Engineer. The Contractor shall not proceed with the application of any pavement markings and/or striping until the Engineer has checked and approved the alignment marks. The Engineer may make minor adjustments to the proposed alignment prior to approval.
Alignment marks may consist of cat-tracking and spotting, or an approved alternative.
Cat-tracking shall consist of stretching a rope on a straight line between control points on tangent alignment and on a true arc through control points on curved alignment and placing spots of paint along the rope. The spots shall be not more than 3 inches in width and not more than 5 feet apart on curves or 10 feet apart on tangents.
Docusign Envelope ID: FA4D7D98-3EC8-4011-8A5C-299EFCAAEE3E Docusign Envelope ID: 01CDC9ED-79C8-4B81-A1E2-FA9FE74C1668
CA\DD\02000.50102\10151745.3
20 (CITY ATTY: 07-17)
Paint for the cat-tracks shall be the same color as the traffic stripe for which they are placed.
Laser guidance equipment shall be capable of maintaining the alignment of traffic stripes with accuracy equivalent to or better than that obtainable through the use of cat tracking as determined by the Engineer.
All work necessary to establish satisfactory alignment for stripes and all layout work required for pavement markings shall be performed by the Contractor at his expense, including correction of minor irregularities in the control points approved by the Engineer. Correction of minor irregularities shall be accomplished by the application of cat tracks, the use of laser guidance devices, or by a combination of these techniques.
Remove Pavement Delineation
Existing traffic stripes and pavement markings that do not conform to the plans and are not removed or obliterated as a result of the various pavement rehabilitation operations, shall be removed by wet sand blasting or grinding as approved by the Engineer.
Mandatory Requirements:
The contractors and their sub-contractors shall wear Hard Hats, Safety Vests and Goggles at all work sites.
Contractors shall require each of his employees to wear basic public works working attire. Contractors Employees shall to wear uniforms at all times when working on City property which clearly identifies to the public the name of the Contractor responsible for the maintenance services and the employee’s name.
Contractors shall park their vehicles and equipment to comply with all safety standards of OSHA or CAL-OSHA.
The Contractor shall abide by the provisions of the latest edition of the Work Area Traffic Control Handbook.
The Contractor shall promptly clean all job sites when work is completed, generated from their operations and follow all City of Corona Best Management Practices for National Pollutant Discharge Elimination System (NPDES) regulations. The City of Corona NPDES regulations may be accessed at this link:
http://www.discovercorona.com/City-Departments/Public-Works/Development-andPermits/NPDES-Useful-Links.aspx Major rehabilitation and construction of street facilities is handled by the Capital Improvement Projects Section of Public Works and is not a part of this contract.
Docusign Envelope ID: FA4D7D98-3EC8-4011-8A5C-299EFCAAEE3E Docusign Envelope ID: 01CDC9ED-79C8-4B81-A1E2-FA9FE74C1668
CA\DD\02000.50102\10151745.3
21 (CITY ATTY: 07-17)
NOTE – NOT PUBLIC PROJECT WORK
This Agreement generally governs only work which is considered to be “maintenance work” under CMC Section 3.08.010(k) and Public Contract Code Section 22002(d) and does not include “public project” work under CMC Section 3.08.010(m) and Public Contract Code Section 22002(c). The only time that an individual call-out, as described in Exhibit “B” and Exhibit “C” attached hereto, might include “public project” work is when an individual call-out is strictly limited to an amount that is not required to be informally or formally bid under the CMC or state law (e.g. less than $60,000), and individual projects shall not be split to fall below that amount.
Docusign Envelope ID: FA4D7D98-3EC8-4011-8A5C-299EFCAAEE3E Docusign Envelope ID: 01CDC9ED-79C8-4B81-A1E2-FA9FE74C1668
CA\DD\02000.50102\10151745.3
22 (CITY ATTY: 07-17)
EXHIBIT “B”
SCHEDULE OF SERVICES
Contractor shall perform the Services within the Term of this Agreement, in accordance with the Schedule of Services set forth in this Exhibit.
Mobilization
The Contractor shall not start work in the City until he receives a written work order from the City Traffic Engineer, or his assigned staff. The Contractor must have such list in his possession before starting work. The Contractor shall perform only that work listed and will only be compensated for the work listed on the work order. The Contractor shall be given a minimum of $3,500.00 of work to warrant sending out a crew. All cost for mobilization for each work order, regardless of quantity of work requested, shall be considered included in the unit bid price for the requested work and no additional compensation to the Contractor shall be made.
Contractor shall respond to routine requests for service within five (5) working days of the initial notification/request.
Contractor shall respond with a crew to provide emergency street striping and pavement marking repairs within two (2) working days of the City of Corona making the request for emergency services.
Scheduling of Work Orders
Contractor shall notify the City Traffic Engineer, or his assigned staff, the estimated start date of the work within seven (7) calendar days of receiving the work orders. The start date of work orders meeting the minimum mobilization charges shall not exceed twenty-one (21) calendar days. Work orders must be completed in seven (7) calendar days after start of work unless other arrangements have been made with the City. Contractor shall be liable for liquidated damages as set forth in the Contract Agreement section 3.2.7.1 due to delayed start beyond the allotted twenty-one (21) calendar days. Contractor shall also be liable for liquidated damages as set forth in the Contract Agreement due to delayed completion of work beyond the allotted seven (7) calendar days after start of work.
Hours of Operation
The hours of operation for the performance of the Work shall be 8:30 AM to 3:30 PM, Monday through Friday. No lane closures will be permitted prior to 8:30 AM or after 3:30 PM unless Contractor obtains prior written approval from City Engineer.
On some street segments, the volume of traffic may require that the work must be at night or on the weekend. The contractor shall obtain written approval from the City Traffic Engineer prior to Docusign Envelope ID: FA4D7D98-3EC8-4011-8A5C-299EFCAAEE3E Docusign Envelope ID: 01CDC9ED-79C8-4B81-A1E2-FA9FE74C1668
CA\DD\02000.50102\10151745.3
23 (CITY ATTY: 07-17)
scheduling the work in these locations. The nighttime work hours are 10:00 PM to 4:00 AM and weekend work hours are 7:00 AM to 4:00 PM.
AS-NEEDED SERVICES
Each individual call-out under this Agreement is a separate project for purposes the City’s bidding and purchasing requirements.
Contractor shall provide the Services on an as-needed basis, and as scheduled and directed by the City’s Representative.
For each individual call-out, Contractor shall respond, mobilize and be on-site ready to start work no later than 24 hours after notification for routine work, repairs and installations.
Contractor must be able to respond by telephone to emergency call-out notifications from City within Two (2) working Days of being notified by City that there is an emergency, and to be mobilized and on-site within one (1) hour of such emergency notification by City.
Contract Term
The contract term shall be effective pursuant to Section 3.1.2 above with two (2) additional option two-year renewal periods, on an as-needed basis, with no guaranteed usage for street striping and pavement marking Services. Bid prices shall remain effective and in force for the entire initial contract terms. City reserves the right to exercise option year renewals in its sole discretion. Subsequent contract, term extensions, if exercised by the City, are as follows:
Option 1, if exercised, shall be effective July 1, 2026 through June 30, 2028 Option 2, if exercised, shall be effective July 1, 2028 through June 30, 2030 Option year pricing shall be negotiated by the Parties prior to commencement of each additional two-year period. Negotiated price adjustments will be made in accordance with and shall not exceed the percentage of change in the United States Bureau of Labor Statistics Consumer Price Index “All Urban Consumers for Riverside, California, Area (CPI-U), not seasonally adjusted, for the most recent twelve (12) months for which statistics are available. This method of price adjustment shall apply to each extension period exercised. Optional years shall become effective only upon issuance by the City of a duly authorized Purchase Order.
Docusign Envelope ID: FA4D7D98-3EC8-4011-8A5C-299EFCAAEE3E Docusign Envelope ID: 01CDC9ED-79C8-4B81-A1E2-FA9FE74C1668
CA\DD\02000.50102\10151745.3
24 (CITY ATTY: 07-17)
EXHIBIT “C”
COMPENSATION
Contractor shall receive compensation, including authorized reimbursements, for all Services rendered under this Agreement at the rates set forth in this Exhibit.
Docusign Envelope ID: FA4D7D98-3EC8-4011-8A5C-299EFCAAEE3E Docusign Envelope ID: 01CDC9ED-79C8-4B81-A1E2-FA9FE74C1668
CA\DD\02000.50102\10151745.3
25 (CITY ATTY: 07-17)
BONDS
Each individual call-out under this Agreement is a separate project for purposes of the City’s bidding and purchasing requirements, including, but not limited to, its bond requirements provided for in Civil Code Section 9550, which mandates that the City require a payment bond for certain public work projects involving an expenditure in excess of $25,000.
Payment Bonds: Contractor shall provide a 100% payment bond for all individual call-out projects for which a project work order has been issued by the City in excess of $25,000.
Docusign Envelope ID: FA4D7D98-3EC8-4011-8A5C-299EFCAAEE3E Docusign Envelope ID: 01CDC9ED-79C8-4B81-A1E2-FA9FE74C1668
CA\DD\02000.50102\10151745.3
26 (CITY ATTY: 07-17)
Performance Bonds: Contractor shall be required to provide a 100% performance bond whenever the City indicates that one is required in the project work order issued for an individual call-out project.
Cost of Bonds: Whenever a bond is required by the City for an individual call-out project, Contractor will be able to include the costs of the bonds for that individual call-out.
Docusign Envelope ID: FA4D7D98-3EC8-4011-8A5C-299EFCAAEE3E Docusign Envelope ID: 01CDC9ED-79C8-4B81-A1E2-FA9FE74C1668
CA\DD\02000.50102\10151745.3
1 (CITY ATTY: 07-17)
CITY OF CORONA
MAINTENANCE/GENERAL SERVICES AGREEMENT
WITH WGJ ENTERPRISES. INC. DBA PCI
(“AS-NEEDED” STREET STRIPING AND PAVEMENT MARKING MAINTENANCE AND REPAIR SERVICES – RFP 25-014SB)
1. PARTIES AND DATE.
This Agreement is made and entered into this _________ day of ____________________, 2025 (“Effective Date”) by and between the City of Corona, a municipal corporation organized under the laws of the State of California with its principal place of business at 400 South Vicentia Avenue, Corona, California 92882 (“City”) and WGJ Enterprises, Inc. dba PCI a California. corporation with its principal place of business at 975 W. 1st St, Azusa, CA 91702 (“Contractor”). City and Contractor are sometimes individually referred to as “Party” and collectively as “Parties” in this Agreement.
2. RECITALS.
2.1 Contractor.
Contractor desires to perform and assume responsibility for the provision of certain maintenance or other general services required by the City on the terms and conditions set forth in this Agreement. Contractor represents that it is experienced in providing “as-needed” street striping and pavement marking maintenance and repair services to public clients, that it and its employees or subcontractors have all necessary licenses and permits to perform the Services in the State of California, and that is familiar with the plans of City. Contractor shall not subcontract any portion of the work required by this Agreement, except as expressly stated herein, without prior written approval of City. Subcontracts, if any, shall contain a provision making them subject to all provisions stipulated in this Agreement.
2.2 Project.
City desires to engage Contractor to render such services for the “As-Needed” Street Striping and Pavement Marking Maintenance and Repair Services, RFP 25-014SB project (“Project”) as set forth in this Agreement.
2.4 As-Needed Services
This Agreement is for as-needed or on-call services. This means that each individual call-out under this Agreement is a separate project for purposes of the City’s bidding and purchasing requirements, including, but not limited to, its bond requirements provided for in Civil Code Section 9550, which mandates that the City require a payment bond for certain public work projects involving an expenditure in excess of $25,000.
3. TERMS.
Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
2 (CITY ATTY: 07-17)
3.1 Scope of Services and Term.
3.1.1 General Scope of Services. Contractor promises and agrees to furnish to the City all labor, materials, tools, equipment, services, and incidental and customary work necessary to fully and adequately supply the professional “as-needed” street striping and pavement marking maintenance or other general services necessary for the Project (“Services”).
The Services are more particularly described in Exhibit “A” attached hereto and incorporated herein by reference. All Services shall be subject to, and performed in accordance with, this Agreement, the exhibits attached hereto and incorporated herein by reference, and all applicable local, state and federal laws, rules and regulations.
3.1.2 Term. The term of this Agreement shall be from
____________________________ to June 30, 2026 (“Term”), unless earlier terminated as provided herein. Contractor shall complete the Services within the Term of this Agreement and shall meet any other established schedules and deadlines. The Parties may, by mutual, written consent, extend the Term of this Agreement one or more times by executing a written amendment pursuant to Section 3.5.8 below (each a “Renewal Term”). The terms “Term” and “Renewal Term” may sometimes be generally and collectively referred to as “Term” in this Agreement.
3.2 Responsibilities of Contractor.
3.2.1 Control and Payment of Subordinates; Independent Contractor. The Services shall be performed by Contractor or under its supervision. Contractor will determine the means, methods and details of performing the Services subject to the requirements of this Agreement. City retains Contractor on an independent contractor basis and not as an employee.
Contractor retains the right to perform similar or different services for others during the Term of this Agreement. Any additional personnel performing the Services under this Agreement on behalf of Contractor shall also not be employees of City and shall at all times be under Contractor’s exclusive direction and control. Contractor shall pay all wages, salaries, and other amounts due such personnel in connection with their performance of Services under this Agreement and as required by law. Contractor shall be responsible for all reports and obligations respecting such additional personnel, including, but not limited to: social security taxes, income tax withholding, unemployment insurance, disability insurance, and workers’ compensation insurance.
3.2.2 Schedule of Services. Contractor shall perform the Services within the Term of this Agreement, in accordance with the Schedule of Services set forth in Exhibit “B” attached hereto and incorporated herein by reference, and in accordance with any other completion schedule or milestones which may be separately agreed upon in writing by the Parties. Contractor represents that it has the professional and technical personnel required to perform the Services in conformance with such conditions. In order to facilitate Contractor’s conformance with the Schedule, City shall respond to Contractor’s submittals in a timely manner. Upon request of City, Contractor shall provide a more detailed schedule of anticipated performance to meet the Schedule of Services.
Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
3 (CITY ATTY: 07-17)
3.2.3 Conformance to Applicable Requirements. All Services performed by Contractor shall be subject to the approval of City.
3.2.4 City’s Representative. The City hereby designates Savat Khamphou, Public Works Director or his or her designee, to act as its representative for the performance of this Agreement (“City’s Representative”). City’s Representative shall have the power to act on behalf of the City for all purposes under this Agreement. Contractor shall not accept direction or orders from any person other than the City’s Representative or his or her designee.
3.2.5 Contractor’s Representative. Contractor hereby designates William Jacob, or his or her designee, to act as its representative for the performance of this Agreement (“Contractor’s Representative”). Contractor’s Representative shall have full authority to represent and act on behalf of the Contractor for all purposes under this Agreement. The Contractor’s Representative shall supervise and direct the Services, using his best skill and attention, and shall be responsible for all means, methods, techniques, sequences and procedures and for the satisfactory coordination of all portions of the Services under this Agreement.
3.2.6 Coordination of Services. Contractor agrees to work closely with City staff in the performance of Services and shall be available to City’s staff, consultants and other staff at all reasonable times.
3.2.7 Standard of Care; Performance of Employees. Contractor shall perform all Services under this Agreement in a skillful and competent manner, consistent with the standards generally recognized as being employed by professionals in the same discipline in the State of California. Contractor represents and maintains that it is skilled in the professional calling necessary to perform the Services. Contractor agrees that all employees and subcontractors shall have sufficient skill and experience to perform the Services assigned to them. Finally, Contractor represents that it, its employees and subcontractors shall have all licenses, permits, qualifications and approvals of whatever nature that are legally required to perform the Services, including a City Business License, and that such licenses and approvals shall be maintained throughout the Term of this Agreement. As provided for in the indemnification provisions of this Agreement, Contractor shall perform, at its own cost and expense and without reimbursement from the City, any services necessary to correct errors or omissions which are caused by the Contractor’s failure to comply with the standard of care provided for herein. Any employee of the Contractor or its sub-contractors who is determined by the City to be uncooperative, incompetent, a threat to the adequate or timely completion of the Project, a threat to the safety of persons or property, or any employee who fails or refuses to perform the Services in a manner acceptable to the City, shall be promptly removed from the Project by the Contractor and shall not be re-employed to perform any of the Services or to work on the Project.
3.2.8 Disputes. Should any dispute arise respecting the true value of any work done, of any work omitted, or of any extra work which Contractor may be required to do, or respecting the size of any payment to Contractor during the performance of this Contract, Contractor shall continue to perform the Work while said dispute is decided by the City. If Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
4 (CITY ATTY: 07-17)
Contractor disputes the City’s decision, Contractor shall have such remedies as may be provided by law.
3.2.9 Laws and Regulations; Employee/Labor Certifications. Contractor shall keep itself fully informed of and in compliance with all local, state and federal laws, rules and regulations in any manner affecting the performance of the Project or the Services, including all Cal/OSHA requirements, and shall give all notices required by law. Contractor shall be liable for all violations of such laws and regulations in connection with Services. If the Contractor performs any work or Services knowing them to be contrary to such laws, rules and regulations and without giving written notice to the City, Contractor shall be solely responsible for all costs arising therefrom. City is a public entity of the State of California subject to certain provisions of the Health & Safety Code, Government Code, Public Contract Code, and Labor Code of the State. It is stipulated and agreed that all provisions of the law applicable to the public contracts of a municipality are a part of this Contract to the same extent as though set forth herein and will be complied with. These include but are not limited to the payment of prevailing wages, the stipulation that eight (8) hours' labor shall constitute a legal day's work and that no worker shall be permitted to work in excess of eight (8) hours during any one calendar day except as permitted by law. Contractor shall defend, indemnify and hold City, its officials, directors, officers, employees and agents free and harmless, pursuant to the indemnification provisions of this Agreement, from any claim or liability arising out of any failure or alleged failure to comply with such laws, rules or regulations.
3.2.9.1 Employment Eligibility; Contractor. By executing this Agreement, Contractor verifies that it fully complies with all requirements and restrictions of state and federal law respecting the employment of undocumented aliens, including, but not limited to, the Immigration Reform and Control Act of 1986, as may be amended from time to time. Such requirements and restrictions include, but are not limited to, examination and retention of documentation confirming the identity and immigration status of each employee of the Contractor. Contractor also verifies that it has not committed a violation of any such law within the five (5) years immediately preceding the date of execution of this Agreement, and shall not violate any such law at any time during the Term of the Agreement. Contractor shall avoid any violation of any such law during the Term of this Agreement by participating in an electronic verification of work authorization program operated by the United States Department of Homeland Security, by participating in an equivalent federal work authorization program operated by the United States Department of Homeland Security to verify information of newly hired employees, or by some other legally acceptable method. Contractor shall maintain records of each such verification, and shall make them available to the City or its representatives for inspection and copy at any time during normal business hours. The City shall not be responsible for any costs or expenses related to Contractor’s compliance with the requirements provided for in Section 3.2.9 or any of its sub-sections.
3.2.9.2 Employment Eligibility; Subcontractors, Sub-subcontractors and Consultants. To the same extent and under the same conditions as Contractor, Contractor shall require all of its subcontractors, sub-subcontractors and consultants performing any work or Services relating to the Project or this Agreement to make the same verifications and comply with all requirements and restrictions provided for in Section 3.2.9.1.
Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
5 (CITY ATTY: 07-17)
3.2.9.3 Employment Eligibility; Failure to Comply. Each person executing this Agreement on behalf of Contractor verifies that they are a duly authorized officer of Contractor, and understands that any of the following shall be grounds for the City to terminate the Agreement for cause: (1) failure of Contractor or its subcontractors, subsubcontractors or consultants to meet any of the requirements provided for in Sections 3.2.9.1 or
3.2.9.2; (2) any misrepresentation or material omission concerning compliance with such requirements (including in those verifications provided to the Contractor under Section 3.2.9.2); or (3) failure to immediately remove from the Project any person found not to be in compliance with such requirements.
3.2.9.4 Labor Certification. By its signature hereunder, Contractor certifies that it is aware of the provisions of Section 3700 of the California Labor Code which require every employer to be insured against liability for Workers’ Compensation or to undertake self-insurance in accordance with the provisions of that Code, and agrees to comply with such provisions before commencing the performance of the Services.
3.2.9.5 Equal Opportunity Employment. Contractor represents that it is an equal opportunity employer and it shall not discriminate against any subconsultant, employee or applicant for employment because of race, religion, color, national origin, handicap, ancestry, sex or age. Such non-discrimination shall include, but not be limited to, all activities related to initial employment, upgrading, demotion, transfer, recruitment or recruitment advertising, layoff or termination. Contractor shall also comply with all relevant provisions of City’s Minority Business Enterprise program, Affirmative Action Plan or other related programs or guidelines currently in effect or hereinafter enacted.
3.2.9.6Air Quality. Contractor must fully comply with all applicable laws, rules and regulations in furnishing or using equipment and/or providing services, including, but not limited to, emissions limits and permitting requirements imposed by the South Coast Air Quality Management District (SCAQMD) and/or California Air Resources Board (CARB).
Although the SCAQMD and CARB limits and requirements are more broad, Contractor shall specifically be aware of their application to "portable equipment", which definition is considered by SCAQMD and CARB to include any item of equipment with a fuel-powered engine.
Contractor shall indemnify City against any fines or penalties imposed by SCAQMD, CARB, or any other governmental or regulatory agency for violations of applicable laws, rules and/or regulations by Contractor, its subcontractors, or others for whom Contractor is responsible under its indemnity obligations provided for in this Agreement.
Contractor shall comply, and shall ensure all subcontractors comply, with all applicable requirements of the most current version of the regulations imposed by CARB including, without limitation, all applicable terms of Title 13, California Code of Regulations Division 3, Chapter 9 and all pending amendments (“Regulation”).
Throughout the Project, and for three (3) years thereafter, Contractor shall make available for inspection and copying any and all documents or information associated with Contractor’s and its subcontractors’ fleets including, without limitation, the Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
6 (CITY ATTY: 07-17)
Certificates of Reported Compliance (“CRCs”), fuel/refueling records, maintenance records, emissions records, and any other information the Contractor is required to produce, keep or maintain pursuant to the Regulation upon two (2) calendar days’ notice from the City.
Contractor shall be solely liable for any and all costs associated with compliance with the Regulation as well as for any and all penalties, fines, damages, or costs associated with any and all violations, or failures to comply with the Regulation. Contractor shall defend, indemnify and hold harmless the City, its officials, officers, employees and authorized volunteers free and harmless from any claims, liabilities, costs, penalties or interest arising out of any failure or alleged failure to comply with the Regulation.
3.2.10 Insurance.
3.2.10.1 Time for Compliance. Promptly following the Effective Date of this Agreement, but in no event before Contractor commences any Services under this Agreement, Contractor shall provide evidence satisfactory to the City that it has secured all insurance required under this section. Failure to provide and maintain all required insurance shall be grounds for the City to terminate this Agreement for cause.
3.2.10.2 Minimum Requirements. Contractor shall, at its expense, procure and maintain for the duration of the Agreement insurance against claims for injuries to persons or damages to property which may arise from or in connection with the performance of the Agreement by the Contractor, its agents, representatives, employees or subcontractors.
Contractor shall also require all of its subcontractors to procure and maintain the same insurance for the duration of the Agreement. Such insurance shall meet at least the following minimum levels of coverage:
(A) Minimum Scope of Insurance. Coverage shall be at least as broad as the latest version of the following: (1) General Liability: Insurance Services Office Commercial General Liability coverage (occurrence form CG 0001); (2) Automobile Liability:
Insurance Services Office Business Auto Coverage form number CA 0001, code 1 (any auto), or if Contractor has no owned autos, Code 8 (hired) and 9 (non-owned); and (3) Workers’ Compensation and Employer’s Liability: Workers’ Compensation insurance as required by the State of California and Employer’s Liability Insurance. (B) Minimum Limits of Insurance. Contractor shall maintain limits no less than: (1) General Liability: $1,000,000 per occurrence for bodily injury, personal injury, advertising injury and property damage. If Commercial General Liability Insurance or other form with general aggregate limit is used including, but not limited to, form CG 2503, either the general aggregate limit shall apply separately to this Agreement/location or the general aggregate limit shall be twice the required occurrence limit; (2) Automobile Liability:
$1,000,000 per accident for bodily injury and property damage; and (3) Workers’ Compensation and Employer’s Liability: Workers’ Compensation limits as required by the Labor Code of the State of California. Employer’s Liability limits of $1,000,000 per accident for bodily injury or disease.
Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
7 (CITY ATTY: 07-17)
3.2.10.3 Insurance Endorsements. The insurance policies shall contain or be endorsed (amended) to include the following provisions:
(A) General Liability. The general liability policy shall state that: (1) the City, its directors, officials, officers, employees, agents, and volunteers shall be covered as additional insured with respect to liability arising out of work or operations performed by or on behalf of the Contractor, including materials, parts or equipment furnished in connection therewith (the endorsement form shall be at least as broad as ISO Form CG 20 10 11 85 or both CG 20 37 and one of the following: CG 20 10, CG 20 26, CG 20 33 or CG 20 38); and (2) the insurance coverage shall be primary insurance coverage as respects the City, its directors, officials, officers, employees, agents, and volunteers (the endorsement form shall be at least as broad as ISO CG 20 01 04 13). Any insurance or self-insurance maintained by the City, its directors, officials, officers, employees, agents, and volunteers shall be excess of the Contractor’s insurance and shall not be called upon to contribute with it in any way. (B) Waiver of Subrogation – Workers’ Compensation and
Employer’s Liability Coverage. The insurer shall agree to waive all rights of subrogation against the City, its directors, officials, officers, employees, agents, and volunteers for losses paid under the terms of the insurance policy which arise from work or Services performed by the Contractor.
(C) All Coverages. If Contractor maintains broader coverage and/or higher limits than the minimums shown above, the City is entitled to the broader coverage and/or higher limits maintained by Contractor. Thus, any available insurance proceeds in excess of the specified minimum limits of insurance and coverage shall be available to the City.
3.2.10.4 Other Provisions; Endorsements Preferred. Contractor shall endeavor to provide endorsements regarding the following provisions, but nonetheless understands, acknowledges and agrees that the following provisions shall apply and that failure to comply shall be considered to be a breach of this Agreement by Contractor:
(A) Waiver of Subrogation – All Other Policies. Contractor hereby waives all rights of subrogation any insurer of Contractor’s may acquire against the City, its directors, officials, officers, employees, agents, and volunteers for losses paid under the terms of any insurance policy which arise from work or Services performed by the Contractor.
Contractor understands, acknowledges and agrees that this provision is in full force and effect even if the City does not receive a waiver of subrogation endorsement from the insurer. (B) Notice. Contractor shall either: (1) require its insurer to provide thirty (30) days prior written notice to the City before coverage is suspended, voided, or canceled; or (2) notify City in writing that such notice is not available and forward any notice of such actions to the City within two (2) business days from date of receipt by Contractor.
Contractor understands, acknowledges and agrees that this provision is in full force and effect even if the City does not receive a waiver of subrogation endorsement from the insurer.
Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
8 (CITY ATTY: 07-17)
3.2.10.5 Claims Made Policies. The following provisions shall apply to all policies that provide coverage on a claims-made basis: (A) the retroactive date must be shown and must be before the date on which any Services under this Agreement commence; (B) the insurance must be maintained and evidence of insurance must be provided for at least five (5) years after completion of the Project; and (C) if coverage is canceled or not renewed and is not replaced with another claims-made policy with a retroactive date prior to the date on which any Services under this Agreement commence, Contractor must purchase “extended reporting” coverage for a minimum of five (5) years after completion of Project.
3.2.10.6 Deductibles and Self-Insurance Retentions. Any deductibles or self-insured retentions must be declared to and approved by the City. The City may require the Contractor to provide proof of ability to pay losses and related investigation, claims administration and defense expenses within the deductible or self-insured retention. The deductible or self-insured retention may be satisfied by either the named insured or the City.
3.2.10.7 Acceptability of Insurers. Unless under the circumstances a different rating is otherwise acceptable to the City in its sole and absolute discretion, insurance is to be placed with insurers which are satisfactory to the City and which meet either of the following criteria : (1) an insurer with a current A.M. Best’s rating no less than A-:VII and licensed as an admitted insurance carrier in California; or (2) an insurer with a current A.M.
Best’s rating no less than A-:X and authorized to issue the required policies in California.
3.2.10.8 Verification of Coverage. Contractor shall furnish City with original certificates of insurance, as well as amendatory endorsements or copies of the applicable policy language effecting coverage required by this Agreement. All documents must be received and approved by the City before any Services commence; provided, however, that failure to obtain the required documents prior to the commencement of Services shall not waive Contractor’s obligation to provide them. The City reserves the right to require complete, certified copies of all required insurance policies, at any time.
3.2.10.9 Reporting of Claims. Contractor shall report to the City, in addition to Contractor’s insurer, any and all insurance claims submitted by Contractor in connection with the Services under this Agreement.
3.2.10.10 Sub-Contractors. All subcontractors shall comply with each and every insurance provision of this Section 3.2.10. Contractor shall therefore not allow any subcontractor to commence work on any subcontract to perform any part of the Services until it has provided evidence satisfactory to the City that the subcontractor has secured all insurance required under this Agreement.
3.2.10.11 Special Risk or Circumstances. The City reserves the right, in its sole and absolute discretion, to modify the requirements of this Section 3.2.10, including limits, based on any of the following: (A) the nature of the risk of the Services; (B) the prior experience of the insured; (C) the rating or other quality or characteristic of the insurer; (D) any special or unique coverage issues; and (E) any other special or unique circumstances.
Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
9 (CITY ATTY: 07-17)
3.2.11 Safety. Contractor shall execute and maintain its work and Services so as to avoid injury or damage to any person or property. In carrying out its Services, the Contractor shall at all times be in compliance with all applicable local, state and federal laws, rules and regulations, and shall exercise all necessary precautions for the safety of employees appropriate to the nature of the Services and the conditions under which the Services are to be performed.
3.2.12 Bonds.
3.2.12.1 Performance Bond. If required by law or otherwise specifically requested by City in Exhibit “C” attached hereto and incorporated herein by reference, Contractor shall execute and provide to City, when the City approves an individual call-out and issues a project work order for that project, a Performance Bond in the amount of the project work order and in a form provided or approved by the City. If such bond is required, no payment will be made to Contractor until it has been received and approved by the City.
3.2.12.2 Payment Bond. If required by law or otherwise specifically requested by City in Exhibit “C” attached hereto and incorporated herein by reference, Contractor shall execute and provide to City, when the City approves an individual call-out and issues a project work order for that project, a Payment Bond in the amount of the project work order and in a form provided or approved by the City. If such bond is required, no payment will be made to Contractor until it has been received and approved by the City.
3.2.12.3 Bond Provisions. Should, in City’s sole opinion, any bond become insufficient or any surety be found to be unsatisfactory, Contractor shall renew or replace the affected bond within 10 days of receiving notice from City. In the event the surety or Contractor intends to reduce or cancel any required bond, at least thirty (30) days prior written notice shall be given to the City, and Contractor shall post acceptable replacement bonds at least ten (10) days prior to expiration of the original bonds. No further payments shall be deemed due or will be made under this Agreement until any replacement bonds required by this Section are accepted by the City. To the extent, if any, that the total compensation or compensation for a project work order is increased in accordance with the Agreement, the Contractor shall, upon request of the City, cause the amount of the bonds to be increased accordingly and shall promptly deliver satisfactory evidence of such increase to the City. To the extent available, the bonds shall further provide that no change or alteration of the Agreement (including, without limitation, an increase in the total compensation or compensation for a project work order, as referred to above), extensions of time, or modifications of the time, terms, or conditions of payment to the Contractor, will release the surety. If the Contractor fails to furnish any required bond, the City may terminate this Agreement for cause.
3.2.12.4 Surety Qualifications. The bonds must be provided by a surety which is satisfactory to the City and which meets either of the following criteria: (1) a surety with a current A.M. Best’s rating no less than A-:VII and licensed as an admitted surety insurer in California; or (2) a surety with a current A.M. Best’s rating no less than A-:X and authorized to issue the required bonds in California. If a surety does not meet these requirements, the insurer will be considered qualified if it is in conformance with Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
10 (CITY ATTY: 07-17)
Section 995.660 of the California Code of Civil Procedure, and proof of such is provided to the City.
3.2.13 Accounting Records. Contractor shall maintain complete and accurate records with respect to all costs and expenses incurred under this Agreement. All such records shall be clearly identifiable. Contractor shall allow a representative of City during normal business hours to examine, audit, and make transcripts or copies of such records and any other documents created pursuant to this Agreement. Contractor shall allow inspection of all work, data, documents, proceedings, and activities related to the Agreement for a period of three (3) years from the date of final payment under this Agreement.
3.3 Fees and Payments.
3.3.1 Rates & Total Compensation. Contractor shall receive compensation, including authorized reimbursements, for all Services rendered under this Agreement at the rates set forth in Exhibit “C” attached hereto and incorporated herein by reference. The total compensation, including authorized reimbursements, shall not exceed Two Hundred Thousand Dollars ($200,000) per fiscal year (“Total Compensation”) without written approval of City’s Representative. Extra Work may be authorized, as described below, and if authorized, will be compensated at the rates and manner set forth in this Agreement.
3.3.2 Payment of Compensation. Contractor shall submit to City a monthly itemized statement which indicates work completed and hours of Services rendered by Contractor. The statement shall describe the amount of Services and supplies provided since the initial commencement date, or since the start of the subsequent billing periods, as appropriate, through the date of the statement. City shall, within 30 days of receiving such statement, review the statement and pay all approved charges thereon.
3.3.3 Reimbursement for Expenses. Contractor shall not be reimbursed for any expenses unless authorized in writing by City.
3.3.4 Extra Work. At any time during the Term of this Agreement, City may request that Contractor perform Extra Work. As used herein, “Extra Work” means any work which is determined by City to be necessary for the proper completion of the Project, but which the Parties did not reasonably anticipate would be necessary at the execution of this Agreement.
Contractor shall not perform, nor be compensated for, Extra Work without written authorization from City’s Representative.
3.3.5 Prevailing Wages. Contractor is aware of the requirements of Chapter 1 (beginning at Section 1720 et seq.) of Part 7 of Division 2 of the California Labor Code, as well as Title 8, Section 16000 et seq. of the California Code of Regulations (“Prevailing Wage Laws”), which require the payment of prevailing wage rates and the performance of other requirements on “public works” and “maintenance” projects. If the Services are being performed as part of an applicable “public works” or “maintenance” project, as defined by the Prevailing Wage Laws, and if the Total Compensation is $1,000 or more, Contractor and its subcontractors shall fully comply with the Prevailing Wage Laws for their employees and any others to whom Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
11 (CITY ATTY: 07-17)
such laws are applicable. Contractor and its subcontractors shall also be responsible for any and all violations and fines imposed on them pursuant to the Prevailing Wage Laws. Pursuant to SB 854, which amended the Prevailing Wage Laws, this Agreement would also be subject to compliance monitoring and enforcement by the California Department of Industrial Relations (“DIR”). Beginning April 1, 2015, no contractor or subcontractor may be awarded this Agreement unless registered with the DIR pursuant to Labor Code Section 1725.5. The City will report all necessary agreements to the DIR as required by the Prevailing Wage Laws. Contractor shall make copies of the prevailing rates of per diem wages for each craft, classification or type of worker needed to execute the Services available to interested parties upon request and shall post copies at the Contractor’s principal place of business and at the Project site. It is most efficient for the Contractor to obtain a copy of the prevailing wages in effect at the commencement of this Agreement from the website of the Division of Labor Statistics and Research of the DIR located at www.dir.ca.gov/dlsr/. In the alternative, Contractor may obtain a copy of the prevailing wages from the City’s Representative. Contractor shall defend, indemnify and hold the City, its elected officials, officers, employees and agents free and harmless from any claim or liability arising out of any failure or alleged failure to comply with the Prevailing Wage Laws.
3.3.6 Apprenticeable Crafts. If the services are being performed as part of an applicable “public works” or “maintenance” project, as defined by the Prevailing Wage Laws, Contractor shall comply with the provisions of Section 1777.5 of the California Labor Code with respect to the employment of properly registered apprentices upon public works when Contractor employs workmen in an apprenticeable craft or trade. The primary responsibility for compliance with said section for all apprenticeable occupations shall be with Contractor.
3.4 Termination of Agreement.
3.4.1 Grounds for Termination. City may, by written notice to Contractor, terminate the whole or any part of this Agreement at any time and without cause by giving written notice to Contractor of such termination, and specifying the effective date thereof, at least seven (7) days before the effective date of such termination. Upon termination, Contractor shall be compensated only for those Services which have been adequately rendered to City, as well as any authorized reimbursable expenses, and Contractor shall be entitled to no further compensation. Contractor may not terminate this Agreement except for cause.
3.4.2 Effect of Termination. If this Agreement is terminated as provided herein, City may require Contractor to provide all finished or unfinished Documents and Data and other information of any kind prepared by Contractor in connection with the performance of Services under this Agreement. Contractor shall be required to provide such document and other information within fifteen (15) days of the request.
3.4.3 Additional Services. In the event this Agreement is terminated in whole or in part as provided herein, City may procure, upon such terms and in such manner as it may determine appropriate, services similar to those terminated.
3.5 General Provisions.
Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
12 (CITY ATTY: 07-17)
3.5.1 Delivery of Notices. All notices permitted or required under this Agreement shall be given to the respective Parties at the following address, or at such other address as the respective Parties may provide in writing for this purpose:
Contractor:
WGJ Enterprises, Inc.
975 W. 1st Street
Azusa, CA 91702
Attn: William Jacob
City:
City of Corona
400 South Vicentia Avenue
Corona, CA 92882
Attn: Savat Khamphou, Public Works Department
Such notice shall be deemed made when personally delivered or when mailed, forty-eight (48) hours after deposit in the U.S. Mail, first class postage prepaid and addressed to the Party at its applicable address. Actual notice shall be deemed adequate notice on the date actual notice occurred, regardless of the method of service.
3.5.2 Indemnification. To the fullest extent permitted by law, Contractor shall defend (with counsel of City’s choosing), indemnify and hold the City, its directors, officials, officers, employees, volunteers and agents free and harmless from any and all claims, demands, causes of action, costs, expenses, liability, loss, damage or injury of any kind, in law or equity, to property or persons, including wrongful death, to the extent arising out of, pertaining to, or incident to any alleged willful misconduct or negligent acts, errors or omissions of Contractor, its officials, officers, employees, subcontractors, consultants or agents in connection with the performance of the Contractor’s Services, the Project or this Agreement, including without limitation the payment of all settlement amounts, expert witness fees and attorneys fees and other related costs and expenses. Notwithstanding the foregoing, to the extent Contractor's Services are subject to Civil Code Section 2782.8, the above indemnity shall be limited, to the extent required by Civil Code Section 2782.8, to claims that arise out of, pertain to, or relate to the negligence, recklessness, or willful misconduct of the Contractor. Contractor’s obligation to indemnify shall survive expiration or termination of this Agreement, and shall not be restricted to insurance proceeds, if any, received by the City, its directors, officials, officers, employees, agents, or volunteers.
3.5.3 Governing Law; Government Code Claim Compliance. This Agreement shall be governed by the laws of the State of California. Venue shall be in Riverside County. In addition to any and all contract requirements pertaining to notices of and requests for compensation or payment for extra work, disputed work, claims and/or changed conditions, Contractor must comply with the claim procedures set forth in Government Code Sections 900 et seq. prior to filing any lawsuit against the City. Such Government Code claims and any subsequent lawsuit based upon the Government Code claims shall be limited to those matters that remain unresolved after all procedures pertaining to extra work, disputed work, claims, Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
13 (CITY ATTY: 07-17)
and/or changed conditions have been followed by Contractor. If no such Government Code claim is submitted, or if any prerequisite contractual requirements are not otherwise satisfied as specified herein, Contractor shall be barred from bringing and maintaining a valid lawsuit against the City.
3.5.4 Time of Essence. Time is of the essence for each and every provision of this Agreement.
3.5.5 City’s Right to Employ Other Contractors. City reserves right to employ other contractors in connection with this Project.
3.5.6 Successors and Assigns. This Agreement shall be binding on the successors and assigns of the parties.
3.5.6.1 Subcontractors; Assignment or Transfer. Contractor shall not subcontract any portion of the Services required under this Agreement, except as expressly authorized herein, without the prior written approval of the City. Subcontracts, if any, shall include a provision making them subject to all provisions of this Agreement. Contractor shall also not assign, hypothecate or transfer, either directly or by operation of law, this Agreement or any interest herein without the prior written consent of the City. Any attempt to subcontract or take any other action not authorized herein shall be null and void, and any subcontractors, assignees, hypothecates or transferees shall acquire no right or interest by reason of such action.
3.5.7 Construction; References; Captions. Since the Parties or their agents have participated fully in the preparation of this Agreement, the language of this Agreement shall be construed simply, according to its fair meaning, and not strictly for or against any Party. Any term referencing time, days or period for performance shall be deemed calendar days and not work days. All references to Contractor include all personnel, employees, agents, and subcontractors of Contractor, except as otherwise specified in this Agreement. All references to City include its elected officials, officers, employees, agents, and volunteers except as otherwise specified in this Agreement. The captions of the various articles and paragraphs are for convenience and ease of reference only, and do not define, limit, augment, or describe the scope, content or intent of this Agreement.
3.5.8 Amendment; Modification. No supplement, modification or amendment of this Agreement shall be binding unless executed in writing and signed by both Parties.
3.5.9 Waiver. No waiver of any default shall constitute a waiver of any other default or breach, whether of the same or other covenant or condition. No waiver, benefit, privilege, or service voluntarily given or performed by a Party shall give the other Party any contractual rights by custom, estoppel or otherwise.
3.5.10 No Third Party Beneficiaries. Except to the extent expressly provided for in Section 3.5.6, there are no intended third party beneficiaries of any right or obligation assumed by the Parties.
Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
14 (CITY ATTY: 07-17)
3.5.11 Invalidity; Severability. If any portion of this Agreement is declared invalid, illegal, or otherwise unenforceable by a court of competent jurisdiction, the remaining provisions shall continue in full force and effect.
3.5.12 Prohibited Interests. Contractor maintains and warrants that it has not employed nor retained any company or person, other than a bona fide employee working solely for Contractor, to solicit or secure this Agreement. Further, Contractor warrants that it has not paid nor has it agreed to pay any company or person, other than a bona fide employee working solely for Contractor, any fee, commission, percentage, brokerage fee, gift or other consideration contingent upon or resulting from the award or making of this Agreement. Contractor further agrees to file, or shall cause its employees or subcontractors to file, a Statement of Economic Interest with the City’s Filing Officer as required under state law in the performance of the Services. For breach or violation of this warranty, City shall have the right to rescind this Agreement without liability. For the Term of this Agreement, no member, officer or employee of City, during the term of his or her service with City, shall have any direct interest in this Agreement, or obtain any present or anticipated material benefit arising therefrom.
3.5.13 Cooperation; Further Acts. The Parties shall fully cooperate with one another and shall take any additional acts or sign any additional documents as may be necessary, appropriate or convenient to attain the purposes of this Agreement.
3.5.14 Attorney’s Fees. If either Party commences an action against the other Party, either legal, administrative or otherwise, arising out of or in connection with this Agreement, the prevailing Party in such litigation shall be entitled to have and recover from the losing Party reasonable attorney’s fees and all other costs of such action.
3.5.15 Authority to Enter Agreement. Contractor has all requisite power and authority to conduct its business and to execute, deliver, and perform the Agreement. Each Party warrants that the individuals who have signed this Agreement have the legal power, right, and authority to make this Agreement and bind each respective Party.
3.5.16 Counterparts. This Agreement may be signed in counterparts, each of which shall constitute an original.
3.5.17 Entire Agreement. This Agreement contains the entire Agreement of the Parties with respect to the subject matter hereof, and supersedes all prior negotiations, understandings, or agreements. This Agreement may only be modified by a writing signed by both Parties.
[SIGNATURES ON NEXT 2 PAGES]
Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
15 (CITY ATTY: 07-17)
CITY’S SIGNATURE PAGE FOR
CITY OF CORONA
MAINTENANCE/GENERAL SERVICES AGREEMENT
WITH WGJ ENTERPRISES. INC. DBA PCI
(“AS-NEEDED” STREET STRIPING AND PAVEMENT MARKING MAINTENANCE AND REPAIR SERVICES – RFP 25-014SB)
IN WITNESS WHEREOF, the Parties have entered into this Agreement as of the date first written above.
CITY OF CORONA
Approved By: _________________________
Savat Khamphou
Public Works Director/City Engineer
Reviewed By:
_________________________
Rosalva Ureno
City Traffic Engineer
Reviewed By: _________________________
Yasmin Lopez
Purchasing Manager
Attest:
_________________________
Sylvia Edwards, City Clerk
City of Corona, California
Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
16 (CITY ATTY: 07-17)
CONTRACTOR’S SIGNATURE PAGE FOR
CITY OF CORONA
MAINTENANCE/GENERAL SERVICES AGREEMENT
WITH WGJ ENTERPRISES. INC. DBA PCI
(“AS-NEEDED” STREET STRIPING AND PAVEMENT MARKING MAINTENANCE AND REPAIR SERVICES – RFP 25-014SB)
IN WITNESS WHEREOF, the Parties have entered into this Agreement as of the date first written above.
WGJ ENTERPRISES, INC. DBA PCI
a California corporation
By: _________________________
William Jacob
President
By: _________________________
Todd Moysychyn
CFO
Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
17 (CITY ATTY: 07-17)
EXHIBIT “A”
SCOPE OF SERVICES
Contractor promises and agrees to furnish to the City all labor, materials, tools, equipment, services, and incidental and customary work necessary to fully and adequately supply the professional as- needed street striping and pavement marking maintenance and repair services are more particularly described herein.
General
The work performed under this Contract shall include the furnishing of all labor, materials, and equipment necessary to perform “as- needed” street striping and pavement markings within the City. All work shall be done in accordance with the latest edition of Caltrans Standard Plans and Specifications, the City of Corona Standard Plans, and The “Greenbook” Standard Specifications for Public Works Construction, and Technical Specifications herein.
Description of Work/Scope of Works:
The type of street striping and related services shall consist of the following:
1. Thermoplastic or paint reflective pavement arrows, centerlines, lane lines, edge lines, bike lanes, stop and yield bars, crosswalks and pavement marking legends
2. Removing of pavement arrows, centerlines, lane lines, edge lines, bike lanes, stop and yield bars, crosswalks and pavement marking legends
3. Re-striping in thermoplastic or paint per existing alignment
4. Placement of raised pavement markers
5. Paint and removal of reflective color curb markings
Specification for Traffic Striping, Pavement Marking, and Curb Marking GREENBOOK 2021 SPECIFICATIONS
214 – TRAFFIC STRIPING, CURB AND PAVEMENT MARKINGS, AND PAVEMENT
MARKERS
Test Reports and Certification – Replace the first sentence with the following:
Prior to delivery of thermoplastic material, the Contractor shall submit to the Engineer certified copies of the manufacturer’s test reports and MSDS in accordance with 3-8 and 7-10.4.3.
Re-Striping
All re-striping and re-painting of existing traffic stripes shall coincide with the original paintings, regardless of other more restrictive requirements of these Special Provisions unless directed by the Engineer.
Removal of Markings
Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
18 (CITY ATTY: 07-17)
Removing of centerlines, lane lines, raised pavement markers and pavement marking legends shall be accomplished by wet sandblasting or grinding method. Errors made by the Contractor shall be removed at no additional cost to the City. Upon written direction of the City Traffic Engineer, or his assigned staff, pavement markings may be removed by blacking out with black paint.
Preparation
It shall be the responsibility of the Contractor to ensure that, prior to any pavement striping or marking, the surface is clear of all debris.
Traffic Control
The Contractor shall make every effort to assure the safety of vehicular and pedestrian traffic during his operations. The latest edition of the California Manual on Uniform Traffic Control Devices is herein adopted as the minimum safety guidelines. Contractor shall not close any street within the City without first obtaining the approval of the City Engineer.
Thermoplastic Measurement
Thermoplastic traffic stripes will be measured by the units in the bid schedule of each pavement marking type, without deductions for gaps in broken stripes. Each thermoplastic detail that includes multiple stripes such as detail 29 shall be measured as a single linear unit for all four individual stripes as an example.
Thermoplastic Payment
The contract unit prices paid per linear foot for thermoplastic traffic stripes of the patterns designated in this Request for Proposals and per square foot for each pavement marking legend shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all work involved in applying thermoplastic traffic stripes and pavement makings complete in place, including establishing alignment for stripes and layout work, as shown on the plans, as specified in these specifications and the special provisions and as directed by the Engineer. The cost of any necessary raised pavement markers required for any striping detail designated in the Proposal shall be considered to be included in the cost per linear foot for each detail and no separate payment will be made therefore.
Paint Measurement
Painted traffic stripes will be measured by the units in the bid schedule of each pavement marking type, without deductions for gaps in broken stripes. Each painted detail that includes multiple stripes such as detail 29 shall be measured as a single linear unit for all four individual stripes as an example.
Paint Payment
Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
19 (CITY ATTY: 07-17)
The contract unit prices paid per linear foot for painted traffic stripes of the patterns designated in this Request for Proposal and per square foot for each pavement marking legend shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all work involved in applying painted traffic stripes and pavement makings complete in place, including establishing alignment for stripes and layout work, as shown on the plans, as specified in these specifications and the special provisions and as directed by the Engineer. The cost of any necessary raised pavement markers required for any striping detail designated in the Proposal shall be considered to be included in the cost per linear foot for each detail and no separate payment will be made therefore.
Traffic stripes and pavement markings not designated as thermoplastic shall conform to the provisions of Section 84-3 “Painted Traffic Stripes and Pavement Markings” of the Caltrans Standard Specifications and these Special Provisions.
Only water borne paints will be permitted for use with the City.
Pavement Markers
Pavement markers shall conform to the provisions in Section 85, “Pavement Markers”, of the Caltrans Standard Specifications (latest editions) and these Special Provisions.
Control of Alignment and Layout
Before obliterating (or covering) any pavement delineation that is to be replaced on the same alignment and location, as determined by the Inspector, the pavement delineation shall be referenced by the Contractor, with a sufficient number of control points to reestablish the alignment and location of the new pavement delineation. The references shall include the limits or changes in striping pattern, including one- and 2-way barriers lines, limit lines, crosswalks and other pavement markings. Full compensation for referencing pavement delineation shall be considered included in the contract prices paid for new pavement delineation and no additional compensation will be allowed therefore.
Unless otherwise shown, the Contractor shall re-stripe all pavement delineation to existing locations or as directed by the Engineer.
Traffic stripes shall be painted to the alignment approved by the Engineer. The Contractor shall not proceed with the application of any pavement markings and/or striping until the Engineer has checked and approved the alignment marks. The Engineer may make minor adjustments to the proposed alignment prior to approval.
Alignment marks may consist of cat-tracking and spotting, or an approved alternative.
Cat-tracking shall consist of stretching a rope on a straight line between control points on tangent alignment and on a true arc through control points on curved alignment and placing spots of paint along the rope. The spots shall be not more than 3 inches in width and not more than 5 feet apart on curves or 10 feet apart on tangents.
Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
20 (CITY ATTY: 07-17)
Paint for the cat-tracks shall be the same color as the traffic stripe for which they are placed.
Laser guidance equipment shall be capable of maintaining the alignment of traffic stripes with accuracy equivalent to or better than that obtainable through the use of cat tracking as determined by the Engineer.
All work necessary to establish satisfactory alignment for stripes and all layout work required for pavement markings shall be performed by the Contractor at his expense, including correction of minor irregularities in the control points approved by the Engineer. Correction of minor irregularities shall be accomplished by the application of cat tracks, the use of laser guidance devices, or by a combination of these techniques.
Remove Pavement Delineation
Existing traffic stripes and pavement markings that do not conform to the plans and are not removed or obliterated as a result of the various pavement rehabilitation operations, shall be removed by wet sand blasting or grinding as approved by the Engineer.
Mandatory Requirements:
The contractors and their sub-contractors shall wear Hard Hats, Safety Vests and Goggles at all work sites.
Contractors shall require each of his employees to wear basic public works working attire. Contractors Employees shall to wear uniforms at all times when working on City property which clearly identifies to the public the name of the Contractor responsible for the maintenance services and the employee’s name.
Contractors shall park their vehicles and equipment to comply with all safety standards of OSHA or CAL-OSHA.
The Contractor shall abide by the provisions of the latest edition of the Work Area Traffic Control Handbook.
The Contractor shall promptly clean all job sites when work is completed, generated from their operations and follow all City of Corona Best Management Practices for National Pollutant Discharge Elimination System (NPDES) regulations. The City of Corona NPDES regulations may be accessed at this link:
http://www.discovercorona.com/City-Departments/Public-Works/Development-andPermits/NPDES-Useful-Links.aspx Major rehabilitation and construction of street facilities is handled by the Capital Improvement Projects Section of Public Works and is not a part of this contract.
Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
21 (CITY ATTY: 07-17)
NOTE – NOT PUBLIC PROJECT WORK
This Agreement generally governs only work which is considered to be “maintenance work” under CMC Section 3.08.010(k) and Public Contract Code Section 22002(d) and does not include “public project” work under CMC Section 3.08.010(m) and Public Contract Code Section 22002(c). The only time that an individual call-out, as described in Exhibit “B” and Exhibit “C” attached hereto, might include “public project” work is when an individual call-out is strictly limited to an amount that is not required to be informally or formally bid under the CMC or state law (e.g. less than $60,000), and individual projects shall not be split to fall below that amount.
Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
22 (CITY ATTY: 07-17)
EXHIBIT “B”
SCHEDULE OF SERVICES
Contractor shall perform the Services within the Term of this Agreement, in accordance with the Schedule of Services set forth in this Exhibit.
Mobilization
The Contractor shall not start work in the City until he receives a written work order from the City Traffic Engineer, or his assigned staff. The Contractor must have such list in his possession before starting work. The Contractor shall perform only that work listed and will only be compensated for the work listed on the work order. The Contractor shall be given a minimum of $3,500.00 of work to warrant sending out a crew. All cost for mobilization for each work order, regardless of quantity of work requested, shall be considered included in the unit bid price for the requested work and no additional compensation to the Contractor shall be made.
Contractor shall respond to routine requests for service within five (5) working days of the initial notification/request.
Contractor shall respond with a crew to provide emergency street striping and pavement marking repairs within two (2) working days of the City of Corona making the request for emergency services.
Scheduling of Work Orders
Contractor shall notify the City Traffic Engineer, or his assigned staff, the estimated start date of the work within seven (7) calendar days of receiving the work orders. The start date of work orders meeting the minimum mobilization charges shall not exceed twenty-one (21) calendar days. Work orders must be completed in seven (7) calendar days after start of work unless other arrangements have been made with the City. Contractor shall be liable for liquidated damages as set forth in the Contract Agreement section 3.2.7.1 due to delayed start beyond the allotted twenty-one (21) calendar days. Contractor shall also be liable for liquidated damages as set forth in the Contract Agreement due to delayed completion of work beyond the allotted seven (7) calendar days after start of work.
Hours of Operation
The hours of operation for the performance of the Work shall be 8:30 AM to 3:30 PM, Monday through Friday. No lane closures will be permitted prior to 8:30 AM or after 3:30 PM unless Contractor obtains prior written approval from City Engineer.
On some street segments, the volume of traffic may require that the work must be at night or on the weekend. The contractor shall obtain written approval from the City Traffic Engineer prior to Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
23 (CITY ATTY: 07-17)
scheduling the work in these locations. The nighttime work hours are 10:00 PM to 4:00 AM and weekend work hours are 7:00 AM to 4:00 PM.
AS-NEEDED SERVICES
Each individual call-out under this Agreement is a separate project for purposes the City’s bidding and purchasing requirements.
Contractor shall provide the Services on an as-needed basis, and as scheduled and directed by the City’s Representative.
For each individual call-out, Contractor shall respond, mobilize and be on-site ready to start work no later than 24 hours after notification for routine work, repairs and installations.
Contractor must be able to respond by telephone to emergency call-out notifications from City within Two (2) working Days of being notified by City that there is an emergency, and to be mobilized and on-site within one (1) hour of such emergency notification by City.
Contract Term
The contract term shall be effective pursuant to Section 3.1.2 above with two (2) additional option two-year renewal periods, on an as-needed basis, with no guaranteed usage for street striping and pavement marking Services. Bid prices shall remain effective and in force for the entire initial contract terms. City reserves the right to exercise option year renewals in its sole discretion. Subsequent contract, term extensions, if exercised by the City, are as follows:
Option 1, if exercised, shall be effective July 1, 2026 through June 30, 2028 Option 2, if exercised, shall be effective July 1, 2028 through June 30, 2030 Option year pricing shall be negotiated by the Parties prior to commencement of each additional two-year period. Negotiated price adjustments will be made in accordance with and shall not exceed the percentage of change in the United States Bureau of Labor Statistics Consumer Price Index “All Urban Consumers for Riverside, California, Area (CPI-U), not seasonally adjusted, for the most recent twelve (12) months for which statistics are available. This method of price adjustment shall apply to each extension period exercised. Optional years shall become effective only upon issuance by the City of a duly authorized Purchase Order.
Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
24 (CITY ATTY: 07-17)
EXHIBIT “C”
COMPENSATION
Contractor shall receive compensation, including authorized reimbursements, for all Services rendered under this Agreement at the rates set forth in this Exhibit.
Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
25 (CITY ATTY: 07-17)
BONDS
Each individual call-out under this Agreement is a separate project for purposes of the City’s bidding and purchasing requirements, including, but not limited to, its bond requirements provided for in Civil Code Section 9550, which mandates that the City require a payment bond for certain public work projects involving an expenditure in excess of $25,000.
Payment Bonds: Contractor shall provide a 100% payment bond for all individual call-out projects for which a project work order has been issued by the City in excess of $25,000.
Performance Bonds: Contractor shall be required to provide a 100% performance bond whenever the City indicates that one is required in the project work order issued for an individual call-out project.
Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
CA\DD\02000.50102\10151745.3
26 (CITY ATTY: 07-17)
Cost of Bonds: Whenever a bond is required by the City for an individual call-out project, Contractor will be able to include the costs of the bonds for that individual call-out.
Docusign Envelope ID: 33C2EAFE-2908-4251-B311-22BE096AE5E6 Docusign Envelope ID: 8DC943E5-7AE8-49BC-A1D9-154A2B95DBB3
DATE: 04/02/2025
TO: Honorable Mayor and City Council Members
FROM: Public Works Department
2025-133
REQUEST FOR CITY COUNCIL ACTION
SUBJECT:
CONSTRUCTION CONTRACT WITH VENTURE CONSTRUCTION & MANAGEMENT
FOR THE CITY HALL VETERANS MEMORIAL IMPROVEMENTS
EXECUTIVE SUMMARY:
This staff report asks the City Council to find David Ollis Landscape Development, Inc. non-responsive for the City Hall Veterans Memorial Improvements Project (Project), previously awarded on December 4, 2024, and approve a Construction Contract with Venture Construction & Management, in the amount of $488,635, resulting from the rebid process. This project will make several improvements to the Veterans Memorial at City Hall, including adding military flagpoles, removing existing archways, installing amphitheater seating, a granite monument, and additional landscaping and lighting.
RECOMMENDED ACTION:
That the City Council:
a. Find David Ollis Landscape Development, Inc. non-responsive to Notice Inviting Bids 25-019AT and reject all other prior bids for reasons noted in this staff report, and cancel the existing contract.
b. Approve the Construction Contract with Venture Construction & Management for the City Hall Veterans Memorial Improvements Project Re-Bid, No. FC-2023-06, in the amount of $488,635.
c. Award Notice Inviting Bids 25-039AT to Venture Construction & Management, the lowest responsive, responsible bidder, for the total bid amount of $488,635, and waive all minor irregularities in the bidding document as submitted by the said bidder.
d. Authorize the City Manager, or his designee, to execute the Construction Contract with Venture Construction & Management in the amount of $488,635, including any non-substantive extensions, change orders, purchase orders, and amendments up to the amount authorized by Corona Municipal Code Section
3.08.050(H) which is equivalent to 10% or $48,863.
e. Authorize an appropriation in the amount of $122,414 from Measure X Fund 120 to the City Hall Veterans Memorial Improvements Project, No. FC-2023-06.
BACKGROUND & HISTORY:
The current City of Corona Veterans Memorial is located at the south side of City Hall.
On November 10, 2021, the Committee of the Whole (COTW) directed City staff to proceed with an enhancement project including granite monuments, taller flag poles, lighting, signage, landscaping, and seating. After a request for proposals process, the City executed an agreement and purchase order with IDS Group, Inc. in accordance with Corona Municipal Code (CMC) Section 3.08.070.
Three design concepts were developed and presented to the City Council for consideration at the July 19, 2023, meeting. Staff received direction to obtain feedback from the Corona veterans community and released online and printed surveys to collect input. The survey results were presented to the City Council on December 6, 2023, along with a recommendation to proceed with the Option B “Honor and Glory” design with a few modifications, including removing the free-standing archways adjacent to the memorial.
The Project was first advertised for bids on September 30, 2024, pursuant to CMC section
3.08.090, Public projects - formal bidding procedure, and the City’s purchasing policy through the City’s PlanetBids bidding portal. On November 7, 2024, four (4) bids were received through the PlanetBids bidding service. The lowest responsive, responsible bidder was determined to be David Ollis Landscape Development, Inc., and a contract was awarded at the City Council meeting on December 4, 2024.
City staff proceeded to send a Notice of Award to obtain the various required documents, including bonds and insurance, from David Ollis Landscape Development. However, after several attempts, David Ollis Landscape Development was not able to provide all of the insurance policies as required by the bid and contract documents. As a result, staff requests that the City Council find that David Ollis Landscape Development, Inc. failed to provide these documents and deem the contractor non-responsive. Unfortunately, staff
also discovered issues with the bid documents, and thus, all other bids received needed to be rejected, and the project needed to be re-bid.
ANALYSIS:
The Project was re-advertised for bids on February 7, 2025, in the Sentinel Weekly, and the project was posted on the City’s PlanetBids website on January 30, 2025, pursuant to CMC section 3.08.090, Public projects - formal bidding procedure, and the City’s purchasing policy. A total of 380 registered vendors with the City of Corona were notified of the project, 30 prime contractors registered as prospective bidders, and six potential bidders attended a non-mandatory pre-bid job walk on February 11, 2025. On March 13, 2025, four (4) bids were received through the PlanetBids bidding service.
No. Contractor Location Bid Total
1 Venture Construction & Management Corona, CA $488,635 2 Elegant Construction Inc. Irvine, CA $699,550
3 US Builders and Consultants Irvine, CA $945,400
4 RG General Engineering Inc. Norco, CA $1,015,459
Staff has reviewed all bids and recommends awarding the contract to Venture Construction & Management as the lowest responsive, responsible bidder based on the Bid Schedule for a total contract amount of $488,635. City staff has reviewed and verified all licenses and documents for Venture Construction & Management, and all other documentation is in order.
FINANCIAL IMPACT:
This project is currently funded by Measure X Fund 120, with a balance of $507,976.
Upon City Council approval of the appropriation, funding to complete the construction and inspection of the City Hall Veterans Memorial Improvement Project will be available in the Capital Improvement Project No. FC-2023-06.
The estimated construction costs for the project are outlined as follows:
Construction
…………………………………………………………………………………………….
$488,635
Construction Inspection, Labor Compliance, and Staff Time ……………………………… $92,892
Contingency (10%)
……………………………………………………………………………………… $48,863
Total Project Cost
………………………………………………………………………………… $630,390
Staff recommends an appropriation as follows:
Project No. Fund Current
Balance
Requested
Appropriation
Revised
Balance
FC-2023-06
(City Hall
Veterans
Memorial
Improvements)
Measure X
Fund 120
$507,976 $127,414 $630,390
ENVIRONMENTAL ANALYSIS:
The City Hall Veterans Memorial Improvement project action is categorically exempt pursuant to Section 15301 of the Guidelines for the California Environmental Quality Act (CEQA), which states that the operation, repair, maintenance, permitting, leasing, licensing, or minor alteration of existing public or private structures, facilities, mechanical equipment, or topographical features, involving negligible or no expansion of use beyond that existing at the time of the CEQA determination and is therefore exempt from CEQA.
Therefore, no environmental analysis is required and staff has filed a Notice of Exemption with the County of Riverside.
PREPARED BY: TRACY MARTIN, SENIOR PROJECT MANAGER
REVIEWED BY: SAVAT KHAMPHOU, PUBLIC WORKS DIRECTOR
ATTACHMENTS:
1. Exhibit 1 – Location Map
2. Exhibit 2 – Construction Contract
SIXTH
VICENTIA
SEVENTH
BUENA VISTA
PROJECT
LOCATION
CORONA
CITY HALL
CORONA HISTORIC
CIVIC CENTER
CITY OF CORONA
VETERAN'S MEMORIAL ENHANCEMENT PROJECT
PROJECT LOCATION MAP
400 S. VICENTIA AVENUE
CORONA, CA 92882 Ü
CONTRACT
THIS CONTRACT is made this _____ day of ________________, 20___, in the County of Riverside, State of California, by and between the City of Corona, hereinafter called City, and Venture Construction & Management hereinafter called Contractor. The City and the Contractor for the considerations stated herein agree as follows:
ARTICLE 1. SCOPE OF WORK. The Contractor shall perform all Work within the time stipulated the Contract and shall provide all labor, materials, equipment, tools, utility services, and transportation to complete all of the Work required in strict compliance with the Contract Documents as specified in Article 5 below for the following Project:
City Hall Veterans Memorial Improvements Project - REBID, Project No. FC-2023-06, NIB No. 25-039AT
The Contractor and its surety shall be liable to the City for any damages arising as a result of the Contractor’s failure to comply with this obligation.
ARTICLE 2. TIME FOR COMPLETION. A Move-in period of 15 calendar days shall start on the date of issuance of the Notice to Proceed. This period shall be used by the Contractor to confirm utility locations, turn in project submittals or other supporting documentation for approval and procure the necessary material and equipment to complete the Work. The Work shall commence on the last day of the Move-in period or the first Working Day the Contractor actually starts the Work, whichever occurs first. The Contractor shall complete all Work required by the Contract Documents within 75 Working Days. By its signature hereunder, Contractor agrees the time for completion set forth above is adequate and reasonable to complete the Work.
ARTICLE 3. CONTRACT PRICE. The City shall pay to the Contractor as full compensation for the performance of the Contract, subject to any additions or deductions as provided in the Contract Documents, and including all applicable taxes and costs, the sum of Four Hundred Eighty Eight Thousand Six Hundred and Thirty Five Dollars ($488,635.00) Payment shall be made as set forth in the General Conditions.
ARTICLE 4. LIQUIDATED DAMAGES. In accordance with Government Code section 53069.85, it is agreed that the Contractor will pay the City the sum of $1,000 for each and every calendar day of delay beyond the time prescribed in the Contract Documents for finishing the Work, as Liquidated Damages and not as a penalty or forfeiture. In the event this is not paid, the Contractor agrees the City may deduct that amount from any money due or that may become due the Contractor under the Contract. This Article does not exclude recovery of other damages specified in the Contract Documents.
ARTICLE 5. COMPONENT PARTS OF THE CONTRACT. The “Contract Documents” include the following:
Notice Inviting Bids
Instructions to Bidders
Contractor's Bid Forms
Contractor’s Certificate Regarding Workers’ Compensation Bid Bond
Designation of Subcontractors
Docusign Envelope ID: F013DC56-84A9-4600-A7C9-09457FFE9EB3 Docusign Envelope ID: 319377CB-54FB-4FC8-AAE6-937B15330982
Information Required of Bidders
Non-Collusion Declaration form
Contract
Performance Bond
Payment (Labor and Materials) Bond
General Conditions
Special Provisions (or Special Conditions)
Technical Specifications
Addenda
Plans and Contract Drawings
Approved and fully executed change orders
Any other documents contained in or incorporated into the Contract The Contactor shall complete the Work in strict accordance with all of the Contract Documents.
All of the Contract Documents are intended to be complementary. Work required by one of the Contract Documents and not by others shall be done as if required by all. This Contract shall supersede any prior agreement of the parties.
ARTICLE 6. PROVISIONS REQUIRED BY LAW. Each and every provision of law required to be included in these Contract Documents shall be deemed to be included in these Contract Documents. The Contractor shall comply with all requirements of applicable federal, state and local laws, rules and regulations, including, but not limited to, the provisions of the California Labor Code and California Public Contract Code which are applicable to this Project.
ARTICLE 7. INDEMNIFICATION. Contractor shall provide indemnification as set forth in the General Conditions.
ARTICLE 8. PREVAILING WAGES. Contractor is aware of the prevailing wage requirements of Chapter 1 (beginning at Section 1720 et seq.) of Part 7 of Division 2 of the California Labor Code, as well as Title 8, Section 16000 et seq. of the California Code of Regulations (“Prevailing Wage Laws”), which require the payment of prevailing wage rates and the performance of other requirements on “public works” and “maintenance” projects. Contractor and its subcontractors shall fully comply with the Prevailing Wage Laws for their employees and any others to whom such laws are applicable. Contractor and its subcontractors shall also be responsible for any and all violations and fines imposed on them pursuant to the Prevailing Wage Laws. Pursuant to SB 854, which amended the Prevailing Wage Laws, this Contract is subject to compliance monitoring and enforcement by the DIR. Beginning April 1, 2015, no contractor or subcontractor may be awarded this Contract unless registered with the DIR pursuant to Labor Code section 1725.5. The City will report all necessary contracts to the DIR as required by the Prevailing Wage Laws.
Contractor shall make copies of the prevailing rates of per diem wages for each craft, classification or type of worker needed to execute the Work available to interested parties upon request, and shall post copies at the Contractor’s principal place of business and at the Project site. It is most efficient for the Contractor to obtain a copy of the prevailing wages in effect at the commencement of this Contract from the website of the Division of Labor Statistics and Research of the DIR located at www.dir.ca.gov/dlsr/. In the alternative, the Contractor may obtain a copy of the prevailing wages from the City. Contractor shall defend, indemnify and hold the City, its elected officials, officers, employees and agents free and harmless from any claim or liability arising out of any failure or alleged failure to comply with the Prevailing Wage Laws. [REMAINDER OF PAGE LEFT INTENTIONALLY BLANK
Docusign Envelope ID: F013DC56-84A9-4600-A7C9-09457FFE9EB3 Docusign Envelope ID: 319377CB-54FB-4FC8-AAE6-937B15330982
SIGNATURES ON FOLLOWING PAGE]
Docusign Envelope ID: F013DC56-84A9-4600-A7C9-09457FFE9EB3 Docusign Envelope ID: 319377CB-54FB-4FC8-AAE6-937B15330982
IN WITNESS WHEREOF, this Contract has been duly executed by the above-named parties, on the day and year above written.
CITY OF CORONA
By:
______________________________
Savat Khamphou
Public Works Director
Reviewed By:
______________________________
Javier Luna
CIP Manager
Reviewed By:
______________________________
Rachel McLure
CIP Supervisor
Reviewed By:
______________________________
Tracy Martin
Senior Project Manager
Reviewed By:
______________________________
Yasmin Lopez
Purchasing Manager
Attest:
______________________________
Sylvia Edwards, City Clerk
City of Corona, California
Venture Construction & Management
By:
______________________________
Signature
Bobby Ragasa
_____________________________
Name
Owner
______________________________
Title
980460
______________________________
License Number
Docusign Envelope ID: F013DC56-84A9-4600-A7C9-09457FFE9EB3 Docusign Envelope ID: 319377CB-54FB-4FC8-AAE6-937B15330982
DATE: 04/02/2025
TO: Honorable Mayor and City Council Members
Honorable President and Board Members
FROM: Utilities Department
2025-134
REQUEST FOR CITY COUNCIL AND
CORONA UTILITY AUTHORITY ACTION
SUBJECT:
UPDATE ON CONTRACTED EMERGENCY TRANSMISSION WATER MAIN AND PARKING LOT REPAIRS AT 515 SOUTH PROMENADE AVENUE PURSUANT TO CORONA MUNICIPAL CODE SECTION 3.08.130(A)
EXECUTIVE SUMMARY:
This staff report provides the City Council with an update, pursuant to Corona Municipal Code Section 3.08.130(A), on the contracted emergency repairs related to the transmission water main line break that occurred at 515 South Promenade Avenue on March 6, 2025.
RECOMMENDED ACTION:
That the City Council receive and file the update to contracted emergency transmission water main line and parking lot repairs at 515 South Promenade Avenue.
That the Corona Utility Authority review, ratify, and to the extent necessary, direct the City Council to take the above actions.
BACKGROUND & HISTORY:
On March 6, 2025, at approximately 4:00 p.m., the City of Corona Utilities Department responded to a water main break. A thirty-inch diameter transmission water main line at South Promenade Avenue, south of Sampson Avenue, experienced a significant failure.
The thirty-inch cross-town transmission water main provides water to the Home Gardens and Zone 2 service areas.
On March 19, 2025, the City Council was formally notified of the contracted emergency repairs related to the transmission water main line break on South Promenade Avenue, pursuant to Corona Municipal Code (CMC) Section 3.08.130(A).
ANALYSIS:
The water main line break caused significant damage to the parking lot at 515 South Promenade. The Utilities Department (UD) solicited informal bidding from four qualified contractors experienced in asphalt and concrete repairs and received three bids, as shown below.
CT&T Concrete Paving, Inc., is tentatively scheduled to begin the parking lot restoration to minimize the adverse impact on the business.
Staff will request the ratification of the Maintenance/General Services Agreement with CT&T Concrete Paving, Inc. for $95,243.54 at a future City Council meeting with the related cost incurred for the repair of the watermain, remediation and restoration which will include detailed cost information for labor, materials, and equipment.
BASIS FOR EXCEPTION TO COMPETITIVE BIDDING:
Staff believes that an exception to competitive bidding was warranted for this action pursuant to Corona Municipal Code Section 3.08.130(A), which states as follows:
(A) Emergencies. In situations determined by the City Manager to constitute an emergency for a public project pursuant to § 22035 of the Act and Cal. Public Contract Code § 22050. The City Council hereby delegates to the City Manager the power to declare a public emergency and take any directly related and immediate action required by the emergency, up to a total of $175,000, pursuant to § 22035 of the Act and Cal. Public Contract Code § 22050. Emergency expenditures of more than $175,000 shall first be approved by the City Council. Work shall be performed without the benefit of competitive bidding, either formal or informal, only so long as necessary under those sections.
Vendor City Bid Amount
CT&T Concrete Paving, Inc. Diamond Bar, CA $95,243.54
A&Y Asphalt Contractors, Inc. Norco, CA $123,077
TSR Construction Rancho Cucamonga, CA $123,508
Hardy and Harper, Inc Lake Forest, CA No bid received
For projects of more than $45,000, a report on the emergency and work performed shall be provided at the next regular meeting of the City Council, and then at every meeting thereafter required by § 22050. At such meetings, the City Council shall determine, by a four-fifths vote, that there is a need to continue the action without the benefit of informal or formal competitive bidding in accordance with § 22035 of the Act and Cal. Public Contract Code § 22050. The City Council shall terminate the emergency action at the earliest possible date that conditions warrant, so that the remainder of the emergency action may be completed pursuant to a formal bidding procedure.
Staff believes the restoration of the parking lot meets the definition of an emergency, as the immediate repair of the asphalt and concrete at 515 South Promenade Avenue is essential to limit the impact on the business.
FINANCIAL IMPACT:
Funding for the recommended action is available in the Waterline Infrastructure Operating and Maintenance Project No. 71930 within the Water Utility Fund 570.
ENVIRONMENTAL ANALYSIS:
This action is categorically exempt pursuant to Section 15302 (c) of the Guidelines for the California Environmental Quality Action (CEQA), which states that “operation, repair, maintenance, permitting, leasing, licensing, or minor alteration of existing public or private structures, facilities, mechanical equipment, or topographical features, involving negligible or no expansion of use beyond that existing at the time of the CEQA determination” and is therefore exempt from CEQA. This action involves repairs to existing infrastructure to maintain public health and safety. Therefore, is exempt from the requirements of CEQA, and no environmental analysis is required.
PREPARED BY: AFTAB HUSSAIN, ASSISTANT UTILITIES DIRECTOR REVIEWED BY: TOM MOODY, UTILITIES DIRECTOR
DATE: 04/02/2025
TO: Honorable Mayor and City Council Members
FROM: Planning and Development Department
2025-118
REQUEST FOR CITY COUNCIL ACTION
SUBJECT:
RESOLUTION ADOPTING THE CITY’S DWELLING UNIT OCCUPANCY FACTOR ACCORDING TO SECTION 16.35.040 OF THE CORONA MUNICIPAL CODE FOR
DETERMINING THE MAXIMUM AREA OF PARKLAND THAT IS REQUIRED TO BE
DEDICATED FOR RESIDENTIAL SUBDIVISIONS
EXECUTIVE SUMMARY:
This staff report asks the City Council to approve the dwelling unit occupancy factor for determining the maximum area of parkland that is required to be dedicated for residential subdivisions. According to the Quimby Act of the Subdivision Map Act, residential subdivisions are required to dedicate land for parks or pay a fee in lieu of dedicating parkland to the city. Corona Municipal Code (CMC) Chapter 16.35 implements the City’s parkland dedication and in lieu fee according to the Quimby Act. Per CMC Section
16.35.040(C), the City shall establish a dwelling unit occupancy factor according to the latest U.S. Census in determining the amount of parkland to be dedicated for each residential subdivision. The latest dwelling unit occupancy factor shall be established by resolution, which is the reason for this request.
RECOMMENDED ACTION:
That the City Council approve Resolution 2025-017 establishing the dwelling unit occupancy factor based upon the 2020 U.S. Census data for determining the amount of parkland to be dedicated pursuant to Chapter 16.35 of the Corona Municipal Code.
BACKGROUND & HISTORY:
CMC Chapter 16.35 implements the Quimby Act for residential subdivisions. To determine the amount of parkland to be dedicated, the City uses the formula described in CMC Section 16.35.040(D), which is the number of housing units in the subdivision by the occupancy factor for each housing type by the number of acres of park area per 1,000 residents. The City requires three acres of park area per 1,000 residents according to CMC Section 16.35.040(B). Therefore, the formula is represented as follows:
(# of dwelling units) x (occupancy factor) x (.003) = park area to be dedicated The occupancy factor is based on the latest U.S. Census. The latest U.S. Census was done in 2020. Since that time, the City has not adopted an occupancy factor based on the latest census data. According to the 2020 U.S. Census, Corona’s average person per household for a housing unit, which consists of a house, apartment and mobile home, is 3.28 persons.
ANALYSIS:
Resolution 2025-017 will establish the dwelling unit occupancy factor of 3.28 persons per household for determining the amount of land that is to be dedicated for parkland. The dwelling unit occupancy factor will be used for residential subdivisions that are physically providing parkland as part of the development. The latest occupancy factor does not affect the fee in lieu of parkland dedication according to the City’s adopted Development Impact Fee schedule, which is $12,708 per residential dwelling unit within a residential subdivision.
FINANCIAL IMPACT:
The adoption of this resolution does not have a financial impact on the city.
ENVIRONMENTAL ANALYSIS:
This action is exempt pursuant to Section 15061(b)(3) of the Guidelines for the California Environmental Quality Act (CEQA), which states that a project is exempt from the CEQA if the activity is covered by the commonsense exemption that CEQA applies only to projects that have the potential for causing a significant effect on the environment. Where it can be seen with certainty that there is no possibility that the activity in question may have a significant effect on the environment, the activity is not subject to CEQA. The approval of this resolution establishing the dwelling unit occupancy factor according to the latest U.S. Census will not have a significant effect on the environment. Therefore, no environmental analysis is required.
PREPARED BY: JOANNE COLETTA, PLANNING AND DEVELOPMENT DIRECTOR ATTACHMENTS:
1. Exhibit 1 – Resolution 2025-017
RESOLUTION NO. 2025-017
RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CORONA, CALIFORNIA, ESTABLISHING THE
DWELLING UNIT OCCUPANCY FACTOR BASED UPON
2020 CENSUS DATA FOR DETERMINING THE AMOUNT
OF PARKLAND TO BE DEDICATED PURSUANT TO
CHAPTER 16.35 OF THE CORONA MUNICIPAL CODE.
WHEREAS, the Quimby Act, set forth in Government Code Section 66477, authorizes a city, by passage of an ordinance, to require a developer to dedicate land in order to provide park or recreational facilities in order to offset park/open space impacts, where the developer seeks the City of Corona’s (“City”) approval for a project involving the subdivision of land; and
WHEREAS, the Quimby Act permits the City, by ordinance, to require the dedication of land up to the maximum amount of three acres per 1,000 residents of the subdivision; and
WHEREAS, Chapter 16.35 of the City Municipal Code (“CMC”) permits the City Council, by resolution, to set the required amount of parkland to be dedicated up to the statutory maximum amount allowed under the Quimby Act; and WHEREAS, CMC Section 16.35.040(D) provides that the maximum amount of park land the City may require for any subdivision is determined by multiplying the number of dwelling units in the subdivision for each housing type by the occupancy factor for each housing type by .003 (i.e., the ratio of the maximum park area standard of three acres per one thousand population); and
WHEREAS, CMC Section 16.35.040(C) provides that the dwelling unit occupancy factor is to be established by resolution of the City Council using the latest available census data; and
WHEREAS, the most recent United States census data, which was released in 2020, determined that the average persons per household for a housing unit (house, apartment, mobilehome) within the City is 3.28 persons; and
WHEREAS, the City Council desires to establish the dwelling unit occupancy factor using data from the 2020 United States Census, which will be used to determine the required amount of parkland to be dedicated pursuant to CMC Chapter 16.35.
NOW, THEREFORE, BE IT RESOLVED BY THE CITY COUNCIL OF
THE CITY OF CORONA, CALIFORNIA, AS FOLLOWS:
-2-
SECTION 1. Incorporation of Recitals. The above Recitals are true and correct and are incorporated herein by reference.
SECTION 2. Dwelling Unit Occupancy Factor. For purposes of determining the maximum amount of park land that the City may require for a subdivision pursuant to CMC Section 16.35.040, the dwelling unit occupancy factor shall be 3.28 persons for a housing unit (house, apartment, mobilehome).
SECTION 3. Effective Date. This Resolution shall be effective immediately upon adoption.
PASSED, APPROVED AND ADOPTED this 2
nd day of April, 2025.
Mayor of the City of Corona, California
ATTEST:
City Clerk of the City of Corona, California
-3-
CERTIFICATION
I, Sylvia Edwards, City Clerk of the City of Corona, California, do hereby certify that the foregoing Resolution was regularly passed and adopted by the City Council of the City of Corona, California, at a regular meeting thereof held on the 2 nd day of April 2025 by the
following vote:
AYES:
NOES:
ABSENT:
ABSTAINED:
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the official seal of the City of Corona, California, this 2
nd day of April 2025.
City Clerk of the City of Corona, California
[SEAL]
DATE: 04/02/2025
TO: Honorable Mayor and City Council Members
FROM: Community Services Department
2025-144
REQUEST FOR CITY COUNCIL ACTION
SUBJECT:
FIRST AMENDMENT TO THE MAINTENANCE/GENERAL SERVICES AGREEMENT WITH NATIONAL CONSRUCTION RENTALS, INC. TO INCREASE THE COMPENSATION BY $75,000 FOR A TOTAL COMPENSATION OF $175,000 FOR FISCAL YEAR ENDING JUNE 30, 2025
EXECUTIVE SUMMARY:
This staff report asks the City Council to approve the First Amendment to the Maintenance/General Service Agreement with National Construction Rentals, Inc., which would increase compensation by $75,000 to $175,000 for the fiscal year ending June 30, 2025.
RECOMMENDED ACTION:
That the City Council:
a. Approve the First Amendment to the Maintenance/General Services Agreement with National Construction Rentals, Inc. to increase the compensation by $75,000 for total compensation of $175,000 for the fiscal year ending June 30, 2025.
b. Authorize the City Manager, or his designee, to execute the First Amendment to the Maintenance/General Services Agreement with National Construction
Rentals, Inc. for total compensation of $175,000 for the fiscal year ending June 30, 2025.
c. Authorize the City Manager, or his designee, to issue a change order to Purchase Order B250278 to National Construction Rentals, Inc. in the amount of $75,000 for a total purchase order amount of $175,000.
BACKGROUND & HISTORY:
The City of Corona utilizes professional contractual services for on-call temporary fencing and portable potty services throughout its city facilities and parks. These contractual services supply the equipment and materials needed to conduct this work safely and effectively. National Construction Rentals, Inc. currently supplies the city with these services for special events, including the Fourth of July, Summer Concerts, and Holiday Lighting, as well as maintenance-related activities such as annual field renovations.
The City operates parks and facilities throughout Corona. The Community Services Department, in conjunction with the Purchasing Division, is preparing the necessary documents to competitively bid for these services for Fiscal Year (FY) 2026 and enter into a multi-year agreement. The need for these services continues to grow with the expansion of special events throughout the year, enhanced field maintenance services, and closing of fields for rest times.
ANALYSIS:
A purchase order for National Construction Rentals, Inc. was initially issued with an Exception to Bid Memo (ETB) in the amount of $45,000 and was later increased by $55,000 for a total of $100,000 for FY 2025. Due to additional services related to securing properties at the South Mall, field renovations, and other city projects, the Community Services Department is requesting to increase the purchase order to $175,000 for FY 2025.
FINANCIAL IMPACT:
Funding for the recommended actions is available in the Community Services Department’s operating budget.
ENVIRONMENTAL ANALYSIS:
This action is exempt pursuant to Section 15061(b)(3) of the Guidelines for the California Environmental Quality Act (CEQA), which states that a project is exempt from CEQA if the activity is covered by the commonsense exemption that CEQA applies only to projects that have the potential for causing a significant effect on the environment. Where it can be seen with certainty that there is no possibility that the activity in question may have a significant effect on the environment, the activity is not subject to CEQA. This action is to approve a Maintenance and General Services Agreement for temporary fencing and portable potty services, and there is no possibility that approving this agreement will have a significant effect on the environment. Therefore, no environmental analysis is required.
PREPARED BY: MOSES CORTEZ, PARKS & TRIALS MANAGER
REVIEWED BY: DONNA FINCH, COMMUNITY SERVICES MANAGER
ATTACHMENTS:
1. Exhibit 1 – Maintenance and General Services Agreement with National Construction Rentals
ORANGE\DDERLETH\55191.2 PTEAM 03102022
CITY OF CORONA
FIRST AMENDMENT TO
MAINTENANCE/GENERAL SERVICES AGREEMENT
WITH NATIONAL CONSTRUCTION RENTALS, INC.
(AS-NEEDED TEMPORARY FENCING AND PORTABLE RESTROOM RENTAL –
SPECIAL EVENT RENTAL SERVICES)
1. PARTIES AND DATE.
This First Amendment to the Maintenance/General Services Agreement (“First Amendment”) is made and entered into this _________________ by and between the City of Corona (“City”) and National Construction Rentals, Inc., (“Contractor”). City and Contractor are sometimes individually referred to as “Party” and collectively as “Parties” in this First Amendment.
2. RECITALS.
2.1 Agreement. City and Contractor entered into that certain Maintenance/General Services Agreement dated June 20, 2024 (“Agreement”), whereby Contractor agreed to provide as-needed temporary fencing and portable restroom rental services.
2.2 Amendment. City and Contractor desire to amend the Agreement for the first time to amend the Total Compensation by $75,000 to $175,000 for fiscal year ending June 30, 2025.
3. TERMS.
3.1 Rates & Total Compensation. Section 3.3.1 (Rates & Total Compensation) of the Agreement, are hereby deleted in their entirety and replaced with the following:
“3.3.1 Rates & Total Compensation. Contractor shall receive compensation, including authorized reimbursement, for all Services rendered under this agreement at the rates set forth in Exhibit “C” attached hereto and incorporated herein by reference. The total compensation, including authorized reimbursements, shall not exceed One Hundred Seventy-Five Thousand Dollars ($175,000) for fiscal year ending June 30, 2025 (“Total Compensation”) without written approval of the City’s Representative. Extra Work may be authorized, as described below, and if authorized, will be compensated at the rates and manner set forth in this Agreement.”
3.2 Continuing Effect of Agreement. Except as amended by this First Amendment, all provisions of the Agreement shall remain unchanged and in full force and effect.
From and after the date of this First Amendment, whenever the term “Agreement” appears in the Agreement, it shall mean the Agreement as amended by this First Amendment.
Docusign Envelope ID: 039B98BF-13D9-4707-82D2-D6F8EC8A8183 Docusign Envelope ID: 91E92DE7-BABC-4EF1-B84A-985892B6E34A
2 (BB&K: 9-10)
ORANGE\DDERLETH\55191.2 PTEAM 03102022
3.3 Adequate Consideration. The Parties hereto irrevocably stipulate and agree that they have each received adequate and independent consideration for the performance of the obligations they have undertaken pursuant to this First Amendment.
3.4 Counterparts. This First Amendment may be executed in duplicate originals, each of which is deemed to be an original, but when taken together shall constitute but one and the same instrument.
[SIGNATURES ON FOLLOWING PAGE]
Docusign Envelope ID: 039B98BF-13D9-4707-82D2-D6F8EC8A8183 Docusign Envelope ID: 91E92DE7-BABC-4EF1-B84A-985892B6E34A
3 (BB&K: 9-10)
ORANGE\DDERLETH\55191.2 PTEAM 03102022
CITY’S SIGNATURE PAGE
FOR
FIRST AMENDMENT TO
MAINTENANCE/GENERAL SERVICES AGREEMENT
WITH NATIONAL CONSTRUCTION RENTALS, INC.
(AS-NEEDED TEMPORARY FENCING AND PORTABLE RESTROOM RENTAL. –
SPECIAL EVENT RENTAL SERVICES)
IN WITNESS WHEREOF, the Parties have entered into this First Amendment to Maintenance/General Services Agreement as of the date noted on the first page of the Amendment.
CITY OF CORONA
By: _________________________
Donna Finch
Community Services Director
Reviewed By: _________________________
Moses Cortez
Parks and Trails Manager
Reviewed By: _________________________
Yasmin Lopez
Purchasing Manager
Attest: _________________________
Sylvia Edwards, City Clerk
City of Corona, CA
Docusign Envelope ID: 039B98BF-13D9-4707-82D2-D6F8EC8A8183 Docusign Envelope ID: 91E92DE7-BABC-4EF1-B84A-985892B6E34A
ORANGE\DDERLETH\55191.2 PTEAM 03102022
CONTRACTOR’S SIGNATURE PAGE
FOR
FIRST AMENDMENT TO
MAINTENANCE/GENERAL SERVICES AGREEMENT
WITH NATIONAL CONSTRUCTION RENTALS, INC.
(AS-NEEDED TEMPORARY FENCING AND PORTABLE RESTROOM RENTAL. –
SPECIAL EVENT RENTAL SERVICES)
IN WITNESS WHEREOF, the Parties have entered into this First Amendment to Maintenance/General Services Agreement as of the date noted on the first page of the Amendment.
NATIONAL CONSTRUCTION RENTALS, INC.
a California corporation
By: _________________________
Javier Gastelum
Divisional Manager
By: _________________________
Scott Simons
Finance Director
Docusign Envelope ID: 039B98BF-13D9-4707-82D2-D6F8EC8A8183 Docusign Envelope ID: 91E92DE7-BABC-4EF1-B84A-985892B6E34A
DATE: 04/02/2025
TO: Honorable Mayor and City Council Members
FROM: City Manager’s Office – Housing and Homeless Solutions Division 2025-119
REQUEST FOR CITY COUNCIL ACTION
SUBJECT
PUBLIC HEARING FOR CITY COUNCIL CONSIDERATION AND APPROVAL OF AMENDMENT NO. 1 TO THE 2024-2025 AND 2022-2023 ACTION PLANS OF THE
DEPARTMENT OF HOUSING AND URBAN DEVELOPMENT (HUD) CONSOLIDATED PLAN
EXECUTIVE SUMMARY:
The staff report asks the City Council to approve a substantial amendment to the 2024- 2025 and 2022-2023 Action Plans of the HUD Consolidated Plan to cancel an activity (Program Year 2024 Victoria Park Community Center Park Improvements Project Phase III) and transfer the funds to an existing project (Program Year 2022 Victoria Park Improvements Phase I—Splash Pad).
RECOMMENDED ACTION:
That the City Council:
a. Conduct a public hearing to receive comments concerning Amendment No. 1 to Program Year 2024-2025 HUD and Program Year 2022-2023 Action Plans of the HUD Consolidated Plan.
b. Approve Amendment No. 1 to the Program Years 2024-2025 and 2022-2023 Action Plans of the HUD Consolidate Plan to cancel an activity (Program Year
2024 Victoria Park Community Center Park Improvements Project Phase III) and to transfer the funds to an existing project (Program Year 2022 Victoria Park Improvements Phase I - Splash Pad) in excess of 50% of the project’s original budget.
c. Authorize the City Manager, or his designee, to prepare and process all necessary budgetary transactions to effectuate the changes in Amendment No. 1 for the Program Years 2024-2025 and 2022-2023 Action Plans.
d. Authorize the City Manager, or his designee, to negotiate, execute, and amend contracts with sub-recipients, developers, or professional service providers as necessary to implement CDBG funds under the approved projects identified in Amendment No. 1 to the Program Years 2024-2025 and 2022-2023. e. Authorize the City Manager, or his designee, to execute, amend, and submit all plans and documents necessary to administer the CDBG projects identified in Amendment No. 1 to the United States Department of Housing and Urban Development.
BACKGROUND & HISTORY:
The U.S. Department of Housing and Urban Development requires all entitlement communities receiving Community Development Block Grant (CDBG) funds, such as the City of Corona, to prepare and submit a HUD Consolidated Plan (Consolidated Plan) every five years to establish a unified, strategic vision for community development, housing and economic development actions. The Consolidated Plan encompasses the analysis of local community needs and coordinates appropriate responses to those needs and priorities. The Corona City Council adopted its Five-Year Consolidated Plan for 2020- 2024 on June 17, 2020.
The Consolidated Plan is carried out through Annual Action Plans (Action Plan), which provide a concise summary of the actions, activities, and specific federal and non-federal resources that will be used each year to address the priority needs and specific goals identified by the Consolidated Plan. The Corona City Council adopted the 2024-2025 Action Plan on June 5, 2024.
The U.S. Department of Housing and Urban Development (HUD) requires all entitlement communities receiving Community Development Block Grant (CDBG) funds, such as the City of Corona, to prepare and submit a substantial amendment to the Action Plans, to provide residents with the opportunity to review proposed substantial changes to previously approved Action Plan(s), and to offer comments on those changes should there be substantial changes to the use of CDBG or HOME funds. Pursuant to the City of Corona Citizen Participation Plan adopted on June 3, 2020, a substantial amendment to an Annual Action Plan is required when a “substantial” change is proposed, which includes:
Addition of a new project not previously identified in the Action Plan, without regard to funding source;
The cancelation of an existing project identified in the Action Plan, without regard to funding source; or
• Changes in the use of CDBG funds from one eligible activity to another eligible activity meeting the following thresholds:
A net increase or decrease greater than 50% of the activity allocation if the allocation is $50,000 or more as listed in a published Action Plan, or as amended;
A net increase or decrease greater than 100% of the activity allocation if the allocation is less than $50,000 as listed in a published Action Plan or amended; or
A net increase or decrease in an activity allocation greater than $300,000.
ANALYSIS:
After collaborating with the City’s Public Works and Community Services Departments, who are overseeing the construction of the Victoria Park Splashpad Park project, and reviewing project activity expenditures, it was determined that additional funding was needed for year one of the park plan projects to be completed. In support of the City’s 3- year park plan, staff have identified unused CDBG capital improvement funds from the program year 2024-2025 set aside for the Victoria Park Community Center Phase III improvements, which could be used to fill a gap for the additional funding needed in Phase I Victoria Park Splashpad.
The transfer of these funds will support the following objectives: 1) the completion of the Victoria Park Splashpad project without any additional allocation of City funds, 2) support timely expenditure of CDBG grant funds as required by HUD, and 3) cancel an activity.
The transfer of funds is more than 50% of the project’s original budget; therefore, the proposed Substantial Amendment also involves amending the 2022-2023 Action Plan.
To provide additional context for the proposed amendment, it is important to note that the City of Corona receives regular formula-based entitlement grants of CDBG funds through the United States Department of Housing and Urban Development (HUD) each year.
On May 4, 2022, the Corona City Council approved the Program Year 2022-2023 Action Plan to specify the eligible CDBG activities and projects to be undertaken to address the community's needs through the use of the CDBG entitlement allocation. Specifically, the 2022-2023 Action Plan identified Phase I of the Park Projects Plan “Community Facilities and Infrastructure” project, with an allocated budget of $703,775.
On June 5, 2024, the Corona City Council approved the Program Year 2024-2025 Action Plan to specify the eligible CDBG activities and projects to be undertaken to address the community's needs through use of the CDBG entitlement allocation. Specifically, the 2024-2025 Action Plan identified Phase III of the Parks Projects Plan “Community Facilities and Infrastructure” project, with an allocated budget of $613,249. Due to
extenuating circumstances related to the Phase III Victoria Park Community Center project, this activity is no longer feasible.
Action Plan Amendment No. 1 to the Program Years 2024-2025 and 2022-2023 Action Plans reallocates funds between approved Community Development Block Grant projects. The City proposes to delete an activity (PY 2024 Park Improvements Project Phase III) and transfer the funds to an existing project (PY 2022 Victoria Park Improvements Phase I - Splash Pad) over 50% of the project’s original budget. This substantial amendment also involves amending the budgets for these two activities as identified in the table below:
Project Name and Program
Year
Current CDBG
Budget
Proposed New
CDBG Budget via
Substantial
Amendment
Net Change
PY 2024 Victoria Park
Community Center
Improvements Project Phase
III
$613,249 $0 (-$613,249)
PY 2022 Victoria Park
Improvements Phase I $703,775 $1,317,024 (+$613,249)
The proposed Amendment No. 1 also addresses a high-priority need and national objective as set out in the City’s 2020-2024 Consolidated Plan and HUD’s National Objectives. Subject to the program regulations set forth by HUD, CDBG funds will be used for the activities outlined below:
Program Year 2022 Victoria Park Improvements Phase I (Splash Pad Project):
CDBG funds support personnel (review of key project documentation and publication elements) and capital improvement costs (proofs of publication, construction costs, materials, and installation by an approved contractor). The installation will also include purchasing an ADA-compliant splash pad with several water features and designated play areas with multiple sprayers at Victoria Park. Funds will also cover the costs of materials and installation for multiple seating areas around the splash pad and accent lighting surrounding the splash pad. The splash pad will be in an open area within the park that is currently an open and unutilized grass area.
CITIZEN PARTICIPATION:
Notice of the availability of the draft Amendment No. 1 to the Program Year 2022-2023 Action Plan and Program Year 2024-2025 Action Plan was disseminated on the City website at www.CoronaCA.gov/CDBG and via other electronic means. Amendment No. 1 to the 2024-2025 Action Plan and 2022-2023 Action Plans were made available for public review online at www.CoronaCA.gov/CDBG from January 6, 2025, to April 2, 2025.
The public was advised of the public hearing and encouraged to submit comments via email to [email protected]
COMMITTEE ACTION:
On May 4, 2022, and June 5, 2024, the Corona City Council approved the Program Year 2022-2023 and 2024-2025 Action Plans to specify the eligible CDBG activities and projects to be undertaken to address the community's needs through the use of the CDBG entitlement allocation.
FINANCIAL IMPACT:
The planned projects identified in Amendment No. 1 will not impact the general fund.
Amendment No. 1 to the 2024-2025 and 2022-2023 Action Plans recommend canceling and reallocating CDBG funds between approved Community Development Block Grant projects.
ENVIRONMENTAL ANALYSIS:
The development of required plans and the allocation of CDBG funds is an administrative activity exempt under 24 CFR Part 58, Section 58.34 of the National Environmental Policy Act of 1969 (“NEPA”), as amended. Additionally, these activities are not considered to be a “project” under the California Environmental Quality Act (“CEQA”). Individual construction activities will be assessed under NEPA and CEQA.
PREPARED BY: KAREN ROPER, HOUSING AND HOMELESS SOLUTIONS
MANAGER
REVIEWED BY: JACOB ELLIS, CITY MANAGER
ATTACHMENTS:
1. Exhibit 1 - Amendment No. 1 to the 2024-2025 and 2022-2023 HUD Consolidated Annual Action Plans
2. Exhibit 2 – Proof of Publication For Amendment No. 1 to the 2024-2025 and 2022- 2023 HUD Consolidated Annual Action Plans
COMMUNITY DEVELOPMENT BLOCK GRANT PROGRAM
SUBSTANTIAL AMENDMENT NO. 1 TO THE
2024-2025 ACTION PLAN;
&
2022-2023 ACTION PLAN
To be considered by:
April 2, 2025
A. EXECUTIVE SUMMARY
The U.S. Department of Housing and Urban Development (HUD) requires all entitlement communities receiving Community Development Block Grant (CDBG) funds, such as the City of Corona, to prepare and submit a Consolidated Plan every five years to establish a unified, strategic vision for community development, housing and economic development actions. The Consolidated Plan encompasses the analysis of local community needs and coordinates appropriate responses to those needs and priorities.
The Corona City Council adopted its Five-Year Consolidated Plan for 2020-2024 on June 17, 2020.
The Consolidated Plan is carried out through Annual Action Plans, which provide a concise summary of the actions, activities, and the specific federal and non-federal resources that will be used each year to address the priority needs and specific goals identified by the Consolidated Plan. The Corona City Council adopted the most recent 2024-2025 Action Plan on June 5, 2024.
The purpose of a Substantial Amendment to the Action Plan is to provide residents with the opportunity to review proposed substantial changes to previously Approved Action Plan(s) and to offer comments on those changes.
Pursuant to the City of Corona Citizen Participation Plan adopted on June 3, 2020, a Substantial Amendment to an Annual Action Plan is required when a “substantial” change is proposed, which includes:
Addition of a new project not previously identified in the Action Plan, without regard to funding source;
The cancelation of an existing project identified in the Action Plan, without regard to funding source; or
Changes in the use of CDBG funds from one eligible activity to another eligible activity meeting the following thresholds:
• A net increase or decrease greater than 50% of the activity allocation if the allocation is $50,000 or more as listed in a published Action Plan, or as amended; • A net increase or decrease greater than 100% of the activity allocation if the allocation is less than $50,000 as listed in a published Action Plan or amended; or • A net increase or decrease in an activity allocation greater than $300,000.
The Substantial Amendment No. 1 to the 2024-2025 Action Plan is necessary because the City is proposing to cancel an activity (Program Year 2024 Park Improvements Project Phase III) and transfer the funds to an already existing project (Program Year 2022 Victoria Park Improvements Phase I - Splash Pad) in excess of 50% of the project’s original budget (funding budgets and reprogramming described in Section C of this amendment). This Substantial Amendment also involves amending the 2022-2023 Action Plan.
B. CITIZEN PARTICIPATION
A Notice of Public Hearing and the commencement of the 30-day public review period was published in the Weekly Sentinel on January 3, 2025, informing the public of the proposed Substantial Amendment and inviting comments at the public hearing. A secondary Notice to reschedule the Public Hearing and
the culmination of the public review period was published in the Weekly Sentinel on March 21, 2025.
The public review period began on January 6, 2025 and ran through April 2, 2025. Citizens were able to review copies of the Substantial Amendment at the Corona Public Library, City Hall (City Clerk’s Office and the Community Services Department) and on the City’s website at Community Development Block Grant | City of Corona. On April 2, 2025, the Corona City Council will hear public comments regarding the Substantial Amendment.
C. CHANGES TO THE 2022-2023 & 2024-2025 ANNUAL ACTION PLAN ACTIVITIES This Substantial Amendment proposed to the following changes:
Project Name and Program Year Current CBDG
Budget
Proposed New CDBG
Budget via Substantial
Amendment
PY 2024 Park Improvements Project Phase III $613,249 $0 PY 2022 Victoria Park Improvements Phase I $703,775 $1,317,024
Sentinel Weekly News
1101 California Ave., Ste. 100
Corona, CA 92881
(951)-737-9784
Sylvia Edwards
City of Corona, City Clerk
400 S Vicentia Ave
Corona, CA 92882
Proof of Publication 2015.5 C.C.P.
State of CA, County of Riverside
I am a citizen of the United States and a resident of the County aforesaid; I am over the age of eighteen years and not a party to or interested in the above-entitled matter. I am the agent of the printer of the Sentinel Weekly News, a newspaper of general circulation, printed and published weekly in the City of Corona, Corona Public Notice District District, County of Riverside, and which newspaper has been adjudged a newspaper of general circulation by the Superior Court of the County of Riverside State of California on April 14, 2000, that the notice of which the annexed is a printed copy (set in type not smaller than nonpareil), has been published in each regular and entire issue of said newspaper and not in any supplement thereof on the following dates, to-wit:
03/21/25
certify (or declare) under the penalty of perjury that the following is true and correct. Dated at Corona, CA on
Signature
Ad Id: 32198
Your Control #: CIP Substantial Amend English -- Sylvia Edwards Sch Id: 95318
03/21/2025
Cust Id: 1761
03/21/2025 10:24:21 AM
Sentinel Weekly News
1101 California Ave., Ste. 100
Corona, CA 92881
(951)-737-9784
Sylvia Edwards
City of Corona, City Clerk
400 S Vicentia Ave
Corona, CA 92882
Proof of Publication 2015.5 C.C.P.
State of CA, County of Riverside
I am a citizen of the United States and a resident of the County aforesaid; I am over the age of eighteen years and not a party to or interested in the above-entitled matter. I am the agent of the printer of the Sentinel Weekly News, a newspaper of general circulation, printed and published weekly in the City of Corona, Corona Public Notice District District, County of Riverside, and which newspaper has been adjudged a newspaper of general circulation by the Superior Court of the County of Riverside State of California on April 14, 2000, that the notice of which the annexed is a printed copy (set in type not smaller than nonpareil), has been published in each regular and entire issue of said newspaper and not in any supplement thereof on the following dates, to-wit:
03/21/25
certify (or declare) under the penalty of perjury that the following is true and correct. Dated at Corona, CA on
Signature
Ad Id: 32199
Your Control #: CIP Substantial Amend (Spanish) -- Sylvia Edwards, CC Sch Id: 95319
03/21/2025
Cust Id: 1761
03/21/2025 10:24:21 AM
DATE: 04/02/2025
TO: Honorable Mayor and City Council Members
FROM: Planning and Development Department
2025-120
REQUEST FOR CITY COUNCIL ACTION
SUBJECT:
REQUEST BY COUNCIL MEMBER SPEAKE ASKING THE CITY COUNCIL TO CONSIDER AN UPDATE TO THE CITY’S HERITAGE INVENTORY TO INCLUDE
CERTAIN COMMERCIAL STRUCTURES
EXECUTIVE SUMMARY:
This staff report asks the City Council to provide direction to city staff on updating the City’s Heritage Inventory to include certain commercial structures not currently listed.
Structures placed on the Heritage Inventory are considered properties that should be preserved because of the era it was constructed and its association with a historic event.
Properties listed on the Heritage Inventory are eligible to be nominated as a local historic landmark on the City’s Register of Historic Resources.
RECOMMENDED ACTION:
That the City Council provide direction to City staff based on one of the options presented in the staff report.
BACKGROUND & HISTORY:
The Planning Commission adopted Resolution 2040 on April 21, 2003, establishing the City’s Heritage Inventory. The Heritage Inventory lists 544 properties. The properties on the Heritage Inventory are identified by age, architecture, and type (residential or commercial). Each property is also ranked as high, medium, and low for potentially being listed on the Corona Register as a local landmark.
The initial survey of historic properties was done in 1983 by City librarian Gloria Freel which contained approximately 400 properties. In 1986, the City hired a consultant to continue the survey of historic buildings. The consultant added 286 properties to the survey done by Ms. Freel, bringing the total to approximately 700 properties.
In 2002, the properties on the survey were reevaluated by City staff, a community volunteer, and seven consecutive interns over a period of 19 months. In the end, the City recommended that 459 properties be listed on the Corona Heritage Inventory and notified the affected property owners of the city’s recommendation. Eventually, 452 properties were added to the inventory adopted by the Planning Commission on April 21, 2003.
Over time additional properties have been added to the Heritage Inventory, totaling 544 properties.
Properties listed on the Heritage Inventory are:
Eligible to be listed on the Corona Register as a local landmark. Subject to a demolition delay of 30 days.
Demolition requests are decided by the Historic Preservation Board. Demolition requests are based on meeting one of the findings listed in Corona Municipal Code Section 17.63.120(E)(4).
Section 17.63.100 of the CMC outlines the process to list or expand the listing of the Heritage Inventory. An application “may be initiated by the City Council, the Planning Commission, City officials, local entities or a member of the public” at any time (CMC
17.63.100 (A)). The application for each property must include “an official survey describing the features, merits and quality of the site, improvement or natural feature” and a justification of how it meets the criteria listed in CMC 17.63.090.
The following summarizes the process involved in expanding the listing of the Heritage Inventory.
1. Property is identified and surveyed according to CMC Section 17.63.090.
2. Copies of the property survey are distributed for review and comment to the Heritage Librarian, the Corona Historic Preservation Society, and any other agency affected by the expanded listing according to CMC Section 17.63.100(F)(1).
3. Any property owner directly affected by the listing is notified according to CMC Section 17.63.100(F)(2).
4. The public comment and review period shall be no less than 30 days according to CMC Section 17.63.100(F)(4).
5. The public hearing notice on the expanded listing of the Heritage Inventory before the Historic Preservation Board shall be no less than 10 days according to CMC Section 17.63.100(G).
6. The Historic Preservation Board adopts a resolution expanding the listing of the Heritage Inventory according to CMC Section 17.63.100(I).
ANALYSIS:
Expanding the listing of the Corona Heritage Inventory would require each added property to be surveyed according to Section 17.63.090 of the CMC. For a site, historic artifact, improvement, or natural feature to be listed on the Heritage Inventory, it must demonstrate that it should be preserved because of its age, and either its context in the neighborhood, its association with a historic event or period, or its significance to the architectural, engineering, scientific, economic, agricultural, educational, cultural, social, artistic, political or military history of Corona.
In current practice, properties that are eligible for listing as a local landmark need to have been in existence prior to 1950. The City would use the same criteria for properties to be listed on the Heritage Inventory since the properties on the inventory are eligible for listing as a local landmark on the Corona Register.
Expanding the Heritage Inventory is not limited to initiation by City staff. Any member of the public can request that certain property be added to the Heritage Inventory by following the process described in CMC Section 17.63.100.
Options for the City Council to Consider
The following are options for the City Council to consider regarding expanding the Heritage Inventory.
1. Current practice - Proceed with current practice, expanding the Heritage Inventory as interested parties submit applications as described in CMC Section 17.63.100.
Staff time would be limited to processing applications as they are submitted.
2. Public awareness - Conduct a public awareness campaign notifying property owners about the Heritage Inventory and the process of listing a property. Staff would create informational and social media posts to educate residents about the Heritage inventory that could also be shared by CHPS or other interested parties.
Applications would be processed per the current practice.
3. Proactive update - Direct staff to proactively update the Heritage Inventory according to a specific scope of work identified by the City Council (e.g. certain types of properties of a certain age within an identified geographical area). If the council were to direct staff to conduct a survey of potentially eligible properties and screen them for eligibility, it would take considerable effort. It is unknown at this time how many properties would be evaluated and considered for inclusion in the Heritage Inventory. Like the initial surveys, staff would also rely on help from volunteers experienced in historic preservation to identify which properties should be added to the Heritage Inventory and retain a qualified consultant in helping to identify additional properties based on the characteristics listed in CMC Section
17.63.090. Applications for each property would need to be individually prepared but a bulk submission for review may reduce the overall staff time required for processing.
FINANCIAL IMPACT:
Option Amount of Time Potential Cost
1. CURRENT PRACTICE - There is no
application fee to list a property on the
Heritage Inventory. However, there is an
application fee to remove a property from the
Heritage Inventory. The same amount of time
used in removing a property from the
Heritage Inventory would be similar to adding
a property.
4 months approx.
Review of each
property, public
comment period
and noticing
requirement.
$3,896 per
property (approx.
staff time cost)
2. PUBLIC AWARENESS – Staff create a
short informational campaign about listing
properties on the Heritage Inventory that can
be shared on social media, informational
fliers, and through CHPS.
2-3 months Less than $2,000
of staff time for
campaign and
approximately
$3,896 per
property (as
above).
3. PROACTIVE UPDATE - Depending on the
scope of work identified by the City Council,
the number of properties is unknown. If a list
of identified properties is not provided to staff
by a qualified organization that specializes in
historic resources, a consultant would be
hired to assist with evaluating and vetting
properties, conducting the surveys, and
application preparation.
Up to 12 months
for identification
and evaluation of
properties prior to
the 4 months for
review and
approval.
$75,000 to
$100,000 for a
consultant to
identify and
evaluate
properties, and
$10,000 for staff
time to process
the properties and
prepare for public
hearing.
ENVIRONMENTAL ANALYSIS:
This action is exempt pursuant to Section 15061(b)(3) of the Guidelines for the California Environmental Quality Act (CEQA), which states that a project is exempt from CEQA if the activity is covered by the commonsense exemption that CEQA applies only to projects that have the potential for causing a significant effect on the environment. Where it can be seen with certainty that there is no possibility that the activity in question may have a significant effect on the environment, the activity is not subject to CEQA. There is no possibility that this activity will have a significant effect on the environment. Therefore, no environmental analysis is required.
PREPARED BY: JOANNE COLETTA, PLANNING AND DEVELOPMENT DIRECTOR ATTACHMENTS:
1. Exhibit 1 – Request from Council Member Speake dated April 2, 2024
Future Agenda Item Request Form
Future agenda items should be limited to new issues that emerge during the course of the year that are urgent and cannot wait until the next priority setting session of Council before requiring action.
Name: Wes Speake
Date: 4/2/2024
Title Name/Topic: Pursue an Update to the Historic Resources Inventory Background
1. What is the purpose for the request i.e. what you are trying to achieve or do? The Historic inventory was last done in 1982, over 42 years ago. Meaning that iconic buildings like the Silver Dollar Pancake house could be demo ’ed without comment by anyone because it was last altered in 1949. Outside of the 50-year range in 1982. Many others have been excluded that should be on the resources list like Rudy Ramos studio on E Grand Blvd or the Arcade Building on Main Street.
2. What is the scope of the work you wish to see done?
Explore the option to update the Historic resources inventory, including a mechanism for regular updates to the resources list outside of placing a Historic marker as described in
17.63 3. Does this request align with the City’s Strategic Plan? How? #5 Sense of Place- Connecting with our past
4. What is the desired timeline to have the issue considered by Council? Within reason
5. Is the issue urgent requiring action before the next priority setting session of Council (Spring Workshop)?
Yes
Staff Section (To be completed by staff)
Approximate Staff Time Required: ____ Hours
Approximate Cost: $ ____
Joanne Coletta
Planning and Development Director
April 2, 2025
Request by Council Member Speake
The Ask…
City Council provide direction to city
staff on updating the City’s Heritage
Inventory based on one of the
proposed options.
Request by Council Member Speake
Background
Approx. 400 historic
properties surveyed
by City Librarian
Gloria Freel.
Historic properties
survey expanded by
286 properties using
a consultant.
Historic survey
reevaluated by city
staff, 1 community
volunteer, and 7
consecutive interns
in a 19-month period
Resolution adopted
by the Planning
Commission
establishing the
Corona Heritage
Inventory consisting
of 452 properties.
1983 1986 2002 2003
Properties added to
the Heritage
Inventory over time,
which currently
consists of 544
properties.
2025
Background
An application “may be initiated by the City Council, the Planning Commission, city officials, local entities or a member of the public” at any time. The application for each property must include “an official survey describing the features, merits and quality of the site, improvement or natural feature” and a justification of how it meets the criteria listed in CMC 17.63.090.
Corona Municipal Code states…
➢ Eligible to be listed on the Corona Register as
a local landmark.
➢ Subject to a demolition delay of 30 days.
➢ Demolition requests are decided by the
Historic Preservation Board.
➢ Demolition requests are based on meeting one
of the findings listed in CMC Chapter 17.63.
Corona Heritage Inventory
Property Surveyed
City Librarian, CHPS and any other agency affected by the request.
Survey Distributed for review
Public Comment and Review Period (30 days)
Notice to property owner directly affected
Public Hearing by Historic Preservation Board
HPB adopts resolution
10 days public hearing notice
Property in existence before 1950 and meet the findings in CMC Chapter 17.63.
Corona Heritage Inventory Update
OPTION DESCRIPTION ESTIMATED
TIME
POTENTIAL
COST
1 CURRENT PRACTICE - Proceed with current practice, expanding the Heritage Inventory as interested parties to submit applications as described in CMC Section 17.63.100. Staff time would be limited to processing applications as they are submitted.
There is no application fee to list a property on the Heritage Inventory. 4 months
(staff review &
public comment
period and
noticing
requirement)
Approximately $3,896
per property
2 PUBLIC AWARENESS - Conduct a public awareness campaign notifying property owners about the Heritage Inventory and the process to list a property. Staff would create informational and social media posts to educate residents about the Heritage inventory that could also be shared by CHPS or other interested parties. Applications would be processed per the current practice.
2 to 3 months Approximately $2,000
3 PROACTIVE UPDATE - Depending on the scope of work identified by the City Council, the number of properties is unknown. If a list of identified properties is not provided to staff by a qualified organization that specializes in historic resources, a consultant would be hired to assist with evaluating and vetting properties, conducting the surveys, and application Up to 12
months
$75,000 to $100,000
(consultant) + $10,000
(staff) (consultant to
identify and evaluate
properties in addition to
the staff time to process
each property for public
hearing.)
Corona Heritage Inventory Update
OPTION DESCRIPTION ESTIMATED
TIME
POTENTIAL
COST
1 CURRENT PRACTICE - Proceed with current practice, expanding the Heritage Inventory as interested parties to submit applications as described in CMC Section 17.63.100. Staff time would be limited to processing applications as they are submitted.
There is no application fee to list a property on the Heritage Inventory. 4 months
(staff review &
public comment
period and
noticing
requirement)
Approximately $3,896
per property
2 PUBLIC AWARENESS - Conduct a public awareness campaign notifying property owners about the Heritage Inventory and the process to list a property. Staff would create informational and social media posts to educate residents about the Heritage inventory that could also be shared by CHPS or other interested parties. Applications would be processed per the current practice.
2 to 3 months Approximately $2,000
3 PROACTIVE UPDATE - Depending on the scope of work identified by the City Council, the number of properties is unknown. If a list of identified properties is not provided to staff by a qualified organization that specializes in historic resources, a consultant would be hired to assist with evaluating and vetting properties, conducting the surveys, and application Up to 12
months
$75,000 to $100,000
(consultant) + $10,000
(staff) (consultant to
identify and evaluate
properties in addition to
the staff time to process
each property for public
hearing.)
The Ask…
City Council provide direction to city
staff on updating the City’s Heritage
Inventory based on one of the
proposed options.
Request by Council Member Speake
DATE: 04/02/2025
TO: Honorable Mayor and City Council Members
FROM: Public Works Department
2025-136
REQUEST FOR CITY COUNCIL ACTION
SUBJECT:
REQUEST FROM COUNCIL MEMBER SPEAKE FOR PROPOSED IMPROVEMENTS
TO THE MAGNOLIA AVENUE AND EL SOBRANTE ROAD INTERSECTION EXECUTIVE SUMMARY:
This report asks the City Council to provide staff directions to explore treatments to reconfigure the intersection of Magnolia at El Sobrante, quantifying the impacts and benefits of the proposed reconfigurations.
RECOMMENDED ACTION:
That the City Council:
a. Approve staff’s recommendation to implement the short-term plan of crosswalk removal at El Sobrante Road in the interest of removing disruptions to the corridors signal coordination.
b. Provide feedback and direction on the proposed long-term treatments, perform detailed traffic studies to quantify the impacts of these proposed treatments, and prepare a future presentation to discuss conceptual alternatives and study results for the proposed long-term reconfigurations of the intersection of Magnolia at El Sobrante.
BACKGROUND & HISTORY:
Council Member Speake submitted a Future Agenda Item Request Form, requesting available options to improve traffic operations along the Magnolia Avenue corridor, specifically at the intersection of Magnolia Avenue and El Sobrante Road. The Magnolia Avenue Corridor’s operations are complicated by the sheer volume of traffic on Magnolia, Caltrans jurisdiction control of I-15 ramp signals, and the proximity of adjacent intersections to each other. This corridor has been a delicate balance of traffic flow between the I-15 freeway and Magnolia Avenue, a major arterial, since its inception.
The Traffic Engineering Division is responsible for operating and maintaining the traffic flows through the City of Corona. Staff is currently conducting a traffic signal synchronization project at this location, and several proposed improvement suggestions arose out of this engineering effort. As a result, staff proposes both short-term and longterm options, including near-term removal of the delay-inducing crosswalk across Magnolia at El Sobrante Road, reconfiguring the intersection to limit access (right in/right out) with the removal of the traffic signal, and a full reconfiguration of El Sobrante Road terminating short of Magnolia Avenue with the removal of the traffic signal.
ANALYSIS:
Currently, a project to retime or synchronize the traffic signals along the Magnolia Avenue Corridor from Rimpau Avenue to Sixth Street is underway. This effort has shown the constraints that are inhibiting optimal traffic flow on Magnolia Avenue. The corridor comprises of traffic signals owned and operated by the City of Corona, with two Interstate 15 ramp signals in the center of the corridor operated by the State of California Transportation Department (Caltrans). These entities have competing objectives for the use of signal timing on this corridor; Caltrans endeavors to serve the ramps so as not to queue back onto the freeway mainline, and the City of Corona strives to move traffic as efficiently as possible on Magnolia Avenue. These competing objectives are further hampered by the close proximity of El Sobrante Road with the Interstate 15 Southbound Offramp.
Short-Term Improvements
While analyzing the corridor for signal timing change, it was noted that the crosswalk crossing Magnolia Avenue at El Sobrante Road required a substantially high pedestrian timing interval far exceeding the timing required for vehicles to cross. This results in significant delays and causes this intersection to ‘transition’ out of synchronization with its adjacent traffic signals. Each pedestrian activation could cause several minutes out of synch, sending delays up and down the corridor. Removing this crosswalk would enable optimized signal timing and reduce the risk of transition delays. An available crosswalk is located at Rimpau Avenue, just three hundred sixty feet west of El Sobrante.
Potential Long-term Improvements – Option A
A long-term option to optimize the corridor would be to reconfigure the intersection of El Sobrante Road and Magnolia Avenue to a limited access configuration. This would convert the intersection into a permissive “right in/right out” access for both El Sobrante Road and the shopping center driveway and include removing the traffic signal at this
location. With the movements restricted to right in/right out, this enables the former intersection space to be utilized for additional vehicle storage for Rimpau and Freeway turn movements.
Long-term Improvements – Option B
The other option is to permanently remove access from El Sobrante Road to Magnolia Avenue. This would require the “knuckling” of El Sobrante Road, where it meets the driveway of the small shopping center North of Magnolia and West of El Sobrante. This option further benefits reduced conflict points by restricting access, while giving the same benefits of the traffic signal removal. Both restricted access options would require the rerouting or detouring of traffic to other adjacent roadways like the already congested Rimpau Avenue or further to the El Camino Avenue corridor.
Potential Benefits:
Less traffic signal delay
Additional vehicle throughput on Magnolia Avenue
Increased turn movement storage
Less roadway conflict points, resulting in a safer roadway Blank canvas for beautification
Potential Challenges:
Pedestrian delays
Emergency access
Diverted traffic
Reduced access to businesses and shopping center
Staff recommends proceeding with the short-term improvements and is seeking direction from the City Council on studying the long-term options. Studying the long-term options could cost approximately $30,000 and may require additional funding approval from the City Council.
FINANCIAL IMPACT:
The financial impact of the short-term recommendation for crosswalk removal at El Sobrante Road has been determined to be less than $9,500. This would include the use of staff time for the required traffic signal modifications, staff time to prepare public notices and conduct a public meeting to satisfy the requirements of the California Vehicle Code, and the City’s striping contractor to modify the intersection striping. This effort would be covered under the Traffic Engineering Division’s existing budget for signal and striping work.
The financial impact of a long-term potential plan with associated projects reconfigurations has yet to be determined. Researching and preparing studies and conceptual options for the council to consider will require approximately 30 hours of staff time and $30,000 of consultant costs. The Traffic Engineering division can utilize existing on-call contracts with firms qualified to complete this scope of work, but this effort is not budgeted.
ENVIRONMENTAL ANALYSIS:
This action is exempt pursuant to Section 15061(b)(3) of the Guidelines for the California Environmental Quality Act (CEQA), which states that a project is exempt from CEQA if the activity is covered by the general rule that CEQA applies only to projects that have the potential for causing a significant effect on the environment. Where it can be seen with certainty that there is no possibility that the activity in question may have a significant effect on the environment, the activity is not subject to CEQA. This action provides direction to the Public Works Traffic Engineering staff to explore treatments to reconfigure the intersection of Magnolia at El Sobrante, quantifying the impacts and benefits of the proposed reconfigurations. Since there is no possibility that this action will have a significant effect on the environment, no environmental analysis is required. Individual projects will be reviewed for environmental compliance accordingly in the future.
PREPARED BY: AARON COX, SENIOR ENGINEER – TRAFFIC
REVIEWED BY: SAVAT KHAMPHOU, PUBLIC WORKS DIRECTOR
ATTACHMENTS:
1. Exhibit 1 – Presentation
2. Exhibit 2 – Future Agenda Request Form (Speake)
Rosalva Ureno, PE, TE
Transportation Manager/City Traffic Engineer
Aaron M. Cox, PE, TE, PMP
Senior Traffic Engineer
April 2, 2025 Page 376 of 492
The Ask:
That the City Council provide direction to implement
and investigate treatments that can improve the traffic operations along Magnolia Avenue at El Sobrante Road.
Magnolia Ave
INTERSTATE 15
Corridor Operations
• Multiple Agencies – Caltrans operates the ramp signals while City of Corona operates the adjacent intersections
• Competing Objectives – Caltrans prioritizes freeway flow, while the City wants to keep Magnolia moving
• Geometry – Proximity of El Sobrante to the I-15 SB Ramp is ~75 feet
• Control – City has no visibility into how the Caltrans ramp signals are operating. Caltrans has proprietary software that does not interface with our Advanced Traffic Management System. We rely on their clocks being synchronized to GPS time
• Volumes – 2
nd busiest corridor in the City along with the heavy
demand of I-15 freeway traffic
Typical Weekday PM Conditions
El Sobrante Rd at Magnolia Ave
This option maintains full access to and from El Sobrante Avenue, while removing the westerly Magnolia Ave crosswalk.
Removal of this crosswalk facilitates better signal timing coordination for the Magnolia Corridor.
This option would remove the signalized intersection at El Sobrante Rd and Magnolia Ave. and would allow right turn movements in/out of the shopping center as well as El Sobrante Rd. By eliminating the left turns and through movements at this location, additional vehicle storage and more efficient signal timing could be realized.
This option would completely close the El Sobrante Road before intersecting Magnolia Avenue, convert the shopping center to limited access. This option would eliminate the signal at El Sobrante leading to additional vehicle storage, more efficient signal timing, and less conflicting movements.
Short Term
This option is a near term improvement that
would result in operational improvements for
the Magnolia Corridor.
• Delay Improvements - Vehicle timing
substantially shorter than the pedestrian
crosswalk timing required
• Each pedestrian actuation delays up to
30 seconds, and can put the intersection
in transition for up to 6 minutes
• Pedestrian delay to use Rimpau Ave
crosswalk
9 Pedestrians vs 3600 Vehicles
during highest Peak Hour at the
El Sobrante / Magnolia Intersection
Long Term – Option A
• Signal Coordination improvements with
signal at El Sobrante removed
• Additional vehicle storage for more
efficient movements
• Less delays, more corridor throughput
• Reduced Access to El Sobrante and
shopping center
• Detoured Traffic – Route traffic to
Rimpau or El Camino
This option would remove the signalized intersection
at El Sobrante Rd and Magnolia Ave and restrict left
turn movements in and out of the shopping center as
well as El Sobrante Rd. Page 381 of 492
Long Term – Option B
This option would remove the signalized intersection
at El Sobrante Rd and Magnolia Ave and allow right
turn movements in and out of the shopping center
with access to El Sobrante Rd closed off.
• Signal coordination improved with signal
removed
• Less conflict points (Safer)
• Additional vehicle queuing storage for more
efficient movements
• Even less delays, more corridor throughput
• Opportunity to beautify “dead space”
• Reduced access to El Sobrante and Shopping
Centers
• Detoured Traffic – Use Rimpau or El Camino
• Introduce cut-through route through business
• Emergency access concerns Page 382 of 492
01 02
03 Short Term
Option
Long Term
Option A
Long Term
Option B
Concurrence on removal of westerly crosswalk at El Sobrante and Magnolia to improve signal coordination for the Magnolia Avenue Corridor
Direction to study the conversion of El Sobrante and Shopping Center entrances to a limited access configuration including the removal of the traffic signal at El Sobrante at Magnolia Direction to study the conversion of Shopping Center entrance to a limited access configuration, removal of the traffic signal at El Sobrante at Magnolia and removal of access to El Sobrante Road from Magnolia Avenue
The Ask:
That the City Council provide direction to implement
and investigate treatments that can improve the traffic operations along Magnolia Avenue at El Sobrante Road.
Magnolia Ave
INTERSTATE 15
Future Agenda Item Request Form
Future agenda items should be limited to new issues that emerge during the course of the year that are urgent and cannot wait until the next priority setting session of Council before requiring action.
Name: Wes Speake
Date: 12/13/2024
Title Name/Topic: Realignment of the intersection of Magnolia/ El Sobrante Background
1. What is the purpose for the request i.e. what you are trying to achieve or do? Magnolia/ El Sobrante intersection is one of the worst in the city because of its closeness to the SB15 Magnolia off-ramp. I would like to right turn in and out on El Sobrante to eliminate the through traffic. Additionally, look at eliminating the left turn into the Shopping center from Magnolia as well, making it right turn and out only.
2. What is the scope of the work you wish to see done?
Have traffic engineering bring back options to see the impacts and benefits of making this change.
3. Does this request align with the City’s Strategic Plan? How? #3 Sound Infrastructure- This intersection has been a thorn for 40 years
4. What is the desired timeline to have the issue considered by Council? Soon
5. Is the issue urgent requiring action before the next priority setting session of Council (Fall Workshop)?
No
Staff Section (To be completed by staff)
Approximate Staff Time Required: ____ Hours
Approximate Cost: $ ____
DATE: 04/02/2025
TO: Honorable Mayor and City Council Members
FROM: Economic Development Department
2025-138
REQUEST FOR CITY COUNCIL ACTION
SUBJECT:
ECONOMIC DEVELOPMENT STRATEGIC PLAN UPDATE
EXECUTIVE SUMMARY:
This staff report asks the City Council to receive an update and provide feedback on the implementation of the City’s Economic Development Strategic Plan.
RECOMMENDED ACTION:
That the City Council receive an update and provide feedback on the implementation of the Economic Development Strategic Plan.
BACKGROUND & HISTORY:
From April 2021 to August 2022, the City of Corona underwent a planning process to develop a five-year Economic Development Strategic Plan (Plan) to guide the City's economic development efforts. Following extensive community outreach and a thorough market analysis, the Plan was presented to the Council for adoption in August 2022. The Plan is framed around six strategic goals:
1. Elevate Entrepreneurs and Small Businesses
2. Facilitate Business Expansion and Retention
3. Prepare and Support Our Residents for Jobs of the Future
4. Facilitate Planning and Development
5. Encourage Placemaking and Community
6. Enhance Communication and Connection
ANALYSIS:
Stemming from the strategic goals are a series of strategic actions, key performance indicators, and milestone measurements to ensure the best success at achieving the overarching goals. There are 44 strategic actions, 27 key performance indicators, and 21 milestone measurements.
Staff will provide an update on the progress on these measures and overall economic development efforts.
FINANCIAL IMPACT:
There is no financial impact associated with this action.
ENVIRONMENTAL ANALYSIS:
This action is exempt pursuant to Section 15061(b)(3) of the Guidelines for the California Environmental Quality Act (CEQA), which states that a project is exempt from CEQA if the activity is covered by the common sense exemption that CEQA applies only to projects that have the potential for causing a significant effect on the environment. Where is can be seen with certainty that there is no possibility that the activity in question may have a significant effect on the environment, the activity is not subject to CEQA. This action is to receive and file the staff’s presentation. Therefore, no environmental analysis is required.
PREPARED BY: JOEL BELDING, ECONOMIC DEVELOPMENT DIRECTOR REVIEWED BY: JUSTIN TUCKER, ASSISTANT CITY MANAGER
ATTACHMENTS:
1. Exhibit 1 – Economic Development Update Presentation Update
April 2, 2025
Joel Belding & Ashley Zaragoza
Economic Development Director &
Economic Development Manager
ECONOMIC DEVELOPMENT UPDATE
Director Manager Analyst Assistant
OFFICE OF ECONOMIC DEVELOPMENT
Administrator Administrator
Economic Development Strategic Plan
Strategic Goals
Strategic Actions
Key Performance Indicators
Milestone Measurements
6 44
27 21
93%
Of Strategic Actions are
in progress, complete,
or ongoing.
In partnership with our local and regional partners,
elevate and support entrepreneurs and small
businesses in Corona.
Elevate Entrepreneurs & Small Businesses
Facilitate the retention and expansion of existing
businesses and the attraction of new businesses in
Corona.
Facilitate Business Expansion & Retention
Provide our community with the skills resources,
and support they need to prepare for the jobs of
the future in Southern California.
Prepare & Support Our Residents for
Jobs of the Future
Facilitate a collaborative, responsive, efficient, and
business-friendly development review process to
ensure best in class service to our development
community.
Facilitate Planning & Development
Encourage the development of lively public spaces
by celebrating our heritage to promote the local
economy and our community’s health, happiness,
and well being.
Encourage Placemaking & Community
Enhance communication and connection with
community by celebrating our successes and
ensuring all residents have equitable access to
City resources.
Enhance Communication & Connection
Economic Development Strategic Plan
Strategic Goal 1
A new cohort with Asociación de
Emprendedor@s will begin in July
2025!
Partnering with SCORE to launch
an entrepreneurship program, set
to begin in April 2025!
Completed ARPA-funded small
business grant program
Awarded 60 entrepreneurship
grants of $5,000 each
30 small business grants of
$10,000 each.
Promoted 24
businesses since last
Spring
Expanding outreach of
Strategic Goal 2 Assisted 25 companies
with identifying sites for
relocation or expansion.
Enhancing marketing efforts and
tenant outreach to unique retailers
through tradeshows like ICSC.
Successfully connected with
shopping centers and supported
their business promotion and tenant
vacancy needs.
150 Businesses Assisted
Deploying targeted recruitment
strategies and actively engaging
with shopping centers and major
commercial centers.
Strategic Goal 3 Promoted marketing
campaign
24 Current Pledges
Annual New Business Reception
on June 2nd to connect
businesses in Corona with
resources for success.
Advanced development of
the future Innovation
Center & awarded $2.5M
Strategic Goal 4 Launching Family-owned
business workshops in
collaboration with Riverside
County.
Hosted a healthcare workshop
with the Corona Chamber of
Commerce with 37 attendees.
Connected with key healthcare
brokers in the region.
Held 20+ Team Corona
meetings to support business
expansion and relocation
Strategic Goal 5 5 awards for Downtown
Commercial Beautification
Grants up to $20,000
each.
17 Downtown acquisitions
since last Spring
Advanced Downtown
Signage Efforts
Parking Lot Renovation and
New Tenants: Spring 2025
South Mall Branding: Unique
identity for a unique experience
Strategic Goal 6 Enhancing branding and
signage for downtown to
elevate Corona’s core.
12 businesses promoted
via video with 105K views
Recalibrating the Shop Dine
Corona campaign with
continued marketing and
promotion.
Grew target audience through
dedicated outreach and
increased newsletter subscribers
and social media network.
2024: 87,239 jobs
State Unemployment: 5.5%
Riverside County Unemployment: 5.3%
Corona: 4.4%
Employment
$97,709,068 sales tax in 2024
$101,000,000 sale tax revenue in 2023
-3.38%
Sales Tax Generation
3,984 permits issued in 2024
4,727 permits issued in 2023
-15.7$%
Development Permit Activity
9.1% Warehouse, +3.6% increase
14.2% Office, -0.5% decrease
8.2% Retail, -0.2% decrease
Vacancies
266 New Housing Units in 2024
100 New Housing Units in 2023
Housing Development
City of Corona
RETAIL RECRUITMENT HIGHLIGHTS
The Retail Coach has connected with and
submitted market data to over 100 retailers,
restaurants, entertainment concepts, brokers and
developers.
Match List Process
1. TRC created targeted retailer list based on market demographics, psychographics, current retail trends, and industry expertise.
2. Real Estate Inventory
3. Collaboration and feedback from City Staff
4. City-wide survey responses (3,000+) of desired brands & concepts Focused list for Downtown and for the City of Corona as a whole Special emphasis on unique concepts vs. national chains
RETAIL RECRUITMENT HIGHLIGHTS
Retailers, Restaurants, and Entertainment
Concepts look at many variables:
Market Factors
Population Density + Growth (Trade Area + Set Drive-Times/Radials) Income Profile
Psychographics (Tapestry Data)
Planning/Zoning Processes
Incentives
Existing Brands + Performance
Real Estate Factors
Vehicle Traffic
Visibility
Store Spacing
Co-Tenants
Second Generation or New Construction
CORONA RETAIL TRADE AREA
CORONA RETAIL TRADE AREA
CORONA RETAIL TRADE AREA
POPULATION: 157,732 POPULATION: 845,212
Med. Age: 36.7
Ave HHI: $140,000
Med HHI: $108,000
Med. Age: 36.71
Ave HHI: $135,000
Med HHI: $104,000
CORONA RETAIL TRADE AREA
Home Depot:
73% Higher
Foot Traffic
Costco:
57% Higher
Foot Traffic
Texas Roadhouse:
2X Average
Foot Traffic
99 Ranch:
51% Higher
Foot Traffic
CORONA RETAIL TRADE AREA
Home Depot:
2X Average
Foot Traffic
Sams Club:
3X Average
Walmart: Foot Traffic
3X Average
Foot Traffic
BEDFORD MARKETPLACE / CROSSINGS AT CORONA
CORONA RETAIL TRADE AREA
Bath & Body
Works:
Average Store
Foot Traffic
Wood Ranch:
Average Store
Foot Traffic
Express:
25% Lower
Foot Traffic
Trader Joe’s:
Average Store
Foot Traffic
ACE Hardware:
65% Higher
Foot Traffic
RETAIL RECRUITMENT HIGHLIGHTS
Previous recruitment efforts have identified
interested tenants that have requested site
information to review with their brokers include:
- multiple national development firms
- national beverage/package retailers
- multiple coffee concepts
- major flag hotel
- entertainment concepts (trampoline, bowling, etc…)
TRC to continue outreach efforts for new retail,
restaurant, and entertainment brands and
provide direct access to city staff.
A City
Designed
for Action
Recognize Completed Actions
Prioritize Remaining Strategic Actions
Identify Possible Updates
Develop Implementation Schedule
Creating a walkable, vibrant, mixed-use space
that integrates retail, housing, and community
areas while boosting economic growth and
local engagement.
Spring 2025: Assess redevelopment opportunities and
commence Phase 1 demolition.
Fall 2025: Present redevelopment proposals to the City
Council.
Spring 2026: Secure project entitlements.
Summer 2026: Establish a development partnership.
The expansion of economic opportunities will
drive growth and development within the
community. Residents will experience a higher
quality of life through improved services,
infrastructure, and overall living conditions.
South Mall Progress Rate:
North Mall Progress Rate:
Telling Our Story
From Craft to Corporate
See why businesses big and small choose Corona.
Be at the Center of it all!
Development of Industry Infographics, a
Business Programs and Incentive Guide and
more!
A campaign series focused on telling the
Corona story locally and globally!
A Masterclass Series
EDSP Milestone "How To Do
Business" guide
Engaging topics and resources.
Aimed to empower businesses
with an understanding of how to
navigate permits and approvals.
Improved resident awareness of
and support for local businesses
Find a perfect...
Improved business to business
relationships
Expanded tools to attract and
retain job creating businesses
The Next 4 years
2025 2026 2027 2028
Communication Strategy Deployment
EDSP Action Plan
Incentive Strategy
& Small Business
Symposium
Launch Innovation Center
and enhance local and
regional partnerships
South Mall fully leased
North Mall Redevelopment
Commences
North Mall Redevelopment
Phase 1 Complete
Working together to create the talent
pipeline for tomorrow.
Enhancing partnerships for creative
solutions.
Developing livable and walkable
spaces for the community.
DATE: 04/02/2025
TO: Honorable Mayor and City Council Members
FROM: Human Resources Department
2025-137
REQUEST FOR CITY COUNCIL ACTION
SUBJECT:
APPROVAL OF RESOLUTION 2025-020, A RESOLUTION OF THE MAYOR AND CITY
COUNCIL OF THE CITY OF CORONA ESTABLISHING ITS INTENTION TO AMEND
ITS AGREEMENT WITH CALPERS
EXECUTIVE SUMMARY:
This staff report asks the City Council to adopt the resolution stating the City’s intention to amend its contract between the City and the California Public Employees’ Retirement System (CalPERS) to provide Fourth Level 1959 Survivor Benefits for its sworn Police employees, with employees paying for the entire additional cost, and to conduct first reading of Ordinance 3414, amending the City’s CalPERS contract to provide the Fourth Level Survivor Benefit.
RECOMMENDED ACTION:
That the City Council:
a. Adopt Resolution No. 2025-020, the intention to approve an amendment to the contract between the Board of Administration California Public Employees’ Retirement System and the City Council of the City of Corona. b. Introduce, by title only, and waive full reading of consideration of Ordinance No. 3414, first reading of an ordinance authorizing an amendment to the contract
between the City Council of the City of Corona, and the Board of Administration of the California Public Employees’ Retirement System.
BACKGROUND & HISTORY:
The CalPERS 1959 Survivor Benefit Program allows eligible survivors to receive a monthly allowance when CalPERS members who are not covered by Social Security pass away before retirement. There are five (5) levels to the benefit program, each varying in the dollar amount of monthly payments to survivors eligible for the benefit. Benefits are lowest for survivors at Level 1 and highest at Level 5. Currently, the City of Corona provides sworn Police employees with Level 3 survivor’s benefit. Attachment 1 is a CalPERS publication summarizing the 1959 Survivor program.
ANALYSIS:
As part of the new Memoranda of Understanding (MOUs) approved with the Corona Police Employees Association (CPEA) and Corona Police Supervisors Association (CPSA) in December 2024, the City agreed to amend its contract to provide the Fourth Level Survivor benefit. CPEA and CPSA agreed to pay the full additional benefit cost through payroll deductions so that there is no new cost to the City. Shifting from the Third Level to the Fourth Level in the Survivor Benefit program will increase the monthly payments survivors will receive if a covered CalPERS member passes away before retirement.
Provision of this benefit enhancement requires an amendment to the City’s CalPERS contract. The first steps in the contract amendment process are as follows:
The public agency must adopt a Resolution of Intention to amend its CalPERS contract to include the Fourth Level Survivor Benefit. Government Code Section 7507 requires that the future annual costs or benefit change of the proposed contract amendment be made public at a public meeting at least two weeks before the adoption of the final Ordinance amending the CalPERS contract. The public agency must adopt an Ordinance approving the contract amendment after a waiting period of at least 20 days between the adoption of the Resolution of Intention and the adoption of the Final Ordinance.
The proposed actions on this agenda are the first steps in this process. It is recommended that the City Council adopt the Resolution of Intention and conduct the first reading of the Ordinance, amending the CalPERS contract to add the Fourth Level Survivor Benefit for CPEA and CPSA.
Next steps and timeline:
May 5, 2025: Second Reading and Adoption of Final Ordinance June 6, 2025: Effective Date of Ordinance
June 15, 2025: Effective Date of CalPERS Contract Amendment
FINANCIAL IMPACT:
The cost of this contract amendment for Fourth Level of 1959 Survivor Benefits is as follows, as identified in the actuarial variation for this plan amendment, which is attached (Attachment 4). The City’s first-year payment is zero, as noted below:
1. First-Year Employer Normal Cost $ 10,762
2. Five-Year Amortization of Unfunded Liability/Excess
Asset Payment (fixed for 5 years) ($50,643)
3. First-Year Total Employer Cost $ 0
Costs for this benefit are pooled among the participating public agencies. As the actuarial report notes, at this time, both the Third Level pool and the Fourth Level pool have surplus funded ratios, at 472.4% funded and 103.3% funded, respectively. Going forward, the report states that “the pool’s net cost will vary from year to year, depending on actual experience at the rate at which the existing surplus is amortized to offset ongoing employer normal costs”.
While costs will vary over time going forward, there is no anticipated financial impact to the City’s budget associated with this action because those costs will be funded by employee contributions in accordance with the CPEA and CPSA 2025-2027 Memoranda of Understanding. As long as the provisions in these MOU remain unchanged, costs to the City for this benefit will remain at zero as employees in these groups will fund those costs through payroll deduction.
ENVIRONMENTAL ANALYSIS:
This action is exempt pursuant to Section 15061(b)(3) of the Guidelines for the California Environmental Quality Act (CEQA), which states that a project is exempt from CEQA if the activity is covered by the commonsense exemption that CEQA applies only to projects that have the potential for causing a significant effect on the environment. Where it can be seen with certainty that there is no possibility that the activity in question may have a significant effect on the environment, the activity is not subject to CEQA. The approval of this action will not result in a significant effect on the environment. Therefore, no environmental analysis is required.
PREPARED BY: GRECIA MORALES, HUMAN RESOURCES INTERN
REVIEWED BY: LORI SASSOON, CHIEF TALENT OFFICER
ATTACHMENTS:
1. Exhibit 1 – Resolution No. 2025-020
2. Exhibit 2 – Ordinance No. 3414
3. Exhibit 3 – 1959 Survivor Handout
4. Exhibit 4 – 4
th Level Survivor Benefit Valuation Jan 2025
Exhibit 1
1 RESOLUTION NO. 2025-020
RESOLUTION OF INTENTION TO APPROVE AN
AMENDMENT TO CONTRACT BETWEEN THE BOARD
OF ADMINISTRATION CALIFORNIA PUBLIC
EMPLOYEES’ RETIREMENT SYSTEM AND THE CITY
COUNCIL CITY OF CORONA
WHEREAS, the Public Employees’ Retirement Law permits the participation of public agencies and their employees in the Public Employees’ Retirement System by the execution of a contract, and sets forth the procedure by which said public agencies may elect to subject themselves and their employees to amendments to said Law; and WHEREAS, one of the steps in the procedures to amend this contract is the adoption by the governing body of the public agency of a resolution giving notice of its intention to approve an amendment to said contract, which resolution shall contain a summary of the change proposed in said contract; and
WHEREAS, the following is a statement of the proposed change: To provide Section 21574 (Fourth Level of 1959 Survivor Benefits) for local police members.
NOW, THEREFORE, BE IT RESOLVED THAT THE GOVERNING BODY
OF THE ABOVE AGENCY DOES HEREBY GIVE NOTICE OF
INTENTION TO APPROVE AN AMENDMENT TO THE CONTRACT
BETWEEN SAID PUBLIC AGENCY AND THE BOARD OF
ADMINISTRATION OF THE PUBLIC EMPLOYEES’ RETIREMENT
SYSTEM, A COPY OF SAID AMENDMENT BEING ATTACHED
HERETO, AS AN “EXHIBIT” AND BY THIS REFERENCE MADE A PART HEREOF.
PASSED, APPROVED AND ADOPTED this 2nd day of April, 2025 Mayor of the City of Corona, California
ATTEST:
City Clerk of the City of Corona, California
2 CERTIFICATION
I, Sylvia Edwards, City Clerk of the City of Corona, California, do hereby certify that the foregoing Resolution was regularly passed and adopted by the City Council of the City of Corona, California, at a regular meeting thereof held on the 2nd day of April, 2025 by the following vote:
AYES:
NOES:
ABSENT:
ABSTAINED:
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the official seal of the City of Corona, California, this 2nd day of April, 2025 City Clerk of the City of Corona, California
[SEAL]
Exhibit 2
2 ORDINANCE NO. 3414
AN ORDINANCE OF THE OF THE CITY COUNCIL OF THE
CITY OF CORONA, AUTHORIZING AN AMENDMENT TO
THE CONTRACT BETWEEN THE CITY COUNCIL OF THE
CITY OF CORONA, AND THE BOARD OF
ADMINISTRATION OF THE CALIFORNIA PUBLIC
EMPLOYEES’ RETIREMENT SYSTEM.
WHEREAS, in December of 2024, Memoranda of Understanding were approved with the Corona Police Employees Association (CEPA) and Corona Police Supervisors Association (CPSA), and among the provisions in those MOU’s was an agreement for the City to amend its contract with the California Public Employees’ Retirement System (CalPERS) to provide the 1959 Fourth Level Survivor Benefit.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF CORONA
DOES ORDAIN AS FOLLOWS:
SECTION 1. That the amendment to the contract between the City Council of the City of Corona and the Board of Administration, California Public Employees’ Retirement System is hereby authorized, a copy of said amendment being attached hereto, marked Exhibit, and by such reference made a part hereof as though herein set out in full.
SECTION 2. The Mayor of the City of Corona is hereby authorized, empowered, and directed to execute said amendment for and on behalf of said Agency.
SECTION 3. The Mayor shall sign the Ordinance and the City clerk shall attest thereto and shall within 15 days of its adoption cause it, or a summary of it, to be published in a general circulation newspaper published in the City of Corona. This Ordinance shall take effect and be in force 30 days after its adoption.
PASSED, APPROVED AND ADOPTED this 5th day of May, 2025
Mayor of the City of Corona, California
ATTEST:
City Clerk of the City of Corona, California
Exhibit 2
2 CERTIFICATION
I, Sylvia Edwards, City Clerk of the City of Corona, California, do hereby certify that the foregoing Ordinance was regularly introduced at a regular meeting of the City Council of the City of Corona, California duly held on the 2nd day of April, 2025 and thereafter at a regular meeting held on the 5th day of May, 2025 it was duly passed and adopted by the following vote:
AYES:
NOES:
ABSENT:
ABSTAINED:
IN WITNESS WHEREOF, I have hereunto set my hand and affixed the official seal of the City of Corona, California, this 5th day of May, 2025 City Clerk of the City of Corona, California
[SEAL]
1959 Survivor Benefit Program
The 1959 Survivor Benefit provides a monthly allowance to eligible survivors of members who were covered for this benefit program and died before retirement. This benefit coverage is available by contract amendment for those members who are not covered by federal Social Security with their employer. Covered members are required to pay a monthly fee that is deducted from their salary specifically to fund the 1959 Survivor Benefit Program.
The 1959 Survivor Benefit allowance is payable in addition to any other pre-retirement death benefit paid by CalPERS, with the possible exception of the Special Death Benefit. If the 1959 Survivor Benefit is greater than the Special Death Benefit, then the difference is paid as the 1959 Survivor Benefit. Please refer to your CalPERS Member Benefit Booklet for information on the Special Death Benefit and other pre-retirement death benefits.
Upon a member’s pre-retirement death, the respective employer and surviving spouse, registered domestic partner, or dependent children are encouraged to immediately contact CalPERS for assistance.
Monthly Benefit Levels
Currently, there are six different benefit levels. The applicable level depends on the contract the employer has with CalPERS.
County schools members and State members are covered by Level 5.
Local members (city, county, or special district) may be covered by any of the first four levels or by the “Indexed” level, depending on their employer’s contract with CalPERS.
Please refer to the following chart to determine the amounts payable under each level depending on the number of eligible survivors:
Benefit Payments
Benefit Level One Survivor Two Survivors Three or More Survivors Level 1* $180 $360 $430
Level 2* $225 $450 $538
Level 3* $350 $700 $840
Level 4 $950 $1,900 $2,280
Level 5 $750 $1,500 $1,800
Indexed Level $500** $1,000** $1,500**
* These levels are closed for new agencies or for contract amendments ** These benefit amounts increase by 2 percent each January, beginning in January 2001.
Eligible Survivors
Spouse or registered dometic partner: A surviving spouse or registered domestic partner is a person who was legally married, or in a registered domestic partnership, with the member either one year prior to the member’s death, or before the occurrence of the injury or onset of illness that resulted in the member’s death. A surviving spouse or registered domestic partner is entitled to the 1959 Survivor Benefit as long as they have care of an eligible child, OR are at least age 62 (age 60 at Level 4, 5, and under the Indexed Level). A surviving spouse may remarry and continue to receive their allowance.
Children: An unmarried biological or adopted child of the member or an unmarried stepchild (if the child was living with the member in a parent-child relationship) is eligible for benefits while under age 22. An unmarried child incapacitated because of a disability which began before attaining age 22 may be entitled to the benefit until the disability ends. If a child is in the care of the guardian, or is living on their own, the child’s portion of the benefit is payable to the guardian or to the child directly, rather than to the surviving spouse or registered domestic partner.
Parents: A parent may be eligible if there is no surviving spouse, registered domestic partner or eligible children, and the parent(s) was dependent on the member for at least half of their financial support at the time of the member’s death.
Taxability Of The Benefit
The 1959 Survivor Benefit is a taxable allowance and will be reported by CalPERS to the tax authorities each year on a Form 1099R.
Some surviving spouses and registered domestic partners are subject to a mandatory 20 percent federal withholding on all or a portion of their 1959 Survivor Benefit allowance.
If the 20 percent federal withholding applies, a spouse or registered domestic partner may avoid the withholding if they elect to have the allowancedirectly rolled over into an individual retirement account (IRA). A form to elect a rollover will be provided at the time benefits are payable if the payee is subject to the mandatory 20 percent withholding.
All or a portion of the allowance may be rolled over into an IRA, or else be subject to 20 percent withholding, under the following circumstances:
• The entire allowance is subject to 20 percent withholding, or may be rolled over to an IRA, if the payee is a surviving spouse, or registered domestic partner, who has care of children who will all turn age 22 in less than 10 years from the effective date of the allowance.
• A portion of the allowance is subject to 20 percent withholding, or may be rolled over to an IRA, if; 1) the payee is a surviving spouse, or registered domestic partner, who has care of at least two children, and: 2) the payee will have care of only one eligible child in less than 10 years from the effective date of the allowance.
The 20 percent withholding does not apply when a spouse, or registered domestic partner, receives the allowance at age 60 or 62.
In any case, the surviving spouse, or registered domestic partner, is encouraged to call CalPERS for answers regarding their specific tax questions.
For More Information
If you have questions or need further information about the 1959 Survivor Benefit Program, please contact your nearest CalPERS office.
CalPERS Benefit Services Division
P.O. BOX 1652 Sacramento, CA 95812-1652
(888) 225-7377
(877) 249-7442 – Telecommunications Device for the Deaf (916) 795-3988 – Fax
CalPERS Regional Offices
For a directory of CalPERS Regional Offices, refer to the CalPERS online website at www.calpers.ca.gov.
While reading this material, remember that we are governed by the California Public Employees’ Retirement Law. The statements in this handout are general. The retirement law is complex and subject to change; therefore, if there is a conflict between the law and this handout, any decisions will be based on the law.
For specific tax questions, please call your tax advisor.
California Public Employees’ Retirement System
400 Q Street
Sacramento, CA 95811
www.calpers.ca.gov
Produced by the Office of Public Affairs
PERS–PUB–51
January 2024
California Public Employees’ Retirement System
Actuarial Office
400 Q Street, Sacramento, CA 95811 | Phone: (916) 795-3000 | Fax: (916) 795-2744 888 CalPERS (or 888-225-7377) | TTY: (877) 249-7442 | www.calpers.ca.gov 02/07/25 page 1 of 3 Ver. 1/25
City of Corona (CalPERS ID: 1307714161), Safety - Police Amendment Actuarial Valuation Report as of June 30, 2023 Section 21574 - Fourth Level of 1959 Survivor Benefit Program for Local Members The table on the following page shows the change in the liabilities and costs for adopting an increase in the 1959 Survivor Benefit from the Third Level to the Fourth Level for the member category indicated above. The costs are determined using the Term Insurance Funding Method. Under this method, the accrued liability is equal to the present value of benefits to survivors currently receiving payments and deferred benefits payable to a spouse of a deceased member when the spouse attains age
60. The normal cost is equal to the present value of benefits for expected deaths during the upcoming year.
The assets and liabilities for public agencies in the program are pooled for each Level. When a member group contracts for Fourth Level benefits from the Third Level, the employer’s unfunded liability is based on the Third Level funded ratio as of the most recently completed valuation, adjusted for the higher benefit amounts for Fourth Level survivors. The cost to the agency is the adjusted unfunded liability plus the Fourth Level normal cost for five years. The five-year normal cost requirement is necessary to prevent inequitable depletion of the pool’s current surplus by agencies who have not contributed to the surplus.
For the Fourth Level 1959 Survivor Benefit, the CalPERS Board of Administration approved a fiscal year 2024-25 employer normal cost of $5.90 per covered active member, per month. The assets used to determine the unfunded liability are allocated in accordance with a formula based on various factors, including the member category’s accrued liability and length of time in the current level pool, and the current level pool’s total assets and liabilities. Agencies will be allowed to amortize this unfunded liability over a period of five years. If there are excess assets rather than an unfunded liability, the excess will be used to offset the normal cost payments to the extent possible. Your agency’s first-year payment (normal cost plus amortization of unfunded liability/excess assets) is $0. Payments for years two through five will be recalculated each year and will vary according to the number of covered active members and the pool’s revised normal cost.
At the end of five years, the group(s) become part of the pool and the employer’s cost will be the pool’s net cost. Currently the Third Level pool has an employer cost of $0.00 due to the large surplus (472.4% funded ratio). The Fourth Level pool has a modest surplus (103.3% funded ratio), and the pool’s employer net cost after amortization of the surplus is $5.80 per member, per month. Please note, however, that the pool’s net cost will vary from year to year, depending on actual experience and the rate at which the existing surplus is amortized to offset ongoing employer normal costs.
Fiscal Year
Employer Premiums
Third Level Fourth Level
2023-24 $0.00 $5.20
2024-25 $0.00 $5.80
Should your agency elect to proceed with this contract amendment and payments are due, annual payments will be in level dollar amounts and will not be expressed as a percentage of your covered payroll. If payments are due, your agency will be set up on a five-year amortization payment schedule. The first invoice will be sent in June, and your first payment is due within 30 days.
The valuation has been performed in accordance with standards of practice prescribed by the Actuarial Standards Board, and the assumptions and methods are internally consistent and reasonable for this plan, as prescribed by the CalPERS Board of Administration according to provisions set forth in the California Public Employees’ Retirement Law. The valuation has been prepared in accordance with generally accepted actuarial practice.
CalPERS Amendment Actuarial Valuation - June 30, 2023
City of Corona, Safety - Police
CalPERS ID: 1307714161
02/07/25 page 2 of 3 Ver. 1/25
This cost analysis expires July 1, 2025. A Resolution of Intention approved by the agency governing body to amend the contract must be received by this office on or before July 1, 2025 and the amendment effective date must be before July 1, 2025. If either of these two conditions is not met, an updated cost analysis is required to amend the contract.
To complete the contract amendment process based on the enclosed analysis, you must do the following:
• Follow the Contract Amendment Request process on myCalPERS and work with our Retirement Contract Services Unit.
• Complete the adopted resolution and return to CalPERS on or before July 1, 2025. Adoption of the Final Resolution by this date is not required.
If you have questions about the cost analysis, please call (888) CalPERS (225-7377). Please ask to speak to a contract analyst for questions about the timing of the contract amendment. Please ask to speak to me for questions about this cost analysis.
Kurt Schneider, MPA, ASA, EA, MAAA
Supervising Actuary, CalPERS
CalPERS Amendment Actuarial Valuation - June 30, 2023
City of Corona, Safety - Police
CalPERS ID: 1307714161
02/07/25 page 3 of 3 Ver. 1/25
Impact of Amendment
The table below shows the impact of an amendment to the Fourth Level 1959 Survivor Benefit for the specified member category.
Pre-Amendment
Change Due to
Plan Amendment Post-Amendment
Benefit Level Third Fourth
Survivor with 2 or More Eligible Children $840 $2,280
Survivor with One Eligible Child $700 $1,900
Survivor 62 or Older, One Eligible Child,
or Eligible Dependent Parent $350 $950
1. Number of Current Survivors 3 - 3
2. Accrued Liability $115,580 $214,118 $329,698
3. Plan’s Market Value of Assets(1) $545,332 $545,332
4. Unfunded Liability / (Excess Assets)
(2) – (3)
($429,752) $214,118 ($215,634)
5. Unfunded Liability / (Excess Assets)
projected forward to June 30, 2025
($487,067) $264,109 ($222,958)
6. Pool’s Funded Ratio (2) 472.4% N/A
7. Total Employer Normal Cost,
Per Member, Per Month $ 0.80 $ 5.10 $ 5.90
8. Number of Members 152 - 152
9. First-Year Employer Normal Cost
(7) x (8) x 12 N/A $10,762
10. Five-Year Amortization of Unfunded
Liability / (Excess Assets) N/A ($50,643)
11. First-Year Total Employer Cost
(9) + (10), not less than zero N/A $0
12. Member Monthly Premium $ 2.00 - $ 2.00
(1) Assets are allocated as a share of the pool’s assets. (2) The funded ratio for the current pool as of the most recently completed valuation.
DATE: 04/02/2025
TO: Honorable Mayor and City Council Members
FROM: Planning and Development Department
2025-121
REQUEST FOR CITY COUNCIL ACTION
SUBJECT:
CONDITIONAL USE PERMIT 2023-0015 FOR THE ESTABLISHMENT OF A RELIGIOUS FACILITY (MOSQUE) WITHIN AN EXISTING 4,330 SQUARE-FOOT RESIDENTIAL DWELLING, ON 1.37 ACRES LOCATED AT 2460 SOUTH MAIN STREET IN THE R-1-8.4, SINGLE FAMILY RESIDENTIAL, ZONE (APPLICANT: ALI
RAZA RIZVI, SAJJADIA ISLAMIC SOCIETY)
EXECUTIVE SUMMARY:
This staff report asks the City Council to affirm the decision by the Planning and Housing Commission in granting Conditional Use Permit 2023-0015 (CUP2023-0015) for the establishment of a religious facility on 1.37 acres within an existing residential dwelling.
The dwelling is 4,330 square feet and the interior of the structure will be converted to support prayer services, religious teachings, and an administrative office. The exterior of the property will be improved with a parking lot and landscaping. The R-1-8.4 zone is intended for single family residential, but allows religious facilities by a conditional use permit, which is the reason for CUP2023-0015.
RECOMMENDED ACTION:
That the City Council:
a. Take no action, thereby affirming the Planning and Housing Commission’s action granting CUP2023-0015, based on the finding contained in the staff report and conditions of approval.
OR
b. Set the item for review at a subsequent meeting.
BACKGROUND & HISTORY:
The applicant and current owner of the property is the Sajjadia Islamic Society, an organization that provides religious learning programs and a prayer hall for the Shia Islamic community. The Society is currently operating within the Corona North Mall at 425 Corona Mall. The applicant purchased the property at 2460 S. Main Street with the intent of relocating, establishing and operating a mosque. As with other various religious organizations in the City, the Sajjadia Islamic Society would operate the new facility and learning center with its own specific prayer times.
According to Section 17.92.040(B), religious facilities may be permitted by CUP only if the use is located on a site with primary access and at least one frontage on a major, secondary or fully improved collector street. Main Street is a four-lane, Major Arterial.
ANALYSIS:
Site Plan
The property is bordered by single family residential dwellings to the north and west, a church to the south, Nanner’s Way (street) to the northwest, and Main Street to the east.
The existing dwelling and an attached two-car garage are centrally located on the property. Two driveways are located at the property’s east perimeter which provides vehicular access from Main Street. A third driveway is located at the northwest perimeter which provides access from Nanners Way.
No expansion is proposed to the existing building. However, new paved parking spaces with associated drive aisles and landscaping are proposed around the building. The perimeter of the property will be fenced and the new parking lot will be gated.
To facilitate the capture and infiltration of surface runoff, a landscaped bioretention basin is proposed on the northeastern corner of the project site. Minimal grading is proposed and will be limited to leveling the site for the parking lot and providing proper onsite drainage patterns.
Pursuant to the R-1-8.4 zone, the project site requires a 25-foot front-yard building setback, a side yard setback of five feet on one side and 10 feet on the other side, and when adjacent to a street, a 15-foot rear-yard building setback. Per the CMC, when a lot abuts more than one street, the lot’s front yard is considered the narrowest portion abutting the street. As the narrowest portion of the project site fronts Nanners Way, this area is considered the front yard for the purpose of determining the front yard setback area, which makes the portion of the property that abuts Main Street the rear setback area. The existing structure meets the setback requirement of the R-1-8.4 zone.
Elevations
The conversion of the existing single story residential dwelling to its new use as a mosque will include minimal exterior alterations. At the building’s east elevation, one existing window will be demolished, and a new door will be added, coupled with the removal of gates (located forward of the building’s entryway). The building’s existing stucco surfacing, earthtone-colored concrete roof tiles, and general form (gabled roofs, singlestory, etc.) will be unchanged.
Operation
The interior of the new mosque will include two prayer halls totaling 1,675 SF, two reading rooms totaling 495 SF, a breakroom totaling 232 SF, and three restrooms totaling 443 SF. The remaining area consists of a two-car garage (for use by staff), various hallways and storage. New ramps are proposed on the west and east sides of the building that provide pedestrian access from the exterior to the prayer halls. The overall building footprint will be unchanged.
Prayers will be conducted inside the building five times daily, from sunrise to sunset.
While the timing of prayer sessions will vary by time of the year/season (primarily occurring daily at sunrise and sunset), the applicant has provided the current prayer times, shown in Table 1.
Table 1: Prayer Times
Day of the Week Prayer Time
Morning Prayer 5:07 AM
Noon Prayer 12:02 PM
Afternoon Prayer 3:20 PM
Sunset Prayer 5:49 PM
Evening Prayer 6:57 PM
From Saturday through Thursday, the applicant anticipates approximately zero to 10 people in attendance during specified prayer times, with larger gatherings on Friday afternoons and Sunday mornings where the average occupancy inside the building is expected to be between 50 to 75 individuals. Approximately 75 percent of the individuals will be adults, aged 18 and above; 20 percent will be children, aged 12 to 17; and the remaining five percent will be young children under the age of 5 years.
Access And On-Site Circulation
Patrons of the mosque will use the property’s two existing driveways from Main Street.
Driveways will be modified to meet current city standards but maintained in their current locations. The northerly driveway is proposed as the site’s primary entrance and will allow for vehicles traveling southbound on Main Street to make right turns into the site.
Northbound vehicles on Main Street are restricted from making left turns into the site due to an existing raised concrete center median located on Main Street. The southerly driveway is proposed as an exit-only driveway, and vehicles are limited to right turns onto Main Street due to the existing center median on Main Street.
Nanners Way is a local street and the driveway from this street is currently closed off by existing gates. The driveway from Nanners Way will remain gated during all hours of use
on the project site, and only available for use as secondary access for emergency vehicles. As such, the mosque meets the city’s siting criteria for religious facilities as the project site will have primary access from a major arterial street and will not have daily access from streets used by residential neighborhoods.
The parking lot entrance will be gated by an electric automatic gate that is offset from the site’s northerly driveway. As shown on the site plan, this driveway can accommodate the queueing of up to three vehicles from the onsite gate. The gates will remain open when the mosque has prayer services or other religious gatherings. When there are no events, the gates will remain closed. The applicant has agreed, and as required as a condition of approval added by the Planning and Housing Commission, to provide through-access from the on-site drive lane extending from the northerly driveway to the project site’s back drive aisle to allow left turns. This is to allow vehicles to circulate further into the site should any potential stacking occur from the northerly driveway.
No public improvements are required within the right-of-way, as the segments of Main Street and Nanners Way adjacent to the project site are fully developed according to the ultimate right-of-way widths for both streets, including curb and gutter, sidewalk and parkway.
Traffic Trip Generation
Because the mosque will spread out its prayer five times throughout the day, the use is not expected to exceed 50 trips during peak hours. The largest occupancy is expected on Friday afternoon, when approximately between 50 to 75 individuals (including children) would be in attendance. The City’s Traffic Division evaluated the number of p.m. peak hour trips expected on Friday and concluded that the project would result in 18 peak hour trips within one hour between 4:00 p.m. and 6:00 p.m. Also, the use of the mosque on Sunday would be outside of peak traffic times. As such, the proposed mosque is not expected to create traffic impacts on Main Street or other surrounding roadways.
Parking
Per CMC Section 17.76.030, a religious facility is required to have at least one parking space for every 25 square feet of assembly area for the prayer hall. Like other religious facilities, the required parking is based on the floor area used for prayer services, which is the most conservative parking ratio at any given time. Since other uses within the building are during opposite times of the prayer services, the parking spaces normally used for the prayer services are shared with the other uses in the structure.
The mosque requires 67 parking spaces, with 68 parking spaces proposed. The project’s parking compliance is summarized below in Table 2.
Table 2: Parking Requirement
Use Square Footage Parking
Requirement
Parking
Required
Parking
Provided
Prayer Hall 1,675 SF 1 space/25 SF 67 spaces 68 spaces
Men’s Reading Room* 213 SF -- -- --
Ladies Reading
Room*
282 SF -- -- --
Breakroom* 232 SF -- -- --
Office* 99 SF -- -- --
*Uses the opposite time of prayer services.
Walls and Fences
A total of 258 linear feet of new wrought-iron fencing and two metal gates, standing a maximum of six feet in height, are proposed along the easterly perimeter of the property.
An existing block wall along the north property line, chain-link fencing on the south property line, and a block wall along the west property lines would remain.
Landscaping
Landscaping will be provided throughout the site, including around the perimeter, throughout the parking lot, and within a bioretention basin proposed at the lot’s northerly extent. In total, the site will have approximately 19,000 SF of landscaping, including 9,076 SF within the bioretention basin.
FINANCIAL IMPACT:
The applicant paid the application processing fees of $3,874 to cover the cost of the Conditional Use Permit.
ENVIRONMENTAL ANALYSIS:
Per Section 15301 (Class 1 – Existing Facilities) of the State Guidelines for Implementing the California Environmental Quality Act (CEQA) and Section 3.21 of the City’s Local CEQA Guidelines, a Notice of Exemption has been prepared for the project because the project qualifies as a Class 1 (Existing Facilities) categorical exemption. The project involves minor exterior alterations on a site that is 1.37 acres and interior improvements to the inside of an existing building.
PLANNING AND HOUSING COMMISSION ACTION:
At its meeting on March 10, 2025, the Planning and Housing Commission considered the subject matter and took the following action:
Motion was made, seconded (Vernon/Alexander) and carried, with Commissioner Siqueland absent, that the Planning and Housing Commission find the project exempt from the California Environmental Quality Act (CEQA) pursuant to CEQA Guidelines Section 15301 (Class 1 – Existing Facilities), adopt Resolution No. 2661 granting CUP2023-0015, based on the findings contained in the staff report, the conditions of approval and the added conditions of approval. The minutes of the Planning and Housing Commission meeting are included as Exhibit 4.
PREPARED BY: JOANNE COLETTA, PLANNING AND DEVELOPMENT DIRECTOR ATTACHMENTS:
1. Exhibit 1 – Locational and zoning map
2. Exhibit 2 – Site plan for Conditional Use Permit 2023-0015
3. Exhibit 3 – Planning and Housing Commission staff report
4. Exhibit 4 – Draft minutes of the Planning and Housing Commission meeting of March 10, 2025
DN
13 2
8 9 8
28 OVERHANG
18 5.0
0' N
81°5
6'0
6"W
325.00'
N08°01'06"E
N08°01'06"E 299.80'
15 4.4
0' N
81°5
6'0
6"W
D
Y
H
DN
P.O.T
SOFT LANDSCAPE AREA
INFLOW TRAFFIC
OUTFLOW TRAFFIC
5' - 9 1/2"
12' - 2"
SIDE SETBACK REQ. IS 5 FT.
PROVIDED 5 FT.
SIDE SET BACK REQUIRED / LANDSCAPE
IS 5 FT.- PROVIDED 65FT-5 IN.
SIDE SETBACK REQ. IS 5 FT.
PROVIDED 5 FT.
NANNERS WAY
NANNERS WAY
MAIN STREET
65' - 5"
(E) FIRE HYDRANT
(N) PUBLIC FIRE HYDRANT(SUBJUCT
TO FIRE DEPT. APPROVAL)
FIRE TRUCK ENTRY GATE TO BE
EQUIPPED W/ KNOX BOX FOR FIRE
DEPT. THIS GATE TO USED ONLY BY
FIRE DEPT./ EMS
EXISTING
LANDSCAPE SHED
(N) MAN GATE W/
KNOX BOX FOR
FIRE DEPT.
(N) MAN GATE W/
KNOX BOX FOR
FIRE DEPT.
(N) PROPOSED
TRASH ENCLOSURE.
SEE CIVIL DRAWINGS
OCCUPANCY: A3
OCCUPANCY LOAD : 64
OCCUPANCY : A3
OCCUPANCY LOAD :105
OCCUPANCY B
OCCUPANCY
LOAD :5
ENT.
OCCUPANCY B
OCCUPANCY LOAD :6
MEN'S READING
ROOM.
LADIES READING
ROOM.
LADIES PRAYER
HALL
MEN'S PRAYER
HALL
LADIES TOILET
MEN'S TOILET
TOILET
OFFICE
BREAK ROOM
HALLWAY
ENT. HALL
HALLWAY HALLWAY STORE STORE
DN
RAMP
RAMP
DN DN
OCCUPANCY B
OCCUPANCY LOAD : 3
PARKING REQUIREMENT.
OCCUPANCY: A3
PRAYER HALLS AREA: 1,675 SFT.
PARKING REQUIRED 1,675 / 25 = 67
ACCESSIABLE PARKING REQUIRED = 3
PARKING TABULATION
REGULAR PARKING STALLS PROVIDED = 64
COMPACT PARKING STALL PROVIDED = 1
ACCESSIABLE PARKING PROVIDED = 3
_______________________________________
TOTAL PARKING STALLS PROVIDED = 68
BUILDING DATA
TYPE OF CONSTRUCTION = VB
PROPOSED SPRINKLER = S
PROPOSED OCCUPANCY: A3
EXISTING BUILDIND AREA: 4,330 SFT.
LOT AREA: 59867
GROSS OCCUPANT LOAD 184
ADDRESS: 2460 S MAIN STREET, CORONA,
CA 92881
LEGAL DESCRIPTION
APN -113310010
LOT NUMBER 10
PERMIT # B22-05590
NOTE:
THE PROPOSED REMODELED /RENOVATED EXISTING
STRUCTURE WILL BE SPRINKLERED ,AS SHOWN UNDER
BUILDING DATA.
PROPOSED BUILDING SETBACK ON THE EAST OF PROPERTY
(FACING MAIN ST. )IS 15 FEET , BUT DUE TO PARKING THE
LANDSCAPE SETBACK VARIES BETWEEN
NEW ELECTRIC AUTOMATIC GATE NOTES:
THE NEW ELECTRIC AUTOMATIC GATE WILL BE EQUIPPED
WITH TRANSPONDER SENSOR.
THE GATE WILL REMAIN OPEN DURING PRAYER SERVICES
OR ANY OTHER REGLIOUS GATHERING. WHEN THE MOSQUE
DOES NOT HAVE ANY EVENT /PR YER SERVICE THE GATE
WILL REMAIN CLOSED ,THE ATHOURISED PERSONAL WILL
HAVE THE TRANSPONDER CARDS TO OPERATE THE
ELECTRIC AUTOMATIC GATES.
18' - 7"
11' - 0"
TYP.
20' - 0" 25' - 0"
TYP.
18' - 0" R 3' - 0"
R 40' - 6"
6' - 7 1/2"
V.I.F.
24' - 4 1/2" ±
(N) ELECTRIC GATE TO BE
EQUIPPED W/ KNOX OVERIDE
SWITCH FOR FIRE DEPT.
(N) MAN GATE W/ KNOX BOX FOR
FIRE DEPT.
(N) ELECTRIC GATES TO BE
EQUIPPED W/ KNOX
OVERRIDE SWITCH FOR FIRE
DEPT.
EXIT
ENTRANCE
GARAGE
STORAGE
TYP.
20' - 0"
22' - 5"
19'-4".
25' - 0".
COMPACT
NO PARKING NEAR THE WATER BASINLETTER PROVIDED BY CIVIL ENGINEER SIDE LANDSCAPE SETBACK REQ. 5'
FRONT SETBACK / LANDSCAPE REQ. .
25' FT.- PROVIDED 42FT 3 3/4 IN.
45° TYP
25' - 0"
V.I.F.
14' - 9 1/4" ±
39' - 8" ±
45°TYP.
50'-00" F
R
O
M
M
E
DIA
N
R 75' - 10"
FRONT SETBACK PROVIIDED
42' - 3 3/4"
SETBACK REQUIRED
15' - 0"
OWNER:PROJECT NAME:PROJECT ADDRESS:
REVISIONS:
DESCRIPTION DATE
DATE ISSUED:
PROJECT NO:
SCALE:
SHEET NUMBER:
SHEET TITLE:
As indicated
SAJJADIA ISLAMIC SOCIETY
2460 S MAIN STREET, CORONA CA 92882
MOSQUE AT CORONA
03-08-2024
2023-927
A002
PROPOSED
REVISED SITE
PLAN
SITEPLAN LEGEND
SCALE
REVISED SITEPLAN - ACCESS 1/16" = 1'-0" 1
BUILDING SET BACKS
FRONT - NORTH OF PROPERTY
REQUIRED PROVIDED
25'-0" 42'- 3.75"
REMARKS
SIDE - WEST OF PROPERTY 5'-0" 5'- 0"
SIDE - SOUTH OF PROPERTY 5'-0" 5'- 0"
SIDE - NORTH WEST OF PROPERTY 5'-0" 65'- 5"
BACK - EAST OF PROPERTY 15'-0" '- VARIES
AN 0 0" 0'- 0" - 25'-0"
- 25'-0"
DATE: 03/10/2025
TO: Honorable Chair and Commissioners
FROM: Planning and Development Department
2025-100
APPLICATION REQUEST:
CUP2023-0015: Conditional Use Permit for the establishment of a religious facility (mosque) within an existing 4,330 square-foot residential dwelling, on a 1.37-acre property located at 2460 South Main Street. (Applicant: Ali Raza Rizvi representing the Sajjadia Islamic Society Inc., 8685 Orchard Park Drive, Riverside, CA 92508) RECOMMENDED ACTION:
That the Planning and Housing Commission find the project categorically exempt from the California Environmental Quality Act (CEQA) pursuant to CEQA Guidelines Section 15301, and adopt Resolution No. 2661 GRANTING CUP2023-0015, based on the findings contained in the staff report and conditions of approval.
PROJECT SITE SUMMARY:
Area of Property: 1.37 Acres
Existing Zoning: Single Family Residential Zone (R-1-8.4) Existing General Plan: Medium Density Residential (MDR) Existing Land Use: Residential
Proposed Land Use: Religious Facility
Surrounding Zoning/Land Uses:
N: R-1-8.4 / Residential
E: S (School) / School
S: R-2 (Low Density Multiple Family Residential) / Religious Facility W: R-1-8.4 / Residential
BACKGROUND
Conditional Use Permit CUP2023-0015 is a request to allow for the establishment of a new mosque (religious facility) within an existing, vacant single-family dwelling. The dwelling would be remodeled to accommodate the proposed use, and the broader property will be improved with a new surface parking lot and landscaping. The project site is located at 2460 South Main Street and zoned R-1-8.4 (Single-Family Residential Zone). Pursuant to Section
17.92.040 of the Corona Municipal Code (CMC), religious facilities (including churches, mosques and the like) are a permitted use within all residentially zoned parcels with approval of a Conditional Use Permit (CUP).
The applicant and current owner of the property is the Sajjadia Islamic Society, an organization that provides religious learning programs and a prayer hall for the Shia Islamic community. The Society is currently operating within the Corona North Mall at 425 Corona Mall and is seeking to relocate after the property was recently acquired by the City of Corona for redevelopment. The applicant purchased the project site with the intent of relocating, establishing and operating a mosque. As with other various religious organizations in the city, the Sajjadia Islamic Society would operate the new facility with its own specific prayer times and learning center.
The project was initially reviewed by city staff at the Development Plan Review (DPR) Committee meeting held on October 14, 2021. The applicant formally submitted the CUP application on May 15, 2023, and the application was reviewed by staff at the Project and Environmental Review Committee (PRC) meeting held on June 8, 2023. In response to staff’s comments, the applicant revised the plans, with the application ultimately deemed complete on February 4, 2025 and scheduled for the March 10, 2025 Planning and Housing Commission.
PROJECT DESCRIPTION
CUP2023-0015 is a request to establish a mosque within an existing 4,330 square-foot (SF) residential dwelling, to be remodeled to accommodate the new use. The repurposing of the existing structure would also include the construction of a new surface parking lot, trash facilities, landscaping, property-line fencing and gates. The following sections discuss the project’s site plan, hours of operation, access, onsite circulation and other features.
Site Plan
The property is bordered by single family residential dwellings to the north and west, a church to the south, Nanner’s Way (street) to the northwest, and Main Street to the east. The existing buildings and an attached two-car garage are centrally located on the property. Two driveways are located at the property’s east perimeter which provides vehicular access from Main Street. A third driveway is located at the northwest perimeter which provides access from Nanners Way. No expansion is proposed to the existing building. However, new paved parking spaces with associated drive aisles and landscaping are proposed around the building. The perimeter of the property will be fenced and the new parking lot will be gated.
A new trash enclosure is proposed to the southeast of the building and is conditioned to comply with the City’s trash enclosure standards, including surface materials and coloring to match that of the new mosque.
To facilitate the capture and infiltration of surface runoff, a landscaped bioretention basin is proposed on the northeastern corner of the project site; and, minimal grading is proposed and will be limited to leveling out the site for the parking lot and providing proper onsite drainage patterns (Exhibit 3 – Project Plans).
Pursuant to the property’s R-1-8.4 Zoning, the project site requires a 25-foot front-yard building setback, a side yard setback of five feet on one side and 10 feet on the other side, and when adjacent to a street, a 15-foot rear-yard building setback. Per the CMC, when a lot abuts more than one street, the lot’s front yard is considered the narrowest portion abutting the street. As the narrowest portion of the project site fronts Nanners Way, this area is considered the front yard for the purpose of determining the front yard setback area, which makes the portion of the property that abuts Main Street the rear setback area. As shown on the site plan, the mosque meets the setback requirements which are summarized in Table 1 below.
Table 1: R-1-8.4 Setback Requirements
Setback Location R-1-8.4 Zone
Minimum Setback
Complies With Zoning
Setback Requirement?
Front (Nanners Way) 25 ft Yes
Side (West and North lot
lines)
5 ft on one side and 10 ft
on the other side
Yes
Rear (Main Street) 15 ft, when abutting a
street
Yes
Floor Plan and Operations
The interior of the new mosque includes two prayer halls totaling 1,675 SF, two reading rooms totaling 495 SF, and three restrooms totaling 443 SF. The remaining area consists of a two-car garage (for use by mosque staff), a break room, various hallways and storage. New ramps are proposed on the west and east sides of the building that provide pedestrian access from the exterior to the prayer halls. As stated, while the interior of the building will be completely remodeled to accommodate the proposed use, the overall footprint will be unchanged.
Prayers will be conducted inside the building five times daily, from sunrise to sunset. While the timing of prayer sessions will vary by time of the year/season (primarily occurring daily at sunrise and sunset), the applicant has provided staff their current prayer times, shown in Table 2.
Table 2: Prayer Times
Day of the Week Prayer Time
Morning Prayer 5:07 AM
Noon Prayer 12:02 PM
Afternoon Prayer 3:20 PM
Sunset Prayer 5:49 PM
Evening Prayer 6:57 PM
From Saturday through Thursday, the applicant anticipates approximately zero to 10 people in attendance during specified prayer times, with larger gatherings on Friday afternoons and Sunday mornings where the average occupancy inside the building is expected to be between 50 to 75 individuals. Approximately 75 percent of the individuals will be adults, aged 18 and above; 20 percent will be children, aged 12 to 17; and the remaining five percent will be young children under the age of 5 years.
Elevations
The conversion of the existing residential dwelling to its new use as a mosque will include minimal exterior alterations. At the building’s east elevation, one existing window will be demolished and relocated for placement of a new door, coupled with removal of gates (located forward of the building’s entryway); and at the north elevation, existing garage doors will be replaced. The building’s existing stucco surfacing, earthtone-colored concrete roof tiles, and general form (gabled roofs, single-story, etc.) will be unchanged. Overall height is proposed as 17 feet, six inches, less than the 25-foot building limit prescribed by the property’s zoning. Elevations for the proposed religious facility are attached as Exhibit 3.
Access And On-Site Circulation
Patrons of the mosque will use the property’s two existing driveways from Main Street.
According to Section 17.92.040(B), religious facilities may be permitted by CUP only if the use is located on a site with primary access and at least one frontage on a major, secondary or fully improved collector street. Main Street is a four-lane, Major Arterial. Driveways will be modified to meet current city standards but maintained in their current locations. The northerly driveway is proposed as the site’s primary entrance and will allow for vehicles traveling southbound on Main Street to make right turns into the site. Northbound vehicles on Main Street are restricted from making left turns into the site due to an existing raised concrete center median located on Main Street. The southerly driveway is proposed as an exit-only driveway, and vehicles are limited to right turns onto Main Street due to the existing center median on Main Street.
The parking lot entrance will be gated by an electric automatic gate that is offset from the site’s northerly driveway. As shown on the site plan, this driveway can accommodate the queueing of up to three vehicles from the onsite gate. The gates will remain open when the
mosque has prayer services or other religious gatherings. When there are no events, the gates will remain closed.
Nanners Way is a local street and the driveway from this street is currently closed off by existing gates. The driveway from Nanners Way will remain gated during all hours of use on the project site, only available for use as secondary access for emergency vehicles.
Onsite circulation is comprised of one-way and two-way drive aisles which provide vehicular access from the project entrance to the parking spaces. The onsite circulation has been reviewed by city departments, including the Fire Department, for compliance with the applicable codes and requirements.
No public improvements are required within the right-of-way, as the segments of Main Street and Nanners Way adjacent to the project site are fully developed according to the ultimate right-of-way widths for both streets, including curb and gutter, sidewalk and parkway.
Traffic Trip Generation
Because the mosque will spread out its prayer five times throughout the day, the use is not expected to exceed 50 trips during peak hours. The largest occupancy is expected on Friday afternoon, when approximately between 50 to 75 individuals (including children) would be in attendance. The city’s Traffic Division evaluated the number of p.m. peak hour trips expected on Friday and concluded that the project would result in 18 peak hour trips within one hour between 4:00 p.m. and 6:00 p.m. Also, the use of the mosque on Sunday would be outside of peak traffic times. As such, the proposed mosque is not expected to create traffic impacts on Main Street or other surrounding roadways.
Parking
Per CMC Section 17.76.030, a religious facility is required to have at least one parking space for every 25 SF of assembly area. Based on the total size of the mosque’ assembly areas (i.e., prayer halls), the mosque requires 67 parking spaces, with 68 parking spaces proposed. The project’s parking compliance is summarized below in Table 3.
Table 3: Parking Requirement
Use Gross DF Assembly/Prayer
Hall SF
Parking
Requirement
Parking
Required
Parking
Provided
Church/Religious
Facility
4,330 SF 1,675 SF 1 space/25
SF of
assembly
area
67 spaces
68 spaces
Walls and Fences
A total of 258 linear feet of new wrought-iron fencing and two metal gates, standing a maximum of six feet in height, are proposed along the easterly perimeter of the property. An existing block wall along the north property line, chain-link fencing on the south property line, and a block wall along the west property lines would remain.
Landscaping
Landscaping will be provided throughout the site, including around the perimeter, throughout the parking lot, and within a bioretention basin proposed at the lot’s northerly extent. In total, the site will have approximately 19,000 SF of landscaping, including 9,076 SF within the bioretention basin. While the applicant’s letter (attached as Exhibit 5) states that grass, various shrubs, and mulch will be installed, CMC Chapter 17.70 prohibits the use of live turf (grass) except in areas dedicated for recreational or functional needs such as the bioretention basin, and accordingly a condition of approval has been added to require the applicant to install other acceptable landscape materials such as groundcover or shrubs in lieu of live turf.
The CMC also requires parking rows to have half-diamond-shaped landscape planters spaced every six parking spaces (to allow for the planting of shade trees) and sized a minimum of five feet in width. The project has been conditioned to include the half-diamond planters as well as new shrubs at the easterly (rear) property line along the west perimeter (the latter to shield traffic traveling on South Main Street from the adjacent parking lot headlights).
ENVIRONMENTAL ANALYSIS:
Per Section 15301 (Class 1 – Existing Facilities) of the State Guidelines for Implementing the California Environmental Quality Act (CEQA) and Section 3.21 of the City’s Local CEQA Guidelines, a Notice of Exemption has been prepared for the project because the project qualifies as a Class 1 (Existing Facilities) categorical exemption. The project involves minor exterior alterations on a site that is 1.37 acres and interior improvements to the inside of an existing building. A Notice of Exemption has been prepared and is attached herein as Exhibit
9. FISCAL IMPACT
The applicant has paid the applicable application processing fees for the project.
PUBLIC NOTICE AND COMMENTS
A 10-day public notice was mailed to all property owners within a 500-foot radius of the project site, advertised in the Sentinel Weekly News and posted at the project site.
As of the writing of this report, one item of correspondence has been received from the public and is included herein as Exhibit 8.
STAFF ANALYSIS
Conditional Use Permit CUP2023-0015 is a request to allow for the conversion of an existing single-family dwelling into a new religious facility (mosque), a permitted use within all residential zones with approval of a conditional use permit. In compliance with development standards enumerated within the R1-8.4 Zone, the project site can accommodate a new parking lot, trash enclosure, bioretention basin, interior remodel, and exterior façade enhancements. The operation of the mosque will be entirely contained inside the remodeled building and traffic is expected to be minimal during most prayer service times and spread throughout the day. No vehicular access will occur from Nanners Way, and Main Street is capable of supporting the traffic from the mosque, even during highest occupancy on Friday evenings and Sunday mornings.
The mosque meets the city’s siting criteria for religious facilities as the project site will have primary access from a major arterial street and will not have daily access from streets used by residential neighborhoods. Following the remodel of the residential dwelling, the architecture would still represent the appearance and scale of the existing building, and the religious facility would support Corona’s growing Muslim community. Based on the analysis herein, the Planning and Development Department accordingly recommends that the Planning and Housing Commission approve CUP2023-0015, based on the findings below and the recommended conditions of approval attached as Exhibit 6.
FINDINGS OF APPROVAL FOR CUP2023-0015
1. A preliminary environmental assessment has been conducted by the City of Corona and determined that the project does not require further environmental assessment as it qualifies for a Class 1 Categorical Exemption per Section 15301 of the State Guidelines for Implementing the California Environmental Quality Act (CEQA) and Section 3.28 of the City’s Local CEQA Guidelines. According to the State Guidelines, Class 1 categorical exemptions consist of the operation, repair, maintenance, permitting, leasing, licensing, or minor alteration of existing public or private structures, facilities, mechanical equipment, or topographical features involving negligible or no expansion of existing or former use. The project consists of interior alterations, minor exterior changes to an existing structure, and the use will be contained entirely inside the building. Therefore, there is no possibility that the project will have a significant effect on the environment.
2. All the conditions necessary for granting a Conditional Use Permit as set forth in Section
17.92.110 of the Corona Municipal Code do exist in reference to CUP2023-0015 for the following reasons:
a. CUP2023-0015 will not be detrimental to the public health, safety, convenience and general welfare, because the project site is capable of accommodating the onsite improvements associated with the religious facility. The project includes compliant onsite parking, with primary vehicular access provided from South Main Street and emergency access from Nanners
Way. Furthermore, the proposed scope of work has been reviewed by the Fire, Public Works, Police and Planning and Development Department, including therein, the Planning, Development Services and Building Divisions, and found to be in compliance with applicable development standards in the Corona Municipal Code.
b. CUP2023-0015 will not be detrimental to other existing and permitted uses in the area because the proposed use complies with the siting criteria in Section
17.92.040(B) of the CMC for religious facilities and the site plan demonstrates that parking, landscaping, water quality facilities, and trash facilities can be provided on the project site.
c. The project is subject to the Conditions of Approval enumerated in Exhibit 6, which are necessary and desirable for the purpose of protecting public health, safety, convenience, and general welfare of the public, in accordance with the intent and purpose of the City’s zoning regulations.
3. The proposal is consistent with the General Plan for the following reasons:
a. CUP2023-0015 is consistent with Land Use Element Goal LU-8: Assure the integrity, quality, and livability of Corona’s existing residential neighborhoods, preserving those elements that give them character, cohesion, and quality of life. CUP2023-0015 furthers this goal by allowing for the development of a religious facility that is compatible with the surrounding land uses to assure the quality and livability of Corona’s existing neighborhoods within the City. b. CUP2023-0015 is consistent with Land Use Element Policy LU-8.5: Promote development and enhancement of places that serve as the focal point of identity and activity in neighborhoods through the integration and, where feasible, consolidation of parks, schools, community facilities, religious facilities, and similar uses. CUP2023-0015 is consistent with this policy because it allows for the development of a religious facility that will serve as a focal point of identity and activity to the surrounding neighborhood and community.
PREPARED BY: BRENDAN DALDE, ASSISTANT PLANNER
REVIEWED BY: EVAN LANGAN, AICP, SENIOR PLANNER
REVIEWED BY: SANDRA VANIAN, PLANNING MANAGER
SUBMITTED BY: JOANNE COLETTA, PLANNING AND DEVELOPMENT DIRECTOR Exhibits:
1. Resolution No. 2661
2. Locational and Zoning Map
3. Project Plans (Site Plan, Floor Plan, Elevations)
4. Wall and Fence Plan
5. Conceptual Grading and Utility Plan
6. Conditions of Approval
7. Applicant’s letter, dated February 24, 2025
8. Public Correspondence
9. Environmental Documentation
Case Planner: Brendan Dalde (951) 736-2262
RESOLUTION NO. 2661
APPLICATION NUMBER: CUP2023-0015
A RESOLUTION OF THE PLANNING AND HOUSING
COMMISSION OF THE CITY OF CORONA,
CALIFORNIA, GRANTING A CONDITIONAL USE
PERMIT FOR THE ESTABLISHMENT OF A RELIGIOUS
FACILITY (MOSQUE) WITHIN AN EXISTING 4,330
SQUARE-FOOT RESIDENTIAL DWELLING, ON A 1.37-
ACRE PROPERTY, LOCATED AT 2460 SOUTH MAIN
STREET. (APPLICANT: ALI RAZA RIZVI
REPRESENTING THE SAJJADIA ISLAMIC SOCIETY
INC.)
WHEREAS, the application to the City of Corona, California, for a Conditional Use Permit under the provisions of Chapter 17.92 in the Corona Municipal Code, has been duly submitted to said City's Planning and Housing Commission for the establishment of a religious facility (mosque) within an existing 4,330 square-foot residential dwelling, on a 1.37-acre property, located at 2460 South Main Street; and
WHEREAS, the Planning and Housing Commission held a noticed public hearing for CUP2023-0015 on March 10, 2025, as required by law; and
WHEREAS, the Planning and Housing Commission finds that this project is exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301 of the State CEQA Guidelines and Section 3.28 of the City of Corona Local Guidelines for Implementing CEQA because there is no possibility that the activity may have a significant effect on the environment; and
WHEREAS, after close of said hearing, the Commission by formal action, found that all the conditions necessary to granting the Conditional Use Permit as set forth in Corona Municipal Code Section 17.92.110 do exist in reference to CUP2023-0015 based on the evidence presented to the Commission during said hearing; and
WHEREAS, the Planning and Housing Commission based its recommendation to approve CUP2023-0015 on certain conditions of approval and the findings set forth below.
RESOLUTION NO. 2661
APPLICATION NO. CUP2023-0015
PAGE | 2
NOW, THEREFORE, THE PLANNING AND HOUSING COMMISSION
OF THE CITY OF CORONA, CALIFORNIA, DOES ORDAIN AS FOLLOWS:
SECTION 1. CEQA Findings. As the decision-making body for this CUP2023- 0015, the Planning and Housing Commission has determined that this project does not require further environmental assessment because the project qualifies as an exemption under CEQA per Section 15301 of the State Guidelines and Section 3.28 of the City of Corona adopted Local Guidelines for implementing CEQA. There is no evidence presented to the city that the project will have any significant effects on the environment.
SECTION 2. Conditional Use Permit Findings. Pursuant to Corona Municipal Code (“CMC”) section 17.92.110 and based on the entire record before the Planning and Housing Commission, including all written and oral evidence presented to the Commission, the Commission hereby makes and adopts the following findings:
1. A preliminary environmental assessment has been conducted by the City of Corona and determined that the project does not require further environmental assessment as it qualifies for a Class 1 Categorical Exemption per Section 15301 of the State Guidelines for Implementing the California Environmental Quality Act (CEQA) and Section 3.28 of the City’s Local CEQA Guidelines. According to the State Guidelines, Class 1 categorical exemptions consist of the operation, repair, maintenance, permitting, leasing, licensing, or minor alteration of existing public or private structures, facilities, mechanical equipment, or topographical features involving negligible or no expansion of existing or former use. The project consists of interior alterations, minor exterior changes to an existing structure, and the use will be contained entirely inside the building.
Therefore, there is no possibility that the project will have a significant effect on the environment.
2. All the conditions necessary for granting a Conditional Use Permit as set forth in Section
17.92.110 of the Corona Municipal Code do exist in reference to CUP2023-0015 for the following reasons:
a. CUP2023-0015 will not be detrimental to the public health, safety, convenience and general welfare, because the project site is capable of accommodating the onsite improvements associated with the religious facility. The project includes compliant onsite parking, with primary vehicular access provided from South Main Street and emergency access from Nanners Way. Furthermore, the proposed scope of work has been reviewed by the Fire, Public Works, Police and Planning and Development Department, including therein, the Planning, Development Services and Building Divisions, and found to be in compliance with applicable development standards in the Corona Municipal Code. b. CUP2023-0015 will not be detrimental to other existing and permitted uses in the area because the proposed use complies with the siting criteria in Section
17.92.040(B) of the CMC for religious facilities and the site plan demonstrates
RESOLUTION NO. 2661
APPLICATION NO. CUP2023-0015
PAGE | 3
that parking, landscaping, water quality facilities, and trash facilities can be provided on the project site.
c. The project is subject to the Conditions of Approval enumerated in Exhibit 6, which are necessary and desirable for the purpose of protecting public health, safety, convenience, and general welfare of the public, in accordance with the intent and purpose of the City’s zoning regulations.
3. The proposal is consistent with the General Plan for the following reasons:
a. CUP2023-0015 is consistent with Land Use Element Goal LU-8: Assure the integrity, quality, and livability of Corona’s existing residential neighborhoods, preserving those elements that give them character, cohesion, and quality of life.
CUP2023-0015 furthers this goal by allowing for the development of a religious facility that is compatible with the surrounding land uses to assure the quality and livability of Corona’s existing neighborhoods within the City. b. CUP2023-0015 is consistent with Land Use Element Policy LU-8.5: Promote development and enhancement of places that serve as the focal point of identity and activity in neighborhoods through the integration and, where feasible, consolidation of parks, schools, community facilities, religious facilities, and similar uses. CUP2023-0015 is consistent with this policy because it allows for the development of a religious facility that will serve as a focal point of identity and activity to the surrounding neighborhood and community.
SECTION 3. Effective Date. CUP2023-0015 will not become effective until the City Council either takes no action on the report or otherwise makes a decision after a City Council initiated review.
BE IT FURTHER RESOLVED that a copy of this Resolution be delivered to the City Clerk of said City and a copy thereof be sent to the applicant therefore at the address of said applicant as set forth in the application for said Conditional Use Permit.
DN
13 2
8 9 8
28 OVERHANG
18 5.0
0' N
81°5
6'0
6"W
325.00'
N08°01'06"E
N08°01'06"E 299.80'
15 4.4
0' N
81°5
6'0
6"W
D
Y
H
DN
P.O.T
SOFT LANDSCAPE AREA
INFLOW TRAFFIC
OUTFLOW TRAFFIC
5' - 9 1/2"
12' - 2"
SIDE SETBACK REQ. IS 5 FT.
PROVIDED 5 FT.
SIDE SET BACK REQUIRED / LANDSCAPE
IS 5 FT.- PROVIDED 65FT-5 IN.
SIDE SETBACK REQ. IS 5 FT.
PROVIDED 5 FT.
NANNERS WAY
NANNERS WAY
MAIN STREET
65' - 5"
(E) FIRE HYDRANT
(N) PUBLIC FIRE HYDRANT(SUBJUCT
TO FIRE DEPT. APPROVAL)
FIRE TRUCK ENTRY GATE TO BE
EQUIPPED W/ KNOX BOX FOR FIRE
DEPT. THIS GATE TO USED ONLY BY
FIRE DEPT./ EMS
EXISTING
LANDSCAPE SHED
(N) MAN GATE W/
KNOX BOX FOR
FIRE DEPT.
(N) MAN GATE W/
KNOX BOX FOR
FIRE DEPT.
(N) PROPOSED
TRASH ENCLOSURE.
SEE CIVIL DRAWINGS
OCCUPANCY: A3
OCCUPANCY LOAD : 64
OCCUPANCY : A3
OCCUPANCY LOAD :105
OCCUPANCY B
OCCUPANCY
LOAD :5
ENT.
OCCUPANCY B
OCCUPANCY LOAD :6
MEN'S READING
ROOM.
LADIES READING
ROOM.
LADIES PRAYER
HALL
MEN'S PRAYER
HALL
LADIES TOILET
MEN'S TOILET
TOILET
OFFICE
BREAK ROOM
HALLWAY
ENT. HALL
HALLWAY HALLWAY STORE STORE
DN
RAMP
RAMP
DN DN
OCCUPANCY B
OCCUPANCY LOAD : 3
PARKING REQUIREMENT.
OCCUPANCY: A3
PRAYER HALLS AREA: 1,675 SFT.
PARKING REQUIRED 1,675 / 25 = 67
ACCESSIABLE PARKING REQUIRED = 3
PARKING TABULATION
REGULAR PARKING STALLS PROVIDED = 64
COMPACT PARKING STALL PROVIDED = 1
ACCESSIABLE PARKING PROVIDED = 3
_______________________________________
TOTAL PARKING STALLS PROVIDED = 68
BUILDING DATA
TYPE OF CONSTRUCTION = VB
PROPOSED SPRINKLER = S
PROPOSED OCCUPANCY: A3
EXISTING BUILDIND AREA: 4,330 SFT.
LOT AREA: 59867
GROSS OCCUPANT LOAD 184
ADDRESS: 2460 S MAIN STREET, CORONA,
CA 92881
LEGAL DESCRIPTION
APN -113310010
LOT NUMBER 10
PERMIT # B22-05590
NOTE:
THE PROPOSED REMODELED /RENOVATED EXISTING
STRUCTURE WILL BE SPRINKLERED ,AS SHOWN UNDER
BUILDING DATA.
PROPOSED BUILDING SETBACK ON THE EAST OF PROPERTY
(FACING MAIN ST. )IS 15 FEET , BUT DUE TO PARKING THE
LANDSCAPE SETBACK VARIES BETWEEN
NEW ELECTRIC AUTOMATIC GATE NOTES:
THE NEW ELECTRIC AUTOMATIC GATE WILL BE EQUIPPED
WITH TRANSPONDER SENSOR.
THE GATE WILL REMAIN OPEN DURING PRAYER SERVICES
OR ANY OTHER REGLIOUS GATHERING. WHEN THE MOSQUE
DOES NOT HAVE ANY EVENT /PR YER SERVICE THE GATE
WILL REMAIN CLOSED ,THE ATHOURISED PERSONAL WILL
HAVE THE TRANSPONDER CARDS TO OPERATE THE
ELECTRIC AUTOMATIC GATES.
18' - 7"
11' - 0"
TYP.
20' - 0" 25' - 0"
TYP.
18' - 0" R 3' - 0"
R 40' - 6"
6' - 7 1/2"
V.I.F.
24' - 4 1/2" ±
(N) ELECTRIC GATE TO BE
EQUIPPED W/ KNOX OVERIDE
SWITCH FOR FIRE DEPT.
(N) MAN GATE W/ KNOX BOX FOR
FIRE DEPT.
(N) ELECTRIC GATES TO BE
EQUIPPED W/ KNOX
OVERRIDE SWITCH FOR FIRE
DEPT.
EXIT
ENTRANCE
GARAGE
STORAGE
TYP.
20' - 0"
22' - 5"
19'-4".
25' - 0".
COMPACT
NO PARKING NEAR THE WATER BASINLETTER PROVIDED BY CIVIL ENGINEER SIDE LANDSCAPE SETBACK REQ. 5'
FRONT SETBACK / LANDSCAPE REQ. .
25' FT.- PROVIDED 42FT 3 3/4 IN.
45° TYP
25' - 0"
V.I.F.
14' - 9 1/4" ±
39' - 8" ±
45°TYP.
50'-00" F
R
O
M
M
E
DIA
N
R 75' - 10"
FRONT SETBACK PROVIIDED
42' - 3 3/4"
SETBACK REQUIRED
15' - 0"
OWNER:PROJECT NAME:PROJECT ADDRESS:
REVISIONS:
DESCRIPTION DATE
DATE ISSUED:
PROJECT NO:
SCALE:
SHEET NUMBER:
SHEET TITLE:
As indicated
SAJJADIA ISLAMIC SOCIETY
2460 S MAIN STREET, CORONA CA 92882
MOSQUE AT CORONA
03-08-2024
2023-927
A002
PROPOSED
REVISED SITE
PLAN
SITEPLAN LEGEND
SCALE
REVISED SITEPLAN - ACCESS 1/16" = 1'-0" 1
BUILDING SET BACKS
FRONT - NORTH OF PROPERTY
REQUIRED PROVIDED
25'-0" 42'- 3.75"
REMARKS
SIDE - WEST OF PROPERTY 5'-0" 5'- 0"
SIDE - SOUTH OF PROPERTY 5'-0" 5'- 0"
SIDE - NORTH WEST OF PROPERTY 5'-0" 65'- 5"
BACK - EAST OF PROPERTY 15'-0" '- VARIES
AN 0 0" 0'- 0" - 25'-0"
- 25'-0"
DN DN
DN
DN
DN
99 SF
OFFICE
213 SF
MEN's READING
ROOM
1043 SF
MEN'S PRAYER
HALL
282 SF
LADIES READING
ROOM
632 SF
LADIES PRAYER
HALL
211 SF
ENT. HALL
163 SF
HALL WAY
211 SF
LADIES TOILET
124 SF
HALL WAY
161 SF
MEN'S TOILET
JAINT.
433 SF
122 SF GARAGE
STORE
OCCUPANCY: A3
OCCUPANCY LOAD FACTOR: 10
OCCUPANCY LOAD :105
RAMP
6' - 9 1/4" 23' - 3"
6' - 0"
10' - 0 3/4" 33' - 0 3/4"
OCCUPANCY: A3
OCCUPANCY LOAD FACTOR: 10
OCCUPANCY LOAD : 64
22' - 8 1/4" 13' - 4 1/2" 33' - 0 3/4"
29' - 11 1/2"
RAMP
DN.
OCCUPANCY B
OCCUPANCY LOAD FACTOR: 50
OCCUPANCY LOAD :6
OCCUPANCY B
OCCUPANCY LOAD FACTOR: 50
OCCUPANCY LOAD :5
OCCUPANCY B
OCCUPANCY LOAD : 3
OCCUPANCY B
OCCUPANCY LOAD :1
OCC. B
OCC. LOAD :1
HVAC CLOSET
20 SF
STORE
SHOE RACK /
COAT CLOSET
58 SF
HALLWAY
RAMP
71 SF
TOILET
54 SF
STORE
67 SF
STORE
6' - 0"
DN.
232 SF
BREAK ROOM
A200
1 A203 1
A201
1 1 A202
6' - 0"
6' - 0"
V.I.F
69' - 2" ±
V.I.F
30' - 0 1/4" ±
V.I.F
43' - 1 1/2" ±
V.I.F
29' - 11 1/2" ±
V.I.F
17' - 7 1/2" ±
V.I.F
25' - 4 3/4" ±
V.I.F
30' - 0 3/4" ±
9' - 11" 20' - 1 1/2"
8' - 8"
1 2
1 4 1
4 12
10 4 4 2
11 6
8 5
10 10
10 10
10 9
10 10
7 7
1 1
9 9
10 10
FOR CHAIRS
FOR PRAYER MATS
FOR
SUPPLIES
F.F. : VCT/ PARGO FLOORING
F.F. : VCT/ PARGO FLOORING
F.F. : VCT/ PARGO FLOORING
F.F. : VCT/ PARGO FLOORING
F.F. : VCT/ PARGO FLOORING
F.F. : VCT/ PARGO
FLOORING
F.F. : CERMAIC
TILES
F.F. : CERMAIC TILES
F.F. : CERMAIC TILES
F.F. : CARPET
F.F. : CARPET
F.F. : VCT/ PARGO FLOORING
F.F. : VCT/ PARGO FLOORING
F.F. :CONC. FINISH
F.F. :CONC. FINISH
F.F. :CONC. FINISH
(E) 2X 5 1/2" EXTERIOR WALL TO REMAIN
(N) 2X 5 1/2" INTERIOR WALL
(N) 2X 4 1/2" INTERIOR WALL
(E) 2X 3 1/2" EXTERIOR WALL TO RAMAIN
F.F. FLOOR FINISH
1 (N) 6FT. WIDE FRAMED GLASS DOOR W/
SIDE GLASS PANELS-ACCESSIBLE DOOR
2 (N) ACCESSIBLE RAMP WITH RAILING
3 (N) 6FT. WIDE FRAMED GLASS
DOOR-ACCESSIBLE DOOR
4 (N) 3FT. WIDE FRAMED GLASS DOORACCESSIBLE DOOR
5 (N) LADIES ACCESSIBILE TOILET
6 (N) MEN ACCESSIBILE TOILET
7 (N) ABLUTION AREA
8 (N) ACCESSIBILE TOILET
9 (N) 3FT. WIDE ACCESSIBILE DOOR
10 (E) WINDOW
11 (N) 2 CAR GARAGE DOOR
12 (N) WINDOW
OWNER:PROJECT NAME:PROJECT ADDRESS:
REVISIONS:
DESCRIPTION DATE
DATE ISSUED:
PROJECT NO:
SCALE:
SHEET NUMBER:
SHEET TITLE:
As indicated
SAJJADIA ISLAMIC SOCIETY
2460 S MAIN STREET, CORONA CA 92882
MOSQUE AT CORONA
03-08-2024
2023-927
A101
PROPOSED
REMODELED
FLOOR PLAN
SCALE
PROPOSED FLOOR PLAN 3/16" = 1'-0" 1
12 12
12 WALL LEGEND
KEYNOTE LEGEND
V.I.F
10'-6" ±
V.I.F
6'-8" ±
V.I.F
10'-6" ±
V.I.F
6'-8" ±
V.I.F
17'-2"±
(E) CONC. ROOF TILES -TYP. (E) PAINTED WOODEN SIDINGS/
ATTIC VENT -TYP.
(E) PAINTED WOODEN SIDINGS/
ATTIC VENT -TYP.
(N) DOOR /WINDOW
(N) ADA ACCESS RAMP LANDING WITH
PIPE RAILING - TYP
(E) AWINDOW (E) AWINDOW (E) AWINDOW (E) AWINDOW
(E) PAINTED STUCCO PLASTER
FINISH-TYP
10' - 6"
OWNER:PROJECT NAME:PROJECT ADDRESS:
REVISIONS:
DESCRIPTION DATE
DATE ISSUED:
PROJECT NO:
SCALE:
SHEET NUMBER:
SHEET TITLE:
3/16" = 1'-0"
SAJJADIA ISLAMIC SOCIETY
2460 S MAIN STREET, CORONA CA 92882
MOSQUE AT CORONA
03-08-2024
2023-927
A200
RENOVATED
EXTERIOR
BUILDING EAST
ELEVATION
3/16" = 1'-0" 1
EAST ELEVATION
3/16" = 1'-0" 2
RENDERED EAST ELEVATION
V.I.F
10' - 6" ±
(E) CONC. ROOF TILES-TYP. (N) 3FT. WIDE FRAMED
GLASS DOORS -TYP.
(E) PAINTED WOODEN SIDING-TYP.
(N) ADA ACCESS RAMP LANDING WITH
PIPE RAILING - TYP
(E) WINDOW
(E) PAINTED STUCCO
PLASTER FINISH-TYP.
10' - 6"
OWNER:PROJECT NAME:PROJECT ADDRESS:
REVISIONS:
DESCRIPTION DATE
DATE ISSUED:
PROJECT NO:
SCALE:
SHEET NUMBER:
SHEET TITLE:
3/16" = 1'-0"
SAJJADIA ISLAMIC SOCIETY
2460 S MAIN STREET, CORONA CA 92882
MOSQUE AT CORONA
03-08-2024
2023-927
A201
RENOVATED
EXTERIOR
BUILDING WEST
ELEVATION
3/16" = 1'-0"
1 WEST ELEVATION
3/16" = 1'-0"
2 RENDERED WEST ELEVATION
V.I.F
10'-6" ±
(E) CONC. ROOF TILES-TYP. (N) WINDOW (N) 2 CAR GARAGE DOOR (E) PAINTED STUCCO PLASTER
FINISH-TYP
(E) WINDOW-TYP
10' - 6"
OWNER:PROJECT NAME:PROJECT ADDRESS:
REVISIONS:
DESCRIPTION DATE
DATE ISSUED:
PROJECT NO:
SCALE:
SHEET NUMBER:
SHEET TITLE:
3/16" = 1'-0"
SAJJADIA ISLAMIC SOCIETY
2460 S MAIN STREET, CORONA CA 92882
MOSQUE AT CORONA
03-08-2024
2023-927
A202
RENOVATED
EXTERIOR
BUILDING NORTH
ELEVATION
3/16" = 1'-0"
1 NORTH ELEVATION
3/16" = 1'-0"
2 RENDERED NORTH ELEVATION
V.I.F
10' - 6" ±
V.I.F
6' - 8" ±
(E) PAINTED WOODEN
SIDING-TYP
(E) PAINTED STUCCO PLASTER
FINISH-TYP
(E) CONC. ROOF TILES-TYP
(N) 3 FT. WIDE FRAMED
GLASS DOOR
(E)WINDOW
(N) LANDING W/ RAILING
10' - 6"
OWNER:PROJECT NAME:PROJECT ADDRESS:
REVISIONS:
DESCRIPTION DATE
DATE ISSUED:
PROJECT NO:
SCALE:
SHEET NUMBER:
SHEET TITLE:
3/16" = 1'-0"
SAJJADIA ISLAMIC SOCIETY
2460 S MAIN STREET, CORONA CA 92882
MOSQUE AT CORONA
03-08-2024
2023-927
A203
RENOVATED
EXTERIOR
BUILDING SOUTH
ELEVATION
3/16" = 1'-0"
1 SOUTH ELEVATION
3/16" = 1'-0"
2 RENDERED SOUTH ELEVATION
DN
13 2
8 9 8
28 OVERHANG
325.00'
N08°01'06"E
N08°01'06"E 299.80'
15 4.4
0' N
81°5
6'0
6"W
D
Y
H
DN
A204
2 5' - 9 1/2"
12' - 2"
EXISTING CHAINLINK FENCE
ON THE SOUTH SIDE.
BLONGS TO THE CHURCH -TO
REMAIN.
FRONT SET BACK REQUIRED IS 15 FT.-
PROVIDED 65FT-5 IN.
MAIN STREET
65' - 5"
(N) MAN GATE W/
KNOX BOX FOR
FIRE DEPT.
(N) PROPOSED
TRASH ENCLOSURE.
SEE CIVIL DRAWINGS
OCCUPANCY: A3
OCCUPANCY LOAD : 64
OCCUPANCY : A3
OCCUPANCY LOAD :105
OCCUPANCY B
OCCUPANCY
LOAD :5
ENT.
OCCUPANCY B
OCCUPANCY LOAD :6
MEN'S READING
ROOM.
LADIES READING
ROOM.
LADIES PRAYER
HALL
MEN'S PRAYER
HALL
LADIES TOILET
MEN'S TOILET
TOILET
OFFICE
BREAK ROOM
HALLWAY
ENT. HALL
HALLWAY HALLWAY STORE STORE
DN
RAMP
RAMP
DN DN
OCCUPANCY B
OCCUPANCY LOAD : 3
18' - 7"
11' - 0" 20' - 0" 25' - 0" 17' - 11 1/2" R 3' - 0"
R 40' - 6"
6' - 8"
V.I.F.
24' - 4 1/2" ±
(N) ELECTRIC GATE TO BE
EQUIPPED W/ KNOX OVERIDE
SWITCH FOR FIRE DEPT.
(N) MAN GATE W/ KNOX BOX FOR
FIRE DEPT.
(N) ELECTRIC GATES TO BE
EQUIPPED W/ KNOX
OVERRIDE SWITCH FOR FIRE
DEPT.
EXIT
ENTRANCE
GARAGE
STORAGE
39' - 7"
21' - 10 1/2" ± V.I.F.
EXISTING BLOCK MASONARY WALL ON THE NORTH & WEST
SIDE. BLONGS TO THE HOA -TO REMAIN.
PROPOSED NEW METAL
FENCE 6FEET HEIGHT ON
THE EAST SIDE.UNDER
SEPRATE PERMIT
5' - 0"
83' - 6 1/2" ± V.I.F. 3' - 9 3/4" 118' - 7" ± V.I.F. 57' - 9" ± V.I.F.
NO PARKING NEAR THE WATER BASINLETTER PROVIDED BY CIVIL ENGINEER TYP.
8' - 0"
118' - 7" ± V.I.F.
± V.I.F.
83' - 6 1/2" ± V.I.F. 3' - 9 3/4" 57'-9"± V.I.F.
V.I.F.
5' - 0" ±
CL CL CL
CL CL
CL CL
CL CL
CL
METAL MAN GATE
OWNER:PROJECT NAME:PROJECT ADDRESS:
REVISIONS:
DESCRIPTION DATE
DATE ISSUED:
PROJECT NO:
SCALE:
SHEET NUMBER:
SHEET TITLE:
1/16" = 1'-0"
SAJJADIA ISLAMIC SOCIETY
2460 S MAIN STREET, CORONA CA 92882
MOSQUE AT CORONA
03-08-2024
2023-927
A204
BOUNDRY WALL /
PROPOSED METAL
FENCE & METAL
ELECTRIC GATES
1/16" = 1'-0" 1
REVISED SITEPLAN - PROPOSED
FENCEING
1/16" = 1'-0" 2
NEW METAL FENCE ELVATION
EXISTING CHAINLINK FENCE ON THE SOUTH
SIDE. BLONGS TO THE CHURCH -TO REMAIN.
EXISTING BLOCK MASONARY WALL ON THE
NORTH & WEST SIDE. BLONGS TO THE HOA -TO
REMAIN.
NOTE:
PROPOSED DESIGN OF METAL FENCE & METAL ELECTRIC GATE-DESIGN. TO BE UNDER SEPRATE PERMIT
Details: CUP2023-0015: Conditional Use Permit to allow for the establishment of a religious facility (mosque) within an existing, 4,330 square-foot residential dwelling, to be remodeled to accommodate the new use, on one lot located on the west side of South Main Street and south of Nanners Way at 2460 South Main Street. (Applicant: Ali Raza Rizvi, 8685 Orchard Park Drive, Riverside, CA 92508)
LIST OF CONDITIONS
DEPARTMENT CONTACT
BUILDING Anthony Hurley
1. A complete building code analysis for the project will be required due to the change of occupancy.
2. Access, sanitary facilities, and parking shall comply with Title 24 Handicap Requirements.
3. Construction activity shall not occur between the hours of 8:00 pm to 7:00 am, Monday thru Saturday and 6:00 pm to 10:00 am on Sundays and Federal Holidays.
4. Roofing material shall be Class A.
5. Provide occupancy separation(s) in the building(s) in accordance with CBC Chapter 5.
6. Project plans can be submitted electronically online. If hard copy plans are submitted for plan review, the applicant shall submit five (5) complete sets of plans including the following - * Plot Plan * Foundation Plan * Floor Plan * Ceiling and roof framing plan * Electrical Plans (electrical service shall be underground per Corona Municipal Code Section 15.06), including size of main switch, number and size of service entrance conductors, circuit schedule and demand load. * Plumbing and sewer plan, isometric, including underground diagram, water piping diagram, sewer or septic tank location, fixture units, gas piping and vents, heating and air conditioning diagram. * Landscape and Irrigation plans; Submit four (4) complete sets detached from building plans. Landscape Maintenance District plans shall be submitted directly to the Planning and Development Department, Development Services Division. Landscape plans shall be approved prior to the issuance of any Building Permits.
If hard copy plans are submitted for plan review, the applicant shall submit two (2) sets of structural calculations, energy conservation calculations and soils reports. Architects/Engineers stamp and wet signature is required prior to submittal of plan check.
7. Upon tenant improvement plan check submittal there may be additional Building Department requirements.
8. Separate permits are required for all fences, walls, signs, and PV systems.
9. Comply with the Corona Burglary Ordinance contained in CMC chapter 15.52. Copies are available at the Building Division counter or online at www.CoronaCA.gov/Building.
10. All contractors must show proof of State and City licenses, and workmen's compensation insurance to the City prior to the issuance of permits.
11. Buildings shall not be occupied prior to posting of Certificate of Occupancy issued by the Building Division.
12. An approved Construction Waste Management Plan and Recycling Worksheets shall be kept on site and maintained by the applicant, and made available for inspection by City representatives at all times in accordance with the California Green Building Standards Code. Documentation which demonstrates compliance with the minimum recycling of waste materials required by CAL Green shall be provided to the building inspector prior to issuance of Certificate of Occupancy or Final Approval.
Project Number: CUP2023-0015
Applied: 5/15/2023 Approved: 3/10/2025
Closed: Expired:
Status: APPROVED
Parent Project:
Site Address: 2460 S MAIN ST CORONA, CA 92882
Ali Raza
8685 Orchard Park Dr Riverside Ca, 92508
Description:
Applicant:
CUP2023-0015 1 of 7 (Continued on next page)
Project Conditions
City of Corona
BUILDING Anthony Hurley
13. Trash and recycling enclosures shall be accessible per CBC chapter 11B and meet the standards of the City's waste hauler (Waste Management). Provide enlarged plans and details for construction of trash/recycling enclosures.
14. All fees, including but not limited to, occupancy fees, property development tax, and school fees must be paid in full prior to issuance of building permits. Any development impact fees that apply to the project must be paid in full prior to NIC or CofO issuance.
15. Trash enclosure shall be located on a code-compliant accessible path of travel for employees.
16. Provide minimum sized solar PV and battery energy storage system per the California Energy Code. A separate permit is required
17. Utilities shall meet the utility authority's service requirements. Applicant shall coordinate the utility locations and design with the respective utility provider.
18. The on-site electrical service feeding the building shall be underground per CMC chapter 15.60.
19. Project shall be designed to conform to the applicable edition of the California Building Standards Code including local amendments, and the Corona Municipal Code.
20. A pre-construction meeting is required with the building inspector assigned to the project. You may schedule a pre-con meeting by calling 951-736-2250 or emailing [email protected].
21. All deferred features and related permits shall be approved, and the building not be occupied, prior to issuance of CofO.
Utilities will not be released until a CofO, TCO, or Temporary Utility Bond has been issued.
22. Project site shall be kept clean, secure, safe, and BMPs installed and maintained, and follow all city, state, and county requirements and due standard of care.
23. The applicant shall design the project to show compliance with the latest adopted edition of the following codes as applicable:
A. California Building Code
B. California Residential Code
C. California Electrical Code
D. California Mechanical Code
E. California Plumbing Code
F. California Energy Code
G. California Fire Code
H. California Green Building Standards Code
24. Project entitlement approvals shall be obtained prior to plan approval and issuance of Building permits. Final Conditions of Approval shall be made part of set of plans [Conditions of approval shall be pasted on plans]
25. Project plans shall show a parking summary to include the following:
a) Number of parking spaces required/provided.
b) Handicap parking spaces required/provided. (CBC 11A or 11B) c) Number of van accessible parking spaces required/provided. d) Number of EV and EVCS parking spaces required/provided. (CGBSC, sect. 5.106.5.3) e) Bicycle parking facilities required/provided. (CGBSC, sect. 5.106.4) FIRE Xente Baker
1. Show two (2) all weather surface access ways to be approved by the Fire Marshal and construct the access way(s) to accommodate 70,000 lbs. gross vehicle weight during all phases of construction.
2. Meet with Corona Fire Department to determine locations of red curbing and signage by fire hydrants, fire department connections, and designated fire lanes on site.
3. A minimum fire flow of 3000 gallons per minute at 20 psi shall be provided for commercial structures.
4. Provide a code analysis that justifies the change of occupancy, provide at a minimum but not limited to, construction type, allowable area and height, occupancy classification, occupant load etc.
CUP2023-0015 2 of 7 (Continued on next page)
Project Conditions
City of Corona
FIRE Xente Baker
5. A specific address, assigned by the City of Corona, Public Works Department, shall be provided for each building as specified by the fire department address standard which can be obtained at coronaca.gov/fire. Addresses must be illuminated during all hours of darkness.
6. Required fire code permits will be applied for and processed prior to final inspection and/or certificate of occupancy, Fire code permit application and all other guidelines are available at coronaca.gov.
7. Make application for and obtain Occupancy Classification change from the Building Division.
PLANNING
1. To the fullest extent permitted by law, the applicant shall defend, indemnify and hold the City of Corona and its directors, officials, officers, employees, volunteers and agents free and harmless from any and all claims, demands, causes of action, proceedings, costs, expenses, liabilities, losses, damages or injuries of any kind, in law or equity, in any manner arising out of, pertaining to, or incident to any attack against or attempt to challenge, set aside, void or annul any approval, decision or other action of the City of Corona, whether such approval, decision or other action was by its City Council, Planning and Housing Commission or other board, director, official, officer, employee, volunteer or agent. To the extent that Government Code Section 66474.9 applies, the City will promptly notify the applicant of any claim, action or proceeding made known to the City to which Government Code Section 66474.9 applies and the City will fully cooperate in the defense. The Applicant's obligations hereunder shall include, without limitation, the payment of any and all damages, consultant and expert fees, and attorney's fees and other related costs and expenses. The City shall have the right to retain such legal counsel as the City deems necessary and appropriate.
2. Nothing herein shall be construed to require City to defend any attack against or attempt to challenge, set aside, void or annul any such City approval, decision or other action. If at any time Applicant chooses not to defend (or continue to defend) any attack against or attempt to challenge, set aside, void or annul any such City approval, decision or other action, the City may choose, in its sole discretion, to defend or not defend any such action. In the event that the City decides not to defend or continue the defense, Applicant shall be obligated to reimburse City for any and all costs, fees, penalties or damages associated with dismissing the action or proceeding. If at any time both the Applicant and the City choose not to defend (or continue to defend) any action noted herein, all subject City approvals, decisions or other actions shall be null and void. The Applicant shall be required to enter into any reimbursement agreement deemed necessary by the City to effectuate the terms of this condition.
3. Any change in the hours of operation by the religious facility shall be disclosed in writing to the Planning and Development Department and is subject to the review and approval by the Planning and Development Director.
4. All signage shall be constructed in accordance with the signage standards established by the Corona Municipal Code (CMC) Chapter 17.74.
5. This permit hereby allowed is conditional upon the privileges being utilized by the securing of the first permit thereof, or compliance with all conditions on the granting of this conditional use permit within two (2) years after the effective date thereof, and if they are not utilized, or construction work is not begun within said time and carried on diligently to completion, this authorization shall become void, and any privilege or permit granted shall be deemed to have lapsed.
6. The project shall comply with all applicable requirements of the CMC and ordinances, if any, including the payment of all required fees.
7. Separate landscape plans shall be submitted at the time of building plan check and shall be approved prior to the issuance of a building permit. At time of plan check submittal, the applicant shall submit a landscape deposit in the amount of $5,000 directly to the Planning Division to cover third-party landscape plan check and inspection fees. Any amount left remaining from the deposit will be returned to the developer upon project completion.
8. Prior to issuance of a Certificate of Occupancy, the project's on-site landscaping and irrigation shall be installed according to the project's approved landscape plans
9. The trash enclosure shall be consistent with CMC Chapter 17.78. The trash enclosure shall be constructed of decorative block with solid metal gates and covered with a solid or lattice cover painted to match the religious facility's color scheme. All gaps between the block enclosure and cover shall be secured with a durable metal mesh material or similar.
10. The conditional use permit (CUP) is only associated with the approval of a religious facility. Any future building, expansion, or intensification will require the applicant to submit a CUP modification application to the Planning Division for review.
CUP2023-0015 3 of 7 (Continued on next page)
Project Conditions
City of Corona
PLANNING
11. The applicant shall provide parking lot half-diamond shaped landscape planters along the west parking row at a ratio of one per every six parking spaces. The planters shall be a minimum of five (5) feet in width including six-inch curbs (4 feet of plantable area) and shall contain a shade tree.
12. The applicant shall submit a separate fence and wall plan for all perimeter fences and walls for plan check and permits.
13. The applicant's landscape plan shall include a dense-type shrub along the exterior side of the easterly parking area for headlight buffering. The shrubs shall be a minimum of 3 feet in height at the time of installation.
14. A 6 P.C.C. curb is required around all planter areas.
15. The use of live turf is prohibited except in areas dedicated for recreational or functional needs such as bioretention basins. In lieu of live turf, the project may install groundcover, shrubs, trees, or other landscape materials as allowed by CMC Chapter
17.70. 16. The drive aisle extending west from the northerly driveway on Main Street shall be designed as a through-access connecting to the back drive aisle to allow for left turns to prevent possible vehicular stacking on Main Street from this driveway. [ADDED BY THE PLANNING AND HOUSING COMMISSION ON MARCH 10, 2025]
17. At no time shall there be any outdoor audible speakers or amplifying device. [ADDED BY THE PLANNING AND HOUSING COMMISSION ON MARCH 10, 2025]
18. Applicant shall notify congregants that parking and access on any residential street including Nanners Way is prohibited. [ADDED BY THE PLANNING AND HOUSING COMMISSION ON MARCH 10, 2025]
PUBLIC WORKS
1. The Public Works, Planning and Development, and Utilities Department comments for the subject application shall be completed at no cost to any government agency. All questions regarding the intent of the comments shall be referred to the Planning and Development Department, Development Services Division. Should a conflict arise between City of Corona standards and design criteria and any other standards and design criteria, City of Corona standards and design criteria shall prevail.
2. The developer shall comply with the State of California Subdivision Map Act and all applicable City ordinances and resolutions.
3. Prior to issuance of grading permit, the applicant shall demonstrate to the satisfaction of the City Engineer that the proposed project will not unreasonably interfere with the use of any easement holder of the property.
4. All improvement and grading plans shall be drawn on twenty-four (24) inch by thirty-six (36) inch Mylar and signed by a registered civil engineer or other registered/licensed professional as required.
5. The submitted site plan shall correctly show all existing easements, traveled ways, and drainage courses. Any omission or misrepresentation of these documents may require said site plan to be resubmitted for further consideration.
6. In the event that off-site right-of-way or easements are required for the City of Corona master plan facilities to comply with these conditions of approval, the developer is required to secure such right-of-way or easements at no cost to the City.
7. All existing and new utilities adjacent to and on-site shall be placed underground in accordance with City of Corona ordinances.
8. Prior to issuance of a Certificate of Occupancy, the developer shall cause the engineer of record to submit project base line work for all layers in AutoCAD DXF format on Compact Disc (CD) to the Development Services Division. If the required files are unavailable, the developer shall pay a scanning fee to cover the cost of scanning the as-built plans.
CUP2023-0015 4 of 7 (Continued on next page)
Project Conditions
City of Corona
PUBLIC WORKS
9. The developer shall monitor, supervise and control all construction and construction related activities to prevent them from causing a public nuisance including, but not limited to, insuring strict adherence to the following: a) Removal of dirt, debris or other construction material deposited on any public street no later than the end of each working day. (b) Construction operations, including building related activities and deliveries, shall be restricted to Monday through Saturday from 7:00 a.m. to 8:00 p.m., excluding holidays, and from 10:00 a.m. to 6:00 p.m. on Sundays and holidays, in accordance with City Municipal Code 15.04.060, unless otherwise extended or shortened by the Public Works Director or Building Official. (c) The construction site shall accommodate the parking of all motor vehicles used by persons working at or providing deliveries to the site. Violation of any condition or restriction or prohibition set forth in these conditions shall subject the owner, applicant, developer or contractor(s) to remedies as noted in the City Municipal Code. In addition, the City Engineer or Building Official may suspend all construction related activities for violation of any condition, restriction or prohibition set forth in these conditions until such time as it has been determined that all operations and activities are in conformance with these conditions.
10. Prior to issuance of a building permit, the developer shall finish the construction or post security guaranteeing the construction of all public improvements, as applicable. Said improvements shall include, but are not limited to, the following: a) All street facilities.
b) All drainage facilities.
c) All required grading, including erosion control.
d) All required sewer, water and reclaimed water facilities. e) All required landscaping.
f) All under grounding of overhead utilities, except for cables greater than 32k volts.
11. All the grading design criteria shall be per City of Corona standards, Corona Municipal Code Title 15 Chapter 15.36 and City Council Ordinance Number 2568, unless otherwise approved by the City Engineer.
12. Prior to approval of grading plans, the applicant shall submit two (2) copies of a soils and geologic report prepared by a Registered Engineer to the Planning and Development Department, Development Services Division. The report shall address the soil's stability and geological conditions of the site. If applicable, the report shall also address: deep seated and surficial stability of existing natural slopes; modified natural slopes which are subject to fuel zones; manufactured slopes and stability along proposed daylight lines; minimum required setbacks from structures; locations and length of proposed bench drains, sub-drains or french drains; and any other applicable data necessary to adequately analyze the proposed development.
13. Prior to approval of grading plans, erosion control plans and notes shall be submitted and approved by the Planning and Development Department, Development Services Division.
14. Prior to approval of grading plans, the applicant shall obtain a General Construction Activity Storm Water Permit from the State Water Resources Control Board in compliance with National Pollutant Discharge Elimination System (NPDES) requirements.
Proof of filing a Notice of Intent (NOI) will be required by the City. The WDID # shall be displayed on the title sheet of the grading plans.
15. Prior to approval of grading plans, the applicant shall comply with the Federal Clean Water Act and shall prepare a Storm Water Pollution Prevention Plan (SWPPP). The SWPPP shall be available at the project site for review.
16. Prior to the issuance of a grading permit the developer shall submit recorded slope easements or written letters of permission from adjacent landowners in all areas where grading is proposed to take place outside of the project boundaries.
17. Prior to release of grading security, the developer shall cause the civil engineer of record for the approved grading plans to submit a set of as-built grading plans with respect to Water Quality Control facilities.
18. All City of Corona NPDES permit requirements for NPDES and Water Quality Management Plans (WQMP) shall be met per Corona Municipal Code Title 13 Chapter 13.27 and City Council Ordinance Numbers 2291 and 2828 unless otherwise approved by the City Engineer.
19. Prior to the issuance of a grading permit, a Final WQMP, prepared in substantial conformance with the approved Preliminary WQMP, shall be submitted to the Planning and Development Department, Development Services Division for approval. Upon its final approval, the applicant shall submit one copy on a CD-ROM in PDF format.
20. Prior to the issuance of the first Certificate of Occupancy, the applicant shall record Covenants, Conditions and Restrictions (CC&R's) or enter into an acceptable maintenance agreement with the City to inform future property owners to implement the approved WQMP.
CUP2023-0015 5 of 7 (Continued on next page)
Project Conditions
City of Corona