10 TOC Policy Implementation 6/15/24 12/10/24 16 40 40 2 12 112 16 40 40 2 12 112
$3,280 $7,200 $5,600 $240 $1,200 $17,800
$21,797
$5,000
$44,597
Fehr & Peers Totals
Rincon Consultants Totals Subconsultant Budget Totals
GRAND TOTAL
Cotati Santero Way Budget Amendment for Transit-Oriented Communities (TOC) Policy Implementation - 4LEAF, Inc. 4LEAF Totals (Hours & Budget)
$140
Associate Task # Task Description Start End Hrs/Task
Santero Way Specific Plan
Budget Amendment Request - Transportation Analysis
Fehr & Peers understands that the scope of the Cotati Santero Way Specific Plan has been modified to expand the area of potential land use changes versus previous expectations. The additional parcels are located in other Traffic Analysis Zones in the SCTA model and will require additional coordination with the project team to (1) confirm assumptions and (2) confirm that the City of Cotati continues to meet regional modeling land use control totals. The additional parcels located away from the Santero Way corridor also add complexity to the intersection Level of Service analysis as the development is more spread out amongst the five study intersections.
With this amendment, Fehr & Peers will update the travel demand model runs for the land use alternatives to reflect the additional parcels, as well as prepare a Level of Service analysis reflecting the additional parcels. It is presumed with this amendment that the Specific Plan continues to screen from CEQA Transportation section VMT analysis, and that VMT by speed bin data from the SCTA Travel Demand Model would continue to be required to CEQA Air Quality, Greenhouse Gas and Energy section analyses.
Fee Proposal for Santero Way Specific Plan Add-On
Fehr & Peers
Principal-inCharge/PMTravel Model
Expert/QAQCer
Project
Planner/Engineer
Graphics Project Coordinator
Labor
Hours
Direct
Costs
Total
Tasks $320 $285 $205 $215 $160
Additional Coordination on Land Use Assumptions 2 1 4 0 1 8 $165 $2,070 Update Model and Confirm VMT Values 1 2 8 0 1 12 $240 $2,930 Total for all Tasks 3 3 12 0 2 20 $405 $5,000
Notes:
This fee proposal is valid for a period of 90 days from the proposal submittal date.
Actual billing rate at the time of service may vary depending on the final staffing plan at the time the project starts; the overall fee will not be exceeded.
Mileage is billed at the IRS rate plus 10% handling fee Rates and non-key staff are subject to change at any time, without notice, and within the total budget shown 1 Rincon Consultants, Inc.
4825 J Street, Suite 200
Sacramento, California 95819
916-706-1374
www.rinconcons ultants.com
June 6, 2024
Rincon Project No. 22-13884
Luke Lindenbusch, Senior Planner
4LEAF, Inc.
2235 Mercury Way #120
Santa Rosa, California 95407
Via email: [email protected]
Subject: Revised Request #1 for Add Services Request for the Santero Way Specific Plan Environmental Impact Report
Rincon Consultants, Inc. (Rincon) is requesting this scope amendment and budget augmentation to our existing agreement to assist the City of Cotati with continuing work on the Environmental Impact Report (EIR) for the Santero Way Specific Plan Update. The City of Cotati and 4LEAF staff requested the addition of nine additional parcels totaling approximately 14 acres. The following Assessor’s Parcel Numbers (APN) are included in the expansion of the project area: 144-292-023, 144-292-024, 144- 301-010, 144-302-022, 144-302-050, 144-501-004, 144-570-001, 144-720-029, and 144-720- 040. We are seeking an acknowledgement and modification to our budget to accommodate the additional labor associated with this modification to the project area.
Add Services Request
Task 9.0: Project Management
The extended project schedule and revision to the project area will require additional project management labor beyond that in the current authorized scope of work. The additional labor is associated with standard project management tasks including internal team coordination, budget and schedule management, and project oversight.
Task 9.2.1: Updated Notice of Preparation
Due to the modification to the project area, we recommend re-issuance of the Notice of Preparation (NOP). Revisions to the NOP prior to re-issuance include updates to the description of the project area, revisions to the project area figure, and revisions to the project description to incorporate proposed changes to the project area.
Rincon will prepare a draft Updated NOP for City staff to review. The Updated NOP will include all required details including project description, location, dates of public review and dates/location of the public scoping meeting. Rincon will submit a draft Updated NOP in Microsoft Word format for City review. Upon receipt of one round of consolidated comments on the draft Updated NOP, Rincon will prepare a final PDF copy of the Updated NOP for City staff to post on its website and for distribution to public agencies. It is assumed that the City will be responsible for any the Updated NOP distribution list and associated direct mailing of printed copies of the Updated NOP. Rincon will assist with filing the Updated NOP with the State Clearinghouse/Office of Planning and Research and Sonoma County Clerk. It is assumed that the City will complete the County Clerk filing.
City of Cotati
Santero Way Specific Plan EIR
2 The Updated NOP and relevant correspondence received in response to the Updated NOP will be attached as an Appendix to the Draft EIR. The scope of the EIR will be adjusted, if necessary, based on the comments received.
Task 9.4.1: Second Scoping Meeting
Similar to the recommended re-issuance of the NOP, we recommend conducting a second Scoping Meeting during the public review period of the Updated NOP. Rincon will facilitate one public and agency scoping meeting associated with the release of the Updated NOP. The Scoping Meeting will be held during the 30-day review period to introduce the community and responsible agencies to the EIR process and obtain input on the EIR scope of work. Applicable agencies and interested parties would be invited to attend the scoping meeting. The meeting will include a brief presentation, followed by public comment and input from meeting attendees. Rincon will prepare a summary of relevant input gathered, which will be included in the Draft EIR along with relevant written public comments received during the Updated NOP comment period. Rincon assumes the Scoping Meeting will be held at a Planning Commission meeting, which the City will organize. For the purposes of this scope, we have assumed attendance at the scoping meeting will be virtual. Notice of the scoping meeting would be provided in the Updated NOP.
Task 9.5.1: Updated AB 52 and SB 18 Consultation Assistance The changes to the project require updated tribal consultation letters be sent out, in accordance with Assembly Bill (AB) 52 (California Government Code Section 21080.3.1[a]) and Senate Bill (SB) 18 (California Government Code Section 65352.3 and 65352.4). Rincon will utilize the Native American Hertiage Commission contacts list for the project, dated November 13, 2023, and will provide the City with letter templates explaining the project update to the contacts listed. After receipt of letters, Native American Tribes have 30 days to reply to a request for consultation under AB 52 and 90 days under SB 18; the 30-day wait period for AB 52 is subsumed in the wait period for SB 18. This task does not include meetings, outreach, consultation or mailing letters to Tribal governments, although consultation support may be added for an additional cost if needed. Rincon assumes that the City will officially contact all applicable Tribes. Additionally, Rincon will include the new consultation efforts in an assessment of impacts to Tribal Cultural Resources for the CEQA document.
Task 9.6: Administrative Draft EIR
Rincon will revise the draft Administrative Draft EIR sections completed to date to reflect the updated project area. This includes figure revisions as well as narrative revisions to the text, where necessary.
This also includes revisions to chapters of the EIR referencing the NOP publication date, comment period, and scoping meeting, to incorporate the Update NOP publication date, second comment period, and second scoping meeting.
This further includes additional investigation related to cultural and historical resources, including reviewing the potential for historical and archaeological resources to occur within the expanded project site and the potential impacts to those resources as a result of the project. As part of the original cultural resources investigation, Rincon requested a California Historical Resources Information System (CHRIS) records search of the original project site as well as a 0.5-mile radius around the project site, which encompasses the expanded project site. Therefore, a new records search request is not warranted at this time. Rincon will update the technical report to include discussion of the expanded project site. If significant impacts are identified, programmatic mitigation measures will be provided.
City of Cotati
Santero Way Specific Plan EIR
3 Assumptions
• Attendance at the scoping meeting will be virtual.
• No additional field work will be required.
Add Services Fee Estimate
Our estimate for the costs to complete the additional requested tasks described above is $21,797.00 as shown in the table below.
Cost Summary
Task Estimated Cost
Task 9.0 Project Management $1,739.00
Task 9.2.1 Updated Notice of Preparation $1,446.00
Task 9.4.1 Second Scoping Meeting $2,144.00
Task 9.5.1 Updated AB 52 and SB 18 Consultation Assistance $1,603.00 Task 9.6 Administrative Draft EIR $14,865.00
Total $21,797.00
We appreciate your consideration of this request to add services. If you have any questions or would like any additional information, please contact us at your convenience.
Sincerely,
Rincon Consultants, Inc.
Aileen Mahoney
Project Manager
Matt Maddox, AICP MESM
Principal
WEEK OF: 3-Jun 10-Jun 17-Jun 24-Jun 1-Jul 8-Jul 15-Jul 22-Jul 29-Jul 5-Aug 12-Aug 19-Aug 26-Aug 2-Sep 9-Sep 16-Sep 23-Sep 30-Sep 7-Oct 14-Oct 21-Oct 28-Oct 4-Nov 11-Nov 18-Nov 25-Nov 2-Dec 9-Dec
1.0 Project Management
1.1 Commencement Meeting DONE DONE
1.2 Ongoing Project Coordination STARTED 12/10/24 City/4L Cnsltnts City/4L City/4L Cnsltnts City/4L City/4L Cnsltnts City/4L City/4L BOTH City/4L BOTH City/4L City/4L Cnsltnts City/4L City/4L Cnsltnts
2.0 Existing Conditions & Data Analysis
2.1 Existing Conditions & Opportunities DONE DONE
2.2 Housing Policy Options DONE DONE
3.0 Community Engagement
3.1 Community Workshop #1 DONE DONE
3.2 TAC Meeting #1 DONE DONE
3.3 Embedded Community Engagement STARTED 12/10/24
4.0 Land Use & Circulation Alternatives
4.1 Land Use & Transportation Plan Alts DONE DONE
4.2 TAC Meeting #2 6/17/24 7/19/24
4.3 Community Workshop #2 DONE DONE
5.0 Preferred Alternative
5.1 Preparation of Plan Alternatives STARTED 6/14/24
5.2 Community Workshop #3 7/8/24 7/19/24 PC 7/15
6.0 Specific Plan Update Document
6.1 Admin Draft STARTED 8/23/24
6.2 Public Review Draft (45 Days for EIR) 9/16/24 10/31/24
6.3 Community Workshop #4 9/2/24 9/24/24 PC 9/16 CC 9/24
7.0 General Plan/Zoning Amendments
7.1 Text Amendments & Needs Assessment 9/23/24 11/4/24
8.0 Plan Adoption
8.1 Staff Reports 10/7/24 11/4/24
8.2 PC Hearing 10/14/24 11/4/24 PC 11/4
8.3 CC Hearing 11/5/24 12/10/24 CC 12/10
9.0 6/14/24 6/28/24
6/17/24 9/15/24
6/17/24 6/17/24
6/17/24 8/23/24
8/23/24 9/6/24
9/6/24 9/16/24
9/16/24 10/31/24
10/17/24 10/31/24
LEGEND
Ongoing, As Needed
Prep
City Deliverable
City Review
Italics Proposed Date
Cotati Santero Updated Schedule - 4LEAF, Inc.
Task # Task Description Start End
June 2024 Revision
Admin Draft EIR (Rincon)
Review of Admin Draft EIR (City)
Note: timelines assume that data and information requested by 4LEAF will be provided within one week and that all administrative reviews return a single set of non-conflicting comments within 2 weeks of receipt.
Environmental Impact Report (EIR) Milestones
Revised Schedule/Timeframe
Buildout Calculations to City (4LEAF)
Project Description & Revised NOP (Rincon)
6/5/24
6/11/24
Final EIR (Rincon)
Incorporation of City Input (Rincon)
Public Review Draft EIR (City/Rincon)
Tribal Consultation Letters Out (City)
Technical Information to Subconsultants (4LEAF)