FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
1 OF 91
CITY OF CRESCENT CITY
PUBLIC WORKS DEPARTMENT
________________________________________________________
NOTICE INVITING SEALED BIDS,
SPECIAL PROVISIONS,
PROPOSAL AND CONTRACT
FRONT STREET GATEWAY IMPROVEMENTS
PHASE 1C RE-ISSUE
CRESCENT CITY, DEL NORTE COUNTY, CALIFORNIA
_______________________________________________________ For Use in Connection with CALTRANS 2024 Standard Specifications and Standard Plans, and Current Labor Surcharge and Equipment Rental Rates.
__________________________________________________________ CONTRACT NUMBER 2025-1002.33
Bids Open: August 11, 2025
Dated: July 14, 2025
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
2 OF 91
*************************************************************************************************************
IMPORTANT
SPECIAL NOTICES
The Bidder’s attention is directed to the following:
An addenda will be issued to include all Section 3 requirements required for the use of Federal Funding for a Community Development Block Grant. This addenda will be issued to allow time for the solicitation of Minority Business Enterprises and Women-owned Business Enterprises, as well as other contractor requirements.
These documents refer to an Attachment C for this information. Attachment C will be included in this future addenda.
There is a Base Bid with 116 bid items listed. This bid item total includes reserved bid items and not in contract (NIC) bid items. There are no Alternatives. A bid must be submitted for all bid items. The Contract award will be based on the lowest Base Bid.
There are two sets of Plans for this project.
o 2025 City of Crescent City Front Street Improvements Play to L Street o Crescent City Cultural Gateways and Beautification Project An on-site disposal site for clean soil disposal of excavated materials suitable for future fill construction as allowable per Coastal Development Permit. Per CDP this disposal site will be limited to permissible dates, primarily between April 15th and October 15th, 2026. Grading and erosion control for this area must be installed prior to October 15th, 2026.
All work south of the Front Street back of sidewalk is subject to the requirement of the Coastal Development Permit, included within bid documents.
The Engineering Cost Estimate is $4,750,000. This value excludes the cost of the Tolowa Cultural Trail under a separate contract and the cost of the City supplied precast drainage structures as indicated in their respective bid items.
Changes to the Plans
1. “2025.06.11 Front Street Improvements Play to L Streets Plans.pdf” Sheet S-1 corrects the 25.8 LF of 6” PVC to a 4” PVC lateral and cleanout at station 3+60.85 and a 26.2LF 6” PVC lateral to a 4” PVC lateral and cleanout at station 3+56.86.
2. Clarifying Sheet W-1. The City will supply all domestic and irrigation meters.
Clarifications to this projects specifications and plan sheets
1. Clean compactable earth spoils from either the earthwork on Front Street or the grading excavation required for the Gateway project may be placed at the designated soil waste area. No asphalt, concrete, tsunami debris, rocks larger than 6 inches in diameter, or organic materials in excess of 3 inches in diameter may be placed at this location.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
3 OF 91
2. For exterior wall demolition limits to Porte Cochere, please reference sheet L3.01, Note 31, and Sheet A2.11, Detail 1, limiting the first floor demolition to a single panel to be sawcut and removed to an overall width of 13 feet, five inches. This the only panel in the existing exterior of the Porte Cochere concrete wall to be removed.
3. Library parking lot to remain open for the duration of this project.
4. 2nd Street from K Street to L Street to remain open for the duration of the project.
5. The Chamber of Commerce offices and visitor center will remain open and be ADA compliant for the duration of the project. Any additional work to accommodate their access will be considered to be a changed condition and will be paid for as a Change Order by the City.
6. The Door Replacement shown on Sheet A2.12 is not a part of this Base Bid. This work is necessary to the contract to comply with the Second Floor Life and Safety Plan. But as this detail does not provide enough specific information to fairly bid the work, the City elects to delete all the work shown on Sheet A2.12, including the localized cross-decking handrail. This deletion will be a scope reduction to Bid Item 116, “Discovery Center Renovations”. This work will be included in a future Change Order upon selection of the successful bidding contractor.
7. No cross sections are available for the roadwork other than the typical plan sheets provided.
8. The City will not be providing the Survey for this construction project.
9. The water from dewatered excavations be dumped in the sewer system, but the City may have to restrict this disposal method based on seasonal precipitation and ground water intrusion into the sewer system.
10.Sheet L4.01 and Sheet L4.05 Details show the locations of these items. There are a total of 16 seat wall/step lights shown, 8 in the stair treads, 6 in the curved seat walls, and 2 in the seat wall facing the stairs.
11. The point of connection for the electrical elements included in the Gateway set of plans has yet to be determined. As addressed in Bid Item 108, all source wiring and conduits to electrical bid items are not included in the base bid at this time. All costs associated with this are NOT to be included in the base bid as currently shown. Once electrical drawings are available they will be issued via addendum or will be a part of a future change order.
The above special notices do not relieve the Bidder of his/her responsibility to become fully familiar with the Contract Documents including the Plans and Specifications.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
4 OF 91
CRESCENT CITY
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C
DOCUMENT 00 01 10
TABLE OF CONTENTS
IMPORTANT SPECIAL NOTICES
PART A - BIDDING AND CONTRACT REQUIREMENTS GROUP
DIVISION 00 - PROCUREMENT AND CONTRACTING REQUIREMENTS
Section Title
INTRODUCTORY INFORMATION
00 01 10 Table of Contents
PROCUREMENT REQUIREMENTS
00 10 00 Invitation to Bid
00 20 00 Instructions to Bidders
00 31 46 Permits
00 40 00 Bid
00 41 00 Bidding Schedule
00 43 13 Bid Guaranty Bond
00 43 36 Proposed Subcontractors
00 45 13 Certification of Bidder’s Experience and Qualifications 00 45 19 Non-Collusion Affidavit
00 45 21 Anti-Lobbying Certification
CONTRACTING REQUIREMENTS
00 52 00 Agreement
00 61 05 Faithful Performance Bond
00 61 10 Payment Bond
00 62 00 Certificates and Other Forms
00 72 00 General Conditions
PART B – TECHNICAL SPECIFICATIONS GROUP
GENERAL REQUIREMENTS SUBGROUP
DIVISION 01 – GENERAL CONDITIONS AND REQUIREMENTS
01 00 00 General Requirements
01 11 00 Summary of Work
01 20 00 Measurement and Payment
01 21 43 Time Allowances
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
5 OF 91
01 25 00 Substitution Procedures
01 33 00 Submittals
01 45 00 Quality Control
01 45 29 Testing Laboratory Services
01 55 26 Temporary Traffic Control
01 56 39 Temporary Tree and Plant Protection
01 57 23 Water Pollution Prevention
01 71 33 Protection of Property
01 74 23 Final Cleaning
DIVISION 02 – EXISTING CONDITIONS
02 00 00 Existing Conditions
02 01 00 Maintenance of Existing Conditions
02 05 00 Demolition and Removal
02 22 10 Trench and Backfill
02 30 00 Earthwork
02 41 00 Demolition
02 41 19 Selective Demolition
DIVISION 03 – CONCRETE
03 10 00 Concrete Formwork
03 20 00 Concrete Reinforcement
03 30 00 Cast In Place Concrete
03 48 00 Precast Concrete
DIVISION 04 – NOT USED
DIVISION 05 – METALS
05 50 00 Metal Fabrications
DIVISION 06-09 – NOT USED
DIVISION 10 – SIGNAGE
10 14 53 Traffic Signage
10 45 00 Aluminum Signs
DIVISION 11-22 – NOT USED
DIVISION 22 – STORM DRAINS
22 14 00 Storm Drains
DIVISION 23-25 – NOT USED
DIVISION 26 – ELECTRICAL
26 00 00 Electrical
26 01 00 Electrical General Requirements
26 10 00 Basic Materials and Methods
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
6 OF 91
26 40 00 Service and Distribution
26 50 00 Lighting
DIVISION 27-30 NOT USED
DIVISION 31 – EARTHWORK
31 10 00 Site Clearing
31 20 00 Earth Moving
31 22 00 Grading
31 22 13 Earthwork
31 23 17 Sheeting, Shoring & Bracing
31 23 19 Dewatering Excavations
31 23 33 Trench and Backfill
31 40 00 Shoring and Underpinning
DIVISION 32 – EXTERIOR IMPROVEMENTS
32 00 00 Exterior Improvements
32 11 00 Base Courses
32 12 00 Flexible Paving
32 13 13 Concrete Paving
32 13 16 Decorative Paving
32 13 16.15 Lithocrete Lithomosaic - NIC
32 13 73 Concrete Paving Joint Sealants
32 17 00 Paving Specialties
31 17 23 Pavement Markings
32 17 26 Tactile Warning Surfacing
32 33 00 Site Furnishings
32 84 00 Planting Irrigation
32 91 13 Soil Preparation
32 92 00 Turf & Grasses
32 93 00 Plants
32 93 10 Landscape Maintenance
DIVISION 33 – UTILITIES
33 11 13 Pipelines & Appurtenances
33 12 16 Manual Valves
33 14 00 Water Mains
33 30 00 Sanitary Drainage
33 41 00 Storm Utility Drainage Piping
DIVISIONS 34-76 – NOT USED
DIVISION 77 – STREET LIGHTING
00 77 00 Street Lighting
DIVISION 78-85 – NOT USED
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
7 OF 91
DIVISION 86 – GENERAL ELECTRICAL WORK
00 86 00 GENERAL ELECTRICAL WORK
DIVISION 87 – GENERAL ELECTRIAL SYSTEMS
00 87 00 GENERAL ELECTRICAL SYSTEMS
APPENDICES – AVAILABLE ON CITY WEBSITE
Appendix A – SHN Geotechnical Report
Appendix B – LACO Geotechnical Report
Appendix C – Busch Geotechnical Report
Appendix D – Woodward, Clyde, Sherard & Associates Geotechnical Report Appendix E – SWPPP
PART C – PLANS GROUP ENTITLED:
“FRONT STREET IMPROVEMENTS PLAY TO L STREETS” and
“CULTURAL GATEWAYS AND BEAUTIFICATION PROJECT”
ATTACHMENT A – APPLICABLE CURRENT FEDERAL PREVAILING WAGE RATES https://sam.gov/wage-determination/CA20230004/1
ATTACHMENT B – STATE PREVAILING WAGE RATES
https://www.dir.ca.gov/OPRL/DPreWageDetermination.htm
ATTACHMENT C – CDBG LABOR COMPLIANCE
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
8 OF 91
SECTION 00 10 00
INVITATION TO BID
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT # 2025-1002.33
The previously issued “FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C” construction project requesting Invitations to Bid has been cancelled due to material changes in the Scope and bidding requirements. This Invitation to Bid under the new project named “FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE” is the reissuance of a similar project, including revised plan sets and bidding requirements. This Invitation to Bid is available to all potential qualified bidders. There is a mandatory pre-bid walkthrough required of all contractors seeking to bid this project.
Sealed bids for the construction of the FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE will be received by the Owner, the City of Crescent City, at the Crescent City Public Works Department office until 2:00 PM on August 11, 2025. The bids will be opened publicly and read aloud at 2:00 PM on the same day in the Public Works Office. Bids must be addressed to:
City of Crescent City
Public Works Department
377 J Street
Crescent City, CA 95531
Bids must be labeled "Bid for the ‘FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE 2025-1002.33”.
Contractor must be licensed as an (A) General Engineering Contractor by the California Contractors State License Board to bid on this project.
This project includes street and utility improvements on Front Street between Play and L Street, and K Street between Front Street and Second Street. This project also includes Beachfront Park Gateway improvements requiring excavation and grading, pathways, landscaping, and cultural and art element installations on the south side of Front Street between Play Street and L Street.
The street work includes the furnishing of the labor, materials, and equipment for the installation of a replacement storm drain system, replacement water mains, fire hydrants, valving and services, sewer main installation, gas line relocation, irrigation piping and controls, curbs, gutters, sidewalks, and pedestrian crossings, a reconstructed road section for Front and K Streets, and new street lighting fixtures, all in accordance with the drawings and specifications.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
9 OF 91
The Gateway improvements include demolition, earthwork and grading around the Cultural Center on Front Street, new concrete pathways for building access and a cultural trail, decorative concrete elements and concrete retaining/seat walls, irrigation piping and controls, landscaping, area lighting, installation of kiosks with informational and cultural signage, and the construction of foundations for Gateway signage as well as cultural trail structural elements.
The project manual may be inspected at the following locations:
City of Crescent City
Public Works Department
377 J Street
Crescent City CA 95531
(707) 464-9506
Humboldt Builders Exchange
624 C Street
Eureka, CA 95501
(707) 442-3708
Shasta Builders Exchange
2985 Innsbruck Drive
Redding, CA 96003
(530) 221-5556
Placer County Contractors Association
10656 Industrial Ave #160
Roseville, CA 95678
(916) 771-7229
Medford Builders Exchange
2330 Crater Lake Ave.
Medford, OR 97504
(541) 773-5327
Dodge Data & Analytics
www.construction.com
(800) 393-6343
Construction Bidboard
11622 El Camino Real #100
San Diego, CA 92130
(619) 688-0588
Full-size and half-size copies of the project manual may be obtained from the City of Crescent City Public Works Department located at 377 J Street, Crescent City, CA 95531, FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
10 OF 91
(707) 464-9506. One set of full-size plans will be made available at the City office to each bidding contractor or may be obtained on-line. Specifications should be downloaded.
A mandatory pre-bid conference will be held at the City’s Cultural Center located at 1001 Front Street, Crescent City CA 95531 on July 30, 2025 at 10:30 am.
Bidders must correctly prepare and submit the documents listed in Section 00 40 00, Bid. Each bid must be accompanied by a bid guaranty bond, or a certified or cashier's check payable to the order of the Owner in an amount not less than ten percent (10%) of the amount of the bid as a guaranty that the bidder will execute the contract if it is awarded in conformity with the bid form. The successful bidder will also be required to furnish performance and payment bonds, each in an amount not less than one hundred percent (100%) of the contract price in the form provided herein.
At the successful Bidder's option, securities may be substituted for the required retention, in accordance with the provisions of Section 22300 of the California Public Contract Code.
The Owner reserves the right to reject any or all bids and to determine which bid is, in the Owner's judgment, the lowest responsive bid. The Owner also reserves the right to waive any immaterial deviations in any bid and to delete items listed in the bid.
Bids received after the time established for receiving bids will not be considered and will be returned unopened. Except as provided in paragraph 00 20 00-1.04(A), no bidder may withdraw his or her bid after the time established for receiving bids or before the award and execution of the contract, unless the award is delayed for a period exceeding ninety (90) calendar days.
This is a Public Works Project subject to the rate of prevailing wages as established by the California Department of Industrial Relations and the U.S. Department of Labor.
Bidders are notified that the higher of either the Davis-Bacon or the State prevailing wage rate shall apply.
This project is subject to compliance monitoring and enforcement by the Department of Industrial Relations and the U.S. Department of Labor. Full original payrolls must be provided to the City on the WH-347 form as provided in the Labor Compliance Book as well as file or hard copies of DIR weekly payroll reporting.
Bidders are hereby notified that pursuant to Section 1773 et seq. of the California Labor Code, the Owner has obtained from the Director of the Department of Industrial Relations the general prevailing rate of wages and employer payments for health and welfare, vacation, pension, and similar purposes for work to be done within Del Norte County, California. Owner has also provided Davis-Bacon wage rates. Regulations regarding the application of these wage rates are given in paragraph 00 20 00-1.12.
No contractor or subcontractor may be listed on a bid proposal for a public works project unless registered with the Department of Industrial Relations pursuant to Labor FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
11 OF 91
Code section 1725.5 [with limited exceptions from this requirement for bid purposes only under Labor Code section 1771.1(a)].
No contractor or subcontractor may be awarded a contract for public work on a public works project unless registered with the Department of Industrial Relations pursuant to Labor Code section 1725.5.
This agreement is for services related to a project that is subject to the Build America, Buy America Act (BABAA) requirements under Title IX of the Infrastructure Investment and Jobs Act (“IIJA”), Pub. L. 177-58. Absent an approved waiver, all iron, steel, manufactured products, and construction materials used in this project must be produced in the United States, as further outlined by the Office of Management and Budget’s Memorandum M-22- 11, Initial Implementation Guidance on Application of Buy America Preference in Federal Financial Assistance Programs for Infrastructure, April 18,2022.
This project is in-part funded through a Community Development Block Grant (CDGB) and therefore compliance with “SECTION 3” IS REQUIRED. Compliance with the provisions of Section 3 of the HUD Act of 1968, as amended, and as implemented by the regulations set forth in 24 CFR Part 75, and all applicable rules and orders issued hereunder prior to the execution of this Agreement, are to be a condition of this contract and binding upon the Contractor and any subcontractors.
The Contractor further agrees to ensure that opportunities for training and employment arising in connection with a housing rehabilitation, housing construction, or other public construction project are given to low- and very low-income persons residing within the metropolitan area in which the CDBG-funded project is located; where feasible, priority should be given to low- and very low-income persons within the service area of the project or the neighborhood in which the project is located, and to low- and very lowincome participants in other HUD programs; and award contracts.
Date: 7-14-25 By:
David Yeager
Public Works Director
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
13 OF 91
SECTION 00 20 00
INSTRUCTIONS TO BIDDERS
1.01 INSPECTION OF SITE
Bidders are required to inspect the site of the work to satisfy themselves by personal examination or by such other means as they may prefer, of the location of the proposed work, and of the actual conditions of and at the site of work. Bidders should plan to inspect the site of the work during the pre-bid meeting and can schedule additional time by special arrangement with the Owner.
Entrance by bidders to the site of the work for purposes of making exploratory excavations will be by special arrangement with the Owner and under conditions established by the Owner. If, during the course of his or her examination, a bidder finds facts or conditions which appear to be in conflict with the letter or spirit of the project manual, he or she may apply to the Owner, in writing, for additional information and explanation before submitting a bid.
Submission of a bid by the bidder is an acknowledgment that, if awarded the contract, bidder has relied and is relying on bidder’s own examination of (1) the site of the work, (2) access to the site, and (3) all other data and matters requisite to the fulfillment of the work and on his or her own knowledge of existing facilities on and in the vicinity of the site of the work to be constructed under the contract.
The information provided by the Owner is not intended to be a substitute for, or a supplement to the independent verification by the bidder to the extent such independent investigation of site conditions is deemed necessary or desirable by the bidder. Bidder acknowledges that he or she has not relied upon Owner-furnished information regarding site conditions in preparing and submitting a bid.
1.02 EXAMINATION OF PROJECT MANUAL
Each bidder must thoroughly examine and be familiar with those contract documents contained in the project manual. Submission of a bid constitutes acknowledgment, upon which the Owner may rely, that the bidder has thoroughly examined and is familiar with the project manual. Failure or neglect of a bidder to examine any of the contract documents contained in the project manual in no way relieves bidder from any obligation with respect to his bid or to the contract. No claim for additional compensation will be allowed that is based upon a lack of knowledge of the contract documents or the work.
1.03 INTERPRETATION OF PROJECT MANUAL
Bidders, prospective subcontractors, manufacturers, and suppliers may request interpretation of the project manual prior to bid opening. Requests for interpretation must be directed in writing to David Yeager, Director of Public Works, [email protected], 377 J Street, Crescent City, CA 95531 (707) 464-9506. Requests to clarify the source of FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
14 OF 91
materials, equipment, suppliers, or any other matter that does not modify, change, increase, or decrease the scope of work, requires no action by the Owner other than a response to the bidder requesting the clarification. Requests to clarify possible ambiguous, conflicting, or incomplete statements or designs, or any other clarification that modifies, changes, increases or decreases the scope of work, requires issuance of an addendum by the Owner for the interpretation to become effective.
Reference information has been made available on the City’s website that includes information used by the Engineer to prepare the Contract. The information provided on the website is for use by bidder during preparation of the bid and execution of the Contract. The Owner disclaims responsibility for the interpretation by bidders of the reference information.
In some cases, the information was prepared for design purposes and is not intended to provide all the information required by the bidder to tender a bid, construct the system, and provide start up and commissioning services. Reference information is available on the City’s website https://www.crescentcity.org/rfp_bid.html and includes:
Plans
Specifications
Appendices
o Appendix A – SHN Geotechnical Report
o Appendix B – LACO Geotechnical Report
o Appendix C – Busch Geotechnical Report
o Appendix D – Woodward, Clyde, Sherard & Associates Geotechnical Report o Appendix E – SWPPP
Attachment A: Applicable Current Federal Prevailing Wage Rates Attachment B: State Prevailing Wage Rates
Attachment C: Section 3 and CDBG Labor Compliance Program
1.04 BID DOCUMENTS
A. BID FORMS:
1. GENERAL: Bids must be made on the blank bid forms prepared and provided by the Owner. Bids must give the prices proposed, both in writing and in figures, must give all other information requested, and must be signed by the bidder or his authorized representative, with his address.
2. BID PRICES: Bid prices must include everything necessary for the completion of the work including, but not limited to, providing the materials, equipment, tools, plant and other facilities, and the management, superintendence, labor and services, and bonds. Bid prices must include allowance for federal, state, and local taxes. In the event of a difference between a price quoted in words and a price quoted in figures for the same quotation, the words are the amount bid. In the event that the product of a unit price and an estimated quantity does not equal the extended amount quoted, the unit price governs, and the correct product of the unit price and the estimated quantity is deemed to be the amount bid. If the sum of two or more items in a bidding schedule does not equal the total amounts FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
15 OF 91
quoted, the individual item amounts govern, and the correct total is deemed to be the amount bid.
3. BIDDER'S SIGNATURE AND AUTHORITY: If the bid is made by an individual, his or her name, signature, and post office address must be shown; if made by a firm or partnership, the name and post office address of the firm or partnership, a list of the partners, and the signature of at least one of the general partners must be shown; if made by a corporation, the bid must show the name of the state under the laws of which the corporation is chartered, the name and post office address of the corporation, and the title of the person who signs on behalf of the corporation. Any person signing the bid must certify that they are duly authorized to execute contracts on behalf of the bidder.
4. BID IRREGULARITIES: Each bid and the information requested, bound in the project manual, must be enclosed in a sealed envelope, and labeled as specified in the Invitation to Bid. Bidders are warned against making erasures or alterations of any kind, and bids containing omissions, erasures, or irregularities of any kind may be rejected. No oral, telegraphic, or telephonic bids or modifications will be considered.
5. MODIFICATION OF BID: Modification of a bid already received will be considered only if the modification is received prior to the time established for receiving bids.
Modifications must be made in writing, executed, and submitted in the same form and manner as the original bid.
6. WITHDRAWAL OF BIDS: Within five business days after the opening of bids, a bidder may withdraw his or her bid, if he or she establishes to the Owner's satisfaction that a mistake was made in preparing the bid. A bidder who wants to withdraw must give written notice to the Owner, specifying, in detail, how the mistake occurred and how the mistake made the bid materially different than it was intended to be. Withdrawal is not permitted for mistakes resulting from errors in judgment or carelessness in inspecting the site of the work or in reading the project manual.
7. MAJOR EQUIPMENT ITEMS: Certain items of major equipment to be provided under this contract are shown on the plans. The bidder must provide the name of the manufacturer of the equipment to be provided for all major equipment. Only one manufacturer may be indicated for each item. By so indicating, the bidder warrants that equipment manufactured and/or supplied by the named manufacturer will be provided on the project unless review of submittal information or performance under tests reveals that the manufacturer is unresponsive to the contract. Failure to indicate a manufacturer for any equipment may render the bid unresponsive to the invitation to bid and may be a basis for rejection of the bid.
The arrangements specified on the drawings are based on a particular manufacturer's equipment. Where the Contractor selects a manufacturer whose equipment arrangement is different than specified, the total amount listed in the bid must provide for a complete operating installation for each equipment item listed, including any and all changes and additions in structure, piping, buildings, mechanical, electrical and control systems and accessories required to accommodate the listed manufacturer's equipment. The bid must FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
16 OF 91
also include the preparation and submission of detailed drawings, calculations, and manufacturer's data to allow evaluation of the proposed equipment and to show all modifications to the work as necessary to accommodate the proposed manufacturer's equipment.
In the event that the Owner, at its sole discretion, determines that the equipment of the manufacturer listed by the Contractor and submitted for review does not meet the requirements of the contract, the Contractor must select and submit for review equipment of another manufacturer which does meet the contract, and no increase in the total amount of the contract will be allowed.
B. ALTERNATIVE MATERIALS AND EQUIPMENT:
The bidder may offer a deductive price to the Owner for supplying alternative or substitute equipment or material for items specified or shown in the plans by listing the specification section, item description, manufacturer, and deductive amount as a supplement to the bid. The bid must be based on supplying equipment or material from manufacturers or suppliers specified or shown on the plans. Alternative or substitute equipment or material will be considered by the Owner after contract award and will not be used in determining the basis of award. Selection of any offered alternate or substitution will be at the Owner’s sole discretion and will be accomplished by issuing a deductive change order for an amount agreed upon.
Manufacturers or suppliers of materials and equipment may offer an alternative product to the Contractor and request that alternatives to specified products be considered equal. Inclusion of such alternatives in the bid is the responsibility of the Contractor.
Inclusion should only be considered if the Contractor believes the offered alternative is equal in quality to the specified product. After award of contract, such offers of alternative products will be reviewed and processed as a substitution provided under paragraph 00 72 00-4.05.
Any request for substitute or “or equal” shall include the Manufacturer’s Certification of compliance with the Build America, Buy America Act (BABAA) requirements mandated by Title IX of the Infrastructure Investment and Jobs Act (“IIJA”), Pub. L. 177-58.
C. BID GUARANTY:
The bid form must be accompanied by a bid guaranty bond provided by a guaranty company authorized to carry on business in the State of California for payment to the Owner in the sum of at least ten (10) percent of the total amount of the bid price, or, alternatively, by a certified or cashier's check, payable to the Owner in the sum of at least ten (10) percent of the total amount of the bid price. The bond must be executed by a duly licensed surety company, listed in the latest Circular 570 of the United States Treasury Department as being acceptable as surety on federal bonds. The bid guaranty bond must be provided on the form included in Section 00 43 13 of this project manual. The amount payable to the Owner under the bid guaranty bond or the certified or cashier's check, as the case may be, must be forfeited to the Owner as liquidated damages in case of a failure or neglect of the bidder to furnish, execute, and deliver to the Owner the required performance and payment bonds FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
17 OF 91
provided respectively in Sections 00 61 05 and 00 61 10, the evidences of insurance, and to enter into, execute, and deliver to the Owner the agreement on the form provided in Section 00 52 00, within ten (10) calendar days after receiving written notice from the Owner that the award has been made and the agreement is ready for execution.
D. LIST OF SUBCONTRACTORS:
Each bidder must have listed, on the form provided in Section 00 43 36, the name, address, and description of the work, of each subcontractor to whom the bidder proposes to subcontract portions of the work. (Note: All subcontractors must be listed no matter how small the amount of the subcontract). For the purpose of this paragraph, a subcontractor is defined as one who contracts with the Contractor to provide materials and labor, labor only, or who specially fabricates and installs a portion of the work or improvement according to drawings contained in the project manual. Listings and subsequent substitutions, if any, must be done in conformance with the Subletting and Subcontracting Fair Practices Act, commencing at Section 4100 of the Public Contract Code of the State of California. Failure to list subcontractors may render a bid unresponsive and may be grounds for rejection of the bid.
E. HUD SECTION 3 DOCUMENTATION:
This project is partially funded by the State Department of Housing and Community Development (HCD) and the Federal Department of Housing and Urban Development (HUD) and is subject to Section 3 of the Housing and Urban Development Act of 1968 as amended, 12 U.S.C. 1702 u (Section 3).
Failure to complete and provide these forms could result in the bid being considered unresponsive. Bidders must provide completed Section 3 documents as provided in this document.
Bidder’s Proposed Section 3 Contracts/Subcontracts
Bidder’s Section 3 Proposed New Hires
F. HUD SECTION 3 COMPLIANCE
1. Compliance with the provisions of Section 3 of the HUD Act of 1968, as amended, and as implemented by the regulations set forth in 24 CFR Part 75, and all applicable rules and orders issued hereunder prior to the execution of this Agreement, are a condition of this contract and binding upon the Contractor and any subcontractors. Failure to fulfill these requirements will subject the Owner, the Contractor and any subcontractors, their successors and assigns, to those sanctions specified by the Agreement through which Federal assistance is provided. The Contractor certifies and agrees that no contractual or other disability exists that would prevent compliance with these requirements.
2. The Contractor further agrees to comply with these “Section 3” requirements and to include the following language in all subcontracts executed under this Agreement:
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
18 OF 91
“The work to be performed under this Agreement is a project assisted under a program providing direct Federal financial assistance from HUD and is subject to the requirements of Section 3 of the Housing and Urban Development Act of 1968, as amended (12 U.S.C. 1701 et seq.). Section 3 requires that to the greatest extent feasible opportunities for training and employment be given to low- and very low-income residents of the project area, and that contracts for work in connection with the project be awarded to business concerns that provide economic opportunities for low- and very low-income persons residing in the metropolitan area in which the project is located.”
3. The Contractor further agrees to ensure that opportunities for training and employment arising in connection with a housing rehabilitation (including reduction and abatement of lead-based paint hazards), housing construction, or other public construction project are given to low- and very low-income persons residing within the metropolitan area in which the CDBG-funded project is located; where feasible, priority should be given to lowand very low-income persons within the service area of the project or the neighborhood in which the project is located, and to low- and very low-income participants in other HUD programs; and award contracts for work undertaken in connection with a housing rehabilitation (including reduction and abatement of lead-based paint hazards), housing construction, or other public construction project to business concerns that provide economic opportunities for low- and very low-income persons residing within the metropolitan area in which the CDBG-funded project is located; where feasible, priority should be given to business concerns that provide economic opportunities to low- and very low-income residents within the service area or the neighborhood in which the project is located, and to low- and very low-income participants in other HUD programs.
4. The Contractor certifies and agrees that no contractual or other legal incapacity exists that would prevent compliance with these requirements. a. NOTIFICATIONS: The Contractor agrees to send to each labor organization or representative of workers with which it has a collective bargaining agreement or other contract or understanding, if any, a notice advising said labor organization or worker’s representative of its commitments under this Section 3 clause and shall post copies of the notice in conspicuous places available to employees and applicants for employment or training.
b. SUBCONTRACTS: The Contractor will include this Section 3 clause in every subcontract and will take appropriate action pursuant to the subcontract upon a finding that the subcontractor is in violation of regulations issued by the grantor agency. Contractor will not subcontract with any entity where it has notice or knowledge that the latter has been found in violation of regulations under 24 CFR Part 75 and will not let any subcontract unless the entity has first provided it with a preliminary statement of ability to comply with the requirements of these regulations.
G. SMALL AND MINORITY BUSINESSES, WOMEN’S BUSINESS
ENTERPRISES AND LABOR SUPLUS AREA FIRMS:
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
19 OF 91
If subcontractors are to be used, then Contractor must take the following affirmative steps to assure that minority businesses, women’s business enterprises, and labor surplus area firms are used when possible:
1. Placing qualified small and minority businesses and women's business enterprises on solicitation lists;
2. Assuring that small and minority businesses, and women's business enterprises are solicited whenever they are potential sources;
3. Dividing total requirements, when economically feasible, into smaller tasks or quantities to permit maximum participation by small and minority businesses, and women's business enterprises;
4. Establishing delivery schedules, where the requirement permits, which encourage participation by small and minority businesses, and women's business enterprises; and
5. Using the services and assistance, as appropriate, of such organizations as the Small Business Administration and the Minority Business Development Agency of the Department of Commerce.
1.05 BIDDER'S CERTIFICATIONS
A. QUALIFICATION OF BIDDER:
Bidder must certify that he or she is, at the time of bidding, and will be, throughout the period of the contract, licensed under the provisions of Chapter 9, Division 3 of the Business and Professions Code of the State of California to do the type of work contemplated in the project manual. Bidder must further certify that he or she is skilled and regularly engaged in the general class and type of work called for in the project manual.
The bidder must also certify that he or she is knowledgeable of the unusual and peculiar hazards associated with the general class and type of work required to construct the specified project within the terms given in the project manual. Bidder must be competent and skilled in the protective measures necessary for the safe performance of the construction work with respect to such unusual and peculiar hazards.
B. ADDENDA:
Each bid form must include specific acknowledgment, in the space provided, of receipt of all addenda issued and mailed by the Owner during the bidding period. Failure to so acknowledge may result in the bid being rejected as not responsive.
C. NONCOLLUSION AFFIDAVIT:
Pursuant to Section 7106 of the California Public Contract Code, a noncollusion affidavit is required on any public works contract of a public entity. The noncollusion affidavit must be executed by the bidder and notarized on the form provided in Section 00 45 19 of this project manual.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
20 OF 91
D. ANTI-LOBBYING CERTIFICATION:
The bidder shall require that the language of this certification be included in all contracts or subcontracts entered into in connection with this project and that all subrecipients shall certify and disclose accordingly. The anti-lobbying certification must be executed by the bidder on the form provided in Section 00 45 21 of this project manual.
E. DEBARMENT AND SUSPENSION CERTIFICATION.
Contractor’s signature affixed to the BID form shall constitute a certification under penalty of perjury under the laws of the State of California, that Contractor or any person associated therewith in the capacity of owner, partner, director, officer or manager:
6. Is not currently under suspension, debarment, voluntary exclusion, or determination of ineligibility by any federal agency;
7. Has not been suspended, debarred, voluntarily excluded, or determined ineligible by any federal agency within the past three (3) years;
8. Does not have a proposed debarment pending; and
9. Has not been indicted, convicted, or had a civil judgment rendered against it by a court of competent jurisdiction in any matter involving fraud or official misconduct within the past three (3) years.
Any exceptions to this certification must be disclosed to the Owner. Exceptions will not necessarily result in denial of recommendation for award but will be considered in determining responsibility. Disclosures must indicate the party to whom the exceptions apply, the initiating agency, and the dates of agency action.
Exceptions to the Federal Government excluded parties
(https://sam.gov/content/home) maintained by the U.S. General Services Administration are to be determined by FHWA.
F. IRAN CONTRACTING AND STATE OF CALIFORNIA EXECUTIVE ORDER N-6-22:
Bidders must not be on the most current DGS list of Entities Prohibited from Contracting with Public Entities in California per the Iran Contracting Act, 2010, before the Agreement has been executed, unless the bidder is exempted from the certification requirement by Public Contract Code Section 2205(c) or (d). If claiming an exemption, the bidder shall provide written evidence that supports an exemption under Public Contract Code Section 2203(c) or (d) before execution of the contract. Additionally, and to the extent applicable, the Owner shall adhere to State of California Executive Order N-6-22, issued on March 4, 2022, with regard to bidders.
1.06 POSTPONEMENT OF OPENING
The Owner reserves the right to postpone the date and time for receiving and/or opening of bids at any time prior to the date and time established in the Invitation to Bid. Postponement notices will be transmitted via email or mailing service to bidders in the form of addenda.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
21 OF 91
1.07 REJECTION OF BIDS
A. IRREGULAR BIDS:
The Owner reserves the right to reject bids that are incomplete, obscure, or irregular; bids that omit a bid on any one or more items for which bids are required; bids that omit unit prices if unit prices are required; bids in which unit prices are unbalanced in the opinion of the Owner; bids accompanied by insufficient or irregular bid security; and bids from bidders who have previously failed to perform properly or to complete on time contracts of any nature.
B. COLLUSION:
If the Owner has reason to believe that collusion exists among bidders, the Owner will reject the bids of the known participants in such collusion and may, at its option, require that all bidders certify under penalty of perjury that no collusion has occurred or exists. The Owner also, at its option, may reject all bids received.
1.08 RETURN OF BID GUARANTIES
Within 15 calendar days after the bids are opened, the Owner will return the bid guaranties accompanying the bids which are not to be considered in making the award. All other bid guaranties will be held until the contract has been fully executed. After that time, they will be returned to the respective bidders whose bids they accompanied.
1.09 AWARD OF CONTRACT
Within ninety (90) calendar days after the date of opening bids, the Owner will act either to accept a bid or to reject all bids. Acceptance of a bid will be evidenced by a notice of award of contract in writing, delivered in person, or by certified mail, to the bidder whose bid is accepted. No other act of the Owner constitutes acceptance of a bid. The award of contract obligates the bidder whose bid is accepted to furnish performance and payment bonds and evidence of insurance, and to execute the agreement set forth in the project manual. The Owner will award a contract to the lowest responsible bidder that submits a responsive bid.
1.10 BASIS OF AWARD
The award will be made by the Owner to that responsive, responsible, qualified bidder submitting the lowest bid. Inclusion of bid items in the final contract awarded will be at the Owner's sole discretion.
The Contract will be awarded, subject other provisions herein, to the Bidder submitting the lowest Base Bid.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
22 OF 91
If, at any time the contract is to be awarded, the total of the lowest acceptable bid exceeds the funds then estimated by the Owner as available, the Owner may reject all bids or take such other action as best serves the Owner's interests.
The Owner reserves the right to accept or reject any or all bids, and to waive any informalities and immaterial irregularities in said bids, delete certain items from the bid and postpone the award decision date to one that is mutually agreeable to the Owner and the lowest responsible bidder.
1.11 EXECUTION OF CONTRACT
Within 10 calendar days after receiving written notice of the award of the contract, the agreement as provided in Section 00 52 00 must be executed in quadruplicate by the successful bidder and returned with the performance and payment bonds and evidence of insurance. After execution by the Owner, one copy of the agreement will be returned to the Contractor.
1.12 LABOR REQUIREMENTS
A. PREVAILING WAGE RATES AND APPRENTICESHIPS:
Employees of the Contractor and all subcontractors engaged on this project shall be compensated at or above the current highest prevailing wage rate determination issued by the Director of Industrial Relations and the Department of Labor. Copies of the applicable current Federal prevailing wage rates are provided in Attachment A to the project specifications. State prevailing wage rates are to be obtained from the Department of Industrial Relation website and are also provided in Attachment B to the project specifications. The Contractor and all subcontractors shall pay the higher wage rate in each craft, classification, or worker type. Wages to be paid laborers and mechanics on this project must be no less than the minimum either as determined by the Secretary of Labor or as determined by the Director of Industrial Relations in accordance with California Labor Code, Sections 1770, 1773 and 1773.1. Copies of the applicable prevailing wage rates must be posted at the work site.
Compliance with Section 1777.5 of the Labor Code, dealing with the employment of properly registered apprentices in all applicable occupations involved in the construction of this project, shall remain the responsibility of the Contractor. No apprentice may be placed on the job without prior submission of apprenticeship registration, allowable pay rates and approval of Owner’s Representative. Failure to obtain prior approval will require payment of journeyman wages until approval is received.
All apprentices must be registered with both the Department of Labor and the Department of Industrial Relations. All apprentices must be registered with both the Department of Labor and the Department of Industrial Relations.
B. SAFETY AND HEALTH REGULATIONS FOR CONSTRUCTION:
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
23 OF 91
The Contractor must comply with all state and federal laws and county and local ordinances and regulations which in any manner affect the health or safety of those engaged or employed in the work.
C. EMPLOYMENT PERMITS:
The Contractor must provide an employment permit prior to the initiation of any practices, work, method, or operation in accordance with Labor Code Section 6500.
1.13 SOIL INFORMATION
Subsoil investigations have been conducted at the site of the work, and the corresponding reports are included as a reference document available on the City’s website. Soil investigations were conducted for design purposes. The data shown in the reports are for subsurface conditions found at the time of the investigation.
The Owner disclaims responsibility for the interpretation by bidders of data, such as projecting or extrapolating from the test holes to other locations on the site of the work soil bearing values and profiles, soil stability and the presence, level, and extent of underground water for subsurface conditions during construction operations.
1.14 SHEETING, SHORING AND BRACING
In accordance with the provisions of Section 6707 of the California Labor Code, each bidder must list, in the bid item indicated, the amount included in his bid for trench and excavation, adequate sheeting, shoring, and bracing, or equivalent method for the protection of life and limb, work which must conform to applicable State of California Construction Safety Orders.
By listing this sum in his bid, the bidder warrants that his action does not convey tort liability to the Owner, the Owner's employees, or the Construction Manager.
1.15 OFFER OF ASSIGNMENT OF ANTITRUST ACTIONS
As provided by Sections 4550 and 4552 of the California Government Code, in submitting a bid to a public purchasing body, the bidder offers and agrees that if the bid is accepted, it will assign to the Owner all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Sec. 15) or under the Cartwright Act (Chapter 2 [commencing with Section 16700] of Part 2 of Division 7 of the Business and Professions Code), arising from purchases of goods, materials, or services by the bidder for sale to the purchasing body pursuant to the bid. Such assignment is made and becomes effective at the time the purchasing body tenders final payment to the bidder.
1.16 SALES AND USE TAX
Bidder is directed to refer to General Conditions paragraph 00 72 00-2.04 K for sales and use tax requirements for this project.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
24 OF 91
1.17 BID PROTEST PROCEDURES
Crescent City Municipal Code
Chapter 14.24 Bid Protest Procedures
14.24.010 Application.
The protest procedures contained in this chapter apply to formal sealed bids and competitive proposals only. For purposes of this chapter any person who submitted either a bid or proposal is referred to as a “bidder” and any submitted bid or proposal is referred to as a “bid.” (Ord. 808 § 2, 2019)
14.24.020 Eligibility to protest.
Only a bidder who has actually submitted a bid is eligible to submit a bid protest against another bidder. Subcontractors are not eligible to submit bid protests. A bidder may not rely on the bid protest submitted by another bidder but must timely pursue its own protest. (Ord. 808 § 2, 2019)
14.24.030 Bid protest deadline.
Any bid protest must be in writing and received by the city before five p.m. no later than two business days following the bid opening (the “bid protest deadline”). The protesting bidder may submit the bid protest by personal delivery, courier, or facsimile transmission. (Ord. 808 § 2, 2019)
14.24.040 Bid protest—Contents and procedure.
A. Protest Contents. The bid protest must contain a complete statement of the basis for the protest and all supporting documentation. Material submitted after the bid protest deadline will not be considered. The protest must refer to the specific portion or portions of the contract documents upon which the protest is based. The protest must include the name, address, email address and telephone number of the person representing the protesting bidder if different from the protesting bidder.
B. Copy to Protested Bidder. A copy of the protest and all supporting documents must be concurrently transmitted by facsimile transmission or electronic mail (email), before the bid protest deadline, to the protested bidder. (Ord. 808 § 2, 2019)
14.24.050 Response to bid protest—Contents.
A. Response to Protest. The protested bidder may submit a written response to the protest, provided the response is received by the city before five p.m., within two business days after the bid protest deadline or after actual receipt of the bid protest, whichever is sooner (the “response deadline”). The protested bidder may submit the FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
25 OF 91
response to bid protest by personal delivery, courier, or facsimile transmission. The response must include all supporting documentation. Material submitted after the response deadline will not be considered. The response must include the name, address, email address, and telephone number of the person representing the protested bidder if different from the protested bidder.
B. Copy to Protesting Bidder. A copy of the response and all supporting documents must be concurrently transmitted by facsimile transmission or electronic mail (email), before the bid protest deadline, to the protesting bidder. (Ord. 808 § 2, 2019)
14.24.060 Decision.
Within five business days of the response deadline, the city manager will issue a decision on the bid protest. The decision of the city manager is final. (Ord. 808 § 2, 2019)
14.24.070 Exclusive remedy.
The procedure and time limits set forth in this section are mandatory and are the bidder’s sole and exclusive remedy in the event of bid protest. A bidder’s failure to comply with these procedures will constitute a waiver of any right to further pursue a bid protest, including filing a Government Code claim or initiation of legal proceedings. (Ord. 808 § 2, 2019)
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
26 OF 91
SECTION 00 31 46
PERMITS
PART 1 – GENERAL
1.01 The following permits for this project must be obtained and paid for by the Contractor.
A. City Encroachment Permit (fee waived)
B. Crescent City Business License
C. General Permit for Storm Discharges Associated with Construction and Land Disturbance Activities (City to pay fees)
D. Coastal Development Permit
E. 401 Water Quality Permit
F. 404 Army Corps of Engineers
G. Other permits as required by State and Federal laws, rules and regulations.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION (NOT USED)
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
27 OF 91
SECTION 00 40 00
BID
City of Crescent City Date:
377 J Street
Crescent City, CA 95531
The undersigned, as bidder, declares that he or she has have received and examined the project manual entitled “FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE” and will contract with the Owner, on the form of agreement provided herewith, to do everything required for the fulfillment of the contract for the construction of the project at the prices and on the terms and conditions herein contained.
The undersigned agrees that the contract documents include Parts A, B and C of this project manual as well as the referenced federal, state, and local agency requirements, specifically including Attachment C – CDBG Labor Compliance and Section 3 requirements.
The undersigned also agrees that the following are part of this bid:
Section Title
00 40 00 Bid
00 41 00 Bidding Schedule
00 43 13
00 43 36
00 45 13
00 45 19
00 45 21
Bid Guaranty Bond
Proposed Subcontractors
Certification of Bidder's Experience and Qualifications Non-Collusion Affidavit
Anti- Lobbying Certification
Section 3 Requirements (Contractor, Subcontractor, and New Hires) MBE/WBE Outreach documentation (Good Faith Effort) will be required from low bidder.
The undersigned acknowledges that addenda numbers through have been received and have been examined as part of the project manual.
Attached is a bid guaranty bond duly completed by a guaranty company authorized to carry on business in the State of California in the amount of at least ten (10) percent of the total amount of our bid, or alternatively, there is attached a certified or cashier's check payable to the Owner in the amount of at least ten (10) percent of the total amount of our bid.
By submitting this bid, I, the undersigned, verify that Contractor is not listed on the governmentwide exclusions list in the System for Award Management (SAM).
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
28 OF 91
Bidder is familiar with all laws and regulations that may affect cost, progress, and performance of the work, including BABAA requirements.
If the bid is accepted, I, the undersigned, certify that I have authority to sign the agreement without qualifications and to furnish the performance and payment bonds and the required evidence of insurance within 10 calendar days after receiving written notice of the award of the contract.
I, the undersigned, further agree, that if the bid is accepted and a contract for performance of the work is entered into with the Owner, to so plan the work and to prosecute it with such diligence that the work will be completed within the time stipulated. It is expressly understood that time is of the essence.
The bidder declares that the Contractor’s license number and expiration date and representations made therein are stated under penalty of perjury under the laws of the State of California.
Name of Bidder
Contractor's License No.
License Expiration Date
Signature of Bidder
Title of Signatory
Witness Address of Bidder
Title of Witness State of Incorporation
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
29 OF 91
SECTION 00 41 00
BIDDING SCHEDULE – July 14, 2025
PROJECT IDENTIFICATION: FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
THE BID IS SUBMITTED TO: City of Crescent City
BASE BID ITEMS
ITEM
NO.
Plan
Set ITEM DESCRIPTION UNIT QTY. UNIT PRICE
TOTAL
PRICE
1 FR Mobilization LS 1
2 FR SWPP Plan and Reporting LS 1
3 FR Water Pollution Prevention
BMPs LS 1
4 FR Traffic Control LS 1
5 FR 2x CMS Boards LS 1
6 FR Sheeting, Shoring, Bracing LS 1
7 FR Quality Control LS 1
8 FR Material Testing LS 1
9 FR Demolition LS 1
10 FR Excavation for Road &
Walks CY 3,096
11 FR Aggregate Base for paved
section CY 990
12 FR Hot Mix Asphalt Concrete Ton 1,100
13 FR Storm Drain 54" HDPE LF 145
14 FR Storm Drain 48" HDPE LF 62
15 FR Storm Drain 36" HDPE LF 698
16 FR Storm Drain 24" HDPE LF 566
17 FR Storm Drain 18" HDPE LF 188
18 FR Storm Drain 10"&12” HDPE LF 168
19 FR
Junction Box Double lid –
City supplied box, frame
and covers.
EA 2
20 FR
Junction Box Single lid –
City supplied box, frame
and covers
EA 6
21 FR Modifying existing Junction
Boxes
LS 1
22 FR
Drainage Inlets (Caltrans
Type G0) – City supplied
box and grates.
EA 10
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
30 OF 91
23 FR
Drainage Inlets (Caltrans
Type G1) – City supplied
box and grates.
EA 1
24 FR 6" Sanitary Sewer Mainline LF 190
25 FR 4" Sanitary Sewer Lateral LF 70
26 FR Sanitary Sewer Clean-out
with G-5 Boxes & Lids EA 3
27 FR 10" Water Line LF 340
28 FR 8" Water Line LF 530
29 FR 6" Water Line LF 104
30 FR Fire Hydrants EA 2
31 FR 10" Gate Valves with G-5
Boxes & Lids EA 3
32 FR 8" Gate Valves with G-5
Boxes & Lids EA 6
33 FR 6" Gate Valves with G-5
Boxes & Lids EA 4
34 FR 4" Gate Valves with G-5
Boxes & Lids EA 1
35 FR 2” Gate Valves with G-5
Boxes & Lids EA 3
36 FR 1” and/or 2” Service Lines LF 60
37 FR 2" Irrigation Lines LF 210
38 FR Water Meter Connections EA 4
39 FR Relocate Gas Line LF 390
40 FR Electrical LS 1
41 FR Streetlights Single Head EA 5
42 FR Streetlights Double Head EA 3
43 FR
Streetlights - Relocate
salvaged Double Head to
Station 33+50 – FR St. E-1
EA 1
44 FR Stamped Color Concrete
Sidewalks – Northside Front SF 4,800
45 FR Concrete Sidewalk nonstamped Southside Front St SF 5,720 46 FR Concrete Sidewalks – K
Street SF 6,280
47 FR Reinforced Concrete
Driveways SF 2,352
48 FR Reinforced Stamped Color
Concrete Crosswalks SF 2,060
49 FR ADA Dome Panels SF 405
50 FR Concrete Curb & Gutter LF 2,130
51 FR Concrete Curb No Gutter LF 1,240
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
31 OF 91
52 FR Bike Lane Color Asphalt
Treatment SF 1,370
53 FR Pavement Striping and
Signs LS 1
54 FR Storm Drain 42” HDPE LF 122
55 FR 4” Water Line LF 294
56 FR Reserved for future use
57 FR Reserved for future use
58 FR Reserved for future use
59 FR Reserved for future use
60 FR Reserved for future use
61 CG Mobilization LS 1
62 CG SWPP Plan Reporting LS 1
63 CG Water Pollution Prevention
BMPs LS 1
64 CG Pedestrian & Traffic Control LS 1
65 CG Tree protection fencing
installation & removal LF 420
66 CG Clear, Grub & Tree
Removal LS 1
67 CG
Demolition of Miscellaneous
Fencing, Signs, Guard
Rails, & Fixtures
LS 1
68 CG
Demolition of Concrete
Walls, Stairs, Art Panels,
and Porte Cochere Wall
LS 1
69 CG Demolition of Asphalt SF 9,400
70 CG Demolition of Building Deck
& Handrail LS 1
71 CG Mass Excavation and Fill
Including Porte Cochere LS 1
72 CG Excavation & Grading for
Concrete Flatwork SF 11,970
73 CG Aggregate Base for
Flatwork SF 11,970
74 CG Gateway Sign Foundation EA 2 NIC NIC
75 CG Wave Sign Foundation EA 1 NIC NIC
76 CG Concrete Vehicular Paving SF 8,365
77 CG Concrete Sidewalks SF 3,305
78 FR/CG ADA Dome panels – South
side Front Street and Trail SF 255
79 FR
Permeable Concrete
section including drain rock
subgrade
SF 5,900
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
32 OF 91
80 CG Concrete Slab at Porte
Cochere SF 2,120
81 CG Concrete Retaining Walls at
Stairs LF 24
82 CG Concrete Seat Walls LF 88
83 CG Concrete Stairs SF 216
84 CG Concrete Mow Curb LF 115
85 CG Concrete Subgrade (rat)
Slab at Redwood node SF 165 NIC NIC
86 CG
Reinforced Color Concrete
Slabs for Cultural node
surfacing
SF 400 NIC NIC
87 CG Surface colored reinforced
Concrete Trail Markers EA 6 NIC NIC
88 CG Lithocrete Basket Pattern SF 212 NIC NIC
89 CG Lithocrete Pebble Pattern SF 780 NIC NIC
90 CG
Drainage Inlets (Caltrans
Type G2 & GDO) – City
supplied inlets with grates.
EA 3
91 CG Install Area Drains – City
supplied drains with grates. EA 8
92 CG Install French Drains LF 130
93 CG Storm Drain 4-inch HDPE LF 55
94 CG Storm Drain 12-inch HDPE LF 360
95 CG Storm Drain 24-inch HDPE LF 20
96 CG Storm Drain 36-inch HDPE LF 40
97 CG Landscape Soil Import CY 800
98 CG Lawn Irrigation SF 22,400
99 CG Planting Areas Irrigation LS 1
100 CG Planting Lawn SF 22,400
101 CG Planting Ground Covers &
Shrubs LS 1
102 CG Planting Trees EA 19
103 CG 4 inches Bark Mulch CY 50
104 FR/CG Landscaping Maintenance LS 1
105 FR Landscape Rock SF 1,610
106 CG Travel Planning Signs EA 6
107 CG Tolowa Walk Entry Exhibit
(Sheets F6 - F7) LS 1 NIC NIC
108 CG
Install Electrical Control
Panels, conduit and wire for
plaza lighting and power
supply for cultural nodes
and sound boxes.
LS 1 NIC NIC
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
33 OF 91
109 CG Electrical Seat Wall & Steps
Lighting EA 16
110 CG Electrical Lighted Bollards EA 8
111 CG Removable Bollards EA 5
112 CG Install Stair Handrails LF 45
113 CG Install Bicycle Racks EA 3
114 CG Skate Deterrent Features LS 1 NIC NIC
115 CG Drinking Fountain &
Sanitary Sewer Line LS 1
116 CG Discovery Center
Renovations LS 1
TOTAL BASE BID AMOUNT_________________________________________________ _____________________________________________________($_________________).
Quantities shown on the Bid Schedule are estimated for the purposes of bidding only.
Actual construction quantities may vary. A bid price for all items in the Base Bid is required. The bid for each item shall include the cost to perform all the work necessary for a complete project, whether or not any such work is specifically designated on the Plans or in the Specifications.
The cost of all work in the Contract Documents not specifically identified as an item or described as an item must be included in the items and no additional compensation will become due the Contractor by nature of compliance with the Contract Documents except as provided for in the provisions relating to extra work or changes in the work.
Bid award will be based on the lowest Base Bid amount.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
34 OF 91
SECTION 00 43 13
BID GUARANTY BOND
KNOW ALL MEN BY THESE PRESENTS: That we _________________________, as Principal, and , as Surety,
are held and firmly bound unto the City of Crescent City, State of California, as Obligee, each in the penal sum of ten (10) percent of the total amount of the bid of the Principal for the work, this sum not to exceed
dollars ($ ) of lawful money of the United States for the payment of which sum we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.
WHEREAS, the Principal has submitted or is about to submit a bid to the Obligee for the work described as construction of the “FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE” and to which reference is hereby made for all particulars; NOW, THEREFORE, the condition of this obligation is such that if the Principal is awarded the contract, and if the Principal, within the time specified in the bid for such contract, enters into, executes, and delivers to the Obligee an agreement in the form provided therein complete with evidences of insurance and files with the Obligee two bonds, one to guarantee faithful performance and the other to guarantee payment for labor and materials, as required by law, and in the form provided by Obligee, then this obligation will be null and void; otherwise, this obligation will remain in full force and virtue.
AND IT IS HEREBY DECLARED AND AGREED that the Surety will be liable under this obligation as Principal, and that nothing of any kind or nature whatsoever that will not discharge the Principal may operate as a discharge or a release of liability of the Surety. In the event suit is brought upon this bond by the Obligee and judgment is recovered, the Surety shall pay all costs incurred by the Obligee in such suit.
IN WITNESS WHEREOF, the above bounden parties have executed this instrument under their seals this day of , 20 , the name and corporate seal of each corporate party being hereto affixed, and these presents duly signed by its undersigned representative, pursuant to authority of its governing body.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
35 OF 91
SIGNED AND SEALED this day of , 20____.
(SEAL)
Principal
Signature for Principal
Title of Signatory
(SEAL)
Surety
Signature for Surety
Title of Signatory
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
36 OF 91
SECTION 00 43 36
PROPOSED SUBCONTRACTORS
The following information gives the name, business address, and portion of work (description of work to be done) for each subcontractor that will be used in the work if the bidder is awarded the contract. No subcontractor who is not listed may be used without the written approval of the Owner in accordance with the Subletting and Subcontracting Fair Practices Act, commencing with Section 4100 of the Public Contract Code. (Additional supporting data may be attached to this page. Each page must be sequentially numbered, e.g., 00 43 36-2, and headed "Proposed Subcontractors" and must be signed.) Contractor must attach a verification sheet from Department of Industrial Relations (DIR) showing that subcontractors are registered in accordance with Labor Code Section 1725.5.
All Subcontractors’ contracts must include contract language that incorporates all requirements as stated in this contract.
Name Location Place of Business Description of Work DIR NO.
Signature of Bidder
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
37 OF 91
STATE OF CALIFORNIA
Department of Housing and Community Development
COMMUNITY DEVELOPMENT BLOCK GRANT (CDBG) Program
REQUIRED ITEM
BIDDER’S PROPOSED SECTION 3 CONTRACTS/SUBCONTRACTS
Type of Contract
(Business or
Profession)
Total No. Total
Approximate
Dollar Amount
Estimated No. of
Contracts to Section
3 Businesses
Estimated Dollar
Amount to Section
3 Businesses
Section 3 Business Concern:
1. A business that is 51% or more owned by Section 3
Company
residents, or
2. A business whose permanent full time work force is
Project Name
at least 30% are Section 3 residents or,
3. A business which contracts a dollar amount of all
Project Number
subcontracts with businesses as defined in numbers
1 and 2 above.
Person Completing Form
Date
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
38 OF 91
STATE OF CALIFORNIA
Department of Housing and Community Development
COMMUNITY DEVELOPMENT BLOCK GRANT (CDBG) Program
REQUIRED ITEM
BIDDER’S SECTION 3 PROPOSED NEW HIRES
Job Category
Total
Estimated
Positions
Needed for
the Project
No. of
Positions
Occupied by
Permanent
Employees
Number of
Positions
Not
Occupied
No. of
Positions To
be filled with
Section 3
Residents
Officer/Supervisors
Professionals
Technical
Housing Sales/
Rental Management
Office/Clerical
Service Workers
Others
Trade
Journeymen
Apprentices
Trainees
Others
Trade
Journeymen
Apprentices
Trainees
Others
Section 3 Resident:
Individual residing in a public housing project or
within the non-metropolitan county in which the
Company
project is located and whose income does not
exceed 80% of the higher of the median income,
Project Name
adjusted for family size, for the county of residence
or the non-metropolitan area of the state.
Project Number
Person Completing Form
Date
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
39 OF 91
SECTION 00 45 13
CERTIFICATION OF BIDDER’S
EXPERIENCE AND QUALIFICATIONS
The undersigned bidder certifies that he or she is, when the bid is submitted and will be, throughout the period of the contract, licensed by the State of California to do the type of work required under terms of the contract documents. Bidder further certifies that he or she is skilled and regularly engaged in the general class and type of work called for in the contract documents.
In accordance with the requirements of paragraph 00 20 00-1.05 A, the bidder represents that he or she is competent, knowledgeable and has special skills with respect to the nature, extent, and inherent conditions of the work to be performed. Bidder acknowledges that there are certain peculiar and inherent conditions existent in the construction of the particular facilities he or she is bidding on that may create, during the construction program, unusual or peculiar unsafe conditions that will be hazardous to persons or property. Bidder expressly acknowledges that he or she is aware of these peculiar risks and that he or she has the skill and experience to foresee them, assess them, and to adopt protective measures to adequately and safely perform the construction work with respect to the hazards.
Signed this day of , 20 .
Name of Bidder
Contractor’s License No. and State
_____________________________________
Contractor’s DUNS Number
Signature of Bidder
Title of Signatory
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
40 OF 91
SECTION 00 45 19
NON-COLLUSION AFFIDAVIT
NONCOLLUSION AFFIDAVIT TO BE EXECUTED BY BIDDER, NOTARIZED, AND
SUBMITTED WITH BID FOR PUBLIC WORKS
STATE OF CALIFORNIA
COUNTY OF__________________________
_______________________________________being first duly sworn, deposes and says (name)
that he or she is ________________________________________________________ of (Position Title)
_______________________________________________________________________, (the Bidder)
the party making the foregoing bid; that the bid is not made in the interest of, or on behalf of, any undisclosed person, partnership, company, association, organization, or corporation; that the bid is genuine and not collusive or sham; that the bidder has not directly or indirectly induced or solicited any other bidder to put in a false sham bid, and has not directly or indirectly colluded, conspired, connived, or agreed with any bidder or anyone else to put in a sham bid, or that anyone will refrain from bidding; that the bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference with anyone to fix the bid price of the bidder or any other bidder, or to fix any overhead, profit, or cost element of the bid price, or of that of any other bidder, or to secure any advantage against the public body awarding the contract of anyone interested in the proposed contract; that all statements contained in the bid are true; and, further, that the bidder has not, directly or indirectly, submitted his or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, or paid, and will not pay, any fee to any corporation, partnership, company, association, organization, bid depository, or to any member or agent thereof to effectuate a collusive or sham bid.
DATED:______________________ By__________________________________ (Person signing for Bidder)
Subscribed and sworn to before me on
(Notarial Seal) ____________________________________
____________________________________
(Notary Public)
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
41 OF 91
SECTION 00 45 21
ANTI-LOBBYING CERTIFICATION
The following certification and disclosure regarding payments to influence certain federal transactions are made per the provisions contained in 2 CFR 200 – Appendix II and 31 U.S.C. 1352, the “Byrd Anti‐Lobbying Amendment.”
(a) 2 CFR 200 – Appendix II, “Contract Provisions for Non-Federal Entity Contracts Under Federal Awards” is hereby incorporated by reference into this certification. (b) The offeror, by signing its offer, hereby certifies to the best of his or her knowledge and belief that:
(1) No Federal appropriated funds have been paid or will be paid to any person for influencing or attempting to influence an officer or employee of any agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress on his or her behalf in connection with the awarding of any Federal contract, the making of any Federal grant, the making of any Federal loan, the entering into of any cooperative agreement, and the extension, continuation, renewal, amendment or modification of any Federal contract, grant, loan, or cooperative agreement;
(2) If any funds other than Federal appropriated funds (including profit or fee received under a covered Federal transaction) have been paid, or will be paid, to any person for influencing or attempting to influence an officer or employee of any agency, a Member of Congress, an officer or employee of Congress, or an employee of a Member of Congress on his or her behalf in connection with this solicitation, the offeror shall complete and submit, with its offer, OMB standard form LLL, Disclosure of Lobbying Activities, to the Contracting Officer; and (3) He or she will include the language of this certification in all subcontract awards at any tier and require that all recipients of subcontract awards in excess of $150,000 shall certify and disclose accordingly.
(c) This certification is a material representation of fact upon which reliance is placed when this transaction was made or entered into. Submission of this certification and disclosure is a prerequisite for making or entering into this contract imposed by section 1352, title 31, United States Code. Any person making an expenditure prohibited under this provision or who fails to file or amend the disclosure form to be filed or amended by this provision, shall be subject to a civil penalty of not less than $10,000, and not more than $100,000, for each such failure.
SIGNATURE:_______________________________________________________ COMPANY NAME:________________________________ DATE: _______________
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
42 OF 91
SECTION 00 52 00
AGREEMENT
THIS AGREEMENT is made this __ day of , 20 , by and
between the City of Crescent City, a California municipal corporation hereinafter called the "Owner," and
, hereinafter called the
"Contractor."
WHEREAS, the Owner has caused a project manual to be prepared comprised of one volume of bidding and contract requirements, technical specifications, and drawings for the construction of the “FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE” as described therein; and
WHEREAS, the Contractor has offered to perform the proposed work in accordance with the terms of the contract as defined in Section 00 72 00; NOW, THEREFORE, in consideration of the mutual covenants and agreements of the parties contained in the contract and to be performed, the Contractor hereby agrees to complete the work at the price and on the terms and conditions therein contained, and the Owner agrees to pay the Contractor the contract price provided therein for the fulfillment of the work and the performance of the covenants set forth herein.
It is expressly understood and agreed by the parties that with regard to all dates and time periods set forth, or referred to, in this Agreement, time is of the essence.
The further terms, conditions, and covenants of this agreement are set forth in the contract documents, each of which is attached hereto and by this reference made a part hereof:
Volume One:
Part A, Bidding and Contract Requirements (including Addenda numbers through );
Part B, Technical Specifications; and
Part C, a set of drawings consisting of one volume.
Attachment A, Federal Prevailing Wage Rates / Classifications Attachment B, State Prevailing Wage Rates / Classifications Attachment C: Section 3 and CDBG Labor Compliance Program IN WITNESS WHEREOF, the parties have caused this agreement to be executed by their duly authorized representatives this ___ day of __________________, 20____ at Crescent City, California.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
43 OF 91
Signature for Owner
Title of Signatory
Attest:
Signature
Title of Signatory
Name of Contractor
Signature for Contractor
Title of Signatory
Attest:
Signature
Title of Signatory
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
44 OF 91
SECTION 00 61 05
FAITHFUL PERFORMANCE BOND
KNOW ALL MEN BY THESE PRESENTS, THAT:
WHEREAS, the City of Crescent City, California, a municipal corporation (hereinafter "Owner") and (hereinafter "Principal") have
entered into an agreement dated _________________ for the construction of the “FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE” (hereinafter “Project”), which agreement is hereby incorporated by reference and made a part hereof; and WHEREAS, said Principal is required under the terms of said agreement to furnish a bond for the faithful performance thereof.
NOW, THEREFORE, WE, the Principal, and , a
corporation organized and existing under the laws of the State of ________________ and duly authorized to transact business under the laws of the State of California, as Surety, are held and firmly bound unto the Owner, as obligee, in the penal sum of dollars ($_______________________), lawful money of the United States, said sum being not less than one hundred percent (100%) of the estimated amount payable by Owner under the terms of the Agreement for which payment well and truly to be made, we bind ourselves, our heirs, executors, administrators and successors, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH THAT, if the above bounden Principal, his or its heirs, executors, administrators, successors, or assigns, must in all things stand to and abide by, and well and truly keep and faithfully perform the covenants, conditions, and agreements in the said contract and any alterations made as therein provided, on his or their part, to be kept and performed at the time and in the manner therein specified, and in all respects according to their true intent and meaning, and will indemnify and save harmless, the Owner, its officers and agents as therein stipulated, then this obligation will become null and void; otherwise it will remain in full force and virtue and Principal and Surety, in the event suit is brought on this bond, will pay to the Owner such reasonable attorney's fees and costs as fixed by the court.
As a condition precedent to the satisfactory completion of the said contract, the above obligation in the said amount will hold good for a period of one (l) year after the completion and acceptance of the said work, during which time if the above bounden Principal, his or its heirs, executors, administrators, successors or assigns should fail to make full, complete, and satisfactory repair and replacements or totally protect the said Owner from loss or damage made evident during said period of one year from the date of acceptance of said work, and resulting from or caused by defective materials and/or faulty workmanship in the prosecution of the work done, the above obligation in the said amount will remain in full force and effect. However, anything in this paragraph to the contrary notwithstanding, the obligation of the Surety hereunder will continue so long as any obligation of the Principal remains.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
45 OF 91
And the said Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration, or addition to the terms of the contract or to the work to be performed thereunder or the specifications accompanying the same will, in any way, affect its obligations on this bond, and it does hereby waive notice of any such change, extension of time, alteration, or addition to the terms of the contract or to the work or to the specifications. Said Surety hereby waives the provisions of Sections 2819 and 2845 of the Civil Code of the State of California.
IN WITNESS WHEREOF, the above bounden parties have executed this instrument under their seals this day of , 20 , the name and corporate seal of each corporate party being hereto affixed, and these presents duly signed by its undersigned representative, pursuant to authority of its governing body.
Principal
(Seal)
Signature for Principal
Title of Signatory
Surety
(Seal)
Signature for Surety
Title of Signatory
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
46 OF 91
SECTION 00 61 10
PAYMENT BOND
KNOW ALL MEN BY THESE PRESENTS, THAT:
WHEREAS, the City of Crescent City, hereinafter designated the "Owner," has on _______________, 20 , awarded to ,
hereinafter designated as the "Principal," a contract for the construction of the “FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE”; and
WHEREAS, said Principal is required to furnish a bond in connection and with said contract, providing that if said Principal, or any of his or its subcontractors, should fail to pay for any materials, provisions, or other supplies used in, upon, for, or about the performance of the work contracted to be done, or for any work or labor done thereon of any kind, the Surety of this bond will pay the same to the extent hereinafter set forth; NOW, THEREFORE, WE, the Principal, and , as
Surety, are held and firmly bound unto the Owner the penal sum of dollars ($ ) lawful money of the United States, for the payment of which sum well and truly to be made, we bind ourselves, our heirs, executors, administrators, and successors, jointly and severally, firmly by these presents.
THE CONDITION OF THIS OBLIGATION IS SUCH, that if said Principal, his or its heirs, executors, administrators, successors, or assigns, should fail to pay for any materials, provisions, or other supplies used in, upon, for, or about the performance of the work contracted to be done, or for any work or labor thereon of any kind or for amount due under the Unemployment Insurance Act with respect to such work or labor, or for any amounts due, or to be withheld pursuant to Sections l8806 of the Revenue and Taxation Code of the State of California with respect to such work or labor, as required by the provisions of Chapter III, Division V, Title I, of the Government Code of the State of California, and provided that the persons, companies, or corporations so furnishing said materials, provisions, or other supplies, appliances, or power use, in, upon, for, or about the performance of the work contracted to be executed or performed, or any person who performs work or labor upon same, or any person who supplies both work and materials, thereto, have complied with the provisions of said Government Code, then said surety will pay the same in or to an amount not exceeding the amount hereinabove set forth, and also will pay in case suit is brought upon this bond, such reasonable attorney's fees to the Owner as fixed by the court.
This bond will inure to the benefit of any and all persons, companies, and corporations entitled to file claims under said Government Code, so as to give a right of action to them or their assigns in any suit brought upon this bond.
And the said Surety, for value received, hereby stipulates and agrees that no change, extension of time, alteration, or addition of the terms of the contract or to the work to be performed thereunder or the specifications accompanying the same will, in any way, affect FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
47 OF 91
its obligations of this bond, and it does hereby waive notice of any change, extension of time, alteration, or addition to the terms of the contract or to the work or to the specifications.
Said Surety hereby waives the provisions of Sections 2819 and 2845 of the Civil Code of the State of California.
IN WITNESS WHEREOF, the above bounden parties have executed this instrument under their seals this day of , 20 , the name and
corporate seal of each corporate party being hereto affixed and these presents duly signed by its undersigned representative, pursuant to authority of its governing body.
Principal
(Seal)
Signature for Principal Title
Surety
(Seal)
Signature for Surety Title
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 00
48 OF 91
SECTION 00 62 00
CERTIFICATES AND OTHER FORMS
The forms listed below and included in this Section will be used for this project and may be referenced from other Sections of the project manual:
Form No. Title
01300-A Submittal Transmittal Form
Contractor may use electronic versions of these forms.
01300-A. SUBMITTAL TRANSMITTAL FORM:
SUBMITTAL TRANSMITTAL
Submittal Description: Submittal No:1
Spec Section:
Routing Sent Received
OWNER: Contractor/CM
PROJECT: CM/Engineer
Engineer/CM
CONTRACTOR: CM/Contractor
We are sending you Attached Under separate cover via ________________. Submittals for review and comment
Product data for information only
Remarks:
Item Copies Date
Section
No. Description
Review
actiona
Reviewer
initials
Review
comments
attached
aNote: NET = No exceptions taken; MCN = Make corrections noted; A&R = Amend and resubmit; R = Rejected Attach additional sheets if necessary.
Contractor
Certify either A or B:
A. We have verified that the material or equipment contained in this submittal meets all the requirements, including coordination with all related work, specified (no exceptions).
B. We have verified that the material or equipment contained in this submittal meets all the requirements specified except for the attached deviations.
No. Deviation
Certified by:
Contractor's Signature
1 See paragraph 00 33 00-4.0 A, Transmittal Procedure.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
SECTION 00 72 00
GENERAL CONDITIONS
PART 1 – GENERAL INFORMATION
1.01 DEFINITIONS OF WORDS AND TERMS
Where used in the project manual, the following words and terms have the meanings indicated. The meanings are applicable to the singular, plural, masculine and feminine forms of the words and terms.
Acceptance. Formal action of the Owner in determining that the Contractor's work has been completed in accordance with the contract and in notifying the Contractor in writing of the acceptability of the work.
Act of God. A cataclysmic phenomenon of nature, such as an earthquake, flood, tsunami, or cyclone. Rain, wind, high water, or other natural phenomenon which might reasonably have been anticipated from historical records of the general locality of the work are not to be treated as Acts of God.
Addenda. Supplemental written specifications or drawings issued prior to execution of the contract which modify or interpret the project manual by addition, deletion, clarification, or corrections.
Bid. Offer of a bidder submitted on the prescribed form setting forth the price or prices of the work to be performed.
Bidder. Individual, partnership, corporation, or a combination thereof, including joint venturers, offering a bid to perform the work.
Business Day. Days that City Hall are open to the public.
City of Crescent City. To be considered the same as “Owner”, refer to “Owner”.
Construction Manager. The person designated, in writing, by the Owner to act as its representative at the construction site and to perform construction inspection services and administrative functions relating to this contract. Initial contact by the Contractor with the Owner will be through the Construction Manager.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
Contract. The writings and drawings embodying the legally binding obligations between the Owner and the Contractor for completion of the work. The contract comprises the following documents included in Part A, Part B, and Part C:
Project Manual Invitation to Bid Information for Bidders Bid Proposal General Conditions Supplementary Conditions Special Conditions Specifications Contract Drawings
Addenda Bonds Agreement
Notice of Award Notice to Proceed Change Orders
Directives Design Brief
Contract Drawings. The drawings included in the project manual plus those prepared by the Owner and the Contractor pursuant to the terms of the contract. They include:
1. Drawings in Part C of the project manual.
2. Modifying drawings issued by addenda.
3. Drawings submitted by the Contractor during the progress of the work and accepted by the Owner either as attachments to change orders or as non-modifying supplements to drawings in Part C and drawings issued by addenda.
4. Drawings submitted by the Owner to the Contractor during the progress of the work either as attachments to the change orders or as explanatory supplements to drawings in Part C and drawings issued by addenda.
Contract Price. Amount payable to the Contractor under the terms and conditions of the contract based on the price given on the bidding schedule, with adjustments made in accordance with the contract. The base amount given in the bidding schedule must be either a lump sum bid, or the summation of the unit price bids multiplied by the estimated quantities set forth in the bid form.
Contract Time. Number of calendar days stated in the contract for the completion of the work or portions thereof.
Contractor. The individual, partnership, corporation, or combination thereof, including joint venturers who enter into the contract with the Owner for the performance of the work. The term includes subcontractors, equipment and material suppliers, and their employees.
Contractor's Plant and Equipment. Equipment, material, supplies, and all other items, except labor, brought onto the site by the Contractor to carry out the work, but not to be incorporated in the work.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
Day. Calendar day.
Design Professional. Professional Engineer licensed to practice in the State of California retained by the Contractor.
Direct. Action of the Owner or Construction Manager by which the Contractor is ordered to perform or refrain from performing work under the contract.
Directive. Written documentation of the actions of the Owner or Construction Manager in directing the Contractor.
Equipment. Mechanical, electrical, instrumentation, or other device with one or more moving parts, or devices requiring an electrical, pneumatic, electronic, or hydraulic connection.
Furnish. To deliver to the job site or other specified location any item, equipment, or material.
Herein. Refers to information presented in the project manual.
Holidays. Legal holidays designated by the state or specifically identified in the supplementary conditions.
Install. Placing, erecting, or constructing complete in place any item, equipment, or material.
Owner. A public or quasi-public agency or authority, corporation, association, partnership, or individual for whom the work is to be performed. Under this contract, the Owner is identified by name in the agreement.
Owner's Representative. The person other than the Construction Manager designated in writing by the Owner to act as its agent on matters relating to this contract.
Paragraph. For reference or citation purposes, paragraph refers to the paragraph, or paragraphs, called out by section number and alphanumeric designator. For example, this definition is found in paragraph 00 72 00-1.01; permits and licenses are discussed in paragraph 00 72 00-1.05 B.
Person. The term, person, includes firms, companies, corporations, partnerships, and joint ventures.
Project. The undertaking to be performed under the provisions of the contract.
Project Manual. Those contract documents prepared for bidding and as amended by addenda.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
Provide. Furnish and install, complete in place.
Punch List. List of incomplete items of work and of items of work that are not in conformance with the contract. The list will be prepared by the Construction Manager when the Contractor (1) notifies the Construction Manager in writing that the work has been completed in accordance with the contract and (2) requests in writing that the Owner accept the work.
Shown. Refers to information presented on the drawings, with or without reference to the drawings.
Specifications. That part of the contract documents consisting of written descriptions of the technical features of materials, equipment, construction systems, standards, and workmanship.
Specify. Refers to information described, shown, noted, or presented in any manner in any part of the contract.
Submittals. The information which is specified for submission to the Construction Manager in accordance with Division 1 of the project manual.
Substantial Completion. Sufficient completion of the project or the portion thereof to permit utilization of the project, or portion thereof for its intended purpose. Substantial completion requires not only that the work be sufficiently completed to permit utilization, but that the Owner can effectively utilize the substantially completed work. Determination of substantial completion is solely at the discretion of the Owner. Substantial completion does not mean complete in accordance with the contract nor does substantial completion of all or any part of the project entitle the Contractor to acceptance under the contract.
Substantial Completion Date. Date when the Owner puts into service the project, or that portion of the project that has been determined to be substantially complete.
Work. The labor, materials, equipment, supplies, services, and other items necessary for the execution, completion, and fulfillment of the contract.
Working Day. Calendar days.
1.02 JOINT VENTURE CONTRACTOR
If Contractor is a joint venture of two or more contractors, the grants, covenants, provisos and claims, rights, power, privileges, and liabilities of the contract are joint and several. Any notice, order, direct request, or any communication required to be or that may be given by the Owner or the Construction Manager to the Contractor under this contract, is sufficiently given to all persons in the joint-venture Contractor if it is given to any one or more of such persons. Any notice, request or other communication given by any one of such FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
persons to the Owner or the Construction Manager under this contract is deemed to have been given by and binds all persons in the joint-venture.
1.03 CONTRACT REQUIREMENTS
A. SUCCESSORS' OBLIGATIONS:
The grants, covenants, provisos and claims, rights, powers, privileges, and liabilities obtained in the contract documents must be read and held as made by and with, and granted to and imposed upon, the Contractor and the Owner and their respective heirs, executors, administrators, successors, and assigns.
B. ASSIGNMENT OF CONTRACT:
The contract must not be assigned in whole or in part without the written consent of the Owner. Involuntary assignment of the contract as caused by the Contractor being adjudged bankrupt, assignment of the contract for the benefit of Contractor's creditors or appointment of a receiver on account of Contractor's insolvency is considered as failure to comply with the provisions of the contract and subject to the termination provisions contained herein.
C. WAIVER OF RIGHTS:
Except as herein provided, no action or want of action on the part of the Contractor, Owner, Owner's Representative, or Construction Manager at any time with respect to the exercise of any right or remedies conferred upon them under this contract is a waiver on the part of the Contractor and Owner of any of their rights or remedies. No waiver is effective except in writing by the party to be charged. No waiver of one right or remedy acts as a waiver of any other right or remedy or as a subsequent waiver of the same right or remedy.
D. OFFER OF ASSIGNMENT OF ANTITRUST ACTIONS:
As provided by Sections 4550 and 4551 of the Government Code, in entering into a public works contract or a subcontract to supply goods, services, or materials pursuant to a public works contract, the Contractor or subcontractor offers and agrees to assign to the awarding body all rights, title, and interest in and to all causes of action it may have under Section 4 of the Clayton Act (15 U.S.C. Sec. 15) or under the Cartwright Act (Chapter 2 [commencing with Section 16700] of Part 2 of Division 7 of the Business and Professions Code), arising from purchases of goods, services, or materials pursuant to the public works contract or the subcontract. This assignment is effective at the time the awarding body tenders final payment to the Contractor, without further acknowledgment by the parties.
E. AMENDMENT OF GENERAL CONDITIONS:
These general conditions may be amended only by mutual consent of the Owner and the Contractor in writing.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
1.04 LABOR STANDARDS
A. WAGES:
1. GENERAL: The Contractor and each subcontractor engaged in the work must pay each employee an amount not less than the rate established for each trade or occupation listed by the Director of the Department of Industrial Relations, State of California, or the Secretary of the Department of Labor, whichever is greater. An employee whose type of work is not covered by any of the classified wage rates must be paid not less than the rate of wage listed for the classification which most nearly corresponds to the type of work to be performed.
2. STATE/FEDERAL: State prevailing wages as set by the California Department of Industrial Relations and Federal (Davis-Bacon) prevailing wage rates as set by the Department of Labor for the work to be performed under this contract are included in Attachments A and B hereto.
3. PENALTY: The Contractor must forfeit, as penalty, to the Owner twenty-five dollars ($25.00) for each laborer, worker, or mechanic employed for each calendar day or portion thereof such laborer, worker, or mechanic is paid less than the general prevailing rate of wages for any work done under this contract, by him or by a subcontractor under him, in violation of the provisions of the California Labor Code, and, in particular, Sections 1770 and 1780 thereof.
4. PAYMENT OF WAGES: Pursuant to the Davis-Bacon Wage Act, Contractor and its subcontractors are required to pay wages not less than once per week.
B. PREFERENCE FOR RESIDENT LABOR:
In the employment of labor for performance of the work, the Contractor must give preference to qualified persons residing within the general area of the work.
C. HOURS OF LABOR:
Pursuant to the California Labor Code, eight hours of labor constitutes a legal day's work. The Contractor or any subcontractor may not require any more than eight hours of labor in a day from any person employed in the performance of the work under this contract.
Failure of the Contractor to perform the work in accordance with this policy of the State of California is a failure on his part to comply with the provisions of this contract.
D. OVERTIME WORK:
Overtime and shift work may be established as a regular procedure by the Contractor with reasonable notice and written permission of the Owner. No work other than overtime and shift work established as a regular procedure will be performed between the hours of 6:00 p.m. and 7:00 a.m. nor on Saturdays, Sundays or holidays except such work as is FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
necessary for the proper care and protection of the work already performed or in case of an emergency.
All work over eight hours per day and/or 40 hours per week is considered overtime. Hours over 8 in a day and/or 40 hours in a week must be paid at 1.5 times the rate of regular hours. Double time is required and due for work beyond 12 hours in a workday or eight hours on the seventh day of a work week.
Contractor agrees to pay the costs of overtime inspection except those occurring as a result of overtime and shift work established as a regular procedure. Overtime inspection includes inspection required during holidays, Saturdays, Sundays, and weekdays between the hours of 6:00 p.m. and 7:00 a.m. Costs of overtime inspection will cover engineering, inspection, general supervision, and overhead expenses that are directly chargeable to the overtime work. Contractor agrees that Owner will deduct such charges from payments due the Contractor.
E. COPELAND ANTI-KICKBACK ACT: Contractor agrees that it will comply with the Copland “Anti-Kickback” Act (18 U.S.C. 874) as supplemented in Department of Labor regulations (29 CFR Part 3). As applied to this contract, the Copland “Anti-Kickback” Act make is unlawful to induce, by force, intimidation, threat or procuring dismissal from employment, or otherwise, any person employed in the construction or repair of public buildings or public works, financed in whole or part in part by the Unites States, to give up any part of the compensation to which that person is entitled under a contract of employment.
F. APPRENTICES:
The Contractor and subcontractors under him must comply with the requirements of Sections 1777.5 and 1777.6 of the Labor Code in the employment of apprentices.
Information relative to apprenticeship standards, wage schedules, and other requirements may be obtained from the Director of Industrial Relations, ex-officio the Administrator of Apprenticeship, San Francisco, California, or from the Division of Apprenticeship Standards and its branch offices.
All apprentices must be certified from the Department of Industrial Relations and the Department of Labor. Certificates from each program must be submitted with first payroll the apprentice works. Failure to provide the required certificates shall result in non-payment of the pay request(s) until the proper documents are provided.
G. TRAVEL AND SUBSISTENCE PAY:
The Contractor and subcontractors under him must comply with the requirements of Section 1773.8 of the Labor Code in the payment of travel and subsistence payments to each workman needed to execute the work, as such travel and subsistence payments are FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
defined in the applicable collective bargaining agreements filed in accordance with Section 1773.8.
H. CONTRACT WORK HOURS AND SAFETY STANDARDS ACT (40 USC 3701-3708):
1. Overtime requirements. No contractor or subcontractor contracting for any part of the contract work which may require or involve the employment of laborers or mechanics shall require or permit any such laborer or mechanic in any workweek in which the individual is employed on such work to work in excess of 40 hours in such workweek unless such laborer or mechanic receives compensation at a rate not less than one and onehalf times the basic rate of pay for all hours worked in excess of 40 hours in such workweek.
2. Violation; liability for unpaid wages; liquidated damages. In the event of any violation of the clause set forth in subparagraph (1) of this paragraph, the contractor and any subcontractor responsible therefor shall be liable for the unpaid wages. In addition, such contractor and subcontractor shall be liable to the United States (in the case of work done under contract for the District of Columbia or a territory, to such District or to such territory), for liquidated damages. Such liquidated damages shall be computed with respect to each individual laborer or mechanic, including watchmen and guards, employed in violation of the clause set forth in subparagraph (1) of this paragraph, in the sum of $10 for each calendar day on which such individual was required or permitted to work in excess of the standard workweek of 40 hours without payment of the overtime wages required by the clause set forth in sub paragraph (1) of this paragraph.
3. Withholding for unpaid wages and liquidated damages. HUD or its designee shall upon its own action or upon written request of an authorized representative of the Department of Labor withhold or cause to be withheld, from any moneys payable on account of work performed by the contractor or subcontractor under any such contract or any other Federal contract with the same prime contract, or any other Federally-assisted contract subject to the Contract Work Hours and Safety Standards Act which is held by the same prime contractor such sums as may be determined to be necessary to satisfy any liabilities of such contractor or subcontractor for unpaid wages and liquidated damages as provided in the clause set forth in subparagraph (2) of this paragraph.
4. Subcontracts. The contractor or subcontractor shall insert in any subcontracts the clauses set forth in subparagraph (1) through (4) of this paragraph and also a clause requiring the subcontractors to include these clauses in any lower tier subcontracts. The prime contractor shall be responsible for compliance by any subcontractor or lower tier subcontractor with the clauses set forth in subparagraphs (1) through (4) of this paragraph.
5. No laborer or mechanic may be required to work in surrounding or under working conditions which are unsanitary, hazardous, or dangerous as established by Secretary of Labor pursuant to the Contract Work Hours and Safety Standards Act (codified at 40 USC 3701-3708).
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
I. STATE OF CALIFORNIA LABOR CODE § 1810 AND §1811
Contractor shall comply with Labor Code §1810 and §1811 which stipulates that eight hour labor constitutes a legal day's work, and §1812 which stipulates that the contractor and subcontractors shall keep an accurate record showing the name of and actual hours worked each calendar day and each calendar week by each worker employed by him in connection with the work performed under the terms of the contract. Failure to comply with these sections of the of the Labor Code will subject the contractors to penalty and forfeiture provisions of the Labor Code §1813.
J. DRUG FREE WORKPLACE COMPLIANCE
Contractor certifies that it shall comply with the Drug Free Workplace Act of 1988, as amended, 2 CFR Part 182 – Governmentwide Requirements for Drug-Free Workplace (Financial Assistance), and the appropriate Federal Agency Regulations for Grants and Agreements, whichever would be applicable under Federal law, regarding Drug Free Workplace compliance. Contractor shall require compliance, if applicable, from subcontractors.
K. ELIGIBLE WORKERS
Contractor shall ensure that all employees complete the I-9 form to certify that they are eligible for lawful employment under the Immigration and Nationality Act (8 U.S.C. 1324a). Contractor shall comply with regulations regarding certification and retention of the completed forms. These requirements also apply to any subcontract awarded under this contract. Contractor agrees to make these forms available in accordance with the access to records and record retention provisions of this contract.
L. “SECTION 3” CLAUSE
1. This is a HUD Section 3 construction contract. Contractors and subcontractors must address the Section 3 employment work hours benchmarks for Section 3 Workers and Targeted Section 3 Workers as established by the U.S. Department of Housing and Urban Development at 24 CFR Part 75.
a. This is a Section 3 covered project. Section 3 projects mean housing rehabilitation, housing construction, and other public construction projects assisted under HUD programs that provide housing and community development financial assistance when the total amount of assistance to the project exceeds $200,000. The project is the site or sites together with any building(s) and improvements located on the site(s) that are under common ownership, management, and financing.
b. The work to be performed under this contract is subject to the requirements of Section 3 of the Housing and Urban Development Act of 1968, as amended, 12 U.S.C. 1701u (Section 3). The purpose of Section 3 is to ensure that employment and other economic opportunities generated by the U.S. Department of Housing and Urban Development (HUD) assistance or HUD assisted projects covered by FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
Section 3, shall, to the greatest extent feasible, be directed to low- and very lowincome persons, particularly persons who are recipients of HUD assistance for housing.
c. The parties to this contract will comply with HUD's regulations as set forth in 24 CFR Part 75, which implement Section 3. As evidenced by their execution of this contract, the parties to this contract certify that they are under no contractual or other impediment that would prevent them from complying with the Part 75 regulations.
d. The Contractor agrees or representative of workers with which the Contractor has a collective bargaining agreement or other understanding, if any, a notice advising the labor organization or workers' representative of the Contractor's commitments under this Section 3 clause and will post copies of the notice in conspicuous places at the work site where both employees and applicants for training and employment positions can see the notice. The notice shall describe the Section 3 preference, shall set forth minimum number and job titles subject to hire, availability of apprenticeship and training positions, the qualifications for each; the name and location of the person(s) taking applications for each of the positions; and the anticipated date the work shall begin. e. The Section 3 requirements apply to all contractors and subcontractors performing work in connection with a Section 3 covered project. Contractor means any entity entering into a contract with (a) a recipient to perform work in connection with work in connection with a Section 3 project; or (b) a subrecipient for work in connection with a Section 3 project. Subcontractor means any entity that has a contract with a Contractor to undertake a portion of the contractor's obligation to perform work in connection with a Section 3 project. f. The contractor agrees to include this Section 3 Clause in every subcontract subject to compliance with regulations in 24 CFR Part 75, and agrees to take appropriate action, as provided in an applicable provision of the subcontract or in this Section 3 Clause, upon a finding that the subcontractor is in violation of the regulations in 24 CFR Part 75. The contractor will not subcontract with any subcontractor where the contractor has notice or knowledge that the subcontractor has been found in violation of regulations under 24 CFR Part 75. g. The Contractor acknowledges that subrecipients, contractors, and subcontractors are required to meet the employment, training, and contraction requirements of 24 CFR 75.19, regardless of whether Section 3 language is included in recipient or subrecipient agreements, program regulatory agreements, or contracts.
h. The contractor will certify that any vacant employment positions, including training positions, that are filled (1) after the contractor is selected, but before the contract is executed, and (2) with persons other than those to whom the regulations of 24 CFR Part 75 require employment opportunities to be directed, were not filled to circumvent the contractor's obligations under 24 CFR Part 75. i. Noncompliance with HUD's regulations in 24 CFR Part 75 may result in sanctions, termination of this contract for default, and debarment or suspension from future HUD assisted contracts.
j. The Contractor agrees to submit, and shall require its Subcontractors to submit FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
to them, annual reports detailing the total number of labor hours worked on the Section 3 Project, the total number of labor hours worked by Section 3 Workers, and the total number of hours worked by Targeted Section 3 Workers, and any affirmative efforts made during the quarter to direct hiring efforts to low- and very low-income persons, particularly persons who are Section 3 workers and Targeted Section 3 workers.
2. The contractor agrees to send to each labor organization or representative of workers with which the contractor has a collective bargaining agreement or other understanding, if any, a notice advising the labor organization or workers' representative of the contractor's commitments under this Section 3 clause and will post copies of the notice in conspicuous places at the work site where both employees and applicants for training and employment positions can see the notice. The notice shall describe the Section 3 preference, shall set forth minimum number and job titles subject to hire, availability of apprenticeship and training positions, the qualifications for each; and the name and location of the person(s) taking applications for each of the positions; and the anticipated date the work shall begin.
3. The contractor agrees to engage in qualitative efforts including but not limited to:
a. Engaging in outreach efforts to generate job applicants who are Targeted Section 3 Workers.
b. Providing training or apprenticeship opportunities.
c. Providing or referring Section 3 Workers to services supporting work readiness and retention (e.g., work readiness activities, interview clothing, test fees, transportation, childcare).
d. Engaging in outreach efforts to identify and secure bids from Section 3 business concerns.
e. Promoting the use of business registries designed to create opportunities for disadvantaged and small businesses.
f. Engaging in outreach and referrals with the state one-stop system of the workforce Innovation and Opportunity Act.
4. The contractor agrees to include this Section 3 clause in every subcontract subject to compliance with regulations in 24 CFR part 75, and agrees to take appropriate action, as provided in an applicable provision of the subcontract or in this Section 3 clause, upon a finding that the subcontractor is in violation of the regulations in 24 CFR part 75. The contractor will not subcontract with any subcontractor where the contractor has notice or knowledge that the subcontractor has been found in violation of the regulations in 24 CFR part 75.
5. The contractor must meet the requirements of 24 CFR part 75.19, regardless of whether Section 3 language is included in agreements, program regulatory agreements, or contracts. these requirements include:
a. Employment and Training
i. To the greatest extent feasible, and consistent with existing Federal, state and local laws and regulations, contractors covered by this subpart will ensure that employment and training opportunities FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
arising in connection with Section 3 projects are provided to Section 3 Workers within the metropolitan area (or nonmetropolitan county) in which the project is located.
ii. Where feasible, priority for opportunities and training should be given to:
1. Section 3 Workers residing within the service area or the neighborhood of the project; and
2. YouthBuild participants.
b. Contracting
i. To the greatest extent feasible, and consistent with existing Federal, state and local laws and regulations, recipients covered by this subpart shall ensure contracts for work awarded in connection with Section 3 projects are provided to business concerns that provide economic opportunities to Section 3 Workers residing with in the metropolitan area (or nonmetropolitan county) in which the project is located.
ii. Where feasible, priority for contracting opportunities should be given to:
1. Section 3 business concerns that provide economic
opportunities to Section 3 Workers residing within the service area or the neighborhood of the project; and
2. YouthBuild programs.
7. The contractor will certify that any vacant employment positions, including training positions, that are filled (1) after the contractor is selected but before the contract is executed, and (2) with persons other than those to whom the regulations of 24 CFR part 75 require employment opportunities to be directed, were not filled to circumvent the contractor’s obligations under 24 CFR part 75.
8. Noncompliance with HUD’s regulations in 24 CFR part 75 may result in sanctions, termination of this contract for default, and debarment or suspension from future HUD assisted contracts.
9. With respect to work performed in connection with Section 3 covered Indian housing assistance, Section 7(b) of the Indian Self-Determination and Education Assistance Ace (25 U.S.C 450e) also applies to the work to be performed under this contract. Section 7(b) requires that to the greatest extent feasible (i) preference and opportunities for training and employment shall be given to Indians, and (ii) preference in the award of contracts and subcontracts shall be given to Indian organizations and Indian-owned Economic Enterprises. Parties to this contract that are subject to the provisions of Section 3 and section 7(b) agree to comply with Section 3 to the maximum extent feasible, but not in derogation of compliance with Section 7(b).
10. Contractor will retain all documentation, Contracts, and records for a minimum of five years.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
1.05 LAWS, REGULATIONS AND PERMITS
A. GENERAL:
The Contractor must give the notices required by law and comply with all laws, ordinances, rules, and regulations pertaining to the conduct of the work. The Contractor is liable for violations of the law in connection with any work provided by the Contractor. If the Contractor observes that the drawings, specifications or other portions of the project manual are at variance with any laws, ordinances, rules, or regulations, he must promptly notify the Construction Manager in writing of such variance. The Owner must promptly review the matter and, if necessary, issue a change order or take any other action necessary to bring about compliance with the law, ordinance, rule or regulation in question. Contractor agrees not to perform work known to be contrary to any laws, ordinances, rules, or regulations.
B. PERMITS AND LICENSES:
Unless otherwise specified herein, permits and licenses from governmental agencies that are necessary only for and during the prosecution of the work and the subsequent guarantee period must be secured and paid for by the Contractor. Permits and licenses of regulatory agencies that are necessary to be maintained after completion of the guarantee period must be secured and paid for by the Owner.
C. PATENTS AND ROYALTIES:
1. The costs involved in fees, royalties or claims for any patented invention, article, process, or method that may be used upon or in a manner connected with the work under this contract or with the use of completed work by the Owner, must be paid by the Contractor. The Contractor and Contractor’s sureties must protect and hold the Owner, the design engineer, and the Construction Manager, together with their officers, agents, and employees, harmless from any and all loss, defense costs and expenses, including attorneys’ fees, and against any and all demands made for such fees or claims brought or made by the holder of any invention or patent. Before final payment is made on the account of this contract, the Contractor must, if requested by the Owner, furnish acceptable proof of a valid release from all such fees or claims.
2. Should the Contractor, or the Contractor’s agent, or employee or any of them, be enjoined from furnishing or using any invention, article, material or plans supplied or required to be supplied or used under this contract, the Contractor must promptly pay such royalties and secure the requisite licenses; or, subject to acceptance by the Owner, substitute other articles, materials or appliances in lieu thereof which are of equal efficiency, quality, finish, suitability, and market value to those planned or required under the contract.
Descriptive information of these substitutions must be submitted to the Construction Manager for determination of general conformance to the design concept and the construction contract. Should the Owner elect to refuse the substitution, the Contractor agrees to pay such royalties and secure such valid licenses as may be requisite for the Owner, the Owner’s officers, agents, and employees or any of them, to use such invention, FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
article, material, or appliance without being disturbed or in any way interfered with by any proceeding in law or equity arising from that use.
D. COMPLIANCE WITH ENVIRONMENTAL LAWS:
Contractor shall comply with all applicable standards, orders or regulations issued pursuant to the Clean Air Act (42 U.S.C. 7401-7671q) and the Federal Water Pollution Control Act as amended (33 U.S.C. 1251-1387). Violations must be reported to the Federal awarding agency and the Regional Office of the Environmental Protection Agency (EPA).
E. HUMAN TRAFFICKING:
Pursuant to the Trafficking Victims Protection Act of 2000 (22 USC 7101 et seq.) and as required by 2 CFR part 175, the Contractor, its employees, subcontractors and their employees, must not:
1. Engage in severe forms of trafficking in persons during the contract term;
2. Procure a commercial sex act during the contract term; or
3. Use forced labor in the performance of the contract or any subcontract.
Definitions are contained at 22 U.S.C. 7102.
1.06 HEADINGS
Headings to parts, divisions, sections, paragraphs, subparagraphs and forms are inserted for convenience of reference only and do not affect the interpretation of the contract documents.
1.07 SUBCONTRACTS
The Contractor must perform with the Contractor’s own organization not less than one-half of the work and must not sublet to one subcontractor more than one-third of the work without the prior written consent of the Owner.
1.08 CONFLICT OF INTEREST
A. GENERAL:
If Contractor violates any provisions of the following Sections, such actions by the Contractor will render this Agreement void. (Public Contracts Code Section 10420).
B. CURRENT STATE EMPLOYEES: (Public Contracts Code Section 10410)
1. No officer or employee may engage in any employment, activity, or enterprise from which the officer or employee receives compensation FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
or has a financial interest, and which is sponsored or funded by any state agency, unless the employment, activity or enterprise is required as a condition of regular State employment.
2. No officer or employee may contract on his or her own behalf as an independent contractor with any State agency to provide goods or services.
C. FORMER STATE EMPLOYEES: (Public Contracts Code Section 10411)
1. For the two-year period from the date, he or she left State employment, no former state officer or employee may enter into a contract in which he or she engaged in any of the negotiations, transactions, planning, arrangements, or any part of the decision-making process relevant to the contract while employed in any capacity by any State agency.
2. For the twelve-month period from the date, he or she left State employment, no former State officer or employee may enter into a contract with any State agency if he or she was employed by the State agency in a policy-making position in the same general subject area as the proposed contract within the 12-month period prior to his or her leaving State service.
1.09 NON-DISCRIMINATION
A. During the performance of this contract, Contractor shall not deny the contract's benefits to any person on the basis of race, religious creed, color, national origin, ancestry, physical disability, mental disability, medical condition, genetic information, marital status, sex, gender, gender identity, gender expression, age, sexual orientation, or military and veteran status, nor shall they discriminate unlawfully against any employee or applicant for employment because of race, religious creed, color, national origin, ancestry, physical disability, mental disability, medical condition, genetic information, marital status, sex, gender, gender identity, gender expression, age, sexual orientation, or military and veteran status. Contractor shall ensure that the evaluation and treatment of employees and applicants for employment are free of such discrimination.
B. Contractor shall comply with the provisions of the Fair Employment and Housing Act (Gov. Code Sections 12900 et seq.), the regulations promulgated thereunder (California Code of Regulations, Title 2, Sections 11000 et seq.), the provisions of Article
9.5, Chapter 1, Part 1, Division 3, Title 2 of the Government Code (Gov. Code Sections 11135-11139.5), and the regulations or standards adopted by CALTRANS to implement such article.
C. Contractor shall permit access by representatives of the Department of Fair Employment and Housing, Caltrans and CITY upon reasonable notice at any time during the normal business hours, but in no case less than 24 hours' notice, to such of its books, FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
records, accounts, and all other sources of information and its facilities as said Department or Caltrans shall require to ascertain compliance with this clause.
D. Contractor and its subcontractors shall give written notice of their obligations under this clause to labor organizations with which they have a collective bargaining or other agreement.
E. Contractor shall include the nondiscrimination and compliance provisions of this clause in all agreements with its subcontractors, and shall include a requirement in all agreements with all of same that each of them in turn include the nondiscrimination and compliance provisions of this clause in all contracts and subcontracts they enter into to perform work under this contract
F. Contractor must also comply with regulations relative to non-discrimination in federally-assisted programs of the U.S. Department of Transportation (49 CFR 21 – Effectuation of Title VI of the Civil Rights Act of 1964). Specifically, the Contractor shall not participate either directly or indirectly in the discrimination prohibited by 49 CFR §21.5, including employment practices and the selection and retention of subcontractors.
1.10 FEDERAL EQUAL EMPLOYMENT OPPORTUNITY CLAUSE
During the performance of this contract, Contractor agrees as follows:
(1) Contractor will not discriminate against any employee or applicant for employment because of race, color, religion, sex, sexual orientation, gender identity, or national origin. Contractor will take affirmative action to ensure that applicants are employed, and that employees are treated during employment without regard to their race, color, religion, sex, sexual orientation, gender identity, or national origin. Such action shall include, but not be limited to the following:
Employment, upgrading, demotion, or transfer; recruitment or recruitment advertising; layoff or termination; rates of pay or other forms of compensation; and selection for training, including apprenticeship. Contractor agrees to post in conspicuous places, available to employees and applicants for employment, notices to be provided setting forth the provisions of this nondiscrimination clause.
(2) Contractor will, in all solicitations or advertisements for employees placed by or on behalf of the contractor, state that all qualified applicants will receive consideration for employment without regard to race, color, religion, sex, sexual orientation, gender identity, or national origin.
(3) Contractor will not discharge or in any other manner discriminate against any employee or applicant for employment because such employee or applicant has inquired about, discussed, or disclosed the compensation of the employee or applicant or another employee or applicant. This provision shall not apply to FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
instances in which an employee who has access to the compensation information of other employees or applicants as a part of such employee's essential job functions discloses the compensation of such other employees or applicants to individuals who do not otherwise have access to such information, unless such disclosure is in response to a formal complaint or charge, in furtherance of an investigation, proceeding, hearing, or action, including an investigation conducted by the employer, or is consistent with Contractor's legal duty to furnish information.
(4) Contractor will send to each labor union or representative of workers with which s/he has a collective bargaining agreement or other contract or understanding, a notice to be provided advising the said labor union or workers' representatives of Contractor's commitments under this section, and shall post copies of the notice in conspicuous places available to employees and applicants for employment.
(5) Contractor will comply with all provisions of Executive Order 11246 of September 24, 1965, and of the rules, regulations, and relevant orders of the Secretary of Labor.
(6) Contractor will furnish all information and reports required by Executive Order 11246 of September 24, 1965, and by rules, regulations, and orders of the Secretary of Labor, or pursuant thereto, and will permit access to his books, records, and accounts by the administering agency and the Secretary of Labor for purposes of investigation to ascertain compliance with such rules, regulations, and orders.
(7) In the event of Contractor's noncompliance with the nondiscrimination clauses of this contract or with any of the said rules, regulations, or orders, this contract may be canceled, terminated, or suspended in whole or in part and the contractor may be declared ineligible for further Government contracts or federally assisted construction contracts in accordance with procedures authorized in Executive Order 11246 of September 24, 1965, and such other sanctions may be imposed and remedies invoked as provided in Executive Order 11246 of September 24, 1965, or by rule, regulation, or order of the Secretary of Labor, or as otherwise provided by law.
(8) Contractor will include the portion of the sentence immediately preceding paragraph (1) and the provisions of paragraphs (1) through (8) in every subcontract or purchase order unless exempted by rules, regulations, or orders of the Secretary of Labor issued pursuant to section 204 of Executive Order 11246 of September 24, 1965, so that such provisions will be binding upon each subcontractor or vendor. Contractor will take such action with respect to any subcontract or purchase order as the administering agency may direct as a means of enforcing such provisions, including sanctions for noncompliance:
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
Provided, however, that in the event Contractor becomes involved in, or is threatened with, litigation with a subcontractor or vendor as a result of such direction by the administering agency, Contractor may request the United States to enter into such litigation to protect the interests of the United States.
1.11 REHABILITATION ACT OF 1973:
The Contractor, subcontractors, manufacturers, and suppliers further agrees to implement the Rehabilitation Act of 1973, as amended, and its regulations, 24 CFR Part 8, including, but not limited to, for Contractors, subcontractors, manufacturers, and suppliers with fifteen (15) or more permanent full or part time employees, the local designation for a specific person charged with local enforcement of this Act, as the “504 Coordinator.”
1.12 REBATES, KICKBACKS OR OTHER UNLAWFUL CONSIDERATION:
Contractor warrants that this Agreement was not obtained or secured through rebates, kickbacks or other unlawful consideration either promised or paid to any Crescent City employee. For breach or violation of this warranty, Crescent City shall have the right, in its discretion, to terminate this Agreement without liability, to pay only for the value of the work actually performed, or to deduct from this Agreement price or otherwise recover the full amount of such rebate, kickback or other unlawful consideration.
1.13 AMERICANS WITH DISABILITIES ACT:
Contractor agrees that curing the course of performing work under this project, it will fully comply with the applicable provisions of the American with Disabilities Act (ADA) of 1990, as amended, which prohibits discrimination on the basis of disability, as well as all applicable regulations and guidelines issued pursuant to the AD (42 USC Section 12101 et seq.).
1.14 INTELLECTUAL PROPERTY TERMS:
A. GENERALLY: To the extent any intellectual property is created or produced for under this Agreement, and not covered in other provisions herein, Contractor agrees to take reasonable steps to ensure that the City and Caltrans have the rights necessary to allow for use of the intellectual property in a fashion substantially similar to other rights for non-commercial uses and State government purposes described in this Agreement.
B. INVENTIONS: Inventions are any idea, methodologies, design, concept, technique, invention, discovery, improvement, or development regardless of patentability made by Contractor and/or a subcontractor during the term of this Agreement and in performance of any work under this Agreement, provided that either the conception or reduction to practice thereof occurs during the term of this Agreement and in performance of work issued under this Agreement. Contractor and any subcontractor hereby grant the City and Caltrans Government Purpose Rights to any invention created as a result of the work performed under this Agreement. “Government Purpose Rights” are the unlimited, FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
irrevocable, worldwide, perpetual, royalty-free, non-exclusive rights, and licenses to use, modify, reproduce, perform, release, display, create derivative works from, and disclose any said invention. “Government Purpose Rights” also include the right to release or disclose said invention(s) outside Caltrans for any State government purpose and to authorize recipients to use, modify, reproduce, perform, release, display, create derivative works from, and disclose the invention(s) for any State government purpose. “Government Purpose Rights” do not include any rights to use, modify, reproduce, perform, release, display, create derivative works from, or disclose the invention(s) for any commercial purpose.
C. AVOIDANCE OF INFRINGEMENT: Contractor and subcontractors must agree to avoid designing or developing any items that infringe one (1) or more patents or other intellectual property rights of any third party. If Contractor or a subcontractor becomes aware of any such possible infringement in the course of performing any work under this Agreement, then the Contractor or subcontractor must immediately notify the City in writing, and the City will then immediately notify Caltrans in writing.
1.15 CHILD SUPPORT COMPLIANCE ACT
Contractor acknowledges and agrees to the following:
The Contractor recognizes the importance of child and family support obligations and shall fully comply with all applicable state and federal laws relating to child and family support enforcement, including, but not limited to, disclosure of information and compliance with earnings assignment orders, as provided in Chapter 8 (commencing with section 5200) of Part 5 of Division 9 of the Family Code; and
The Contractor, to the best of their knowledge, is fully complying with the earnings assignment orders of all employees and is providing the names of all new employees to the New Hire Registry maintained by the California Employment Development Department.
1.16 ENERGY EFFICIENCY:
The Contractor shall comply with mandatory standards and policies relating to energy efficiency which are contained in the California energy conservation plan issued in compliance with the Energy Policy and Conservation Act (Public Law 94-163).
1.17 ARCHITECTURAL BARRIERS ACT AND THE AMERICANS WITH DISABILITIES ACT:
The Architectural Barriers Act of 1968 (42 U.S.C. 4151-4157) requires certain Federal and Federally funded buildings and other facilities to be designed, constructed, or altered in accordance with standards that ensure accessibility to, and use by, people with physical disabilities. A building or facility designed, constructed, or altered with funds allocated or reallocated under this subpart after November 21, 1996 and that meets the definition of residential structure as defined in 24 CFR 40.2, or the definition of building as FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
defined in 41 CFR 101-19.602(a), is subject to the requirements of the Architectural Barriers Act of 1968 and shall comply with the Uniform Federal Accessibility Standards.
PART 2 – OWNER-CONTRACTOR RELATIONS
2.01 AUTHORITY OF OWNER
A. GENERAL:
The Owner, acting through the Owner's Representative and the Construction Manager, has the authority to act as the sole judge of the work and materials with respect to both quantity and quality as set forth in the contract. It is expressly stipulated that the drawings, specifications, and other contract documents establish the requirements as to the nature of the completed work and, except in those instances where the nature of the completed work is dependent on the method of performance, do not purport to control the method of performing work.
B. AUTHORITY OF OWNER'S REPRESENTATIVE:
1. GENERAL: Except for those decisions expressly reserved to the City Council of the City of Crescent City, the Owner's Representative has the authority to act on behalf of the Owner on change orders, progress payments, contract decisions, and acceptability of the Contractor's work.
2. CHANGE ORDERS: Up to an aggregate limit of 10% of the contract price, the Owner's Representative has the authority to accept or reject change orders proposed by either the Construction Manager or the Contractor.
3. PROGRESS PAYMENTS: The Owner's Representative has the authority to accept or reject requests for progress payments which have been submitted by the Contractor and recommended by the Construction Manager.
4. CONTRACT DECISIONS: Should the Contractor disagree with the Construction Manager's decision with respect to the contract, the Contractor may request that the Owner's Representative review the Construction Manager's decision and make a determination on behalf of the Owner in the manner provided under paragraph 00 72 00-
2.05 F.2.
5. ACCEPTABILITY OF WORK: The Owner's Representative has the authority to make the initial determination of the acceptability of the work as provided under paragraph 00 72 00-7.05. The Owner's Representative also has the authority to accept or reject initially the Construction Manager's recommendations regarding retention of defective work as provided in paragraph 00 72 00-4.09 B. Each of these determinations is made subject to the authority of the City Council of the City of Crescent City.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
6. EARLY POSSESSION: The Owner's Representative has the authority to take early possession in accordance with paragraph 00 72 00-7.06.
C. AUTHORITY OF CONSTRUCTION MANAGER:
1. GENERAL: The Construction Manager is the construction site representative of the Owner, employed to act as advisor and consultant to the Owner in construction matters related to the contract. The Owner has delegated its authority to the Construction Manager to make initial decisions regarding questions which may arise as to the quality or acceptability of materials furnished, and work performed and as to the manner of performance and rate of progress of the work under the contract. The Construction Manager interprets the intent and meaning of the contract and makes initial decisions with respect to the Contractor's fulfillment of the contract and the Contractor's entitlement to compensation. The Contractor must look initially to the Construction Manager in matters relating to the contract. The Construction Manager's decisions are subject to review by the Owner's Representative in accordance with paragraph 00 72 00-2.05 F.2.
2. INSPECTION OF CONSTRUCTION: The Construction Manager must be granted access to the work and to the site of the work and to the places where work is being prepared or where materials, equipment, and machinery are being obtained for the work. If requested by the Construction Manager, the Contractor must provide the assistance necessary for obtaining such access and must provide information related to the inspection of construction.
3. CHANGE ORDERS: The Construction Manager has the authority to initiate or recommend change orders. Change orders are subject to review and approval by the Owner.
D. USE OF CONTRACTOR'S PLANT AND EQUIPMENT:
Contractor agrees to make available to the Owner his plant and equipment for the performance of work at the project site. The Owner agrees that the use of such plant and equipment is extra work and will be paid for accordingly.
2.02 RESPONSIBILITIES OF OWNER
A. ATTENTION TO WORK:
The Owner will notify the Contractor in writing of the name of the Owner's Representative and of the Construction Manager. The Construction Manager normally will be at the site of the work. During the Contractor’s absences, the Contractor may contact a previously designated representative of the Construction Manager.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
B. OWNER'S EMPLOYEES:
The Owner is responsible for the adequacy, efficiency, and sufficiency of its employees and of any consultant, supplier or subcontractor employed by the Owner.
2.03 AUTHORITY OF CONTRACTOR
A. CONTRACTOR'S REPRESENTATIVE:
The Contractor must notify the Owner in writing of the name of the person who will act as the Contractor's representative and will have the authority to act in matters relating to this contract. This person must have authority to carry out the provisions of the contract and to supply materials, equipment, tools, and labor without delay for the performance of the work.
B. CONSTRUCTION PROCEDURES:
The Contractor will supervise and direct the work. He has the authority to determine the means, methods, techniques, sequences, and procedures of construction, except in those instances where the Owner, to define the quality of an item of work, specifies in the contract, a means, method, technique, sequence, or procedure for construction of that item of work.
C. SUBCONTRACTORS:
Subcontractors do not have a direct relationship with the Owner. The persons engaged in the work, including employees of subcontractors and suppliers, are considered employees of the Contractor and their work is subject to the provisions of the contract.
References in the project manual to actions required of subcontractors, manufacturers, suppliers, or any person other than the Contractor, the Owner or the Construction Manager require the Contractor in turn to require that subcontractor, manufacturer, supplier, or person to perform the specified action.
2.04 RESPONSIBILITIES OF CONTRACTOR
A. SUBCONTRACTORS, MANUFACTURERS AND SUPPLIERS:
The Contractor is responsible for the adequacy, efficiency and sufficiency of subcontractors, manufacturers, suppliers, and their employees. The Contractor must perform, with Contractor’s own organization, contract work amounting to not less than 50 percent of the original total contract price.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
B. CONTRACTOR'S EMPLOYEES:
The Contractor is responsible for the adequacy, efficiency, and sufficiency of Contractor’s employees. Workers must have sufficient knowledge, skill, and experience to perform properly the work assigned to them.
C. PAYMENT FOR LABOR AND MATERIALS:
The Contractor must pay and require Contractor’s subcontractors to pay any and all accounts for labor including Workers Compensation premiums, State Unemployment and Federal Social Security payments and other wage and salary deductions required by law.
The Contractor also must pay and require Contractor’s subcontractors to pay any and all accounts for services, equipment, and materials used by Contractor’s and by subcontractors during the performance of work under this contract. These accounts must be paid as they become due and payable. If requested by the Owner, the Contractor must furnish to the Owner proof of payment of these accounts.
D. ATTENTION TO WORK:
The Contractor, acting through the Contractor’s representative, must give personal attention to and manage the work so that it is prosecuted faithfully. When the Contractor’s representative is not personally present at the project site, a designated alternate must be available and have the authority to act on the Contract.
E. EMPLOYEE SAFETY:
The Contractor alone is responsible for the safety of Contractor’s employees and subcontractors’ employees. The Contractor must maintain the project site and perform the work in a manner that meets the Owner's responsibility under statutory and common law for the provision of a safe place to work.
F. PUBLIC SAFETY AND CONVENIENCE:
The Contractor must conduct the work so as to insure the least possible obstruction to traffic and inconvenience to the general public and the residents in the vicinity of the work.
Work will be performed so as to insure the protection of persons and property. No road or street will be closed to the public except with the permission of the Construction Manager and the proper governmental authority. Fire hydrants on or adjacent to the work must be accessible to firefighting equipment. Temporary provisions must be made by the Contractor to insure the use of sidewalks, private and public driveways and proper functioning of gutters, sewer inlets, drainage ditches and culverts, irrigation ditches, and natural water courses.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
G. COOPERATION WITH CONSTRUCTION MANAGER:
The Contractor, when requested, must assist the Construction Manager in obtaining access to work which is to be inspected. The Contractor must provide the Construction Manager with information requested in connection with the inspection of the work.
H. RECORDS RETENTION
Contractor must use an accounting system that conforms to Generally Accepted Accounting Principles (GAAP) and enables the determination of incurred costs at interim points of completion and provides support for reimbursement payment vouchers or invoices.
All accounting records, books, records, accounts, documentation, and all other materials to this Contract must be maintained for a minimum of three (3) years from the date of final payment to Contractor and shall be held open to inspection, copying and audit by representatives of the Owner, Caltrans, the California State Auditor, and auditors representing the federal government, during reasonable times at Contractor’s office.
Contractor must permit access to all records of employment, employment advertisements, employment application forms, and other pertinent data and records by the State Fair Employment Practices and Housing Commission or any other agency of the State of California designated by Caltrans, for the purpose of any investigation to ascertain compliance with grant agreement between Owner and Caltrans.
I. WORK SITE SECURITY
The Owner has limited security at the area the work is to take place; therefore, the Contractor may not rely upon the Owner’s security to protect the work site from theft or vandalism. The Contractor is responsible for providing necessary security measures to prevent theft or vandalism of material and equipment stored on site, work that has been completed, and work that is in the process of being completed. The Contractor must repair or replace any damage or theft that occurs throughout the course of the work at no additional cost to the Owner.
J. CONTRACTOR AND SUBCONTRACTORS DAILY WORK REPORTS
The Contractor must submit a daily report to the Construction Manager at the end of each shift worked. Daily reports will include the following:
1. List all personnel working on the project and their classification,
2. Equipment utilized,
3. Shift and hours worked,
4. Accident report(s) if applicable,
5. Material/Equipment deliveries,
6. Production report covering day’s activities.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
K. SALES AND USE TAX REQUIREMENTS
During the performance of this Agreement, Contractor, for itself, its assignees, and successors in interest, must:
1. USE TAX DIRECT PAYMENT PERMIT: For all leases and purchases of materials, equipment, supplies or other tangible property used to perform the Contract and shipped from outside California, the Contractor and any subcontractor leasing or purchasing the materials, equipment, supplies or other tangible personal property must obtain a Use Tax Direct Payment Permit from the California State Board of Equalization (SBE) in accordance with the applicable SBE criteria and requirements.
2. SELLER’S PERMIT: Contractor and any construction subcontractor whose subcontract is for $5,000,000 or more must elect to allocate the local sales and use tax derived from the Contract directly to the local jurisdiction (Del Norte County) where the jobsite is located. For this purpose, the Contractor and such subcontractors must obtain a seller’s permit or a sub-permit of their seller’s permit for the specific jobsite and allocate the local tax to the jobsite on Schedule C of their sales and use tax return.
L. COST PRINCIPLES
Contractor agrees that (a) Contract Cost Principles and Procedures, 48 CFR, Federal Acquisition Regulations System, Chapter 1, Part 31, et seq., shall be used to determine the allowability of individual Project cost items and (b) all parties shall comply with Federal administrative procedures in accordance with 2 CFR, Part 200, Uniform Administrative Requirements, Cost Principles, and Audit Requirements for Federal Awards. Contractor shall comply with Federal administrative procedures in accordance with 2 CFR, Part 200, Uniform Administrative Requirements, Cost Principles and Audit Requirements for Federal Awards to the extent applicable.
M. MANDATORY ORGANIC WASTE RECYCLING
Pursuant to Public resources Code Sections 42649.8 et seq., if Contractor generates two (2) cubic yards or more of organic waste or commercial solid waste per week, the Contractor must arrange for organic waste or commercial was recycling services that separate/source organic waste for organic waste recycling. The Contractor must provide the Owner with proof of compliance, i.e., organic waste recycling services or commercial waste recycling services that separate/source organic waste recycling.
2.05 OWNER-CONTRACTOR COORDINATION
A. SERVICE OF NOTICE:
Notice, order, direction, request, or other communication given by the Construction Manager or Owner to the Contractor is well and sufficiently given to the Contractor if left at any office used by the Contractor or delivered to any of Contractor’s officers, clerks or FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
employees or posted at the site of the work or mailed to the Contractor at the address given in the contract document or mailed to the Contractor's last known place of business. If mailed by first-class mail, any form of communication is deemed to have been given to and received by the Contractor one day after the date of mailing.
B. SUGGESTIONS TO CONTRACTOR:
A plan or method of work suggested by the Owner or the Construction Manager to the Contractor but not specified or required, if adopted or followed by the Contractor in whole or in part, is used at the risk and responsibility of the Contractor. The Owner and the Construction Manager assume no responsibility for the decision to use that plan or method of work and they are not liable for any defects in the work that result from or are caused by use of such plan or method of work.
C. COOPERATION:
The Contractor agrees to permit entry to the site of the work by the Owner or other contractors performing work on behalf of the Owner. The Contractor must afford to the Owner and other contractors and their employees, reasonable facilities and cooperation and must arrange the work and dispose of the materials so as not to interfere with the activities of the Owner or of others upon the site of the work. The Contractor must promptly make good any injury or damage that may be sustained by other contractors or employees of the Owner at the hands of Contractor. The Contractor must join the work to that of others and perform the work in proper sequence in relation to that of others.
If requested by the Contractor, the Owner will arrange meetings with other contractors performing work on behalf of the Owner to plan coordination of construction activities. The Owner must keep the Contractor informed of the planned activities of other contractors.
Differences or conflicts arising between the Contractor and other contractors employed by the Owner or between the Contractor and the workers of the Owner with regard to their work must be submitted to the Construction Manager for a decision in the matter. If the work of the Contractor is affected or delayed because of any act or omission of other contractors or of the Owner, the Contractor may submit for the Owner's consideration, a documented request for a change order.
D. DEVIATION FROM CONTRACT:
Neither the Contractor nor the Owner may make an alteration or variation in, addition to, or deviation or omission from the terms of this contract without the written consent of the other party.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
E. DIFFERING SITE CONDITIONS:
Pursuant to Public Contract Code Section 7104, the Contractor must promptly, and before such conditions are disturbed, notify the Owner in writing of:
1. Material that the Contractor believes may be material that is hazardous waste, as defined in Section 25117 of the Health and Safety Code, that is required to be removed to a Class I, Class II, or Class III disposal site in accordance with provisions of existing law.
2. Subsurface or latent physical conditions at the site differing from those indicated by information about the site made available to bidders prior to the deadline for submitting bids.
3. Unknown physical conditions at the site, of an unusual nature, differing materially from those both ordinarily encountered and generally recognized as inhering in work of the character provided for in this contract.
The Owner must promptly investigate the conditions, and if Owner finds that such conditions do materially differ, or do involve hazardous waste and cause an increase or decrease in the Contractor's cost of, or the time required for, performance of any part of the work under this contract, whether or not the work is changed as a result of such conditions, an equitable adjustment will be made, and the contract modified in writing accordingly.
In the event that a dispute arises between the Owner and the Contractor whether the conditions materially differ, or involve hazardous waste, or cause a decrease or increase in the contractor’s cost of, or time required for, performance of any part of the work, the contractor shall not be excused from any scheduled completion date provided for by the contract, but shall proceed with all work to be performed under the contract. The contractor shall retain any and all rights provided either by contract or by law which pertain to the resolution of disputes and protests between the contracting parties.
No claim by the Contractor under this clause is allowed unless the Contractor has given the notice required, except that the Owner may extend the prescribed time.
No claim by the Contractor for an equitable adjustment under this clause will be allowed if it is asserted after final payment under this contract.
F. CLAIMS:
1. DETERMINATION BY CONSTRUCTION MANAGER: Questions
regarding the meaning and intent of the contract documents must be referred by the Contractor in writing to the Construction Manager for a decision. The Construction Manager must respond to the Contractor in writing with a decision. If the Contractor disagrees with the Construction Manager's decision or considers that the decision requires extra work, he FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
must, within five calendar days, notify the Construction Manager in writing of the disagreement or of the claimed extra work involved and of the estimated cost of said work.
2. APPEALS TO THE OWNER'S REPRESENTATIVE: In the event the Contractor disagrees with any determination or decision of the Construction Manager, the Contractor may, within 15 calendar days of the date of such determination or decision, appeal the determination or decision to the Owner's Representative. The Owner's Representative must review the appeal and transmit a decision in writing to the Contractor within 30 calendar days from the receipt of the appeal. Any failure of the Contractor to appeal the decision or the determination of the Construction Manager within the 15-day period constitutes a waiver of the Contractor's right thereafter to assert a claim resulting from such determination or decision.
3. ARBITRATION: All claims, counterclaims, disputes and other matters in question between the Owner and the Contractor that are not resolved between the Owner's Representative and the Contractor will be decided by arbitration if the parties mutually agree, or in a court of competent jurisdiction within the state in which the Owner is located.
PART 3 – SPECIFICATIONS AND DRAWINGS
3.01 INTERPRETATION OF SPECIFICATIONS AND DRAWINGS
A. GENERAL:
The specifications and drawings are intended to be explanatory of each other. Work specified on the drawings and not in the specifications, or vice versa, must be executed as if it were specified in both.
B. REQUEST FOR CLARIFICATION:
In the event the work to be done or matters related to the work are not sufficiently detailed or explained in the contract documents, the Contractor must apply to the Construction Manager for further explanations as may be necessary and must conform thereto so far as may be consistent with the terms of the contract. In the event of doubt or question arising respecting the true meaning of the specifications or drawings, reference must be made to the Construction Manager for a decision. Should the Contractor disagree with the Construction Manager's decision, the Contractor may appeal to the Owner's Representative in accordance with paragraph 00 72 00-2.05 F.2.
3.02 DIVISION OF SPECIFICATIONS AND DRAWINGS
Specifications and drawings are divided into groups for the convenience of the Owner and Construction Manager. These divisions are not for the purpose of apportioning work or responsibility for work among subcontractors, suppliers, and manufacturers.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
3.03 DISCREPANCIES IN SPECIFICATIONS AND DRAWINGS
A. ERRORS AND OMISSIONS:
If the Contractor, in the course of the work, becomes aware of any claimed errors or omissions in the contract documents or in the Owner's field work, the Contractor must immediately inform the Construction Manager in writing. The Construction Manager must promptly review the matter and if it is found that finds an error or omission has been made; the Construction Manager must then determine the corrective actions and advise the Contractor accordingly. If the corrective work associated with an error or omission increases or decreases the amount of work called for in the contract, the Owner must issue an appropriate change order. After discovery of an error or omission by the Contractor, related work performed by the Contractor is done at the Contractor’s risk unless authorized by the Construction Manager. In the event the Contractor disagrees with the determination of the Construction Manager under this provision, the Contractor may appeal to the Owner's Representative in accordance with paragraph 00 72 00-2.05 F.2.
B. CONFLICTING PROVISIONS:
In cases of conflict between the specifications and drawings, the more stringent governs. Figure dimensions on drawings govern over scale dimensions and detail drawings govern over general drawings. In the event an item of work is described differently in two or more locations on the drawings and in the specifications, the Contractor must request a clarification from the Construction Manager.
C. UTILITIES:
The Owner has endeavored to determine the existence of utilities at the site of the work from the records of the owners of known utilities in the vicinity of the work. The positions of these utilities as derived from such records are shown on the drawings. No excavations were made to verify the locations shown for underground utilities. The service connections to these utilities are not shown on the drawings. It is the responsibility of the Contractor to determine the exact location of utilities and service connections thereto. The Contractor must make its own investigations, including exploratory excavations, to determine the locations and type of existing utilities, including service connections, prior to commencing any work that could result in damage to those utilities. The Contractor must immediately notify the Construction Manager as to any utility discovered by him in a different position than shown on the drawings or that is not shown on the drawings.
Work on utilities must be performed and paid for as follows:
1. Known utilities. The Contractor must provide all labor, equipment, materials, and services necessary to remove, relocate or maintain utilities specified on the drawings. The work on each utility must be performed in a manner satisfactory to the utility owner. The utility owner has the option of doing such work with its own forces at the FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
Contractor's expense or permitting the work to be performed by the Contractor.
2. Service connections. Locations of service connections are not specified on the drawings. The Contractor must provide all labor, equipment, and material to remove, relocate or maintain service connections. The work on service connections must be performed in a manner satisfactory to the service connection owner. The service connection owner has the option of doing such work with its own forces at the Contractor's expense or permitting the work to be performed by the Contractor.
3. Unknown utilities. When a utility is not specified on the drawings, or it is located in a position different from that specified on the drawings, and interferes with the work, a change order based on changed site conditions will be issued in accordance with paragraph 00 72 00-7.02.
Interference with the work is defined as a utility that crosses or projects into the plane of the work at an elevation between the top and bottom of the work. If it is necessary to remove, relocate, or temporarily maintain the utility, that work must be included in the change order.
The utility owner has the option of doing such work at the Contractor's expense or permitting the work to be performed by the Contractor. In either case, the cost of the work will be included in the change order.
No representations are made that the obligations to move or temporarily maintain the utility and to pay the cost thereof is or is not required to be borne by the owner of such utility, and it is the responsibility of the Contractor to investigate to find out whether or not the cost is required to be borne by the owner of the utility.
The right is reserved to governmental agencies and to owners of utilities to enter upon streets, alleys, rights-of-way or easements for the purpose of making changes in their property made necessary by the work and for the purpose of maintaining and making repairs to their property.
3.04 SUBMITTALS
Where required by the specifications, the Contractor must submit specified information that will enable the Construction Manager to advise the Owner whether the Contractor's proposed materials, equipment or methods of work are in general conformance to the design concept and in compliance with the drawings and specifications. The requirements for submittals are specified in Part B of the project manual.
3.05 CONTRACTOR'S COPIES OF PROJECT MANUALS
Within 10 business days after notice to proceed, the Owner will furnish to the Contractor 4 sets of project manuals including 2 sets of half-size drawings, and 2 sets of full-size FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
drawings. The Contractor is advised that revisions incorporating changes by addenda will not be incorporated into the reduced or full-size drawings furnished under the provisions of this paragraph. Additional copies of the project manual, if required by the Contractor, will be furnished by the Owner at cost. The Contractor must keep at the construction site at least one set of the project manual and one set of full-size drawings.
PART 4 – MATERIAL, EQUIPMENT AND WORKMANSHIP
4.01 GENERAL
Unless otherwise specifically stated in the contract documents, the Contractor must provide and pay for materials, labor, tools, equipment, water, light, power, transportation, supervision, and temporary construction of any nature, and other services, and facilities of any nature, to execute, complete, and deliver the work within the specified time. Material and equipment must be new and of a quality at least equal to that specified. Equipment offered must be current models which have been in successful regular operation under comparable conditions. This requirement does not apply to minor details, nor to thoroughly demonstrated improvements in design or in materials of construction. All construction work must be executed in conformity with the standard practice of the relevant trade.
4.02 PRODUCT DATA
Where required by the specifications, the Contractor must provide product data, which is a submittal furnished for information only. The information and data furnished is required by the Owner for inspecting, testing, operating, and maintaining parts of the work. The requirements for product data are specified in Part B of the project specifications.
4.03 QUALITY
Where the contract requires that materials or equipment be provided or that construction work be performed, and detailed specifications of such materials, equipment or construction work are not set forth, the Contractor must perform the work using materials and equipment of the best grade in quality and workmanship obtainable in the market, from firms of established good reputations, and must follow standard practices in the performance of construction work. The work performed must be in conformity and harmony with the intent to secure the highest standard of construction and equipment of work as a whole and in part.
4.04 MATERIAL AND EQUIPMENT SPECIFIED BY NAME
When material or equipment is specified by reference to two or more patents, brand names, or catalog numbers, it is understood that this is referenced for the purpose of defining the performance or other salient requirements, and that other materials or equipment, of equal capacities, quality and function will be considered by the Owner upon the Contractor's request for substitution. Requests for substitution must be made in accordance with paragraph 00 72 00-4.05.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
4.05 REQUESTS FOR SUBSTITUTION
The Contractor may offer material or equipment of equal or better quality and performance in substitution for those specified. The Owner will consider offers for substitution only from the Contractor and will not acknowledge or consider such offers from suppliers, distributors, manufacturers, or subcontractors. The Contractor's offers of substitution must be made in writing to the Construction Manager and must include sufficient data to enable the Construction Manager to assess the acceptability of the material or equipment for the particular application and requirements.
If the offered substitution necessitates changes to or coordination with other portions of the work, the data submitted must include drawings and details showing such changes.
Contractor agrees to perform these changes as part of the substitution of material or equipment at no additional cost to the Owner. Within 30 calendar days after receipt of the offer of substitution, the Construction Manager will review the material submitted by the Contractor and advise the Contractor of objections, if any, to the proposed substitution or if further information is required. Upon notification by the Construction Manager, the Contractor must either provide material or equipment that complies with project specifications or if requested, furnish additional information. Although the Construction Manager may not take any objections to the proposed substitution, that will not relieve the Contractor from responsibility for the efficiency, sufficiency, quality and performance of the substitute material or equipment, in the same manner and degree as the material and equipment specified by name. Any cost difference associated with a substitution must be reflected in the offer and the contract documents must be modified by a change order.
4.06 DEMONSTRATION OF COMPLIANCE WITH CONTRACT REQUIREMENTS A. INSPECTION:
To demonstrate Contractor’s compliance with the contract requirements, the Contractor must assist the Construction Manager in the performance of inspection work.
The Contractor must grant the Construction Manager access to the work and to the site of the work, and to the places where work is being prepared, or whence materials, equipment or machinery are being obtained for the work. The Contractor must provide information requested by the Construction Manager in connection with inspection work.
If the contract documents, laws, ordinances, or any public regulatory authority require parts of the work to be specially inspected, tested or approved, the Contractor will give the Construction Manager adequate prior written notice of the availability of the subject work for examination.
If parts of the work are covered in contravention of the Construction Manager's directive, the cost of exposing the work for inspection and closing must be borne by the Contractor regardless of whether or not the work is found to be in compliance with the contract.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
If any work is covered in the absence of the Construction Manager's directive to the contrary, the Contractor must, if directed to do so by the Construction Manager, uncover, expose or otherwise make available for inspection, portions of covered work. If it is found that such work is defective, the Contractor must bear the expense of uncovering and reconstructing. If the work is found to be in compliance with the contract, the Contractor will be allowed an increase in the contract price, or an extension in the contract time, or both. A change order will be issued to document the increase, extension, or both.
B. SAMPLES OF MATERIALS:
In cases where compliance with contract requirements for materials to be incorporated in the work requires laboratory examination or special testing, the Contractor must provide samples or specimens as requested by the Construction Manager. Such samples or specimens must be provided in ample time to permit making proper test analysis and examinations before incorporating the material into the work. Tests of material will be conducted in accordance with the technical specifications. In the absence of a specific test requirement, the Construction Manager will determine the appropriate standard test to be used.
C. CERTIFICATION:
In cases where compliance of materials or equipment to contract requirements is not readily determinable through inspection and tests, the Construction Manager will request that the Contractor provide properly authenticated documents, certificates, or other satisfactory proof of compliance. These documents, certifications, and proofs must include performance characteristics, materials of construction and the physical or chemical characteristics of materials.
D. INSPECTION AT POINT OF MANUFACTURING:
If Owner’s inspection and testing of materials or equipment in the vicinity of the work is not practicable, the specifications may require that the inspection and testing or witnessing of tests take place at the point of manufacture. In this case and in the event the remote inspection and testing is not specified and is requested by the Owner, the required travel, subsistence, and labor expenses will be paid by the Owner. If the Contractor requests the Owner to inspect and test material or equipment at the point of manufacture, then the additional cost to the Owner for travel, subsistence, and labor expenses must be paid by the Contractor.
4.07 STORAGE OF MATERIALS AND EQUIPMENT
Materials and equipment must be stored so as to insure the preservation of their quality and fitness for the work. Stored equipment and materials must be located so as to facilitate inspection. The Contractor is responsible for damages that occur in connection with the care and protection of materials and equipment until final acceptance of the work.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
4.08 MANUFACTURER'S DIRECTIONS
Manufactured articles and materials and equipment must be applied, installed, connected, erected, adjusted, tested, operated, and maintained as recommended by the manufacturer, unless otherwise specified. Manufacturer's installation instructions and procedures must be provided or obtained prior to installation of the manufactured articles, material, and equipment. Conflicts between manufacturer’s installation instructions and these specifications require the Contractor to make a request for information (RFI).
4.09 DEFECTIVE WORK
A. CORRECTION OF DEFECTIVE WORK:
When, and as often as the Construction Manager determines through his or her inspection procedures to be the case, material, equipment or workmanship incorporated in the project do not meet the requirements of the contract, the Construction Manager will give written notice of the noncompliance to the Contractor. Within five days from the receipt of the notice, the Contractor must undertake the work necessary to correct the deficiencies, and to comply with the contract. If the Contractor disagrees with the Construction Manager's determination and believes that the corrective work should be covered by a change order, the Contractor must immediately notify the Owner's Representative, in writing, setting forth the Contractor’s position. Within five days after receipt of the Contractor's notification, the Owner's Representative will review the matter and notify the Contractor, in writing, of his or her determination. If the Owner's Representative determines that the corrective work is required to comply with the contract, the Contractor must proceed with that work. As a condition precedent to the Contractor's request for either additional compensation or time extension, or both, resulting from the performance of the corrective work, the Contractor must, within 15 calendar days after receipt of the Owner's Representative's determination, notify the Owner's Representative in writing of the Contractor’s intent to claim additional compensation, time or both. The Contractor must document the cost information associated with the corrective work with daily records in accordance with paragraph 00 72 00-7.02 F and provide that information to the Construction Manager monthly. Receipt of the cost data by the Construction Manager will not be construed to be an acceptance of the corrective work, or an authorization for a change order to cover the corrective work.
B. RETENTION OF DEFECTIVE WORK:
Prior to acceptance of the project, the Owner may, at its option, retain work which is not in compliance with the contract if the Owner determines that such defective work is not of sufficient magnitude or importance to make the work dangerous or undesirable. The Owner also may retain defective work, if, in the opinion of the Construction Manager, and with concurrence of the Owner's Representative, removal of that work is impractical or will create conditions that are dangerous or undesirable. Just and reasonable value for such defective work will be judged by the Owner and appropriate deductions will be made in the payments due, or to become due to the Contractor. Final acceptance does not act as FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
a waiver of the Owner's right to recover from the Contractor an amount representing the deduction for retention of defective work.
4.10 GUARANTEE
The guarantee period is 365 days from the Notice of Completion. During the guarantee period, the Contractor must, upon the receipt of notice in writing from the Owner, promptly make all repairs arising out of defective materials, workmanship, or equipment. The Owner is hereby authorized to make such repairs, if ten days after giving of such notice to the Contractor, the Contractor has failed to make or undertake the repairs with due diligence.
In case of an emergency where, in the opinion of the Owner, delay could cause serious loss or damage, repairs may be made without notice to the Contractor and the expenses in connection with those repairs are chargeable to the Contractor.
For the purpose of this paragraph, "acceptance of the work" means the acceptance of the project by the Owner, in accordance with paragraph 00 72 00-7.07. "Acceptance of the work" does not extinguish any covenant or agreement on the part of the Contractor to be performed or fulfilled under this contract that has not, in fact, been performed or fulfilled at the time of such acceptance. All covenants and agreements continue to be binding on the Contractor until they have been fulfilled.
The Owner and the Contractor agree that guarantee on the equipment possessed and used by the Owner in accordance with paragraph 00 72 00-7.06 will commence on the date that the Owner takes possession of the equipment and so notifies the Contractor in writing.
Owner and Contractor further agree that such taking possession and use will not be deemed as substantial completion or acceptance of any part of the work. Takeover of equipment will be at the Owner's option and will not be made until the equipment can be put into routine service on a permanent basis.
4.11 DOMESTIC PREFERENCE
In accordance with 2 CFR 184.322, as appropriate and to the extent consistent with law, the Grantee should, to the greatest extent practicable under this contract, provide a preference for the purchase, acquisition, or use of goods, products, or materials produced in the United States (including but not limited to iron, aluminum, steel, cement, and other manufactured products). The requirements of this paragraph must be included in all subawards and in all contracts and purchase orders for work or products under this contract.
Additionally, the funding source dictates that the Grantee meet the 2 CFR 184 to Build America, Buy America (BABA) Act.
4.12 PROCUREMENT OF RECOVERED MATERIALS UNDER RCRA
Contractor must comply with Section 6002 of the Solid Waste Disposal Act, as amended by the Resource Conservation and Recovery Act (RCRA) (42 U.S.C. 6962). The requirements of Section 6002 include procuring only items designated in guidelines of the Environmental FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
Protection Agency (EPA) at 40 CFR Part 247 that contain the highest percentage of recovered materials practicable, consistent with maintaining a satisfactory level of competition, where the purchase price of an item exceeds $10,000 or the value of the quantity acquired during the preceding fiscal year exceeded $10,000; procuring solid waste management services in a manner that maximizes energy and resource recovery; and establishing an affirmative procurement program for procurement of recovered materials identified in the EPA guidelines.
PART 5 – LIABILITY AND INSURANCE
5.01 LIABILITY OF CONTRACTOR
The Contractor is liable for any and all losses or damages from whatever cause that, prior to final acceptance, may occur on or to any part of the work. The Contractor is not liable for losses or damages caused solely by the act of the Owner.
The Contractor is liable for damages and injury to persons owning property, on or in the vicinity of the work, or which occur to a person, persons, or any property whatsoever, arising out of the Contractor's performance of this contract. The Contractor's liability is not dependent upon whether or not such damage or injury be caused by the negligence of the Contractor, and whether or not such damage or injury is caused by the inherent nature of the work as specified.
The Contractor must indemnify and hold the Owner, the Construction Manager, the design engineer, and their officers, principals, agents, subcontractors, and employees, harmless from any and all loss, defense cost, expense, claims, demand or liability whatsoever, arising from allegations of injuries to persons or damage to property related to the performance of this contract, regardless of concurrent negligence on the part of such indemnitees. This indemnification obligation is not limited in any way by any limitation on the amount or type of damages, compensation or benefits payable by or for the Contractor or any subcontractor under workers compensation acts, disability benefit acts, or another employee benefit act.
In case any suit or legal proceeding is brought against the Owner, the Construction Manager, the design engineer, or their officers, principals, agents, subcontractors, or employees, on account of loss or damage sustained by person, or persons, or property, as a result of the performance of the work covered by this contract, the Contractor agrees to assume the cost of defense of that action, and to pay the expenses connected therewith, and the judgments that may be obtained against the Owner, the Construction Manager, the design engineer, or their officers, principals, agents, subcontractors, or employees, in such suits. In the event that a lien is placed against the property of the Owner, the Construction Manager, the design engineer, or their officers, principals, agents, subcontractors, or employees, as a result of such suits, the Contractor agrees immediately to cause the same to be dissolved and discharged by giving bond or otherwise. This agreement to defend and to pay the related expenses exists whether or not the alleged injuries or damage are due to the negligence of the Contractor, and whether or not the alleged injuries or damage are caused by the inherent nature of the work, as specified.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
The mention of specific duties or liabilities imposed on the Contractor are not a limitation or restriction of general duties or liabilities imposed upon the Contractor by the contract.
Reference to specific duties or liabilities is made herein, merely for the purpose of explanation.
5.02 BONDS
The Contractor must provide two bonds, each in the amount of 100 percent of the contract price. One bond will serve as security for the faithful performance of the work and the other as security for the faithful payment and satisfaction of the persons furnishing materials and performing labor on the work. The bonds must be issued by a corporation duly and legally licensed to transact surety business in the State of California. The two bonds must remain in force throughout the period required to complete the work, and thereafter for a period of 365 calendar days after final acceptance of the work. The bonds must be executed by a duly licensed surety company that is listed in the latest Circular 570 of the United States Treasury Department as being acceptable as surety on federal bonds. No surety's liability on the bonds may exceed the underwriting limitations for the respective surety specified in Circular 570. The scope of the bonds or the forms thereof prescribed in these contract documents in Sections 00 61 05 and 00 61 10 in no way affect or alter the liabilities of the Contractor to the Owner.
5.03 INSURANCE
A. GENERAL:
1. EVIDENCE OF INSURANCE: Prior to execution of the contract, the Contractor must file, with the Owner, evidence of insurance from the insurer, certifying to the coverage of the insurance required herein. The evidence of insurance must be certified by a properly authorized officer, agent, general agent, or qualified representative of the insurer, and must certify the names of the insured, the type and amount of insurance, the location and operations to which the insurance applies, and the expiration date. The evidence must include the agreement of the insurer to give, by certified mail, notice to the Owner at least 30 calendar days prior to the effective date of cancellation, lapse, or material change in the policy.
This Certificate of Insurance is not an insurance policy and does not amend, extend, or alter the coverage afforded by the policies listed herein. Notwithstanding any requirement, term, or condition of the contract with respect to which this certificate is issued, the insurance afforded by the policies described herein is subject to the terms, exclusions, and conditions of such policies.
2. CANCELLATION OF INSURANCE: The Contractor must deliver to the Owner policies of insurance and the receipts for payment of premiums thereon. Should the Contractor neglect to obtain and maintain in force such insurance and deliver such policy or policies and receipts to the Owner, then Owner may obtain and maintain such insurance.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
The Contractor hereby appoints the Owner as its true and lawful attorney, to do the things necessary for this purpose. Money expended by the Owner under the provisions of this paragraph for insurance premiums will be charged to the Contractor. Failure of the Owner to obtain such insurance in no way relieves the Contractor of his responsibilities under this contract.
3. ACCEPTABILITY OF INSURERS. Insurance is to be placed with insurers authorized to conduct business in the State of California with a current A.M. Best rating of no less than A: VII, unless otherwise approved by the Owner.
B. MINIMUM SCOPE AND LIMIT OF INSURANCE:
1. Coverage shall be at least as broad as:
a. Commercial General Liability (CGL): Insurance Services Office (ISO) Form CG 00 01 covering CGL on an “occurrence” basis, including products and completed operations, property damage, bodily injury and personal & advertising injury with limits no less than $5,000,000 per occurrence. If a general aggregate limit applies, either the general aggregate limit shall apply separately to this project/location (ISO CG 25 03 or 25 04) or the general aggregate limit shall be twice the required occurrence limit. The required insurance must be maintained until final acceptance of the work and must continue for a period of 365 calendar days after the final acceptance of the work.
b. Automobile Liability: Insurance Services Office Form CA 0001 covering Code 1 (any auto), with limits no less than $5,000,000 per accident for bodily injury and property damage.
c. Workers’ Compensation insurance as required by the State of California, with Statutory Limits, and Employers’ Liability insurance with a limit of no less than $1,000,000 per accident for bodily injury or disease.
d. Builder’s Risk (Not required for this Contract) (Course of Construction) insurance utilizing an “All Risk” (Special Perils) coverage form, with limits equal to the completed value of the project and no coinsurance penalty provisions. Such coverage shall name the Owner as a loss payee. Consistent with California Public Contracts Code, Section 7105, builders risk insurance is not required for coverage of losses in excess of five percent of the contract price for damages resulting from earthquakes in excess of magnitude of 3.5 on the Richter scale or from tidal waves. Coverage in the amount of five percent of the contract price for such losses must be provided by the Contractor.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
2. If the contractor maintains broader coverage and/or higher limits than the minimums shown above, the Entity requires and shall be entitled to the broader coverage and/or the higher limits maintained by the contractor.
Any available insurance proceeds in excess of the specified minimum limits of insurance and coverage shall be available to the Entity.
3. The insurance policies are to contain or be endorsed to contain the following provisions:
a. The Owner, its officers, officials, employees, and volunteers are to be covered as additional insureds on the CGL policy with respect to liability arising out of work or operations performed by or on behalf of the Contractor including materials, parts, or equipment furnished in connection with such work or operations and automobiles owned, leased, hired, or borrowed by or on behalf of the Contractor. General liability coverage can be provided in the form of an endorsement to the Contractor’s insurance (at least as broad as ISO Form CG 20 10, CG 11 85 or both CG 20 10, CG 20 26, CG 20 33, or CG 20 38; and CG 20 37 forms if later revisions used).
b. For any claims related to this project, the Contractor’s insurance coverage shall be primary insurance coverage at least as broad as ISO CG 20 01 04 13 as respects the Entity, its officers, officials, employees, and volunteers. Any insurance or self-insurance maintained by the Entity, its officers, officials, employees, or volunteers shall be excess of the Contractor’s insurance and shall not contribute with it.
4. Contractor hereby agrees to waive rights of subrogation which any insurer of Contractor may acquire from Contractor by virtue of the payment of any loss. Contractor agrees to obtain any endorsement that may be necessary to affect this waiver of subrogation. The Workers’ Compensation policy shall be endorsed with a waiver of subrogation in favor of the Owner for all work performed by the Contractor, its employees, agents, and subcontractors.
PART 6 – PROGRESS AND COMPLETION
6.01 NOTICE TO PROCEED
After execution of the contract by the Owner, written notice to proceed will be given by the Owner to Contractor. Notwithstanding other provisions of the contract, the Contractor is not obligated to perform work and the Owner is not obligated to accept or pay for work performed by the Contractor prior to date of the notice to proceed. The Owner's knowledge of work FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
being performed prior to date of the notice to proceed does not obligate the Owner to accept or pay for such work.
6.02 CONTRACT TIME
A. GENERAL:
Time is of the essence of the contract. The Contractor must promptly start the work after the date of the notice to proceed and must prosecute the work so that the project is complete within the time specified in paragraph 1.01 of Section 01 21 43 “Time Allowances”. During periods when weather or other conditions are unfavorable for construction, the Contractor will pursue only such portions of the work as will not be damaged thereby. No portions of the work where acceptable quality or efficiency will be affected by unfavorable conditions may be constructed while those conditions exist. It is expressly understood and agreed by and between the Contractor and the Owner that the contract time for completion of the work is reasonable, taking into consideration the average climatic and economic conditions and other factors prevailing in the locality of the work.
B. CONSTRUCTION SCHEDULE:
The Contractor must provide a construction schedule and reports for scheduling and coordinating the work within the contract time. Contract time extensions must be incorporated into updated schedules, reflecting their effect at the time of occurrence. Failure of the Contractor to comply with these requirements for submittal of the construction schedule and reports may be cause for delay in review of progress payments by the Construction Manager.
C. CONSTRUCTION PROGRESS:
The Contractor must furnish such manpower, materials, facilities, and equipment as may be necessary to insure the prosecution and completion of the work in accordance with the accepted schedule. If work falls behind the accepted construction schedule, the Contractor agrees that he will take some or all of the following actions to return the project to the accepted schedule. These actions may include the following:
1. Increase manpower in quantities and crafts;
2. Increase the number of working hours per shift, shifts per working day, working days per week, or the amount of equipment, or any combination of the foregoing; and/or
3. Reschedule activities.
If requested by the Construction Manager, the Contractor must prepare a proposed schedule revision demonstrating a plan to make up the lag in progress and insure completion of the work within the contract time. The proposed revision must be submitted FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
to the Construction Manager in accordance with Section 01 33 00. Upon receipt of an acceptable proposed schedule, the revision to the construction schedule must be made in accordance with Section 01 33 00 Paragraph 4. All actions to return the project to the accepted schedule are at the Contractor's expense.
The Contractor must pay all costs incurred by the Owner that result from the Contractor's action to return the project to its accepted schedule. Contractor agrees that Owner may deduct such charges from payments due the Contractor. It is further understood and agreed that none of the services performed by the Construction Manager in monitoring, reviewing, and reporting project status and progress operate to relieve the Contractor of responsibility for planning and managing construction work in conformance with the construction schedule.
D. DELAYS:
1. NOTICE OF DELAYS: When the Contractor foresees a delay in the prosecution of the work and, in any event, immediately upon the occurrence of a delay that the Contractor regards as unavoidable, he or she must notify the Construction Manager in writing of the probability of the occurrence of the delay, the extent of the delay, and its probable cause. The Contractor must take immediate steps to prevent, if possible, the occurrence or continuation of the delay. If this cannot be done, the Construction Manager must determine how long the delay is likely to continue and to what extent the prosecution and completion of the work are being delayed. The Construction Manager must also determine whether the delay is to be considered avoidable or unavoidable and notify the Contractor of his or her determination. The Contractor agrees that no claim is allowed for delays the causes of which are not called to the attention of the Construction Manager at the time of their occurrence or as soon thereafter as Contractor becomes aware of them.
2. AVOIDABLE DELAYS: Avoidable delays in the prosecution of the work include delays that could have been avoided by the exercise of care, prudence, foresight, and diligence on the part of the Contractor or its subcontractors. Avoidable delays include:
a. Delays which may in themselves be unavoidable, but which affect only a portion of the work and do not necessarily prevent or delay the prosecution of other parts of the work nor the completion of the whole work within the contract time.
b. Time associated with the reasonable interference of other contractors employed by the Owner which do not necessarily prevent the completion of the whole work within the contract time.
3. UNAVOIDABLE DELAYS: Unavoidable delays in the prosecution or completion of the work include delays that result from causes beyond the control of the Contractor and could not have been avoided by the exercise of care, prudence, foresight, and diligence on the part of the Contractor or its subcontractors. Delays in completion of FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
the work of other contractors employed by the Owner will be considered unavoidable delays insofar as they interfere with the Contractor's completion of the work. Delays due to normal weather conditions are not regarded as unavoidable because the Contractor agrees to plan its work with prudent allowances for interference by normal weather conditions. Delays caused by Acts of God, fire, unusual storms, floods, tidal waves, earthquakes, strikes, labor disputes, freight embargoes and shortages of materials are considered unavoidable delays if they prevent the Contractor from proceeding with at least seventy-five percent (75%) of the normal labor and equipment force for at least five hours per day toward completion of the current controlling item on the accepted critical path schedule.
If abnormal conditions prevent the work from beginning at the usual starting time, or prevent the Contractor from proceeding with seventy-five percent (75%) of the normal labor and equipment force for a period of at least five hours per day, and the crew is dismissed as a direct consequence, Contractor will not be charged for a working day whether or not conditions change so that the major portion of the day could be considered to be suitable for work on the controlling item.
E. EXTENSION OF TIME:
1. AVOIDABLE DELAYS: If the work is not completed in the accepted construction schedule, including any extension of time that may have been granted for unavoidable delays, the Contractor will be assessed damages for those costs incurred by the Owner that are attributable to the fact that the work was not completed on schedule.
The Owner may grant an extension of time for avoidable delay if he or she deems it in its best interest. If the Owner grants an extension of time for avoidable delay, the Contractor agrees to pay actual costs, including charges for engineering, inspection, and administration, as specified in Section 00 72 00 Paragraph 7.04, incurred during the extension.
2. UNAVOIDABLE DELAYS: For delays that the Contractor considers to be unavoidable, he must submit to the Construction Manager complete information demonstrating the effect of the delay on the controlling operation in the accepted construction schedule. The submission must be made within 30 calendar days of the occurrence that is claimed to be the cause of the unavoidable delay. The Construction Manager will review the Contractor's submission and determine the number of days of unavoidable delay and the effect of any unavoidable delay on controlling operations of the work. The Owner agrees to grant an extension of time to the extent that unavoidable delays affect controlling operations in the construction schedule. During such extension of time, neither extra compensation, nor engineering inspection and administration, nor damages for delay will be charged to the Contractor. It is understood and agreed by the Contractor and Owner that time extensions due to unavoidable delays will be granted only if such unavoidable delays involve controlling operations which would prevent completion of the whole work within the specified contract time.
3. LIQUIDATED DAMAGES: It is agreed by the parties to the contract that in case all the work called for under the contract in all parts and requirements is not FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
finished or completed within the number of calendar days as set forth in Section 01 21 43 “Time Allowances,” damage will be sustained by the Owner, and that it is and will be impracticable and extremely difficult to ascertain and determine the actual damage which the Owner will sustain in the event of and by reason of the delay; and it is therefore agreed that the Contractor will pay to the Owner, the sum of One Thousand dollars ($1,000.00) per day for each and every calendar day's delay in finishing the work in excess of the number of working days prescribed or for work completed after November 30, 2026; and the Contractor agrees to pay the liquidated damages herein provided for, and further agrees that the Owner may deduct the amount thereof from any moneys due or that may become due the Contractor under the contract.
6.03 SUSPENSION PROCEDURES
The Owner may, at its convenience and at any time and without cause, suspend, delay, or interrupt all or any part of the work for a period of not more than 90 days by notice in writing to the Contractor. The Owner must specify the date on which the work must be resumed.
The work must be resumed by the Contractor within 10 days after receiving written notice from the Owner to do so. The Contractor will be allowed an increase in the contract price or an extension of contract time, or both, directly attributable to any suspension if he makes a claim therefore as provided in the paragraphs related to change of contract price and change of contract time.
6.04 DEFAULT PROCEDURES
A. EVENTS OF DEFAULT:
The Owner may declare the Contractor in default of the contract if any one or more of the following events occurs:
1. Contractor is bankrupt or insolvent.
2. Contractor makes a general assignment for the benefit of creditors.
3. A trustee or receiver is appointed for Contractor, or for any of Contractor's property.
4. Contractor files a petition to take advantage of any debtor's act, or to reorganize under any bankruptcy chapter or law.
5. Contractor repeatedly fails to make prompt payments to subcontractors or others for labor, materials, or equipment.
6. Contractor disregards laws, ordinances, rules, regulations, or orders of any public body having jurisdiction.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
7. Contractor disregards the authority of Construction Manager.
8. Contractor violates in any substantial way the provisions of the contract documents by failing, neglecting, or refusing to proceed according to and in full compliance with the provisions and covenants of the contract documents, including completing the work within the time prescribed.
B. NOTICE OF DEFAULT AND OPPORTUNITY TO CURE:
In the event the Owner declares the Contractor be in default, the Owner will must give written notice of default to the Contractor’s Representative either personally or by certified mail to the business address of the Contractor. Notice will be given as of the date of personal service or the date of delivery of the certified mail. Except for emergencies, the Contractor will have ten (10) days to cure the default after the date of the notice. If the default cannot be reasonably cured within ten (10) days, then Contractor must commence to cure the breach within ten (10) days and diligently and continuously prosecute such cure to completion within a reasonable amount of time, which in no event may be later than twentyone (21) days after receipt of the notice.
C. REMEDIES FOR DEFAULT:
In the event that the Contractor fails to cure any default declared by Owner within the time period set forth above, then the Owner may pursue any remedies available under law or equity, including, without limitation, the following:
1. Invoke Performance Bond. The Owner may, with or without terminating the contract and reserving to itself all rights to damages related thereto, exercise its right under the performance bond.
2. Suspend the Contract. The Owner may, without terminating the contract and reserving to itself all rights to damages related thereto, suspend all or any portion of this contract for as long a period of time as the Owner determines, in its sole discretion, appropriate, in which event the Owner will have no obligation to adjust the contract price or contract time, and will have no liability to Contractor for damages if the Owner directs Contractor to resume work.
3. Perform and Withhold. The Owner may, without terminating the contract, engage others to perform the work or portion of the work that has not been performed by Contractor and withhold the cost thereof to the Owner from future payments to Contractor, reserving to itself all rights to damages related thereto.
4. Delete Certain Services. The Owner may, without terminating the contract, delete certain portions of the work, reserving to itself all rights to damages related thereto.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
5. Terminate the Contract. The Owner may terminate all or any part of this contract for default in accordance with the provisions below, reserving to itself all rights to damages related thereto.
6. Additional Provisions. All of Owner’s rights and remedies under this contract are cumulative and in addition to those rights and remedies available in law or in equity. Designation in the contract of certain breaches as material may not be construed as implying that other breaches not so designated are not material nor may such designations be construed as limiting Owner’s right to terminate the contract, or the exercise of its other rights or remedies for default, to only material breaches. Owner’s determination of whether there has been noncompliance with the contract so as to warrant exercise by Owner of its rights and remedies for default under the contract, will be binding on all parties. No termination or action taken by Owner after such termination will prejudice any other rights or remedies of Owner provided by law or equity or by the contract upon such termination; and Owner may proceed against Contractor to recover all damages, liquidates or otherwise, suffered by Owner.
6.05 TERMINATION PROCEDURES
A. TERMINATION FOR DEFAULT:
1. The Owner may terminate the contract upon 7 days’ written notice to Contractor and to Contractor’s surety whenever the Contractor is declared to be in default and fails to timely cure the default. Notice will be given as of the date of personal service or the date of delivery of the certified mail.
2. After termination of the contract for default, the Owner may exclude the Contractor from the site and take possession of the work and all of the Contractor's tools, appliances, construction equipment, and machinery at the site and use the same to the full extent they could be used by the Contractor. The Owner may incorporate in the work all materials stored at the site or for which the Owner has paid the Contractor and that are stored elsewhere. In such case, the Contractor is not entitled to receive any further payment until the work is finished.
3. If the unpaid balance of the contract price exceeds the direct and indirect cost of the completed work, including compensation for additional professional services, the excess must be paid to the Contractor. If such costs exceed such unpaid balance, the Contractor must pay the difference to the Owner. The costs incurred by the Owner will be verified by the Construction Manager and incorporated into a FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
change order, but in finishing the work, the Owner will not be required to obtain the lowest figure for work performed.
4. Where the Contractor's services have been so terminated by the Owner, the termination does not affect any rights of the Owner against the Contractor for damages then existing or that may thereafter accrue.
Any retention or payment of monies due the Contractor by the Owner will not release the Contractor from liability for said damages.
5. If the Owner terminates this contract for default, and it is thereafter determined that the Contractor had not failed to perform its obligations or defaulted in any way, the termination will then be deemed to have been effected for the convenience of the Owner. In that event, any adjustment of compensation to Contractor must be in accordance with paragraph 00 72 00-6.05 B.
B. TERMINATION BY OWNER FOR OTHER THAN DEFAULT:
1. The Owner may, without prejudice to any other remedy it may have under the provisions of the contract, terminate this contract, in whole or in part, at any time by giving written notice to Contractor or its representative either personally or by certified mail. Termination is effective upon receipt of the notice by Contractor. Contractor must immediately discontinue work and take all reasonable steps with its suppliers and subcontractors to minimize cancellation charges and other costs.
2. In the event of termination for reasons other than default of Contractor, Contractor is entitled to recover all reasonable costs incurred in connection with performance of the work, plus any cost and expense reasonably and necessarily incurred in connection with the termination, plus a percentage of the profit based on the percentage of completion of the work.
C. TERMINATION BY CONTRACTOR:
If the work is stopped by order of a court, a public authority, or the Owner for a period of 90 calendar days or more, through no act or fault of the Contractor or anyone employed by him or his subcontractors, then the Contractor may terminate the contract upon 10 calendar days’ written notice to the Owner either by personal delivery or certified mail, effective upon receipt. The Owner must implement procedures as set forth in paragraph 00 72 00-6.05 B.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
PART 7 – MEASUREMENT AND PAYMENT
7.01 PAYMENTS TO CONTRACTOR
A. BREAKDOWN OF CONTRACT PRICES:
If the Contractor disagrees with the Measurement and Payment section of Part B and except in cases where unit prices form the basis for payment under the contract, the Contractor must, within 20 days of receipt of the notice to proceed, submit a breakdown of the contract price showing the value assigned to each part of the work including an allowance for profit and overhead. In submitting the breakdown, the Contractor certifies that it is not unbalanced and that the value assigned to each part of the work represents its estimate of the actual cost, including profit and overhead, of performing that part of the work.
The breakdown must be sufficiently detailed to permit its use by the Construction Manager as one of the bases for evaluating requests for payment.
B. PROJECT STATUS REVIEW:
Contractor and Construction Manager will meet each month prior to the Contractor submitting the progress payment request for the previous month. The purpose of the meeting is to review project status in relation to the construction schedule; review value of work completed during the previous month; and, if applicable, review Contractor's plans to return project status to that required by the schedule. Within 5 days following this meeting, the Contractor must submit a written progress report comprising:
1. A copy of the current construction schedule marked up to indicate percent complete, actual completion or start dates since the previous review, and the estimated remaining duration for each activity in progress.
2. Reasons any activities are behind schedule and a description of the corrective steps being taken.
C. PROGRESS PAYMENTS:
1. PAYMENT REQUEST PROCEDURES: By the 5th day of each
month, the Contractor must submit to the Construction Manager a partial-payment estimate, filled out and signed by the Contractor, covering acceptable work performed during the previous month or since the last partial payment estimate was submitted. If requested by the Construction Manager, the Contractor must provide additional data to support the payment estimate. Additional data may include satisfactory evidence of payment for equipment, materials, and labor including payments to subcontractors and suppliers.
Requests for payment for delivered equipment and material must be accompanied by certified invoices by the suppliers. Such equipment and material must be suitably and safely stored at the site of the work.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
2. REVIEW PROCEDURES: Within 7 days after receipt of the partial payment estimate, the Construction Manager will review the estimate and either (a) indicate in writing to the Owner's Representative his or her concurrence with the estimate and the Construction Manager’s recommendation that payment be made or (b) indicate in writing to the Contractor his or her reasons for not concurring with the estimate. If the Construction Manager recommends payment and the Owner's Representative concurs, the Owner will, within 30 calendar days after receipt of the Construction Manager's recommendation, pay the Contractor a progress payment on the basis of the approved partial-payment estimate.
The payments will take into account the retention provisions provided for herein.
In the event the Construction Manager does not concur with the estimate, the Contractor may make the changes necessary to obtain the Construction Manager's concurrence and resubmit the partial-payment estimate or submit the original progresspayment estimate directly to the Owner's Representative, indicating in writing his or her reasons for refusing to make the changes necessary to obtain concurrence.
3. RETENTION: The Owner will retain a percentage of each payment except as specified below, in accordance with Public Contract Code Section 7201. The retained amount is available for the protection and payment of the person, or persons, mechanics, subcontractors, or material men who perform labor or work under the contract, and persons who supply such person, persons or subcontractors with components and supplies for carrying on such work.
The Owner will retain five (5) percent of each progress payment.
Under no circumstances may any provision of this section be construed to limit the ability of the Owner to withhold 150 percent of the value of any disputed amount of work from the final payment, as provided for in Section 7107 of the Public Contract Code. In the event of a good faith dispute, nothing in this section may be construed to require the Owner to pay for work that is not approved or accepted in accordance with the proper plans or specifications.
4. WITHHOLDING: The Construction Manager may refuse to
recommend the whole or any part of any payment if, in the Construction Manager's opinion, it would be incorrect to make such recommendation to the Owner. The Construction Manager may also refuse to recommend any payment, or because of subsequently discovered evidence or the result of any tests, may nullify any payment previously recommended to such extent as may be necessary in the Construction Manager's opinion to protect the Owner from loss as a result of:
a. Defective or damaged work.
b. A deductive change order.
c. Persistent failure of the Contractor to perform the work in accordance with the contract documents, including failure to FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
maintain the progress of the work in accordance with the construction schedule. Persistent failure to maintain the progress of the work means that for a period of two consecutive months following a written notice from the Construction Manager, the Contractor fails to correct a behind-schedule condition at a rate that would reasonably indicate that he will finish the project on schedule.
d. Disregard of authority of the Construction Manager or the laws of any public agency having jurisdiction.
e. Failure to submit required Labor Compliance documentation for the Contractor and/or subcontractor(s).
The Owner may refuse to make payment of the full amount recommended by the Construction Manager because of claims made against the Owner on account of Contractor's performance or furnishing of the work or because liens have been filed in connection with the work or because there are other items entitling Owner to reduce the amount recommended. In such case, the Owner will give Contractor prompt written notice with a copy to the Construction Manager stating the reasons for each action.
4. STOP PAYMENT NOTICES: The Owner, by and through the
Construction Manager or other authorized officers, may at its option and at any time retain out of any amounts due the Contractor, sums sufficient to cover claims filed pursuant to Section 3179, et seq., of the Civil Code of the State of California.
D. FINAL PAYMENT:
On the condition that no liens or claims are outstanding, and all required labor compliance documentation has been received to the satisfaction of the City, Owner will make final payment to the Contractor in the manner provided by law following the expiration of 35 calendar days after acceptance of the work and filing of the notice of completion by the Owner. Final payment must include the entire sum found to be due under this contract after deducting previous payments and such other lawful amounts as the terms of this contract describe. Prior estimates and payments, including those relating to extra work or work omitted, are subject to correction by the final payment.
Acceptance by the Contractor of final payment acts as a release to the Owner of all claims by and all liability to the Contractor other than claims in stated amounts that may be specifically excepted by the Contractor for things done or furnished in connection with this work and for every act and neglect of the Owner and others relating to or arising out of this work. Payment by the Owner does not release the Contractor or its surety from any obligation under the contract or under the performance bond and payment bonds.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
7.02 CHANGE ORDERS
A. GENERAL:
The Owner may, at any time, without notice to the sureties, by written order designated or indicated to be a change order, make any change in the work within the general scope of the contract, including but not limited to the following changes:
1. In the specifications (including drawings and designs).
2. In the method or manner of performance of the work.
3. In the Owner-furnished facilities, equipment, materials, services, or site.
4. Directing acceleration in the performance of the work.
Any other written order or an oral order (which terms as used in this paragraph include direction, instruction, interpretation, or determination) from the Owner, that causes any such change, must be treated as a change order under this clause, if the Contractor gives the Owner written notice stating the date, circumstances, and source of the order and if the Contractor regards the order as a change order.
Except as provided in this clause, no order, statement, or conduct of the Owner is or may be treated as a change order under this clause nor does it entitle the Contractor to an equitable adjustment.
If any change under this clause causes an increase or decrease in the Contractor's cost of, or the time required for, the performance of any part of the work under this contract, whether or not changed by any order, an equitable adjustment must be made and the contract modified in writing accordingly. However, except for claims based on defective specifications, claims will not be allowed for any costs incurred more than 20 days before the Contractor gives written notice as required. Also, in the case of defective specifications for which the Owner is responsible, the equitable adjustment includes any increased cost reasonably incurred by the Contractor in attempting to comply with such defective specifications.
If the Contractor intends to assert a claim for an equitable adjustment under this clause, the Contractor must, within 30 days after receipt of a written change order or the furnishing of a written notice, submit to the Owner a written statement setting forth the general nature and monetary extent of such claim, unless the Owner extends this period.
The statement of claim hereunder may be included in the notice.
A claim by the Contractor for an equitable adjustment will not be allowed if it is asserted after final payment under this contract.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
B. EXTRA WORK:
Extra work means providing materials and equipment and performing work not directly or by implication called for by the contract. Changes in measured quantity under a unit price contract or item are not extra work. If the Owner requires extra work, the Owner may (1) do it itself, (2) employ others to do it, (3) direct the Contractor to perform the extra work at unit bid price or a combination of such items, (4) direct the Contractor to perform the extra work at a mutually agreed upon lump sum, or (5) direct the Contractor to perform the extra work on a time and expense basis.
C. OMITTED WORK:
The Owner may, by written order to the Contractor, omit work, equipment, and material to be provided under the contract, and the value of the omitted work, equipment and material will be deducted from the contract price. The deducted value will be a lump sum or unit bid price agreed upon in writing by the Contractor and Owner based on the breakdown and cost information submitted by the Contractor.
D. UNIT BID PRICE CHANGE:
Increases or decreases in the quantity of a contract item of work that was bid on a unit basis will be made by comparing the total pay quantity of such item of work with the Construction Manager's estimate. When changes in quantities exceed 25 percent of the original bid quantity and the total dollar change of that bid item is significant, the Owner will review the unit price to determine if a new unit price should be negotiated. Methods for Changed Quantity Payment Adjustments shall be those specified in the Caltrans Standard Specifications, latest edition.
E. LUMP SUM CHANGES:
Whenever the Contractor is directed to perform extra work on a lump-sum basis, changes in contract price resulting from the extra work will be based on a mutually agreed upon lump-sum price. The Contractor's proposal for such changes must include a detailed breakdown of labor and materials costs for the extra work to be performed by its forces and the forces of its subcontractors or material suppliers as may be required. The breakdown must include any labor surcharge and any sales- or use-tax cost. Whenever the Owner requests that the Contractor prepare a lump-sum price in connection with a change order, the Contractor is entitled to the costs incurred in the preparation of that price whether or not the lump-sum amount is finally accepted by the Owner. Those costs will be incorporated in the lump-sum amount.
Compensation for the extra work will be based on the direct costs as listed in the detailed proposal, plus a mutually agreed upon percent of direct costs for overhead and profit, plus one percent (1%) of those direct costs for bond. The allowance for overhead and profit must include full compensation for overhead, including superintendence, and FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
additional overhead attributable to a time extension granted because of the change order and no separate charge may be made for overhead.
When the change order involves work omitted, the reduction of the contract price will be based on the direct costs listed in the detailed proposal submitted by the Contractor. An additional reduction may be made of an amount that is identified as reduced overhead costs attributable to the work omitted. No reduction will be made for profit originally attributable to the omitted work.
F. TIME AND EXPENSE CHANGES:
1. GENERAL: Whenever the Contractor is directed to perform extra work on a time and expense basis, the Contractor must maintain accurate records. Each day a record of labor, materials, and equipment costs will be submitted to the Construction Manager for verification. These records will reflect the actual and necessary expenses pertaining to the extra work and will be available for audit. Audits conducted under this provision must be in accordance with generally accepted auditing standards and established procedures and guidelines of the reviewing or audit agency(ies).
Payment to the Contractor for extra work performed on a time-and-expense basis will consist of the actual necessary expense for doing the extra work, plus an allowance of 15 percent of labor, material and equipment rental for overhead, general superintendence, and profits, plus one percent (1%) of those direct costs for bond. This basis of payment applies to work done directly by the Contractor and to work done by a subcontractor, except the one percent (1%) allowance for bond does not apply to work performed by a subcontractor. When the work is done by a subcontractor, the Contractor may add five percent (5%) to the subcontractor's charges to cover overhead and profit and one percent (1%) for bond.
In determining time-and-expense compensation, the term "actual necessary expense" means the sum of (1) materials and equipment, (2) labor, (3) supervision, (4) construction equipment, (5) professional services, and (6) other costs. “Charges” for such items means the actual cost whether incurred by the Contractor, a subcontractor or others.
The items making up "actual necessary expense" are defined as follows:
2. MATERIALS AND EQUIPMENT: Materials and equipment means costs for materials and equipment provided by the Contractor and necessarily used in the work includes applicable taxes.
3. LABOR: The cost of labor will be the sum of actual wages paid, labor surcharge, and subsistence and travel allowances. Actual wages paid include employer payments to or on behalf of the worker for health and welfare, pension, vacation, and similar purposes. The labor surcharge includes applicable labor-related taxes, Workers Compensation Insurance premiums, public liability and property damage insurance premiums, and other legally required costs directly related to labor. Where subsistence and travel allowance are required for performance of extra work, the charges include the actual amount paid to each worker for these items.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
4. SUPERVISION: If, in the Owner's judgment, full-time supervision of the extra work is required, it will be authorized in writing by the Construction Manager and charges for that supervision will be included as an actual necessary expense. Charges for supervision of the extra work by the Contractor's representative are not part of actual necessary expense.
5. CONSTRUCTION EQUIPMENT: Charges for the use of construction equipment required in the performance of extra work will be based on rental rates set forth in the State of California then-current official published document covering rental of equipment used on force account work. For equipment not listed in that document, the rental rate will be as listed by the local section of the Associated General Contractors. If the equipment is not listed by the Associated General Contractors, the rental rate will be mutually agreed upon in writing between the Contractor and Owner prior to the use of the unlisted equipment. The reasonable cost of moving equipment onto and off the job site will be included, but equipment rental will not be paid when the equipment is inoperative due to breakdowns. Individual pieces of equipment or small tools having a replacement value of $100 or less are considered expendable and no payment will be made for these.
When equipment is used on the extra work for less than five days, hourly rates will be used. Less than 30 minutes of operation is considered one-half hour of operations.
When equipment is used on the extra work for more than five days, daily rates apply. In that case, less than four hours of operation is considered to be one-half day of operation.
6. PROFESSIONAL SERVICES: Professional services are included in "actual necessary expense" provided that the Owner has determined that such services are necessary and that the Construction Manager has authorized in writing the provision of such services.
7. OTHER COSTS: Charges for items not included in paragraphs 7.02 F.1 through 6 may be included as "actual necessary expense" if such additional items are authorized in advance and in writing by the Construction Manager.
7.03 CHARGES TO CONTRACTOR
Everything charged to the Contractor under the terms of this contract must be paid by the Contractor to the Owner on demand. Such charges may be deducted by the Owner from money due or to become due to the Contractor under the contract. The Owner may recover such charges from the Contractor or from its surety.
7.04 COMPENSATION TO OWNER FOR TIME EXTENSION
The Owner, in exchange for granting an extension of time for avoidable delay, must be compensated by the Contractor for the actual costs to the Owner of engineering, inspection, general supervision, and overhead expenses that are directly chargeable to the work and FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
accrue during the period of such extension. The actual costs do not include charges for final inspection and preparation of the final estimate by the Owner.
7.05 SUBSTANTIAL COMPLETION
The Contractor, on considering the work to be substantially complete and ready for its intended use, must so notify the Construction Manager in writing. The notification must include an itemized list of remaining incomplete work. If the Construction Manager determines that the work is not substantially complete, he will so notify the Contractor in writing identifying the reasons for such a determination. If the Construction Manager finds the work substantially complete, he will meet with the Contractor to; (1) prepare a punch list of incomplete items of work; (2) define the division of responsibility between Owner and Contractor with respect to security, operation, maintenance, utilities, insurance, and warranties; and (3) describe any other issues related to acceptance of the substantially completed work. Upon reaching agreement with the Contractor, the Construction Manager will write to the Owner, certifying that the work is substantially complete, listing the items of incomplete work, stating the date for completion of incomplete work, defining the division of responsibilities, and setting forth any other terms related to acceptance.
The Owner, who has sole discretion for determination of substantial completion, will review the Construction Manager's certification that the work is substantially complete and concurring with that certification, will notify the Contractor, in writing, that the work is accepted as substantially complete. Except for any portion(s) of work specified for early completion or required by the Owner for early possession (paragraph 00 72 00-7.06), substantial completion will not occur for any work until the entire project is ready for possession and use. The acceptance notice will include a punch list of incomplete work items, set the date for their completion, describe the division of responsibility between the Owner and Contractor, and describe any other terms of acceptance. The Contractor will acknowledge receipt of the acceptance notice in writing, indicating acceptance of all of its terms and provisions.
Upon receipt of the Contractor's acknowledgment letter, the Owner will take possession of the work or portion of the work and put it into its intended service. The date that the work or portion of the work is put into service will become the date of substantial completion. Unless otherwise specified, warranties will begin on the date of substantial completion.
Subsequent to the substantial completion date, the Owner may exclude the Contractor from the work during such periods when construction activities might interfere with the operation of the project. The Owner, however, will allow the Contractor reasonable access for completion or correction of incomplete punch list items.
7.06 POSSESSION OF PORTIONS OF THE PROJECT
Should the Contractor fail to meet any date specified for substantial completion of the work or any portion of the work requiring early possession and use by the Owner, the Owner may, after a 10-day written notice to the Contractor, take over such portion or all of the work that FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2024-1002.3
DIVISION 00
is behind schedule. In such case, the Construction Manager will prepare a punch list of incomplete work. The Owner may allow the Contractor reasonable access to the work at such times that the operation of the project will not be affected or that the Contractor may complete the work his or herself after giving the Contractor notice of its intention to do so.
The cost of Owner's work will be charged to and deducted from amounts due to the Contractor. The substantial completion date will be established as the date when the Owner actually begins using the project or portion of the project for its intended purpose. Division of responsibilities between Owner and Contractor, beginning of warranties, and any other issues relating to substantial completion will be as specified in paragraph 00 72 00-7.05.
7.07 ACCEPTANCE OF THE PROJECT
Upon completion of the work, including portions of the work previously accepted as substantially complete, the Contractor must notify the Construction Manager, in writing, that the work is complete. Upon receipt of the notification, the Construction Manager will determine if the work conforms to the terms of the contract. If the Construction Manager finds materials, equipment, or workmanship that do not meet the terms of the contract, then the Construction Manager will prepare a punch list of non-conforming items and submit it to the Contractor. Following completion of the corrective work by the Contractor, the Construction Manager must notify the Owner that the work has been completed in accordance with the contract. Final determination of the acceptability will be made by the Owner. Upon acceptance of the project, the Owner will immediately file a notice of completion. For portions of the project not previously accepted as substantially complete, the conditions of guarantee commence on the date that the Owner files a notice of completion.
The final application for payment must be accompanied by all required documentation called for in the contract, including complete and legally effective releases or waivers of liens in a form acceptable to Owner. Subject to prior approval of Owner, Contractor may submit in lieu of the lien releases and waivers: (1) receipts of releases in full; (2) an affidavit that the releases and receipts cover all labor, services, materials, and equipment for which a lien could be filed and that all payrolls, materials, and equipment bills and other indebtedness connected with the work for which Owner or Owner's property might in any way be responsible have been paid or otherwise satisfied; and (3) consent of the surety, if any, to final payment. If any subcontractor or supplier fails to furnish a release or receipt in full, Contractor may furnish a bond or other collateral satisfactory to Owner to indemnify Owner against any lien. The final application for payment must also include all Labor Compliance documentation including all payrolls, forms, and outstanding restitution payments have been made and submitted to Owner’s satisfaction.
If, after reviewing the Contractor's final application for payment, including all documentation required, the Construction Manager determines that the work is complete, then the Construction Manager will recommend that final payment, including all retainages, be made by the Owner. The final payment will be due and payable by the Owner within 30 days after any legal notice periods have expired.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
1 OF 75
PART B – TECHNICAL SPECIFICATIONS GROUP
DIVISION 01 – GENERAL REQUIREMENTS
SECTION 01 00 00
GENERAL REQUIREMENTS
PART 1 – GENERAL
Some of the following general and specific requirements are duplicated in other sections.
Some requirements stated elsewhere may not be in this section. The Contractor must comply with all requirements set forth in this section, other sections and as set forth in any referenced documents.
A. GENERAL CONTRACTOR RESPONSIBILITIES
The Contractor must satisfy himself or herself as to the nature and location of the work, the general and local conditions, particularly those bearing upon availability of transportation, disposal areas, storage areas for materials, labor, water, electric power, and uncertainties of weather, or similar physical conditions at the site, the conformation and conditions of the ground, the character of equipment or facilities needed preliminary to and during the prosecution of the work and all other matters which can in any way affect the work or the cost thereof under this contract.
Any failure by the Contractor to acquaint himself or herself with all the available information will not relieve him or her from responsibility for properly estimating the difficulty or cost of successfully performing the work.
The Contractor will be solely and completely responsible for conditions of the job site, including the safety of all persons and property during performance of the work. This requirement will apply continuously and not be limited to normal working hours.
The Contractor must maintain strict compliance with all job site rules, local, state, and federal regulations, and safety precautions.
Safety provisions must conform to U.S. Department of Labor (OSHA), the California Occupational Safety and Health Act, and all other applicable federal, state, county and local laws, ordinances, codes, the requirements set forth below, and any regulations that may be detailed in other parts of these Specifications.
Contractor must comply with all trench and excavation shoring and construction techniques required for general safety, worker protection and protection of adjacent property. The Contractor will be required to take extra precautions to protect buildings in close proximity to his work. See Section 01 71 33, “Protection of Property”.
Contractor must comply with standards established by the Construction Safety Orders.
Contractor must keep the working area clean, safe, appropriately barricaded, and FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
2 OF 75
illuminated.
Contractor must provide to the City the name of the Competent Person on excavation sites and ensure that all excavations are inspected and that safety procedures are implemented by the Competent Person.
Contractor must provide the City with documented training records for all employees, i.e., Trenching and Shoring, Confined Spaces in Construction, etc.
Contractor must provide all protective equipment (shoring, ladders, PPE, gas monitor, etc.) to be utilized by workers and ensure their proper use.
Contractor must provide site-specific safety reviews a minimum of once a week. Reviews are to be documented including the topics discussed, names of employees present, and be signed by Supervisor or Competent Person. Documentation is to be provided to Project Manager weekly.
Contractor agrees to immediately notify Project Manager of any injuries or near-miss events (“incidents”) on the job site. The City reserves the right to perform its own investigation of any incidents and contractor must provide access to all personnel, equipment, maintenance records, and training documents pertinent to the investigation.
The Project Manager and Field Safety Officer have the authority to stop work if, in their opinion, the Contractor has created an unsafe working condition. Such work stoppage will be at the expense of the Contractor and will not add time to the Contract Time.
Contractor must maintain all documents required by Cal/OSHA on the job site and make them available to all employees and city representatives. Examples include Injury & Illness Prevention Program, Code of Safe Practices, and Heat Illness Prevention Program.
Contractor is responsible for screening all subcontractors with respect to safety and compliance with the requirements contained herein.
Contractor must report to the City and Engineer any condition which may pose a threat to the health and welfare of the City, Contractor's employees, or the general public.
Contractor must install the new sewer lines and manholes in such a manner as to not interrupt the normal flow of wastewater or cause surcharging of upstream sewer lines. Temporary bypass piping or pumps may be installed as required.
Contractor's operations must not cause a nuisance, a public health hazard or discharge of untreated wastewater to the surface or groundwater.
Contractor will be responsible for repairing any damage to existing streets and private property caused by his operations. The Engineer will determine the extent of the damage.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
3 OF 75
Contractor is responsible for the repairs. Contractor must get approval from engineer regarding the method of repair.
Contractor and all Subcontractors must be properly licensed in the State of California for any work they perform.
Contractor must obtain the required permits concerning equipment storage and work areas and for disposal of materials produced during excavation.
Contractor must ensure waste materials are properly handled and disposed in accordance with all applicable City, County, state, and federal regulations, and safety precautions.
All waste materials, debris, rubbish, and unsuitable materials must be removed and disposed of at sites to be provided by the Contractor. The Contractor must make his own arrangements for the disposal of materials.
B. PROGRESS SCHEDULE
Within ten (10) working days of the award of contract, the Contractor must submit to the Engineer, for review and approval, a progress schedule for the project. A revised progress schedule must be submitted every two weeks and when there is any change in the Contractors work schedule.
C. PUBLIC INFORMATION
The Contractor must keep all users/occupants (residents, business operators, etc.) of properties adjacent to, or impacted by, the project advised of any disruption in access or use of the property. This will be by written notice to the property user/occupant each week of activity expected over the following 2 weeks. The notices will include the weekly traffic diversion and closure information required in Section 01 55 26, “Traffic Control”. Copies of all such notices must be delivered to the City also. Notices shall be reviewed and approved by the City before distribution to the public.
D. AIR AND WATER POLLUTION CONTROL
.
The Contractor must follow the Storm Water Pollution Prevention Plan (SWPPP) for the entire project conforming to Section 01 57 23, “Water Pollution Prevention” as well as all applicable standards, orders or regulations issued pursuant to the Federal Water Pollution Control Act, as amended (33 USC 1251-1387) and the Clean Air Act (42 USC 7401-7671q).
E. TRAFFIC CONTROL
Contractor must prepare and submit a Traffic Control Plan conforming to Section 01 55 26, “Temporary Traffic Control”. A schematic traffic control plan is included in the Project Plans.
Please note that the traffic control plan will need to be staged in two phases to ensure access to Play Street during the entire construction.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
4 OF 75
F. SANITARY SEWER AND OTHER BYPASSES
Contractor must prepare and submit a Sanitary Sewer Bypass Plan, or other bypass plan for other utilities, if planning a bypass. Plan must be approved by Owner prior to implementing.
G. INFORMATION ON SITE CONDITIONS
Contractor’s attention is directed to Section 02 00 00, “Existing Conditions” for specific information regarding the project site and surrounding area.
Information derived from inspection of logs, reports, or from Plans showing locations of utilities and structures will not in any way relieve the Contractor from any risk, or from properly examining the site and making such additional investigations as he may elect, or from properly fulfilling all the terms of the Contract Documents.
Some subsurface soil investigations information is provided in the Appendices. Also, see the geotechnical plan sheets for bore hole locations.
H. ADDITIONAL INFORMATION
Prior to bidding, Bidders may make their own subsurface investigations subject to time schedules and arrangements approved in advance by the City. Before starting any subsurface investigation, obtain all necessary permits for such work.
I. DISCREPANCIES
In the event of discrepancy in site conditions, Plans, or Specifications, immediately notify the Engineer. Do not proceed with any work of the nature or in the area of the discrepancy until the discrepancy has been fully resolved.
J. PROJECT LAYOUT
Horizontal and vertical control data is provided in the Plans. The Contractor is responsible to lay out the entire project including pipe alignment, manhole locations, sanitary sewer laterals, street alignment and curb grades and street grades. The maximum deviation for sewer and storm drainpipes is 0.25 feet for horizontal alignment and 0.02 feet for flow grade. The maximum deviation for street centerline is 0.1 foot for horizontal alignment and 0.05 foot for grade. Street curbs and gutters must follow plans within 0.02 feet.
K. WATER
Water for flushing lines, dust control, site cleanup or other construction related purposes is available from the City of Crescent City. Water will be paid for by the Contractor.
L. MATERIALS
Attention is directed to Section 01 33 00, “Submittal Procedures”, and also to Section 6, "Control of Materials," of the Caltrans 2018 Standard Specifications.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
5 OF 75
The Contractor must submit detailed manufacturer’s information, data or certifications for any materials, product or equipment proposed to be furnished and installed for this project, giving manufacturer's name, catalog number, and catalog cut for each item where applicable. The submittal must be accompanied by copies of the manufacturers' current recommended method of installation.
Contractor must comply with the Build America, Buy America (BABA) Act as stipulated in 2 CFR 184.
Contractor must comply with section 6002 of the Solid Waste Disposal Act as amended by the Resource Conservation and Recovery Act. The requirements of Section 6002 include procuring only items designated in guidelines of the EPA at 40 CFR part 2457 that contain the highest percentage of recovered materials practicable, consistent with maintaining a satisfactory level of competition.
M. SUBSTITUTIONS
The Contract is based on the use of certain materials, equipment, and methods as shown on the Plans and described in these Special Provisions. The Engineer will consider proposals for substitution of materials, equipment, and methods only when such proposals are accompanied by full and complete technical data and all other information required by the Engineer to evaluate the proposed substitution. Do not proceed to substitute materials, equipment, or methods unless such substitution has been specifically approved by the Engineer.
When a specific product, material, equipment, or method is identified in the specifications, with or without an “or equal” phrase, do not assume that a substitute product, material, equipment, or method will be approved until the item has been specifically approved in writing by the Engineer.
Contractor must verify, prior to bidding, that all specified items will be available in time for timely progress of the work. Costs of delays because of non-availability of specified items will be borne by the Contractor.
N. TESTING
Attention is directed to the provisions in Section 6-3, "Quality," of the Standard Specifications.
Test methods designated in these specifications refer to the most current California Department of Transportation method as listed in the "Standard Specifications" unless otherwise noted. The test methods must be from the State of California, Business and Transportation Agency, Department of Transportation (Caltrans), Standard Specifications, latest edition.
In addition to any required tests, the Engineer may select random sample(s) of any material proposed to be used on the project. Such samples may be subjected to the appropriate test(s) to confirm compliance with the specifications.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
6 OF 75
O. SALVAGE OF EXISTING MATERIALS
Where indicated on the plans, salvage materials and deliver such materials to the City Corporation Yard, 900 Tenth Street, Crescent City. The Owner may direct salvage of other materials at Owners sole discretion. All other materials will become the property of the Contractor.
P. TRAFFIC
The Contractor will have to divert and/or control vehicular traffic through or around the project area. There is significant two-way vehicular traffic flow (estimated at 2000 vehicles per day) along the corridor of Front Street, Play Street, Stamps Way, and Howe Drive. This traffic must be diverted through and/or around these intersections during construction. Vehicular access to properties west of L Street and south of Second Street must be maintained at all times.
The diversion of traffic around and/or through these intersections must be addressed in the Contractor’s Traffic Control Plan. The Owner has provided a Traffic Control Plan that must be incorporated in the Contractor’s Traffic Control Plan.
There is pedestrian traffic through the project area that must be maintained.
Q. PRIVATE PROPERTY
If excavation or construction materials or equipment are to be stored on private property, written permission must be obtained from the property owner granting permission and absolving the City of all responsibility for the consequences of such activity prior to use of the property.
There are existing buildings adjacent to the project. Access to these buildings must be maintained at all times. Precautions must be taken to prevent any damage to these buildings.
Any damage to private property due to Contractor’s operations will be repaired at the Contractor’s expense. Owner will obtain right(s) of entry onto private property for planned work.
R. ON-SITE STORAGE AND STAGING
The areas shown include Front Street between L Street and the Play Street intersection, and the public parking lot adjacent to Front Street between Play Street and K Street, as delineated on the Plans. These areas are available to the Contractor for his field office and to store materials and equipment. These areas are available at no cost, provided (1) the Contractor fence the area with a six-foot minimum height fence defining the boundary of the area being used for the Contractor’s operations, and (2) the Contractor must restore the area to its preproject condition at no cost to the City.
S. MANDATORY ORGANIC WASTE RECYCLING
It is understood and agreed that pursuant to Public Resources Code Sections 42649.8 et seq., if contractor generates two (2) cubic yards or more of organic waste or commercial solid waste per week, then Contractor must arrange for organic waste or commercial waste recycling services that separate/source organic waste for organic waste recycling. The Contractor shall provide the City with proof of compliance, i.e., organic waste recycling services or commercial waste recycling services that separate/source organic waste recycling.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
7 OF 75
T. DISCOVERY OF ARCHAEOLOGICAL MATERIAL
If buried archaeological material, items not shown on the plans, are encountered during any phase of construction within the public right-of-way, construction must be immediately halted at that location and the City must be notified. The Contractor must abide by the conditions of the Contract Documents and conform with the General Conditions., including but not limited to compliance with the National Historic Preservation Act of 1966 (16 U.S.C. Section 470).
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
8 OF 75
SECTION 01 11 00
SUMMARY OF WORK
1.01 GENERAL
A. The following Summary of Work is not meant to be an all-inclusive description of every item of Work necessary for a complete project. This Summary of Work is meant to aid the Contractor in developing an accelerated understanding of the basic project requirements.
B. Descriptions that are included in this Summary of Work will be considered part of the Specifications and Contract.
C. The work will generally be performed on City property or within the 60-foot-wide rightof-way of on City streets, portions of adjacent side street rights-of-way, and other property owned by the City of Crescent City. Owner will obtain right(s) of entry needed for work to be performed on property not owned by the City.
D. The Contractor must become acquainted with the nature and location of the work, the general and local conditions, particularly those bearing upon availability of transportation, disposal areas, storage areas for materials, labor, water, electric power, and uncertainties of weather, or similar physical conditions at the site, the conformation and conditions of the ground, the character of equipment or facilities needed preliminary to and during the prosecution of the work and all other matters which can in any way affect the work or the cost thereof under this contract.
1.02 WORK COVERED BY CONTRACT DOCUMENTS
A. PROJECT SUMMARY
All work is located in Crescent City, California. The location of the project is shown on the Plans.
B. DESCRIPTION OF WORK:
Generally, the Work consists of furnishing all labor, materials, equipment, and incidentals, and performing all work required to complete the project. Where Owner supplies materials or equipment, Contractor is responsible for all other items to create a fully functional system. The work includes, but is not limited to:
This project includes street and utility improvements on Front Street between Play and L Street, and K Street between Front Street and Second Street. This project also includes Beachfront Park Gateway improvements requiring excavation and grading, pathways, landscaping, and cultural and art element installations on the south side of Front Street between Play Street and L Street.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
9 OF 75
The street work includes the furnishing of the labor, materials, and equipment for the installation of a replacement storm drain system, replacement water mains, fire hydrants, valving and services, sewer main installation, gas line relocation, irrigation piping and controls, curbs, gutters, sidewalks, and pedestrian crossings, a reconstructed road section for Front and K Streets, and new street lighting fixtures, all in accordance with the drawings and specifications.
The Gateway improvements include demolition, earthwork and grading around the Cultural Center on Front Street, new concrete pathways for building access and a cultural trail, decorative concrete elements and concrete retaining/seat walls, irrigation piping and controls, landscaping, area lighting, installation of kiosks with informational and cultural signage, and the construction of foundations for Gateway signage as well as cultural trail structural elements.
The Bidder must provide bids for all of the “Base Bid” items. The contract will be awarded, if awarded, to the low Bidder on the Base Bid. The City may, at its sole discretion, award the contract for the “Base Bid” project only, or the “Base Bid” plus alternates, or the City may decide to remove portions of the work in the awarded contract at a later date.
C. DESIGN/BUILD INTENT OF CONTRACT (NOT USED)
D. CONTRACTOR’S DUTIES:
1. Except as specifically noted, Contractor shall provide and pay for:
a. Labor, materials, and equipment;
b. Tools, construction equipment, and machinery;
c. Water, heat, and utilities required for construction; and d. All other facilities and services necessary for proper execution and completion of work, including commissioning.
e. Temporary water and sewer hookups where required, whether shown not on the plans or not.
2. Building and all other demolition as needed and indicated on the plans. Obtain all necessary permits and perform asbestos and lead paint removal and disposal conforming to all regulations.
3. Pay legally required sales, consumer, and use taxes.
4. Prepare a Construction Schedule and Schedule of Values and receive approval from the Owner as required by these Contract Documents.
5. Procure and maintain all insurance and bonds required by these Contract Documents.
6. Secure and pay for proper execution and completion of the Work, and applicable permits and licenses, as necessary.
7. Give all required notices.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
10 OF 75
8. Comply with codes, ordinances, rules, regulations, orders, and other legal requirements of public authorities which bear on performance of the Work.
9. Promptly submit written notice to Engineer of observed variance of contract documents from legal requirements.
10. Enforce strict discipline and good order of employees. Do not employ on the work:
a. Unfit persons; or
b. Persons not skilled in assigned tasks.
11. Prepare a Shoring Plan specific to the construction demolition and sequencing performed on this project.
E. PERMITS AND AGREEMENTS:
Contractor shall obtain and comply with all permits not specifically obtained by Owner.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
11 OF 75
SECTION 01 20 00
MEASUREMENT AND PAYMENT
1.0 GENERAL
A. LUMP SUM PAYMENT ITEMS:
Payment items for the work of this contract for which contract lump sum payments will be made are listed in the Bid Schedule and described below. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved.
The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials (where not provided by City), equipment, performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests, reports, and for performing all work required for which separate payment is not otherwise provided.
B. UNIT PRICE PAYMENT ITEMS:
Payment items for the work of this contract on which the contract unit price payments will be made are listed in the Bid Schedule and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials (where not provided by City), and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests, and reports, and for performing all work required for each of the unit price items.
2.0 BID ITEMS
BASE BID – FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C
1. Mobilization – Front: Mobilization is as described in Section 9-1.16D, “Mobilization” of the Standard Specifications. Mobilization will be paid on a lump sum basis in accordance with Public Contract Code as follows provided that total mobilization cost does not exceed 10 percent of the total bid: 50 percent when 5 percent of the project is earned. 75 percent when 10 percent is earned. 95 percent when 20 percent is earned. 100 percent when 50 percent is earned. Where mobilization exceeds 10 percent of the contract, see Public Contract Code.
2. SWPPP Plan and Reporting – Front: This item includes all additional work necessary for developing a stormwater pollution prevention plan by a qualified QSD and reporting results of work covered under this item in accordance with Specification Section 01 57 23. This lump sum item will be paid based on the percent of the project earned, rounded down to the nearest 10 percent.
3. Water Pollution Prevention BMPs – Front: This item includes all additional work necessary for meeting the requirements set out in the SWPPP and work covered under this item in accordance with Specification Section 01 57 23. This lump sum FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
12 OF 75
item will be paid based on the percent of the project earned, rounded down to the nearest 10 percent.
4. Traffic Control – Front: Traffic Control is as described in Specification Section 01 55 26, “Temporary Traffic Control”. This lump sum item will be paid based on the percent of the project earned, rounded down to the nearest 10 percent.
5. 2x CMS Boards – Front: This item shall include the placement, rental and maintenance of two Changeable Message Signs adequate for traffic control required for the detour off Highway 101 directing traffic flow around the construction site as required for completion of the project. This bid item will be paid at each progress payment based on the number of months completed for the duration of required traffic control of the project.
6. Sheeting Shoring and Bracing – Front: This item shall include all temporary sheeting, shoring, and bracing, or equivalent methods, adequate for the protection of life or limb, which shall conform to the applicable construction safety orders as required for completion of the project as described in Specification Section 31 23 17. This bid item is pursuant to Labor Code Section 6707. This lump sum item will be paid based on the percent of the project earned, rounded down to the nearest 10 percent.
7. Quality Control – Front: Quality Control as described in Specification Section 01 45 00 shall be paid on a lump sum based on the percent of the project earned, rounded down to the nearest 10 percent.
8. Materials Testing – Front: Materials Testing as described in Specification Section 01 45 29 shall be paid on a lump sum based on the percent of the project earned, rounded down to the nearest 10 percent.
9. Demolition – Front: Demolition is as described in Specification Section 02 41 00, “Demolition.” Demolition shall cover all work identified on Plan Sheets DM 1-5 of “Front Street Improvements Play to L Streets” and all other necessary demolition work not covered under other bid items. Work includes but is not limited to removal and disposal or salvage of existing sidewalks, curb and gutters, paving, aggregate base, light poles, trees and landscaping, logs, foundations, seawalls, signs, storm drainage, sanitary sewer manholes, and pipes. This lump sum item will be paid based on the percent of the project earned, rounded down to the nearest 10 percent.
10. Excavation for Road and Walks – Front: This item will be paid based on the bid unit price per cubic yard. Excavation work includes: required removal to make sidewalk and road sections per plan detail. Scarification and compaction of subgrade to required 90% compaction prior to placement of aggregate base material for all paved areas and new curbs, gutters, and sidewalks. 40 percent will be paid based on excavation of native material. 10 percent will be paid based on completion of scarification and compaction. The remaining 50 percent will be paid once subgrade is prepared and ready to accept aggregate base. This item will be paid based on Owner’s estimate of the percent complete for each of the above activities.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
13 OF 75
11. Aggregate Base for paved section – Front: This item will be paid on the bid unit price per cubic yard and includes all labor, materials, and equipment necessary to import, place, grade, and compact the aggregate base rock for the road base as shown on the Plans. The Owner will only pay for base rock quantities identified in the bid schedule. Contractor is responsible for proper grading and placement of subgrade to achieve lines and grades. This item will be paid based on Owner’s estimate of the percent of total aggregate base placed during each billing cycle.
12. Hot Mix Asphalt Concrete – Front: This item includes all work necessary to provide and place hot mix asphaltic concrete. This item will be paid on the bid unit price per ton. The Owner will only pay for Hot Mix Asphalt quantities identified in the bid schedule. Contractor is responsible for proper grading and placement of subgrade and rock to achieve lines and grades. This item will be paid based on Owner’s estimate of the number of tons of hot mix asphalt placed during each billing cycle.
13. Storm Drain 54 inch HDPE – Front: Installation of 54-inch diameter Storm Drainpipe will be paid at the bid unit price per foot. Work shall include the installation of the pipes in accordance with all specifications. Work shall be performed in accordance with Specification Section 22 14 00 and comprises the following: trench excavation and disposal of native material, removal and disposal of existing pipe or structures where shown, installation of new and replacement piping and connections, connection to existing facilities including the couplings needed to join dissimilar pipes, backfill material, and compaction of materials to subgrade (soil ready to receive road base). Pipe measurement will include the actual length of pipe installed and will not include waste pipe or measurement through junction structures or other structures.
14. Storm Drain 48 inch HDPE – Front: Installation of 48-inch Storm Drainpipe will be paid at the bid unit price per foot in accordance with item 13 above.
15. Storm Drain 36 inch HDPE – Front: Installation of 36-inch Storm Drainpipe will be paid at the bid unit price per foot in accordance with item 13 above.
16. Storm Drain 24 inch HDPE – Front: Installation of 24-inch Storm Drainpipe will be paid at the bid unit price per foot in accordance with item 13 above.
17. Storm Drain 18 inch HDPE – Front: Installation of 18-inch Storm Drainpipe will be paid at the bid unit price per foot in accordance with item 13 above.
18. Storm Drain 10 inch and 12 inch HDPE – Front: Installation of 12-inch Storm Drainpipe will be paid at the bid unit price per foot in accordance with item 13 above.
19. Junction Box Double Lid – Front: The City to supply the junction box, grade rings, and frame and covers. Installation of the precast concrete manholes will be paid for on a per each basis. Work shall include installation of the new manholes in accordance with all specifications. This item comprises the following: excavation and disposal of native material, removal and disposal of existing structures where FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
14 OF 75
shown, backfill material, and compaction of materials to subgrade (Aggregate base ready to receive HMA within 3 feet of box). 90 percent will be paid on completion of compaction to subgrade. Final 10 percent will be paid upon adjusting lids to grade and completion of paving.
20. Junction Box Single Lid – Front: The City to supply the junction box, grade rings, and frame and covers. Installation of the precast concrete manholes will be paid for on a per each basis. Work shall include installation of the new manholes in accordance with all specifications. This item comprises the following: excavation and disposal of native material, removal and disposal of existing structures where shown, backfill material, and compaction of materials to subgrade (Aggregate base ready to receive HMA within 3 feet of box). 90 percent will be paid on completion of compaction to subgrade. Final 10 percent will be paid upon adjusting lids to grade and completion of paving.
21. Modifying existing Junction Box – Front: Modification existing concrete manhole will be paid for on a lump sum based on the percent of project earned. Work shall include modification of the existing manhole in accordance with all plans and specifications. This item comprises the following: excavation and disposal of native material, removal and disposal of existing structures where shown, backfill material, and compaction of materials to subgrade (Aggregate base ready to receive HMA within 3 feet of box). Payment shall be rounded down to the nearest 10 percent, until 90 percent is earned on completion of compaction to subgrade.
Final 10 percent will be paid upon adjusting lids to grade and completion of paving.
22. Drainage Inlets (Caltrans Type G0) – Front: The City to supply the drainage inlets and grates. Installation of the concrete drop inlets (CalTrans Type G0) including hot dip galvanized grate, will be paid for on a per each basis. Work shall include the installation of the new inlets in accordance with all specifications. This item comprises the following: excavation and disposal of native material, removal and disposal of existing structures where shown, placement of precast inlets, placement of backfill material, and compaction of materials.
23. Drainage Inlets (Caltrans Type G1) – Front: The City to supply the drainage inlets and grates. Installation of the concrete drop inlets (CalTrans Type G1) including hot dip galvanized grate, will be paid for on a per each basis. Work shall include the installation of the new inlets in accordance with all specifications. This item comprises the following: excavation and disposal of native material, removal and disposal of existing structures where shown, placement of precast inlets, placement of backfill material, and compaction of materials.
24. 6” Sanitary Sewer Mainline – Front: Installation of sewer lines will be paid at the bid unit price per foot. Work shall include installation of the new lines in accordance with all specifications. This item comprises the following: trench excavation and disposal of native material, removal and disposal of existing lines and structures where shown, installation of new and replacement piping and connections, connection to existing facilities including the couplings needed to join dissimilar FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
15 OF 75
pipes, backfill material, and compaction of materials to subgrade (soil ready to receive road base).
25. 4” Sanitary Sewer Lateral – Front: Installation of sewer lines will be paid at the bid unit price per foot. Work shall include installation of the new lines in accordance with all specifications. This item comprises the following: trench excavation and disposal of native material, removal and disposal of existing lines and structures where shown, installation of new and replacement piping and connections, connection to existing facilities including the couplings needed to join dissimilar pipes, backfill material, and compaction of materials to subgrade (soil ready to receive road base).
26. Sanitary Sewer Cleanout with G-5 Boxes & Lids – Front: Installation of the sanitary sewer cleanouts including piping and G-5 boxes, will be paid for on a per each basis. Work shall include the installation of the new cleanouts in accordance with all specifications. This item comprises the following: excavation and disposal of native material, removal and disposal of existing structures where shown, placement of piping and boxes, placement of backfill material, and compaction of materials. 90 percent will be paid on completion of compaction to subgrade. Final 10 percent will be paid upon completion of paving.
27. 10” Water Line – Front: Installation of water lines will be paid at the bid unit price per foot. Work shall include installation of the new lines in accordance with all specifications. This item comprises the following: trench excavation and disposal of native material, removal and disposal of existing lines and structures where shown, installation of new and replacement piping and connections, connection to existing facilities including the couplings needed to join dissimilar pipes, backfill material, and compaction of materials to subgrade (soil ready to receive road base). 90 percent will be paid on completion of compaction to subgrade. Final 10 percent will be paid upon required testing, flushing, and disinfection being completed successfully.
28. 8” Water Line – Front: Installation of water lines will be paid at the bid unit price per foot. Work shall include installation of the new lines in accordance with all specifications. This item comprises the following: trench excavation and disposal of native material, removal and disposal of existing lines and structures where shown, installation of new and replacement piping and connections, connection to existing facilities including the couplings needed to join dissimilar pipes, backfill material, and compaction of materials to subgrade (soil ready to receive road base). 90 percent will be paid on completion of compaction to subgrade. Final 10 percent will be paid upon required testing, flushing, and disinfection being completed successfully.
29. 6” Water Line – Front: Installation of water lines will be paid at the bid unit price per foot. Work shall include installation of the new lines in accordance with all specifications. This item comprises the following: trench excavation and disposal of native material, removal and disposal of existing lines and structures where shown, installation of new and replacement piping and connections, connection to FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
16 OF 75
existing facilities including the couplings needed to join dissimilar pipes, backfill material, and compaction of materials to subgrade (soil ready to receive road base). 90 percent will be paid on completion of compaction to subgrade. Final 10 percent will be paid upon required testing, flushing, and disinfection being completed successfully.
30. Fire Hydrants – Front: Installation of new fire hydrants assembly will be paid for on an installation per each basis. Work shall include the installation of the new hydrants in accordance with all specifications. This item comprises the following:
trench excavation and disposal of native material, removal and disposal of existing lines and structures where shown, backfill material, installation of companion valve and G-5 box and lid, and compaction of materials to grade. 90 percent will be paid on completion of compaction to subgrade. Final 10 percent will be paid upon completion of all required testing, flushing, and disinfection is completed successfully.
31. 10” Gate Valves with G-5 Valve Boxes & Lids – Front: Installation of water valves and precast boxes will be paid for on a per each basis. Work shall include the installation of the new valves & boxes in accordance with all specifications. Water valves include mainline valves, valves for service connections and irrigation, combination air valves, and blow-off valves. This item comprises the following:
excavation and disposal of native material, removal, and salvage of existing valves and/or structures where shown, backfill material, installation of valves and needed appurtenances, and compaction of materials to grade. 90 percent will be paid on completion of compaction to subgrade if all required testing, flushing, and disinfection are completed successfully. Final 10 percent will be paid upon completion of paving.
32. 8” Gate Valves with G-5 Valve Boxes & Lids – Front: Installation of water valves and precast boxes will be paid for on a per each basis. Work shall include the installation of the new valves & boxes in accordance with all specifications. Water valves include mainline valves, valves for service connections and irrigation, combination air valves, and blow-off valves. This item comprises the following: excavation and disposal of native material, removal, and salvage of existing valves and/or structures where shown, backfill material, installation of valves and needed appurtenances, and compaction of materials to grade. 90 percent will be paid on completion of compaction to subgrade if all required testing, flushing, and disinfection are completed successfully. Final 10 percent will be paid upon completion of paving.
33. 6” Gate Valves with G-5 Valve Boxes & Lids – Front: Installation of water valves and precast boxes will be paid for on a per each basis. Work shall include the installation of the new valves & boxes in accordance with all specifications. Water valves include mainline valves, valves for service connections and irrigation, combination air valves, and blow-off valves. This item comprises the following: excavation and disposal of native material, removal, and salvage of existing valves and/or structures where shown, backfill material, installation of valves and needed appurtenances, and compaction of materials to grade. 90 percent will be paid on completion of FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
17 OF 75
compaction to subgrade if all required testing, flushing, and disinfection are completed successfully. Final 10 percent will be paid upon completion of paving.
34. 4” Gate Valves with G-5 Valve Box & Lids – Front: Installation of water valves and precast boxes will be paid for on a per each basis. Work shall include the installation of the new valves & boxes in accordance with all specifications. Water valves include mainline valves, valves for service connections and irrigation, combination air valves, and blow-off valves. This item comprises the following: excavation and disposal of native material, removal, and salvage of existing valves and/or structures where shown, backfill material, installation of valves and needed appurtenances, and compaction of materials to grade. 90 percent will be paid on completion of compaction to subgrade if all required testing, flushing, and disinfection are completed successfully. Final 10 percent will be paid upon completion of paving.
35. 2” Gate Valves with G-5 Valve Box & Lids – Front: Installation of water valves and precast boxes will be paid for on a per each basis. Work shall include the installation of the new valves & boxes in accordance with all specifications. Water valves include mainline valves, valves for service connections and irrigation, combination air valves, and blow-off valves. This item comprises the following: excavation and disposal of native material, removal, and salvage of existing valves and/or structures where shown, backfill material, installation of valves and needed appurtenances, and compaction of materials to grade. 90 percent will be paid on completion of compaction to subgrade if all required testing, flushing, and disinfection are completed successfully. Final 10 percent will be paid upon completion of paving.
36. 1” and/or 2” Service Lines – Front: Installation of water lines will be paid at the bid unit price per linear foot. Work shall include installation of the new lines in accordance with all specifications. This item comprises the following: trench excavation and disposal of native material, removal and disposal of existing lines and structures where shown, backfill material, and compaction of materials to subgrade (soil ready to receive road base).
37. 2” Irrigation Lines – Front: Installation of irrigation lines will be paid at the bid unit price per linear foot. Work shall include installation of the new lines in accordance with all specifications. This item comprises the following: trench excavation and disposal of native material, removal and disposal of existing lines and structures where shown, backfill material, and compaction of materials to subgrade (soil ready to receive landscaping). .
38. Water Meter Connections – Front: City to supply meters and boxes. Installation of Water Meters will be paid for on a per each basis. Work shall include the installation of the new meters in accordance with all specifications. This item comprises the following: excavation and disposal of native material, removal, and salvage of existing meters and/or structures where shown, connection to existing facilities including the couplings needed to join dissimilar pipes, placing of meter and box and lid and needed appurtenances, backfill material, and compaction of materials to grade.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
18 OF 75
39. Relocate Gas Line – Front: Gas materials and installation done by Blue Star Gas..
Excavation and backfill for gas lines will be paid at the bid unit price per linear foot.
This item comprises the following: coordination with Blue Star Gas, trench excavation and disposal of native material, removal and disposal of existing lines and structures where shown, backfill material, and compaction of materials to subgrade (soil ready to receive road base).
40. Electrical – Front: This item shall be paid on a lump sum basis and shall include all light pole foundations, foundations for meter pedestals, pull boxes, electrical conduit with pull tape, receptacles, covers, related conductors, electrical enclosures, breakers, needed appurtenances and other subsurface items related to the final buildout of the electrical system, as shown on the Plans. Confirm on site the existing points of connection for all work inclusive with this contract. All work is to be installed where shown on the Plans or as directed by the City or the Engineer. This item comprises the following: coordination with Pacific Power; trench or other excavation and disposal of native material; removal and disposal of existing conductors; backfill material; purchase and installation of conduits, pull tape, pull boxes, needed appurtenances, aggregate base, and compaction of materials to grade. This item to be paid based on Owner’s estimate of the percent of related work installed on the project during each billing cycle.
41. Streetlights Single Head– Front: This item shall be paid on a per each basis and shall include all the work necessary to install light poles and all equipment needed for fully functional lights. All work is to be installed where shown on the Plans or as directed by the City or the Engineer. This item comprises the following: furnishing and installation of light poles (poles, mounting arms, luminaires, and hardware).
42. Streetlights Double Head – Front: This item shall be paid on a per each basis and shall include all the work necessary to install light poles and all equipment needed for fully functional lights. All work is to be installed where shown on the Plans or as directed by the City or the Engineer. This item comprises the following: and furnishing and installation of light poles (poles, mounting arms, luminaires, and hardware).
43. Streetlights Relocate Salvaged Double Head – Front: This item shall be paid on a per each basis and shall include all the work necessary to relocate the salvaged light pole included as shown in the demolition plan sheets and placed with on a new foundation in the planter island at approximately Station 33+50. The existing adjacent pull box has the necessary wiring to complete this item. This item comprises the following: furnishing and installation of light poles (poles, mounting arms, luminaires, and hardware).
44. Stamped Color Concrete Sidewalks – Northside Front Street: This item will be paid at the bid unit price per square foot. This item includes all work necessary to construct concrete sidewalks on the north side of Front Street including, subgrade preparation, placing and compaction of aggregate base, coloring the concrete, stamping of the concrete (using city provided stamps), and all other items needed to install the sidewalks in accordance with the specifications. The City will provide the stamps.
Reference color notes in specification 32 13 13. This item to be paid based on FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
19 OF 75
Owner’s estimate of the square footage of sidewalk installed on the project during each billing cycle.
45. Concrete Sidewalks – Southside Front Street: This item will be paid at the bid unit price per square foot. This item includes all work necessary to construct concrete sidewalks on the south side of Front Street and Play Street including, subgrade preparation, placing and compaction of aggregate base, and all other items needed to install the sidewalks in accordance with the specifications. This item to be paid based on Owner’s estimate of the square footage of sidewalk installed on the project during each billing cycle.
46. Concrete Sidewalks – K Street: This item will be paid at the bid unit price per square foot. This item includes all work necessary to construct concrete sidewalks on the K Street including, subgrade preparation, placing and compaction of aggregate base, and all other items needed to install the sidewalks in accordance with the specifications. This item to be paid based on Owner’s estimate of the square footage of sidewalk installed on the project during each billing cycle.
47. Reinforced Concrete Driveways – Front: Reinforced concrete will be paid based on the bid unit price per square foot. This item includes all labor, materials, and equipment necessary to construct valley gutters, driveways, subgrade preparation, placing and compaction of aggregate base, rebar, and all other items needed to install the driveways in accordance with the plans and specifications. This item to be paid based on Owner’s estimate of the square feet of concrete installed on the project during each billing cycle.
48. Reinforced Stamped Color Concrete Crosswalk – Front: Reinforced concrete will be paid based on the bid unit price per square foot. This item includes all labor, materials, and equipment necessary to construct colored and stamped concrete street crossings, subgrade preparation, placing and compaction of aggregate base, coloring the concrete, stamping of the concrete (using city provided stamps), rebar, and all other items needed to install the crossings, in accordance with the plans and specifications. Reference color notes in specification 32 13 13. This item to be paid based on Owner’s estimate of the square feet of concrete installed on the project during each billing cycle.
49. ADA Dome Panels - Front: This item is to be paid on a per square foot basis. This item includes all labor, materials, and equipment needed for installation of detectable warning surfaces placed at the ramps and crosswalks as shown on the Plans and in accordance with the CalTrans Standard Plans and Specifications.
Concrete material is excluded from this bid item. The square footage of each Detectable Warning Surface may vary per location. This item to be paid based on Owner’s estimate of the square feet of panels installed on the project during each billing cycle.
50. Concrete Curb and Gutter – Front: This item will be paid on the bid unit price per linear foot and includes all work necessary to construct concrete curbs and gutters including excavation and disposal of native soils, subgrade preparation, aggregate FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
20 OF 75
base, compaction, and all other items needed for a complete and functioning curb and gutter system. This item to be paid based on Owner’s estimate of the linear feet of curb and gutter installed on the project during each billing cycle.
51. Concrete Curb No Gutter – Front: This item will be paid on the bid unit price per linear foot and includes all work necessary to construct concrete curbs, including excavation and disposal of native soils, subgrade preparation, aggregate base, compaction, and all other items needed for a contiguous curb as shown on the Plans.
This item to be paid based on Owner’s estimate of the linear feet of curbs installed on the project during each billing cycle.
52. Bike Lane Color Asphalt Treatment – Front: Asphalt coloring will be paid based on the bid unit price per square foot. This item includes all labor, materials, and equipment necessary to mark pavement in accordance with the plans, specifications, Chapter 3G of the California MUTCD, and chapter 84-2 of the CalTrans Standard specifications. This item to be paid based on Owner’s estimate of the square feet of pavement marking installed on the project during each billing cycle.
53. Pavement Striping and Signs – Front: This item includes all work necessary to stripe crosswalks, center lines, fog lines and other striping as shown on the Plans. This item will be paid for on a lump sum price basis based on Owner’s estimate of the percent of striping completed during each billing cycle.
54. Storm Drain 42 inch HDPE – Front: Installation of 42-inch Storm Drainpipe will be paid at the bid unit price per foot in accordance with item 13 above.
55. 4” Water Line – Front: Installation of water lines will be paid at the bid unit price per foot. Work shall include installation of the new lines in accordance with all specifications. This item comprises the following: trench excavation and disposal of native material, removal and disposal of existing lines and structures where shown, installation of new and replacement piping and connections, connection to existing facilities including the couplings needed to join dissimilar pipes, backfill material, and compaction of materials to subgrade (soil ready to receive road base). 90 percent will be paid on completion of compaction to subgrade. Final 10 percent will be paid upon required testing, flushing, and disinfection being completed successfully
56. Reserved for future use
57. Reserved for future use
58. Reserved for future use
59. Reserved for future use
60. Reserved for future use
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
21 OF 75
61. Mobilization – Gateway: Mobilization is as described in Section 9-1.16D, “Mobilization” of the Standard Specifications. Mobilization will be paid on a lump sum basis in accordance with Public Contract Code as follows provided that total mobilization cost does not exceed 10 percent of the total bid: 50 percent when 5 percent of the project is earned. 75 percent when 10 percent is earned. 95 percent when 20 percent is earned. 100 percent when 50 percent is earned. Where mobilization exceeds 10 percent of the contract, see Public Contract Code.
62. SWPPP Plan and Reporting – Gateway: This item includes all additional work necessary for developing a stormwater pollution prevention plan by a qualified QSD and reporting results of work covered under this item in accordance with Specification Section 01 57 23. This lump sum item will be paid based on the percent of the project earned, rounded down to the nearest 10 percent, until 90 percent is earned. The final 10 percent will be paid with the final payment.
63. Water Pollution Prevention BMPs – Gateway: This item includes all additional work necessary for meeting the requirements set out in the SWPPP and work covered under this item in accordance with Specification Section 01 57 23. This lump sum item will be paid based on the percent of the project earned, rounded down to the nearest 10 percent, until 90 percent is earned. The final 10 percent will be paid with the final payment.
64. Pedestrian & Traffic Control – Gateway: Traffic Control is as described in Specification Section 01 55 26, “Temporary Traffic Control”. This lump sum item will be paid based on the percent of the project earned, rounded down to the nearest 10 percent.
65. Tree protection fencing installation and removal – Gateway: Installation (and removal after construction) of tree protection fencing will be paid at the bid unit price per foot.
Work shall include the installation in accordance with all plans and specifications.
Work comprises the following: underground utility locating, fence post installation, stretching of temporary tree protection and removal of all components after construction. 70 percent will be paid based on completion of the temporary fence installation. The remaining 30 percent will be paid upon successful removal of fencing. Some of the fencing shown on the plans is under the Beachfront Park Tolowa Cultural Trail Project contract.
66. Clear, Grub & Tree Removal – Gateway: This item will be paid based on the bid unit price per lump sum. Clearing and grubbing to be as described in Specification Section 31 10 00, “Site Clearing.” Work includes but is not limited to removal and disposal or salvage of trees, shrubs, and grass. This lump sum item will be paid based on the percent of the project earned, rounded down to the nearest 10 percent.
Some of this work shown on the plans is under the Beachfront Park Tolowa Cultural Trail Project contract.
67. Demolition of Miscellaneous Fencing, Signs, Guard Rails & Fixtures – Gateway:
Demolition is as described in Specification Section 02 41 00, “Demolition.” Demolition shall cover all work identified on Plan Sheets L3.01-3.04 of “Cultural Gateways and FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
22 OF 75
Beautification Project” and all other necessary demolition work not covered under other bid items. Work includes but is not limited to removal and disposal or salvage of fencing, signs, guard rails and fixtures shown in plans. This lump sum item will be paid based on the percent of the project earned, rounded down to the nearest 10 percent.
68. Demolition of Concrete Walls, Stairs, Art Panels, and Porte Cochere – Gateway:
Demolition is as described in Specification Section 02 41 00, “Demolition.” Demolition shall cover all work identified on Plan Sheets L3.01-3.04 of “Cultural Gateways and Beautification Project” and all other necessary demolition work not covered under other bid items. Work includes but is not limited to removal and disposal or salvage of concrete walks, stairs, art panels and Porte Cochere wall panels to grades shown in the plan set. This lump sum item will be paid based on the percent of the project earned, rounded down to the nearest 10 percent.
69. Demolition of Asphalt – Gateway: This bid item will be paid based on the bid unit price per square foot. Demolition is as described in Specification Section 02 41 00, “Demolition.” Demolition shall cover all work identified on Plan Sheets L3.01-3.04 of “Cultural Gateways and Beautification Project” and all other necessary demolition work not covered under other bid items. Work includes but is not limited to removal and disposal or salvage of asphalt surfaces shown in plans. This item will be paid based on Owner’s estimate of the square feet of asphalt demolished during each billing cycle. Some of this work shown on the plans is under the Beachfront Park Tolowa Cultural Trail Project contract.
70. Demolition of Building Deck & Handrail – Gateway: Demolition is as described in Specification Section 02 41 00, “Demolition.” Demolition shall cover the work identified on Plan Sheets S2.10 and S7.01 of “Cultural Gateways and Beautification Project”. Work includes but is not limited to removal and disposal or salvage of building deck and handrail. This lump sum item will be paid based on the percent of the project earned, rounded down to the nearest 10 percent.
71. Mass Excavation and Fill including Porte Cochere – Gateway: This item shall be paid on a lump sum basis and shall include removal and relocation of spoils to grade front of Cultural Center per plan detail. 50 percent will be paid based on excavation of native material. 10 percent will be paid based on completion of scarification and compaction. The remaining 40 percent will be paid once subgrade is prepared and ready to accept aggregate base and stockpile areas are all cleaned and graded out.
72. Excavation and Grading for Concrete Flatwork – Gateway: This bid item will be paid based on the bid unit price per square foot. Excavation work includes: required removal to make sidewalk and road sections per plan detail. Scarification and compaction of subgrade to required 90% compaction prior to placement of aggregate base material for all paved areas and new curbs, gutters, and sidewalks. 40 percent will be paid based on excavation of native material. 10 percent will be paid based on completion of scarification and compaction. The remaining 50 percent will be paid once subgrade is prepared and ready to accept aggregate base. Some of this work FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
23 OF 75
shown on the plans is under the Beachfront Park Tolowa Cultural Trail Project contract. The provided bid quantities have been adjusted to exclude this work.
73. Aggregate Base for Flatwork – Gateway: This item will be paid on the bid unit price per square foot and includes all labor, materials, and equipment necessary to import, place, grade, and compact the aggregate base rock for the concrete flatwork as shown on the Plans (excluding street sidewalks). The Owner will only pay for base rock quantities identified in the bid schedule. Contractor is responsible for proper grading and placement of subgrade to achieve lines and grades. This item will be paid based on Owner’s estimate of the percent of total aggregate base placed during each billing cycle. Some of this work shown on the plans is under the Beachfront Park Tolowa Cultural Trail Project contract. The provided bid quantities have been adjusted to exclude this work.
74. Gateway Sign Foundation @ Play Street: Not in Contract
75. Wave Sign Foundation @ M Street: Not in Contract
76. Concrete Vehicular Paving – Gateway: This item will be paid at the bid unit price per square foot. This item includes all work necessary to construct 6-inch unreinforced concrete walkway including subgrade preparation, and all other items needed to install the paving in accordance with the plans and specifications. This item to be paid based on Owner’s estimate of the square footage of paving installed on the project during each billing cycle. Some of this work shown on the plans is under the Beachfront Park Tolowa Cultural Trail Project contract. The provided bid quantities have been adjusted to exclude this work.
77. Concrete Sidewalks – Gateway: This item will be paid at the bid unit price per square foot. This item includes all work necessary to construct 4-inch unreinforced concrete sidewalks, including subgrade preparation, and all other items needed to install the sidewalks in accordance with the Cultural Gateways and Beautification Project plans & specifications. This item to be paid based on Owner’s estimate of the square footage of sidewalk installed on the project during each billing cycle. Some of this work shown on the plans is under the Beachfront Park Tolowa Cultural Trail Project contract. The provided bid quantities have been adjusted to exclude this work.
78. ADA Dome Panels – Front & Gateway: This item is to be paid on a per square foot basis. This item includes all labor, materials, and equipment needed for installation of detectable warning surfaces placed at the ramps and crosswalks as shown on the Front Street Improvements Play to L Streets Plans, Cultural Gateways and Beautification Project Plans on the southside sidewalk on Front Street and the Cultural Trail, and in accordance with the CalTrans Standard Plans and Specifications. Concrete material is excluded from this bid item. The square footage of each Detectable Warning Surface may vary per location. This item to be paid based on Owner’s estimate of the square feet of panels installed on the project during each billing cycle. Some of this work shown on the plans is under the Beachfront Park Tolowa Cultural Trail Project contract. The provided bid quantities have been adjusted to exclude this work.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
24 OF 75
79. Permeable Concrete – Front: This item will be paid at the bid unit price per square foot. This item includes all work necessary to construct vehicular permeable concrete pavement, subgrade preparation, placing and compaction of permeable aggregate base, and all other items needed to install the permeable concrete in accordance with the Front Street Improvements Play to L Streets plans & specifications. This item to be paid based on Owner’s estimate of the square footage of permeable concrete installed on the project during each billing cycle. This item does not receive reinforcing steel.
80. Concrete Slab @ Porte Cochere– Gateway: This item will be paid at the bid unit price per square foot. This item includes all work necessary to construct a 4-inch thick nonreinforced concrete slab with a broom finish at the Porte Cochere, subgrade preparation, and all other items needed to install the slab in accordance with the Cultural Gateways and Beautification Project plans & specifications. This item to be paid based on Owner’s estimate of the square footage of sidewalk installed on the project during each billing cycle.
81. Concrete Retaining Wall at Stairs – Gateway: This item will be paid at the bid unit price per linear foot. This item includes all work necessary to construct a retaining wall at the stairs including subgrade preparation, placing and compaction of aggregate base, and all other items needed to install the retaining wall in accordance with the Cultural Gateways and Beautification Project plans & specifications. This item to be paid based on Owner’s estimate of the linear feet of wall installed on the project during each billing cycle.
82. Concrete Seat Wall – Gateway: This item will be paid at the bid unit price per linear foot. This item includes all work necessary to construct a seat wall including subgrade preparation, placing and compaction of aggregate base, and all other items needed to install the seat wall in accordance with Detail 4 & 7 on L9.03 of the Cultural Gateways and Beautification Project plans & specifications. This item to be paid based on Owner’s estimate of the linear feet of wall installed on the project during each billing cycle. Some of this work shown on the plans is under the Beachfront Park Tolowa Cultural Trail Project contract. The provided bid quantities have been adjusted to exclude this work.
83. Concrete Stairs – Gateway: This item will be paid at the bid unit price per square foot.
This item includes all work necessary to construct concrete stairs including subgrade preparation, and all other items needed to install the stairs in accordance with L9.04 of the Cultural Gateways and Beautification Project plans & specifications. This item to be paid based on Owner’s estimate of the square feet of wall installed on the project during each billing cycle.
84. Concrete Mow Curb – Gateway: This item will be paid at the bid unit price per linear foot. This item includes all work necessary to construct a 6-inch wide concrete mow band including subgrade preparation, placing and compaction of aggregate base, and all other items needed to install the band in accordance with Detail 6 on L9.02 of the Cultural Gateways and Beautification Project plans & specifications. This item FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
25 OF 75
to be paid based on Owner’s estimate of the linear feet of wall installed on the project during each billing cycle. Some of this work shown on the plans is under the Beachfront Park Tolowa Cultural Trail Project contract. The provided bid quantities have been adjusted to exclude this work.
85. Concrete Subgrade (rat) Slab – Gateway: Not in Contract.
86. Reinforced Color Concrete Slabs for Cultural Node Surfacing – Gateway Nodes: Not in Contract
87. Surface colored reinforced Concrete Trail Markers – Gateway: Not in Contract
88. Lithocrete Basket Pattern: Not in Contract
89. Lithocrete Pebble Pattern: Not in Contract
90. Drainage Inlets (Caltrans Type G2 and GD0) – Gateway: The City to supply the drainage inlets and grates. Installation of the concrete drop inlets (CalTrans Type G2 and GD0) including hot dip galvanized grate, will be paid for on a per each basis. Work shall include the installation of the new inlets in accordance with all specifications. This item comprises the following: excavation and disposal of native material, removal and disposal of existing structures where shown, placement of precast inlets, placement of backfill material, and compaction of materials.
91. Install Area Drains – Gateway: The City to supply the drainage inlets and grates.
Installation of the concrete area drain inlets including hot dip galvanized grate, will be paid for on a per each basis. Work shall include the installation of the new inlets in accordance with all specifications. This item comprises the following: excavation and disposal of native material, removal and disposal of existing structures where shown, placement of precast inlets, placement of backfill material, and compaction of materials.
92. Install French Drains – Gateway: Installation of the French drains, will be paid for per linear foot. Work shall include the installation of the filter wrapped perforated pipe and drain rock in accordance with all plans and specifications. This item comprises the following: excavation and disposal of native material, placement of drain rock, filter wrapped perforate pipe, and placement of backfill material.
93. Storm Drain 4 inch HDPE – Gateway: Installation of 4-inch diameter Storm Drainpipe will be paid at the bid unit price per foot. Work shall include the installation of the pipes in accordance with all specifications. Work shall be performed in accordance with Specification Section 22 14 00 and comprises the following: trench excavation and disposal of native material, removal and disposal of existing pipe or structures where shown, installation of new and replacement piping and connections, connection to existing facilities including the couplings needed to join dissimilar pipes, backfill material, and compaction of materials to subgrade (soil ready to receive base rock if applicable). Pipe measurement will include the actual length FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
26 OF 75
of pipe installed and will not include waste pipe or measurement through junction structures or other structures.
94. Storm Drain 12 inch HDPE – Gateway: Installation of 12-inch Storm Drainpipe will be paid at the bid unit price per foot in accordance with item 93 above.
95. Storm Drain 24 inch HDPE – Gateway: Installation of 24-inch Storm Drainpipe will be paid at the bid unit price per foot in accordance with item 93 above.
96. Storm Drain 36 inch HDPE – Gateway: Installation of 36-inch Storm Drainpipe will be paid at the bid unit price per foot in accordance with item 93 above.
97. Landscape Soil Import – Gateway: This item will be paid on the bid unit price per cubic yard and includes all labor, materials, and equipment necessary to import, place, grade, and compact the landscaping soil as shown on the plans and specifications including Specification 32 91 13. The Owner will only pay for soil quantities identified in the bid schedule. Contractor is responsible for proper grading and placement of soil to achieve lines and grades. This item will be paid based on Owner’s estimate of the cubic yards of soil placed during each billing cycle.
98. Lawn Irrigation – Gateway: Installation of irrigation lines will be paid at the bid unit price per square foot. Work shall include installation of the new lines, sprinklers, valves, and fittings, etc. in accordance with all plans and specifications including Specification 32 84 00. This item comprises the following: trench excavation and disposal of native material, removal and disposal of existing lines and structures where shown, backfill material, and compaction of materials to subgrade (soil ready to receive landscaping).
99. Planting Areas Irrigation – Gateway: Installation of irrigation lines will be paid at the bid unit price per lump sum. Work shall include installation of the new lines, sprinklers, valves, fittings, controllers, sensors, backflow devices, meters, etc. in accordance with all plans and specifications including Specification 32 84 00. This item comprises the following: trench excavation and disposal of native material, removal and disposal of existing lines and structures where shown, backfill material, and compaction of materials to subgrade (soil ready to receive landscaping).
100. Planting Lawn – Gateway: Seeding of lawn will be paid at the bid unit price per square foot. Work shall include soil preparation, approval of seed mixture, and seeding, etc. in accordance with all plans and specifications including Specification 32 92 00. 50 percent will be paid on completion of soil preparation and 40 percent will be paid on completion of seeding.
101. Planting Ground Cover & Shrubs – Gateway: Planting of ground cover and shrubs will be paid at the bid unit price per lump sum. Work shall include soil preparation, approval of seed/plant selection, and placement, etc. in accordance with all plans and specifications including Specification 32 93 00.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
27 OF 75
102. Planting Trees – Gateway: Planting of trees will be paid at the bid unit price per each. Work shall include soil preparation, approval of tree selection size and type, root barrier (if applicable), and placement, etc. in accordance with all plans and specifications including Specification 32 93 00. This item will be paid based on Owner’s estimate of the number of trees placed during each billing cycle. 103. 4 inches Bark Mulch – Gateway: Application of 4 inches of bark mulch will be paid at the bid unit price per cubic yard. Work shall include importing and placement of mulch in accordance with all plans and specifications. This item will be paid based on Owner’s estimate of the cubic yards of mulch placed during each billing cycle. 104. Landscaping Maintenance – Front & Gateway: Landscape maintenance will be paid at the bid unit price per lump sum. Work shall include as required reseeding/replacement of trees/shrubs/plants which die for any cause, pruning, irrigation system inspection and maintenance, application of bark mulch, fertilizer, herbicide, and/or pesticide in accordance with all Front Street Improvements Play to L Streets plans, Cultural Gateways and Beautification Project plans, and specifications including Specification 32 93 10. 8.3 percent will be paid on a monthly progress payment over the course of one year starting with the City’s issuance of a Substantial Completion letter.
105. Landscaping Rock - Front: Landscaping shall be paid on a square foot basis and shall include labor, materials, and equipment needed to install decorative rock, geotextile (filter fabric), and all other landscaping as shown on the Front Street Improvements Play to L Streets plans and specifications. This item will be paid based on Owner’s estimate of the square feet of landscaping rock placed during each billing cycle.
106. Travel Planning Signs – Gateway: Installation of travel planning signs will be paid at the bid unit price per each. Work shall include assembly, placement and coordination with interpretive fabricator in accordance with all Detail 8 on L9.01 and sheet F8 in the Cultural Gateways and Beautification Project plans and specifications. The City to provide artwork and panels to be placed within Signs.
This item will be paid based on Owner’s estimate of the number of signs placed during each billing cycle.
107. Welcome Sign: Not in Contract
108. Install Electrical Control Panels, conduit and wire for lighted bollards, wall/stair plaza lighting, and power supply for cultural nodes and sound boxes: Not in Contract 109. Electrical Seat Wall & Steps Lighting – Gateway: The installation of recessed lighting shall be paid on a per each basis and shall include all labor, fixtures as shown in Detail 2 on L9.05 of the Cultural Gateways and Beautification Project plans and specifications. All work is to be installed where shown on the Plans or as directed by the City or the Engineer. This item to be paid based on Owner’s estimate of the number of fixtures installed on the project during each billing cycle.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
28 OF 75
110. Electrical Lighted Bollards – Gateway: The installation of lighted bollards shall be paid on a per each basis and shall include all labor, foundation, fixtures as shown in Detail 6 on L9.05 of the Cultural Gateways and Beautification Project plans and specifications. All work is to be installed where shown on the Plans or as directed by the City or the Engineer. This item to be paid based on Owner’s estimate of the number of bollards installed on the project during each billing cycle. 111. Removable Bollard – Gateway: The installation of removable bollards shall be paid on a per each basis and shall include all labor, foundation, inserts, sleeves, and adjacent paving related to the final buildout of the removable bollards as shown in Detail 7 on L9.05 of the Cultural Gateways and Beautification Project plans and specifications. All work is to be installed where shown on the Plans or as directed by the City or the Engineer. This item to be paid based on Owner’s estimate of the number of bollards installed on the project during each billing cycle. 112. Install Stair Handrails – Gateway: Installation of the handrails at concrete stairs will be paid for per linear foot. Work shall include the fabrication and installation of the handrail (excluding skate deterrence features) in accordance with page L9.04 & L9.05 of the Cultural Gateways and Beautification Project plans and specifications.
This item comprises the following: embedment/foundation, placement, and finish of handrails. This item to be paid based on Owner’s estimate of the number of linear feet installed on the project during each billing cycle. 113. Install Bicycle Racks – Gateway: Installation of the bicycle racks at the Porte Cochere will be paid for per each. Work shall include the purchase and installation of the bicycle racks in accordance with detail 1 on page L9.05 of the Cultural Gateways and Beautification Project plans and specifications. This item comprises the following: footing/foundation, flange placement, and installation of bicycle rack.
This item to be paid based on Owner’s estimate of the number of racks installed on the project during each billing cycle.
114. Skate Deterrent Features – Gateway: Not in Contract 115. Drinking Fountain and Sanitary Sewer Line – Gateway: The installation of the accessible drinking fountain and the 4-inch sanitary sewer line will be paid at the bid unit price per lump sum. Installation of the accessible drinking fountain shall include foundation, surface mounting, and plumbing in accordance with detail 3 on sheet L9.05. Installation of the 4-inch sanitary sewer line with gravity drainage to the manhole on Play Street comprises the following: excavation and disposal of native material, removal and disposal of existing structures, backfill material, temporary sewer connections to provide continuous service, and compaction of materials per sheet C1.00 of the Cultural Gateways and Beautification Project plans, and specifications. This item 90 percent will be paid on completion of installation and compaction to subgrade. The final 10 percent will be paid with the final payment.
116. Discovery Center Renovation – Gateway: Renovations will be paid at the bid unit price per lump sum. Work shown on sheets A2.11 (excluding A2.12) and structural FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
29 OF 75
sheet S0.01 through S0.03 include first floor landscaping, concrete wall modifications, removal of steel railing, wood bridge, exit signage, and patch/repair balcony deck and handrailing in accordance with all Cultural Gateways and Beautification Project plans, and specifications.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
30 OF 75
SECTION 01 21 43
TIME ALLOWANCES
1.0 COMPLETION SCHEDULE
1.01 BASE BID
The Contractor will have until November 30, 2026 to complete all items associated with the California Clean Gateway Project.
The Contractor may, at his/her option, work seven days per week and holidays.
K Street and 2nd Street intersection must be only be shut down for a maximum of 75 calendar days. This work must be completed prior to reworking the Front Street entrance to this parking lot. If the contractor elects to perform this work on an alternate project schedule, this schedule change must be approved by the City. This parking lot will not at any time be entirely closed to the public.
1.02 ADDITIVE ALTERNATIVE 1 – N/A
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
31 OF 75
SECTION 01 25 00
SUBSTITUTION PROCEDURES
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and other Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes administrative and procedural requirements for substitutions.
1.3 DEFINITIONS
A. Substitutions: Changes in products, materials, equipment, and methods of construction from those required by the Contract Documents.
1. Substitutions for Cause: Changes proposed by Contractor that are required due to changed Project conditions, such as unavailability of product, regulatory changes, or unavailability of required warranty terms.
2. Substitutions for Convenience: Changes proposed by Contractor or Owner that are not required to meet other Project requirements but may offer advantage to Contractor or Owner.
1.4 ACTION SUBMITTALS
A. Substitution Requests: Submit documentation identifying product or fabrication or installation method to be replaced. Include Specification Section number and title and Drawing numbers and titles.
1. Documentation: Show compliance with requirements for substitutions and the following, as applicable:
a. Statement indicating why specified product or fabrication or installation method cannot be provided, if applicable.
b. Coordination of information, including a list of changes or revisions needed to other parts of the Work and to construction performed by Owner and separate contractors that will be necessary to accommodate proposed substitution. c. Detailed comparison of significant qualities of proposed substitutions with those of the Work specified. Include annotated copy of applicable Specification Section.
Significant qualities may include attributes, such as performance, weight, size, durability, visual effect, sustainable design characteristics, warranties, and specific features and requirements indicated. Indicate deviations, if any, from the Work specified.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
32 OF 75
d. Product Data, including drawings and descriptions of products and fabrication and installation procedures.
e. Samples, where applicable or requested.
f. Certificates and qualification data, where applicable or requested. g. List of similar installations for completed projects, with project names and addresses as well as names and addresses of architects and owners. h. Material test reports from a qualified testing agency, indicating and interpreting test results for compliance with requirements indicated.
i. Detailed comparison of Contractor's construction schedule using proposed substitutions with products specified for the Work, including effect on the overall Contract Time. If specified product or method of construction cannot be provided within the Contract Time, include letter from manufacturer, on manufacturer's letterhead, stating date of receipt of purchase order, lack of availability, or delays in delivery.
j. Cost information, including a proposal of change, if any, in the Contract Sum. k. Contractor's certification that proposed substitution complies with requirements in the Contract Documents, except as indicated in substitution request, is compatible with related materials and is appropriate for applications indicated. l. Contractor's waiver of rights to additional payment or time that may subsequently become necessary because of failure of proposed substitution to produce indicated results.
2. Landscape Architect's Action: If necessary, Landscape Architect will request additional information or documentation for evaluation within seven days of receipt of a request for substitution. Landscape Architect will notify Contractor of acceptance or rejection of proposed substitution within 15 days of receipt of request, or seven days of receipt of additional information or documentation, whichever is later. a. Forms of Acceptance: Change Order, Construction Change Directive, or Landscape Architect's Supplemental Instructions for minor changes in the Work. b. Use product specified if Landscape Architect does not issue a decision on use of a proposed substitution within time allocated.
1.5 QUALITY ASSURANCE
A. Compatibility of Substitutions: Investigate and document compatibility of proposed substitution with related products and materials. Engage a qualified testing agency to perform compatibility tests recommended by manufacturers.
1.6 PROCEDURES
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
33 OF 75
A. Coordination: Revise or adjust affected work as necessary to integrate work of the approved substitutions.
1.7 SUBSTITUTIONS
A. Substitutions for Cause: Submit requests for substitution immediately on discovery of need for change, but not later than 15 days prior to time required for preparation and review of related submittals.
1. Conditions: Landscape Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Architect will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution is consistent with the Contract Documents and will produce indicated results.
b. Substitution request is fully documented and properly submitted. c. Requested substitution will not adversely affect Contractor's construction schedule.
d. Requested substitution has received necessary approvals of authorities having jurisdiction.
e. Requested substitution is compatible with other portions of the Work. f. Requested substitution has been coordinated with other portions of the Work. g. Requested substitution provides specified warranty.
h. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
B. Substitutions for Convenience: Landscape Architect will consider requests for substitution if received within 60 days after the Notice of Award. Requests received after that time may be considered or rejected at discretion of Landscape Architect.
1. Conditions: Landscape Architect will consider Contractor's request for substitution when the following conditions are satisfied. If the following conditions are not satisfied, Landscape Architect will return requests without action, except to record noncompliance with these requirements:
a. Requested substitution offers Owner a substantial advantage in cost, time, energy conservation, or other considerations, after deducting additional responsibilities Owner must assume. Owner's additional responsibilities may include compensation to Landscape Architect for redesign and evaluation services, increased cost of other construction by Owner, and similar FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
34 OF 75
considerations.
b. Requested substitution does not require extensive revisions to the Contract Documents.
c. Requested substitution is consistent with the Contract Documents and will produce indicated results.
d. Substitution request is fully documented and properly submitted. e. Requested substitution will not adversely affect Contractor's construction schedule.
f. Requested substitution has received necessary approvals of authorities having jurisdiction.
g. Requested substitution is compatible with other portions of the Work. h. Requested substitution has been coordinated with other portions of the Work.
i. Requested substitution provides specified warranty.
j. If requested substitution involves more than one contractor, requested substitution has been coordinated with other portions of the Work, is uniform and consistent, is compatible with other products, and is acceptable to all contractors involved.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
35 OF 75
SECTION 01 33 00
SUBMITTALS
1.0 GENERAL
Submittals covered by these requirements include manufacturers' information, shop drawings, test procedures, test results, samples, requests for substitutions, and miscellaneous work-related submittals. Submittals shall also include, but not be limited to, mechanical, electrical and electronic equipment, systems, materials, reinforcing steel, fabricated items, piping, and conduit details. The Construction Superintendent shall furnish all drawings, specifications, descriptive data, certificates, samples, tests, methods, schedules, and manufacturer's installation and other instructions as specifically required in the contract documents to demonstrate fully that the materials and equipment to be furnished and the methods of work comply with the provisions and intent of the contract documents.
The Contractor and his designees will be set up as users in the City’s Virtual Project Manager (VPM). VPM is a cloud-based system that will be used to process all payments, RFI’s, submittal, reports, and will act as a file for all other project documents. If a Contractor is unable to scan documents or provide digital submittals, the City will digitize and upload the documents required as part of this Contract at the Contractor’s expense. These expenses will be billed to the Contractor on a monthly basis.
2.0 CONSTRUCTION SUPERINTENDENT'S RESPONSIBILITIES
The Construction Superintendent shall be responsible for the accuracy and completeness of the information contained in each submittal and shall assure that the material, equipment, or method of work shall be as described in the submittal. The Construction Superintendent shall verify that all features of all products conform to the specified requirements. Submittal documents shall be clearly edited to indicate only those items, models, or series of equipment, which are being submitted for review. All extraneous materials shall be crossed out or otherwise obliterated. The Construction Superintendent shall ensure that there is no conflict with other submittals and notify the Engineer in each case where his submittal may affect the work of another contractor. The Construction Superintendent shall coordinate submittals among his subcontractors and suppliers including those submittals complying with unit responsibility requirements and applicable technical sections.
The Construction Superintendent should coordinate submittals with the work so that work will not be delayed. He should coordinate and schedule different categories of submittals, so that one will not be delayed for lack of coordination with another.
The Construction Superintendent should not proceed with work related to a submittal until the submittal process is complete. This requires that submittals for review and comment shall be returned to the Construction Superintendent stamped "No Exceptions Taken" or "Make Corrections Noted." The Construction Superintendent shall certify on each submittal document that he has reviewed the submittal, verified field conditions, and complied with the contract documents.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
36 OF 75
3.0 CATEGORIES OF SUBMITTALS
A. GENERAL
Submittals fall into two general categories; submittals for review and comment, and submittals which are primarily for information only. Submittals which are for information only are generally specified as PRODUCT DATA in Part 2 of applicable specification sections.
B. SUBMITTALS FOR REVIEW AND COMMENT
All submittals except where specified to be submitted as product data for information only shall be submitted by the Construction Superintendent to the Engineer for review and comment.
C. SUBMITTALS (PRODUCT DATA) FOR INFORMATION ONLY
Where specified, the Construction Superintendent shall furnish submittals (product data) to the Engineer for Information only. If required, submittal requirements for operation and maintenance manuals, which are included in this category, are specified elsewhere.
4.0 TRANSMITTAL PROCEDURE
A. GENERAL
Contractor must use VPM for submittal. If Contractor is unwilling or unable to use VPM, then follow the following procedure. City will charge Contractor for digitization and uploading of all paper submittals.
Unless otherwise specified, submittals regarding material and equipment shall be accompanied by Transmittal Form 01300-A specified in Section 00 62 00. Submittals for operation and maintenance manuals, information, and data shall be accompanied by Transmittal Form 01730-A specified in Section 01999. A separate form shall be used for each specific item, class of material, equipment, and items specified in separate, discrete sections, for which the submittal is required.
Submittal documents common to more than one piece of equipment shall be identified with all the appropriate equipment numbers. Submittals for various items shall be made with a single form when the items taken together constitute a manufacturer's package or are so functionally related that expediency indicates checking or review of the group or package as a whole.
A unique number, sequentially assigned, shall be noted on the transmittal form accompanying each item submitted. Original submittal numbers shall have the following format:
"XXX"; where "XXX" is the sequential number assigned by the Construction Superintendent.
Resubmittals shall have the following format: "XXX-Y"; where "XXX" is the originally assigned submittal number and "Y" is a sequential letter assigned for resubmittals, i.e., A, B, or C being the 1st, 2nd, and 3rd resubmittals, respectively. Submittal 25B, for example, is the second resubmittal of submittal 25.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
37 OF 75
B. DEVIATION FROM CONTRACT
Contractor shall utilize VPM for this process.
If the Construction Superintendent proposes to provide material, equipment, or method of work which deviates from the project manual, he shall indicate so under "deviations" on the transmittal form accompanying the submittal copies.
C. SUBMITTAL COMPLETENESS
Submittals which do not have all the information required to be submitted, including deviations, are not acceptable and will be returned without review.
5.0 REVIEW PROCEDURE
A. GENERAL
Submittals are specified for those features and characteristics of materials, equipment, and methods of operation which can be selected based on the Construction Superintendent's judgment of their conformance to the specified requirements. Other features and characteristics are specified in a manner which enables the Construction Superintendent to determine acceptable options without submittals. The review procedure is based on the Construction Superintendent's guarantee that all features and characteristics not requiring submittals conform as specified. Review shall not extend to means, methods, techniques, sequences, or procedures of construction, or to verifying quantities, dimensions, weights or gages, or fabrication processes (except where specifically indicated or required by the project manual) or to safety precautions or programs incident thereto.
Review of a separate item, as such, will not indicate approval of the assembly in which the item functions.
When the contract documents require a submittal, the Construction Superintendent shall submit using VPM. Upon Construction Manager’s or Owner’s request, the Contractor shall provide:
1. Four (4) copies of all submitted information plus one reproducible original of all information shall be transmitted with submittals for review and comment.
2. Unless otherwise specified, 2 copies of all submitted information shall be transmitted with submittals (Product Data) for information only.
B. SUBMITTALS FOR REVIEW AND COMMENT:
Comments will normally be returned through VPM. If VPM is not able to be used for whatever reason, then the following procedure will apply.
Unless otherwise specified, within 20 calendar days after receipt of a submittal for review and comment, the Engineer shall review the submittal and return 2 copies of the marked-up reproducible original noted in 1 above. The reproducible original will be retained by the Engineer.
The returned submittal shall indicate one of the following actions:
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
38 OF 75
1. If the review indicates that the material, equipment, or work method complies with the project manual, submittal copies will be marked "NO EXCEPTIONS TAKEN." In this event, the Construction Superintendent may begin to implement the work method or incorporate the material or equipment covered by the submittal.
2. If the review indicates limited corrections are required, copies will be marked "MAKE CORRECTIONS NOTED." The Construction Superintendent may begin implementing the work method or incorporating the material and equipment covered by the submittal in accordance with the noted corrections.
Where submittal information will be incorporated in O&M data, a corrected copy shall be provided.
3. If the review reveals that the submittal is insufficient or contains incorrect data, copies will be marked "AMEND AND RESUBMIT." Except at his own risk, the Construction Superintendent shall not undertake work covered by this submittal until it has been revised, resubmitted, and returned marked either "NO EXCEPTIONS TAKEN" or "MAKE CORRECTIONS NOTED."
4. If the review indicates that the material, equipment, or work method does not comply with the project manual, copies of the submittal will be marked "REJECTED - SEE REMARKS." Submittals with deviations which have not been identified clearly may be rejected. Except at his own risk, the Construction Superintendent shall not undertake the work covered by such submittals until a new submittal is made and returned marked either "NO EXCEPTIONS TAKEN" or "MAKE CORRECTIONS NOTED."
C. SUBMITTALS (PRODUCT DATA) FOR INFORMATION ONLY:
Such information is not subject to submittal review procedures and shall be provided as part of the work under this contract and its acceptability determined under normal inspection procedures.
6.0 EFFECT OF REVIEW OF CONSTRUCTION SUPERINTENDENT'S SUBMITTALS Review of contract drawings, methods of work, or information regarding materials or equipment the Construction Superintendent proposes to provide, shall not relieve the Construction Superintendent of his responsibility for errors therein and shall not be regarded as an assumption of risks or liability by the Engineer, or by any officer or employee thereof, and the Construction Superintendent shall have no claim under the contract on account of the failure, or partial failure, of the method of work, material, or equipment so reviewed. A mark of "NO EXCEPTIONS TAKEN" or "MAKE CORRECTIONS NOTED" shall mean that the Engineer has no objection to the Construction Superintendent, upon his own responsibility, using the plan or method of work proposed, or providing the materials or equipment proposed.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
39 OF 75
SECTION 01 45 00
QUALITY CONTROL
PART 1 – GENERAL
1.01 DESCRIPTION
This section specifies administrative and procedural requirements for quality control services, field inspections, and field testing of civil and structural constructs required for this project. Contractor is responsible for the quality assurance and quality control of their respective work.
1.02 DEFINITIONS
Quality Control System (QCS): The quality control, assurance, and inspection system established and carried out to ensure compliance with the Plans and Specifications.
QCS Supervisor: That person in responsible charge of the work occurring, as designated by the Contractor in the QCS Plan.
QCS Inspector: Responsible, certified personnel inspecting the various constructs at specified milestones and during the project overall and designated by the Construction Manager. The Special Inspector is part of the QCS Inspector team.
Factory Test: Tests made on various materials, products, and component parts prior to shipment to the job site.
Field Tests: Tests and analyses made at or in the vicinity of the job site in connection with the actual construction.
Certified Inspection Report: Reports signed by approved inspectors attesting that the items inspected meet the specification requirements other than any exceptions included in the report.
Certificate of Compliance: Certificate from the manufacturer of the material or equipment identifying said manufacturer, product and referenced standard, and shall be signed by a designated officer of the manufacturer.
Standard Compliance: Condition whereby specified materials or equipment must conform to the standards of organizations such as the American National Standard Institute (ANSI), American Society for Testing and Materials (ASTM), Underwriters Laboratories (UL) or similar organization.
Quality Assurance: The day-to-day, in-process supervisory observations of work and materials conducted by the Contractor to assure that the proper methods and materials are being used and installed by tradesmen.
Source Quality Control: The in-process testing, and inspections conducted by the QCS Inspector(s) to verify that the materials, equipment, workmanship and shop manufactured constructs are in compliance with the Contract Documents, applicable Codes and standards.
Field Quality Control: The testing and inspections conducted by the QCS Inspector(s) in the field during and at the completion of each construct to verify that FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
40 OF 75
the in-process and completed construction is in compliance with the Contract Documents and applicable codes and standards.
Energy Star Inspector/Certifier: Designated and paid for by the Owner.
Building Official/Building Inspector: As defined by the IBC and California Code of Regulations Title 24. The City Building Official, City Manager, and City Public Works Director are each designated to act in this role.
1.03 REFERENCES
This section contains references to the following documents. They are a part of this section as specified and modified. Where a referenced document contains references to other standards, those documents are included as references under this section as if referenced directly. In the event of conflict between the requirements of this section and those of the listed documents, the requirements of this section shall prevail.
Unless otherwise specified, references to documents shall mean the documents in effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the Agreement if there were no Bids). If referenced documents have been discontinued by the issuing organization, references to those documents shall mean the replacement documents issued or otherwise identified by that organization, or if there are no replacement documents, the last version of the document before it was discontinued.
Where document dates are given in the following listing, references to those documents shall mean the specific document version associated with that date, regardless of whether the document has been superseded by a version with a later date, discontinued, or replaced.
Reference Title
ASTM C102 Practice for Laboratories Engaged in the Testing of Building Sealants.
ASTM C802 Practice for Conducting an Inter-Laboratory Test Program to Determine the Precision of Test Methods for Construction.
ASTM D3740 Practice for Evaluation of Agencies Engaged in Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction.
ASTM D4561 Practice for Quality Control Systems for an Inspection and testing Agency for Bituminous Paving Materials.
ASTM E329 Practice for Use in the Evaluation of Inspection and Testing Agencies as Used in Construction.
IBC 2016 California Building Code
1.04 CONTRACTOR’S RESPONSIBILITIES
Contractor’s responsibilities shall be as follows:
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
41 OF 75
1. Monitor quality assurance over suppliers, manufacturers, products, services, site conditions, and workmanship, to produce work of specified quality.
2. Coordinate with, schedule specified inspections by, and provide normal and customary assistance to the QCS Inspectors.
3. Comply fully with manufacturers’ instructions, including each step-in sequence.
4. Should manufacturers’ instructions conflict with Contract Documents, request clarification before proceeding from Construction Manager.
5. Comply with specified standards as a minimum quality for the work except when more stringent tolerances, codes, or specified requirements indicate higher standards or more precise workmanship.
6. Perform work by persons qualified to produce workmanship of specified quality.
7. Notify Building Inspector with 48-hour notice to observe all construction elements related to the project, regardless of trade, prior to covering. No work elements shall be covered prior to written acceptance by the Building Inspector. If so, the work shall be exposed and recovered by and at the sole expense of the Contractor.
8. To demonstrate his compliance with the contract requirements, the Contractor must assist the Construction Manager in his performance of inspection work.
The Contractor must grant the Construction Manager access to the work and to the site of the work, and to the places where work is being prepared, or whence materials, equipment or machinery are being obtained for the work.
The Contractor must provide information requested by the Construction Manager in connection with inspection work.
9. If the contract documents, laws, ordinances, or any public regulatory authority require parts of the work to be specially inspected, tested, or approved, the Contractor will give the Construction Manager adequate prior written notice of the availability of the subject work for examination.
10. If parts of the work are covered in contravention of the Construction Manager's directive, the cost of exposing the work for inspection and closing must be borne by the Contractor regardless of whether or not the work is found to be in compliance with the contract.
11. If any work is covered in the absence of the Construction Manager's directive to the contrary, the Contractor must, if directed to do so by the Construction Manager, uncover, expose, or otherwise make available for inspection, portions of covered work. If it is found that such work is defective, the Contractor must bear the expense of uncovering and reconstructing. If the work is found to be in compliance with the contract, the Contractor will be allowed an increase in the contract price, or an extension in the contract time, or both. A change order will be issued to document the increase, extension, or both.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
42 OF 75
1.05 REGULATORY REQUIREMENTS
A. GENERAL
Comply with all Federal, State, and local Codes as referenced herein. Such regulations apply to activities including, but not limited to, sitework and zoning, building practices and quality, on and offsite disposal, safety, sanitation, nuisance, and environmental quality.
B. SPECIAL INSPECTION
Special Inspection shall be performed by the Special Inspector under contract with the Construction Manager. Special Inspection is in addition to, but not replacing, other inspections and quality control requirements herein. Where sampling and testing required herein conforms to Special Inspection standards, such sampling and testing need not be duplicated.
C. STRUCTURAL OBSERVATION
Engineer shall make visual inspections of the work to assess general conformance with the Contract Documents at significant construction stages and at completion of the structural system. The QCS shall include a preliminary set of Structural Observations and what items are expected to be observed. Contractor shall request this preliminary set from Engineer through Construction Manager and submit as part of their QCS submittal.
The following structural milestones shall be considered significant construction stages:
(NONE)
D. FIELD SAMPLE PROCEDURES
When field samples are specified in a unit of work, construct each field sample to include work of all trades required to complete the field sample prior to starting related field work. Field samples may be incorporated into the project after acceptance by Construction Manager. Remove unacceptable field samples when directed by Construction Manager. Acceptable samples represent a quality level for the work.
1.06 CONTRACTOR DESIGNED STRUCTURAL SYSTEMS
A. DESIGN ENGINEERING:
Contractor shall employ and pay for engineering services from a Professional Engineer registered in the State of California for structural design of Contractor designed structural systems including but not limited to temporary shoring and bracing, formwork FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
43 OF 75
support, and support systems for fire protection, plumbing, mechanical, electrical systems, and equipment.
B. TESTS AND INSPECTIONS OF CONTRACTOR DESIGNED
STRUCTURAL SYSTEMS:
Contractor shall pay for preliminary testing of concrete, grout, and mortar mix designs where required by Code or the submittal process prior to start of such work.
Contractor shall pay for required shop and site inspection of Contractor designed structural systems where required by Code or these specifications, to the extent such testing and inspection exceeds that required for the structural system on the drawings and in these specifications.
C. MANUFACTURERS’ FIELD SERVICES AND REPORTS
When specified in individual specification Sections, product suppliers or manufacturers shall provide qualified staff personnel to observe site conditions, conditions of surfaces and installation, quality of workmanship, start-up of equipment, test, adjust, and balance of equipment as applicable, and to provide instructions when necessary. Contractor shall submit qualifications of observer to Construction Manager 30 days in advance of required observations. QCS Inspector shall record observations and site decisions or instructions given to applicators or installers that are supplemental or contrary to manufacturers’ written instructions.
D. JOB SITE CONDITIONS
Schedule to ensure all preparatory work has been accomplished prior to proceeding with current work. Proceeding with the work constitutes acceptance of conditions. Allow adequate time for materials susceptible to temperature and humidity to “stabilize” prior to installation.
E. SUBMITTALS
The following information shall be provided in accordance with Section 01 33 00:
1. A copy of this specification section, with addendum updates included, and all referenced and applicable sections, with addendum updates included, with each paragraph check-marked to indicate specification compliance or marked to indicate requested deviations from specification requirements. Check marks () shall denote full compliance with a paragraph as a whole. If deviations from the specifications are indicated, and therefore requested by the Contractor, each deviation shall be underlined and denoted by a number in the margin to the right of the identified paragraph, referenced to a detailed written explanation of the reasons for requesting the deviation. The Construction Manager shall be the FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
44 OF 75
final authority for determining acceptability of requested deviations.
The remaining portions of the paragraph not underlined will signify compliance on the part of the Contractor with the specifications.
Failure to include a copy of the marked-up specification sections, along with justification(s) for any requested deviations to the specification requirements, with the submittal shall be sufficient cause for rejection of the entire submittal with no further consideration.
2. Written description of Contractor’s proposed QCS plan in sufficient detail to illustrate understanding and approach. The QCS plan and submittal shall include a log showing anticipated inspections, Special Inspections, and source and field Quality Assurance procedures.
Preliminary submittal of the QCS plan may be made prior to commencing field work. The preliminary submittal will illustrate the project’s initial three (3) month’s work and be followed one month later by a final QCS plan submittal.
3. Contractor’s proposed QCS Supervisor, qualifications, and if requested, references.
4. Preliminary structural observation set as described in paragraph 1.05 C.
5. Complete structural system information describing Contractor designed structural systems, including sealed calculations, shop and erection drawings, product literature for the various components, ICBO Evaluation Reports for structural components, and a discussion of risk issues associated with the proposed system which could adversely impact overall project completion.
6. If requested by the Construction Manager during the work, manufacturer’s field services and reports. If not so requested, treat same as Product Data.
PART 2 – PRODUCTS
2.01 SOURCE QUALITY CONTROL
A. CONTRACTOR RESPONSIBILITIES:
Provide source quality control according to the reviewed and accepted QCS plan and paragraph 1.04 herein. Coordinate with Construction Manager to facilitate the work of the Testing Laboratory specified in Section 01 45 29 and Special Inspector. Provide ready access to sampling and inspection locations and incidental labor customary in such sampling and inspections. Timely prepare and submit submittals and revise as indicated FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
45 OF 75
by review comments. Comply with technical requirements in each specification Section that applies to the work.
B. CONSTRUCTION MANAGER RESPONSIBILITIES:
Review Contractor’s tracking of QCS activities at monthly meetings. Facilitate completion of submittal review per Section 01 33 00. Assist Contractor to ensure that Special Inspection occurs where and when specified.
C. ACCEPTANCE CRITERIA:
Acceptable characteristics and quality of a particular item or construct is defined in that item or construct’s specification Section.
2.02 PRODUCT DATA
The following product data shall be provided in accordance with Section 01 33 00.
1. Manufacturers’ field services and reports unless requested by Construction Manager to be submitted for review.
2. Special Inspection reports, unless otherwise directed in each technical specification Section.
PART 3 – EXECUTION
3.01 FIELD QUALITY CONTROL
Field quality control responsibilities of the Contractor and Construction Manager are substantially the same as described in paragraph 2.01, with the exception that this work occurs primarily on the jobsite as the work progresses, and Special Inspection will occur more often than at the source.
Acceptable characteristics and quality of a particular item or construct is defined in that item or construct’s specification section.
3.02 REGULATORY COMPLIANCE – SPECIAL INSPECTIONS
The following types of work require Special Inspection according to Chapter 17 of the IBC and each system’s specification section:
1. Structure fill.
2. Structural concrete and reinforcing.
3. Anchor bolts and post-installed anchor systems.
4. Structural steel and aluminum including connections.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
46 OF 75
Section 01 45 29 describes Testing Laboratory sampling, testing, and reporting, much of which is conforming to Special Inspection requirements, and need not be replicated.
Contractor designed structural systems are subject to the same Special Inspection requirements as all other work.
3.03 CORRECTION OF DEFECTIVE WORK
Remove and replace defective, rejected, and condemned work at Contractor’s expense until such work meets the requirements of Contract Documents. Costs for Inspection of corrected work shall be paid by the Contractor.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
47 OF 75
SECTION 01 45 29
TESTING LABORATORY SERVICES
PART 1 – GENERAL
1.01 DESCRIPTION
This Section specifies Quality Control testing and reporting performed by the Testing Laboratory. Construction Manager shall select a qualified Testing Laboratory and contract for the services specified herein, except as specifically noted where Contractor may elect to utilize Testing Laboratory to fulfill submittal requirements. Such an arrangement does not relieve the Contractor from their responsibility to provide the completed project as specified, and to perform Quality Assurance according to the QCS as reviewed and accepted.
1.02 REFERENCES
This section contains references to the following documents. They are a part of this section as specified and modified. Where a referenced document contains references to other standards, those documents are included as references under this section as if referenced directly. In the event of conflict between the requirements of this section and those of the listed documents, the requirements of this section shall prevail.
Unless otherwise specified, references to documents shall mean the documents in effect at the time of Advertisement for Bids or Invitation to Bid (or on the effective date of the Agreement if there were no Bids). If referenced documents have been discontinued by the issuing organization, references to those documents shall mean the replacement documents issued or otherwise identified by that organization or, if there are no replacement documents, the last version of the document before it was discontinued.
Where document dates are given in the following listing, references to those documents shall mean the specific document version associated with that date, regardless of whether the document has been superseded by a version with a later date, discontinued, or replaced.
Reference Title
AASHTO T27Standard Method of Test for Sieve Analysis of fine and Coarse Aggregate
ACI 214 Evaluation of Strength Test Results of Concrete ASTM A880 Criteria for Use in Evaluation of Testing Laboratories and Organizations for Examination and Inspection of Steel,
Stainless Steel, and Related Alloys
ASTM C29 Standard Test Method for Bulk Density (“Unit Weight”) and Voids in Aggregate
ASTM C31 Making and Curing Concrete Test Specimens in the Field ASTM C39 Compressive Strength of Cylindrical Concrete Specimens FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
48 OF 75
Reference Title
ASTM C42 Obtaining and Testing Drilled Cores and Sawed Beams of Concrete
ASTM C127 Standard Test Method for Density, Relative Density (Specific Gravity), and Absorption of Coarse Aggregate
ASTM C136 Standard Method for Sieve Analysis of Fine and Coarse Aggregates
ASTM
C143/C143M
Slump of Hydraulic Cement Concrete
ASTM C172 Sampling Freshly Mixed Concrete
ASTM C802 Conducting an Inter-laboratory Test Program to Determine the Precision of Test Methods for Construction Materials
ASTM C1021 Laboratories Engaged in the Testing of Building Sealants ASTM Cl077 Laboratories Testing Concrete and Concrete Aggregates for Use in Construction and Criteria for Laboratory Evaluation ASTM D75 Sampling Aggregates
ASTM D1556 Test Method for Density of Soil in Place by the Sand-Cone Method
ASTM D1557 Test Methods for Moisture-Density Relations of Soils and SoilAggregate Mixtures Using 10-lb (4.5-kg) Rammer and 18-in. (457-mm) Drop
ASTM D2419 Standard Test Method for Sand Equivalent Value of Soils and Fine Aggregate
ASTM D2487 Classification of Soils for Engineering Purposes ASTM D3017 Test Method for Moisture Content of Soil and Soil- Aggregate in Place by Nuclear Methods (Shallow Depth)
ASTM D3441 Standard Test Method for Mechanical cone Penetration Tests of Soil
ASTM D3666 Specification for Minimum Requirements for Agencies Testing and Inspecting Road and Paving Materials
ASTM D3740 Minimum Requirements for Agencies Engaged in the Testing and/or Inspection of Soil and Rock as Used in Engineering Design and Construction
ASTM D4318 Liquid Limit, Plastic Limit, and Plasticity Index of Soils ASTM D4561 Quality Control Systems for Organizations Producing and Applying Bituminous Paving Materials
ASTM D4832 Standard Test Method for Preparation and Testing of Controlled Low Strength Material (CLSM) Test Cylinders
ASTM E4 Force Verification of Testing Machines
ASTM E329 Agencies Engaged in the Testing and/or Inspection of Materials Used in Construction
ASTM E543 Agencies Performing Nondestructive Testing
ASTM E994 Calibration and Testing Laboratory Accreditation Systems General Requirements for Operation and Recognition
IBC 2022 California Building Code
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
49 OF 75
1.03 TESTING LABORATORY QUALIFICATIONS
Testing Laboratory shall satisfy the following qualifications:
1. Recommended Requirements for Independent Laboratory Qualification, published by American Council of Independent Laboratories.
2. Conform to the requirements of ASTM E329 in particular and other reference standards as generally pertain to this project.
3. Authorized to operate in the State of California, with personnel and equipment based sufficiently close to the project to allow short-notice site access for sampling and testing.
4. Acceptable to Owner, Construction Manager, and local building authorities.
1.04 TESTING LABORATORY RESPONSIBILITIES
Testing Laboratory shall provide qualified personnel at the site and cooperate with Construction Manager and Contractor in performance of the following services:
1. Perform specified independent inspection, sampling, and testing of products in accordance with specified standards, to determine compliance with requirements of Contract Documents.
2. Provide sampling equipment and personnel, deliver samples to the testing laboratory, record field measurements, and cure samples as required by Contract Documents.
3. Perform Building Department required tests and inspections, including Special Inspection as specified in Section 01 45 00.
4. Timely prepare and deliver reports summarizing results of tests and inspections.
5. Attend pre-construction conferences and, if requested, a limited number of progress meetings where Quality Control, testing, and inspection issues require discussion.
6. When directed by the Construction Manager or requested by the Contractor, provide special and additional tests and inspections to verify material compliance with requirements of Contract Documents.
a. Construction Manager shall pay for special tests and inspections where work conforms to the Contract Document requirements.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
50 OF 75
b. Contractor shall pay for additional tests and inspections where work fails to comply with Contract Document requirements (re-inspection) and for costs associated with cancelled or short-notice re-scheduling of requested sampling, testing, and inspection. Testing Laboratory work requested by Contractor to fulfill submittal requirements shall also be considered additional tests.
1.05 CONTRACTOR RESPONSIBILITIES
Contractor shall deliver adequate samples of materials proposed to be used and which require testing to the Testing Laboratory. Contractor shall cooperate with Testing Laboratory personnel and provide access to the work and to manufacturer’s facilities.
Contractor shall provide incidental labor and facilities to provide access to work to be tested, to obtain and handle samples at the site or at source of products to be tested, to facilitate tests and inspections, storage and curing of test samples.
Contractor shall notify Testing Laboratory and Construction Manager 24 hours prior to expected time for operations requiring inspection, sampling, and testing services.
1.06 TEST AND INSPECTION REPORTS
A. REPORT CONTENTS:
At a minimum, Test and Inspection Reports shall include the following:
1. Project name and date of report.
2. Testing Laboratory name, address, telephone number, name of laboratory field sampling personnel, lab testing personnel, or QCS Inspector as applicable.
3. Date, time, and location of sampling, testing, and inspecting.
4. Ambient temperature and weather conditions at the site or shop and curing conditions of samples.
5. Product identification and referenced specification Section number.
6. Type of sample, test, and inspection and industry standard for sampling and testing.
7. Results of sample, test, and inspection.
8. Evaluation of compliance with requirements in Contract Documents.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
51 OF 75
9. Certified Inspection Reports shall specifically indicate the qualification of the inspector to render judgment and certify said inspection.
10. When requested by Construction Manager, interpretation of test results.
B. DISTRIBUTION OF TEST AND INSPECTION REPORTS:
Test and Inspection reports shall be submitted to the Construction Manager for distribution as Product Data described in Section 01 33 00, unless technical specification sections require submittal for review. Test reports shall be submitted not more than two days after completion of required tests. Inspection reports shall be submitted immediately if deficiencies or significant irregularities are noted, and in no case less than two working days after said inspection. Provide six (6) copies of all reports.
1.07 SUBMITTALS
The following information shall be provided in accordance with Section 01 33 00:
A. A copy of this specification section, with addendum updates included, and all referenced and applicable sections, with addendum updates included, with each paragraph check-marked to indicate specification compliance or marked to indicate requested deviations from specification requirements.
Check marks () shall denote full compliance with a paragraph as a whole.
If deviations from the specifications are indicated, and therefore requested by the Contractor, each deviation shall be underlined and denoted by a number in the margin to the right of the identified paragraph, referenced to a detailed written explanation of the reasons for requesting the deviation.
The Construction Manager shall be the final authority for determining acceptability of requested deviations. The remaining portions of the paragraph not underlined will signify compliance on the part of the Contractor with the specifications. Failure to include a copy of the markedup specification sections, along with justification(s) for any requested deviations to the specification requirements, with the submittal shall be sufficient cause for rejection of the entire submittal with no further consideration.
B. Documentation of conformance with Testing Laboratory Qualifications as specified in paragraph 01 45 29-1.03 herein.
C. Form A described in paragraph 01 45 29-3.03 herein, by both Testing Laboratory and Contractor.
D. Final laboratory report as described in paragraph 01 45 29-3.04.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
52 OF 75
1.08 LIMITS ON TESTING LABORATORY AUTHORITY
Testing Laboratory may not release, revoke, alter, or enlarge on requirements of Contract Documents. Testing Laboratory may not approve or accept any portion of the work, nor assume any duties of Contractor. Testing Laboratory has no authority to stop the work.
PART 2 – PRODUCTS
2.01 SOURCE QUALITY CONTROL
A. GENERAL
Source quality control is defined in Section 01 45 00. This Section provides general guidelines as to the sampling, tests, and inspections required of products and manufactures prior to delivery to the project site and should be considered a minimum.
Additional information and requirements are provided in each technical specification Section and those requirements shall control over this Section when in conflict. Absence of a test, inspection or requirement listed herein from a subsequent specification Section does not relieve the Testing Laboratory or the Contractor from their respective responsibilities specified in this Section.
B. REFERENCE STANDARDS IN OTHER SECTIONS
Codes, standards, and other references called out below, but which are not listed in paragraph 1.02 are described in other specification Sections and not repeated herein.
C. FILL MATERIALS
1. IMPORTED FILL MATERIALS: Testing Laboratory may conduct additional testing on behalf of Contractor to prepare required submittals specified in Section 31 20 00 and Section 31 23 33. Tests shall conform to the following for both Source and Field Quality Control:
Test Standard
Procedure
Moisture content ASTM D3017
Gradation ASTM C136
Density in-place ASTM D1556
Moisture-density relationships ASTM D1557
Liquid Limit, Plasticity Index ASTM D4318
2. TYPE C FILL MATERIAL: Testing Laboratory shall conduct required testing to verify on-site materials proposed for fill conforms to specification Section 31 20 00. Contractor shall pay Testing Laboratory for such sampling and testing. Sampling and testing shall FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
53 OF 75
Classify Soil according to ASTM D2487 including Liquid Limit, Plasticity Index, and determine optimum moisture content and density relationship, and other data as required for proper use of this material.
D. PAVING MATERIALS:
Provide sampling and testing requested by Construction Manager or additional testing as requested by Contractor to verify materials proposed for use conform to specification Section 31 20 00 and Section 32 12 00.
E. CONCRETE REINFORCING:
Provide sampling and testing requested by Construction Manager or additional testing as requested by Contractor to verify materials proposed for use conform to specification Section 03 30 00.
F. CAST-IN-PLACE CONCRETE:
1. GENERAL: Field sampling and testing shall be performed by the testing laboratory specified in paragraph 01 45 29-1.01 A. Samples shall be taken at random locations and at such times to represent the quality of the materials and work throughout the project. The laboratory shall provide the necessary labor, materials, and facilities for sampling. Aggregates shall be sampled not less than 30 days prior to the use of such aggregates in the work. At Contractor’s expense, Testing Laboratory may assist Contractor in formulating concrete mix designs, testing and reporting same, and providing the services of a Professional Engineer to review and seal the mix design.
2. AGGREGATES: Samples shall be taken at the discharge gates of the bins feeding the weigh hopper. The Contractor shall provide safe and suitable facilities for obtaining samples. Testing shall confirm continuing conformance with specifications for gradation, cleanliness, and sand equivalent. A maximum of one test per day of each aggregate is required. Sampling shall be repeated when the source of material is changed or when unacceptable deficiencies or variations from the specified requirements of materials are found in testing. The full test program is required before source changes will be accepted. Aggregate samples shall be tagged, and their sources shall be identified.
3. COARSE AGGREGATE: A sample weighing between 50 and 60 pounds shall be taken after the batch plant is brought up to full operation conforming to ASTM D75. Sample and test coarse FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
54 OF 75
aggregate each 400 cubic yards of concrete. The samples shall be taken so that a uniform cross section, accurately representing the materials on the belt or in the bins, is obtained.
4. FINE AGGREGATE: Samples shall be taken as specified for coarse aggregate. Sample and test fine aggregate each 200 cubic yards of concrete. The samples shall be taken for sieve analysis of fine aggregate and specific gravity tests. Samples of sand shall be taken when the sand is moist.
G. STRUCTURAL STEEL:
1. Shop Weld Inspection for Structural Steel, and Steel Fabrications:
AWS Certified Welding Inspector shall visually inspect 100 percent of structural welds and will inspect 25 percent of fillet welds greater than 5/16 inch, 100 percent of butt welds, moment connection welds, and full penetration groove welds by ultra-sonic or magnetic particle inspection. Acceptance Criteria: AWS D 1.1. Paragraph 8.15.1 for visual inspection and Paragraphs 8.15.2.1 and 8.15.2.2 for ultrasonic or magnetic particle inspection.
2. Shop Inspection of High-Strength Bolted Connections: Inspect 100 percent of high-strength bolted connections according to AISC “Specification for Structural Joints Using ASTM A325 or A490 Bolts.” All such bolts shall be fully tensioned unless otherwise noted on the drawings.
3. Materials’ Conformance to Specifications: Testing Laboratory shall sample and test such items to ensure Standard Compliance for any specified steel materials, connection hardware, and details for which mill certificates or other required certificates have not been submitted. Contractor shall pay for the cost of such sampling, additional testing, and reporting.
H. MISCELLANEOUS METALWORK:
Provide sampling and testing requested by Construction Manager or additional testing as requested by Contractor to verify materials proposed for use conform to specification Sections 05 50 00.
I. COATING SYSTEMS:
Provide sampling and testing requested by Construction Manager or additional testing as requested by Contractor to verify materials proposed for use conform to specification Section 10 14 53, Section 10 45 00, and Section 32 17 00.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
55 OF 75
PART 3 – EXECUTION
3.01 FIELD QUALITY CONTROL
A. GENERAL:
Field quality control is defined in Section 01 45 00. This Section provides general guidelines as to the sampling, tests, and inspections required of work in progress or completed in the field and should be considered a minimum. Additional information and requirements are provided in each technical specification Section and those requirements shall control over this Section when in conflict. Absence of a test, inspection or requirement listed herein from a subsequent specification Section does not relieve the Testing Laboratory or the Contractor from their respective responsibilities specified in this Section.
B. REFERENCE STANDARDS IN OTHER SECTIONS:
Codes, standards, and other references called out below, but which are not listed in paragraph 1.02 are described in other specification Sections and not repeated herein.
C. EARTHWORK AND FILL:
1. GENERAL: The Construction Manager will coordinate the taking of samples and making tests to check compliance with these specifications. The Contractor shall remove surface material at locations designated by the Construction Manager and provide such assistance as necessary for sampling and testing. The Construction Manager may direct the Contractor to construct inspection trenches in compacted or consolidated backfill to determine that the Contractor has complied with these specifications. Payment for inspection trenches shall be as specified in paragraph 01 45 00 –
1.04(7).
2. Subgrade Preparation and Compaction: Verify depth of scarification, moisture content is within optimal limits for compaction, and degree of compaction achieved. Frequency of testing shall generally conform to 25 foot maximum spacing for strip footings, each isolated pad footing, every 900 square feet for slabs and mat foundations, or as directed by the Construction Manager in light of actual geometry and conditions extent.
3. Structure Fill: Verify material provided, lift thickness, and compaction density. Frequency of sampling and testing shall be the same as for Subgrade Preparation and Compaction.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
56 OF 75
4. Structure Backfill: Verify material provided, lift thickness, and compaction density. Frequency of sampling and testing shall be as directed by the Construction Manager but not less than every 2 feet vertical lifts and every 1600 square feet of filled area.
5. Other Fill Materials: Verify material used, lift thickness, and compaction density. Frequency of sampling and testing shall be as directed by the Construction Manager.
D. PAVING:
1. EARTHWORK AND BASE AGGREGATE: Provide sampling and
testing same as Fill described above and specified in Section 32 00
00. Frequency shall conform to Asphalt Concrete Pavement, below.
2. HOT MIX ASPHALT PAVEMENT: Sample and test pavement
thickness and installation per Caltrans Standard Specifications.
Thickness verification shall be made at a frequency not to exceed 1600 square feet of roadway or parking zones or as directed by the Construction Manager.
3. SITEWORK CONCRETE AT PAVEMENT: Sitework concrete at
pavement consists of curbs, gutters, monolithic curb/sidewalk, inlet structures, catch basins, and other concrete construction in contact with paving or necessary for a complete paving job but not associated with buildings or structural work controlled by the IBC.
Testing Laboratory shall conduct sampling and testing the same as specified for cast-in-place concrete in Section 32 00 00, except strength cylinder testing shall occur at one-half the frequency (placing rate) as for structural concrete.
4. Provide Special Inspection for wedge anchors, undercut anchors, adhesive anchors, epoxy anchors, and all other anchoring systems installed in hardened concrete as required by that product’s ICBO Evaluation Report, or equivalent.
5. Site Inspection of Structural Anchor Bolts: Visually inspect all structural anchor bolts for grade, diameter, embedment, geometry, or type (“J” bolt or hex-head), quantity, and general location.
Contractor shall assume all responsibility for detailed dimensions locating each individual bolt, each bolt group in total, and locations of bolts within each group (template).
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
57 OF 75
E. GROUT:
1. CEMENTITIOUS GROUT FOR STRUCTURAL BEARING: Visually
inspect all column baseplates, and grouted zone between structural struts/beams and their supporting wall elements. Determine complete fill beneath baseplate by tapping with hammer and noting hollow reports. Verify grout conforms to specification by observing empty bags, which Contractor shall leave visible adjacent to area used until inspection complete.
2. EPOXY GROUT FOR EQUIPMENT BASES: Provide inspection
conforming to applicable specification Sections and their reference standards, details on the Drawings, and the requirements of the epoxy grout manufacturer.
F. STRUCTURAL STEEL:
1. SITE WELD INSPECTION FOR STRUCTURAL STEEL AND STEEL
FABRICATIONS: Visually inspect 100 percent of structural welds.
Inspect 25 percent of fillet welds greater than 5/16 inch, 100 percent of butt welds, moment connection welds, and complete penetration groove welds by ultra-sonic or magnetic particle inspection.
2. ACCEPTANCE CRITERIA: AWS D 1.1. Paragraph 8.9 for visual inspection and paragraphs 8.13 for ultra-sonic and 18.14.4 for magnetic particle inspection.
3. FIELD INSPECTION OF HIGH-STRENGTH BOLTED
CONNECTIONS: Inspect 100 percent of high-strength bolted connections according to AISC “Specification for Structural Joints Using ASTM A325 or A490 Bolts.” All such bolts shall be fully tensioned unless otherwise noted on the drawings.
4. BEND TESTS: Perform bend test on 10 percent of welded shear connectors. Modify test method and frequency if alternate (nonwelded) shear connectors utilized by Contractor.
G. MISCELLANEOUS METALWORK AND GUARDRAILING:
1. MISCELLANEOUS METALWORK: Provide field inspections and testing if requested by Construction Manager for the work specified in Section 05 50 00. Sampling and testing shall conform to the applicable Reference Standard or Code listed in that section.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
58 OF 75
H. COATING SYSTEMS:
1. COATING SYSTEMS: Provide inspection as requested by
Construction Manager, and additional inspections as requested by Contractor.
3.02 EVALUATION AND CORRECTION
A. EVALUATION:
Satisfactory completion of work will be judged on results of laboratory, shop, and site tests and inspections.
B. CORRECTIONS:
If results of tests and inspections indicate work is below requirements of Contract Documents, that portion of work is defective and shall be repaired or replaced by the Contractor at no additional expense to the Owner by methods specified in each material or system’s Section. Corrective action shall continue until such work meets the requirements of the Contract Documents.
3.03 SCHEDULE OF INSPECTIONS AND TESTS
Form A below shall be used to coordinate sampling and testing provided by Testing Laboratory, Construction Manager, Contractor, and other parties, if any. Testing Laboratory shall fill out Form A with anticipated inspections, sampling, and testing, submit for review by Construction Manager and for information to Contractor, and revise as directed. After receipt of Testing Laboratory’s Form A submittal, Contractor shall submit Form A to identify sampling and testing requested for submittal preparation, and with an allowance for additional inspections. Such allowance shall not be less than five percent (5 percent) of the anticipated Field Quality Control budget for the Testing Laboratory, but shall not contractually commit Contractor to such expenditure, unless additional inspections requested and then only to their extent.
Form A: Anticipated sampling, testing, and inspections by Testing Laboratory and Contractor. Prepared by ___ Testing Laboratory ___ Contractor (check one).
Electronic version available upon request. Expand each cell as necessary to provide a complete scope description.
Specification Section
Source Quality
Control
Field Quality
Control
03 30 00 Cast-in-Place Concrete
05 50 00 Metal Fabrications
10 14 53 Traffic Signs
10 45 00 Aluminum Signs
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
59 OF 75
31 20 00 Earth Moving
32 12 00 Flexible Paving
32 17 00 Paving Specialties
3.04 FINAL LABORATORY REPORT:
A final report, prepared by the testing laboratory, shall be provided at the completion of all concreting. This report shall summarize the findings concerning concrete used in the project and provide totals of concrete used by class and structure. Final quality control charts for compressive strength tests for classes of concrete specified in each major structure shall be included. The report shall also include the concrete batch plant's coefficient of variation and standard deviation results for each class of concrete as determined in accordance with ACI 214.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
60 OF 75
SECTION 01 55 26
TEMPORARY TRAFFIC CONTROL
PART 1 – GENERAL
1.01 DESCRIPTION
Work covered in this section consists of all labor, materials, and equipment required to provide adequate traffic control and regulation through construction areas and street affected by the work.
1.02 QUALITY ASSURANCE
A. QUALIFICATIONS OF WORKERS:
Provide Sufficient Skilled workers and supervisors who shall be present at all times during execution of this portion of the work and shall be thoroughly familiar with traffic regulations, permits, etc., and the materials and techniques specified.
B. CODES AND STANDARDS:
1. Where reference is made to the State Standard Specifications, reference shall mean State of California, Department of Transportation, Standard Specifications, latest edition.
2. Lights, flags, and other warning and safety devices for street and highway work shall conform to the requirements set forth in the current “Manual of Traffic Controls for Construction and Maintenance Work Zones,” issued by the California State Department of Transportation.
1.03 TRAFFIC CONTROL PLAN AND PERMITS
The Contractor shall submit a complete traffic control plan indicating how construction will be sequenced and traffic will be handled during construction. The Construction Manager will review this plan for conformance to the Specifications and to ensure adequate thought has gone into the handling of traffic. The plan shall clearly identify work which will interfere with traffic on public roadways, and the estimated duration of work.
This plan shall be in conformance with the Contractor’s schedule.
Contractor shall obtain encroachment permits at his own expense for any work or traffic control to be performed in public roads. Permit is not required when road is owned and controlled by this project’s Owner.
The Contractor is to work within in the requirements set forth in the Caltrans Encroachment Permit for the traffic devices, detour signage, and CMS boards placed within the Caltrans ROW.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
61 OF 75
1.04 PRODUCT HANDLING
No material or equipment shall be stored where it will interfere with the free and safe passage of public traffic. At the end of each day’s work and at other times when construction operations are suspended for any reason, Contractor shall remove all equipment and other obstructions from that portion of the roadway open for use by the public traffic.
PART 2 – PRODUCTS
2.01 EQUIPMENT
Contractor shall furnish, erect, and maintain, at his or her expense and without cost to the Owner, such fences, barricades, lights and signs, and other devices as are necessary to prevent accidents or damage or injury to the public. Contractor shall also furnish such flag persons and guards as are necessary to give adequate warning to traffic of any dangerous condition to be encountered. Equipment shall be furnished and kept clean and in good repair by the Contractor at his own expense.
PART 3 – EXECUTION
3.01 TRAFFIC CONTROL
A. MAINTAINING TRAFFIC
Contractor shall expedite the passage of public traffic through and around the work.
The Contractor shall furnish and install signs, detours, lights, flares, barricades, and shall furnish flag persons and other facilities for the convenience and direction of public traffic.
The cost of maintaining traffic, including conforming with the requirements stated herein, furnishing such signs, detours, lights, flares, barricades, flag persons and other facilities shall be considered as part of the contract price and no extra payment will be made for such.
B. PUBLIC CONVENIENCE
1. Contractor’s operation shall be conducted so that they offer the least possible obstruction and inconvenience to the public. Contractor shall have under construction no greater amount of work than can be executed properly with due respect to the rights of the public.
Contractor shall provide personal advance notice to each affected resident informing them of impending work and provide ample time to remove vehicles and estimated time of driveway closure.
2. Spillage resulting from hauling or ditching operations along or across any public traveled way shall be removed daily.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
62 OF 75
3. Construction operation shall be conducted in such a manner as to cause as little inconvenience as possible to abutting property owners and tenants. Convenient access to driveways, houses, and buildings along the line of the work shall be maintained and temporary approaches to crossing or intersecting streets shall be provided and kept in good condition.
C. PUBLIC SAFETY
1. Whenever the Contractor’s operations create a condition hazardous to the public, Contractor shall furnish, erect, and maintain such fences, barricades, lights, signs, and other devices as are necessary to prevent accidents or damage or injury to the public.
2. Should the Contractor appear to be neglectful or negligent in furnishing warning and protective measures as above specified, the Construction Manager may direct attention to the existence of hazard, and the necessary warning and protective measures shall be furnished and installed by the Contractor at Contractor’s expense, without cost to the Owner. Should the Construction Manager point out any inadequacy or warning and protective measures, such action on the part of the Construction Manager shall not relieve the Contractor from responsibility for public safety or abrogate Contractor’s obligation to furnish and pay for these devices.
D. DETOURS
Detours shall comply with conditions issued with the Encroachment Permit.
E. TRAFFIC CONTROL PLAN SUBMITTAL
A conceptual Traffic Control Plan has been included in the Project Plans.
The Final Traffic Control Plan shall be consistent with the conceptual Traffic Control Plan shown on the Project Plans, Standard Plans and the “Manual of Traffic Controls for the Construction and Maintenance in Work Zones”. The plan shall show the details of, and designate, all signs, barricades, marking and other traffic control devices the Contractor will use to maintain the passage of public traffic (including pedestrians) through, around and within the project site during construction. The plan shall demonstrate how access to all properties will be maintained at all times during construction. The plan shall describe any detours to be created, streets to be closed, lane closures, and the anticipated maximum traffic delays due to temporary road or lane closures. The City will approve, conditionally approve, or reject the submitted plan within five (5) business days.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
63 OF 75
The Contractor shall submit a traffic control plan indicating the preferred method of construction and traffic control plan which complies with these Specifications. Before closing any street to through traffic, the Contractor shall obtain prior approval from the Construction Manager 14 days in advance of closure. Street closures and detours shall allow for access to public facilities and shall allow for passage of emergency vehicles.
By noon each Monday, the Contractor shall submit a written schedule of planned closures for the following week period, defined as Friday noon through the following Friday noon. The closure schedule shall show the locations and times when the proposed closures are to be in effect. The Contractor will be notified of disapproved closures or closures that require coordination with other parties as a condition of approval, by Wednesday noon. Traffic closure information shall be included in the weekly Public Information notices required by Section 01 00 00, “General Requirements”.
The Traffic Control Plan shall describe short term traffic control measures for the work along Front Street, K Street, and Play Street. Attention is directed to Section 7-1.03, “Public Convenience,” and Section 7-1.04 “Public Safety” of the Caltrans Standard Specifications. Nothing in these Special Provisions shall be construed as relieving the Contractor from the responsibilities specified in these sections.
The Traffic Control Plan shall be updated or revised within five (5) working days of the Engineer’s written request to do so.
F. NOTICES:
Contractor shall expedite the passage of public traffic through and around the work.
The Contractor shall furnish and install signs, detours, lights, flares, barricades, and shall furnish flag persons and other facilities for the convenience and direction of public traffic.
The costs of maintaining traffic, including conforming with the requirements stated herein; public notification; and furnishing such signs, detours, lights, flares, barricades, flag persons and other facilities shall be considered in the total bid.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
64 OF 75
SECTION 01 56 39
TEMPORARY TREE AND PLANT PROTECTION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section includes general protection and pruning of existing trees and plants that are affected by execution of the Work, whether temporary or permanent construction.
B. Related Requirements:
1. Section 01 50 00 "Temporary Facilities and Controls" for temporary site fencing.
2. Section 31 10 00 "Site Clearing" for removing existing trees and shrubs.
3. Section 31 20 00 "Earth Moving"
1.3 DEFINITIONS
A. Caliper (DBH): Diameter breast height; diameter of a trunk as measured by a diameter tape at a height 54 inches above the ground line.
B. Plant-Protection Zone: Area surrounding individual trees, groups of trees, shrubs, or other vegetation to be protected during construction and indicated on Drawings.
C. Tree-Protection Zone: Area surrounding individual trees or groups of trees to be protected during construction and indicated on Drawings.
D. Vegetation: Trees, shrubs, groundcovers, grass, and other plants.
1.4 ACTION SUBMITTALS
A. Product Data: For each type of product.
B. Shop Drawings:
1. Include plans, elevations, sections, and locations of protection-zone fencing and signage, showing relation of equipment-movement routes and material storage locations with protection zones.
2. Detail fabrication and assembly of protection-zone fencing and signage.
3. Indicate extent of trenching by hand or with air spade within protection zones.
C. Samples: For each type of the following:
1. Wood Chip Mulch: 1-quart volume of wood chip mulch; in sealed plastic bags labeled with composition of materials by percentage of weight and source of mulch.
2. Organic Mulch: 1-quart volume of wood chip mulch; in sealed plastic bags labeled with composition of materials by percentage of weight and source of mulch.
3. Protection-Zone Fencing: Assembled Samples of manufacturer's standard size made from full-size components.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
65 OF 75
4. Protection-Zone Signage: Full-size Samples of each size and text, ready for installation.
D. Tree Pruning Schedule: Written schedule detailing scope and extent of pruning of trees to remain that interfere with or are affected by construction.
1. Species and size of tree.
2. Location on site plan. Include unique identifier for each.
3. Reason for pruning.
4. Description of pruning to be performed.
5. Description of maintenance following pruning.
1.5 INFORMATIONAL SUBMITTALS
A. Qualification Data: For arborist and tree service firm.
B. Certification: From arborist, certifying that trees indicated to remain have been protected during construction according to recognized standards and that trees were promptly and properly treated and repaired when damaged.
C. Maintenance Recommendations: From arborist, for care and protection of trees affected by construction during and after completing the Work.
D. Existing Conditions: Documentation of existing trees and plantings indicated to remain, which establishes preconstruction conditions that might be misconstrued as damage caused by construction activities.
1. Use sufficiently detailed photographs or video recordings.
2. Include plans and notations to indicate specific wounds and damage conditions of each tree or other plants designated to remain.
E. Quality-control program.
1.6 QUALITY ASSURANCE
A. Arborist Qualifications: Certified Arborist as certified by ISA.
B. Tree Service Firm Qualifications: An experienced tree service firm that has successfully completed temporary tree and plant protection work similar to that required for this Project and that will assign an experienced, qualified arborist to Project site during execution of the Work.
C. Quality-Control Program: Prepare a written program to systematically demonstrate the ability of personnel to properly follow procedures and handle materials and equipment during the Work without damaging trees and plantings. Include dimensioned diagrams for placement of protection zone fencing and signage, the arborist's and tree-service firm's responsibilities, instructions given to workers on the use and care of protection zones, and enforcement of requirements for protection zones.
1.7 FIELD CONDITIONS
A. Do not store equipment or allow access within protection zones as indicated on Drawings. The following practices are prohibited within protection zones:
1. Storage of construction materials, debris, or excavated material.
2. Cleaning of materials or equipment.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
66 OF 75
3. Moving or parking vehicles or equipment.
4. Foot traffic.
5. Erection of sheds or structures.
6. Impoundment of water.
7. Excavation or other digging unless otherwise indicated.
8. Attachment of signs to or wrapping materials around trees or plants.
B. Do not direct vehicle or equipment exhaust toward protection zones.
C. Prohibit heat sources, flames, ignition sources, and smoking within or near protection zones and wood chip mulch.
D. Keep trees free of nails, screws, fasteners or other devices.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Wood Chip Mulch: Free from deleterious materials and suitable as a top dressing for trees and shrubs, consisting of one of the following:
1. Type: Shredded hardwood
2. Size Range: 3 inches maximum, 1/2 inch minimum
3. Color: Natural.
B. Protection-Zone Fencing: Fencing fixed in position and meeting one of the following requirements: Previously used materials may be used when approved by Owner's Representative.
1. Plastic Protection-Zone Fencing: Plastic construction fencing constructed of high-density extruded and stretched polyethylene fabric with 2-inch maximum opening in pattern and weighing a minimum of 0.4 lb/ft.; remaining flexible from minus 60 to plus 200 deg F; inert to most chemicals and acids; minimum tensile yield strength of 2000 psi and ultimate tensile strength of 2680 psi; secured with plastic bands or galvanized-steel or stainless-steel wire ties; and supported by tubular or T-shape galvanized-steel posts spaced not more than 96 inches apart.
a. Height: 48 inches
b. Color: High-visibility orange, nonfading.
C. Protection-Zone Signage: Shop-fabricated, rigid plastic or metal sheet with attachment holes prepunched and reinforced; legibly printed with nonfading lettering and as follows:
1. Size: As shown on Drawings
2. Lettering: 3-inch-high minimum, black characters on white background.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Erosion and Sedimentation Control: Examine the site to verify that temporary erosion- and sedimentation-control measures are in place. Verify that flows of water redirected from construction areas or generated by construction activity do not enter or cross protection zones.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
67 OF 75
B. Prepare written report, endorsed by arborist, listing conditions detrimental to tree and plant protection.
3.2 PREPARATION
A. Locate and clearly identify trees, shrubs, and other vegetation to remain or to be relocated. Tie a 1-inch blue vinyl tape around each tree trunk at 54 inches above the ground.
B. Protect tree root systems from damage caused by runoff or spillage of noxious materials while mixing, placing, or storing construction materials. Protect root systems from ponding, eroding, or excessive wetting caused by dewatering operations.
C. Tree-Protection Zones: Mulch areas inside tree-protection zones and other areas indicated. Do not exceed indicated thickness of mulch.
1. Apply 4-inch uniform thickness of wood chip mulch unless otherwise indicated. Do not place mulch within 6 inches of tree trunks.
3.3 PROTECTION ZONES
A. Protection-Zone Fencing: Install protection-zone fencing along edges of protection zones before materials or equipment are brought on the site and construction operations begin in a manner that will prevent people from easily entering protected areas except by entrance gates. Construct fencing so as not to obstruct safe passage or visibility at vehicle intersections where fencing is located adjacent to pedestrian walkways or in close proximity to street intersections, drives, or other vehicular circulation.
B. Protection-Zone Signage: Install protection-zone signage in visibly prominent locations in a manner approved by Owner's Representative. Install one sign spaced approximately every 20 feet on protection-zone fencing, but no fewer than four signs with each facing a different direction.
C. Maintain protection zones free of weeds and trash.
D. Maintain protection-zone fencing and signage in good condition as acceptable to Owner's Representative and remove when construction operations are complete and equipment has been removed from the site.
1. Do not remove protection-zone fencing, even temporarily, to allow deliveries or equipment access through the protection zone.
2. Temporary access is permitted subject to preapproval in writing by arborist if a root buffer effective against soil compaction is constructed as directed by arborist. Maintain root buffer so long as access is permitted.
3.4 EXCAVATION
A. General: Excavate at edge of protection zones and for trenches indicated within protection zones according to requirements in Section 312000 "Earth Moving" unless otherwise indicated.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
68 OF 75
B. Trenching within Protection Zones: Where utility trenches are required within protection zones, excavate under or around tree roots by hand or with air spade, or tunnel under the roots by drilling, auger boring, or pipe jacking. Do not cut main lateral tree roots or taproots; cut only smaller roots that interfere with installation of utilities. Cut roots as required for root pruning. If excavating by hand, use narrowtine spading forks to comb soil and expose roots.
C. Do not allow exposed roots to dry out before placing permanent backfill. Provide temporary earth cover or pack with peat moss and wrap with burlap. Water and maintain in a moist condition. Temporarily support and protect roots from damage until they are permanently relocated and covered with soil.
3.5 ROOT PRUNING
A. Prune tree roots that are affected by temporary and permanent construction if unavoidable. Prune as follows:
1. Cut roots manually by digging a trench and cutting exposed roots with sharp pruning instruments; do not break, tear, chop, or slant the cuts. Do not use a backhoe or other equipment that rips, tears, or pulls roots.
2. Cut Ends: Do not paint cut root ends
3. Temporarily support and protect roots from damage until they are permanently redirected and covered with soil.
4. Cover exposed roots with burlap and water regularly.
5. Backfill as soon as possible according to requirements in Section 312000 "Earth Moving."
B. Root Pruning at Edge of Protection Zone: Prune tree roots 12 inches outside of the protection zone by cleanly cutting all roots to the depth of the required excavation.
3.6 CROWN PRUNING
A. Prune branches that are affected by temporary and permanent construction. Prune branches as directed by arborist.
1. Prune to remove only injured, broken, dying, or dead branches unless otherwise indicated. Do not prune for shape unless otherwise indicated.
2. Do not remove or reduce living branches to compensate for root loss caused by damaging or cutting root system.
3. Pruning Standards: Prune trees according to ANSI A300 (Part 1) B. Unless otherwise directed by arborist and acceptable to Owner's Representative, do not cut tree leaders.
C. Cut branches with sharp pruning instruments; do not break or chop.
D. Do not paint or apply sealants to wounds.
E. Provide subsequent maintenance pruning during Contract period as recommended by arborist.
F. Chip removed branches and spread over areas identified by Owner's Representative.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
69 OF 75
3.7 FIELD QUALITY CONTROL
A. Inspections: Engage a qualified arborist to direct plant-protection measures in the vicinity of trees, shrubs, and other vegetation indicated to remain and to prepare inspection reports.
3.8 REPAIR AND REPLACEMENT
A. General: Repair or replace trees, shrubs, and other vegetation indicated to remain or to be relocated that are damaged by construction operations, in a manner approved by Owner's Representative.
1. Submit details of proposed pruning and repairs.
2. Perform repairs of damaged trunks, branches, and roots within 24 hours according to arborist's written instructions.
3. Replace trees and other plants that cannot be repaired and restored to fullgrowth status, as determined by Owner's Representative.
B. Trees: Remove and replace trees indicated to remain that are more than 25 percent dead or in an unhealthy condition before the end of the corrections period or are damaged during construction operations that Owner's Representative determines are incapable of restoring to normal growth pattern.
1. Small Trees: Provide new trees of same size and species as those being replaced for each tree.
2. Large Trees: Provide new tree(s) in quantity and caliper size for each tree being replaced that measures more than 4 inches in caliper size. Total DBH replaced must equal DBH of tree damaged.
a. Species: As selected by Owner's Representative
b. Plant replacement trees in location as directed by Owner’s Representative.
3. Plant and maintain new trees as specified in Section 329300 "Plants."
3.9 DISPOSAL OF SURPLUS AND WASTE MATERIALS
A. Disposal: Remove excess excavated material, displaced trees, trash, and debris and legally dispose of them off Owner's property.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
70 OF 75
SECTION 01 57 23
WATER POLLUTION PREVENTION
PART 1 – GENERAL
The work to be done under this section includes the furnishing of all labor, materials, equipment, tools, and incidentals as required to prevent the pollution of surface or groundwater from the effects of construction of the Project. Contractor shall comply with the Construction General Permit Order 2009-0009-DWQ.
PART 2 – PRODUCTS
The City requires a Storm Water Pollution Prevention Plan (SWPPP) for this Project by a qualified QSD per the statewide General Storm Water Permit requirements. All reporting and inspections of the SWPPP will be performed by the Contractor. The attached and enclosed SWPPP are for suggestion purposes only. The City is not providing support or direction as how to comply with Permitting.
PART 3 – EXECUTION
The Contractor will provide all labor, materials, tools, equipment, and necessary incidentals to implement the Storm Water Pollution Prevention Plan (SWPPP) and the Erosion and Runoff Control Plan and as otherwise necessary to prevent surface water or groundwater pollution from the effects of the Project construction. Contractor shall have a qualified SWPPP Practitioner overseeing the implementation of the SWPPP in accordance with the statewide general permit.
Contractor shall upload all required reports, submittals, another required documentation in accordance with the statewide general permit to the SMARTS system.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
71 OF 75
SECTION 01 71 33
PROTECTION OF PROPERTY
PART 1 – GENERAL
The work to be done under this section shall include the furnishing of all materials, labor, tools, equipment, and necessary incidentals as required to protect public and private property during construction and, if necessary, restore same if damaged.
PART 2 – PRODUCTS
Contractor must submit a Building Protection Plan for any building within a horizontal distance of double the depth of any excavation. (For example, for an excavation of 12 feet, a building 24 feet or less from the excavation must have a Building Protection Plan). The plan will describe how the excavation will be made and backfilled to prevent any horizontal or vertical movement that could potentially damage the building, and must include, at a minimum the following:
1. method and equipment to excavate,
2. detailed plans of shoring method,
3. detailed plans of any specific support, bracing or underpinning of the building,
4. description of method of backfilling,
5. description of shoring removal,
6. description of method of monitoring movement of the building.
The City will approve, conditionally approve, or reject the submitted plan within five (5) business days of receipt. The City’s approval of the plan will not relieve the Contractor of his or her full responsibility for any damage done as a result of the project.
No Building Protection Plan or Foundation Monitoring is required where the depth of excavation does not exceed 6 feet below grade. This does not relieve the Contractor from his responsibility to protect property or make repairs to damaged property.
PART 3 – EXECUTION
3.01 BUILDINGS
A. No excavation may proceed within 100 feet of a building requiring a Building Protection Plan until said plan has been approved. Neither may any excavation proceed until all monitoring benchmarks have been set and preexcavation lines and/or grades determined.
B. Buildings must be monitored daily while excavation, backfilling and compaction work is taking place within 50 feet of the building. After FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
72 OF 75
completion of compaction, monitoring must continue on a monthly basis for one year after project completion. Monitoring must be performed by a licensed Land Surveyor or Registered Civil Engineer. Written field notes must be kept of the monitoring and copies provided the City upon request.
C. The Contractor will be liable for any damage to any building and must hold the City harmless from any liability or expense for injury, damage, or repair to same.
D. Contractor will be responsible for repairing any damage to existing buildings caused by his operations. The Engineer will determine the extent of the damage and the method of repair.
3.02 MISCELLANEOUS
All dewatering, excavation, shoring, bracing, backfilling, compaction, and removal of dewatering system must proceed in accordance with the approved plan.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
73 OF 75
SECTION 01 74 23
FINAL CLEANING
PART 1 - GENERAL
A. At the completion of work and immediately prior to final inspection, cleaning of the entire project shall be accomplished according to the following provisions:
1. The Contractor shall thoroughly clean, sweep, wash, and polish all work and equipment provided under the contract including finishes. The cleaning shall leave the structures and site in a complete and finished condition to the satisfaction of the Construction Manager.
2. All subcontractors shall similarly perform, at the same time, an equivalent thorough cleaning of all work and equipment provided under their contracts.
3. The Contractor shall remove all temporary structures and all debris, including all nails, dirt, sand, gravel, rubbish, and waste material.
4. Should the Contractor not remove rubbish or debris or not clean the facilities and site as specified, the Owner reserves the right to have the cleaning done at the expense of the Contractor.
5. Only experienced workers or professional cleaners shall be employed for final cleaning.
6. Only cleaning materials recommended by the manufacturer of the surface to be cleaned shall be used.
7. Cleaning materials shall be used only on surfaces recommended by the cleaning material manufacturers.
8. In preparation for substantial completion or occupancy, a final inspection of sight-exposed surfaces, and of concealed spaces, shall be conducted.
9. Grease, dust, dirt, stains, labels, fingerprints, and other foreign materials shall be removed from sight-exposed finished surfaces. Polish surfaces so designated to shine finish.
10. Marred surfaces shall be repaired, patched, and touched up to specified finish, to match adjacent surfaces.
11. Materials shall be handled in a controlled manner with as few handlings as possible. Do not drop or throw materials from heights.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
74 OF 75
B. OWNER OCCUPANCY
As a condition precedent to final acceptance or release of a portion of the facility for use by the Owner, the Contractor and all subcontractors shall thoroughly clean all surfaces to leave same in first-class condition.
C. POST-CONSTRUCTION REPAIRS
The Contractor shall make such minor repairs and alterations as may be necessary to make any structure or component ready for occupancy. This section shall not apply after or to the extent that the Owner has taken possession of a portion of the facilities on which the Contractor has performed work.
D. SITE CLEANUP
1. For all roadway work, the Contractor shall conform the work to acceptable line and grade, as determined by the Engineer. In addition, the Contractor shall have the sidewalks and streets affected by the work swept by a street or sidewalk cleaner as determined by the Construction Manager. Other surfaces of the grounds shall be rake cleaned. The Owner will not authorize final payment until the Contractor has removed all rubble and debris from the street and adjoining work areas, including all temporary storage and parking areas used by the Contractor.
2. The Contractor's use of private property for whatever use regarding this project, such as access, materials and equipment storage, waste disposal, etc., will require a written agreement between the property owner and the Contractor, submitted to the City for approval prior to use of the private property. The agreement shall specifically hold the City harmless, free of any responsibility, resulting from use of the private property.
3. For pipelines, storm sewers, catch basins and manholes, prior to their activation or at the conclusion of the project, the Contractor shall thoroughly clean all of the new pipes by flushing with water for fluid lines. Debris cleaned from the lines shall be removed from the lowest access point. All existing storm drains that will remain in service in the project must also be cleaned.
4. All temporary utility drops, fencing, and water supply outlets shall be removed.
5. All plant gate identification signs, barricades, tools, rubbish collection receptacles and other such items shall be removed by the Contractor.
6. All dust, mud, excavated spoils, and construction debris shall be removed from all roadways, ditches, shoulders and private property. The Contractor's FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C – RE-ISSUE
CONTRACT 2025-1002.33
DIVISION 01
75 OF 75
operations shall not cause any increase in the turbidity of runoff waters as defined and controlled by the California Regional Water Quality Control Board, North Coast Region.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 00 00 – EXISTING CONDITIONS
1 of 2
SECTION 02 00 00
EXISTING CONDITIONS
PART 1 – GENERAL
1.01 RELATED INFORMATION
Related information and requirements are included in the individual Sections of the Specifications and the project Permits.
1.02 INFORMATION ON SITE CONDITIONS
Information obtained by the Engineer regarding site conditions, existing facilities, and similar data are shown on the Plans.
1.03 CONTRACTOR'S RESPONSIBILITIES
A. The Contractor shall satisfy himself as to the nature and location of the work, the general and local conditions, particularly those bearing upon availability of transportation, disposal, handling, and storage of materials, availability of labor, water, electric power, roads, work in sensitive environment and uncertainties of weather, or similar physical conditions at the site, the conformation and conditions of the ground, the character of equipment facilities needed preliminary to and during the prosecution of the work and all other matters which can in any way affect the work or the cost thereof under this contract.
B. The Contractor further shall satisfy himself as to the character, quality, and quantity of surface and subsurface materials to be encountered from inspecting the site, any exploratory work done by the City, as well as from information presented by the Plans and Specifications made a part of this contract. Any failure by the Contractor to acquaint himself with all the available information will not relieve him from responsibility for properly estimating the difficulty or cost of successfully performing the work.
C. The Contractor shall anticipate underground obstructions such as utility lines, concrete, water table, soil conditions and debris. No extra payment will be allowed for the removal, replacement, repair, or possible increased cost caused by underground obstructions. Any such lines or obstructions indicated on the map show only the approximate location and must be verified in the field by the Contractor. The District and Engineer will endeavor to familiarize the Contractor with all known underground obstructions, but this will not relieve the Contractor from full responsibility in anticipating and locating all underground obstructions.
D. The Contractor shall note that heavy truck and equipment operations may cause roadway and parking lot damage in excess of normal usage.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 00 00 – EXISTING CONDITIONS
2 of 2
Damage caused to the streets by Contractor's operations shall be repaired by the contractor at no additional cost to the City. A series of photographs shall be logged by the Contractor for approval by the Engineer to establish existing conditions prior to construction.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 01 00 – MAINTENANCE OF EXISTING CONDITIONS
1 of 3
SECTION 02 01 00
MAINTENANCE OF EXISTING CONDITIONS
PART 1 – GENERAL
1.01 DESCRIPTION
A. Related requirements specified elsewhere:
See Division 01 regarding general conditions specific to the Contract. See also Section 02 00 00 regarding site conditions.
See Plans for the locations of utilities.
1.02 CALIFORNIA ADMINISTRATIVE CODE
A. Section 1540(a)1 of Construction Safety Orders (Title 8) California Administrative Code, Section 1540 states:
1. "Prior to opening an excavation, effort shall be made to determine whether underground installations; i.e., sewer, water, fuel, electric lines, etc., will be encountered and, if so, where such underground installations are located. When the excavation approaches the approximate location of such an installation, the exact location shall be determined by careful probing or hand digging; and, when it is uncovered, adequate protection shall be provided for the existing installation. All known owners of underground facilities in the area concerned shall be advised of proposed work at least 48 hours prior to the start of actual excavation."
B. In line with California's Administrative Code, Section 1540, Contractor shall make the effort to determine the exact location of underground installations.
PART 2 – PRODUCTION – OWNERS
2.01 UTILITIES AFFECTED
A. GENERAL:
Underground Service Alert (USA) North 811 shall be contacted at least 72 hours before any work commences. USA North 811 can be contacted at (800) 642-2444.
B. ELECTRICAL
In the project area, Pacific Power has control of overhead and underground power. Where overhead power service to a structure known to require electrical service does not exist, then underground power FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 01 00 – MAINTENANCE OF EXISTING CONDITIONS
2 of 3
service shall be assumed to exist. Pacific Power can be contacted at (888) 221-7070.
C. WATER SERVICE
City of Crescent City Water/Sewer Department can be contacted at (707) 464-6517.
D. SEWER SERVICE
City of Crescent City Water/Sewer Department can be contacted at (707) 464-6517.
E. ROADS / STREETS / DRAINAGE
The City of Crescent City has jurisdiction over roads, streets, and drainage in the City. City Public Works can be contacted at (707) 464-9506.
F. TELEPHONE
Frontier Communications can be contacted at (541) 269-3375.
G. GAS/PROPANE SERVICE
Blue Star Gas is the provider of in-street buried gas lines. Blue Star Gas can be reached at 541 251-8912.
H. CABLE TELEVISION / INTERNET
Charter Communications (Spectrum) can be contacted at (866) 874-2389. (This is the public-facing customer service number).
PART 3 – EXECUTION
3.01 CONTRACTOR RESPONSIBILITY
A. It may be expected that there will be some variation in location of existing utilities from that as shown on the Plans. Contractor is also hereby notified that there are likely additional irrigation lines in the project area that are not shown on the plans. Actual location can best be determined in the field after pre-marking by the various utilities affected. Contractor is required to contact Underground Services Alert (USA), also known as “USA North 811” before beginning any excavations.
B. The Contractor shall be responsible for determining the location of existing service laterals, irrigation lines, or appurtenances whenever the presence of such utilities on the site of the construction can be inferred from the presence of other visible facilities, such as building, meter and junction boxes, located on or adjacent to the site.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 01 00 – MAINTENANCE OF EXISTING CONDITIONS
3 of 3
C. The Contractor shall promptly notify the Engineer in writing in the event that the Contractor discovers utility facilities not identified by the Engineer in the Contract Plans or Specifications.
D. It should be understood that the various utilities are indicated on the Plans to show only the approximate location and must be verified in the field by the Contractor. It may be expected that there will be variation in location from that as shown on the Plans to the actual location. Actual location can best be determined in the field after pre-marking by the various utilities affected. The various utilities will cooperate with the Contractor to endeavor to familiarize the Contractor with all known underground utilities, obstructions, but this will not relieve the Contractor from assuming full responsibility in anticipating and locating their actual location with respect to utilities which the Contractor must locate and identify under the provisions hereof.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 41 00 – DEMOLITION AND REMOVAL
1 of 7
SECTION 02 05 00
DEMOLITION AND REMOVAL
PART 1 – GENERAL
1.01 DESCRIPTION
A. Demolition consists of furnishing transportation, labor, tools, equipment, and incidentals necessary to demolish items as described in this Specification as well as items as noted on the Drawings.
B. All materials resulting from the demolition work, unless specified otherwise, shall become the property and responsibility of the Contractor for both demolition and disposal. Title to and ownership of all materials to be removed, except as specified otherwise, is vested in the Contractor upon receipt of notice to proceed. The Owner will not be responsible for the condition, loss of, or damage to, such material after notice to proceed is issued.
C. The work includes, but is not strictly limited to:
1. Removal of existing asphalt paving where shown on plans or otherwise required for project completion.
2. Removal of existing concrete sidewalk, curbs, gutters, and similar structures where shown on plans or otherwise required for project completion.
3. Removal of existing buried debris and unsuitable material as shown on plans or otherwise required for project completion.
4. Removal of existing underground utilities where shown on plans or otherwise required for project completion.
5. Locating existing underground utilities not located by USA North 811 or others.
1.02 QUALITY ASSURANCE
A. GENERAL
1. All work shall be performed in accordance with local codes and regulations, applicable state industrial safety provisions, and the requirements of the Occupational Safety and Health Act (OSHA).
2. In addition to complying with all pertinent codes and regulations, comply with the requirements of those
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 41 00 – DEMOLITION AND REMOVAL
2 of 7
insurance carriers providing coverage for thiswork.
3. The Contractor shall alter or rework existing concrete structures as shown and as specified. Generally, when items of equipment and piping are removed, the areas and surfaces from which items were removed shall be left with a neat appearance and finish compatible with surrounding areas, colors, and surfaces. The Contractor shall perform all painting, sanding, grouting, sacking, resurfacing, and other work as necessary to comply with the above requirements.
Prior to structural modifications, all surfaces shall be subject to inspection by the Owner.
4. Miscellaneous cutting, patching, and painting necessitated as a result of visual conditions, and the reworking of abutting surfaces as required to make new work join and match existing surfaces to remain, shall be part of the work under this contract.
5. Prospective Contractors shall visit the job site to ascertain the work required to meet the requirements as shown on the plans and specified herein.
B. OPERATING REQUIREMENTS
1. Demolition shall be performed in such a manner as to not harm adjacent structures, existing landscaping, or natural vegetation. The Contractor shall assume full responsibility for such disturbance. All costs of any such repair, rehabilitation, or modifications shall be borne by the Contractor.
2. When removing materials or portions of existing structures, the Contractor shall take all precautions and use all necessary barriers and other protective devices so as not to damage the structures beyond the limits necessary for the new work, nor to damage the structures or contents by falling or flying debris.
3. Contractor shall contain, remove, and transport debris and rubbish in a manner that will prevent spillage into adjacent areas. Clean up any spillage into adjacent areas as necessary.
1.03 SUBMITTALS
A. Submittals shall be provided in accordance with Section 01 33 00 and shall include the following information:
1. A copy of this specification section, with addendum updates included, with each paragraph check-marked to indicate specification compliance or marked to indicate requested deviations from specification requirements. A check mark () shall denote full FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 41 00 – DEMOLITION AND REMOVAL
3 of 7
compliance with a paragraph as a whole. If deviations from the specifications are indicated, and therefore requested by the Contractor, each deviation shall be underlined and denoted by a number in the margin to the right of the identified paragraph, referenced to a detailed written explanation of the reasons for requesting the deviation. The Construction Manager shall be the final authority for determining acceptability of requested deviations. The remaining portions of the paragraph not underlined will signify compliance on the part of the Contractor with the specifications.
Failure to include a copy of the marked-up specification sections, along with justification(s) for any requested deviations to the specification requirements, with the submittal shall be sufficient cause for rejection of the entire submittal with no further consideration.
2. Equipment to be used.
3. Methods of removal and staging.
4. Environmental measures planned to prevent contamination of groundwater, stormwater, or the Owner’s property during the course of work.
5. Maintenance, fueling, trucking, barging and disposal routes.
6. Anticipated governmental agency coordination and permits.
PART 2 – PRODUCTS (NOT USED)
PART 3 – EXECUTION
3.01 GENERAL
A. Prior to any demolition work, Contractor shall carefully inspect the site and determine the extent of work involved. Report any discrepancy to the Engineer immediately.
B. All work of altering existing structures shall be done at such time and in such manner as will comply with the approved time schedule. So far as possible before any part of the work is started, all tools, equipment, and materials shall be assembled and made ready so that the work can be completed without delay.
C. The Contractor shall cut, repair, reuse, excavate, demolish, or otherwise revise parts of the existing structures, piping, or appurtenances, as indicated on the drawings, herein specified, or necessary to permit completion of the work under this contract.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 41 00 – DEMOLITION AND REMOVAL
4 of 7
D. Where necessary or required for the purpose of making connections, the Contractor shall cut existing pipelines in a manner to provide an approved joint. Where required, weld beads, flanges or couplings shall be provided, as required. The Contractor shall provide suitable plugs, bulkheads, or other means to hold back the flow of water or other liquids, all as required in the performance of the work under this contract.
3.02 DUST AND DEBRIS CONTROL
A. Dust resulting from demolition and removal work shall be controlled to prevent the spread of dust and to avoid creation of a nuisance or hazard in the surrounding area. Refer to Section 01 41 00 for regulatory requirements.
3.03 PROTECTION
A. The Contractor shall protect all electrical and fire protection facilities and utilities where removal of existing materials is necessary to accomplish the work. The Contractor shall provide all necessary labor and material to build barricades and temporary services or connections for electrical, mechanical, and plumbing utilities.
B. The Contractor shall protect all existing utility lines from damage that are made known to the Contractor prior to demolition work and that are not explicitly included in the demolition work. The Contractor shall initiate a “Underground Service Alert” survey to identify all existing utilities.
C. The Contractor shall repair any damage to utility lines caused by the Contractor, as directed by the Construction Manager, at no additional cost to the Owner.
D. Where the public safety is endangered in the area of removal work, barricades for traffic shall be used and advance notice shall be given to the Construction Manager prior to beginning any such work.
E. The Contractor shall protect trees, plant growth, and features designated to remain as final landscaping.
F. The Contractor shall protect survey monuments, elevation benchmarks, and similar existing structures from damage or displacement unless otherwise directed by the Owner.
3.04 USE OF EXPLOSIVES:
The use of explosives of any kind is strictly prohibited.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 41 00 – DEMOLITION AND REMOVAL
5 of 7
3.05 SAW CUTTING
When portions of asphalt pavements and concrete pads are to be removed and later construction is to be connected, edges shall be saw cut, on a neat line at right angles to the curb face.
3.06 COLD PLANE ASPHALT CONCRETE SURFACE
A. GENERAL
Cold Planing shall include all work necessary to remove existing asphalt and/or concrete pavement to a predetermined depth as indicated on the drawings. Planing asphalt concrete pavement shall be performed by the cold planning method. Planing of the asphalt concrete pavement shall not be done with the heater planing method.
B. EQUIPMENT
The machine used for planing shall have performed satisfactory on similar work and shall meet the following requirements herein
1. The planing machine shall be specifically designed and built for the planingof bituminous pavements without the addition of heat.
Cold planing machines shall be equipped with a cutter head not less than 30 inches in width and shall be operated so that no fumes or smoke will be produced.
2. The machine shall be operated in a way so that no fumes or smoke will be produced. The machine shall be capable of removing the paving material next to curbs or gutters and be designed such that the operator thereof can at all times observe the planing operation without leaving the controls.
C. CONSTRUCTION
1. Pavement Removal: Prior to cold planing, on streets to have a uniform depth of the existing surface removed, all utility covers shall be lowered such that the cutting teeth of the planing machine passes over the adjusted lid or frame. Contractor will be responsible for maintaining any temporary asphalt fill material over these facilities until the final paving surface is installed.
2. Temporary Marking: The Contractor shall clearly mark or reference lowered sanitary sewer and water valves in case emergency access is required by the agency responsible for operation of the sewer and water system.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 41 00 – DEMOLITION AND REMOVAL
6 of 7
3. Spatial and Geometric Requirements: The depth, width, and shape of the cut shall be as shown on the typical cross sections or as designated by the Engineer. The final cut shall result in a uniform surface conforming to the typical cross sections. The outside lines of the planed area shall be neat and uniform.
Planing asphalt concrete pavement operations shall be performed without damage to the surfacing to remain in place. Where transverse joints are planed in the pavement at conform lines, no drop-off shall remain between the existing pavement and the planed area when the pavement is opened to public traffic. If asphalt concrete has not been placed to the level of existing pavement before the pavement is to be opened to public traffic a temporary asphalt concrete taper shall be constructed. Asphalt concrete for temporary tapers shall be placed to the level of the existing pavement and tapered on a slope of 1:200
(Vertical:Horizontal) or flatter to the level of the planed area.
4. Air Pollution Control: The Contractor shall take all necessary measures to avoid the dispersion of dust. Attention is directed to Section 7 of the Standard Specifications.
3.07 EXISTING MATERIALS TO BE REMOVED
A. No on-site sale of salvage will be allowed. No removals shall be made from the site by any person other than the Contractor or employees of the Contractor.
B. The Contractor shall not interfere with the use of or access to adjacent facilities.
C. The Contractor shall provide and place bracing and shoring to prevent movement or damage to structures and improvements which are to remain.
Contractor shall locate lines shown on plans that are not marked by “USA”.
The Contractor shall cease operation and notify the Construction Manager immediately if the safety of any facility appears to be endangered. The Contractor shall not resume operations until safe conditions have been restored.
D. Removal work shall be performed in accordance with applicable requirements of authorities having jurisdiction and under the Engineer’s inspection. The Contractor shall have on the work site, copies of applicable extracts of: Construction Safety Orders and General Industrial Safety Orders issued by the State Division of Industrial Safety. The Contractor shall comply with provisions of these and other applicable laws, ordinances, and regulations.
E. Burning of material on site shall not be permitted.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 41 00 – DEMOLITION AND REMOVAL
7 of 7
3.08 SALVAGED ITEMS
The Owner has the right to salvage any items scheduled for removal. The Contractor shall notify the Construction Manager 5 days prior to any salvage or demolition work to determine the disposition of items to be removed. Items the Owner wishes to keep shall be placed at a location specified by the Owner.
The stockpile location is:
Crescent City Corporation Yard
900 10th Street,
Crescent City, CA 95531
3.09 DISPOSITION OF MATERIAL
A. Unless otherwise noted, all materials and equipment to be removed, except for equipment or material listed for salvage, shall become the property of the Contractor, and shall be promptly removed from the property. Under no circumstances shall the Contractor use the Owner’s or adjacent property’s trash receptacles, or dumpsters located at or near the work site for any purpose.
B. If required, materials to be reused or relocated shall be carefully removed and stored to prevent damage and reinstalled as the work progresses.
3.10 CLEAN-UP
A. Debris and rubbish shall be removed and transported in a manner that will prevent spillage onto existing streets or adjacent areas. All debris shall be removed off site at the Contractor’s expense.
B. All applicable federal, state, and local regulations regarding handling and disposal shall be strictly complied with.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 22 10 – TRENCH AND BACKFILL
1 of 8
SECTION 02 22 10
TRENCH EXCAVATION AND BACKFILL
PART 1 – GENERAL
1.01 DESCRIPTION
A. WORK INCLUDED:
The work covered in this Section consists of performing all operations necessary to excavate all earth, regardless of character and subsurface conditions, from the trench or adjacent thereto, and to place stabilization, bedding, cover, water removal, backfill, base, and compaction as shown on the Plans and as specified or as may be ordered by the Engineer.
B. GENERAL INTENT:
1. It is the general intent of these Specifications to specify conduct of the Work in such manner as to cause the general public a minimum of inconvenience with no exposure to unsafe conditions during construction and to provide a trench that will properly support and protect the pipe and have no settlement on improved streets and only minor settlement in other areas where such settlement will not be noticed, or compensation made for any expected settlement.
The degree of compaction and type of material will vary in accordance with type of pipe, and soil and surface conditions.
2. The Contractor shall obtain compaction and install base and temporary paving promptly.
3. If the Contractor does not properly clean up (in the opinion of the Engineer and District) then the Engineer shall have the option of using outside equipment and labor to perform the work and such costs will be withheld from the contract.
4. It is the general intent to use material as shown on the Plans where proper compaction and a stable surface can be obtained.
Stabilization material and import will be provided only where directed by the Engineer.
5. No backfilling shall be done until the installation to be covered has been inspected, tested, and approved for covering. Compaction of backfill shall proceed immediately after backfilling.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 22 10 – TRENCH AND BACKFILL
2 of 8
1.02 QUALITY ASSURANCE
A. QUALIFICATIONS OF WORKMEN:
Provide sufficient skilled workmen and supervisors who shall be present at all times during execution of this portion of the Work and who shall be thoroughly familiar with the type of construction involved and the materials and techniques specified.
B. CODES AND STANDARDS:
1. Testing, when required, will be in accordance with all pertinent codes and regulations and with selected standards of the American Society for Testing and Materials as listed below:
Specific Gravity: ASTM D854
Laboratory Compaction: ASTM D1557, Method A
or C. In-place Density: ASTM D1556 or ASTM
D2922.
Particle Size Analysis of Soils: ASTM D422.
Plastic Limit and Plasticity Index: ASTM
D4318. Soil Classification: ASTM D2487.
In-place Moisture Content: ASTM D3017.
2. Where reference is made to the State Standard Specifications, reference shall mean: State of California, Business and Transportation Agency, Department of Transportation
(Caltrans), Standard Specifications, most recent edition, excluding measurement and payment items.
1.03 GUARANTEES
The Contractor shall guaranty his work against settlement for a period of one year after the Notice of Completion has been filed and shall repair all damage caused by settlement within that time. For the purpose of this Specification, settlement will be deemed to have occurred if the following conditions exist:
A. On paved areas, the depression of 3/8-inch below the average of the sides of the uncut portion shall be deemed a settlement.
B. Along shoulder areas and unpaved portions of the site, a depression of ¾ -inch below the average of the sides of the uncut portion shall be deemed a settlement.
C. Across all fields, pastures, or areas untraveled by automotive equipment, a depression of 1½ inches below the average of the sides of the uncut FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 22 10 – TRENCH AND BACKFILL
3 of 8
portion shall be deemed a settlement. In this regard, any settlement that causes drainage problems or concentration causing water to run along the ditch way shall be subject to correction immediately during the entire guaranty period.
PART 2 – PRODUCTS
2.01 EXCAVATION
Excavation is unclassified. The Contractor shall complete all excavation regardless of type, nature, or condition of the materials encountered. The Contractor shall make his own estimate of the kind and extent of the various materials to be excavated in order to accomplish the work. The Contractor should note specifications for native backfill and determine where excavated material can be used for that purpose.
2.02 STABILIZATION MATERIAL
Stabilization material shall consist of uniformly graded coarse aggregate of which at least 90 percent by weight shall be crushed particles. The percent composition by weight shall conform to the following grading:
SIEVE SIZE PERCENT PASSING
3” 100
1” 0-10
Stabilization material shall be free from excessive dirt or other organic material.
2.03 BEDDING AND COVER MATERIAL
Bedding shall be crushed rock aggregate uniformly graded from No. 4 to ¾-inch particle size. One hundred percent shall pass the ¾-inch sieve and 95% shall be retained on the No. 4 sieve. Material shall have a minimum durability index of
35. Material shall be free of loam, organic material, or vegetable matter. A minimum of 25% by weight shall be crushed particles.
2.04 CRUSHED WASHED STONE
Crushed washed stone shall be 2 inches minus, well graded, free of fines and with not more than 10% passing the ¾” sieve.
2.05 SAND BEDDING AND COVER MATERIAL
Shall have a minimum sand equivalent of 45 and shall be uniformly graded from No. 4 to 200 mesh screen. Not more than 8 percent of the material shall pass the 100-mesh screen. The material may be screened from the 3/4-inch minus gravel bedding and cover noted in paragraph 2.03, providing it meets these specifications.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 22 10 – TRENCH AND BACKFILL
4 of 8
2.06 NATIVE BACKFILL
Shall be selected material excavated from the trench. In all cases it must be capable of compaction to at least the relative compaction required with in-place moisture, must not have a moisture content of 5 percent over optimum if silty or clayey material where it will not provide a stable subsurface. Native material over 6 inches from the pipe may have rocks or stones up to 6 inches in diameter provided they can be incorporated in the trench without bridging.
2.07 STRUCTURE BACKFILL
Shall conform to the State Standard Specifications and shall have a minimum sand equivalent of not less than 20. 100 percent shall pass a 3-inch sieve, 35 to 100 percent shall pass a No. 4 sieve and 20 to 100 percent shall pass the 30- mesh screen. It shall be free from organic matter and unsatisfactory material.
2.08 NATIVE TOPSOIL
Shall be native material collected within the top 12 inches of the original grade.
2.09 IMPORTED BACKFILL
Where specified may be any of the above (2.02 through 2.08) except native material from the immediate area. It shall have a minimum sand equivalent of 30.
One hundred percent shall pass the 3-inch sieve; no more than 80% shall pass the 100-mesh sieve screen. If sand is to be utilized as import, no more than 30% shall pass the 100-mesh screen.
2.10 CLASS II AGGREGATE BASE
Class II aggregate base shall be ¾ inch minus conforming to Section 26 of the State Standard Specifications. This material may be used at the Contractor's option for pipe zone bedding and cover material and as imported backfill.
2.11 DRAIN ROCK
Shall be Class 2 Permeable material and conform to Section 68-2 of the State Standard Specifications.
2.12 RESEEDING WORK REQUIRED
A. The general intent is for the finished worksites to resemble the areas as they existed in the native condition. The restoration is to be accomplished through the implementation of the following efforts.
1. The preservation of the native environment including trees, rocks, and general topographic features through care in planning and workmanship during the construction of the facilities.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 22 10 – TRENCH AND BACKFILL
5 of 8
2. The replacement of physical objects that must be removed for the construction.
3. The provision of a finished site that will provide for the rapid revegetation of areas to their natural site.
B. GENERAL
All cut areas and all fills and all areas through fields or "open areas" shall be fertilized and seeded back to that area where undisturbed material exists. Fertilizing and seeding shall be as follows:
1. Fertilizer, seed mix and mulch shall be subject to the approval of the Engineer and as noted on the plan set.
PART 3 – EXECUTION
3.01 GENERAL
A. The Contractor shall do all excavation of whatever substance is encountered to the lines and grades shown on the Plans. All materials suitable for use as backfill shall be piled in an orderly manner a sufficient distance from the edge of the trench to avoid overloading and to prevent sliding into the trench. The Contractor shall do such grading or work as is necessary to prevent surface water from entering the excavation.
B. No more than 200 feet of open trench shall be excavated in advance of laying the pipe. Not more than 50 feet of excavated trench shall remain un-backfilled at the end of each day's work. The remainder of the trench shall be backfilled, initially compacted, and opened to traffic. All operations shall be carried out in an orderly fashion. Backfilling, compacting, base and cleanup shall be accomplished as sections of the pipe are installed. Traffic through the work area shall be impeded or obstructed as little as possible.
3.02 WIDTH OF TRENCH
A. Except where otherwise specifically permitted, sides of trenches shall be vertical, shored as required, and shall be of uniform width from top to bottom. Trenches for small diameter laterals may be installed in narrow "Ditch-Witch" type of trench.
B. The maximum width of trench measured at the top of the pipe shall not exceed the width allowed for various classifications of pipe or if none are given, they shall not exceed the dimensions shown on the plans.
C. If trench widths exceed those shown on the plans, install all additional stabilization material, bedding, cover, backfill, base, and paving in conformance with these specifications at no FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 22 10 – TRENCH AND BACKFILL
6 of 8
additional cost to the District.
3.03 PAVING REMOVAL
A. Asphalt concrete shall be cut with a suitable tool before excavation.
Cutting with a spade or jackhammer will be allowed as will cutting with a suitable grader-mounted wheel provided that a neat orderly result is accomplished. Breaking of concrete or seal coats with excavation equipment will not be permitted.
B. All edges of asphalt, armor coats or seal coats shall be cut vertically, with a neat, square edge.
C. In all cases existing paving shall be cut out after construction and just prior to final paving, to a point 6 or more inches wider than each side of the trench line.
3.04 GRADE AND ALIGNMENT CONTROL
A. Contractor shall construct the trench to the line and grades as established by the Engineer. Proper allowance shall be made for pipe thickness, bedding material and stabilization material.
B. Any part of the trench excavated below grade shall be backfilled with stabilization or bedding material and compacted to a density equal to the undisturbed trench bottom at Contractor's expense.
C. The pipe shall be accurately centered on alignment and shall be laid neat and true to provide good hydraulic characteristics in keeping with the grade and pipe size specified. The pipe shall be laid to provide a continuous slope so that any air pockets created are relieved with an air release valve.
3.05 SHORING, SHEETING AND BRACING
The Contractor shall furnish and install all shoring, sheeting, and bracing required to support adjacent earth banks and structures for the protection and safety of all personnel working in the trench. All shoring, sheeting, and bracing shall conform to the requirements of the State or local agents having jurisdiction over such matters. Remove shoring, sheeting, and bracing in a manner that will protect the workman and prevent caving of banks and damage to the pipe, excavation, backfill or adjacent property. See specific details elsewhere in these Specifications and in Cal OSHA requirements.
3.06 STABILIZATION
If unstable trench bottoms are encountered, additional excavation shall be performed to the depth ordered by the Engineer. Trench stabilization material shall then be placed up to the bottom plane of the bedding material. See Bid FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 22 10 – TRENCH AND BACKFILL
7 of 8
items for payment if any. If separate payment is authorized as a Bid item, the amounts shall be calculated by the theoretical quantity obtained by multiplying the trench width, up to the maximum widths shown on the Plans times the depth requested times the length, all as authorized by the Engineer.
3.07 TRENCH BACKFILL IN THE PIPE ZONE
A. The Contractor shall backfill the pipe zone with the bedding and cover material specified to the dimensions shown on the Plans. Bedding material shall be added to the trench so that it will extend up on the pipe to 1/3 of its depth. The trench shall then be final graded by hand to provide a secure bedding full length with hand excavations made for bells or collars. Additional bedding shall then be installed and the sides of the pipes tamped to not less than 90 percent compaction to secure full length bedding and proper pipe wall support. After this, cover material shall be added and mechanically compacted to a relative compaction not less than 90 percent.
B. In trench bottoms that are wet with running water or rapidly infiltrating water, gravel bedding shall be used. In deep or wide trenches where pipe support is critical or near the allowable strength of the pipe, gravel bedding shall be used. In dry trenches or where pipe support is not as critical, sand bedding material may be used. These materials must be provided up to just over the mid-point of the pipe or in critical areas (deep-wide) shall be carried up to a point of two-thirds of the pipe depth.
3.08 TRENCH BACKFILL
A. CLASS 2 AGGREGATE BASE:
Class 2 Aggregate Base shall be compacted to relative compaction not less than 90 percent relative compaction in gravel road areas, and 95 percent relative compaction under paved area (flexible or rigid pavement).
B. NATIVE:
Trench shall be backfilled with native material which may be placed by machine. Materials may be settled by, mechanical tamping, grading or other approved method, taking care not to float the pipe, all depending on existing soil conditions. When the topsoil has been stripped this material shall be placed in the upper portion of the trench. Top of the trench will be neatly finished as detailed on the Plans with a crown to accommodate future settlement in the areas where this can be allowed due to lack of traffic, drainage problems, unsightliness or the like.
Native backfill shall be compacted to a relative compaction of not FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 22 10 – TRENCH AND BACKFILL
8 of 8
less than 90 percent.
3.09 JETTING
Jetting shall not be allowed.
3.10 COMPACTION
All compaction shall be to the densities specified. Pipe zone materials (bedding and cover materials) shall be compacted to a relative density of not less than 90 percent. The depth of each lift shall not exceed 12 inches of loose material and will be limited to such depth as can be compacted to the specified density with the equipment being used. The top of the trench shall be final compacted (where necessary) by the use of a pneumatic or drop hammer taking care not to damage sewer line or other utilities.
3.11 TESTING
A. Relative compaction shall be the densities specified hereinbefore. In clay materials of higher moisture content dry densities shall be used.
B. The District’s Testing Laboratory will make all tests when advised by the Contractor that in his opinion sufficient densities have been achieved. Engineer shall determine the number and location of tests required. Contractor shall furnish a backhoe and operator upon request to the Testing Laboratory, at no cost to the District. Compaction Testing shall occur only if required by the District and be certified by the Contractor as meeting Project requirements.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 30 00 – EARTHWORK
1 of 8
SECTION 02 30 00
EARTHWORK
PART 1 - GENERAL
1.01 SUMMARY
A. SECTION INCLUDES:
Clearing, grubbing, excavation, aggregate materials for fill and grading purposes, compaction and grading necessary or required for the construction of the work as covered by these Specifications and indicated on the Drawings. Clearing shall normally be performed in advance of other construction operations in accordance with requirements of these Specifications. The excavation shall include, without classification, the removal and disposal of all materials of whatever nature encountered, including water and all other obstructions that would interfere with the proper construction and completion of the required work.
B. RELATED SECTIONS:
1. Section 02 05 00 Demolition and Removal
2. Section 02 22 10 Trench Excavation and Backfill
1.02 REFERENCES
The publications listed below form a part of this specification to the extent referenced. The publications are referred to in the text by basic designation only.
American Society for Testing and Materials (ASTM) Publications:
ASTM C 136 (1996a) Sieve Analysis of Fine and Coarse Aggregates ASTM D 422 (1963; R 1998) Particle-Size Analysis of Soils ASTM D 1140 (1997) Amount of Material in Soils Finer than the No. 200 (75-micrometer) Sieve
ASTM D 1557 (1998) Laboratory Compaction Characteristics of Soil Using Modified Effort 56,000 ft-lbf/cu. ft.
ASTM D 2487 (1998) Classification of Soils for Engineering Purposes (Unified Soil Classification System)
ASTM D 2922 (1996) Density of Soil and Soil-Aggregate in Place by Nuclear Methods (Shallow Depth)
ASTM D 3017 (1988; R 1996el) Water Content of Soil and Rock in Place by Nuclear Methods (Shallow Depth)
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 30 00 – EARTHWORK
2 of 8
ASTM D 4318 (1998) Liquid Limit, Plastic Limit, and Plasticity Index of Soils
1.03 SUBMITTALS
A. Submit in accordance with Section 01 33 00.
B. SUBMIT THE FOLLOWING:
1. Contractors Testing Laboratory Qualifications: Submit qualifications of contractor’s in-house material testing laboratory.
2. Samples and Test Results: Furnish, without additional cost to the Owner, such quantities of import materials as may be required for test purposes. Cooperate with the Engineer and furnish necessary facilities for sampling and testing of all materials and workmanship.
Submit test results from Contractor’s Quality Control Laboratory for import materials. Tests shall be performed within 60 days of the submission. All material furnished and all work performed shall be subject to rigid inspection and no material shall be delivered to the site until it has been favorably reviewed by the engineer or used in the construction work until it has been inspected in the field by the engineer.
1.04 QUALITY ASSURANCE
A. SOURCE QUALITY CONTROL:
Test import materials proposed for use to demonstrate that the materials conform to the specified requirements. Tests shall be performed by contractor’s in-house quality control organization.
B. FIELD QUALITY CONTROL:
1. The Contractor shall:
a. Review and test materials proposed for use.
b. Inspect placement and compaction of fill.
c. Test soils during placement of fill.
2. Contractor shall excavate holes for in-place soil sampling.
Contractor shall be responsible for costs of additional inspection and re-testing resulting from non-compliance.
C. STOCKPILE CLEANUP
1. The Contractor shall remove stockpile, leave area in clean and neat condition.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 30 00 – EARTHWORK
3 of 8
D. TESTING METHODS:
1. Specific Gravity: ASTM D854
2. Laboratory Compaction: ASTM D1557, Method A or C.
3. In-place Density: ASTM D1556 or ASTM D2922.
4. Particle Size Analysis of Soils: ASTM D422.
5. Plastic Limit and Plasticity Index: ASTM D4318.
6. Soil Classification: ASTM D2487.
7. In-place Moisture Content: ASTM D3017.
E. DEFINITION:
Relative Compaction: In-place density divided by the maximum dry density laboratory compaction expressed as percentage.
1.05 PRESERVATION OF PROPERTY
A. Where construction is to be performed in the vicinity of trees and shrubbery, the work shall be carried on in a manner which will cause minimum damage.
B. All damage shall be immediately reported to the Engineer who will file a report so that penalties may be determined.
1.06 EXPLOSIVES
The Contractor shall not use explosives of any kind on the premises.
1.07 ADDITIONAL SAFETY RESPONSIBILITIES
A. The Contractor shall be responsible for ensuring such measures:
1. Comply fully with 29 CFR Part 1926 OSHA Subpart P Excavations and Trenches requirements.
2. Provide necessary support to the sides of excavations.
3. Provide safe access to the Engineer’s sampling and testing within the excavation.
4. Provide safe access for backfill, compaction, and compaction testing.
5. Maintain excavations in a safe manner that shall not endanger property, life, health, or the project schedule. All earthwork shall be performed in strict accordance with applicable law, including local ordinances and applicable OSHA requirements.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 30 00 – EARTHWORK
4 of 8
1.08 ARCHAEOLOGICAL MONITORING
A. The Contractor shall notify the Engineer a minimum of 72 hours in advance of any excavation and will not proceed with any excavation work until cleared to do so by the Engineer. A Tribal monitor or archaeologist may be on site during construction activities. The contractor is advised that if any archaeological findings are discovered during construction that the monitor or archaeologist has the authority to slow or stop construction activities as they deem necessary.
PART 2 – PRODUCTS
2.01 MATERIALS
A. CLASS 2 AGGREGATE BASE
Class 2 aggregate base shall be ¾” minus conform to Section 26 of the State Standard Specifications.
B. DRAIN ROCK
Shall be Class 2 Permeable material and conform to Section 68-2 the State Standard Specifications.
C. STRUCTURE BACKFILL
Shall conform to Section 21 of the State Standard Specifications and shall have a minimum sand equivalent of not less than 20. 100 percent shall pass a 3-inch sieve, 35 to 100 percent shall pass a No. 4 sieve and 20 to 100 percent shall pass the 30-mesh screen. It shall be free from organic matter and unsatisfactory material.
D. TOPSOIL
Shall conform to the State Standard Specifications and shall be a natural friable surface soil without admixtures of undesirable subsoil, refuse, asphalt, oils, metals, or foreign materials. It shall be reasonably free from roots, hard clay, coarse gravel, stones larger than one inch in any dimensions, noxious weeds, tall grass, brush, sticks or other material which would be detrimental to the proper development of vegetative growth.
E. ROCK SLOPE PROTECTION
Shall conform to Section 72 of the State Standard Specifications, size to be as indicated on the Plans.
F. EMBANKMENT / IMPORT BORROW
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 30 00 – EARTHWORK
5 of 8
Shall conform to Section 19-7 of the State Standard Specifications.
PART 3 – EXECUTION
3.01 CLEARING AND GRUBBING WORK REQUIRED
A. LOCATIONS
Where required and directed by the engineer and per Section 02 10 00.
B. REMOVAL AND DISPOSAL OF MATERIAL:
All of the debris type material resulting from the above clearing and other miscellaneous site clearing required by the work or any excavation shall be removed from the site of the work and deposited at the Contractor's disposal site (see Section 01 74 23).
3.02 CONTROL OF WATER
The Contractor shall be responsible for furnishing temporary drainage facilities to convey and dispose of surface water falling on or passing over the site.
Contractor shall comply with all best management practices for prevention of water pollution as described in Section 01 57 23.
3.03 EXISTING UTILITIES
GENERAL:
The known existing utilities are shown on the Drawings in their approximate location. The Contractor shall exercise care in avoiding damage to all utilities, as they will be held responsible for their repair if damaged. There is no guarantee that all utilities or obstructions are shown, or that locations indicated are accurate. Utilities are piping, conduits, wire, cable, ducts, manholes, pull boxes and the like, located at the project site and adjoining said site.
Excavations around underground electrical ducts and conduits shall be performed using extreme caution to prevent injury to workmen or damage to electrical ducts or conduits. Similar precautions shall be exercised around gas lines, telephone, and television cables.
3.04 EXCAVATING
A. Excavate subsoil to accommodate formwork for paving, and site structures.
B. Slope banks to angle of repose or flatter, if shown on the plans, unless shoring is used.
C. Grade top perimeter of excavation to prevent surface water from draining into excavation.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 30 00 – EARTHWORK
6 of 8
D. Hand trim excavation. Remove loose matter.
E. Notify Owner’s Representative of unexpected subsurface conditions.
F. Correct areas over excavated with appropriate backfill and compact as specified or as directed by Engineer.
G. PROTECTION:
1. Prevent displacement or loose soil from falling into excavation; maintain soil stability
2. Protect structures, utilities and other facilities from damage caused by settlement, lateral movement, undermining, washout, and other hazards created by earth operations.
3.05 FILL
A. Compact subgrade as necessary to support density requirements of subsequent layers of fill.
B. Use Class 2 aggregate base to raise the existing grades to final subgrades, or as shown on the plans.
C. Compact all fill materials to a minimum of 95% of its maximum dry density, unless otherwise indicated in the Plans or Specifications.
D. Fill in lifts allowing time for Contractor’s materials tester to test each lift for compaction.
3.06 DITCHES:
Cut ditches accurately to the cross sections and grades shown. Take care not to over excavate ditches and backfill excessive excavation to grade. Trim all roots, stumps, rock, and other foreign matter from the sides and bottom of the ditches.
Compact the surfaces of ditch slopes and bottom.
3.07 TESTING:
Where required, all testing shall be performed by an approved testing laboratory. When test results indicate, as determined by the Engineer, that compaction is not as specified, the material shall be removed, replaced and recompacted to meet specification requirements. Tests on re-compacted areas shall be performed at Contractor’s expense to determine conformance with specification requirements. Inspections and test results shall be certified by the Contractor’s laboratory. These certifications shall state that the test results are representative of the materials or conditions being certified by the tests.
3.08 TRENCH EXCAVATION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 30 00 – EARTHWORK
7 of 8
A. Excavation for pipe and other utilities shall be in open cut. The trench shall be as wide as necessary for sheeting and bracing and the proper performance of the work up to the maximum width permitted by the typical cross-sections shown on the Drawings. The sides of the trenches shall be vertical in paved areas. The bottom of the trench shall be constructed to the grades and shapes indicated on the Drawings. Should the Contractor desire to use other equivalent methods, he shall submit his method of construction to the Engineer for favorable review prior to its use.
B. Take care not to over excavate. Accurately grade the bottom of the trenches to provide uniform bearing and support for each section of the pipe or conduit at every point along its entire length, except for the portions of the pipe sections where it is necessary to excavate for bell holes and for the proper sealing of pipe joints, and as hereinafter specified. Dig bell holes and depressions for joints after the trench bottom has been graded. In order that the pipe rests on the bedding for as nearly its full length as practicable. Bell holes and depressions shall be only of such length, depth, and width as required for properly making the joint.
Remove stones as necessary to avoid point bearing.
C. Backfill and compact over-excavations to 95% relative compaction with bedding material. There shall be no additional payment to the Contractor for over-excavations not directed by the Engineer. Remove unsatisfactory material encountered below the grades shown as directed by the Engineer and replace with bedding material. Payment for removal and replacement of such unsatisfactory material directed by the Engineer shall be made in accordance with the provisions of the General Conditions.
D. Provide ladders for access to the trench by construction and inspection personnel.
3.09 SUPPORT OF EXCAVATIONS
A. Adequately support excavation for trenches and structures to meet all applicable requirements in the current rules, orders, and regulations.
Excavation shall be adequately shored, braced, and sheeted so that the earth will not slide or settle and so that all existing structures and all new pipe and structures will be fully protected from damage. Keep vehicles, equipment, and materials far enough from the excavation to prevent instability.
B. Take all necessary measures to protect excavations and adjacent improvements from running, caving, boiling, settling, or sliding soil resulting from the high groundwater table and the nature of the soil excavated.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 30 00 – EARTHWORK
8 of 8
C. The support for excavation shall remain in place until the pipeline or structure has been completed. During the backfilling of the pipeline or structure, the shoring, sheeting, and bracing shall be carefully removed so that there shall be no voids created and no caving, lateral movement, or flowing of the subsoils.
3.010 COMPACTION
A. Add water to the backfill material or dry the material as necessary to achieve specified compaction density of each layer of backfill being compacted. Employ such means as may be necessary to secure a uniform moisture content throughout the material of each layer being compacted.
B. After the material has been moisture conditioned, compact it with compaction equipment appropriate for the use to achieve specified compaction.
C. If the backfill material becomes saturated from rains or any other source because it was not compacted to the specified density or was not backfilled and compacted to surface grade, through negligence or otherwise, remove the faulty material and replace it with suitable material compacted to the specified density. No additional payment will be made for doing such work or removal and replacement.
D. Compaction of embankment and backfill materials by flooding, ponding, or jetting will not be permitted.
3.011 FINISH GRADING
Except where shown otherwise in the Drawings, restore the finish grade to the original contours and to the original drainage patterns. Grade surfaces to drain away from structures. The finished surfaces shall be smooth and compacted.
3.012 DISPOSAL OF EXCAVATED MATERIAL
Dispose of unsuitable material or excavated material in excess of that needed for backfill or fill offsite.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 41 00 - DEMOLITION
1 OF 3
SECTION 02 41 00
DEMOLITION
QUALITY CONTROL PART 1 – GENERAL
1.01 WORK INCLUDED:
A. Removal and disposal of designated foundations, walls, concrete, utilities, mechanical, lighting, and other structures.
B. Removal and disposal of all other materials needed to accomplish the project.
1.02 QUALITY ASSURANCE:
A. Contractor Qualifications: Minimum of 5 years experience in demolition of comparable structures.
B. Requirements of Regulatory Agencies:
1. Comply with requirements of codes.
2. Comply with requirements of local Public Health Authority.
3. Comply with local utility companies and/or utility districts.
1.03 SUBMITTALS:
A. Certificates of severance of utility services.
B. Permit for transport and disposal of debris.
C. Demolition procedures and operational sequence for review by Owner's Representative
1.04 JOB CONDITIONS:
A. Protection:
1. Erect barriers, fences, guard rails, enclosures, chutes, and shoring to protect structures, and utilities remaining intact.
2. Protect designated trees and plants from damage.
3. If required by governing authorities, provide alternate routes around closed or obstructed traffic ways.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 41 00 - DEMOLITION
2 OF 3
B. Maintaining Traffic:
1. Ensure minimum interference with roads, street, driveways, sidewalks, and adjacent facilities.
2. Do not close or obstruct streets, sidewalks, alleys, or passageways without permission from authorities having jurisdiction.
PART 2 - PRODUCTS (Not Applicable)
PART 3 - EXECUTION
3.01 REPARATION:
A. Prepare adjacent areas to prevent injury, movement, or settlement of structures which are to remain.
B. Arrange for and verify termination of utility services to include removing meters and capping lines.
C. Examine the areas and conditions under which the work of this Section will be performed. Correct conditions detrimental to timely and proper completion of the work. Do not proceed until unsatisfactory conditions are corrected.
D. Remove items scheduled to be salvaged for Owner, and place in designated storage area.
3.02 DEMOLITION:
A. Remove designated foundations, walls, concrete, utilities, mechanical, lighting, and other structures and dispose of in accordance with rules and regulations.
Stockpile ballast, gravel, and other pavement materials when required.
B. Coordinate removal and relocation of power poles, street lighting, telephone lines and site lighting, with the local electric utility and the Owner.
C. Remove existing water services, sanitary sewer and storm drainage pipe and structures as indicated and as necessary to facilitate new construction.
D. Remove old foundations, cisterns, etc., which may be encountered within the construction area. Storm drains to be abandoned shall have each open end filled with concrete that is vibrated into place until no more concrete will flow into pipe end. A plywood form shall be constructed so that a minimum of 3-ft of head can be placed on the pipe end. Other openings in storm drains to be abandoned shall be filled in a similar fashion. City may camera lines in order to determine other locations to be filled.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 41 00 - DEMOLITION
3 OF 3
3.03 SELECTIVE STRUCTURAL DEMOLITION
A. General:
1. Prior to the start of demolition, carefully study the drawings and these Specifications.
2. In company with the Owner or the Owner’s representative, visit the site and verify the extent of demolition to be performed under this contract.
B. Observe all safety and health precautions as required for removal of hazardous materials when hazardous materials are identified as part of the demolition activity.
Refer to specific work requirements associated with hazardous material removal.
C. Protect other components, materials, and landscaping in the vicinity of the demolition to prevent unintentional damage to components and materials that are not to be removed. Provide temporary support of structures that are to remain that are affected by the materials to be demolished and removed.
D. Remove materials as designated on the drawings.
E. Demolished materials that are not to be salvaged for reuse on this project shall be considered to be the property of the contractor and shall be completely removed from the jobsite and disposed of properly.
F. The contractor shall be responsible for repair of all components, materials, and landscaping damaged as part of the demolition process at no additional cost to the Owner.
G. Existing light pole foundations may be either entirely removed or chipped off at 36- inches below finished grade.
3.04 DEBRIS REMOVAL:
A. Promptly remove demolition debris from site.
B. Obtain permission from applicable regulatory authority for disposal of debris to waste disposal site.
C. Do not store or burn materials on site.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 41 19 – SELECTIVE DEMOLITION
1 OF 6
SECTION 02 41 19
SELECTIVE DEMOLITION
PART 1 - GENERAL
1.1 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 01 Specification Sections, apply to this Section.
1.2 SUMMARY
A. Section Includes:
1. Demolition and removal of selected site elements.
a. Clear & grub
b. Asphalt paving
c. Walls & steps
d. Curbs
2. Salvage of existing items to be reused or recycled.
a. Concrete bench
b. Discovery Center Signage
c. Existing monuments
d. Artwork
e. Signage
3. Existing to remain.
a. Seawall
B. Related Requirements:
1. Section 01 10 00 "Summary" for restrictions on use of the premises, Owner-occupancy requirements, and phasing requirements.
2. Section 01 56 39 "Temporary Tree and Plant Protection" for temporary protection of existing trees and plants that are affected by selective demolition.
3. Section 01 73 00 "Execution" for cutting and patching procedures.
4. Section 01 35 16 "Alteration Project Procedures" for general protection and work procedures for alteration projects.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 41 19 – SELECTIVE DEMOLITION
2 OF 6
5. Section 31 10 00 "Site Clearing" for site clearing and removal of aboveand below-grade improvements not part of selective demolition.
6. Section 31 20 00 "Earth Moving" for soil material fills.
1.3 DEFINITIONS
A. Remove: Detach items from existing construction and dispose of them off-site unless indicated to be salvaged or reinstalled.
B. Remove and Salvage: Detach items from existing construction, in a manner to prevent damage, and deliver to City Corporation yard located at 900 10th Street, Crescent City, CA.
C. Existing to Remain: Leave existing items that are not to be removed and that are not otherwise indicated to be salvaged or reinstalled.
1.4 MATERIALS OWNERSHIP
A. Unless otherwise indicated, demolition waste becomes property of Contractor.
B. Historic items, relics, antiques, and similar objects including, but not limited to, cornerstones and their contents, commemorative plaques and tablets, and other items of interest or value to Owner that may be uncovered during demolition remain the property of Owner.
1. Carefully salvage in a manner to prevent damage and promptly return to Owner.
1.5 INFORMATIONAL SUBMITTALS
A. Engineering Survey: Submit engineering survey of condition of building.
B. Schedule of Selective Demolition Activities: Indicate the following:
1. Detailed sequence of selective demolition and removal work, with starting and ending dates for each activity.
2. Interruption of utility services. Indicate how long utility services will be interrupted.
3. Coordination for shutoff, capping, and continuation of utility services.
C. Predemolition Photographs or Video: Show existing conditions of adjoining construction, including finish surfaces, that might be misconstrued as damage caused by demolition operations. Comply with Section 013233 "Photographic Documentation." Submit before Work begins.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 41 19 – SELECTIVE DEMOLITION
3 OF 6
D. Warranties: Documentation indicating that existing warranties are still in effect after completion of selective demolition.
1.6 CLOSEOUT SUBMITTALS
A. Inventory: Submit a list of items that have been removed and salvaged.
1.7 QUALITY ASSURANCE
A. Refrigerant Recovery Technician Qualifications: Certified by an EPA-approved certification program.
1.8 FIELD CONDITIONS
A. Conditions existing at time of inspection for bidding purpose will be maintained by Owner as far as practical.
1. Before selective demolition, remove the following items: Henry Souse Jr.
Monument.
2. Salvaging of monument to be monitored by City staff during operation and transport.
B. Notify Owner's Representative of discrepancies between existing conditions and Drawings before proceeding with selective demolition.
C. Hazardous Materials: It is not expected that hazardous materials will be encountered in the Work.
1. If suspected hazardous materials are encountered, do not disturb; immediately notify Owner's Representative. Hazardous materials will be removed by Owner under a separate contract.
PART 2 - PRODUCTS
2.1 PERFORMANCE REQUIREMENTS
A. Regulatory Requirements: Comply with governing EPA notification regulations before beginning selective demolition. Comply with hauling and disposal regulations of authorities having jurisdiction.
B. Standards: Comply with ASSE A10.6 and NFPA 241.
PART 3 - EXECUTION
3.1 EXAMINATION
A. Verify that utilities have been disconnected and capped before starting selective FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 41 19 – SELECTIVE DEMOLITION
4 OF 6
demolition operations.
B. Survey of Existing Conditions: Record existing conditions by use of measured drawings.
1. Comply with requirements specified in Section 013233 "Photographic Documentation."
2. Inventory and record the condition of items to be removed and salvaged.
Provide photographs or video of conditions that might be misconstrued as damage caused by salvage operations.
3. Before selective demolition or removal of existing building elements that will be reproduced or duplicated in final Work, make permanent record of measurements, materials, and construction details required to make exact reproduction.
3.2 UTILITY SERVICES AND MECHANICAL/ELECTRICAL SYSTEMS
A. Existing Services/Systems to Remain: Maintain services/systems indicated to remain and protect them against damage.
1. Arrange to shut off utilities with utility companies.
2. If services/systems are required to be removed, relocated, or abandoned, provide temporary services/systems that bypass area of selective demolition and that maintain continuity of services/systems to other parts of building.
3. Disconnect, demolish, and remove fire-suppression systems, plumbing, and HVAC systems, equipment, and components indicated on Drawings to be removed.
a. Piping to Be Removed: Remove portion of piping indicated to be removed and cap or plug remaining piping with same or compatible piping material.
b. Piping to Be Abandoned in Place: Drain piping and cap or plug piping with same or compatible piping material and leave in place. c. Equipment to Be Removed: Disconnect and cap services and remove equipment.
d. Equipment to Be Removed and Reinstalled: Disconnect and cap services and remove, clean, and store equipment; when
appropriate, reinstall, reconnect, and make equipment operational.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 41 19 – SELECTIVE DEMOLITION
5 OF 6
e. Equipment to Be Removed and Salvaged: Disconnect and cap services and remove equipment and deliver to Owner.
f. Ducts to Be Removed: Remove portion of ducts indicated to be removed and plug remaining ducts with same or compatible ductwork material.
g. Ducts to Be Abandoned in Place: Cap or plug ducts with same or compatible ductwork material and leave in place.
3.3 PROTECTION
A. Temporary Protection: Provide temporary barricades and other protection required to prevent injury to people and damage to adjacent buildings and facilities to remain.
1. Provide protection to ensure safe passage of people around selective demolition area.
B. Remove temporary barricades and protections where hazards no longer exist.
3.4 SELECTIVE DEMOLITION, GENERAL
A. Site Access and Temporary Controls: Conduct selective demolition and debrisremoval operations to ensure minimum interference with roads, streets, walks, and walkways.
B. Removed and Salvaged Items:
1. Store items in a secure area until delivery to Owner.
2. Transport items to Owner's storage area at 900 10th Street.
3. Protect items from damage during transport and storage.
C. Removed and Reinstalled Items:
1. Clean and repair items to functional condition adequate for intended reuse.
2. Pack or crate items after cleaning and repairing. Identify contents of containers.
3. Protect items from damage during transport and storage.
4. Reinstall items in locations indicated. Comply with installation requirements for new materials and equipment. Provide connections, supports, and miscellaneous materials necessary to make item functional FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
02 41 19 – SELECTIVE DEMOLITION
6 OF 6
for use indicated.
D. Existing Items to Remain: Protect construction indicated to remain against damage and soiling during selective demolition. When permitted by Owner's Representative, items may be removed to a suitable, protected storage location during selective demolition and reinstalled in their original locations after selective demolition operations are complete.
3.5 SELECTIVE DEMOLITION PROCEDURES FOR SPECIFIC MATERIALS A. Concrete: Demolish in small sections. Using power-driven saw, cut concrete to a depth of at least 3/4 inch at junctures with construction to remain. Dislodge concrete from reinforcement at perimeter of areas being demolished, cut reinforcement, and then remove remainder of concrete. Neatly trim openings to dimensions indicated.
B. Concrete Slabs-on-Grade: Saw-cut perimeter of area to be demolished, and then break up and remove.
3.6 DISPOSAL OF DEMOLISHED MATERIALS
A. Remove demolition waste materials from Project site and dispose of them in an EPA-approved construction and demolition waste landfill acceptable to authorities having jurisdiction.
1. Do not allow demolished materials to accumulate on-site.
2. Remove and transport debris in a manner that will prevent spillage on adjacent surfaces and areas.
3. Comply with requirements specified in Section 017419 "Construction Waste Management and Disposal."
B. Burning: Do not burn demolished materials.
3.7 CLEANING
A. Clean adjacent structures and improvements of dust, dirt, and debris caused by selective demolition operations. Return adjacent areas to condition existing before selective demolition operations began.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
03 10 00 – CONCRETE FORMWORK
1 of 3
SECTION 03 10 00
CONCRETE FORMWORK
PART 1 – GENERAL
1.1 SCOPE
The work includes the furnishing and installing and removing of forms for all cast-in-place concrete work as shown and noted on the plans and specified herein.
1.2 CODES AND STANDARDS
The American Concrete Institute’s “Recommended Practice for Concrete Formwork”, ACI 347, and the Uniform Building Code, Section 2606, are hereby made a direct part of this specification, and all concrete formwork included in this contract shall conform with the applicable requirements therein except as specified otherwise herein.
1.3 RELATED WORK
A. Section 01 11 00: SUMMARY OF WORK
B. Section 03 20 00: CONCRETE REINFORCEMENT
C. Section 03 30 00: CAST-IN-PLACE CONCRETE
1.4 QUALITY ASSURANCE
A. Design of structures shown on drawings includes no allowance for imposed construction loads. Provide forms, shoring and falsework adequate for dead loads and live loads plus imposed loads during construction.
B. It shall be the Contractor’s responsibility to design, construct and maintain safe forms, shoring, and falsework at all times in accordance with applicable Cal/OSHA regulations.
C. Tolerances of formwork shall comply with ACI 117-latest editions. Failure of finished concrete work to meet specified tolerances shall be remedied at Contractor’s expense.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Boards for unexposed concrete, not otherwise scheduled or specified, shall be Douglas Fir, conforming to the “Standard Grading and Dressing Rules No. 16”, most current edition, of the West Coast Lumber Inspection Bureau. Boards shall be S4S.
Contractor, at his option, may use plywood for forms in lieu of boards. Plywood, if used shall be “B-B Plyform Class I Exterior” grade, conforming to U.S. Products Standard PS 1, 5/8" minimum thickness. Plywood used for exposed concrete shall be a high density overlay type especially manufactured for form work.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
03 10 00 – CONCRETE FORMWORK
2 of 3
B. FORM TIES AND SPREADERS: Standard metal form clamp assembly, of type acting as spreaders and leaving no metal within 2" of concrete face. Inner tie-rod shall be left in concrete when forms are removed. Submit samples and manufacturer’s specifications to Engineer for review and approval of Owner before using. Wood spreaders will not be permitted.
C. FORM COATING: Non-grain raising and non-staining type that will not leave residual matter on surface of concrete or adversely affect proper bonding of subsequent application of other material applied to concrete surface. Coatings containing mineral oils or other nondrying ingredients are not permitted.
PART 3 - EXECUTION
3.1 CONSTRUCTION
A. Earth Forms: Construct wood edge strips at each side of trench at top to secure reinforcing and prevent trench from sloughing. Form sides of footings where earth sloughs. Earth forms shall be tamped firm and cleaned of all debris and loose material before depositing concrete.
B. Formwork – General: The engineering and construction of all formwork, shoring and bracing shall be carried out by and under the direction of the Contractor, who shall be responsible for the engineering, construction, maintenance, and safety of all formwork during the entire construction period.
C. The formwork shall be designed for the loads and lateral pressures outlined in Part 3, Section 102, of ACI 347 latest edition.
D. Wood forms shall be constructed of sound material, shall be of the correct shape and dimensions, mortar tight, and of sufficient strength, and so braced and tied together that the movement of men, equipment, materials, or placing and vibrating the concrete will not distort the forms from their design shape under all imposed loads. The form shall be so constructed that they may be easily removed without damage to the concrete. Before concrete is placed in any form, the horizontal and vertical positions of the form shall be carefully verified, and all inaccuracies corrected. All wedging and bracing shall be completed in advance of placing of concrete.
E. Framing and Bracing: Framing bracing, supporting members, and centering shall be of ample size and strength to safely carry, without deflection, all dead and live loads to which forms may be subjected, and shall be spaced sufficiently close to prevent any bulging or sagging of forms. Concrete out of line, level, or plumb will be cause for rejection of the whole work affected.
F. Tolerances: Variation from plumb in lines, surfaces, and arises shall not exceed 1/8" in 10 feet.
G. Chamfered Corners: All exposed corners shall be chamfered ¾", unless shown otherwise on plans. Provide molding in forms for all chamfering required.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
03 10 00 – CONCRETE FORMWORK
3 of 3
H. Form Ties: Form ties shall be of sufficient strength and used in sufficient quantities to prevent spreading of the forms. Ties shall be placed at least 2" away from the finished surface of the concrete.
I. Arrangement: Arrange formwork to allow proper erection sequence and to permit form removal without damage to concrete.
J. Embedded Items: Provisions shall be made for pipes, sleeves, anchors, inserts, reglets, anchor slots, nailers, and other features. No wood other than necessary nailing blocks shall be imbedded in concrete. Complete cooperation shall be extended to suppliers of imbedded items from other trades as required. All imbedded items shall be securely anchored in correct location and alignment prior to placing concrete. All imbedded items shall be subject to Engineer’s review, inspection, and approval.
K. Coating of Forms: Thoroughly clean forms and coat with specified form coating before each use. Do not reuse any form for exposed work which cannot be reconditioned to “like new” condition. Apply form coating to all forms before placing reinforcing steel.
L. Inspection: Prior to placing of any concrete, and after placement of reinforcing steel in the forms, Contractor shall notify Owner so that proper inspection may be made. Such notification shall be made at least 24 hours in advance of placing concrete to permit proper arrangements to be made for inspection.
M. Rejection of Defective Work Due to Improper Forms: Any movement or bellying of forms during construction or variations in excess of the tolerances specified will be considered just cause for the removal of such forms and, in addition, the concrete work so affected. Reconstruction of forms and new concrete (including disposal of rejected materials) shall be furnished at no additional cost to the Owner.
3.2 REMOVAL OF FORMS
A. Do not remove forms of shoring until concrete has attained sufficient strength to support its own weight and all imposed construction and permanent loads. Any damage to the Work resulting from early removal of forms or shoring or early imposed loading shall be corrected at no added expense to the Owner.
B. The minimum time for forms and shoring to remain in place for slabs on grade and sides of footings shall be 24 hours.
C. During the period that forms are in place on the concrete work, forms shall be kept wet at all times.
D. Re-use of Forms: Clean and recondition form material before each re-use.
Unsatisfactory material shall be rejected and removed from the site.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
03 20 00 – CONCRETE REINFORCEMENT
1 of 4
SECTION 03 20 00
CONCRETE REINFORCEMENT
PART 1 – GENERAL
1.1 SCOPE
The work includes the furnishing and installing of reinforcing steel for all cast-in-place concrete.
Contractor shall check project or drawings for anchors, inserts, conduits, sleeves, and any other items which are required to be cast in concrete and shall make necessary provisions as required so that reinforcing steel will not interfere with the placement of such embedded items.
1.2 CODES AND STANDARDS
A. Except as modified by the requirements specified herein and/or the details on the drawings, all work included in this section shall conform to the applicable provisions of the following codes and standards:
1. “Uniform Building Code”: Latest Edition, Chapter 26, Concrete.
2. Concrete Reinforcing Steel Institute (CRSI): “Recommended Practice for Placing Reinforcing Bars”, latest edition.
3. American Concrete Institute (ACI): “Manual of Standard Practice for Detailing Reinforced Concrete Structures”, ACI 315, latest edition.
4. American Society for Testing and Materials (ASTM): The Specifications and standards hereinafter referred to, latest edition.
1.3 RELATED WORK
A. Section 01 11 00: SUMMARY OF WORK
B. Section 03 10 00: CONCRETE FORMWORK
C. Section 03 30 00: CAST-IN-PLACE CONCRETE
1.4 SUBMITTALS
A. Mill affidavits, stating the grades and physical and chemical properties of the reinforcing steel, and conformance with ASTM Specifications, shall be submitted to the Engineer for review and approval by Owner before delivery of the steel to the job site.
B. Shop bending diagrams, placing lists and drawings of reinforcing steel shall be submitted to the Engineer, including actual bar lengths to nearest inch measured to intersection of tangent extensions of the outside bar surface. Bar placement diagrams shall clearly show dimensions of each bar splice.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
03 20 00 – CONCRETE REINFORCEMENT
2 of 4
C. An electronic submittal will be accepted in only the following format.
1. The file shall be in pdf format.
2. Each project submittal shall be a separate file.
3. Each file shall be labeled in the following sequence:
a. Owner Name/Project Name
b. Submittal No.
c. Description
D. Engineer’s review shall be general, and approval will not relieve Contractor of responsibility for accuracy.
1.5 STORAGE
A. Reinforcing steel shall be transported to the building site, stored, and covered in a manner which will ensure that no damage shall occur to it from moisture, dirt, grease, or any other cause that might impair bond to concrete.
B. A sufficient supply of approved reinforcing steel shall be stored on the building site at all times to ensure that there will be no delay of the work. Identification of steel shall be maintained after bundles are broken.
PART 2 - PRODUCTS
2.1 MATERIALS
A. Reinforcing Bars: New, deformed, billet steel bars conforming to ASTM A615-82(S1) Grade 60 unless otherwise indicated. Deliver bars new and free from rust and mill scale in original bundles with mill tags intact.
B. Accessories: Reinforcement accessories, consisting of spacers, chairs, ties, and similar items shall be provided as required for spacing, assembling, and supporting reinforcement in place. Use no aluminum, galvanized steel, plastic or stainless-steel supports or accessories. Supports shall conform to the applicable requirements of the CRSI Standards Chapter 3 specified herein. Use precast concrete block supports with embedded wire ties or dowels for placement on grade or on membranes.
C. Tie Wire: Tie wire for reinforcement shall be 16-gauge or heavier, where indicated or specified, black or galvanized steel wire, conforming to ASTM A82-79.
PART 3 - EXECUTION
3.1 FABRICATION
A. Fabrication of steel reinforcement shall be in accordance with the details shown on the plans. Where specific details are not shown or noted, comply with the applicable requirements of the “Codes and Standards” here in before specified.
B. Bars shall be accurately bent, cut, and placed as indicated on the drawings. Bars shall be bent cold; heating of bars will not be permitted. Bars shall not be bent or FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
03 20 00 – CONCRETE REINFORCEMENT
3 of 4
straightened in any manner that will injure the material. Bars with kinks or bends not scheduled will be rejected.
3.2 PLACING
A. General: Place reinforcing steel as indicated and in accordance with the applicable requirements of referenced specified. Install reinforcement accurately and secure against movement, particularly under the weight of workmen and placement of concrete.
1. Clean reinforcement of loose rust and mill scale, earth, and other materials which may reduce or destroy bond with concrete.
B. Reinforcing Supports: Support reinforcing bars above earth and on forms by concrete blocks or other approved noncorrodible supports. Support legs of accessories in forms without embedding in form surface. Space chairs and accessories to conform with CRSI’s “Recommended Practice for Placing Bar Supports”. No wood will be permitted inside forms.
C. Placing and Tying: Set reinforcing in place, and rigidly and securely tie or wire with 16-gauge steel tie wire in the position indicated, or as directed. Point ends of wire away from forms.
D. The reinforcement shall be so secured in position that it will not be displaced during the placement of concrete.
E. Spacing: Minimum center to center distance between parallel bars shall be in accordance with the details on the plans or, where not shown, the clear spacing shall be 2 times the bar diameter but in no case less than 1½" nor less than 1-1/3" times the maximum size aggregate.
F. Splices: Laps of splices, where shown or noted on plans, shall be adequate to transfer stress by bond. Splicing shall meet requirements of ACI 318 and applicable building codes unless noted otherwise on drawings. Splices of adjacent bars shall be staggered with no more than 50% of the laps at any given joint. Reinforcing bars marked continuous shall be spliced with a minimum lap of (40) bar diameters in masonry and (30) bar diameters in concrete. Approved mechanical coupling may be used for horizontal steel.
G. Dowels: Dowels shall be tied securely in place before concrete is deposited. In the event there are no bars in position to which dowels may be tied, No. 3 minimum shall be added to provide proper support and anchorage. Bending of dowels after placement of concrete will not be permitted.
H. Welding of reinforcing bars is not permitted.
I. All bars shall be free from rust, scale, oil, or any other coating that would reduce or destroy the bond between concrete and steel.
J. Cleaning: Reinforcement, at time of pour, shall be free of all coatings that would impair bond to concrete.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
03 20 00 – CONCRETE REINFORCEMENT
4 of 4
K. Additional Reinforcing: Provide additional reinforcing bars at sleeves and openings as indicated or required. Where additional bars are not shown for such location, obtain Engineer instructions and provide additional bars as directed at no extra cost to the Owner.
3.3 INSPECTION
A. Contractor shall notify Engineer at least 48 hours ahead of each concrete pour, and no concrete shall be placed until all reinforcing steel has been installed, inspected, and approved by the Inspector.
B. The following reinforcing steel work will be considered defective and shall be removed and replaced at no additional cost to the Owner.
1. Bars with kinks or bends not shown on drawings
2. Bars injured due to bending or straightening
3. Bars heated for bending
4. Reinforcement not placed in accordance with the plans and/or specifications
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
03 30 00 – CAST-IN-PLACE CONCRETE
1 of 4
SECTION 03 30 00
CAST-IN-PLACE CONCRETE
PART 1 – GENERAL
1.01 WORK INCLUDED:
Concrete required for this work is indicated on the Drawings and includes, but is not limited to: Minor concrete work including curb ramps, sidewalks, crosswalks, curbs, valley gutters, streetlamp footings, and miscellaneous structures.
1.02 REFERENCE SPECIFICATIONS
A. All concrete in this section shall conform to the requirements of Section 90-2 "Minor Concrete", 2018 Standard Specifications by the State of California, Department of Transportation except as modified by the supplemental requirements herein, excluding measurement and payment items.
B. Design, detailing and fabrication of reinforcing steel shall conform to ACI 315-74 "Manual of Standard Practice for Detailing Reinforced Concrete Structures" and ACI 318-71 "Building Code Requirements for Reinforced Concrete."
C. Form work and finishing as well as construction methods and miscellaneous materials shall conform to Section 51 "Concrete Structures" of 2018 Standard Specification excluding measurement and payment items.
1.03 SUBMITTALS
Refer to Section 01 33 00 – Submittals for the requirements for submittals.
PART 2 – PRODUCTS
2.01 CONCRETE
A. Concrete shall comply with Caltrans Minor Concrete Standards with the minimum quantities or within the ranges listed below.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
03 30 00 – CAST-IN-PLACE CONCRETE
2 of 4
Concrete shall be air entrained (2% +/-1%).
Minimum Maximum Minimum
psi @ 28 Size Sacks of Slump
Location days Aggregate Cement/C.Y. Range
All driveways, 3,600 3/4 5.7 4-6
Sidewalks,
crosswalks, C&G
B. Additive color to be used in stamped sidewalks and stamped crosswalks only. Integral color to be Mountain Trail. Driveways, ADA Ramps, concrete pavement, and curbs and gutters to have no color added.
C. ADMIXTURES:
The use of admixtures shall be confined to those admixtures listed below.
Admixtures shall be batched in strict accord with manufacturer's recommendations.
1. Any stabilizers or retarders added will be at the expense of the Contractor.
2.02 CEMENT
Cement shall be Portland, conforming to ASTM C-150, Type II.
2.03 AGGREGATES
Aggregates shall conform to Caltrans testing and gradations.
2.04 REINFORCING STEEL
Reinforcing steel shall conform to ASTM A615, Grade 40. Reinforcing to be placed in driveways, crosswalks, and concrete paving Alternative #2.
2.05 CHEMICAL BONDING AGENT
Chemical bonding agent shall be of aqueous phase, film forming, non-oxidizing composition.
2.06 GROUTS
A. Non-shrink type (handrails, equipment bases, etc.):
1. Compatible with handrail metal.
2. Premixed, one of the following or an approved equal:
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
03 30 00 – CAST-IN-PLACE CONCRETE
3 of 4
a. "Quick Rok", Preco Chemical Corp., Plainview, N.Y.
b. "Masterflow 713", Master Builders Co., Cleveland, Ohio.
B. Ordinary "Dry Pack":
1. Ratio 1 part Portland cement, 2 parts sand (by weight).
2. Water to produce damp, formable consistency.
PART 3 – EXECUTION
3.01 GENERAL
A. Conform to State Standard Specification, Section 51. Measurement and Payment sections are not applicable.
B. Concrete repairs of damaged sidewalks, driveways, curbs, gutters, and other concrete items shall be made to the same line and grade and with concrete of a similar finish, texture, and color to the adjoining concrete.
3.02 REINFORCING STEEL
A. Detail in accordance with ACI 315-74 and ACI 318-71.
3.03 FORM WORK
A. Design and engineering of form work, as well as construction of same is the responsibility of the Contractor.
B. Use 3/4-inch x 3/4-inch chamfers at all sharp edges.
3.04 FINISHES
A. City will provide Contractor with a boardwalk stamp for use on all sidewalks and crosswalks as indicated on the plans.
B. Provide "ordinary surface finish" as defined in Section 51 of Caltrans Standard Specifications for all formed surfaces not specified otherwise.
C. All exterior concrete shall be sloped so as to drain without puddling, minimum 1/8 inch/foot where not shown. Slab finishes shall be defined as indicated in ACI 301 except that power floating or troweling versus hand finishing will be at the Contractor's option. Where not otherwise noted, flat and sloped surfaces shall be a broomed finish and all slab finishes shall be a fine broom finish.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
03 30 00 – CAST-IN-PLACE CONCRETE
4 of 4
3.05 BONDING AGENT
A. Prior to application, surfaces shall be cleaned of all dirt, dust, oil, grease, wax, effervescence, and loose base material.
B. After uniform application is allowed to dry until no longer tacky, then pour required concrete material.
3.06 PLACING
Placing of concrete shall be done immediately after mixing. No concrete shall be placed or used after it has begun to set and no re-tempering will be allowed. The method used in placing shall be such that concrete is conveyed to place and deposited without separation of the ingredients. No concrete shall be placed with a free unconfined fall in excess to ten (10) feet for concrete containing a highrange water-reducing admixture (superplasticizer) and five (5) feet for other concrete. Concrete shall not be allowed to cascade through reinforcing steel in such manner as to promote segregation. Do not support runways on reinforcing steel.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
03 48 00 – PRE-CAST CONCRETE SPECIALTIES
1 of 6
SECTION 03 48 00
PRE-CAST CONCRETE SPECIALTIES
PART 1 – GENERAL
1.01 RELATED DOCUMENTS
A. Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.
B. Prestressed Concrete Institute MNL 117 "Manual for Quality Control for Plants and Production of Architectural Precast Concrete Products" - 3rd Edition, primarily Appendix J.
C. Prestressed Concrete Institute's "Architectural Precast Concrete Design Manual, 2nd Edition".
D. ASTM standards as stated herein.
1.02 SUMMARY
A. This Section includes site pre-cast concrete, complete, as shown and as specified for fence posts and rails.
1.03 REFERENCES
A. ASTM - American Society for Testing and Materials.
B. ACI - American Concrete Institute, Manual of Concrete Practice.
C. STANDARD SPECIFICATIONS:
2018 Standard Specifications of the State of California, Department of Transportation.
1.04 PROJECT/SITE CONDITIONS
A. FIELD MEASUREMENTS:
Verify field measurements and dimensions where required and show on shop drawings.
1.05 QUALITY ASSURANCE
A. QUALIFICATIONS:
Show successful experience in precast concrete work, including not less than 5 years of experience in design, engineering, fabrication, and installation of precast concrete systems similar to the work required for this project.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
03 48 00 – PRE-CAST CONCRETE SPECIALTIES
2 of 6
1.06 SUBMITTALS
A. PRODUCT DATA:
Manufacturer's current catalog cuts and specifications for the following:
B. SHOP DRAWINGS:
Shop and erection drawings, including profiles, finish, edges, color, dimensions, joints, details of inserts, reinforcing and connections to all adjoining work. Drawings requiring licensed civil or structural engineers shall include registered stamp in the State where the project is located.
C. SAMPLES:
One each full-sized piece of each type of pre-cast concrete material including finishes, colors, and joints. Verify desired colors by owner prior to submitting samples.
D. CERTIFICATES:
Three (3) certified copies of concrete mix design for each batch used.
1.07 DELIVERY, STORAGE, AND HANDLING
A. DELIVERY:
Transport and deliver all pre-cast concrete units on pallets, packaged in such a manner so that no damage occurs to the product. Catalog items shall be delivered in their original containers, with seals unbroken and labels intact until their installation. Wrapped or bundled materials shall clearly show their manufacturer's name and trademark.
B. STORAGE:
Cover with non-staining, waterproof paper when necessary to protect them from weather.
C. DAMAGED MATERIALS:
Be responsible for all damage or disfiguration of pre-cast work until Final Acceptance. Remove off site and replace at no additional cost to Owner all damaged or rejected pre-cast materials.
1.08 SEQUENCING AND SCHEDULING
A. COORDINATION:
Coordinate with the work of all other sections to insure the following:
1. All such portions of work as are all or in part imbedded, built-in, attached to, supported by, or covered over by the pre-cast FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
03 48 00 – PRE-CAST CONCRETE SPECIALTIES
3 of 6
concrete work are executed in ample time that progress of work is not delayed.
2. Sequence work to avoid cutting or patching pre-cast concrete.
3. Coordinate proper installation of all accessories imbedded in the pre-cast concrete for the provision of holes, openings, etc., necessary to the execution of the work of other trades.
B. Scheduling: Insure that accepted precast concrete units are delivered to the site in ample time so as not to delay the progress of the work.
1.09 WARRANTY
Manufacturer to warrant fabrications to be free from defects due to materials and workmanship for a minimum of five years.
PART 2 – PRODUCTS
2.01 MATERIALS
A. PORTLAND CEMENT:
1. Type: ASTM C150, Type I or II. Use only one brand and type for entire job.
2. Minimum Compressive Strength at 28 Days: 5000 psi.
3. Maximum Absorption Rate:
a. Regular Weight Concrete: Five (5) percent.
b. Lightweight Concrete: Twelve (12) percent.
B. AGGREGATES:
1. Regular Weight Concrete:
ASTM C33, with maximum 3/4 in. size or to maximum 1/5 width of minimum precast section.
2. Lightweight Concrete:
ASTM C330, with maximum 5/8 in. size or to maximum 1/5 width of minimum precast section.
2.02 ACCESSORIES
A. REINFORCEMENTS:
1. Reinforcing Bars: ASTM A615 Grade 40 deformed billet-steel bars, clean and free from rust, scale, or coating that will reduce bond.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
03 48 00 – PRE-CAST CONCRETE SPECIALTIES
4 of 6
2. Welded Wire Fabric: ASTM A185. Leave tags designating wire size and spacing on each roll until ready for use.
B. WATER:
Clean, potable, free from injurious amounts of oils, alkalis, organic materials, and other deleterious materials. As available from Owner.
Transport as required.
C. AIR ENTRAINMENT:
ASTM C260
D. MORTAR:
1:6 Portland Cement/sand
E. GROUT:
Portland Cement Grout Mix: 1,800 psi min. compressive strength at 28 days.
Joints up to 1/2 in.: 1:2:1/4 Portland Cement/sand/lime Joints 1/2 in. or more: 1:3:1/4 Portland Cement/sand/lime
2.03 MIXES
A. PORTLAND CEMENT:
Riverside white cement.
B. AGGREGATE:
Olympia #1 sand, 200 lbs. per sack of cement.
C. COLORING AGENT:
L.M. Scofield Co., No. 1266 Cool Grey, 6 oz. per sack of cement.
Confirm colors with owner in submittal.
D. SHOP ASSEMBLY:
Tolerances:
1. Dimensions: + 1/16 in. per 10 ft. or + 1/8 in. per unit, whichever is greater.
2. Thickness: 1/8 in.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
03 48 00 – PRE-CAST CONCRETE SPECIALTIES
5 of 6
PART 3 – EXECUTION
3.01 EXAMINATION
A. EXISTING CONDITIONS:
Examine surfaces to receive pre-cast concrete work. Report to Owners Representative conditions found to be in conflict or detrimental to installation of pre-cast concrete work.
3.02 PREPARATION
A. FIELD MEASUREMENT:
Verify field measurements prior to installation precast work. Do not install precast work where conditions differ from those shown on Drawings or in Specifications.
B. CLEANING:
Remove dirt and setting materials on finish surfaces prior to application of mortar, pre-cast concrete materials or signs.
3.03 INSTALLATION
A. Do not install any precast units that have any defects that exceed the acceptable PCI MNL-117 tolerances for dimensions and color if installation would result in unsatisfactory performance or appearance in the opinion of the Owners Representative.
B. Install precast concrete members plumb, level, and in alignment in accordance with PCI MNL- 117 erection tolerances and the contract documents. Provide temporary supports and bracing as required to maintain position, stability, and alignment as members are being permanently connected.
C. Protect the precast units from discoloration and staining when washing down the surrounding masonry by covering the precast units with plastic sheeting and/or by thoroughly soaking them with clear water to prevent dirty washdown water from being absorbed into them. If dirty washdown water gets on the precast, hose it off immediately with clear water.
D. Patching or repair of damaged precast units is not allowed. Damaged units shall be replaced with new units. when viewed with the unaided eye under good typical day lighting at a 20 foot distance.
E. Sealing: Only exterior stair treads and other units that may come in contact with salt or other deicing compounds must be sealed with a penetrating sealer approved by the Owners representative. The sealer is to be applied in accordance with the sealer manufacturer's instructions FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
03 48 00 – PRE-CAST CONCRETE SPECIALTIES
6 of 6
after the units have been installed, cured, patched, and cleaned. Do not apply sealer before installation since it may prevent mortar, joint sealant, and patches from adhering. After application of the sealer the finish must be free of air pockets, pock marks, chipped edges, or honeycomb effects.
3.04 CLEANING
A. After completion of pre-cast concrete installation, clean surfaces of excess or spilled mortar or concrete materials. No acids or prepared cleaners shall be used without the approval of the precast Fabricator.
B. Use mild soap, fiber brushes and clean water. Avoid contamination of adjacent work.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
05 50 00 – METAL FABRICATIONS
1 of 4
SECTION 05 50 00
METAL FABRICATIONS
PART 1 – GENERAL
1.01 RELATED DOCUMENTS
Drawings and general provisions of the Contract, including General and Supplementary Conditions and Division 1 Specification Sections, apply to this Section.
1.02 SCOPE
Provide and install, complete, all metal work as shown and specified. This work includes, but is not limited to, metal signs, fasteners, piling, and site concrete.
Related work specified elsewhere:
03 48 00 Site Precast Concrete Specialties
10 14 53 Traffic Signage
26 00 00 Electrical
1.03 STANDARDS
The following standards are hereby made a part of this section and miscellaneous metal work shall conform to the applicable requirements therein except as otherwise specified herein or shown on the drawings. Nothing contained herein shall be construed as permitting work that is contrary to code requirements or governing rules and regulations.
Section 75 of the Department of Transportation Standard Specifications, latest edition.
Steel Structures Painting Council Surface Preparation Specifications, Vol. 2, Painting Manual.
1.04 SHOP DRAWINGS
Provide shop drawings per Section 01 33 00 Submittal Procedures.
PART 2 – PRODUCTS
2.01 FASTENINGS
A. Intent of Drawings: The drawings are intended to show the number, size and spacing of nails, bolts, and screws, etc., required for structural strength. If any particular joint is not shown on the drawings, it shall be FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
05 50 00 – METAL FABRICATIONS
2 of 4
provided with bolts, screws, and/or nails, as required to be consistent with the fully detailed joints and shall be subject to the approval of the Owners Representative.
B. Furnish all hardware required for fastenings, as shown on the drawings, and as specified herein, and as required to complete the work. All fasteners shall be stainless steel unless otherwise indicated. Fasteners shall include, but not be limited to, the following:
1. Nails: Unless otherwise noted, nails shall common wire of adequate size for type of fastening, ASTM-153.
2. Nuts and Bolts: Shall be machine nuts and bolts, lag bolts, or carriage bolts of structural grade stainless steel conforming to ASTM A-153, of sizes indicated on the drawings. Anchor bolts shall have cut threads.
3. Washers: Shall be of stainless steel, ASTM 153.
4. Lag Screws: Shall be of structural grade stainless steel, and shall be hex headed wherever possible, ASTM 153.
2.02 MATERIALS
A. Steel Fabrications
1. Steel tube: Cold-formed, conforming to ASTM A 500, Grade B.
2. Steel plates, shapes, bars: Conforming to ASTM A 36.
3. Concrete inserts: Malleable iron, ASTM A 47, or cast steel, ASTM A 27, inserts, with steel bolts, washers, and shims; hot dip galvanized.
4. Anchors and inserts: Furnish inserts and anchoring devices to be built into other work for installation of miscellaneous metal items.
Coordinate delivery to job site to avoid delay. Use non-ferrous metal or hot dip galvanized anchors and inserts for exterior resistance. Use toothed steel or lead expansion bolt devices for drilled-in-place anchors. Furnish inserts, as required, to be set into concrete or masonry work.
5. Fasteners: Use fasteners made of the same basic metal as the fastened metal, unless otherwise indicated. Do not use metals that are corrosive or incompatible with materials joined. Provide exposed fasteners, if any, which match finish of fastened metal, unless otherwise indicated.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
05 50 00 – METAL FABRICATIONS
3 of 4
B. Aluminum fabrications shall include, but not be limited to, the following:
1. Aluminum piles
2. Aluminum bolt clips
3. Bolts and nuts for clips
4. Crossbrace bolts and nuts
5. End caps
6. Rivets for end caps
7. Aluminum Signs
8. All other necessary miscellaneous parts and materials.
9. The above-mentioned items shall be either:
a. Dant Alum-A-Stand, available through Ross Recreation Equipment, P.O. Box 785, Novato, CA 94947 (415) 892-
0717.
b. Aluminum planking, available through Playground Products, Inc., 1761 Smith Avenue, San Jose, CA 95112 (408) 998-
4090.
c. Approved equal.
All aluminum shall be marine grade and corrosion resistant.
PART 3 – EXECUTION
3.01 GENERAL
A. Verify all measurements at site prior to ordering materials.
B. Coordinate all metal work with adjoining work for details of attachment, fitting, etc. Do all cutting, shearing, drilling, punching, threading, tapping, etc., required for miscellaneous metal or for attachment of adjacent work.
Drill or punch holes; do not use cutting torch. Shearing and punching shall leave true lines and surfaces.
C. Conceal all fastenings where practicable. Thickness of metal and details of assembly and supports shall give ample strength and stiffness. Form joints exposed to weather to exclude water.
D. Provide all lugs, clips, anchors, and miscellaneous fastenings necessary for the complete assembly and installation.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
05 50 00 – METAL FABRICATIONS
4 of 4
E. Set all work plumb, true, rigid, and neatly trimmed out.
F. Where items must be incorporated or built into adjacent work, deliver to trade responsible for proper location of such items.
3.03 BOLTED, SCREWED AND RIVETED CONNECTIONS
A. In general, use bolts for field connections only as detailed. Provide washers under all heads and nuts. Draw all nuts tight and nick threads of permanent connections to prevent loosening. Use beveled washers where bearing is on sloped surfaces.
B. Each bolt hole shall be drilled 1/16 inch larger than the bolt diameter.
C. Where screws must be used for permanent connections in ferrous metal, use flat head type, countersunk, with screw slots filled and finished smooth and flush.
3.04 CLEAN UP
A. Protection and Cleaning: Remove all soiled and foreign matter from finished surfaces and apply such protective measures as required to prevent damage or discoloration of any kind until acceptance of project.
B. During construction, keep premises as clear as possible of materials and debris, and at the completion of work remove all tools, appliances, materials, and debris from the premises.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
10 14 53 – TRAFFIC SIGNAGE
1 of 6
SECTION 10 14 53
TRAFFIC SIGNAGE
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. Furnishing and installing roadside traffic signage.
B. Install new signs on metal poles, unless otherwise indicated.
C. Preservative treatment for wood posts and bracing.
1.02 RELATED SECTIONS
A. Section 01 33 00 Submittal Procedures
1.03 REFERENCES
A. American Society for Testing and Materials (ASTM):
1. ASTM A36 – Carbon Structural Steel
2. ASTM A53 – Pipe, Steel, Black and Hot-Dipped, Zinc-Coated Welded and Seamless
3. ASTM A123 – Zinc (Hot-Dip Galvanized) Coatings on Iron and Steel Products
4. ASTM A153 – Zinc Coating (Hot-Dip) on Iron and Steel Hardware
5. ASTM A167 – Stainless and Heat-Resisting Chromium-Nickel Steel Plate, Sheet, and Strip.
6. ASTM A325 – Structural Bolts, Steel, Heat Treated, 120/105 ksi Minimum Tensile Strength
7. ASTM A653 – Steel Sheet, Zinc-Coated (Galvanized) or Zinc-Iron AlloyCoated (Galvannealed) by the Hot-Dip Process
8. ASTM A1011 – Steel, Sheet and Strip, Hot-Rolled, Carbon, Structural, HighStrength Low-Alloy, High-Strength Low-Alloy with Improved Formability, and Ultra-High Strength
B. State of California, Department of Transportation (Caltrans)
1. Caltrans – California Manual on Uniform Traffic Control Devices (MUTCD), and Uniform Sign Chart
2. Caltrans – 2018 Standard Specifications and Uniform Sign Chart FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
10 14 53 – TRAFFIC SIGNAGE
2 of 6
C. California Redwood Association:
1. Redwood Inspection Service (RIS) - Grades of California Redwood Lumber D. Western Wood Products Association (WWPA):
1. Western Lumber Grading Rules
E. West Coast Lumber Inspection Bureau (WCLIB):
1. Standard No. 17 – Grading Rules for West Coast Lumber F. American Wood Protection Association (AWPA):
1. AWPA Book of Standards
a. AWPA U1 – Use Category System
b. AWPA M4 – Care of Preservative-treated Wood Products
1.04 QUALITY ASSURANCE
A. Comply with Project Quality Program Requirements (see 1.02 above).
B. Manufacturer and Applicator/Installer Qualifications:
1. Manufacturer’s Qualifications: Minimum of 5 years’ experience in manufacturing of specified materials/products, with record of successful inservice performance.
2. Applicator/Installer Qualifications: Engage applicator/installer with minimum 5 years’ experience in installation of materials/products similar in material, design, and to extent indicated for this Project.
a. Installer Certification: Obtain written certification from manufacturer, certifying that installer is approved by, licensed, or certified by manufacturer for installation of specified materials/products or systems. b. Provide list of minimum 5 projects similar in nature and size to that of this Project, where specified materials/products have been successfully installed/used.
C. Marker Panels: Type N, Type P, and Type R mounted on post with traffic sign are considered to be sign panels.
D. Sign Panels Furnished and Installed by Contractor: Reflectorized on aluminum sheeting material.
1. Conform to Caltrans Uniform Sign Chart for size, shape, color, and legend of each sign.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
10 14 53 – TRAFFIC SIGNAGE
3 of 6
1.05 SUBMITTALS
A. Refer to Section 01 33 00 Submittal Procedures, for submittal requirements and procedures.
B. Material Safety Data Sheets (MSDS): Manufacturer’s Material Safety Data Sheets for each type of material used in Work.
1.06 DEFINITIONS
A. VOC: Volatile Organic Compound, as defined in NCAQMD Rule 101 – Definitions:
1. Any volatile compound of carbon, excluding methane, carbon monoxide, carbon dioxide, carbonic acid, metallic carbides or carbonates, ammonium carbonate, and exempt compounds.
B. NCAQMD: North Coast Air Quality Management District
1.07 REGULATORY REQUIREMENTS
A. Conform to requirements of Federal, State, and local authorities having jurisdiction.
PART 2 - PRODUCTS
2.01 MATERIAL
A. Metal Posts:
1. Mountings for Traffic Signs: Installed on barriers or railings. a. Fabricate from minimum 14 gage welded or seamless steel pipe conforming to ASTM A53 Grade B, and structural steel conforming to ASTM A36 or ASTM 1011, Grade 33.
b. Bolted Connections and Anchorages: Conform to provisions in Section 55-
1.02D(6) and Caltrans 2018 Standard Specifications, Section 75-1.02. c. Concrete Anchorage Devices: Conform to requirements in Caltrans 2018 Standard Specifications, Section 75-3.92C.
2. Mounting for Ground-Mounted Traffic Signs: Wide flange metal posts fabricated from structural steel conforming to ASTM A36 or ASTM 1011, Grade 33.
a. Provide bolts, nuts, and washers for breakaway connections at wide flange steel posts conforming to ASTM A325.
3. Galvanize metal parts of traffic sign mountings after fabrication.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
10 14 53 – TRAFFIC SIGNAGE
4 of 6
a. Apply galvanizing conforming to 2018 Caltrans Standard Specifications, Section 75- 1.02B.
B. Wood Posts and Braces: Posts of nominal four inches by four inches in size, and braces, constructed from of one of following:
1. Construction Heart Grade Redwood, Highway Post Grade Redwood, or Heart Structural Grade Redwood, conforming to RIS - Grades of California Redwood Lumber
2. Light Framing Construction Grade Douglas Fir, free of heart center; or Structural Light Framing No. 2 Grade Hem-Fir, free of heart center conforming to WCLIB Standard No. 17, or WWPA - Western Lumber Grading Rules
C. Sign Panel Fastening Hardware:
1. Frame Assemblies for Multiple Sign Installations: Fabricate of structural steel conforming to ASTM A36, or of aluminum alloy, where indicated. a. Hot dip galvanized frames fabricated of structural steel after fabrication.
2. Back Braces for Signs: Commercial quality, mild steel, hot dip galvanized after fabrication.
3. Straps and Saddle Brackets: For mounting Sign Panels on electroliers, sign structure posts, and traffic signal standards.
a. Corrosion resistant chromium nickel steel conforming to ASTM A167, Type 302.
b. Theft proof bolts indicated to be stainless steel with chromium content of not less than 17 percent and nickel content of not less than eight percent.
4. Lag Screws, Bolts (except theft proof bolts), Metal Washers, and Nuts:
Commercial quality steel, hot dip galvanized after fabrication. a. Fiber Washers: Commercial quality.
5. Galvanizing: Conform to provisions in 2018 Caltrans Standard Specifications, Section 75-1.02B for iron and steel hardware.
6. Use stainless steel fastenings for wood preservative treated wood; do not use galvanized fastenings.
D. Wood Preservative Treated Materials:
1. Where lumber is indicated or specified to be preservative treated, comply with applicable requirements of AWPA U1 - Use Category System:
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
10 14 53 – TRAFFIC SIGNAGE
5 of 6
a. Pressure treat wood members in contact with ground or fresh water with waterborne preservative to minimum retention of 0.40 lbs./cu. ft. b. Pressure treat above ground wood members with waterborne preservative to minimum retention of 0.25 lbs./cu. ft.
c. After treatment, kiln-dry lumber to maximum moisture content of 19 percent.
2. Complete fabrication of treated items prior to treatment where possible. a. If cut after treatment, coat cut surfaces to comply with AWPA M4.
PART 3 - EXECUTION
3.01 CONSTRUCTION
A. Excavate holes to required depth for bottom of posts, as indicated B. Place posts in holes excavated in ground.
C. Line between center of top of post and center of post at ground line to be plumb within tolerance not to exceed 0.02 foot in ten feet.
D. Backfill space around wooden posts to finished ground surface with selected earth or sand, free of rocks or other deleterious material.
1. Place backfill material in layers approximately 0.33 foot thick; moisten each layer and thoroughly compact.
E. Backfill metal posts with Class C Portland cement concrete conforming to provisions in Caltrans Standard Specifications, Section 90 or, at Contractor’s option.
1. Backfill material may consist of Portland cement concrete produced from commercial quality aggregates and cement, containing not less than 470 pounds of cement per cubic yard.
F. Dispose of surplus excavated material as directed by City or its designee.
G. Carefully drill holes for bolts, threaded rods, or expansion anchorage devices in existing concrete by employing methods that will not cause spalling of concrete adjacent to holes.
H. Install traffic signs at locations indicated or where directed by City or its designee conforming to provisions in Section 56 – Signs, of Caltrans Standard Specifications and where indicated.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
10 14 53 – TRAFFIC SIGNAGE
6 of 6
3.02 SIGN PANEL INSTALLATION
A. Sign Panels: Install in accordance with details shown or as directed by City or its designee.
1. Chipping or bending of sign panels is considered cause to require replacement.
B. Closure Inserts: Install into openings at edges of adjacent sign panel sections.
1. Adjacent edges of sign panels are to be in contact for their full length.
2. Mount overlapping letters and borders at sign panel joints on face of sign with blind, self-plugging type rivets.
C. Sign Panels: Attach to metal and wood posts, electroliers, sign structure posts, and traffic signal standards and mast arms with fastening hardware of types and sizes indicated.
D. Bore pilot holes with bit size equal to base of lag screw thread
1. Install lag screws by turning lag screw into pilot holes by use of wrench.
E. Furnish sign panels and fastening hardware.
F. Do not remove existing traffic signs until replacement signs have been installed or until existing signs are no longer required for direction of public traffic, unless otherwise directed by City or its designee.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
10 45 00 – ALUMINUM SIGNS
1 of 5
SECTION 10 45 00
EXTERIOR ALUMINUM SIGNS
PART 1 – GENERAL
1.01 SUMMARY
A. Description of Work
Exterior sign, of aluminum construction, non-illuminated, with flat face.
B. Related Section
Section 05 50 00 – Metals and Hardware
1.02 QUALITY CONTROL
A. SUPPLIER
Obtain all products in this section from a single supplier.
B. REGULATORY REQUIREMENTS
Products shall meet requirements of the Americans with Disabilities Act Accessibility Guidelines (ADAAG) and local amendments and modifications.
C. INSTALLER
Installation shall be performed by installer specialized and experienced in work similar to that required for this project.
D. REVIEWS
Contractor shall submit shop drawings and color samples for all sign faces to the Owners Representative prior to fabrication.
1.03 SUBMITTALS
Submit in accordance with requirements of Division 1.
A. PRODUCT DATA
Submit product data for specified products. Include material details for each sign specified.
B. SHOP DRAWINGS
Submit shop drawings showing layout, profiles, and product components, including dimensions, anchorage, and accessories.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
10 45 00 – ALUMINUM SIGNS
2 of 5
C. SAMPLES
Submit supplier’s standard color chart for selection purposes and selected colors for verification purposes.
D. INSTALLATION
Submit supplier’s installation instructions.
E. CLOSEOUT SUBMITTALS
Submit operation and maintenance data for installed products, including precautions against harmful cleaning materials and methods.
Submit warranty documents specified herein.
1.04 DELIVERY, STORAGE, AND HANDLING
Comply with requirements of Division 1.
Comply with manufacturer's ordering instructions and lead time requirements to avoid construction delays.
Deliver products in manufacturer's original, unopened, undamaged containers with identification labels intact.
Store products protected from weather, temperature, and other harmful conditions as recommended by supplier.
Handle products in accordance with manufacturer's instructions.
PART 2 – PRODUCTS
2.01 SUGGESTED MANUFACTURERS OR APPROVED EQUIVALENT
A. Security Signs
2424 SE Holgate
Portland, Oregon 97202
Ph: 503.232.4172
www.securitysigns.com
B. Sea Reach Limited
146 NE Yamhill Street Sheridan, OR 97378
503·843·2005 phone
503·843·2744 fax
[email protected]
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
10 45 00 – ALUMINUM SIGNS
3 of 5
2.02 SIGNAGE MATERIALS / COMPONENTS
A. Materials and Components:
1. Aluminum Panels: Alumalite plate, thickness and size as specified by plans. Dimensions as shown on drawings.
2. Surface Treatment Finish – Painted Surfaces: Apply Matthews Acrylic Polyurethane (MAP) as recommended by manufacturer specifications. Topcoat Matthews Acrylic Polyurethane 2.0 mils DFT. (min.) Use colors selected from manufacturer’s standard colors.
3. Surface Treatment Finish – Vinyl: Vinyl applications to be 3M marinegrade.
4. Fasteners: All fasteners must be corrosion resistant stainless steel.
2.03 FABRICATION – GENERAL
A. General: Comply with requirements indicated for materials, thicknesses, finishes, colors, designs, shapes, sizes, and details of construction.
B. Allow for thermal movement resulting from a maximum ambient temperature change (range) of 100 °F (38 °C). Design, fabricate, and install sign assemblies to prevent buckling, opening up of joints, and overstressing of welds and fasteners.
C. Mill joints to a tight, hairline fit. Form joints exposed to the weather to exclude water penetration.
D. Preassemble signs in the shop to the greatest extent possible to minimize field assembly. Disassemble signs only as necessary for shipping and handling limitations. Clearly mark units for reassembly and installation, in a location not exposed to view after final assembly.
E. Conceal fasteners if possible; otherwise, locate fasteners to appear inconspicuous.
F. Form panels to required size and shape. Comply with requirements indicated for design, dimensions, finish, color, and details of construction.
G. Coordinate dimensions and attachment methods to produce message panels with closely fitting joints. Align edges and surfaces with one another in the relationship indicated.
H. Increase material thickness or reinforce with concealed stiffeners or backing materials as required to produce surfaces without distortion, buckles, warp, or other surface deformations.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
10 45 00 – ALUMINUM SIGNS
4 of 5
I. Avoid seams in Alumalite panels when possible, if seams are unavoidable conceal them to the greatest extent possible.
PART 3 – EXECUTION
3.01 EXAMINATION
A. Site Verification of Conditions: Verify installation conditions previously established under other sections are acceptable for product installation in accordance with manufacturer's instructions.
B. Scheduling of installation by Owner or its representative implies that substrate and conditions are prepared and ready for product installation.
Proceeding with installation implies installer’s acceptance of substrate and conditions.
3.02 INSTALLATION
Install product in accordance with supplier’s instructions.
Install product in locations indicated using mounting methods recommended by sign manufacturer and free from distortion, warp, or defect adversely affecting appearance.
Install product level, plumb, and at heights indicated.
Install product at heights to conform to Americans with Disabilities Act Accessibility Guidelines (ADAAG) and applicable local amendments and regulations.
Install signs within the following tolerances and in accordance with manufacturer's recommendations:
Within ¼ inch vertically and horizontally of intended location.
3.03 CLEANING, PROTECTION, AND REPAIR
Repair scratches and other damage which might have occurred during installation. Replace components where repairs were made but are still visible to the unaided eye from a distance of 10 feet as determined by Owner.
Remove temporary coverings and protection to adjacent work areas. Clean installed products in accordance with manufacturer's instructions prior to Owner's acceptance. Remove construction debris from project in accordance with provisions in Division 1.
3.04 SIGN SCHEDULE
Schedule: Refer to signage schedule and Drawings for sizes, locations, and layout of signage types, sign text copy, and graphics.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
10 45 00 – ALUMINUM SIGNS
5 of 5
PART 4 - MEASUREMENT AND PAYMENT
4.01 All work under this section shall be paid for at the lump sum price bid for exterior aluminum signs and shall include full compensation for furnishing all labor, materials, tools, equipment, and incidentals, and for doing all the work involved in exterior aluminum signs, and related incidental work.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
22 14 00 – STORM DRAINS
1 of 7
SECTION 22 14 00
STORM DRAINS
PART 1 – GENERAL
The work to be done under this section shall include the furnishing of all materials, labor, tools, equipment, and necessary incidentals to install new storm drainpipe complete and in place.
PART 2 – PRODUCTS
2.01 PIPE
Storm drainpipe shall be dual wall corrugated high density polyethylene pipe with smooth interior with integral bell conforming to AASHTO M294, Type S, such as manufactured by ADS, Inc. N-12 ST IB pipe, or equal. Joints shall be “water tight” meeting the requirements of ASTM D3212. Storm drain pipe shall be of the size designated on the Plans. Fittings shall meet the requirements of AASHTO M294.
Pipe shall use an integral bell and spigot joint meeting AASHTO M294. The joint shall be joined water tight. The outside diameter of the integral bell and spigot joint shall not be more than 2 inches greater than the average outside diameter of the pipe barrel.
Contractor shall submit manufacturer’s and supplier’s certification that pipe and fittings provided comply with these Special Provisions.
Storm drainage inlets (drop inlets) shall be Type GO per Caltrans Standard Plans (Drawing D74B). Drainage inlets maybe either cast-in-place or precast units. Inlet grates shall be Type 24-12 per Caltrans Standard Plans (Drawing D77A).
Junction boxes shall be as specified in Section 03 30 00.
2.02 IMPORT MATERIALS
For any import materials the Contractor proposes to use in the backfill of any excavation, the Contractor shall submit test reports from a certified laboratory demonstrating the proposed material complies with these Special Provisions. Import materials include, stabilization material, bedding material, embedment material, backfill, slurry, concrete, and aggregate base material.
2.03 GEO-TEXTILE
Geo-textile shall be GEOTEX 2X2HF as manufactured by Propex, Marafi 600X as manufactured by TenCate, or equal woven polypropylene fabric grid fabric. Contractor shall submit manufacturer’s data sheets for the geo-textile to be used according to Section 31 20 00.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
22 14 00 – STORM DRAINS
2 of 7
PART 3 – EXECUTION
3.01 GENERAL
The Contractor shall provide all labor, materials, tools, equipment, and necessary incidentals, to install storm drainpipe as indicated on the Plans, described herein or as otherwise required for a complete job.
Before excavation for the installation of any storm drain near where there are buildings possibly connected to the sanitary sewer system, the Contractor shall locate, by “pothole” excavation, all existing sewer service laterals adequately to determine if there is any conflict with the storm drain installation.
Contractor shall bypass all storm water flows around his work. The bypassed flows shall be discharged to the existing storm drainage system. Bypasses shall not overload the capacity of the storm drainage system being used.
3.02 PIPE HANDLING
Care shall be taken during transporting of the pipe to ensure that the pipe is not cut or damaged in any manner. Pipe bowed, deformed, cut, or otherwise damaged during shipping or storage will be rejected.
Pipe stored on the job site shall be covered with canvas or other opaque material to protect it from the sun's rays. Air circulation shall be provided under the covering.
The pipe, especially the inside of the pipe and ends, shall be kept clean at all times, including while stored, during and after laying.
3.03 TRENCH EXCAVATION
The Contractor shall complete all excavation regardless of the type, nature, or condition of the materials encountered.
Existing buildings, power and telephone lines, fences, waterlines, storm drains or other conduits, curbs, sidewalks, and other structures in the vicinity of the work shall be supported and protected from injury by the Contractor during the construction and until the completion of the work. The Contractor shall repair, at his/her expense, any damage to such facilities.
Existing asphaltic pavement shall be saw cut, wheel cut or ground out to the limits shown on the Plans or, where not shown on the Plans to the anticipated limits of the excavation. The asphaltic concrete pavement edges must be saw cut prior to re-paving.
Asphaltic concrete must be removed from the Project area.
Contractor shall “pothole” at each end of a section of storm drain that connects with existing storm drains before excavating the trench between ends in order to establish the FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
22 14 00 – STORM DRAINS
3 of 7
alignment for the storm drain to be installed. The alignment shall be approved by the Engineer prior to trenching that section.
The Contractor shall control excavations and stockpiling in a manner to prevent water from entering the excavations.
Contractor shall keep all excavations free of water during construction in accordance with the approved Dewatering Plan.
If the trench width or depth exceeds that shown on the Plans, the additional bedding, embedment and backfill materials required shall be supplied and installed at no additional cost.
Excavated pipe, fittings, manholes, organic debris, and material determined by the Engineer to be unsuitable shall be immediately removed from the Project area.
Where concrete pavement, including street pavement, sidewalks, and pedestrian walkways, are to be removed, it shall be saw cut or removed at existing full-depth joints. All concrete pavement shall be removed from the Project area.
Except where excavated soils will be used for backfill, the Contractor shall remove all excavated material from the Project site.
Disposal of excavated material is the responsibility of the Contractor. The Contractor shall be responsible for all costs associated with disposal of materials produced from excavation. The Contractor shall obtain the required permits for disposal of materials produced during excavation.
3.04 PIPE LAYING
The pipe shall be carefully lowered in the trench to prevent damage. Pipe shall not be dropped or dumped into the trench.
Pipe shall be placed online and grade in accordance with the Plans or as modified by the Engineer. Some deviation in the horizontal alignment may be required to properly connect with junction boxes.
The maximum deviation for storm drainpipe is 0.25 feet for horizontal alignment and 0.02 feet for flow grade.
The pipe shall be placed on an unyielding foundation true to the approved line and grade with uniform bearing under the full length of the pipe with hand excavation (bell holes) at the couplings. In no case shall the pipe be supported by the coupling or bell. Pipe shall be centered in the trench.
The pipe must not be placed in water. The trench must be dewatered as provided in FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
22 14 00 – STORM DRAINS
4 of 7
Section 31 23 19, “Dewater Excavations” before placing any bedding material or stabilization material.
Cut pipe as recommended by the pipe manufacturer. Dress cut ends as recommended by the coupling and/or pipe manufacturer.
Pipe, especially the ends, shall be carefully cleaned before the pipe is joined. Whenever work ceases for any reason, the end of the pipe shall be closed with a watertight fitting, plug or cover. The interior of the pipe shall be kept free from dirt, foreign material or debris as the work progresses and the pipe shall be cleaned after completion.
Join pipe in accordance with the manufacturer's recommendations. Lubricant if required or recommended, shall be furnished by the pipe manufacturer, and no substitutes will be permitted.
Where specific items are not covered within these Special Provisions, reference shall be made to the manufacturer's suggested specifications and installation guides.
Pipe shall be connected at manholes and/or junction boxes by either a grouted connection or a precast connector as detailed in the Plans.
3.05 STABILIZATION MATERIAL
Where soft, wet, or spongy conditions are encountered in the trench at the pipe subgrade (or structure base sub-grade), and the soil is determined to be unsuitable by the Engineer as a foundation material, the trench (or structure base) shall be over excavated as directed by the Engineer and Stabilization Material shall be imported and installed.
The geotextile grid fabric shall be placed across the bottom of the excavation and up the sides. No lap or splice is allowed parallel to the pipeline; only transverse laps of at least 12 inches will be permitted. After placement of the geotextile, stabilization material can be placed and compacted.
Stabilization material shall consist of uniformly graded coarse aggregate of which at least 25% by weight shall be crushed particles. The percent composition by weight shall conform to the following grading:
Sieve Size Percent Passing
3" 100%
¾" 0% - 5%
Stabilization material shall be compacted to a minimum of 90% relative compaction.
Payment for Stabilization Material will be made only if approved by the Engineer prior to installation.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
22 14 00 – STORM DRAINS
5 of 7
3.06 BACKFILL
The Contractor shall be solely responsible for providing the correct compaction equipment and techniques to achieve the compaction standards. All costs involved with achieving compaction standards shall be the Contractor’s responsibility.
Except where designated on the Plans excavated soils may NOT be used as trench backfill. All backfill material shall be 3/4-inch maximum Class 2 Aggregate Base conforming to Section 26 of the Standard Specifications.
Backfill material, above the pipe embedment zone, up to within 24 inches of the finished surface, shall be placed in lifts not to exceed 12 inches and compacted to a relative compaction density as indicated on the Plans, but in no case less than 90%.
Backfill material around structures, such as but not limited to junction boxes, shall be compacted to 95%.
Backfill materials shall be manually or mechanically compacted. Jetting will not be allowed.
Care shall be taken not to damage or displace any pipe, manholes or any structure or utility with compacting operation.
Stabilization, bedding, pipe embedment and backfill materials shall be placed and compacted in accordance with the requirements of 31 20 00, “Earth Moving”, and as shown on the Plans.
The placement and compaction of embedment material and backfill shall be accomplished in a manner that does not disturb the pipe.
The moving and/or removal of shoring, sheeting, trench boxes or shields or any other means of trench support shall not disturb the pipe location, jointing or its surrounding embedment material. Any voids left in the embedment or backfill material shall be carefully filled and compacted to the requirements of the material surrounding the void.
The removal of shoring shall not disturb the pipe, junction box or other structure or utility or cause the loss of compaction of the bedding, embedment or backfill material. Voids created by removal of shoring shall be filled with material and compacted to the requirements of the adjacent trench backfill.
3.07 BEDDING MATERIAL
Bedding material shall be ¾ inch maximum Class 2 Aggregate Base conforming to Section 26 of the Standard Specifications. Bedding material shall be compacted to a minimum of 90% relative compaction.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
22 14 00 – STORM DRAINS
6 of 7
3.08 EMBEDMENT MATERIAL
Embedment material (haunch and cover) shall be ¾ inch maximum Class 2 Aggregate Base conforming to Section 26 of the Standard Specifications. Embedment material shall be placed in layers, each layer not to exceed 8 inches and compacted before the placement of the next layer. Embedment material shall be worked under both sides of the pipe in the haunch area to provide uniform support. The embedment material shall be filled to an elevation of 12 inches above the top of the pipe. All materials placed in the pipe embedment zone shall be compacted by hand, light mechanical equipment or other means that will not damage or move the pipe. Embedment material shall be compacted to 90% relative density.
The Contractor’s testing agent shall determine if the required compaction standards have been achieved according to the results of compaction testing per California Test 216 or 231.
A failing test indicates that the required compaction standards have not been achieved.
Trench or other fill areas that fail compaction tests shall be reworked or re-excavated and replaced, if necessary, at no additional cost to the City.
The Contractor’s testing agent will make compaction tests when advised by the Contractor that the densities have been achieved. The Contractor shall give the Engineer at least 24 hours’ notice that compacted material is ready to be tested. Failure to give adequate notice can result in testing delays which will be the responsibility of the Contractor. The Engineer shall determine the number and location of tests required. Contractor shall, at no cost to the City, make all excavations needed to perform the compaction tests. Excavations for compaction tests shall be backfilled with material similar to that excavated and compacted to the specified density.
It is estimated that approximately one compaction test will be taken for every 100 feet of trench. The quantity of tests does not include those tests that fail to meet the specified relative density. The number of tests may be increased or decreased based on Contractor performance in meeting compaction requirements (high failure rate means more tests; low failure rate means fewer tests).
The Contractor shall not proceed with placement of succeeding lifts of material until the previous lifts have achieved the specified compaction. Failure to comply with this requirement will result in the rejection of all lifts above the failing layer.
The Contractor will bear the cost of all compaction testing.
3.09 GUARANTEE
The Contractor shall guarantee his work against settlement for a period of one year after filing the Notice of Completion. The Contractor shall repair, at his expense, any settlement within that time. Settlement will be deemed to have occurred if:
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
22 14 00 – STORM DRAINS
7 of 7
1. City streets or concrete walkways: a depression of 0.05 foot below the lower edge of a 12-foot straight edge.
2. Unpaved areas: a depression of 1½ inches below the average of the sides of the uncut area.
3. Any settlement that causes drainage problems, such as ponding of water, or concentrates flowing water resulting in soil erosion.
3.10 CLEANING
The pipe shall be kept clean at all times. After backfill has been placed and junction boxes installed, the pipe (whether new or existing), junction boxes (whether new or existing), drainage inlets (whether new or existing), and all other components of the storm drain system shall be cleaned of any accumulated debris. No debris of any type shall be allowed to remain in the finished installation. Debris cleaned from the line shall be removed at each manhole, drainage inlet, or junction box. Debris shall be removed from the job site. Use of cleaning pig is required.
All existing storm drains that will remain in service at end of project shall be cleaned by mandrel or cleaning pig of an appropriate diameter within 60 days of notice to proceed.
3.11 INSPECTION
After initial cleaning of existing storm drains to remain, the City may preform inspections and make additional repair recommendations and requests.
After completion of the storm drainpipe, including junction boxes and the placement of backfill the storm drain pipe may be television inspected by the City. Any defects in the pipe, debris encountered, leaks observed, open joints, excessive deflection (5% of the average inside diameter), or any other defects in material or workmanship shall be corrected by the Contractor.
Where infiltration is observed, the Contractor shall make the necessary repairs to eliminate any visible infiltration. All visible leakages shall be repaired regardless of test results. Repairs shall be made at no cost to the City.
Any cracks, open joints or other defects shall be repaired by the Contractor at no cost to the City, even if no infiltration is observed.
For one year after Project completion, the City may, at its expense, conduct such additional inspections and tests it deems necessary, such as television inspection and mandrel deflection test. If any defect is observed, including but not limited to cracks, leaks, offset or separated joints or excessive deflection, the Contractor shall, at his/her expense, make the necessary repair(s) to correct the defect(s). (Excessive deflection is that exceeding 5% of the average inside diameter of the pipe.) The corrective work shall be commenced within 30 days of notification of the test results. The methods of correction shall be subject to the City’s review and approval.
END OF SECTION
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
26 00 00 – ELECTRICAL
1 of 13
SECTION 26 00 00
ELECTRICAL
PART 1 - GENERAL
1.01 SECTION INCLUDES
A. WORK INCLUDED:
1. Provide all required labor, project equipment, materials, tools, construction equipment, safety equipment, transportation, test equipment, and satisfactorily complete all electrical work shown on the Drawings, included in these Specifications, or required for a complete and fully operating facility. In addition, provide wiring for the equipment that will be provided under other Divisions of these Specifications.
2. Provide conduit and wire for streetlights and bollards. Contractor shall be responsible for conduit and wire to these devices even if not specifically shown on the Drawings or specified herein.
3. Provide metered service equipment and service disconnect switches. All enclosures for this project shall be NEMA 3R or 4X depending on actual locations.
4. Salvaged Materials – At least 2 business days before hauling the material to the salvaged material stockpile location, notify the Director.
The stockpile location is:
Crescent City Corporation Yard
900 10th Street,
Crescent City, CA 95531
B. SAFETY:
Conduct operations in accordance with NFPA 70E, Standard for Electrical Safety Requirements for Employee Workspaces.
1.02 SUBMITTALS
A. SHOP DRAWINGS:
1. GENERAL: Submit Product Review or Product information shop drawings for materials and equipment as required under each Specification Section.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
26 00 00 – ELECTRICAL
2 of 13
2. For Product Review submittals, submit a single, complete submittal package for all items specified in a particular Specification Section.
Submittal packages shall be organized by equipment type. Include separators and tabs or other means of identifying each
Specification paragraph (e.g., 2.01, 2.02, etc.) of the submittals or other means of identifying each section of the submittal.
B. AS-BUILT SHOP DRAWINGS:
The Contractor shall submit redlined drawings that provide current factual information including deviations from, and amendments to the drawings and changes in the work, concealed and visible, shall be provided as instructed. The as-built drawings shall show all new installations with respect to fixed installations not associated with the systems specified herein. Cable and wire shall be accurately identified and shall locate the connection and routing to and away from bases, housings, and boxes.
Prior to Final Acceptance, deliver one complete set to the Engineer for review. After such review, provide copies of all CAD produced drawings on storage media satisfactory to the Engineer in AutoCAD DWG format.
C. MANUALS:
1. Furnish manual for equipment where Manuals are specified in the equipment Specifications. Electrical manual shall be consolidated and submitted as a single manual.
2. Include equipment descriptions, record shop drawings, operation and maintenance instructions, parts ordering data, and ratings for the equipment furnished for this project.
D. SPARE PARTS:
For each piece of equipment, submit a list of recommended spare parts.
Include part numbers and the name, address, and telephone number of the supplier.
E. The following shall be submitted in accordance with Section 01 33 00, Submittal Procedures:
1. SHOP DRAWINGS
a. Metered service equipment
b. Wiring and circuit diagrams
2. PRODUCT DATA
a. Enclosed circuit breakers
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
26 00 00 – ELECTRICAL
3 of 13
b. Disconnect switches
c. All dry utility products based on respective Utility Designs
1.03 QUALITY ASSURANCE
A. CODES:
All electrical equipment and materials, including installation and testing, shall conform to the following applicable codes:
1. National Electrical Code (NEC), current edition in force at the Project site
2. National Electrical Safety Code (NESC), current edition
3. Occupational Safety and Health Act (OSHA) standards
4. Acceptance Testing Specifications for Electrical Power Distribution Equipment and Systems, International Electrical Testing Association (NETA).
B. STANDARDS:
Equipment shall conform to applicable standards of American National Standards Institute (ANSI), Electronics Industries Association (EIA), Institute of Electrical and Electronics Engineers (IEEE), and National Electrical Manufacturers Association (NEMA). The revisions of these standards in effect on the date of issuance of the Contract Documents shall apply.
C. LABELING:
Underwriters Laboratories (UL) listing is required for all equipment and materials where such listing is offered by the Underwriters Laboratories.
Safety labeling and listing by other organizations, such as ETL Testing Laboratories, may be substituted for UL labeling and listing if acceptable to the authority having code enforcement jurisdiction. Provide service entrance labels for all equipment required by the NEC to have such labels.
D. CONTRACTOR'S EXPENSE:
Obtain and pay for all required bonds, insurance, licenses, permits and inspections, and pay all taxes, fees, and utility charges that will be required for the electrical construction work.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
26 00 00 – ELECTRICAL
4 of 13
1.04 DRAWINGS
A. DRAWINGS:
The Electrical Drawings are diagrammatic; exact locations of electrical products shall be verified in the field with the Engineer. Except where special details are used to illustrate the method of installation of a particular piece or type of equipment or material, the requirements or descriptions in this Specification shall take precedence in the event of conflict.
1. Locations of equipment, panelboards, pull boxes, conduits, stubups, power pedestals, and lighting fixtures are approximate unless dimensioned; verify locations with the Engineer prior to installation.
2. Field verify scaled dimensions on Drawings.
3. Review the Drawings and Specification Divisions of other trades and perform the electrical work that will be required for the installations.
4. Should there be a need to deviate from the Electrical Drawings and Specifications, submit written details and reasons for all changes to the Engineer for review.
5. Seismic Certification: Design Calculations and attachment drawings as required by elsewhere.
B. AS-BUILT DRAWINGS:
1. Maintain a complete and accurate record set of Drawings for the electrical construction work.
2. Record all work that is installed differently than shown on the Drawings.
3. Upon completion of the work, transfer all marked changes to a clean set of full-size Drawings with red ink. Mark the Drawings "RECORD DRAWINGS" and submit them to the Engineer when the electrical work is completed.
4. Locate all underground conduits using an Engineer or Surveyor qualified to perform topographic surveying.
1.05 FACTORY TESTS
A. Submit reports of factory tests and adjustments performed by equipment manufacturers to the Engineer prior to field testing and adjustment of the FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
26 00 00 – ELECTRICAL
5 of 13
equipment. These reports shall identify the equipment and show dates, results of tests, measured values, and final adjustment settings. Provide factory tests and adjustments for equipment where factory tests are specified in the equipment Specifications.
1.06 INSPECTIONS
A. The Engineer may inspect the fabricated equipment at the factory before shipment to job site. Provide the Engineer with sufficient prior notice so that an inspection can be arranged at the factory.
B. Inspection of the equipment at the factory by the Engineer will be made after the manufacturer has performed satisfactory checks, adjustments, tests, and operations.
C. Review of the equipment at the factory shall not relieve the Contractor of responsibility for the proper installation and satisfactory startup operation of the equipment to the satisfaction of the manufacturer and the Engineer.
1.07 COORDINATION
A. Coordinate the electrical work with the other trades, code authorities, utilities, and the Owner.
B. Where connections must be made to existing installations, properly schedule all the required work, including the power and control system shutdown periods. Schedule and carry out shutdowns so as to cause the least disruption to operation of the Owner’s facilities and privately owned facilities.
C. When two trades join together in an area, make certain that no electrical work is omitted.
1.08 JOB CONDITIONS
A. OPERATIONS:
1. Keep all power shutdown periods to a minimum.
2. Carry out shutdowns only after the schedule has been reviewed and accepted by the Engineer.
B. CONSTRUCTION POWER:
1. Make all arrangements for the required construction power.
2. When required, provide all equipment, materials, and wiring in accordance with the applicable codes and regulations.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
26 00 00 – ELECTRICAL
6 of 13
3. Upon completion of the project, remove all temporary construction power equipment, material, and wiring from the site as the property of the Contractor.
C. STORAGE:
Provide adequate storage for all equipment and materials which will become part of the completed facility so that it is protected from weather, dust, water, or construction operations. All equipment shall be stored in accordance with manufacturer’s recommendations. Provide this information upon request by Engineer.
1.09 DAMAGED PRODUCTS
A. Notify the Engineer in writing in the event that any equipment or material is damaged.
B. Obtain prior review by the Engineer before making repairs to damaged products.
1.10 OPTIONAL EQUIPMENT
A. For optional or substituted equipment, refer to Division 1.
1.11 LOCATIONS
A. GENERAL: Use equipment, materials, and wiring methods suitable for the types of locations in which they are located, as defined in Paragraph 1.11 B herein.
B. DEFINITIONS OF TYPES OF LOCATIONS:
1. Dry Locations: All those indoor areas which do not fall within the definition below for Wet Locations and which are not otherwise designated on the Drawings.
2. Wet Locations: All locations exposed to the weather, whether under a roof or not, unless otherwise designated on the Drawings.
PART 2 - PRODUCTS
2.01 STANDARD OF QUALITY
A. Products that are specified by manufacturer, trade name, or catalog number establish a standard of quality and do not prohibit the use of equal products of other manufacturers provided they are approved by the Engineer prior to installation.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
26 00 00 – ELECTRICAL
7 of 13
B. It is the intent of these Specifications and Drawings to secure high quality materials and equipment in order to facilitate operation and maintenance of the facility. All equipment and materials shall be new and the products of reputable suppliers having adequate experience in the manufacture of these particular items. For uniformity, only one manufacturer will be accepted for each type of product. All equipment shall be designed for the service intended and shall be of rugged construction, of ample strength for all stresses that may occur during fabrication, transportation, erection, and continuous or intermittent operation. All equipment shall be adequately stayed, braced, and anchored and shall be installed in a neat and workmanlike manner. Appearance and safety, as well as utility, shall be given consideration in the design of details.
C. All components and devices installed shall be standard items of industrial grade, unless otherwise noted, and shall be of sturdy and durable construction suitable for long, trouble-free service.
2.02 NAMEPLATES
A. For each piece of electrical equipment, provide a manufacturer's nameplate showing manufacturer’s name, location, the pertinent ratings, and the model designation.
B. Identify each piece of equipment and related controls with a rigid laminated engraved phenolic nameplate. Engrave nameplates with the inscriptions indicated on the Drawings and, if not so indicated, with the equipment name. Securely fasten nameplates in place using two stainless steel screws or, where approved by the Engineer, with epoxy cement.
Where no inscription is indicated on the Drawings, furnish nameplates with an appropriate inscription furnished by the Engineer upon prior request by the Contractor.
2.03 FASTENERS
A. Fasteners for securing equipment to walls, floors, and the like shall be stainless steel. When fastening to existing walls, floors, and the like, provide wedge anchors. Provide capsule anchors for bolts 3/8-inch and larger. Size anchors to meet load requirements.
2.04 PAINTING
A. Equipment: Repair any final paint finish that has been damaged or is otherwise unsatisfactory, to the satisfaction of the Engineer.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
26 00 00 – ELECTRICAL
8 of 13
2.05 ENCLOSURES
A. Unless otherwise noted, provide enclosures as follows:
1. Dry Locations: NEMA Type 1.
2. Wet Locations: NEMA Type 3R or 4X, as noted on the Drawings.
2.06 PRE-CAST CONCRETE BOXES AND COVERS
A. Pre-cast concrete boxes and covers shall conform to California Standard Specifications. Lids shall be traffic rated. Provide submittals in accordance with Section 01 33 00 “Submittal Procedures.” PART 3 - EXECUTION
3.01 REQUIREMENTS
A. All electrical installations shall conform to the codes and standards outlined in this Section.
3.02 WORKMANSHIP
A. Assign a qualified representative who shall supervise the electrical construction work from beginning to completion and final acceptance.
B. Perform all labor using qualified craftsmen, who have had experience on similar projects. Provide first-class workmanship for all installations.
C. Ensure that all equipment and materials fit properly in their installations.
The installation shall comply with the requirements and recommendations of NFPA 70 and IEEE C2, and local codes where required.
1. Metallic Materials: Metallic materials shall be protected against corrosion as specified. Aluminum shall not be used in contact with concrete. Where aluminum conductors are connected to dissimilar metal, suitable dielectric fittings shall be used.
2. Ferrous Metal Hardware: Ferrous metal hardware shall be hot dip galvanized in accordance with ASTM A 123/A 123M and ASTM A 153/A 153M.
D. Perform any required work to correct improperly fit installations at no additional expense to the Owner. The Contractor shall become familiar with details of the work, verify dimensions in the field, and advise the Owner of any discrepancy before performing any work.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
26 00 00 – ELECTRICAL
9 of 13
3.03 EXCAVATION AND BACKFILL
A. Provide the excavations for electrical equipment foundations and trenches for conduits as shown on the Drawings.
B. Exercise caution during all excavation work and avoid damage to existing underground pipes. Exercise extreme caution when working near existing electrical conduits and facilities. Field verify the location of all electrical facilities before proceeding with any nearby work.
C. Refer to Division 31 Earthwork of these Specifications for all excavation and backfilling work.
3.04 CONCRETE
A. Where shown on the Drawings or specified, provide the required concrete installations for conduit encasement and equipment foundations.
B. Refer to Division 3 Concrete of these Specifications for all concrete work.
3.05 CONDUCTOR IDENTIFICATION
A. Identify all wires and cables in conformance with the requirements of Section 26 10 00. This requirement applies to all equipment provided under this contract, regardless of Division, as well as to all conductors provided or worked on during this contract.
3.06 INSTALLING EQUIPMENT
A. Provide the required inserts, bolts, anchors, and securely attach all equipment and materials to their supports.
B. Install all floor mounted equipment on 3-inch high reinforced concrete pads. The Contractor, suppliers, and fabricators shall take this requirement into consideration when designing, fabricating, and installing panels and other enclosures so that height above the floor of the operating handles of electrical devices meets the requirements of these Specifications and applicable codes.
3.07 CUTTING, DRILLING, AND WELDING
A. Provide any cutting, drilling, and welding that is required for the electrical construction work.
B. Structural members shall not be cut or drilled, except when favorably reviewed by the Engineer. Use a core drill wherever it is necessary to drill through concrete or masonry.
FRONT STREET GATEWAY IMPROVEMENTS PHASE 1C - REISSUE
CONTRACT 2025-1002.33
26 00 00 – ELECTRICAL
10 of 13
C. Provide the required welding for equipment supports. Conduits and fittings shall not be welded to structural steel.