Cities Index.
Harris Proposal_2027 Pavement Preservation

Cotati City Council
May 26, 2026

Document
Harris Proposal_2027 Pavement Preservation
Meeting
May 26, 2026
Body
Cotati City Council
Pages
4
Original file
1.9 MB
Text extracted from the city's file for reading and search. Open the original on cotaticity.primegov.com. That file is the official record.

1401 Willow Pass Road Suite 500 Concord, CA 94520-7964 925.827.4900 f.866.356.0998 weareharris.com (Email to [email protected])
Date: May 15, 2026
Craig Scott
DPW/City Engineer
City of Cotati
201 West Sierra Avenue
Cotati, CA 94931
Engineering Design Services for the
2027 Pavement Preservation Project
Dear Craig:

Harris & Associates (Harris) is pleased to present this proposal for civil engineering design services for the 2027 Pavement Preservation Project as requested. The following will present an outline of our proposed scope of services. We have provided a Scope of Work Matrix in Attachment A. It is our intent that this outline provides enough detail, so our approach is clearly defined. It should be noted that this scope is based on the latest 5 Year Paving CIP Update for FY25/26 to FY30/31, corresponding with City Staff and our understanding of the project schedule (to be constructed in July 2026).

PROJECT UNDERSTANDING
This project will include the preservation streets listed in YR 2027 of the current 5 Yr CIP Paving Update (dated 3/13/25).

YR 2027 estimated construction cost = $608,860
The anticipated construction budget = $750K.

There are thirteen (13) street segments that will receive slurry seal, crack seal, and base repairs (dig outs) as part of the preventative maintenance program. Fieldwork will be performed, and PS&E documents will be developed.

The following streets will be included in the project limits with approximate costs per the latest 5 Year Paving CIP Update for FY25/26 to FY30/31:
1401 Willow Pass Road Suite 500 Concord, CA 94520-7964 925.827.4900 f.866.356.0998 weareharris.com Street Name Begin End Length
(LF) Treatment Approx. Cost
FY2027 Slurry Seal
Benson Ln Bridge Loretto Ave 160
Dig Out 10%,
Crack Seal,
Slurry Seal
$5,428
Lakewood Ave Lincoln Ave La Salle Ave 1800
Dig Out 10%,
Crack Seal,
Slurry Seal
$87,609
Larch Ave Lincoln Ave La Salle Ave 1,425
Dig Out 10%,
Crack Seal,
Slurry Seal
$69,357
La Salle Ave East Cotati Ave Larkspur Ct 1,000
Dig Out 10%,
Crack Seal,
Slurry Seal
$63,183
La Salle Ave Larkspur Ct Loretto Ave 980
Dig Out 10%,
Crack Seal,
Slurry Seal
$61,919
Lincoln Ave Loretto Ave La Salle Ave 840
Dig Out 10%,
Crack Seal,
Slurry Seal
$45,840
Lincoln Ave La Salle Ave City Limits 884
Dig Out 10%,
Crack Seal,
Slurry Seal
$48,241
Linden Ave Lincoln Ave Larch Ave 722
Dig Out 10%,
Crack Seal,
Slurry Seal
$35,141
Linden Ct Linden Ave End 285
Dig Out 10%,
Crack Seal,
Slurry Seal
$13,871
Loretto Ave Benson Ln Lincoln Ave 741
Dig Out 10%,
Crack Seal,
Slurry Seal
$36,066
Loretto Ave Benson Ln La Salle Ave 970
Dig Out 10%,
Crack Seal,
Slurry Seal
$47,212
ORH William West Sierra Ave 800
Dig Out 10%,
Crack Seal,
Slurry Seal
$81,967
Larkspur Ct La Salle Ave End 180
Dig Out 20%,
Crack Seal,
Slurry Seal
$12,845
Subtotal FY2027 Slurry Seal 10,787 LF $608,680
We have generated a map of the listed streets above. See Exhibit 1 McGinnis Cir
Silver
Dr
Cotati
Oaks
Ct
Gilman Ranch Rd
Meadowbrook Ct
S Hwy 101
N
Hwy
101
Kingston
Ln
Sunflower
Dr
Oak
Cir
Ryan Ln
Dino Ct
Myrtle Ave
Revard
Ct
Primero
Ct
Matteri Cir
Blodgett
St
Lancaster Dr
Skilling Ct
Cotati Ave
S Hwy 101
School St
Park
Ave
Lakewood Ave
Loma Linda Dr
Christensen
Ct
Houser St
Sierra Ave
Cotati Ave
S Hwy 116
Aaron St
Ford Ln
Lasker Ln
Village Ct
Gilbert Ct
Manor Ct
Lund
Hill
Ln
Cypress Ave
Arthur St
Sycamore Ln
Helman Ln
Lebec Ln
Cotati Ave
Portal St
Locust Ave
Grove
St
Eucalyptus Ave
Breen Way
Loretto Ave
Redwood Dr
Tracks
Trebino Ct
Nelson Ln
Madrone Ave
Scenario Years by Treatment
2024-5yr CIP_3-12-25 - All Treatments - Printed: 3/13/2025

CITY OF COTATI
1401 Willow Pass Road Suite 500 Concord, CA 94520-7964 925.827.4900 f.866.356.0998 weareharris.com The above costs include 10% Design fee, 10% Construction fee, and 15% Contingency.

Harris will also provide updates to the 5 Year Pavement CIP report. NCE will assist us with the StreetSaver updates. We will update the existing data with recently completed streets and add FY32 and FY33 to the program. Please note that this task will extend beyond the 2027 Pavement Preservation Project completion.

PROJECT SCHEDULE
The tentative design schedule is shown below:
• May 27, 2026 – NTP (tentative)
• May 28, 2026 to May 28, 2026 – Fieldwork
• May 29, 2026 to June 9, 2026 – Prepare/Submit 90% PS&E • June 10, 2026 to June 12, 2026 – City review
• June 15, 2026 to June 19, 2026– Prepare/Submit Final PS&E • June 22, 2026 to July 13, 2026 – Advertising period (21 days) • July 28, 2026 – Council Approval to Construct / Award • August 10, 2026 – Construction start
Harris performed the fieldwork for the 2027 slurry streets during the field investigation phase of the 2026 Pavement Preservation project in May 2025 when the streets were included in the original scope. However, the 2027 slurry seal streets were later removed from the 2026 project after fieldwork was completed. Therefore, we allowed 1 day of fieldwork to revisit the streets and investigate any additional changes from the previous field visit.

The design work will be completed by June 19, 2026, and awarded on July 28, 2026. The schedule assumes 3 working days for City review of Harris deliverables. Harris will not be responsible for delays to the project schedule beyond sole control. The desired timeframe for slurry seal installation is between May and mid-October (70 degrees and rising).

PROJECT DELIVERABLES
The 90% and Final PS&E documents will include specifications, cost estimate and a set of fullsize plans in pdf format. The full-size plans will comprise of:
• Title Sheet
• Key Map that will show the treated streets (Slurry/Crack Seal) • Detail Sheet
• Detailed spreadsheet showing dig outs and quantity takeoff for each street segment 1401 Willow Pass Road Suite 500 Concord, CA 94520-7964 925.827.4900 f.866.356.0998 weareharris.com We will also keep a record of the digout locations painted on the streets as part of our field investigation notes in case the contractor requests a copy of them during construction.

We will provide updated StreetSaver reports as requested by the city. This will include decision tree revisions, network summary statistics, maintenance history reports, and FY32-FY33 Scenario Treatment CIP Report.

PROPOSED FEE
Please see the attached fee proposal for Harris’ level of effort (Attachment B) to execute the scope of work. The proposed fee is in the not-to-exceed total amount of $70,975. Attention is directed at the assumptions attached to this fee proposal, indicating inclusions and exclusions in developing our fee basis.

Once we receive the Notice to Proceed, the design process will begin immediately to open bids and award by late July 2026.

Please contact Luella Gabriel (925-969-8140) or Eric Smith (949-536-2508) if you have any questions regarding our proposal. We look forward to working with you again.

Sincerely,
Harris & Associates
Luella Gabriel Eric Smith, PE
Project Manager Director, Transportation Engineering
Enclosures: Exhibit 1 – 2027 Project Limits Map
Attachment A: Scope of Work Matrix
Attachment B: Fee Proposal and Assumptions

Page 1 ends

City of Cotati
2027 Pavement Preservation Project

TASK OUR APPROACH DELIVERABLE
00 PROJECT ADMINISTRATION

0.1 Progress Meetings Monthly meetings with City staff and others as appropriate throughout design process.

Notes of each meeting
highlighting agreedupon action items.

0.2 Progress Report A brief progress report will accompany each monthly Harris invoice. It will discuss budget and schedule status, issues resolved and unresolved, and “next steps”.

Monthly status report.

0.3 Project Management Tasks Project setup, budgeting, scheduling and internal meetings to ensure project is running smoothly.

1.0 INVESTIGATION PHASE

1.1 Kick-off Meeting We will meet with staff to confirm the scope of work, schedule, budget, and availability of project documents; review project goals and conceptual designs; discuss the format of deliverables; and clarify responsibilities of each party.

Meeting notes with lists,
as appropriate.

1.2 Data Collection We will conduct an inventory of street data such as width, length, striping, etc. and prepare field exhibits for field investigation.

Spreadsheet showing
data for each street.

1.3 Field Investigation A team of two Harris staff will walk each of the project streets to locate and measure digouts, take inventory of existing utility covers, identify striping, and confirm project limits.

Field notes of digout
locations will be
available for the
contractor, if requested.

Page 2 ends

City of Cotati
2027 Pavement Preservation Project

TASK OUR APPROACH DELIVERABLE

2.0 FINAL DESIGN PHASE

2.1 Design Plans (90%) We will submit a 90% package for review and comment by City and others.

Final design will not proceed until the 90% package is approved by the City.

Preliminary area map,
plans, spreadsheet, and
standard striping
details.

2.2 Opinion of Probable Construction Cost (90%) A 90% opinion of probable cost will be provided. We will utilize the resources of our expert design and construction management staff to provide current, realistic construction costs.

Preliminary itemized
cost estimate,
segregated by street if
required by the City.

2.3 Specifications and Contract Documents (90%) At the 90% stage, we will prepare technical specifications for review and comment by City staff. Specifications will be based upon City and Caltrans standard documents.

Draft special provisions
(technical specs) at the
90 percent stage.

2.4 Quality review (90%) Prior to the 90% submittal, all plans and documents will be reviewed by Harris’ Quality Manager. Quality review ensures document accuracy and completeness, and reduces necessary City review time
N/A

2.5 Review Meeting (1 meeting) At a meeting with City staff, we will discuss our 90% design package. Meeting notes.

2.6 Final Contract Documents (PS&E) After staff reviews and comments on the final draft documents, we will revise as needed and resubmit PDFs of contract documents for bidding by the City. A final, detailed engineer’s estimate of probable construction cost will be provided.

Contract documents in
PDF format.

3.0 BID PERIOD SERVICES

3.1 Attend Pre-Bid Meeting We will attend a pre-bid meeting scheduled by the City to answer questions from prospective bidders.

Meeting notes,
including a list of
questions asked.

Page 3 ends

City of Cotati
2027 Pavement Preservation Project

TASK OUR APPROACH DELIVERABLE

3.2 Answer Bidders Questions We will answer questions from bidders by telephone during the advertising period. We will log questions and provide City with documentation.

Log of questions
received, and answers
given, for City to
distribute if appropriate.

3.3 Prepare Addenda (assume 2) We will prepare any required addenda for distribution by the City. Addenda to bid package.

4.0 DESIGN SERVICES DURING CONSTRUCTION

4.1 Attend Construction Kick-off Meeting We will attend the meeting and answer any questions from the CM and contractor
Meeting minutes

4.2 Attend Construction Meetings (up to 4) We will attend weekly construction meetings if requested to answer field questions from the contractor
Meeting minutes

4.3 Respond to RFI’s (assume 4) We will respond to RFI’s sent from the CM to answer contractor questions and make recommendations to the City.

RFI responses
uploaded through CM
construction software

4.4 Review Contractor Submittals (assume 6) We will review all contractor submittals and make recommendations to the City.

Submittal Reviews
uploaded through CM
construction software

4.5 Change Order Assistance (assume 2) We will provide the City with the necessary documentation for change order processing.

Written response and
recommendation for
each change order.

4.6 Site visits (up to 2) Harris team will visit the site when requested and at during punchlist walk Punchlist items checklist

4.7 Prepare Record Drawings Once Harris receives Asbuilt markups from the CM we will update the Final set of plans and perform an internal QC and add Record Drawing stamp.

Submit Record
Drawings in PDF format

Page 4 ends

City of Cotati
2027 Pavement Preservation Project

TASK OUR APPROACH DELIVERABLE

5.0 5 Year Pavement CIP StreetSaver Update

5.1 Coordination with NCE Harris will coordinate with NCE with updates to the 5 Year Pavement CIP StreetSaver data.

Provide city with
updated reports from
StreetSaver as needed
SC NCE NCE will update data to StreetSaver by inputting recently completed street information and adding FY32 and FY33 to the CIP program Provide city with
updated reports from
StreetSaver as needed

ESTIMATED LEVEL OF EFFORT
CITY OF COTATI DATE:5/15/26
2027 Pavement Preservation Project ATTACHMENT B

PHASE, TASK PROJECT PROJECT PROJECT DESIGN SUBCONSULTANT

DIR MGR ENGR ENGR NCE

0.0 PROJECT ADMINISTRATION PHASE

0.1 Progress Meetings (4 mtgs) 4 $1,060

0.2 Progress Reports (4 reports) 4 $1,060

0.3 Project Management Tasks 0.5 16 4 $5,253
SUBTOTAL HOURS 0.5 0 24 4 0 $7,373

1.0 INVESTIGATION PHASE

1.1 Kick-off Meeting 1 1 2 $770

1.2 Data Collection 1 8 8 $3,145

1.3 Field Investigation 16 $2,320
SUBTOTAL HOURS 0 0 2 9 26 $6,235

2.0 FINAL DESIGN PHASE

2.1 Design Plans (90%) 0.5 4 10 40 $9,163

2.2 Estimate of Probable Construction Cost (90%) 1 8 8 $3,145

2.3 Specifications and Contract Documents (90%) 4 8 $2,780

2.4 Quality Review (90%) 8 $2,360

2.5 Review Meeting (1 Mtg) 1 $265

2.6 Final Contract Documents 0.5 4 2 12 24 $7,923
SUBTOTAL HOURS 1 12 12 38 72 $25,635

3.0 BID PERIOD SERVICES

3.1 Attend Pre-Bid Meeting 2 2 $960

3.2 Answer Bidder's Questions 4 6 $2,350

3.3 Prepare Addenda (assume 2) 4 8 2 $3,070
SUBTOTAL HOURS 0 0 10 16 2 $6,380

4.0 DESIGN SERVICES DURING CONSTRUCTION

4.1 Attend Construction Kick-off Meeting 1 1 $480

4.2 Attend construction meetings (up to 4) 0.5 4 2 $1,643

4.3 Respond to RFI's (assume 4) 2 4 $1,390

4.4 Review Contractor Submittals (assume 6) 2 8 $2,250

4.5 Change Order Assistance 2 8 4 $2,830

4.6 Site Visits (up to 2) 4 4 $1,920

4.7 Prepare Record Drawings 1 1 8 $1,720
SUBTOTAL HOURS 0.5 1 16 27 12 $12,233

5.0 5-YEAR PAVEMENT CIP UPDATE FY27-FY34

5.1 Coordination with NCE 8 $2,120
SC NCE $ 10,000 $10,000
SUBTOTAL HOURS 0 0 8 0 0 $12,120
HOURS PER POSITION 2 13 64 94 112
HOURLY RATE (TYPICAL) $305 $295 $265 $215 $145
FEE ESTIMATE PER POSITION $610 $3,835 $16,960 $20,210 $16,240 SUBCONSULTANT MARKUP $1,000
PROJECT TOTAL $70,975
ASSUMPTIONS UPON WHICH LEVEL OF EFFORT ESTIMATE IS BASED:

1. 2. Hourly rates shown are averages. Actual rates for positions may vary slightly.

3. Hours and fee for individual tasks are a guide; the total hours and cost for the project takes precedence.

4. Hours and fee may be renegotiated if the project is delayed by factors beyond Harris' control.

5. 6. City will provide the following:
-Access to any available drawings or information relevant to the project. -Final "front-end" documents.
-Printing of PS&E set for bid advertisement and construction. -Notify utility agencies

7. We assume a construction cost estimate of approximately $750K which includes Design(10%) and CM (10%) services + 15% Cont.

8. The number of budgeted meetings is indicated.

9. 10. No utility mapping will be required.

11. No public meetings or Council presentations will be required.

12. No topography surveys will be required.

13. Fee assumes design completion in year 2026.

14. Task 5 - 5 Year CIP Pavement StreetSaver Update scope will continue into 2028.

15. Hourly rates shown include all indirect costs, including travel time, mileage, miscellaneous reproduction and copying costs, mailings and delivery costs.

HARRIS & ASSOCIATES
TOTAL
QA/QC

HARRIS & ASSOCIATES
Harris will identify and quantity all base failure areas. A spreadsheet will be developed for the base repair areas and inserted into the plans. The base repair locations will not be delineated on the plans but field notes will be available upon request.

BASE SERVICES
City comments at each review stage will be presented to Harris promptly and on one consolidated set of marked-up documents.

Slurry treated sheets will be identified in a key map and detailed spreadsheets will be developed to reflect the quantity takeoff for each street segment. p. 1 of 1
CD281.55.2509
January 21, 2026
Ms. Luella Gabriel
Project Manager
Harris & Associates
1401 Willow Pass Road, Suite 500
Concord, CA 94520
RE: Letter Proposal — Harris-NCE City of Cotati CIP StreetSaver Updates Dear Ms. Gabriel,
Based on recent discussions, we are providing this letter proposal to assist Harris & Associates with StreetSaver updates in support of the City of Cotati’s Capital Improvement Program (CIP) paving projects. This effort will support the StreetSaver-related tasks associated with the 2027 Street Improvements Project, including streets repackaged from the 2026 Pavement Preservation Project.

Services will focus on updating maintenance and rehabilitation information, decision trees, and scenario outputs to reflect current CIP decisions, consistent with prior CIP support efforts and to support Harris’s overall project delivery.

Scope of Services
To achieve the City’s goals and objectives we propose the following tasks:

Task 1 - Project Administration
 Provide overall project coordination and administrative support related to the StreetSaver updates.  Coordinate with Harris staff regarding data needs, assumptions, schedules, and deliverables.  Participate in up to two working meetings to review inputs, assumptions, and results.

Deliverables:
 Coordination support to facilitate completion of StreetSaver updates.

Task 2 - Maintenance and Rehabilitation Update
 Review available CIP paving information and recent maintenance and rehabilitation activities.  Update StreetSaver sections to reflect completed maintenance and rehabilitation treatments.

Deliverables:
 Maintenance History Report
Page | 2
Task 3 – Decision Tree Update
 Review existing treatments and decision tree structures in StreetSaver.  Update decision tree using unit costs and treatment information provided by Harris and/or the City.  Coordinate updates and assumptions with Harris prior to finalizing.

Deliverables:
 Updated Decision Tree
Task 4 – CIP Scenario and Map Generation
 Develop and run StreetSaver scenarios to support CIP planning and project clustering by area.  Evaluate preventive maintenance and rehabilitation strategies consistent with City’s goals.  Provide scenario outputs and summaries to support Harris’s CIP development efforts.  Generate GIS-based maps illustrating scenario results using the existing StreetSaver database configuration.

Deliverables:
 Sections Selected for Treatment report
 Network Summary & Cost Summary Reports
 Network Summary Statistic Report
 Work Plan Map generated from existing StreetSaver database Assumptions
 This scope includes up to two (2) coordination or working meetings, which will be held via web/Teams.  Harris will provide unit costs per square yard (and linear feet for crack sealing) for each treatment in the decision tree. NCE will update unit costs in StreetSaver prior to generating scenarios.  Task 4 includes up to three (3) scenario iterations.
 GIS maps will be generated using the existing StreetSaver database structure. No re-segmentation, relinking, GIS data editing, or shapefile development is included.  No field surveys are included.
 This scope is limited to StreetSaver related support for CIP paving projects.  This scope of work and associated fee are specific to this project and are separate from the City’s upcoming PTAP update.
 Services will be performed on a time-and-materials basis up to the not-to-exceed amount of $10,000.

Any work requested beyond this amount or outside the scope described in this letter will require prior written authorization from Harris & Associates and may be subject to a contract amendment or additional budget approval.

Page | 3
 Services will be performed on an as-needed basis in coordination with Harris & Associates, with timing dependent on project needs and the availability of required inputs.

Schedule
The project schedule will be coordinated with Harris & Associates and will be dependent on the availability of required inputs, City decisions, and access to the StreetSaver database. Specific milestones and delivery dates will be confirmed during project coordination.

Fee & Billing
The estimated fee shown below reflects the StreetSaver support services described in this letter proposal and will be performed on a time-and-materials basis, with a not-to-exceed amount of $10,000.

We appreciate the opportunity to support Harris & Associates on this effort. Please let us know if you have any questions or would like to discuss this scope further.

Regards,

Vijay Pulijal, PE Marissa Baclig
Principal Project Manager
Principal-inCharge Project Mgr Clerical

1.0 Project Administration 1 4 4 1,665 $

2.0 Maintenance and Rehabiliation Update 6 1,176 $

3.0 Decision Tree Update 8 1,568 $

4.0 CIP Scenario and Map Generation 28 5,591 $
$ 10,000
Hourly Breakdown by Personnel
Total Cost
Task Description