September 9, 2022
Craig Scott
City of Cotati
201 West Sierra Avenue
Cotati, CA. 94931
Subject: Proposal for Construction Management Services
West Sierra Ave Sewer Replacement
Dear Craig:

The West Sierra Avenue Sewer Replacement project replaces the sewer in West Sierra Avenue from Olof Street to Water Road has been designed and the project is out to bid. It is understood that City desires Brelje and Race to provide a proposal for Construction Phase Services.

The project has been broken into three parts, the Base, Additive A, and Additive B. The Base includes replacement of approximately 1,700 lineal feet of sewer main including six intermediate manholes and fifteen laterals, Additive A includes replacement of one manhole and three laterals on existing sewer mains, and Additive B includes an additional 500 feet of sewer main, two additional intermediate sewer manholes, and three laterals. It is understood the City will award the Base plus Additive A.

Brelje and Race proposes to provide all required construction phase services generally described as comprehensive construction management services including construction observation. Brelje and Race will arrange for and conduct the preconstruction conference, review the contractors proposed schedule, review and process shop drawings, respond to RFI’s, provide construction staking, prepare and process any agreed-upon change orders, prepare and submit applications for payment to the City, perform daily construction observation and prepare daily reports, participate in the final inspection with City staff and prepare record drawings and forward them together with a photo log to the City.

Enclosed is an exhibit that shows our work hour and fee estimates for the proposed services. The requested budgets for the services, total $135,000. The work hours listed for construction observation assume a construction duration of not more than 55 working days.

Craig Scott
September 9, 2022

Page 2 of 2 ends

Please don’t hesitate to contact me should there be any questions regarding this proposal.

Very truly yours,

BRELJE & RACE
Brent Beazor
enclosures

PHASE TASK DESCRIPTION
Associate
Principal
Engineer CAD
Technician
Construction
Engineer
Subconsultant ($)
Compaction
Testing 1.01 Project Management 36

1.02 Pre-Construction Conference 4 41.03 Schedule Review 41.04 Site Visits 4 41.05 Change Orders and RFI's 4 4 41.06 Shop Drawings 8 24 41.07 Applications for Payment 8 61.08 Progress Meeting 24 141.09 Construction Observation 440 $26,0001.10 Substantial Completion Notice 21.11 Record Drawings 2 4 81.12 Final Inspection 3 4 Subtotal 99 38 8 474 $26,000
Total Hours 99 38 8 474 $26,000
Hourly Rate $225 $175 $145 $165 N/A
Subtotal Cost $22,275 $6,650 $1,160 $78,210 $26,000
Construction PhaseTotal $135,000
Construction Phase Services
West Sierra Avenue Sewer Replacement Project
Base Plus Additive A
City of Cotati
ENGINEERING SERVICES WORK HOUR ESTIMATE and COST TABULATION September 9, 2022

WORKHOURS

Page 1 of 1 ends