Cities Index.
BFP Phase 1B Addenda Four 4-14-26

Crescent City City Council
April 23, 2026

Document
BFP Phase 1B Addenda Four 4-14-26
Meeting
April 23, 2026
Body
Crescent City City Council
Original file
2.6 MB
Text extracted from the city's file for reading and search. Open the original on www.crescentcity.org. That file is the official record.

CRESCEN

CITY OF CRESCENT CITY
CALIFORNI ADDENDUM NO. 4
FOR

BEACHFRONT PARK IMPROVEMENTS
PHASE 1B
April 14, 2026
NOTICE IS HEREBY GIVEN TO BIDDERS regarding changes to the above-mentioned project contract documents. This Amendment shall be considered part of the bid documents as though it had been issued at the same time and shall be incorporated integrally therewith. Where provisions of the following supplementary data differ from those of the original bid documents, this Amendment shall govern and take precedence.

This addendum DOES NOT change the Bid Date and Time.

Bid Date and Time remain as:

Bid date: April 17, 2026
Bid time: 3:00 p.m.

Changes to the Specifications
Bidding Schedule Section 00 41 00
Measurement and Payment - 01 20 00
Addenda #4 is updating the Bid Schedule, Section 00 41 00, of the bid documents.

Quantity changes to items:
#11 Demolition of Existing Concrete New quantity 11,500 s.f. #12 Demolition of Existing Asphalt Concrete New quantity 29,200 s.f. #13 Rough Grading Area New quantity 19,300 S.Y.
# 14 Rain Garden Excavation New quantity 830 c.y.
# 47 Concrete Vehicular Paving 6" section New quantity 39,300 s.f. # 48 Concrete Pedestrian Walks 4" section New quantity 12,440 s.f. # 49 Concrete Pedestrian Walks 4" section
Playground New quantity 5,280 s.f.
#50 Concrete Decorative Paving 4" section New quantity 2,130 s.f. #80 Playground Boulders - 2 ton New quantity 9 each
BEACHFRONT PARK IMPROVEMENTS - PHASE 1B
CONTRACT 2026-1056.3
ADDENDUM NO. 4
Addenda #4 is correcting the conflict in Measurement and Payment, Bid Item #80, Playground Boulders. This is the only change to Section 01 20 00 in this Addendum.

Changes to the Plans:

None
Attached Exhibits:

None
Questions and Answers:

Question #1 - May the bid documents be submitted electronically? ANSWER: No.

Please confirm your bid documents include the attached Bid Schedule.

Please acknowledge all received addenda on your bid documents.

This completes Addendum No. 4
It includes these (2) pages and the (2) Specification Sections listed below:
00 41 00 - Addenda #4 (4 pages), and 01 20 00 Addenda #4 (25 pages).

David yeg _April 14, 2026
David Yeager Public Works Director Date
BEACHFRONT PARK IMPROVEMENTS - PHASE 1B
CONTRACT 2026-1056.3
ADDENDUM NO. 4
SECTION 00 41 00

BIDDING SCHEDULE
PROJECT IDENTIFICATION: Beachfront Park Improvements Phase 1B THE BID IS SUBMITTED TO: City of Crescent City
BID SCHEDULE - Addenda #4
ITEM | ITEM DESCRIPTION UNIT QTY. UNIT TOTAL
NO. PRICE PRICE
1 Mobilization - Front Street 1 LS
2 SWPPP Updating and Reporting - City to 1 LS
provide initial SWPP plan
Water Pollution Prevention BMPs - prebid 1 LS 20,000 20,000 budget to be negotiated upon City provided
SWPPP approval.
4 Pedestrian and Traffic Control 1 LS
5 Tree protection fencing installation & removal 572 LF Sheeting, Shoring, Bracing 1 LS
7 Quality Control 1 LS
8 Material Testing 1 LS
9 Clear, Grub and Tree removal 1 LS
10 Demolition of Existing Facilities including 1 LS
Monument Salvage
11 Demolition of Existing Concrete 11,500 SF
12 Demolition of Existing Asphalt Concrete 29,200 SF
13 Rough Grading 19,300 SY
14 Rain Garden Excavation 830 CY
15 Import Soil for Berm Placement and 3500 CY
Amphitheater capping
16 Aggregate Base for asphalt paved section 90 CY
17 Hot Mix Asphalt Concrete 80 Ton
18 Pavement Striping and Wheel Stops 1 LS
19 Crackfill & Sealcoat Playground Parking Lot 17400 SF 20 Parking and Path of Travel signs 1 LS
21 Storm Drain 4" Solid HDPE and inlet piping 100 LF
22 Storm Drain 8" HDPE 120 LF
23 Storm Drain 12" HDPE 560 LF
24 Flared End Section - 8" and 12" 6 EA
25 Duckbill Outlet 1 EA
26 Rentention Basin Inlets - 8" & 12" 8 EA
27 French Drain with perforated 4" pipe 120 LF
28 Connect to Existing Storm Drain LS
1 29 Drainage Inlets - Type GO EA
BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
00 41 00 - BIDDING SCHEDULE - ADDENDA #4
1 of 4
30 Adjust Existing Inlets to Grade 1 EA
31 4" Sanitary Sewer Lateral DELETED 363
32 Sanitary Sewer Clean out with G-5 Bex& 3 EA ----
Lids DELETED
33 1" Water Line DELETED 340 LF ----
34 Install water meters - Meter & Meter Box 3 EA
supplied by City
35 Reconnect restroom sewer / water DELETED LS
36 Electrical - All labor, equipment, and LS
materials not covered in below items
37 Lighted Bollards 10 EA
38 Step Lighting Deleted 6 EA ---- ----
39 Stamps Way Entry Lighting Deleted 1 LS ---- ---
40 Post Lights 2 EA
41 Electrical Transformer Vault Install Deleted EA ---
42 600A MDP Panel EA
43 400A SDP Panel 1 EA
44 Food Truck Pedestals - 220v 5 EA
45 220v Outlets-Deleted ---- ---- ---- ---
46 110v Outlets 23 EA
47 Concrete - Vehicular Paving - 6" section 39,300 SF
48 Concrete - Pedestrian Walks - 4" section 12,440 SF
49 Concrete - Pedestrian Walks - 4" section - 5,280 SF
Playground
50 Concrete Decorative Paving - 4" section 2,130 SF
51 Concrete Exercise Equipment Pad - 6" 1100 SF
section DELETED
52 Grade and Rock for Concrete Paving 45020 SF
53 ADA Detectable Warning Panels 200 SF
54 Curb Band Type 1 at existing playground- 6" 40 LF
× 24"
55 Roll-over curb - includes prep & 60 LF
reinforcement
56 Play Matta curb band type 2 150 LF
57 Concrete Stage, Foundation, Ramp and 140 CY
Stairs including prep & reinforcement
58 Concrete Seat Walls - Including prep and 66 LF
reinforcement
59 Concrete mow band x 1'6" wide under 340 LF
playground perimeter fencing
60 Landscape soil import 500 CY
61 Irrigation - Lawns 82,800 SF
62 Irrigation - Planters excluding Rain Gardens 9,100 SF 63 Seeded lawns - Includes soil application, 82,800 SF
tilling, grading, and seeding
64 Plantings - Ground covers and shrubs 9,100 SF
65 Plantings - Rain gardens - DELETED See 24,400 SF ---- ----- Section 01 20 00 notes for details
BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
00 41 00 - BIDDING SCHEDULE - ADDENDA #4
66 Plantings - Berms - DELETED ---
67 Trees - 4'-6' height, B&B 11 EA
68 Mulch - Bark to 4" depth 130 CY
69 Landscaping Maintenance 1 LS
70 Play Surface Play Matta - standard pad areas 3475 SF 71 Play Surface Play Matta - thickened pad fall 3800 SF zone pad areas
72 Playground Equip - Redwood Tree climber 1 LS
and ramp
73 Playground Equip - Swing 3 Bay 1 LS
74 Playground Equip - We-Go-Swing 1 LS
75 Playground Equip - We-Go-Round-Merry-Go- 1 LS
76 Playground Equip - We-Saw-See-Saw LS
77 Playground Equip - Concrete embankment 1 LS
78 Playground Fencing - Perimeter 400 LF
79 Playground Specialized Fencing - - - - ---
80 Playground Shotcrete Boulders EA
81 Picnic Tables EA
82 Standard Concrete Benches 9 EA
83 Furnish and Install removable bollards 5 EA
84 Furnish and Install stage rail 70 LF
85 Purchase and install bike racks 5 EA
86 Drinking Fountain 1 LS
87 Fencing - Guardrail DELETED 170 LF ---- ---
88 Irrigation - Connections and Backflow 1 LS
Devices
89 Cast-in-place Grated Trench Drains 26 LF
90 Raised curb type 1, pool driveway 345 LF
91 Playground Equip - Humpback Whale 1 LS
Climber
92 Playground Equip - Morphe Dome LS
93 Playground Equip - Lighthouse Rock Climber 1 LS
94 Playground Equip - Animato Metal Lophone 1 LS
95 Playground Equip - Ditty Metal Lophone 1 LS
96 Playground Equip - Grandioso Chimes 1 LS
97 Playground Equip - Drums (3) Total 1 LS
98 Playground Equip - Misc items not covered 1 LS
by bid items 70 through 80 and 91 through 97
99 Valley Gutter - reinforced 6" by 4 foot wide 150 LF
100 Miscellaneous Concrete Curb, gutters and 1 LS
ramps at transition areas not included in
pedestrian and vehicular pathways.

Total ( Items 1 - 100) | XXXXX XXXXX XXXXX
BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
00 41 00 - BIDDING SCHEDULE - ADDENDA #4

TOTAL BID AMOUNT
($_
The cost of all work in the Contract Documents not specifically identified as an item or described as an item shall be included in the items and no additional compensation shall become due the Contractor by nature of compliance with the Contract Documents except as provided for in the provisions relating to extra work or changes in the work.

Bid award will be based on the lowest aggregate of the Total Bid Amount.

Actual contract amount will include all items in accordance with paragraph 00 20 00-1.10.

END OF SECTION
BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
0 41 00 - BIDDING SCHEDULE - ADDENDA #4
SECTION 01 20 00 - Addenda #4

MEASUREMENT AND PAYMENT

1.0 GENERAL
A. LUMP SUM PAYMENT ITEMS:

Payment items for the work of this contract for which contract lump sum payments will be made are listed in the Bid Schedule and described below. All costs for items of work, which are not specifically mentioned to be included in a particular lump sum or unit price payment item, shall be included in the listed lump sum item most closely associated with the work involved.

The lump sum price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials (where not provided by City), equipment, performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests, reports, and for performing all work required for which separate payment is not otherwise provided.

B. UNIT PRICE PAYMENT ITEMS:

Payment items for the work of this contract on which the contract unit price payments will be made are listed in the Bid Schedule and described below. The unit price and payment made for each item listed shall constitute full compensation for furnishing all plant, labor, materials (where not provided by City), and equipment, and performing any associated Contractor quality control, environmental protection, meeting safety requirements, tests, and reports, and for performing all work required for each of the unit price items.

C. PROGRESS PAYMENTS:

1. PAYMENT REQUEST PROCEDURES: By the 5th day of each month, the Contractor must submit to the Construction Manager a partial-payment estimate, filled out and signed by the Contractor, covering acceptable work performed during the previous month or since the last partial payment estimate was submitted. If requested by the Construction Manager, the Contractor must provide additional data to support the payment estimate. Additional data may include satisfactory evidence of payment for equipment, materials, and labor including payments to subcontractors and suppliers. Requests for payment for delivered equipment and material must be accompanied by certified invoices by the suppliers. Such equipment and material must be suitably and safely stored at the site of the work.

2. REVIEW PROCEDURES: Within 7 days after receipt of the partial payment estimate, the Construction Manager will review the estimate and either (a) indicate in writing to the Owner's Representative his or her concurrence with the estimate and the Construction Manager's recommendation that payment be made or (b) indicate in writing to the Contractor his or her reasons for not concurring with the estimate. If the Construction Manager recommends payment and the Owner's Representative concurs, the Owner will, within 30 calendar days after receipt of the Construction Manager's recommendation, pay the Contractor a progress payment on the basis BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 200- MEASUREMENT 612, 01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4 of the approved partial-payment estimate. The payments will take into account the retention provisions provided for herein.

In the event the Construction Manager does not concur with the estimate, the Contractor may make the changes necessary to obtain the Construction Manager's concurrence and resubmit the partial-payment estimate, or submit the original progress-payment estimate directly to the Owner's Representative, indicating in writing his or her reasons for refusing to make the changes necessary to obtain concurrence.

RETENTION: The Owner will retain a percentage of each payment except as specified below in accordance with Public Contract Code Section 7201. The retained amount is available for the protection and payment of the person, or persons, mechanics, subcontractors, or material men who perform labor or work under the contract, and persons who supply such person, persons or subcontractors with components and supplies for carrying on such work.

The Owner will retain five (5) percent of each progress payment.

4. WITHHOLDING: The Construction Manager may refuse to recommend the whole or any part of any payment if in the Construction Manager's opinion it would be incorrect to make such recommendation to the Owner. The Construction Manager may also refuse to recommend any payment, or because of subsequently discovered evidence or the result of any tests, may nullify any payment previously recommended to such extent as may be necessary in the Construction Manager's opinion to protect the Owner from loss as a result of:
a. Defective or damaged work.
b. A deductive change order.

Persistent failure of the Contractor to perform the work in accordance with the contract documents, including failure to maintain the progress of the work in accordance with the construction schedule. Persistent failure to maintain the progress of the work means that for a period of two consecutive months following a written notice from the Construction Manager, the Contractor fails to correct a behind- schedule condition at a rate that would reasonably indicate that he will finish the project on schedule.
d. Disregard of authority of the Construction Manager or the laws of any public agency having jurisdiction.
e. Failure to submit required Labor Compliance documentation for the Contractor and/or subcontractor(s).

The Owner may refuse to make payment of the full amount recommended by the Construction Manager because of claims made against the Owner on account of Contractor's performance or furnishing of the work or because liens have been filed in connection with the work or because there are other items entitling Owner to reduce the amount recommended. In such BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-10564
11 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #
2 of 25
case, the Owner will give Contractor prompt written notice with a copy to the Construction Manager stating the reasons for each action.

1. STOP PAYMENT NOTICES: The Owner, by and through the Construction Manager or other authorized officers, may at its option and at any time retain out of any amounts due the Contractor, sums sufficient to cover claims filed pursuant to Section 3179, et seq., of the Civil Code of the State of California.

D. FINAL PAYMENT:

On the condition that no liens or claims are outstanding and all required labor compliance documentation has been received to the satisfaction of the City, Owner will make final payment to the Contractor in the manner provided by law following the expiration of 35 calendar days after acceptance of the work and filing of the notice of completion by the Owner. Final payment must include the entire sum found to be due under this contract after deducting previous payments and such other lawful amounts as the terms of this contract describe. Prior estimates and payments, including those relating to extra work or work omitted, are subject to correction by the final payment Acceptance by the Contractor of final payment acts as a release to the Owner of all claims by and all liability to the Contractor other than claims in stated amounts that may be specifically excepted by the Contractor for things done or furnished in connection with this work and for every act and neglect of the Owner and others relating to or arising out of this work. Payment by the Owner does not release the Contractor or its surety from any obligation under the contract or under the performance bond and payment bonds.

7.02 CHANGE ORDERS
A. GENERAL:

The Owner may, at any time, without notice to the sureties, by written order designated or indicated to be a change order, make any change in the work within the general scope of the contract, including but not limited to the following changes:

In the specifications (including drawings and designs).

In the method or manner of performance of the work.

In the Owner-furnished facilities, equipment, materials, services, or site.

Directing acceleration in the performance of the work.

Any other written order or an oral order (which terms as used in this paragraph include direction, instruction, interpretation, or determination) from the Owner, that causes any such change, must be treated as a change order under this clause, if the Contractor gives the Owner written notice stating the date, circumstances, and source of the order and if the Contractor regards the order as a change order.

BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4
3 of 25
Except as provided in this clause, no order, statement, or conduct of the Owner is or may be treated as a change order under this clause nor does it entitle the Contractor to an equitable adjustment.

If any change under this clause causes an increase or decrease in the Contractor's cost of, or the time required for, the performance of any part of the work under this contract, whether or not changed by any order, an equitable adjustment must be made and the contract modified in writing accordingly. However, except for claims based on defective specifications, claims will not be allowed for any costs incurred more than 20 days before the Contractor gives written notice as required. Also, in the case of defective specifications for which the Owner is responsible, the equitable adjustment includes any increased cost reasonably incurred by the Contractor in attempting to comply with such defective specifications.

If the Contractor intends to assert a claim for an equitable adjustment under this clause, the Contractor must, within 30 days after receipt of a written change order or the furnishing of a written notice, submit to the Owner a written statement setting forth the general nature and monetary extent of such claim, unless the Owner extends this period. The statement of claim hereunder may be included in the notice.

A claim by the Contractor for an equitable adjustment will not be allowed if it is asserted after final payment under this contract.

B. EXTRA WORK:

Extra work means providing materials and equipment and performing work not directly or by implication called for by the contract. Changes in measured quantity under a unit price contract or item are not extra work. If the Owner requires extra work, the Owner may (1) do it itself, (2) employ others to do it, (3) direct the Contractor to perform the extra work at unit bid price or a combination of such items, (4) direct the Contractor to perform the extra work at a mutually agreed upon lump sum, or (5) direct the Contractor to perform the extra work on a time and expense basis.

C. OMITTED WORK:

The Owner may, by written order to the Contractor, omit work, equipment, and material to be provided under the contract, and the value of the omitted work, equipment and material will be deducted from the contract price. The deducted value will be a lump sum or unit bid price agreed upon in writing by the Contractor and Owner based on the breakdown and cost information submitted by the Contractor.

A. UNIT BID PRICE CHANGE:

Increases or decreases in the quantity of a contract item of work that was bid on a unit basis will be made by comparing the total pay quantity of such item of work with the Construction Manager's estimate. When changes in quantities exceed 25 percent of the original bid quantity and the total dollar change of that bid item is significant, the Owner will review the unit price to determine if a new unit price should be negotiated. Methods for Changed Quantity Payment Adjustments shall be those specified in the Caltrans Standard Specifications, latest edition BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4
4 of 25
E. LUMP SUM CHANGES:

Whenever the Contractor is directed to perform extra work on a lump-sum basis, changes in contract price resulting from the extra work will be based on a mutually agreed upon lump-sum price. The Contractor's proposal for such changes must include a detailed breakdown of labor and materials costs for the extra work to be performed by its forces and the forces of its subcontractors or material suppliers as may be required. The breakdown must include any labor surcharge and any sales- or use-tax cost. Whenever the Owner requests that the Contractor prepare a lump-sum price in connection with a change order, the Contractor is entitled to the costs incurred in the preparation of that price whether or not the lump-sum amount is finally accepted by the Owner.

Those costs will be incorporated in the lump-sum amount.

Compensation for the extra work will be based on the direct costs as listed in the detailed oroposal, plus a mutually agreed upon percent of direct costs tor overhead and profit, plus one percent (1%) of those direct costs for bond. The allowance for overhead and protit must include full compensation for overhead, including superintendence, and additional overhead attributable to a time extension granted because of the change order and no separate charge may be made for overhead.

When the change order involves work omitted, the reduction of the contract price will be based on the direct costs listed in the detailed proposal submitted by the Contractor. An additional reduction may be made of an amount that is identified as reduced overhead costs attributable to the work omitted. No reduction will be made for profit originally attributable to the omitted work.

F. TIME AND EXPENSE CHANGES:

1. GENERAL: Whenever the Contractor is directed to perform extra work on a time and expense basis, the Contractor must maintain accurate records. Each day a record of labor, materials, and equipment costs will be submitted to the Construction Manager for verification.

These records will reflect the actual and necessary expenses pertaining to the extra work and will be available for audit. Audits conducted under this provision must be in accordance with generally accepted auditing standards and established procedures and guidelines of the reviewing or audit agency(ies).

Payment to the Contractor for extra work performed on a time-and-expense basis will consist of the actual necessary expense for doing the extra work, plus an allowance of 15 percent of labor, material and equipment rental for overhead, general superintendence and profits, plus one percent (1%) of those direct costs for bond. This basis of payment applies to work done directly by the Contractor and to work done by a subcontractor, except the one percent (1%) allowance for bond does not apply to work performed by a subcontractor. When the work is done by a subcontractor, the Contractor may add five percent (5%) to the subcontractor's charges to cover overhead and profit and one percent (1%) for bond.

In determining time-and-expense compensation, the term "actual necessary expense" means the sum of (1) materials and equipment, (2) labor, (3) supervision, (4) construction equipment, (5) professional services, and (6) other costs. "Charges" for such items means the BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4
5 of 25
actual cost whether incurred by the Contractor, a subcontractor or others. The items making up "actual necessary expense" are defined as follows:

2. MATERIALS AND EQUIPMENT: Materials and equipment means costs for materials and equipment provided by the Contractor and necessarily used in the work includes applicable taxes.

3. LABOR: The cost of labor will be the sum of actual wages paid, labor surcharge, and subsistence and travel allowances. Actual wages paid include employer payments to or on behalf of the worker for health and welfare, pension, vacation and similar purposes. The labor surcharge includes applicable labor-related taxes, Workers Compensation Insurance premiums, public liability and property damage insurance premiums, and other legally required costs directly related to labor. Where subsistence and travel allowance are required for performance of extra work, the charges include the actual amount paid to each worker for these items.

4. SUPERVISION: If, in the Owner's judgment, full-time supervision of the extra work is required, it will be authorized in writing by the Construction Manager and charges for that supervision will be included as an actual necessary expense. Charges for supervision of the extra work by the Contractor's representative are not part of actual necessary expense.

5. CONSTRUCTION EQUIPMENT: Charges for the use of construction equipment required in the performance of extra work will be based on rental rates set forth in the State of California then-current official published document covering rental of equipment used on force account work. For equipment not listed in that document, the rental rate will be as listed by the local section of the Associated General Contractors. If the equipment is not listed by the Associated General Contractors, the rental rate will be mutually agreed upon in writing between the Contractor and Owner prior to the use of the unlisted equipment. The reasonable cost of moving equipment onto and off the job site will be included, but equipment rental will not be paid when the equipment is inoperative due to breakdowns. Individual pieces of equipment or small tools having a replacement value of $100 or less are considered expendable and no payment will be made for these.

When equipment is used on the extra work for less than five days, hourly rates will be used.

Less than 30 minutes of operation is considered one-half hour of operations. When equipment is used on the extra work for more than five days, daily rates apply. In that case, less than four hours of operation is considered to be one-half day of operation.

PROFESSIONAL SERVICES: Professional services are included in "actual necessary expense" provided both that the Owner has determined that such services are necessary and the Construction Manager has authorized in writing the provision of such services.

7. OTHER COSTS: Charges for items not included in paragraphs 7.02 F.1 through 6 may be included as "actual necessary expense" if such additional items are authorized in advance and in writing by the Construction Manager.

BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4.
6 of 25

7.03 CHARGES TO CONTRACTOR
Everything charged to the Contractor under the terms of this contract must be paid by the Contractor to the Owner on demand. Such charges may be deducted by the Owner from money due or to become due to the Contractor under the contract. The Owner may recover such charges from the Contractor or from its surety.

7.04 COMPENSATION TO OWNER FOR TIME EXTENSION
The Owner, in exchange for granting an extension of time for avoidable delay, must be compensated by the Contractor for the actual costs to the Owner of engineering, inspection, general supervision, and overhead expenses that are directly chargeable to the work and accrue during the period of such extension. The actual costs do not include charges for final inspection and preparation of the final estimate by the Owner.

7.05 SUBSTANTIAL COMPLETION
The Contractor, on considering the work to be substantially complete and ready for its intended use, must so notify the Construction Manager in writing. The notification must include an itemized list of remaining incomplete work. If the Construction Manager determines that the work is not substantially complete, he will so notify the Contractor in writing identifying the reasons for such a determination. If the Construction Manager finds the work substantially complete, he will meet with the Contractor to; (1) prepare a punch list of incomplete items of work; (2) define the division of responsibility between Owner and Contractor with respect to security, operation, maintenance, utilities, insurance, and warranties; and (3) describe any other issues related to acceptance of the substantially completed work. Upon reaching agreement with the Contractor, the Construction Manager will write to the Owner, certifying that the work is substantially complete, listing the items of incomplete work, stating the date for completion of incomplete work, defining the division of responsibilities, and setting forth any other terms related to acceptance.

The Owner, who has sole discretion for determination of substantial completion, will review the Construction Manager's certification that the work is substantially complete and concurring with that certification, will notify the Contractor, in writing, that the work is accepted as substantially complete. Except for any portion(s) of work specified for early completion or required by the Owner for early possession (paragraph 00 72 00-7.06), substantial completion will not occur for any work until the entire project is ready for possession and use. The acceptance notice will include a punch list of incomplete work items, set the date for their completion, describe the division of responsibility between the Owner and Contractor, and describe any other terms of acceptance. The Contractor will acknowledge receipt of the acceptance notice in writing, indicating acceptance of all of its terms and provisions.

Upon receipt of the Contractor's acknowledgment letter, the Owner will take possession of the work or portion of the work and put it into its intended service. The date that the work or portion of the work is put into service will become the date of substantial completion. Unless otherwise specified, warranties will begin on the date of substantial completion.

BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4
7 of 25
Subsequent to the substantial completion date, the Owner may exclude the Contractor from the work during such periods when construction activities might interfere with the operation of the project. The Owner, however, will allow the Contractor reasonable access for completion or correction of incomplete punch list items.

7.06 POSSESSION OF PORTIONS OF THE PROJECT
Should the Contractor fail to meet any date specified for substantial completion of the work or any portion of the work requiring early possession and use by the Owner, the Owner may, after a 10-day written notice to the Contractor, take over such portion or all of the work that is behind schedule. In such case, the Construction Manager will prepare a punch list of incomplete work.

The Owner may allow the Contractor reasonable access to the work at such times that the operation of the project will not be affected or the Contractor may complete the work his or herself after giving the Contractor notice of its intention to do so. The cost of Owner's work will be charged to and deducted from amounts due to the Contractor. The substantial completion date will be established as the date when the Owner actually begins using the project or portion of the project for its intended purpose. Division of responsibilities between Owner and Contractor, beginning of warranties, and any other issues relating to substantial completion will be as specified in paragraph 00 72 00-7.05.

2.0 BID ITEMS
Mobilization: Mobilization is as described in Section 9-1.16D, "Mobilization" of the Standard Specifications. Mobilization will be paid on a lump sum basis as follows provided that total mobilization cost does not exceed 10 percent of the total bid: 25 percent when 10 percent of the project is earned. 50 percent when 20 percent is earned. 75 percent when 50 percent is earned. 100 percent when 75 percent is earned. Where mobilization exceeds 10 percent of the contract, see Public Contract Code.

SWPPP Plan and Reporting: This item includes all additional work necessary for maintaining and updating the stormwater pollution prevention plan by a qualified QSD. Includes reporting results of work covered under this item in accordance with Specification Section 01 57 23. The City is to provide and upload the initial plan to the SMARTS website. This lump sum item will be paid based on the percentage of the project earned, rounded down to the nearest 10 percent, until 90 percent is earned. The final 10 percent will be paid with the final payment.

Water Pollution Prevention BMPs: This item includes all additional work necessary for meeting the requirements set out in the SWPPP and work covered under this item in accordance with Specification Section 01 57 23. As the approved SWPPP is not available at bid time, a pre-bid budget of $20,000 will be established for the installation and maintenance of the project BMPs. Upon approval of the SWPPP, it BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT — ADDENDA #4
8 of 25
will be provided to the successful bidder with actual costs to be negotiated or handled on a T&M basis.

4. Pedestrian & Traffic Control: Traffic Control is as described in Specification Section 01 55 26, "Temporary Traffic Control". This lump sum item will be paid based on the percentage of the project earned, rounded down to the nearest 10 percent. The final 10 percent will be paid with the final payment.

Tree protection fencing installation and removal: Installation (and removal after construction) of tree protection fencing will be paid at the bid unit price per linear foot. Work shall include the installation in accordance with all plans and specifications including specification section 01 56 39. Work comprises the following: underground utility locating, fence post installation, stretching of temporary tree protection and removal of all components after construction. 70 percent will be paid based on completion of the temporary fence installation. The remaining 30 percent will be paid upon successful removal of fencing.

6. Sheeting Shoring and Bracing: This item shall include all temporary sheeting, shoring, and bracing, or equivalent methods, adequate for the protection of life or limb, which shall conform to the applicable construction safety orders as required for completion of the project as described in Specification Section 31 23 17 and 31 40

00. This bid item is pursuant to Labor Code Section 6707. This lump sum item will be paid based on the percent of the project eamed, rounded down to the nearest 10 percent.

Quality Control: Quality Control as described in Specification Section 01 45 00 shall be paid on a lump sum based on the percentage of the project earned, rounded down to the nearest 10 percent.

8. Materials Testing: Materials Testing as described in Specification Section 01 45 29 shall be paid on a lump sum based on the percentage of the project earned, rounded down to the nearest 10 percent.

Clear, Grub & Tree Removal: This item will be paid based on the bid unit price per lump sum. Clearing and grubbing to be as described in Specification Section 31 10 00, "Site Clearing." Work includes but is not limited to removal and disposal or salvage of trees, shrubs, and grass. This lump sum item will be paid based on the percentage of this item completed.

10. Demolition of Existing Facilities including Monument Salvage: Demolition is as described in Specification Section 02 41 00, "Demolition." Demolition shall cover all work identified on Plan Sheets L3.01 - L3.04 and all other necessary demolition work not covered under other bid items. Work includes but is not limited to removal and disposal or salvage of existing items not covered in bid items #11 and #12. These items may include aggregate base, light poles, trees and landscaping, foundations, seawalls, signs, storm drainage, sanitary sewer manholes, and other buried utilities.

This lump sum item will be paid based on the percentage of this item completed.

BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4
9 of 25

11. Demolition of Existing Concrete: Demolition is as described in Specification Section 02 41 00, "Demolition." Demolition shall cover all work identified on Plan Sheets L3.01 - L3.04 and all other necessary demolition work not covered under other bid items. Work includes but is not limited to removal and disposal of existing sidewalks, curb and gutters. This lump sum item will be paid based on the percentage of this item completed.

12. Demolition of Existing Asphalt Concrete: Demolition is as described in Specification Section 02 41 00, "Demolition." Demolition shall cover all work identified on Plan Sheets L3.01 - L3.04 and all other necessary demolition work not covered under other bid items. Work includes but is not limited to removal and disposal of existing asphalt. This lump sum item will be paid based on the percentage of this item completed.

13. Rough Grading: This item will be paid based on the bid unit price per square yard.

Grading work includes: required removal, moving, importing and placement of sub- soil to prepare the site for other bid items at a future date. Scarification and compaction of subgrade to required 90% compaction prior to placement of top soil, aggregate base material, etc. 40 percent will be paid based on excavation of native material according to plans and specifications including specification section 31 22

00. 10 percent will be paid based on completion of scarification and compaction. The remaining 50 percent will be paid once subgrade is prepared and ready to accept top condition. This item will be paid based on Owner's estimate of the percentage complete for each of the above activities.

14. Rain Garden Excavation: This item will be paid based on the bid unit price per cubic yard. Excavation work includes: required removal to construct rain garden per plan grades. This item will be paid based on Owner's estimate of the percentage complete for each of the above activities.

15. Import Soil for Berm Placement and Amphitheater Capping: This item will be paid based on the bid unit price per cubic yard and includes all labor, materials, and equipment necessary to import (or transport city approved spoils from other sites), place, grade, and compact the soil as shown on the Plans. The Owner will only pay for soil quantities identified in the bid schedule. Contractor is responsible for proper grading and placement of subgrade to achieve lines and grades per plans and specifications including section 32 91 13. This item will be paid based on Owner's estimate of the percent of total soil placed during each billing cycle.

16. Aggregate Base for asphalt paved section: This item will be paid on the bid unit price per cubic yard and includes all labor, materials, and equipment necessary to import, place, grade, and compact the aggregate base rock for the road base as shown on the Plans. The Owner will only pay for base rock quantities identified in the bid schedule. Contractor is responsible for proper grading and placement of subgrade to achieve lines and grades according to plans and specifications including section 32 BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4
10 of 25
11 00. This item will be paid based on Owner's estimate of the percent of total aggregate base placed during each billing cycle.

17. Hot Mix Asphalt Concrete: This item includes all work necessary to provide and place hot mix asphaltic concrete. This item will be paid on the bid unit price per ton. The Owner will only pay for Hot Mix Asphalt quantities identified in the bid schedule.

Contractor is responsible for proper grading and placement of subgrade and rock to achieve lines and grades. This item will be paid based on Owner's estimate of the number of tons of hot mix asphalt placed during each billing cycle.

18. Pavement Striping and Wheelstops: This item includes all work necessary to stripe crosswalks, center lines, fog lines, parking spaces and other striping as shown on the Plans. This item includes all work necessary to place wheel stops as shown on the Plans. This item will be paid for per lump sum price based on Owner's estimate of the percentage of striping and wheel stops completed during each billing cycle.

19. Crackfill & Sealcoat Playground Parking Lot: This item includes all work necessary to hot-air-lance clean cracks to be filled, placement of Crafco Roadsaver Low Tack 543 crack seal or equivalent, and placement of a seal coat as shown on the Plans.

This item will be paid on the bid unit price per square foot based on Owner's estimate of the square feet completed during each billing cycle.

20. Parking and Path of Travel Signs: This item includes all work necessary to procure and place (including foundation and pole) the signs as shown on the Plans and specifications including section 10 14 53 and 10 45 00. This item will be paid for per lump sum price based on Owner's estimate of the percentage of signs completed during each billing cycle.

21. Storm Drain 4 24 inch HDPE solid and inlet piping: Installation of 4-inch diameter Storm Drain pipe will be paid at the bid unit price per foot. Work shall include the installation of the pipes in accordance with all specifications. Work shall be performed in accordance with Specification Section 22 14 00 and 33 41 00 and comprises the following: trench excavation and disposal of native material, removal and disposal of existing pipe or structures where shown, installation of new and replacement piping and connections, connection to existing facilities including the couplings needed to join dissimilar pipes, backfill material, and compaction of materials to subgrade (soil ready to receive road base). Pipe measurement will include the actual length of pipe installed and will not include waste pipe or measurement through junction structures or other structures. This item will be paid for per linear foot based on Owner's estimate of the number of feet installed during each billing cycle.

22. Storm Drain 8 18 inch HDPE: Installation of 8-inch Storm Drain pipe will be paid at the bid unit price per foot in accordance with item 21 above.

23. Storm Drain 12 inch HDPE: Installation of 12-inch Storm Drainpipe will be paid at the bid unit price per foot in accordance with item 21 above.

BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4
11 of 25

24. Flared End Section: Installation of 8 inch and 12 inch flared end section will be paid for on a per each basis. Work shall include the installation of the new ends in accordance with all specifications. This item comprises the following: excavation and disposal of native material, removal and disposal of existing structures where shown, placement of flared ends, placement of backfill material, and compaction of materials. This item will be paid for per each based on Owner's estimate of the number of flared ends installed during each billing cycle.

25. Duckbill Outlet: Installation of the duckbill outlet will be paid for on a per each basis.

Work shall include the installation of the new outlet in accordance with all specifications. This item comprises the following: excavation and disposal of native material, removal and disposal of existing structures where shown, placement of Duckbill outlet, placement of backfill material, and compaction of materials. This item will be paid for per each based on Owner's estimate of the number of outlets installed during each billing cycle.

26. Retention Basin Inlets: Installation of the retention basin inlets will be paid for on a per each basis. Work shall include the installation of the new inlets in accordance with all specifications. This item comprises the following: excavation and disposal of native material, removal and disposal of existing structures where shown, placement of inlets, placement of backfill material, and compaction of materials.

This item will be paid for per each based on Owner's estimate of the number of inlets installed during each billing cycle.

27. Install French Drain: Installation of the French drain including the perforated piping, drain rock and geotextile fabric. Work shall include the installation of the drain system in accordance with all specifications. This item comprises the following:
excavation and disposal of native material, removal and disposal of existing structures where shown, placement of area drains, placement of backfill material, and compaction of materials. This item will be paid for per each based on Owner's estimate of the linear feet of drain installed during each billing cycle.

28. Connect to Existing Storm Drain: Connection to existing storm drain system will be paid at the bid unit price per lump sum. Work shall include the connection of the pipes in accordance with all specifications and plan drawings. Work shall be performed in accordance with Specification Section 22 14 00 and comprises the following: trench excavation and disposal of native material, removal and disposal of existing pipe or structures where shown, installation of new and replacement piping and connections, connection to existing facilities including the couplings needed to join dissimilar pipes, backfill material, and compaction of materials to subgrade (soil ready to receive road base). This item will be paid for based on Owner's estimate of quantity completed during each billing cycle.

29. Drainage Inlets (Caltrans Type GO): Installation of the concrete drop inlets (CalTrans Type GO) including hot dip galvanized grate, will be paid for on a per each basis. Work shall include the installation of the new inlets in accordance with BEACHFRONT PARK IMPROVEMENTS PHASE 1E
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4
12 of 25
all specifications. This item comprises the following: excavation and disposal of native material, , removal and disposal of existing structures where shown, placement of precast inlets, placement of backfill material, and compaction of materials. This item will be paid for per each based on Owner's estimate of the percentage completed during each billing cycle.

30. Adjust Existing Inlets to Grade: Adjustment of the existing inlets) to grade will be paid for on a per each basis. The work comprises the following: sawcutting of asphalt for a clean edge, demolition of existing collar, excavation and disposal of native material, salvaging of existing structures, placement of backfill material as required, setting inlet to grade, compaction of materials, and placing a concrete collar. This item will be paid for per each based on Owner's estimate of the number of inlets adjusted during each billing cycle.

31. 4" Sanitary Sewer Lateral: DELETED _Installation of sewer lines will be paid at the bid unit price per linear foot. Work shall include installation of the new lines in accordance with all specifications. This item comprises the following: trench excavation and disposal of native material, removal and disposal of existing lines and structures where shown, installation of new and replacement piping and connections, connection to existing facilities including the couplings needed to join dissimilar pipes, backfill material, and compaction of materials to subgrade (soil ready to receive road base) according to plans and specifications including section 22 25 35, 22 26 22, and 33 30 00. This item will be paid for based on Owner's estimate of the number of linear feet installed during each billing cycle.

32. Sanitary Sewer Cleanout with G-5 Boxes & Lids: DELETED Installation of the sanitary sewer cleanouts including piping and G-5 boxes, will be paid for on a per each basis. Work shall include the installation of the new cleanouts in accordance with all specifications. This item comprises the following: excavation and disposal of native material, removal and disposal of existing structures where shown, placement of piping and boxes, placement of backfill material, and compaction of materials. 90 percent will be paid on completion of compaction to subgrade. Final 10 percent will be paid upon completion of paving.

33. 1" Water Line: DELETED Installation of water lines will be paid at the bid unit price per linear foot. Work shall include installation of the new lines in accordance with all specifications including section 33 10 00. This item comprises the following:
trench excavation and disposal of native material, removal and disposal of existing lines and structures where shown, installation of new and replacement piping and connections, connection to existing facilities including the couplings needed to join dissimilar pipes, backfill material, and compaction of materials to subgrade (soil ready to receive road base). 90 percent will be paid on completion of compaction to subgrade. Final 10 percent will be paid upon required testing, flushing, and disinfection being completed successfully.

34. Water Meter Connections: City to supply meters and boxes. All other piping and fittings supplied by the contractor. Installation of Water Meters will be paid for on a BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4
13 of 25
per each basis. Work shall include the installation of the new meters in accordance with all specifications. This item comprises the following: excavation and disposal of native material, removal, and salvage of existing meters and/or structures where shown, connection to existing facilities including the couplings needed to join dissimilar pipes, placing of meter and box and lid and needed appurtenances, backfill material, and compaction of materials to grade.

35. Reconnect restroom sewer & water: DELETED Connection of the restroom to existing water & sewer system will be paid at the bid unit price per lump sum. Work shall include the connection of the pipes in accordance with all specifications. Work shall be performed in accordance with Specification Division 33 and comprises the following: trench excavation and disposal of native material, removal and disposal of existing pipe or structures where shown, installation of new and replacement piping and connections, connection to existing facilities including the couplings needed to join dissimilar pipes, backfill material, and compaction of materials to subgrade (soil ready to receive road base). This item will be paid for based on Owner's estimate of the percentage of completion during each billing cycle.

36. Electrical: This item shall be paid on a lump sum basis and shall include pull boxes, electrical conduit, receptacles, covers, related conductors, electrical enclosures, breakers, needed appurtenances and other subsurface items related to the final buildout of the electrical system not itemized in bid items 37 through 46, as shown on the Plans and specifications including division 26. All work is to be installed where shown on the Plans or as directed by the City or the Engineer. This item comprises the following: coordination with Pacific Power; trench or other excavation and disposal of native material; removal and disposal of existing conductors; backfill material; purchase and installation of conduits, pull tape, pull boxes, needed appurtenances, aggregate base, and compaction of materials to grade.

This item to be paid based on Owner's estimate of the percent of related work installed on the project during each billing cycle.

37. Lighted Bollards: This item shall be paid on a per each basis and shall include all the work necessary to install lighted bollards and all equipment needed for fully functional lights. All work is to be installed where shown on the Plans and specifications including section 26 50 00 or as directed by the City or the Engineer. This item comprises the following: furnishing and installation of lighted bollards (poles, base, foundation, and hardware). This item to be paid based on Owner's estimate of the number of bollards installed on the project during each billing cycle.

38. Step Lighting: DELETED This item shall be paid on a per each basis and shall include all the work necessary to install step lighting and all equipment needed for fully functional lights. All work is to be installed where shown on the Plans and specifications including section 26 50 00 or as directed by the City or the Engineer.

This item comprises the following: furnishing and installation of step lights (fixture, base, placement, and hardware). This item to be paid based on Owner's estimate of the number of lights installed on the project during each billing cycle.

BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4
14 of 25

39. Stamps Way Entry Lighting: DELETED This item shall be paid on a lump sum basis and shall include all the work necessary to install the entry way lighting and all equipment needed for fully functional lights. All work is to be installed where shown on the Plans and specifications including section 26 50 00 or as directed by the City or the Engineer. This item comprises the following: furnishing and installation of lights (poles, base, foundation, and hardware). This item to be paid based on Owner's estimate of the percentage installed on the project during each billing cycle.

40. Post Lights: This item shall be paid on a per each basis and shall include all the work necessary to install post lights and all equipment needed for fully functional lights. All work is to be installed where shown on the Plans and specifications including section 26 50 00 or as directed by the City or the Engineer. This item comprises the following:
furnishing and installation of post lights (posts, base, foundation, and hardware).

This item to be paid based on Owner's estimate of the number of posts installed on the project during each billing cycle.

41. Electrical Transformer Vault Install: DELETED This item shall be paid on a per each basis and shall include all the work necessary to install the transformer vault and all equipment needed for fully functional electrical hookup. All work is to be installed where shown on the Plans and specifications including division 26 or as directed by the City or the Engineer. This item comprises the following: furnishing and installation of vault (vault, conduit, base, foundation, and hardware). This item to be paid based on Owner's estimate of the number of vaults installed on the project during each billing cycle.

42. 600A MDP Panel: This item shall be paid on a per each basis and shall include all the work necessary to install the panel and all equipment needed for fully functional electrical hookup. All work is to be installed where shown on the Plans and specifications including section 26 24 16 or as directed by the City or the Engineer.

This item comprises the following: furnishing and installation of panel (panel, conduit, mounting, foundation, and hardware). This item to be paid based on Owner's estimate of the number of panels installed on the project during each billing cycle.

43. 400A SDP Panel: This item shall be paid on a per each basis and shall include all the work necessary to install the panel and all equipment needed for fully functional electrical hookup. All work is to be installed where shown on the Plans and specifications including section 26 24 16 or as directed by the City or the Engineer.

This item comprises the following: furnishing and installation of panel (panel, conduit, mounting, foundation, and hardware). This item to be paid based on Owner's estimate of the number of panels installed on the project during each billing cycle.

44. Food Truck Pedestal 220V: This item shall be paid on a per each basis and shall include all the work necessary to install the pedestals and all equipment needed for fully functional hookup. All work is to be installed where shown on the Plans and BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4
15 of 25
specifications including division 26 or as directed by the City or the Engineer. This item comprises the following: furnishing and installation of the pedestals (fixture, base, foundation, and hardware). This item to be paid based on Owner's estimate of the number of pedestals installed on the project during each billing cycle.

45. 220V Outlets: DELETED This item shall be paid on a per each basis and shall include all the work necessary to install the outlets and all equipment needed for fully functional electrical hookup. All work is to be installed where shown on the Plans and specifications including division 26 or as directed by the City or the Engineer.

This item comprises the following: furnishing and installation of the outlets (fixture, base, foundation, and hardware). This item to be paid based on Owner's estimate of the number of outlets installed on the project during each billing cycle.

46. 110V Outlets: This item shall be paid on a per each basis and shall include all the work necessary to install the outlets and all equipment needed for fully functional electrical hookup. All work is to be installed where shown on the Plans and specifications including division 26 or as directed by the City or the Engineer. This item comprises the following: furnishing and installation of the outlets (fixture, base, foundation, and hardware). This item to be paid based on Owner's estimate of the number of outlets installed on the project during each billing cycle.

47. Concrete Vehicular Paving - 6" Section: This item will be paid at the bid unit price per square foot. This item includes all work necessary to construct 6-inch unreinforced concrete walkway including subgrade preparation, and all other items needed to install the paving in accordance with the plans and specifications including section 32 12 13. This item to be paid based on Owner's estimate of the square footage of paving installed on the project during each billing cycle.

48. Concrete Pedestrian Sidewalks - 4" Section: This item will be paid at the bid unit price per square foot. This item includes all work necessary to construct 4-inch unreinforced concrete sidewalks, including subgrade preparation, and all other items needed to install the sidewalks in accordance with the plans and specifications including section 32 12 13. This item to be paid based on Owner's estimate of the square footage of sidewalk installed on the project during each billing cycle.

49. Concrete Pedestrian Playground Sidewalks - 4" Section: This item will be paid at the bid unit price per square foot. This item includes all work necessary to construct 4- inch unreinforced concrete sidewalks, including subgrade preparation, and all other items needed to install the sidewalks in accordance with the plans and specifications including section 32 12 13. This item to be paid based on Owner's estimate of the square footage of sidewalk installed on the project during each billing cycle.

50. Concrete Decorative Paving - 4" Section: This item will be paid at the bid unit price per square foot. This item includes all work necessary to construct 4-inch unreinforced concrete sidewalks, including subgrade preparation, and all other items needed to install the sidewalks in accordance with the plans and specifications including but not limited to Cast in Place Concrete - 03 30 00; Concrete Paving - 32 BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4
16 of 25
13 13, and Decorative Concrete Paving - 32 13 16. Concrete to be exposed black concrete with embedded glass. This item to be paid based on Owner's estimate of the square footage of sidewalk installed on the project during each billing cycle.

51. Concrete Exercise Equipment Pad - 6" Section: DELETED This item will be paid at the bid unit price per square foot. This item includes all work necessary to construct 6-inch unreinforced concrete pad including subgrade preparation, and all other items needed to install the pad in accordance with the plans and specifications including section 32 12 13. This item to be paid based on Owner's estimate of the square footage of pad installed on the project during each billing cycle.

52. Grade and Rock for Concrete Paving: This item will be paid on the bid unit price per square foot and includes all labor, materials, and equipment necessary to import, place, grade, and compact the aggregate base rock for the concrete flatwork as shown on the Plans and specifications including section 32 11 00. The Owner will only pay for base rock quantities identified in the bid schedule. Contractor is responsible for proper grading and placement of subgrade to achieve lines and grades. This item will be paid based on Owner's estimate of the number of square feet of aggregate base placed during each billing cycle.

53. ADA Dectable Warning Panels: This item is to be paid on a per square foot basis.

This item includes all labor, materials, and equipment needed for installation of detectable warning surfaces placed at the ramps and crosswalks as shown on the Plans and in accordance with the CalTrans Standard Plans and Specifications including section 32 17 26. Concrete material is excluded from this bid item. The square footage of each Detectable Warning Surface may vary per location. This item to be paid based on Owner's estimate of the square feet of panels installed on the project during each billing cycle.

54. Curb Band Type 1 Curb Through Drain: Material callout 2.3. Plan detail 4, sheet L9.02. This item will be paid on the bid unit price per each and includes all work necessary to place the drain through the curb including excavation and disposal of native soils, subgrade preparation, aggregate base, compaction, and all other items needed for installation as shown on the Plans. This item to be paid based on Owner's estimate of the number of linear feet installed on the project during each billing cycle.

55. Roll-over Reinforced Curb: This item will be paid on the bid unit price per linear foot and includes all work necessary to construct concrete roll-over curbs and gutters including excavation and disposal of native soils, subgrade preparation, aggregate base, compaction, steel reinforcement, and all other items needed for a complete and functioning gutter system. This item to be paid based on Owner's estimate of the linear feet of roll-over installed on the project during each billing cycle.

56. Play Matta curb band type 2 (Valley Gutter NOW #99): Material callout 2.4. Plan detail 5, sheet L9.02. This item will be paid on the bid unit price per linear foot and includes all work necessary to construct valley gutters, including excavation and BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4
17 of 25
disposal of native soils, subgrade preparation, aggregate base, compaction, as shown on the Plans. This item to be paid based on Owner's estimate of the linear feet installed on the project during each billing cycle.

57. Concrete Stage, Foundation, Ramp, and Stairs: This item will be paid at the bid unit price per cubic yard. This item includes all work necessary to construct the stage, foundation, ramp and stairs including subgrade preparation, placing and compaction of aggregate base, steel reinforcement, and all other items needed to install the stage in accordance with the plans & specifications. This item to be paid based on Owner's estimate of the cubic yards of concrete placed on the project during each billing cycle.

58. Concrete Seat Wall: This item will be paid at the bid unit price per linear foot. This item includes all work necessary to construct a seat wall including subgrade preparation, placing and compaction of aggregate base, reinforcing steel, and all other items needed to install the seat walls in accordance with Detail 6 on L9.03 of the Beachfront Park Improvements Phase 1B plans and specifications. This item to be paid based on Owner's estimate of the linear feet of wall installed on the project during each billing cycle.

59. Curb Bands - 1'6" wide mow strip under fencing 6" wide: Material callout 2.4.

Plan detail 5, sheet L9.02. This item will be paid at the bid unit price per linear foot.

This item includes all work necessary to construct a one foot 6-inch wide concrete mow band including subgrade preparation, placing and compaction of aggregate base, and all other items needed to install the band in accordance with details on L9.02 of the Beachfront Park Improvements Phase 1B plans and specifications.

This item to be paid based on Owner's estimate of the linear feet installed on the project during each billing cycle.

60. Landscape Soil Import: This item will be paid on the bid unit price per cubic yard and includes all labor, materials, and equipment necessary to import, place, grade, and compact the landscaping soil as shown on the plans and specifications including Specification 32 91 13. The Owner will only pay for soil quantities identified in the bid schedule. Contractor is responsible for proper grading and placement of soil to achieve lines and grades. This item will be paid based on Owner's estimate of the cubic yards of soil placed during each billing cycle.

61. Lawn Irrigation: Installation of irrigation lines will be paid at the bid unit price per square foot. Work shall include installation of the new lines, sprinklers, valves, and fittings, etc. in accordance with all plans and specifications including Specification 32 84 00. This item comprises the following: trench excavation and disposal of native material, removal and disposal of existing lines and structures where shown, backfill material, and compaction of materials to subgrade (soil ready to receive landscaping). Water connection tie-ins and backflow devices will be paid under bid item 88. This item will be paid based on Owner's estimate of the square feet of area covered by the irrigation lines placed during each billing cycle.

BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4
18 of 25

62. Planting Areas Irrigation: Installation of irrigation lines will be paid at the bid unit price per square foot. Work shall include installation of the new lines, sprinklers, valves, controllers, backflow devices, and fittings, etc. in accordance with all plans and specifications including Specification 32 84 00. This item comprises the following: trench excavation and disposal of native material, removal and disposal of existing lines and structures where shown, backfill material, and compaction of materials to subgrade (soil ready to receive landscaping). Water connection tie- ins and backflow devices will be paid under bid item 88. This item will be paid based on Owner's estimate of the square feet of area covered by the irrigation lines placed during each billing cycle.

63. Seeding Lawn: Seeding of lawn will be paid at the bid unit price per square foot.

Work shall include soil preparation (grading, soil application, and tilling), approval of seed mixture, and seeding, etc. all in accordance with all plans and specifications including Specification 32 92 00. This item will be paid based on Owner's estimate of the square feet of completion during each billing cycle. 50 percent will be paid on completion of soil preparation and 40 percent will be paid on completion of seeding.

64. Planting Ground Cover & Shrubs: Planting of ground cover and shrubs will be paid at the bid unit price per square foot. Work shall include soil preparation (grading, soil application, and tilling), approval of seed/plant selection, and placement, etc. in accordance with all plans and specifications including Specification 32 93 00.

This item will be paid based on Owner's estimate of the square feet of completion during each billing cycle. 50 percent will be paid on completion of soil preparation and 40 percent will be paid on completion of planting.

65. Planting Rain Gardens: DELETED Area grading shall be included in Rain Garden excavation bid item. Soil prep for these areas will be excluded at this time. A plant selection redesign will occur after a contract has been awarded.

Planting of rain gardens will be paid at the bid unit price per square foot. Work shall include soil preparation (grading, soil application, and tilling), approval of seed/plant selection, and placement, etc. in accordance with all plans and specifications including Specification 32 93 00. This item will be paid based on Owner's estimate of the square feet of completion during each billing cycle. 50 percent will be paid on completion of soil preparation and 40 percent will be paid on completion of planting.

66. Planting Berms: DELETED Planting of berms will be paid at the bid unit price per square foot. Work shall include soil preparation (grading, soil application, and tilling), approval of seed/plant selection, and placement, etc. in accordance with all plans and specifications including Specification 32 92 00. This item will be paid based on Owner's estimate of the square feet of completion during each billing cycle. 50 percent will be paid on completion of soil preparation and 40 percent will be paid on completion of planting.

BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4

67. Planting Trees Ball & Burlap: Planting of trees will be paid at the bid unit price per each. Work shall include soil preparation, approval of tree selection size and type, root barrier (if applicable), and placement, etc. in accordance with all plans and specifications including Specification 32 93 00. This item will be paid based on Owner's estimate of the number of trees placed during each billing cycle.

68. Bark Mulch 4 inches: Application of 4 inches of bark mulch will be paid at the bid unit price per cubic yard. Work shall include importing and placement of mulch in accordance with all plans and specifications. This item will be paid based on Owner's estimate of the cubic yards of mulch placed during each billing cycle.

69. Landscaping Maintenance: Landscape maintenance will be paid at the bid unit price per lump sum. Work shall include as required reseeding/replacement of trees/shrubs/plants/grass which die for any cause, pruning, irrigation system inspection and maintenance, application of bark mulch, fertilizer, herbicide, and/or pesticide in accordance with all plans and specifications including Specification 32 93 10. This item will be paid (8.3 percent/month) on a monthly progress payment over the course of one year starting with the City's issuance of a Substantial Completion letter.

70. Play Surface Play Matta - Standard Pad areas: Installation of Play Surface with standard pad (walking) thickness will be paid at the bid unit price per square foot.

Work shall include ground preparation (grading, compaction, etc.) and placement of play surface in accordance with all plans and specifications. This item will be paid based on Owner's estimate of the square feet of play surface installed during each billing cycle.

71. Play Surface Play Matta - Thickened pad areas: Installation of Play Surface with thickened pad (fall zone) thickness: Installation of Play Surface will be paid at the bid unit price per square foot. Work shall include ground preparation (grading, compaction, etc.) and placement of play surface in accordance with all plans and specifications. This item will be paid based on Owner's estimate of the square feet of play surface installed during each billing cycle.

72. Playground Equipment- Tree: Installation of the playground tree and ramp will be paid at the bid unit price per lump sum. Work shall include ground preparation (grading, compaction, etc.), placement of foundation, and placement equipment in accordance with all plans and specifications. This item will be paid based on Owner's estimate of the percent completion rounded down to the nearest 10% during each billing cycle.

73. Playground Equipment - Swing 3 Bay: Installation of the playground 3 bay swing will be paid at the bid unit price per lump sum. Work shall include ground preparation (grading, compaction, etc.), placement of foundation, and placement equipment in accordance with all plans and specifications. This item will be paid based on Owner's estimate of the percent completion rounded down to the nearest 10% during each billing cycle.

BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4
20 of 25

74. Playground Equipment - We-Go-Swing: Installation of the playground We-Go- Swing will be paid at the bid unit price per lump sum. Work shall include ground preparation (grading, compaction, etc.), placement of foundation, and placement equipment in accordance with all plans and specifications. This item will be paid based on Owner's estimate of the percent completion rounded down to the nearest 10% during each billing cycle.

75. Playground Equipment - We-Go-Round-Merry-Go-Round: Installation of the playground merry-go-round equipment will be paid at the bid unit price per lump sum. Work shall include ground preparation (grading, compaction, etc.), placement of foundation, and placement equipment in accordance with all plans and specifications. This item will be paid based on Owner's estimate of the percent completion rounded down to the nearest 10% during each billing cycle.

76. Playground Equipment - We-Saw-See-Saw: Installation of the playground See- Saw elements will be paid at the bid unit price per lump sum. Work shall include ground preparation (grading, compaction, etc.), placement of foundation, and placement equipment in accordance with all plans and specifications. This item will be paid based on Owner's estimate of the percent completion rounded down to the nearest 10% during each billing cycle.

77. Playground Equipment - Concrete embankment slide: The installation of the concrete embankment slide equipment including rail elements shall be paid on a per each basis and shall include all labor, foundation, and installation related to the final buildout as shown in the plans and specifications. All work is to be installed where shown on the Plans or as directed by the City or the Engineer. This item to be paid based on Owner's estimate of the number of elements installed on the project during each billing cycle.

78. Playground Fencing: Installation of playground fencing will be paid at the bid unit price per linear foot. This item includes all work necessary to install fencing including foundation, posts, gates, fencing, and all other items needed to install the fence in accordance with plans & specifications including section 32 31 13. This item to be paid based on Owner's estimate of the linear feet of fence installed on the project during each billing cycle.

79. Playground Specialized Fencing DELETED: Installation of specialized playground fencing will be paid at the bid unit price per linear foot. This item includes all work necessary to install fencing including foundation, posts, gates, fencing, and all other items needed to install the fence in accordance with plans & specifications including section 32 31 13. This item to be paid based on Owner's estimate of the linear feet of fence installed on the project during each billing cycle.

80. Playground Shotcrete Boulders: Placement of shotcrete hard rock-boulders will be paid at the bid unit price per square foot each boulder placed of average size. Each boulder to be approximately 3' × 3' × 4', or 2 tons each per average.

BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4
21 of 25
Work shall include excavation, placement, and backfill in accordance with all plans and specifications. This item will be paid based on Owner's estimate of the quantity placed during each billing cycle.

81. Picnic Tables: The installation of the picnic tables shall be paid at the bid unit price per each basis and shall include all labor, foundation, and installation related to the table placement as shown in the plans and specifications. All work is to be installed where shown on the Plans or as directed by the City or the Engineer. This item to be paid based on Owner's estimate of the number of tables installed on the project during each billing cycle.

82. Standard Concrete Benches: The installation of the benches shall be paid at the bid unit price per each basis and shall include all labor, foundation, and installation related to the bench placement as shown in the plans and specifications. All work is to be installed where shown on the Plans or as directed by the City or the Engineer.

This item to be paid based on Owner's estimate of the number of benches installed on the project during each billing cycle.

83. Furnish & Install Removable Bollards: The installation of removable bollards shall be paid on a per each basis and shall include all labor, foundation, inserts, sleeves, and adjacent paving related to the final buildout of the removable bollards as shown in Detail 3 on L9.07 of the Beachfront Park Improvements Phase 1B plans and specifications including section 26 00 00. All work is to be installed where shown on the Plans or as directed by the City or the Engineer. This item to be paid based on Owner's estimate of the number of bollards installed on the project during each billing cycle.

84. Furnish & Install Stage Rail: Installation of the handrails on the Amphitheater Stage will be paid for per linear foot. Work shall include the fabrication and installation of the handrail in accordance with sheets L9.04 & L9.05 of the Beachfront Park Improvements Phase 1B plans and and specifications. This item comprises the following: embedment/foundation, placement, and finish of handrails. This item to be paid based on Owner's estimate of the number of linear feet installed on the project during each billing cycle.

85. Install Bicycle Racks: Installation of the bicycle racks will be paid at the bid unit price per each. Work shall include the purchase and installation of the bicycle racks in accordance with detail 7 on page L9.06 of the Beachfront Park Improvements Phase 1B plans and specifications including section 32 33 00. This item comprises the following: footing/foundation, flange placement, and installation of bicycle rack.

This item to be paid based on Owner's estimate of the number of racks installed on the project during each billing cycle.

86. Drinking Fountain: The installation of the accessible drinking fountain will be paid at the bid unit price per lump sum. Installation of the accessible drinking fountain shall include excavation and disposal of native material, removal and disposal of existing structures, backfill material, compaction of materials, foundation, surface mounting, BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4
22 of 25
and plumbing in accordance with detail 4 on sheet L9.07 of the Beachfront Park Improvements Phase 1B plans, and specifications including section 32 33 00. This item 90 percent will be paid on completion of installation and compaction to subgrade.

The final 10 percent will be paid with the final payment.

87. Fencing - Guardrail: DELETED Installation of the guardrail fencing will be paid at the bid unit price per linear foot. This item includes all work necessary to install fencing including foundation, posts, rail, and all other items needed to install the fence in accordance with plans & specifications including section 32 31 13. This item to be paid based on Owner's estimate of the linear feet of fence installed on the project during each billing cycle.

88. Irrigation - Irrigation water connections and backflow devices: This item to be paid based on the completed percentage of irrigation line tie-ins and backflow devices installed. Work shall include installation of the pot-holing of existing utilities, water line connections, valving, and installation of backflow devices as shown on the plan drawings and as required per the plan specifications section 32 84 00.

This item comprises the following: excavation and disposal of native material, removal and disposal of existing lines and structures where shown, backfill material, and compaction of materials to subgrade (soil ready to receive landscaping). This item will be paid based on Owner's percent complete during each billing cycle.

89. Cast-in-place Trench Drains: This item to be paid by the lineal foot of trench drain installed. Work will include excavation, drain placement, bedding and connecting to the storm drain piping. Concrete finished surfacing to be paid for under the appropriate concrete flatwork item. This item will be paid based on footage drain installed during each billing cycle.

90. Raised Curb, Type 1: Material callout 2.7. Plan detail 8, sheet L9.02. This item will be paid at the bid unit price per linear foot. This item includes all work necessary to construct a 6-inch wide curbing including subgrade preparation, placing and compaction of aggregate base, and all other items needed to install the band in accordance with details on L9.02 of the Beachfront Park Improvements Phase 1B plans and specifications. This item to be paid based on Owner's estimate of the linear feet installed on the project during each billing cycle.

91. Playground Equipment - Humpback Whale: Installation of the humpback whale play equipment will be paid at the bid unit price per lump sum. Work shall include ground preparation (grading, compaction, etc.), placement of foundation, and placement equipment in accordance with all plans and specifications. This item will be paid based on Owner's estimate of the percent completion rounded down to the nearest 10% during each billing cycle.

92. Playground Equipment - Morphe Dome: Installation of the Morphe Dome will be paid at the bid unit price per lump sum. Work shall include ground preparation (grading, compaction, etc.), placement of foundation, and placement equipment in BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4
23 of 25
accordance with all plans and specifications. This item will be paid based on Owner's estimate of the percent completion rounded down to the nearest 10% during each billing cycle.

93. Playground Equipment - Lighthouse Rock Climber: Installation of the playground Lighthouse Rock Climber equipment will be paid at the bid unit price per lump sum.

Work shall include ground preparation (grading, compaction, etc.), placement of foundation, and placement equipment in accordance with all plans and specifications. This item will be paid based on Owner's estimate of the percent completion rounded down to the nearest 10% during each billing cycle.

94. Playground Equipment - Animato Metal Lophone: Installation of the playground Animato Metal Lophone equipment will be paid at the bid unit price per lump sum.

Work shall include ground preparation (grading, compaction, etc.), placement of foundation, and placement equipment in accordance with all plans and specifications. This item will be paid based on Owner's estimate of the percent completion rounded down to the nearest 10% during each billing cycle.

95. Playground Equipment - Ditty Metal Lophone: Installation of the playground Ditty Metal Lophone elements will be paid at the bid unit price per lump sum. Work shall include ground preparation (grading, compaction, etc.), placement of foundation, and placement equipment in accordance with all plans and specifications. This item will be paid based on Owner's estimate of the percent completion rounded down to the nearest 10% during each billing cycle.

96. Playground Equipment - Grandioso Chimes: The installation of the Grandioso Chimes equipment shall be paid on a per each basis and shall include all labor, foundation, and installation related to the final buildout as shown in the plans and specifications. All work is to be installed where shown on the Plans or as directed by the City or the Engineer. This item to be paid based on Owner's estimate of the number of elements installed on the project during each billing cycle.

97. Playground Equipment - Drums (3) sets: Installation of the three playground drum sets listed in plan set. The drum elements will be paid at the bid unit price per lump sum. Work shall include ground preparation (grading, compaction, etc.), placement of foundation, and placement equipment in accordance with all plans and specifications. This item will be paid based on Owner's estimate of the percent completion rounded down to the nearest 10% during each billing cycle.

98. Playground Equipment - Miscellaneous playground expenses: This pay item is intended to cover playground equipment costs not included in the specific bid items listed above. Bid items #70 through #80, and #90 through #98 are lump sum items that should have costs particular to those items. Any other costs not inclusive to those itemized playground items can be placed in this miscellaneous playground expense item. This item to be paid based on Owner's estimate of the percentage complete per the submitted schedule of value for this item for each billing cycle.

BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4
24 of 25

99. Concrete Valley Gutter - 6" x 4 foot: This item will be paid at the bid unit price per linear foot. This item includes all work necessary to construct 6-inch reinforced concrete valley gutter, 6 inches of concrete over 6 inches of base rock. Reinforcing to include four each #4 bar, run lengthwise. The pay item includes subgrade preparation, and all other items needed to install the valley gutter in accordance with the plans and specifications including section 32 12 13. This item to be paid based on Owner's estimate of the linear footage installed on the project during each billing cycle.
100. Transitional ramps, curbs, and gutters: This item will be pay off a percentage of the lump sum price for all work necessary to construct various curbs, gutters and ramps at transitional areas that are not include in the concrete flatwork items listed above. Reinforcing to #3 bar in the gutter pan, curbing and driveway sections only.

The pay item includes subgrade preparation, and all other items needed to install the this transitional concrete in accordance with the plans and specifications including section 32 12 13. This item to be paid based on Owner's estimate of the percentage complete on the project during each billing cycle.

END OF SECTION
BEACHFRONT PARK IMPROVEMENTS PHASE 1B
CONTRACT 2026-1056.3
01 20 00 - MEASUREMENT AND PAYMENT - ADDENDA #4
25 of 25

← All documents from this meeting