Cities Index.
2. Final Cost Summary

Costa Mesa City Council
March 4, 2025

Document
2. Final Cost Summary
Meeting
March 4, 2025
Body
Costa Mesa City Council
Original file
692 KB
Text extracted from the city's file for reading and search. Open the original on costamesa.legistar1.com. That file is the official record.

Contractor: All American Asphalt
400 E. 6th Street, Corona CA
Project: Adams Avenue Rehabilitation Project
City Project No. 23-07

ITEM UNIT PREVIOUS QUANTITY TOTAL QUANTITY PREVIOUS AMOUNT TOTAL CONTRACT

NO DESCRIPTION PRICE QUANTIT Y THIS ESTIMATE TO DATE AMOUNT THIS EST TO DATE PRICE

BASE BID
1 1 LS Mobilization (5% Maximum) $103,537.90 90.00 % 10.00 % 100.00 % $93,184.11 $10,353.79 $103,537.90 $103,537.90 2 1 LS Water Qualit y Best Management Practices $30,621.25 90.00 % 10.00 % 100.00 % $27,559.13 $3,062.13 $30,621.26 $30,621.25 31 L S Traffic & Pedestrian Control, Construction Phasing, Public Convenience & Safety $91,233.00 90.00 % 10.00 % 100.00 % $82,109.70 $9,123.30 $91,233.00 $91,233.00 41 L S Traffic Signing, Thermoplastic Striping, Markings, RPM's & Curb Paintin
g $150,500.00 20.00 % 80.00 % 100.00 % $30,100.00 $120,400.00 $150,500.00 $150,500.00 5 5 EA Reset Existin g Survey Monument and Ties $1,116.75 0.00 EA 0.00 EA 0.00 EA $0.00 $0.00 $0.00 $5,583.75 6 612,810 SF
Cold Mill Ex. Pavement 2.5" per Typical Sections, Plans & Detail A-1 on Sheet 2 of Plans & Crack Seal (crack seal operation delited from the contract
)
$0.43 582,400.00 SF 0.00 SF 582,400.00 SF $250,432.00 $0.00 $250,432.00 $263,508.30 7 1,980 TON Asphalt Concrete (AC) Level Course (Type C2 PG 70-10-RAP) (10% Max. RAP) (0.5” Max. per Typical Sections) $134.25 2,726.06 TON 0.00 TON 2,726.06 TON $365,973.56 $0.00 $365,973.56 $265,815.00 8 8,140 TON Asphalt Rubber Hot Mix (ARHM-GG-C PG 64-16) Surface Course
(2” per Typical Sections) $140.00 6,872.81 TON 0.00 TON 6,872.81 TON $962,193.40 $0.00 $962,193.40 $1,139,600.00 9 2,255 SF
Sawcut & Remove Ex. and Construct 10” Dense Graded Asphalt Concrete (DGAC) Pavement (Type B PG 70-10-RAP) (Max. 10% RAP) over Native (95% Relative Compaction) per Detail A-2 on Sheet 2 of Plans, as directed by the Engineer
$13.00 2,033.00 SF 0.00 SF 2,033.00 SF $26,429.00 $0.00 $26,429.00 $29,315.00 10 32 EA
Adjust Water Valve Can & Cover to Grade $1,048.50 0.00 EA 31.00 EA 31.00 EA $0.00 $32,503.50 $32,503.50 $33,552.00 11 26 EA Adjust Manhole Frame & Cover to Grade $1,398.00 0.00 EA 23.00 EA 23.00 EA $0.00 $32,154.00 $32,154.00 $36,348.00 12 4E A Adjust Storm Drain Manhole Frame & Cover to Grade $1,398.00 0.00 EA 6.00 EA 6.00 EA $0.00 $8,388.00 $8,388.00 $5,592.00 13 4E A Adjust Well Monument Can & Cover to Grade $2,058.00 0.00 EA 3.00 EA 3.00 EA $0.00 $6,174.00 $6,174.00 $8,232.00 14 6,270 SF Taper Cold Mill Existing AC Pavement (2" Max.) per Detail A-1 on Sheet 2 & T
ypical Sections (Royal Palm Drive) $0.60 6,324.00 SF 0.00 SF 6,324.00 SF $3,794.40 $0.00 $3,794.40 $3,762.00 15 1 LS
Sawcut & Remove Ex. Structural Section, PCC & Miscellaneous Improvements (Thickness per Typical Section), Prepare
Sub
grade, Place, Grade and Compact Fill
$12,387.75 100.00 % 0.00 % 100.00 % $12,387.75 $0.00 $12,387.75 $12,387.75 16 62 LF Construct 8” (Min.) PCC Curb over 6” CMB per City Standard Dwg. No. 311, Type A (Modified Variable Curb Face) $223.50 62.00 LF 0.00 LF 62.00 LF $13,857.00 $0.00 $13,857.00 $13,857.00 17 131 SF Construct AC Slot Pavin
g per Detail A-3 on Sheet 2 of Plans $26.00 0.00 SF 131.00 SF 131.00 SF $0.00 $3,406.00 $3,406.00 $3,406.00 18 45 EA
Furnish & Install Type “E” Loop Detectors, 6’ Round, per Caltrans Std. ES-5B. Loop Detectors shall Comply with Latest CA MUTCD and Connect to Existing Conductors and DLC’s to Controller Cabinet
per Plans
$430.25 0.00 EA 55.00 EA 55.00 EA $0.00 $23,663.75 $23,663.75 $19,361.25 19 21 EA
Furnish & Install Type “F” Loop Detectors per Caltrans Std. ES- 5B. Loop Detectors shall Comply with Latest CA MUTCD and Connect to Existing Conductors and DLC’s to Controller Cabinet per Plans
$457.00 0.00 EA 26.00 EA 26.00 EA $0.00 $11,882.00 $11,882.00 $9,597.00 20 4 EA
Furnish & Install Modified Type “F” Loop Detectors in Bike Lane per Caltrans Std. ES-5B. Loop Detectors shall Comply with Latest CA MUTCD and Connect to Existing Conductors and
DLC’s to Controller Cabinet
per Plans
$457.00 0.00 EA 4.00 EA 4.00 EA $0.00 $1,828.00 $1,828.00 $1,828.00 21 8 EA Install New Blue Raised Pavement Markers (BRPMs) $10.75 0.00 EA 8.00 EA 8.00 EA $0.00 $86.00 $86.00 $86.00 22 1 FA Additional Work Items Allowance $100,000.00 0.00 FA 0.00 FA 0.00 FA $0.00 $0.00 $0.00 $100,000.00

22.1 1 LS Grinding Removal of Thermo Bars in 8 Locations and Reinstall with Pain
t 0.00 % 29.40 % 29.40 % $0.00 $29,400.00 $29,400.00
$1,868,020.05 $292,424.47 $2,160,444.52 $2,327,723.20
BI #6.1 (582,400.00) SF Deletin g of Crack Sealing operations from the contract $0.044 (582,400.00) SF 0.00 SF (582,400.00) SF (25,625.60) 0.00 (25,625.60) BI #6.2 (582,400.00) SF Crack Seal Markup deduction (5%) $0.0022 (582,400.00) SF 0.00 SF (582,400.00) SF (1,281.28) 0.00 (1,281.28) ($26,906.88) $0.00 ($26,906.88)
$1,841,113.17 $292,424.47 $2,133,537.64 $2,327,723.20

CITY OF COSTA MESA

BID QUANTITY
GRAND TOTAL :

Deductions and Quntity Adjustment
SUBTOTAL :

SUBTOTAL :

FINAL COST SUMMARY
ATTACHMENT 2

← All documents from this meeting