DATE: 05/07/2024
TO: Honorable Mayor and City Council Members
Honorable President and Board Members
FROM: Public Works Department & Utilities Department
2025-181
REQUEST FOR CITY COUNCIL AND
CORONA UTILITY AUTHORITY ACTION
SUBJECT:
CONSTRUCTION CONTRACT WITH FERREIRA CONSTRUCTION CO, INC. DBA FERREIRA COASTAL CONSTRUCTION IN THE AMOUNT OF $369,672 FOR THE GALLOWAY SEWER LANE EXTENSION PROJECT NO.2021-04; NOTICE INVITING BIDS 25-041CA
EXECUTIVE SUMMARY:
This staff report asks for the City Council to approve the construction contract with Ferreira Construction Co, Inc. DBA Ferreira Coastal Construction. The project encompasses installing 313 lineal feet of new sewer main along Galloway Lane between Inverness Drive and Howe Street. In addition, this project will also install two sewer manholes and four sewer laterals for future connections.
RECOMMENDED ACTION:
That the City Council:
a. Adopt the Plans and Specifications for the Galloway Lane Sewer Extension, Project No. 2021-04, Notice Inviting Bids 25-041CA.
b. Award Notice Inviting Bids 25-041CA to Ferreira Construction Co, Inc. DBA Ferreira Coastal Construction, the lowest responsive, responsible bidder, for the total bid amount of $369,672 and waive any and all minor irregularities in the bidding documents as submitted by said bidder.
c. Approve the Construction Contract with Ferreira Construction Co, Inc. DBA Ferreira Coastal Construction for the Galloway Sewer Lane Extension Project, Project No. 2021-04 in the amount of $369,672.
d. Authorize the City Manager, or his designee, to execute the Construction Contract with Ferreira Construction Co, Inc. DBA Ferreira Coastal Construction, in the amount of $369,672, including any non-substantive extensions, change orders, purchase orders, and amendments up to 10% of total contract cost or $36,967 as authorized in 3.08.050(H).
That the Corona Utility Authority review, ratify, and to the extent necessary, direct the City Council to take the above actions.
BACKGROUND & HISTORY:
The City Council adopted Resolution No. 2020-112 on August 5, 2020, establishing the Capital Improvement Project, Galloway Lane Sewer Extension Project, to extend the public sewage main 313 linear feet on Galloway Lane. In addition, it established the proportionate fair share cost agreement for cost recovery from the five (5) benefited parcels on Galloway Lane.
Mr. Adamson purchased the existing single-family home at 1764 Galloway Lane, and shortly thereafter, the existing septic system on the property began to fail. In accordance with Corona Municipal Code Section 13.12.060, the property owner was not permitted to reconstruct the failed septic system since the existing public sewer line was within two hundred feet of the property. Therefore, Mr. Adamson was required to connect to the public sewer system. Corona Municipal Code section 13.12.100, requires that prior to connecting to the City’s sewer collection system, the person requesting such connection pay a construction charge to cover the proportionate cost of constructing the public sewer in the amount, manner, and time of payment established by resolution of the City Council.
Resolution 2020-112, approved by City Council on August 5, 2020, established the Capital Improvement Project titled Galloway Lane Sewer Extension Project to extend the public sewer main approximately 313 lineal feet on Galloway Lane from the existing terminal manhole just east of 1764 Galloway Lane, up to Howe Street, to connect the private property located at 1764 Galloway Lane, to serve the four (4) additional properties in the same vicinity in the future, and established construction charges to cover the proportionate share for such project for all benefitted parcels.
To coincide with the State and County’s legislation and regulations to protect groundwater quality and public health, it is the goal of the City of Corona Utilities Department to eventually provide all existing homes currently on septic systems with a public sewage system.
ANALYSIS:
City staff completed, reviewed, and approved the plans and Specifications for the Galloway Lane Sewer Extension Project. As specified in the bid package, the City shall award the contract for the project to the lowest responsive, responsible bidder, as determined from the lowest total for the Bid Schedule.
This Project was advertised for bids on February 6, 2025, pursuant to Corona Municipal Code Section 3.08.090, the State's Public Projects – Formal Bidding Procedure and Public Contract Code requirements to fifteen (15) pre-qualified contractors. On March 13, 2025, five (5) bids were received through the PlanetBids bidding service.
The following is a summary of the bid results and the Engineer's Estimate:
Contractor Location Bid Schedule
Amount
Engineer’s Estimate $400,000
1 Ferreira Construction Co, Inc.
DBA Ferreira Coastal
Construction
Rancho Cucamonga, CA $369,672
2 Augustine General
Engineering, Inc.
Alta Loma, CA $460,726
3 MNR Construction, Inc. La Verne, CA $497,490
4 Norstar Plumbing &
Engineering, Inc.
Alta Loma, CA $569,118
5 T.E. Roberts, Inc. Irvine, CA $689,538
Staff reviewed all bids received and recommends awarding the contract based on the Bid Schedule to Ferreira Construction Co, Inc., DBA Ferreira Coastal Construction, as the lowest responsive, responsible bidder, for a total contract amount of $369,672. City staff has reviewed and verified all licenses and references for Ferreira Construction Co., Inc., DBA Ferreira Coastal Construction, and all other documentation is in order.
City staff will perform the construction contract administration, and a contract consultant will perform inspection services. Should the City Council award the contract as recommended, construction is tentatively scheduled to commence in June, with completion anticipated before the end of summer 2025.
FINANCIAL IMPACT:
Funding for the recommended actions and support services in the amount of $462,090 is available in the Galloway Lane Sewer Extension Capital Improvement Project No. UT2020-02 within the Sewer Capacity Fund 440.
The estimated construction cost for this project is outlined as follows:
Construction
………………………………………………………………………………………… $369,672
Construction Support Services (15%) ………….…………………………………………….. $55,451
Construction Contract Change Orders (10%) …………………………………………….. $36,967
Total Construction Cost
……………………………………………………………………….… $462,090
ENVIRONMENTAL ANALYSIS:
This action is categorically exempt pursuant to Section 15061(b)(3) of the Guidelines for the California Environmental Quality Action (CEQA), which states that a project is exempt from CEQA if the activity is covered by the commonsense rule that CEQA applies only to projects that have the potential for causing significant effect on the environment. Where it can be seen with certainty that there is no possibility that the activity in question may have a significant effect on the environment, the activity is not subject to CEQA. This action is also exempt pursuant to Section 15303(d), which provides that the construction of water main, sewage, electrical, gas, and other utility extensions of reasonable length to serve an adjacent single-family residence are exempt from CEQA.
PREPARED BY: KEVIN HANNA, ASSISTANT PROJECT MANAGER
REVIEWED BY: SAVAT KHAMPHOU, PUBLIC WORKS DIRECTOR & TOM MOODY,
DIRECTOR OF UTILITIES