November 11, 2024 Page 1 2024-R___
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21 22
23 24
25 26
27 28
29 30
31 32
33 RESOLUTION NO. 2024-R___

A RESOLUTION OF THE CITY COUNCIL OF CITY OF CULVER CITY, CALIFORNIA, APPROVING EXTENDED CONSTRUCTION HOURS FOR 5700 HANNUM MIXED USE COMPREHENSIVE PLAN PROJECT LOCATED AT 5700 HANNUM AVENUE.

(Extended Construction Hours)

WHEREAS, on October 9, 2023, 5700 Hannum Owner, LLC c/o Lincoln Property Company, (the “Applicant”) filed applications for a General Plan Map Amendment, Zoning Code Map Amendment, Comprehensive Plan, Density and Other Bonus Incentives, and Extended Construction Hours to construct a 6-story, up to 78-foot high, mixed use residential and commercial development on a 2.23 - acre site. (the “Project”). The Project is more specifically described by Los Angeles County Assessor Parcel Number 4134-005-015 in the City of Culver City, County of Los Angeles, State of California at 5700 Hannum Avenue in Culver City, California, 90230; and, WHEREAS, the Extended Construction Hours request specifically asks that earthwork shoring and excavation, concrete pours for mat foundation, concrete pours for decks, and tower crane erection and dismantlement begin at 7:00 AM instead of 8 AM, Monday through Friday ; 7:00 AM instead 9:00 AM on Saturdays; and 7:00 AM instead of 10:00 AM on Sundays; and with these activities ending before 8:00 PM, Monday through Friday; and before 7:00 PM on weekends; and WHEREAS, the Culver City Municipal Code Section 9.07.035 allows an applicant to request extended construction activity of a specific nature, with a limited duration, in nonresidential zoning districts, on construction sites one (1) acre or greater in size, if the exception is determined to be in the public interest; and,
WHEREAS, on July 10, 2024, after conducting a duly noticed public hearing on the subject applications, including full consideration of the applications, plans, staff report, environmental information and all testimony presented, the Planning Commission by a vote of 3 to 0, recommended to the City Council approval of the Extended Construction H ours land use permit; as set forth herein below.

November 11, 2024 Page 2 2024-R___
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21 22
23 24
25 26
27 28
29 30
31 32
33 NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF CULVER CITY, CALIFORNIA, RESOLVES AS FOLLOWS:

SECTION 1. Pursuant to the foregoing recitations and the provisions of the Culver City Municipal Code (CCMC), th e following findings are hereby made pursuant to CCMC Section

9.07.035.C:

A. The construction activity is of a specific nature.

The proposed construction activities are consistent with the type of construction activities that would be permissible during normal construction hours pursuant to the CCMC. The construction activities that would occur during the extended hours would be of a specific nature, limited to Earthwork Shoring/Excavation, Concrete Pours for Mat Foundation, Concrete Pours for Decks, and Tower Crane Erection/Disassembly. An Environmental Impact Report (EIR) was prepared for the property which disclosed that significant construction noise impacts would occur with or without the extended construction hours commencing at 7:00 am instead of 8:00 a.m. on weekdays, 7:00 am instead of 9:00 am on Saturdays, and 7:00 am instead 10:00 am on Sundays. Mitigation measures were included in the EIR to reduce impacts. The extension of construction time by 1 to 3 hours in the morning would reduce the overall construction time period by 60 days.

B. The construction activity is of limited duration.

The Applicant is proposing to increase construction hours as follows:

Type of Construction Daily Construction
Hours
Duration Commencement
of Activity
Earthwork
Shoring/Excavation
7:00 am to 3:00 pm
daily
90 days over
120-day period
2nd month of
construction
Concrete Pours for
Mat Foundation
7:00 am to 5:00 pm
weekdays
and
7:00 am to 6:00 pm
weekends
6 nonconsecutive days
over 8-week period
7th month of
construction
Concrete Pours for
Decks
7:00 am to 5:00 pm
weekdays
30 nonconsecutive days
over 7-month period
11th month of
construction
Tower Crane
Erection/Disassembly
7:00 am to 5:00 pm
weekdays
2 separate 3-day events
(6 days total)
1st event on 7th
month of
construction
and
2nd event on 20th
month of
construction

The extension of the construction hours would reduce overall construction time by 60 days, reducing the time period where impacts to the neighboring properties would occur.

C. The construction activity is occurring in a non-residential zone.

The construction activity will occur in a Planned Development zone that currently does not include residential uses.

November 11, 2024 Page 3 2024-R___
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21 22
23 24
25 26
27 28
29 30
31 32
33 D. The construction site is one or more acres.

The construction site totals 2.23 acres.

E. The extended construction hours request is made in conjunction with a land use permit.

This request is made in conjunction with a request for General Plan and Zoning Map Amendments, a Comprehensive Plan, and a Density and Other Bonus Incentives.

F. It is in the public interest to allow for extended construction hours.

The proposed extended hours would coordinate construction hours across the entire Project site.

The proposed extension of hours detailed in Finding B above would allow construction in an effective and efficient way resulting in a 60 -day reduction of overall construction. A Project Condition requires the City review and approve a Construction Management Plan that will stipulate construction workers park at approved off site locations. This construction parking related condition will be followed during extended construction hours. The construction activity/hours will comply with all Project conditions and all applicable regulations and will not interfere or adversely impact other activities/uses surrounding the Project Site pursuant to Project technical studies. Nuisance factors such as noise and traffic impacts to adjacent properties were analyzed in the Project EIR and mitigate d where possible. The extension of the construction hours would reduce overall construction time by 60 days, reducing the time period where impacts to the neighboring properties would occur. The Project conditions apply to the extended hours and the Public Works Department will review and approve a Construction Management Plan, Pedestrian Protection Plan, and Construction Traffic Management Plan to adequately address potential impacts from the increased hours. Any proposed revisions to these construction pl ans will require Public Works Engineering Division and the Current Planning Division approval. The City may impose additional measures including construction signage informing the public of extended construction hours, increased sound attenuation, and added traffic control construction personnel.

SECTION 2. Pursuant to the foregoing recitations and findings, the City Council of the City of Culver City, California, hereby approves the Extended Construction Hours request subject to mitigations listed in a separate resolution certifying the Project’s EIR and conditions of approval/code requirements listed in the ordinance adopting the Comprehensive Plan/Planned Development 18.

APPROVED and ADOPTED this 11th day of November 2024.

____________________________
DAN O’BRIEN, Vice Mayor
City of Culver City, California

ATTESTED BY: APPROVED AS TO FORM:

___________________________ ____________________________ JEREMY BOCCHINO, City Clerk HEATHER BAKER, City Attorney