Cities Index.
Sonoma Water - Water Transmission System Projects

Cotati City Council
January 14, 2025

Document
Sonoma Water - Water Transmission System Projects
Meeting
January 14, 2025
Body
Cotati City Council
Original file
5.5 MB
Text extracted from the city's file for reading and search. Open the original on cotaticity.primegov.com. That file is the official record.

sonomawater.org
Clean. Reliable. Essential. Every Day.

Water Transmission
System Projects
Kent Gylfe
Director of Engineering
[email protected]
Water is delivered from river
to communities
• Water Transmission
System aqueducts
deliver water to Santa
Rosa, Rohnert Park,
Cotati, Petaluma,
Windsor, Sonoma Valley
and Marin
• Serving homes and
businesses to a
population over 600,00
Capital Improvement Projects
O&M Projects
Planning Efforts
Occidental Rd Well #3
Drilling and Activation
• Drilling project completed in April
2024
• Topside design delayed due to well
development – advertised
December 2024
• Substantial completion in October
2025
• Plan, permit, test and implement
recharge components internally
(2026)
Santa Rosa Plain Wells Drought Resiliency
Project awarded $6.9M State Drought
Relief Grant
Sebastopol Rd Well
Activation
• Design completed and project
advertised in Nov 2023
• Construction in progress with
underground nearly complete
• Electrical equipt. delivery
anticipated Feb 2025
• Well conditioning and cycling
Spring/Summer 2025
• ASR pilot study through Oct 2025
Kastania Tank Recoat
• Project Goals
• Recoat interior/exterior of tank
• Replace cathodic protection
• Seismic analysis/retrofits
• Modifications to tank
appurtenances
• Completed and back in
service September 2024
• Fun fact – Kastania tank
required roughly 6,850
gallons of paint to recoat –
enough to paint an average
1500 ft2 home 250 times
Cotati #3 Recoat and
Seismic Project
• 18MG tank – largest in system
• Bids received October 2024
• Recoat interior/exterior of tank
• Cathodic protection
• Seismic retrofit of foundation
• Modifications to tank appurtenances
• Award January 2025
• Construction anticipated Mar
2025 – Feb 2026
Santa Rosa/Cotati Aqueduct
Cathodic Protection
• Project split in 2 phases based on ease
of R/W and permitting
• Phase 1
• 11 total rectifier/anode well sites
• 11 CP stations
• Phase 2 –
• 20 total rectifier/anode well sites
• 39 CP stations
• Significant coordination with PG&E
• Phase 1 design progressing with
target advertise Mar 2025
• Phase 2 design to follow with target
construction 2026
Wilfred Booster Electrical
Upgrade
• Project includes
• Replace electrical switchgear
building and components
• Add 2nd pump set and piping for
reliability/resiliency
• Capable of pumping north and south
• Electrical switchgear
prepurchase in June 2024
• Advertise scheduled for May
2025
Designs in Progress
• Bennett Valley Fault Crossing
• Seismic resiliency pipeline project
• 30% design complete with target advertise
Summer 2025
• Treatment Modernization Upgrades
• Preliminary feasibility completed Oct 2024
• Multi-phase, multi-year project with Phase 1
design kicking off
• Wohler Demuth
• Emergency storage facility
• Design kicked off with target advertise
Summer 2026
• Kawana-Ralphine-SBS Pipeline - Ph 1
• In process of finalizing scope with consultant
for phase 1 design, environmental, and rightof-way
• Next phase will utilize recent easement
acquisition through Southeast Greenway
Tank Washout Inspections,
Visual Inspections, and
Condition Assessments
• Washout Inspections
• Ralphine 1, 2, 3 & 4
• Eldridge 1
• Sonoma 1&2
• Annadel 1 & 2
• Kawana 1
• Cotati 2 (in progress)
• Kawana 2 (FY 25/26)
• Eldridge 2 (FY 25/26)

Comprehensive Master Plan
• Task 1 complete:
• Water System Baseline
• FY24/25:
• Task 2 – Water Demand
Forecasting
• Task 3 – Basis of Cost
Information
• Task 4 – Methodology for
Project Prioritization
• FY25/26:
• Task 5 – Generate Project
Groupings
• FY26/27:
• Task 6 – Compile Water System
Master Plan

sonomawater.org
Questions?

← All documents from this meeting