Cities Index.
2023 Street Construction and Improvement Projects Proposal

Cotati City Council
June 28, 2022

Document
2023 Street Construction and Improvement Projects Proposal
Meeting
June 28, 2022
Body
Cotati City Council
Original file
777 KB
Text extracted from the city's file for reading and search. Open the original on cotaticity.primegov.com. That file is the official record.

1401 Willow Pass Road Suite 500 Concord, CA 94520-7964 925.827.4900 f.866.356.0998 weareharris.com (USPS and email to [email protected])
Date: June 1, 2022
Craig Scott
DPW/City Engineer
City of Cotati
201 West Sierra Avenue
Cotati, CA 94931
Re: 2023 Cotati Street Construction and Improvements Project Dear Craig:

Our first On-call project with you! Thank you for selecting us as your pavement design consultant and having us submit the proposal for the 2023 Street Construction and Improvements Project. We have provided our project understanding, fee estimate and the tentative project schedule to construct in Spring 2023.

Project Description
Based on the updated draft PMP report from CAP’s the city would like to include the streets listed in Year 2023 (Scenario 1) for this year’s paving project. The 2023 Street Construction and Improvements Project will primarily consist of FDR, Mill & Overlay and Slurry Seal Treatments.

The following streets have tentatively been selected for the paving project:
2023 STREET CONSTRUCTION AND IMPROVEMENTS PROJECT
Street Name Begin End Length (LF) Treatment Approx. Cost Dig Out, Crack Seal, Slurry
Gravenstein
Way Bridge Bridge 1,409
Dig Out,
Crack Seal,
Slurry Seal
$42,320
John Roberts Dr 200 W of Lebec
Lane Macklin Dr 350
Dig Out,
Crack Seal,
Slurry Seal
$10,207
Subtotal Dig Out, Crack Seal, Slurry Seal = 1,759 LF $52,527 FDR
Amber Lane Woodland Hills End 390 FDR $104,442
Delano St Henry St Page St 245 FDR $57,738
Lebec Lane Eucalyptus Ave John Roberts Dr 630 FDR $215,954 Myrtle Ave 50 ft W of Wren Keppel Way 1,140 FDR $501,253 Myrtle Ave Keppel Way City Limits 822 FDR $361,430
Oretsky Way Cypress Ave Cypress Ave 651 FDR $188,285
Page St 50 ft W of Ramble
Creek W Sierra Ave 429 FDR $119,482
Wilford Lane Commerce Ave Meadowbrook Way 1,187 FDR $445,031 Subtotal FDR = 5,494 LF $1,993,615
Mill and Overlay (Edge Grind + 20% Digouts + Fab + 3in OL) Ahlstrom Dr Wilford Lane Gilbert Way 266 Mill & OL $74,718 Lund Hill Lane Val Paraiso Ave Jagle St 494 Mill & OL $117,080 Lund Hill Lane Jagle St Cypress Ave 1,026 Mill & OL $216,147 Macklin Dr Myrtle Ave John Roberts Dr 882 Mill & OL $247,748 Marsh Way E Cotati Ave End 574 Mill & OL $100,771
Myrtle Ave Old Redwood Hwy 50 ft W of Wren 950 Mill & OL $283,526 Wilford Lane Meadowbrook Way Gravenstein Way 456 Mill & OL $132,090 Subtotal Mill and Overlay = 4,648 LF $1,172,080
Slurry Seal
Ahlstrom Cr Wilford Lane Wilford Lane 532 Slurry Seal $17,730 Christensen Ct East School St End 880 Slurry Seal $21,996 Clothier Lane Old Redwood Hwy End 975 Slurry Seal $32,494 Dorfman Dr Clothier 147’ N/O Honor Pl 741 Slurry Seal $24,695 East School St El Rancho End 900 Slurry Seal $34,681
East School St El Rancho W Sierra 522 Slurry Seal $20,115 Forno Way Valparaiso Ave Valparaiso Ave 494 Slurry Seal $14,920 Gilbert Ct Wilford Lane End 171 Slurry Seal $5,699
Gilbert Way Wilford Lane End 708 Slurry Seal $23,595
Gravenstein
Way Old Redwood Hwy Bridge 998 Slurry Seal $31,181
Honor Pl Cul de Sac SW 850’ NE of Dorfman
Dr 850 Slurry Seal $28,328
Issel Ct Water Rd End 357 Slurry Seal $9,295
Jagla St Lund Hill Lane Fehler Ln 190 Slurry Seal $5,343 Logan Pl Cypress Way End 625 Slurry Seal $17,575
Loma Linda Ct Loma Linda Dr End 278 Slurry Seal $7,818
Loma Linda Dr Water Rd End 817 Slurry Seal $22,974
Maple Ave W Cotati Ave End Near Hwy 101 713 Slurry Seal $14,851 Mendelsohn Ct Macklin Dr End 494 Slurry Seal $16,464
Page St Old Redwood Hwy Delano Creek St 540 Slurry Seal $15,747 Pinewood Ct Wilford Lane End 366 Slurry Seal $12,198
Skilling Ct Macklin Dr End 447 Slurry Seal $14,897
Wilford Lane Gravenstein Way Ahlstrom Dr 587 Slurry Seal $18,340 Woodland Hills East School St End 426 Slurry Seal $11,092 Subtotal Slurry Seal = 13,611 LF $422,028
TOTAL = 25,512 LF $3,640,250
We have generated a map of the listed streets above. See Exhibit 1.

The anticipated overall project fee is $3.64M which includes a 11% Design fee, 10% Construction Management fee and 15% contingency.

Typical work to be performed includes:
• Perform field work to verify existing roadway dimensions, striping, utility covers, and other information pertinent to the design.
• Identify and measure dig out areas in slurry seal streets and tabulate in spreadsheet. • Identify deficient curb ramps and propose treatment to bring into compliance. • Notify and coordinate with utility agencies and possibly Caltrans. • Prepare plans, specifications, and cost estimate at 65%, 95%, and Final submittals. • Assist the city during the bid period
• Provide Design Services during construction
Schedule
For the tentative design schedule see Attachment B.

The design work will be completed by early November for advertising period. Construction is scheduled to start in April, however, might be able to start earlier if weather conditions are favorable and project is phased out, regardless, schedule is consistent with optimal weather conditions for paving and slurry seal installation.

Project Deliverables
The 65%, 95% and Final PS&E documents will include specifications, cost estimate and a set of full-size plans. The full-size plans will comprise of:
• Title Sheet
• General Notes Sheet
• Key Map that will show the treated streets (FDR/Mill and OL/Slurry/Crack Seal) • Plan Sheets (FDR and Mill and OL only) at 20-scale - assume 11 sheets • Key Map - Striping
• Striping Plans (FDR and Mill and OL only) at 40-scale - assume 6 sheets • Detail Sheet - assume 5 sheets
• Slurry/Crack Seal Table Sheet – Assume 3 sheets
A detailed spreadsheet showing a quantity takeoff for each street segment will be included.

Fee
Please see the attached fee proposal for Harris’ level of effort (Attachment A) to execute the scope of work. The proposed fee is in the not-to-exceed total amount of $303,628. Attention is directed to the assumptions attached to this fee proposal, indicating inclusions and exclusions in developing our fee basis.

Once we receive the Notice to Proceed, the design process will begin immediately to meet the aggressive schedule.

Please contact Luella Gabriel (925-969-8140) or Zaheer Shaikh (925-322-6582) if you have any questions regarding our proposal. We look forward to working with you again.

Sincerely,
Harris & Associates

Luella Gabriel Zaheer Shaikh, P.E., PMP
Project Manager Director, Engineering Services
Regional Manager
Enclosures: Exhibit 1 – 2023 Street Construction and Improvements Project Map Attachment A: Fee Proposal and Assumptions
Attachment B: Schedule

ESTIMATED LEVEL OF EFFORT

CITY OF COTATI
Attachment A

PROJECT PROJECT PROJECT DESIGN

DIR MGR ENGR ENGR

1.0 PROJECT MANAGEMENT

1.1 Progress Meetings (6 mtgs) 2 6 6 $2,800

1.2 Progress Reports (8 reports) 12 $2,340

1.3 Project Management Tasks 2 40 20 $11,950

1.4 Kick-Off Meeting 2 2 2 2 $1,560
SUBTOTAL HOURS 6 0 60 28 2 $18,650

2.0 INVESTIGATION PHASE (2022)

2.1 Data Collection 2 8 16 $3,910

2.2 Existing Utility Coordination 2 4 12 $2,670

2.3 Utility Locating 2 8 8 $42,000 $44,870

2.4 Site Visits 24 56 56 $22,040

2.5 Pavement Testing and Report 2 8 12 4 $43,000 $47,790

2.6 Cost-Design Life Analysis 1 8 12 16 $6,075
SUBTOTAL HOURS 3 0 46 100 112 42000 43000 $127,355

3.0 PRELIMINARY DESIGN PHASE (to 65%) (2022)

3.1 Preliminary Design Plans (65%) 2 24 60 96 $28,510

3.2 Preliminary Opinion of Probable Const. Cost (65%) 1 4 16 24 $7,055

3.3 Preliminary Specifications (65%) 1 12 24 8 $7,975

3.4 Review Meeting (1 Mtg) 2 2 $940

3.5 Quality Control Review (65%) 20 $5,200
SUBTOTAL HOURS 6 20 42 100 128 $49,680

4.0 FINAL DESIGN PHASE (2022)

4.1 Pre-Final Design Plans (95%) 2 20 44 80 $22,770

4.2 Pre-Final Estimate of Probable Const. Cost (95%) 1 2 8 16 $4,185

4.3 Pre-Final Specifications (95%) 1 8 12 4 $4,515

4.4 Quality Review (95%) 20 $5,200

4.5 Review Meeting (1 Mtg) 2 2 $940

4.6 Final Contract Documents 2 8 12 24 40 $14,490
SUBTOTAL HOURS 8 28 44 88 140 $52,100

5.0 BID PERIOD SERVICES (2022)

5.1 Pre-Bid Meeting 2 4 4 $2,050

5.2 Answer Bidder's Questions 1 8 8 $3,275

5.3 Prepare Addenda (assume 2) 1 8 8 4 $3,795
SUBTOTAL HOURS 4 0 20 20 4 $9,120

6.0 DESIGN SERVICES DURING CONSTRUCTION (2023)

6.1 Review Contractor Submittals (assume 20
submittals) 4 20 12 4 $7,910

6.2 Review Contractor RFI's (assume 12 RFI's) 4 12 12 4 $6,304

6.3 Attend Pre-Construction Meeting 2 2 2 $1,040

6.4 Attend Weekly Construction Meetings (Virtual)
(assume 10 mtgs) 2 10 10 $4,429

6.5 Change Order Assistance 2 12 12 4 $5,737

6.6 Field visits (assume 4) 2 12 12 12 $6,808

6.7 Prepare Asbuilts 2 4 2 32 $5,995
SUBTOTAL HOURS 14 2 72 62 58 $38,223
TOTAL HOURS (2022) 27 48 212 336 386 42000 43000 $256,905 TOTAL HOURS (2023) 14 2 72 62 58 $38,223
HOURS PER POSITION 41 50 284 398 444
HOURLY RATE 2022 (TYPICAL) $275 $260 $195 $180 $130
HOURLY RATE 2023 (TYPICAL) $283 $268 $201 $185 $134
FEE ESTIMATE PER POSITION $11,391 $13,016 $55,801 $71,975 $57,946 $42,000 $43,000 $85,000 SUBCONSULTANT MARKUP (10%) $8,500
PROJECT TOTAL $303,628
ASSUMPTIONS UPON WHICH LEVEL OF EFFORT ESTIMATE IS BASED:

1. Hourly rates shown are averages. Actual rates for positions may vary slightly.

2. Hours and fee for individual tasks are a guide; the total hours and cost for the project takes precedence.

3. Hours and fee may be renegotiated if the project is delayed by factors beyond Harris' control.

4. 5. City will provide the following:
-Access to any available drawings or information relevant to the project. - "Front-end" documents boiler plate
-Printing of PS&E set for bid advertisement and construction.

6. The number of budgeted meetings is indicated.

7. 8. Utility locating project limits will extend 10 feet beyond existing edge of pavement and will include horizontal and vertical data.

9. Fee assumes design completion in year 2022.

10. Fee assumes construction in year 2023.

TOTAL

HARRIS & ASSOCIATES
City comments at each review stage will be presented to Harris promptly and on one consolidated set of marked-up documents. 2023 - STREET CONSTRUCTION AND IMPROVEMENTS PROJECT
F3 &
Associates PEI
Subconsultants

HARRIS & ASSOCIATES
DATE: 05/31/22

PHASE, TASK QA/QC
Harris will identify and quantity all base failure areas. The base repair locations will not be shown on the plans, but will be available if requested during construction.

Attch A_2023_Fee proposal - Street Construction_5-31-22.xls Page 1 of 1 ID Task Name Duration Start Finish
1 Council Approval 1 day Tue 6/28/22 Tue 6/28/22
2 Notice to Proceed 1 day Fri 7/1/22 Fri 7/1/22
3 Kick-off Meeting 1 day Tue 7/5/22 Tue 7/5/22
4 Preliminary Design Phase 49 days Tue 7/5/22 Mon 9/12/22 5 Investigation Phase 10 days Tue 7/5/22 Mon 7/18/22
6 Preliminary Design
Development (65%)
23 days Tue 7/19/22 Thu 8/18/22
7 Quality Control Review
(65%)
10 days Fri 8/19/22 Thu 9/1/22
8 City Review 5 days Fri 9/2/22 Fri 9/9/22
9 City Review Meeting 1 day Mon 9/12/22 Mon 9/12/22
10 Final Design Phase 41 days Tue 9/13/22 Tue 11/8/22
11 Pre-Final Design
Development (95%)
18 days Tue 9/13/22 Thu 10/6/22
12 Quality Control Review
(95%)
3 days Fri 10/7/22 Tue 10/11/22
13 City Review 5 days Wed 10/12/22 Tue 10/18/22
14 City Review Meeting 1 day Wed 10/19/22 Wed 10/19/22
15 Final Contract
Documents
14 days Thu 10/20/22 Tue 11/8/22
16 Bid Period Services 23 days Wed 11/9/22 Tue 12/13/22 17 Bid Advertising 21 days Wed 11/9/22 Fri 12/9/22
18 Bid Opening 1 day Mon 12/12/22 Mon 12/12/22
19 Council Approval to
Construct
1 day Tue 12/13/22 Tue 12/13/22
20 Construction Assistance
Services
129 days Wed 12/14/22 Mon 6/19/23
21 Contracts and
Mobilization
8 days Wed 12/14/22 Fri 3/24/23
22 Construction 60 days Mon 3/27/23 Mon 6/19/23
6/28
7/1
7/5
12/12
May '22 Jun '22 Jul '22 Aug '22 Sep '22 Oct '22 Nov '22 Dec '22 Jan '23 Feb '23 Mar '23 Apr '23 May '23 Jun '23 Jul '23 Task Split Milestone Summary
COTATI - 2023 Street Construction and Improvements Project Attachment B Date: Fri 5/27/22