December 1, 2023
Craig Scott
City of Cotati
201 West Sierra Avenue
Cotati, CA 94931
Subject: Proposal for Construction Phase Services
Cypress Avenue Sewer Repairs
B&R File No. 4656.06
Dear Craig:

The Cypress Avenue Sewer Repairs project performs sewer repairs at various locations on the sewer in Cypress Avenue between West Sierra Avenue and approximately 150 feet south of the southerly intersection with Oretsky Way. The project has been designed and is currently out to bid. It is understood that the City desires Brelje & Race to provide a proposal for Construction Phase Services.

Brelje & Race proposes to provide all required construction phase services generally described as comprehensive construction management services including construction observation. Brelje & Race will arrange for an conduct the preconstruction conference, review the contractors proposed schedule, review and process submittals and shop drawings, respond to RFIs, prepare and process and agreedupon change orders, prepare and submit applications for payment to the City, participate in progress meetings, perform daily construction observation and prepare daily reports, perform compaction testing, participate in the final inspections with City staff and provide notice of substantial completion, and prepare record drawings and transmit them together with a photo log to the City.

We propose to perform the above work on a time-and-materials, not-to-exceed basis within a budget of $110,200. The Task, Work Hour and Cost Tabulation and a copy of our current Services Rate Schedule is enclosed. The work hours listed for construction observation assume a construction duration of not more than 30 working days.

We appreciate this opportunity to provide professional engineering services. Please do not hesitate to contact me should there be any questions regarding this proposal.

Very truly yours,

BRELJE & RACE
___________________________________
Brent Beazor, P.E.

Senior Principal

TASK DESCRIPTION
Senior
Principal
Managing
Engineer
Engineer I CAD
Technician
Construction
Engineer
Subconsultant ($)
Name
Beazor Stetina RGH
1 1.01 Project Management 8 24

1.02 Pre-Construction Conference 2 4 21.03 Schedule Review 41.04 Submittals and Shop Drawings 2 6 24 21.05 Change Orders and RFIs 2 6 4 41.06 Applications for Payment 2 81.07 Progress Meetings 12 81.08 Construction Observation 1 6 2 2401.09 Compaction Testing 1 4 $20,0001.10 Final Inspection and Substantial Completion Notice 3 6 41.11 Record Drawings 1 2 6 8 2 Subtotal 22 82 36 12 0 $20,000
Total Hours 22 82 36 12 258 N/A
Hourly Rate $250 $220 $185 $145 $180 N/A
Subtotal Cost $5,500 $18,040 $6,660 $1,740 $46,440 $20,000 SUBTOTAL $98,380
CONTINGENCY 10% $9,800
REPRO & PLOT $0
10% $2,000
TOTAL $110,200

WORKHOURS
Construction Phase Services for Cypress Avenue Sewer Repairs TASK, WORK HOUR and COST TABULATION
November 28, 2023

SUBCONSULTANT

MARK-UP
City of Cotati
Construction Phase
Services

SERVICES RATE SCHEDULE
EFFECTIVE MARCH 1, 2023

PROFESSIONAL SERVICES
Senior Principal ................................................................................................................ $250.00/hour Associate Principal ............................................................................................................ 235.00/hour Associate (Managing Engineer) ....................................................................................... 220.00/hour Senior Project Advisor ..................................................................................................... 215.00/hour Senior Engineer ................................................................................................................. 210.00/hour Engineer II ......................................................................................................................... 195.00/hour Engineer I ........................................................................................................................... 185.00/hour Engineering Technician II ............................................................................................... 170.00/hour Engineering Technician I ................................................................................................. 160.00/hour Senior Planner .................................................................................................................... 185.00/hour Planner ................................................................................................................................ 160.00/hour Senior Surveyor .................................................................................................................. 190.00/hour Surveyor .............................................................................................................................. 175.00/hour Survey Technician ............................................................................................................. 165.00/hour CAD Technician Supervisor ............................................................................................ 170.00/hour CAD Designer ................................................................................................................... 150.00/hour CAD Technician ................................................................................................................ 145.00/hour Engineering Intern ............................................................................................................ 130.00/hour Construction Engineer ..................................................................................................... 180.00/hour Construction Technician II.............................................................................................. 155.00/hour Construction Technician I ............................................................................................... 130.00/hour Technical Writer ................................................................................................................ 125.00/hour EXPERT WITNESS & MEDIATION SERVICES $600.00/hour

FIELD SURVEYING
One-man Party $220.00/hour
(Including Survey Equipment & Vehicle)
Two-man Party $300.00/hour
(Including Survey Equipment & Vehicle)
Three-man Party $370.00/hour
(Including Survey Equipment & Vehicle)
CLERICAL SERVICES $95.00/hour
OUTSIDE CONSULTANTS Cost + 10% Handling Charge
OUTSIDE PLOTTING AND REPRODUCTION Cost + 10% Handling Charge

IN-HOUSE PLOTTING
Vellum or Bond $8.00/sheet
Mylar 20.00/sheet
Note
Brelje & Race does not charge separately for many of the expenses that are traditionally recouped from the Client as “reimbursable”. The hourly rates listed above are inclusive of all expenses for vehicle mileage, surveying materials, incidental copying services and computer hardware, software and other information technology costs.