RESOLUTION NO. 2025-R __________
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF
CULVER CITY, CALIFORNIA , INCORPORATING THE
BUCKINGHAM PARKWAY (BETWEEN GREEN VALLEY
CIRCLE AND HANNUM AVENUE) PAVING PROJECT
INTO THE LIST OF CITY PROJECTS TO BE FUNDED BY
SB 1 (THE ROAD REPAIR AND ACCOUNTABILITY ACT )
IN FISCAL YEAR 2025-2026.
WHEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017 (Chapter 5, Statutes of 2017) , was passed by the Legislature and signed into law by the Governor in April 2017 in order to address the significant multi -modal transportation funding shortfalls statewide; and
WHEREAS, SB 1 includes accountability and transparency provisions that will ensure the residents of the City of Culver City are aware of the projects proposed for funding in the Culver City community and which projects have been completed each fiscal year; and WHEREAS, the City Council must approve by resolution a list of all projects proposed to receive funding from the Road Maintenance and Rehabilitation Account (RMRA), created by SB 1, which must include a description and the location of each proposed project, a proposed schedule for the project’s completion, and the estimated useful life of the improvement; and
WHEREAS, the City will receive an estimated $ 1,095,117 in RMRA funding in Fiscal Year 2025-2026 from SB 1; and
WHEREAS, the City used a Pavement Management System or Los Angeles County Bridge Inspection report to develop the SB 1 project list; and WHEREAS, the funding from SB 1 will help the City maintain and rehabilitate 111 centerline miles of streets, seven bridges, and add active transportation infrastructure throughout the City; and
-2-
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21 22
23 24
25 26
27 28
WHEREAS, the 20 21 California Statewide Local Streets and Roads Needs Assessment found that the City’s streets and roads are in an “ at risk ” condition and this revenue will help the City increase the overall quality of its road system and over the next decade will bring City streets and roads into a “good” condition; and WHEREAS, the SB 1 project list and overall investment in the City’s local streets and roads infrastructure, with a focus on basic maintenance and safety, investing in complete streets infrastructure, and using cutting -edge technology, materials and practices, will have significant positive co-benefits statewide.
NOW, THEREFORE, the City Council of the City of Culver City, California, DOES HEREBY RESOLVE, as follows:
1. The foregoing recitals are true and correct.
2. The City Council hereby approves the following project for funding with Road Maintenance and Rehabilitation Account revenues:
Project Title : Annual Street Paving Project Buckingham Parkway (between Green Valley Circle and Hannum Avenue, PS-005)
Project Description : Grind and overlay of Buckingham Parkway (between Green Valley Circle and Hannum Avenue ), including full depth removal and replacement of failed pavement areas, replacement of damaged curb, gutter and sidewalk, and traffic striping restoration and improvements
Project Location: Buckingham Parkway ( between Green Valley Circle and Hannum Avenue)
/ / /
/ / /
/ / /
-3-
1 2
3 4
5 6
7 8
9 10
11 12
13 14
15 16
17 18
19 20
21 22
23 24
25 26
27 28
Estimated Project Schedule: Start (2025)– Completion (2026) Estimated Project Useful Life: 15 – 20 years
APPROVED AND ADOPTED on the _____day of __________, 2025.
____________________________
DAN O’BRIEN, Mayor
City of Culver City, California
ATTEST: APPROVED AS TO FORM:
_______________________________ ____________________________ JEREMY BOCCHINO, City Clerk HEATHER BAKER, City Attorney