Attachment No. 7

PROJECT SUMMARY
APPLICATION TITLE & CASE NO:

Costco Fueling Station Relocation and Expansion: The project consists of a Conditional Use Permit Modification (P2021-0135-CUP/M) for the relocation and expansion of an existing fueling station, surface parking , and associated project design features and site improvements.

PROJECT ADDRESS/LOCATION: APPLICANT INFORMATION:
13431 – 13463 Washington Boulevard
(±3.2-acre portion between Walnut Ave and Glencoe
Ave)
Costco Wholesale
999 Lake Drive
Issaquah, WA 98027
PERMIT/APPLICATION TYPE:

Administrative Use Permit
Conditional Use Permit Modification
Administrative Site Plan Review
Site Plan Review
Administrative Modification
Variance
Master Sign Program
Certificate of Appropriateness
Certificate of Exemption
DOBI
Tentative Parcel Map
Tentative Tract Map
Lot Line Adjustment
Zoning Code Amendment - Text
Zoning Code Amendment -Map
General Plan Amendment - Text
General Plan Amendment - Map
Planned Unit Development
Specific Plan
Other: Administrative Modification
APPROVAL BODY: Public Hearing Public Meeting Administrative Administrative
Planning Commission
City Council
Redevelopment Agency
Other:

ENVIRONMENTAL DETERMINATION AND NOTICING:

CEQA
Determination
Categorical Exemption (CEQA Section 15332, Class 32)
Negative Declaration
Mitigated Negative Declaration
Environmental Impact Report
CEQA Noticing Notice of Exemption (w/in 5 days of decision) Notice of Intent to Adopt (21 days prior to decision)
Notice of Determination (w/in 5 days of decision)
Fish & Game Certificate of Fee Exemption (w/in 5 days of decision) Notice of Preparation Notice of Availability Notice of Completeness PUBLIC NOTIFICATION:

Mailing
Date: 07/03/2024
Property Owners
Occupants
Adjacent Property Owners & Occupants
w/in 500’ foot radius
w/in 500’ foot radius / extended
Other: Beyond 500’ radius
Posting
Date: N/A
Onsite (1 per frontage) Offsite Other:

Publication
Date: N/A
Culver City News Other:

Courtesy
Date: 07/03/2024
City Council
Commissions
Master Notification List
Culver City Website
Nextdoor
Press Release
HOA /Neighborhood Groups
Culver City Organizations
Other: GovDelivery (Planning
Commission and Public Notification)

PROJECT SUMMARY

Page 2 of 3 ends

GENERAL INFORMATION:

General Plan
Regional Center
Zoning
Commercial Regional Retail (CRR)
Redevelopment Plan
N/A
Overlay Zone/District
Commercial Zero Setback
Site Description
A ±3.2-acre portion of land within Lots 1, 2, 4, and
7 of PM 284-74-75 (parcels identified by Los
Angeles County Assessor’s Parcel Numbers 4236-
029-003, 4236-029-008, and 4236-029-009), in the
City of Culver City, County of Los Angeles, State of
California
Existing Land Use
Fueling station and two commercial structures (retail,
food retail)

ADJACENT ZONING AND LAND USES
Location Zoning Land Use
North R1 and R2* One- and 2-story single- and multi-family residential South CG Multi-story commercial/office
East: CG and R1 Mixed-use, commercial; single-family residential West C2 and R1* Parking lot, commercial; single and multi-family residential *Within City of Los Angeles
Project Data Existing Proposed Required
Lot Area: ±3.2 acres NA NA
Building Size: 8,480 s.f. 0** s.f. NA
**Excludes open fueling station canopy
Parking: Existing Proposed Required
Standard 842 798 None
Compact 91 80 None
Accessible 30 29 29
Total: 963 907 None
Building Height:

Existing Proposed Required
24 ft. 17.5 ft. 56 ft. (maximum)
Building Setbacks:

Existing Proposed Required
Front (Washington) 10 ft. 25 ft. 15 ft.

Rear (north) +700 ft. +700 ft. 15 ft.

Side (east) 5 ft. 55 ft. 15 ft.

Side (west) 10 ft. 65 ft. 15 ft.

ESTIMATED DEVELOPMENT FEES:

New Development Impact: $6,822
Mobility: N/A
In Lieu Parkland: N/A
Affordable Housing Impact:

N/A
Art in Public Places: TBD
Plan Check: TBD
School District: N/A
Sewer: TBD
Note: Additional fees may be assessed by other Divisions/Departments during the approval process.

INTERDEPARTMENTAL REVIEW:

The Project Review Committee reviewed the project during the Preliminary Project Review phase and following the application submittal, and provided responses. Comments have been incorporated into the plans or were made part of the recommended conditions of approval.

PROJECT SUMMARY

Page 3 of 3 ends

Project Description
The fueling station relocation and expansion will include the following project design features.

Project Design Feature 1 (PDF-1): Temporary noise barriers to be provided at the following locations to block the line-of-sight between the construction equipment and the adjacent noise sensitive uses. • Along the project’s western property line: Noise barrier shall provide minimum 20 dBA noise reduction (minimum 16 feet high, relative to local grade elevation) at the residences across the Project Site to the west (receptor location R1).
• Along the project’s northern property line: Noise barrier shall provide minimum 5 dBA noise reduction (minimum 6 feet high, relative to local grade elevation) at the residences to the northwest (receptor location R5).
• Along the existing fuel station eastern property line: Noise barrier shall provide minimum 12 dBA noise reduction (minimum 12 feet high, relative to local grade elevation) to the residences across the Project Site to the east (receptor location R3).

Project Design Feature (PDF -2): The Project contractor will use power construction equipment with properly operating and maintaine d noise shielding and muffling devices, consistent with manufacturers’ standards.

Project Design Feature (PDF-3): The Project construction activities will avoid concurrent construction with the Washington Boulevard Stormwater and Urban Runoff Project (City’s Sewer Project) within:
• 500 feet of receptor location R1
• 400 feet of receptor location R3
• 100 feet of receptor location R4
Landscaping
Plantings along the street edges of the (Washington Blvd and Walnut Ave) will incorporate screening shrubs, with taller plantings along portions of Walnut Ave. The species will be selected to complement the existing landscape plantings while improving screening and tree canopy shade cover.

Refuse
The refuse requirements have been reviewed and confirmed to comply wit h applicable requirements by the Environmental Programs and Operations (EPO) Division.

Parking and Circulation
Culver City no longer has minimum parking requirements, though the applicant team has provided each unit with two parking spaces within an attached garage. Dedicated bike parking is not required due to the size of the Project.

Noise
The tallest of the noise barriers listed in the project design features above, will be placed to provide the most noise reduction at the closest residential properties along Walnut Ave, just west of the proposed relocated fueling station. Additionally, construction equipment utilized for the Project will have properly operating and maintained noise shielding and muffling devices. Coordination with the City’s stormwater project will also minimize noise by avoiding concurrent construction within specified distances of the surrounding residential streets.