CONTRACTOR: Zusser Company, Inc.
528 Palisades Drive, Suite 504, Los Angeles, CA 90272
Project: GREENVILLE-BANNING CHANNEL HYDRODYNAMIC SEPARATOR (HDS) INSTALLATION PROJECT CITY PROJECT NO. 25-02
ITEM UNIT TOTAL QUANTITY TOTAL CONTRACT
NO DESCRIPTION PRICE TO DATE TO DATE PRICE
BASE BID
1 1 LS MOBILIZATION AND DEMOBILIZATION $80,000.00 100.00 % $80,000.00 $80,000.00 2 1 LS CLEARING AND GRUBBING $100,000.00 100.00 % $100,000.00 $100,000.00 31 L S EROSION, SEDIMENT, AND CHEMICAL CONTROL PLAN
(ESCCP) $10,000.00 100.00 % $10,000.00 $10,000.00
4 1 LS EXCAVATION AND SHORING $180,000.00 100.00 % $180,000.00 $180,000.00 5 1 LS CONSTRUCT MODIFIED JUNCTION STRUCTURE 'A' $64,000.00 100.00 % $64,000.00 $64,000.00 6 1 LS CONSTRUCT MODIFIED JUNCTION STRUCTURE 'B' $31,000.00 100.00 % $31,000.00 $31,000.00 7 1 LS CONSTRUCT CDS UNIT STRUCTURE $254,750.00 100.00 % $254,750.00 $254,750.00 8 1 LF 36-INCH DIA. RCP PIPE AND JOINTS $55,000.00 100.00 LF $55,000.00 $55,000.00 9 200 TON 3/4-INCH GRAVEL BASE MATERIAL $75.00 200.00 TON $15,000.00 $15,000.00 10 1 LS ACCESS ROAD GRADING $7,000.00 100.00 % $7,000.00 $7,000.00
ALLOWANCES
11 1 FA ALLOWANCES $15,000.00 100.00 % $15,000.00 $15,000.00 1 LS EXTRA WORK #1 - GROUNDWATER $81,000.00 100.00 LS $81,000.00 $892,750.00 $811,750.00
BID QUANTITY
FUNDS USED FOR GROUNDWATER ISSUE
CHANGE ORDER #1
SUBTOTAL :
ATTACHMENT 1