Project Engineer
Design Engineer II
Design Engineer I
Project Surveyor
Surveyor
Survey Technician
2 Person Field Crew
LAUD Division Manager
LAUD Project Manager
Landscape Designer II
Landscape Designer I
FEHR & PEERS
$162 $139 $113 $177 $129 $97 $328 $253 $239 $114 $92
2.0 RESEARCH EXISTING CONDITIONS2.6 Additional Supplemental Survey 2 6 10 16 34 $7,346 $7,346 Subtotal Phase 2 0 0 0 2 6 10 16 0 0 0 0 34 $7,346 $0 $7,346
5.0 FINAL ENGINEERING/CONSTRUCTION CONTRACT DOCUMENTS5.1 AM#1 60% PS&E Additional Plan Production 32 100 180 1 4 8 80 405 $48,905 - $48,905
5.2 AM#1 90% PS&E Additional Plan Production 5 46 32 1 32 60 56 232 $30,713 - $30,713
5.3 AM#1 100% PS&E Additional Plan Production 2 10 20 1 4 8 16 61 $7,567 - $7,567
5.4 AM#1 Final PS&E Additional Plan Production 1 4 8 1 2 4 8 28 $3,545 - $3,545 Subtotal Phase 5 40 160 240 0 0 0 0 4 42 80 160 726 $90,730 $0 $90,730
6.0 BIDDING SERVICES 6.1 AM#1 Additional Bidding Phase Support 2 2 2 2 8 $1,308 $500 $1,808 Subtotal Phase 6 2 2 0 0 0 0 0 0 2 2 0 8 $1,308 $500 $1,808
7.0 ENGINEERING CONSTRUCTION SERVICES 7.4 AM#1 Additional Record Drawings 2 4 2 8 8 24 $4,210 $1,500 $5,710 Subtotal Phase 7 2 4 0 0 0 0 0 2 8 8 0 24 $4,210 $1,500 $5,710 TOTAL HOURS 44 166 240 2 6 10 16 6 52 90 160 792OTHER DIRECT COSTS $0 $0 $0TOTAL COST $7,128 $23,074 $27,120 $354 $774 $970 $5,248 $1,518 $12,428 $10,260 $14,720 $103,594 $2,000 $105,594 COST PROPOSAL FOR PROJECT SCOPE: Corona- Ontario Avenue Widening at Lincoln Avenue PO No. P23003 Subconsultants
TOTAL COST Total
Hours
Total MT
Cost
Please note that the rates shown are for estimating purposes only. See rate schedule for actual rates/ranges. 7/18/2025