CITY OF CULVER CITY PZ-428 May 2026

CONTRACT DOCUMENTS
AND

SPECIFICATIONS
FOR

Sidewalk, Curb Ramp, and Driveway Approach Improvement
Project, PZ-428

CITY OF CULVER CITY

BID NO. #2673

Public Works Department

City of Culver City
9770 Culver Boulevard
Culver City, CA 90232-0507
(310) 253-5600

__________________________________________

Yanni Demitri, P.E., T.E., Public Works Director and City Engineer

CITY OF CULVER CITY PZ-428 May 2026

TABLE OF CONTENTS

PAGE

SECTION A - NOTICE INVITING BIDS .................. ....................................................... A-1 through A-2

SECTION B - INSTRUCTIONS TO BIDDERS ............ .................................................. B-1 through B-7

SECTION C - BID FORMS/FEDERAL FORMS ............ ............................................. C-1 through C-16

SECTION D - AWARD AND EXECUTION OF CONTRACT .... .................................. D-1 through D-10

SECTION E - SPECIAL PROVISIONS .................... .................................................... E-1 through E-28

SECTION F - TECHNICAL SPECIFICATIONS .............. ............................................... F-1 through F-8

APPENDICES

A – Sidewalk, Curb Ramp and Driveway Approach Impro vement Exhibit

B – Hillside Cemetery Entrance Exhibit

C - Construction Standard Details

D – Public Works Department EPO: Service Agreement and C&D Fees

E – Fiber line Microtrench Detail

CITY OF CULVER CITY PZ-428 May 2026

NOTICE INVITING BIDS

SECTION A PAGE A-1

CITY OF CULVER CITY PZ-428 May 2026

CITY OF CULVER CITY

NOTICE INVITING SEALED BIDS
FOR

Sidewalk, Curb Ramp, and Driveway Approach Improvem ent Project, PZ-428 BID NO. #2673

1. ANNOUNCEMENT

Notice is hereby given that electronic bids will be accepted by Culver City PlanetBids, for furnishing all labor, services, materials, and equipment, and perf orming all work to provide for a complete and acceptable project for:

Sidewalk, Curb Ramp, and Driveway Approach Improvem ent Project, PZ-428, BID NO. #2673

In the City of Culver City and in strict accordance with the plans and specifications in the Office of the Public Works Director and City Engineer of the City of Culver City, 9770 Culver Boulevard, Culver City, CA. 90232.

2. DESCRIPTION OF WORK:

The work to be done consists of furnishing all mate rials, equipment, tools, labor and incidentals as required in the specifications and contract documen ts, for the following project(s): “Sidewalk, Curb Ramp, and Driveway Approach Improvement Project, PZ -428".

3. COMPLETION OF WORK:

All work to be done under this contract shall be co mpleted within Sixty (60) working days , beginning on the date the Contractor actually commences the W ork or on the tenth (10 th ) day after the issuance
of the "Notice to Proceed" by the City Engineer, whichever comes first.

4. BIDDING PROCEDURES

All bids and bidding procedures must comply with th e "Instruction to Bidders", Section B of the Bid Documents.

5. SUBMISSION OF BIDS

Bid’s must be submitted electronically through
Culver City PlanetBids , by or before 3:00 p.m. (PST) on Thursday, May 28th, 2026 . (“Proposal Deadline”).
https://www.planetbids.com/portal/portal.cfm?Compan yID=39483&access

The electronic procurement system will not accept a ny Bid’s after the Deadline. Only a Proposal submitted electronically through Culver City’s PlanetBids will be considered for evaluation. No separate hardcopy materials will be accepted by the City.

6. BID SECURITY

Each Bidder shall submit a form of Bid Guaranty suc h as a money order, a cashier's check, certified check, cash, or surety bond for the sum of ten perc ent (10%) of the total amount of the bid and made payable to the City of Culver City as a guaranty th at the Bidder, if its bid is accepted, will enter i nto a satisfactory contract and furnish a bond for the fa ithful performance thereof, and for the payment of labor and materials costs, and insurance in accorda nce with the requirements of the contract documents.

Bid security must be submitted electronically throu gh
Culver City PlanetBids along with the bid
proposal. (https://www.planetbids.com/portal/portal.cfm?Compan yID=39483&access )

SECTION A PAGE A-2

CITY OF CULVER CITY PZ-428 May 2026

7. BID DOCUMENTS

A copy of the plans and specifications shall be available on Culver City PlanetBids . (https://www.planetbids.com/portal/portal.cfm?Compan yID=39483&access )

8. PRE-BID CONFERENCE (Not Required)

Not Required

9. FORM AND STYLE OF BIDS

Bids must be prepared on the forms provided with th e BID DOCUMENTS and must be in compliance with the INSTRUCTIONS TO BIDDERS. Bidders shall no t change the wording of the forms provided, except as required by Addendum.

10. QUESTIONS/REQUESTS FOR INTERPRETATION

Questions with regards to this bid should be submit ted through Culver City PlanetBids by Tuesday,
May 19, 2026 at 3:00pm PST . All firms registered for the bid will receive re sponses to all questions and any other addenda that may be released, electronically by Thursday, May 21, 2026. (https://www.planetbids.com/portal/portal.cfm?Compan yID=39483&access )

11. RIGHT TO REJECT BIDS

The Owner reserves the right to reject any or all b ids as the best interests of the Owner may dictate.

Bidders are referred to Section B-18 of the "INSTRUCTIONS TO BIDDERS," for additional qualification requirements.

12. WAGE RATES AND PUBLIC WORKS CONTRACTOR REGISTRATION PROGRAM

In accordance with the California Labor Code, no worker employed in work under contract to the Owner shall be paid less than the State of California Pre vailing wage rates. Contractor shall comply with a ll other Federal, State and local laws related to labor.

Pursuant to California Labor Code Section 1771.1(a) , “A contractor or subcontractor shall not be qualified to bid on, be listed in a bid proposal, subject to the requirements of Section 4104 of the Public Contract Code, or engage in the performance of any contract for public work, as defined in this chapter, unless currently registered and qualified to perfor m public work pursuant to Section 1725.5. It is no t a violation of this section for an unregistered contr actor to submit a bid that is authorized by Section 7029.1 of the Business and Professions Code or by S ection 10164 or 20103.5 of the Public Contract Code, provided the contractor is registered to perf orm public work pursuant to Section 1725.5 at the time the contract is awarded.”

13. CONFLICT OF INTEREST

The CONTRACTOR affirms that in the procurement of t his contract, there was no apparent or real conflict of interest as outlined in 2 CFR Part 200.318 (c)(1)(2).

14. CONTRACTOR'S LICENSE

All bidders shall be licensed under provisions of Chapter 9, Division 3 of the Business and Professions Code of the State of California to do the type of w ork contemplated in the project. In accordance wit h provisions of California Public Contract Code Secti on 3300, the Owner has determined that the Contractor shall possess a valid Class "A" or “C-8” License at the time that the bid is submitted.

Failure to possess the specified license shall render the bid as non-responsive.

--End of Section—

CITY OF CULVER CITY PZ-428 May 2026

SECTION B

INSTRUCTIONS TO BIDDERS
SECTION B PAGE B-1

CITY OF CULVER CITY PZ-428 May 2026

SECTION B - INSTRUCTIONS TO BIDDERS

1. DEFINITIONS

Alternate Bid
"Alternate Bid" shall mean an amount stated in the Bid as set forth in the supplementary bid forms, to be added to or deducted from the Total Base Bid, if the corresponding substitution or change in the Work, materials or other items as described in the Bid Documents, is accepted by Owner.

Total Base Bid
"Total Base Bid" shall mean the sum stated in the Total Base Bid Form for which the Bidder offers to perform the Work described in the Bidding Documents. The Total Base Bid is the base to which work, materials, or other items may be added to or from which work, materials, or other items may be deleted, for sums stated in the Alternate Bid form.

Bid Date
"Bid Date" shall mean the deadline (including date and time) set forth in the Notice Inviting Bids accompany these Instructions.

Bid Form
"Bid Forms" shall mean the Total Base Bid Form, the Supplementary Bid Forms, and other additions attached hereto, all of which constitute part of the Bid Documents.

Bid Documents
"Bid Documents" shall mean all documents provided b y Owner to Bidder for Bidder's use and consideration in preparation of its Bid. Bidding d ocuments include the Notice Inviting Bids, these Instructions to Bidders and any supplements or addi tions hereto, the Bid Proposal Form, the Supplementary Bid Forms, the Statement of Contracto r's Qualifications, other sample bid and contract forms, the Contract Documents, Drawings, P lans, and Specifications, all documents referenced in the Contract Documents, and all Adden da issued prior to execution of the Contract.

Bidder
"Bidder" shall mean any individual, firm, partnersh ip, corporation, or combination thereof, submitting a Bid for the work, acting directly or through a duly authorized representative.

Sub-bidder
"Sub-bidder" shall mean a person or entity who submits a Bid to a Bidder for materials, equipment or labor (including quantity surveyors) for a porti on of the Work and who is identified on the appropriate Supplementary Bid Form.

Contract Documents
"Contract Documents" shall mean all documents execu ted by Owner and Bidder to evidence their agreements relating to the Work. The Contract Docu ments include, but are not limited to, the Owner-Contractor Agreement; any supplementary and o ther conditions or provisions; the Drawings, the Plans, the Specifications and all Add enda issued prior to execution of the Owner-Contractor Agreement; and all modifications thereof.

Unit Price
"Unit Price" shall mean an amount stated in the Sup plementary Bid Form as a price unit of measurement for materials, equipment and/or services or a portion of the Work as described in the Bid Documents, and shall include all elements of th e described portion of the Work, including materials, labor, overhead and profit.

SECTION B PAGE B-2

CITY OF CULVER CITY PZ-428 May 2026
Work

"Work" shall mean the construction required by the Contract Documents and includes all tools, materials, and labor necessary to produce such cons truction and all materials and equipment incorporated or to be incorporated in such construction.

2. BID AND BID FORMS

Owner Supplied Forms
Bid forms (Section C, “Bid Forms”) have been provid ed with this document by the Office of the Public Works Director/City Engineer of the City of Culver City. All bids for this project must be submitted on said original supplied by the Office o f the City Engineer of the City of Culver City.

Bid forms shall be completely filled out and signed by the Bidder or, if a partnership, by all partners or, if a corporation, by its President, Secretary and Treasurer, in the designated spaces.

Filling-in Forms
All blank spaces for unit prices, extensions and to tals must be filled in. Signatures shall be completely and personally executed. If erasures ar e made, they must be initialed by the Bidder over his signature.

Modifications Prohibited
Bids shall not contain any recapitulation, inserted by the Bidder, of work to be done. Alternative proposals will not be considered unless specifically requested. No oral or telephone modifications will be considered.

Submitting Bids
All bids must be submitted electronically via Culve r City PlanetBids . The electronic procurement system will not accept any Bid’s after the Deadline . Only a Proposal submitted electronically through Culver City’s PlanetBids will be considered for evaluation. No separate hardcopy materials will be accepted by the City.

ALTERNATE BIDS
The Contractor shall complete bid schedules for all Alternate Bids. Failure to complete all bid schedules will be considered a non-responsive bid.

Bids May Be Rejected
Bids may be rejected if there is any alteration of the bid form, additions not called for, conditional bids, qualifying provisions, incomplete entries, or irregularities of any kind. The Owner reserves the right to reject any or all bids.

3. ADDENDA

3.1 Addenda

Addenda for the project will be posted on
Culver City PlanetBids . PlanetBids automatically sends electronic alerts to registered bid holders of addenda notifications.

3.2 Acknowledgment of Addenda

Each Bidder shall ascertain prior to submitting a B id that the Bidder has received all Addenda issued, and the Bidder shall acknowledge its receip t in the Bid Form. Failure to acknowledge all addenda may result the bid proposal being deemed as non-responsive by the City.

4. INTERPRETATION OF PLANS AND SPECIFICATIONS

If any person contemplating submitting a bid for th e project is in doubt as to the meaning of any requirement of plans or specifications or finds any discrepancies in or omissions from the plans or SECTION B PAGE B-3

CITY OF CULVER CITY PZ-428 May 2026
specifications, he may submit Culver City PlanetBid s a written request for an interpretation or correction thereof. The person making the request will be responsible for its prompt delivery.

Interpretations or corrections will be made by adde nda to specifications or by dated revisions of plans with a copy of each addition or change being furnished, through the Public Works Director/City Engineer or Construction Manager, to each known prospective Bidder. Questions concerning the contract form, bonding requirements or similar documents shall be directed to Culver City PlanetBids.

5. EXAMINATION OF SITE, PLANS, SPECIFICATIONS AND OTHER DOCUMENTS

Each Bidder shall carefully examine the plans, thes e specifications and the forms for all other contract documents, and shall visit the site of the proposed work to fully inform him/herself of all existing conditions and limitations that may affect the execution and cost of work under the contract.

He/She shall include in the individual bid prices t he cost of all labor, materials, supplies, overhead and profit for each such bid item. The failure or omission of any Bidder to obtain and examine the plans or specifications, any form, instrument, adde ndum, or any other document, or to visit and acquaint him/herself with conditions at the construction site, shall in no respect relieve him/her from any obligation imposed by his/her bid or by award or execution of the contract. The submission of a bid shall be taken as prima facie evidence that t he Bidder has read, understands and agrees to comply with all instructions contained herein.

6. COMPLETE BIDDING AND CONTRACT DOCUMENTS

A complete set of Bid documents contains the follo wing documents:

1. Notice Inviting Bids, Section A;

2. Instruction to Bidders, Section B;

3. Any or all addenda/addendum;

4. Bid Forms, Section C;

5. Award and Execution of Contract, Section D;

6. Special Provisions, Section E;

7. Technical Specifications, Section F, appendice s and appended drawings.

7. BID GUARANTY

Bid Guaranty Enclosed With Bid
Each bid shall be accompanied by an approved form o f Bid Guaranty such as a cashier's check, money order, certified check or cash, or surety bond in favor of the Owner for an amount of at least ten percent (10%) of the amount of the bid as a gua ranty that the Bidder will provide bonds and insurance, and enter into a contract with the Owner for construction of the project. No bid shall be considered, unless such Bid Guaranty is enclosed.

In lieu of the foregoing, any bid may be accompanie d by a surety bond in said amount, furnished by a surety authorized to do surety business in the State of California, guaranteeing that said bidder will enter into the contract and file the required bonds within the designated period.

Bid security must be submitted electronically throu gh Culver City PlanetBids along with the bid proposal.

SECTION B PAGE B-4

CITY OF CULVER CITY PZ-428 May 2026
Owner to Enforce Bid Guaranty

If within the time frame specified in Section B-18 of these Specifications, the successful bidder fails or neglects to enter into the contract and file the required bonds, the Owner may deposit in its treasury said bid security and not return it to the defaulting bidder.

Bid Guaranty Return

Upon execution of the contract with the successful Bidder, the Bid Guaranties of all Bidders will be returned by the City of Culver City.

8. REJECTION OF BIDS

The Owner reserves the right to reject any or all b ids and to waive any apparent clerical errors or discrepancies, or minor informalities if to do so seems to best serve the interests of the Owner.

9. WITHDRAWAL OF BIDS

Any Bidder may withdraw his bid, without obligation, either personally or by written request, at any time prior to the scheduled closing time for receip t of bids, provided that such personal or written request is delivered to the place specified in Section 5 of the "NOTICE INVITING BIDS" for receipt of Bids, prior to the Bid Date.

10. FACSIMILE MODIFICATION OF BIDS

No facsimile modification of bids will be allowed.

11. OPENING OF BIDS

Bid results will be available after the closing on the Culver City Planet Bids portal.

12. BIDDERS INTERESTED IN MORE THAN ONE BID

Bid’s must be submitted electronically through Culver City PlanetBids. A person, firm or corporation that has submitted a sub proposal to a Bidder or th at has quoted prices of materials to a Bidder is not hereby disqualified from submitting a sub proposal or quoting prices to other Bidders.

13. NON-COLLUSION AFFIDAVITS

The Owner requires all Bidders to execute a Non-Collusion Affidavit in the form included in the Bid Documents. The Owner also reserves the right to re quire that the Bidder shall, before awarding any subcontract, obtain from any or all proposed Su bcontractors a Non-Collusion Affidavit in the form included in the Bid Documents.

14. LIST OF SUBCONTRACTORS FILED WITH BID

In accordance with the provisions of the Public Contracts Code of the State of California relating to listing of subcontractors, each Bidder must submit with his bid the name and location of place of business of each proposed Subcontractor who will pe rform work or labor or render service to the Bidder for the construction of the project covered by the bid, in an amount in excess of one-half of one percent (0.5%) of the Bidder's bid and shall state the portion of the work which will be done by each Subcontractor. Failure to specify subcontracto rs shall result in penalties according to Public Contracts Code.

SECTION B PAGE B-5

CITY OF CULVER CITY PZ-428 May 2026

15. LICENSING OF CONTRACTORS

All Bidders and Subcontractors submitting bids shall be licensed in accordance with the provisions of the Business and Professions Code of the State o f California pertaining to the licensing of contractors. The license shall be valid and active at the time of submitting a bid, and remain so throughout the duration of the Contract for the successful bidder and sub-bidders.

16. APPROXIMATE ESTIMATES

The quantities set forth on the bid form, if any, are approximate only, being given as a basis for the comparison of bids; and the Owner does not, expressly or by implication, agrees that these will be the final quantities. The Bidder agrees that the O wner will not be responsible if any of said quantities are found to be incorrect; and the Bidde r agrees not to make any claim for damages or for loss of profits because of a difference between the quantities of the various classes of work as estimated and the work actually done. If any error , omission or misstatement shall be discovered in the estimated quantities, the same shall not invalidate the contract executed pursuant to this bid or release the Bidder from the execution and comple tion of the whole or part of the work herein specified, in accordance with these specifications and the plans herein mentioned and the prices herein agreed upon and fixed therefore, or excuse h im from any of the obligations or liabilities hereunder, or entitle him to any damages or compens ation otherwise than as provided for in the contract executed pursuant to this bid.

17. GENERAL REQUIREMENTS

It is the purpose of the Owner, pursuant to these specifications, to realize work on a project, which is complete in every detail and respect. The Bidder shall furnish all equipment, materials and labor and perform all work required to accomplish this pu rpose. The Bidder shall not omit any item of work or fail to furnish any element, component or p art thereof, whether or not such is specifically called for in the Contract Documents, which is necessary for a satisfactory completion of the project.

18. AWARD OF CONTRACT

The contract will be awarded to the lowest responsible and responsive Bidder. If award is made, it will be based on the lowest responsive and responsible total base bid Contract price. Selection of any or all alternates shall be at the sole discreti on of the Owner. The Owner, however, reserves the right to reject any or all bids, and, so far as permitted by law, to waive any informality in the bids received in order to serve the best interests of th e Owner. If an award is made, the contract shall be awarded within ninety (90) days after the opening of the bids. Within ten (10) days of the mailing by the Owner of notification of award of contract a nd the contract form, Bidder shall provide and return to the Owner all required bonds and insurance documents and the executed formal contract.

In determining if a Bidder is a responsive bidder, the Owner shall consider the following in addition to other requirements in these bid documents:

a. Quality of services offered.

b. Proven capacity of the Bidder to perform the con tract or provide the supplies or services required in a timely and competent manner. The evaluation of the Contractor's capacity to perform the contract or pr ovide the supplies or services required in a timely and competent manner shall be based on the information provided by the Contractor in Section C-5 "Declarat ion of Bidder's Qualifications," as well as other pertinent data available to the Owner.

c. Character, integrity, reputation, judgment, expe rience and efficiency of the Bidder.

SECTION B PAGE B-6

CITY OF CULVER CITY PZ-428 May 2026

19. BONDS

The successful bidder will be required to file and pay for costs of bonds in the proper sums from a bonding company acceptable to the Owner. Forms for these bonds are included in Section D. The "Labor and Materials Payment Bond" and "Faithful Pe rformance Bond" shall be for one hundred percent (100%) of the contract price (including base bid, adjustments and addenda).

20. INSURANCE CERTIFICATES AND POLICIES

Proof of insurance in an amount required by the Bid Specifications Section D-6 must be provided and endorsed to name: the City of Culver City, memb ers of its City Council, its boards and commissions, officers, agents, and employees as additional insured for the particular operations of the insured which affect the Owner.

21. INDEMNIFICATION.

To the fullest extent permitted by law, Contractor shall indemnify, defend (at Contractor's sole expense, with legal counsel approved by City) and h old harmless the City of Culver City, members of its City Council, its boards and commiss ions, officers, agents, and employees (hereinafter, "Indemnitees"), from and against all loss, damage, cost, expense, liability, claims, demands, suits, reasonable attorneys' fees and judg ments arising from or in any manner connected to Contractor 's or its employees or agen t’s acts, errors or omissions related to this Agreement. This indemnification includes, but is n ot limited to, tort liability to a third person for bodily injury and property damage.

Notwithstanding the foregoing, nothing herein shall be construed to require Contractor to indemnify an Indemnitee from any claim arising from the sole negligence, active negligence or willful misconduct of that Indemnitee.

The duty to defend referenced herein is wholly inde pendent from the duty to indemnify, arises upon written notice by City to Contractor of a clai m within the potential scope of this indemnification provision, and exists regardless of any determination of the ultimate liability of Contractor, City or any Indemnitee.

22. ASSIGNMENT OF CONTRACT RESTRICTED

No assignment by the Bidder of any contract to be e ntered into in accordance with Notice Inviting Bids and these instructions or any part thereof, or of funds to be received there under, will be recognized by the Owner unless such assignment had prior written approval of the Owner and the surety on all bonds had notice of such assignment in writing and has consented thereto in writing.

In entering into the Contract or any Subcontract fo r the Project, the Contractor and Subcontractor offer and agree to assign to the Owner all right, title and interest in and to all causes of action they may have under Section 4 of the Clayton Act (15 U.S .C. Sec. 15) or under the Cartwright Act (Chapter 2 [commencing with Section 16700] of Part 2 of Division 7 of the Business and Professions Code), arising from the Contract or any Subcontract. This assignment shall be deemed made and effective at the time the Owner tenders final payme nt to the Contractor, without further acknowledgment by the parties.

23. SHORING

Pursuant to the provisions of the California Labor Code Section 6707, each bid submitted in response to this Invitation to Bid shall contain, a s a bid item, adequate sheeting, shoring, and bracing, or equivalent method, for protection of life and limb in trenches and open excavation, which shall conform to applicable safety orders. By list ing this sum, the bidder warrants that its action SECTION B PAGE B-7

CITY OF CULVER CITY PZ-428 May 2026
does not convey tort liability to the Owner, the En gineer, the Construction Manager, and their employees, agents and subconsultants.

24. OTHER PERMITS, FEES AND LICENSES

The Contractor shall, prior to the start of constru ction, obtain, pay, and comply with all necessary permits as required as the result of its work, incl uding but not limited to the permit(s) described herein and as attached in the appendix .

In addition to the requirements above noted, the Co ntractor shall possess a valid City of Culver City business license at the time of contract agreement execution and fo r the duration of the contract. The fee for said business license shall be based upon the total amount bid for the contract. Amount of fee may be obtained from the C ity of Culver City, Finance Department, Treasury Division at (310) 253-5870.

All bidders are encouraged to utilize Culver City s ubcontractors and suppliers to the extent they are available, competitive and qualified. However, no bid will be affected either positively or negatively by the inclusion or exclusion of such Culver City businesses.

-- End of Section --

SECTION C

CITY OF CULVER CITY PZ-428 May 2026

SECTION C

BID FORMS

SECTION C C-1

CITY OF CULVER CITY PZ-428 May 2026

BID FORM

FIRM
NAME ______________________________________________________________

ADDRESS _________________________________________________________

_________________________________________________ _______

TELEPHONE _________________________________________________________

FAX NUMBER ________________________________________________________

FOR

Sidewalk, Curb Ramp, and Driveway Approach Improvement Project, PZ-428

FOR

CITY OF CULVER CITY

CULVER CITY, CALIFORNIA

BID NO. #2673

1 TOTAL BID BASE FORM

TO THE HONORABLE CITY COUNCIL

CITY OF CULVER CITY, CALIFORNIA

This Bid is submitted in accordance with the adver tised "Notice Inviting Bids" requesting sealed bids for furnishing all labor, services, materials and equipment and performing all work necessary for: Sidewalk, Curb Ramp, and Driveway Approach Improvem ent Project, PZ-428.

Having carefully examined the location of the prop osed work and the Bid Documents for same and read the accompanying proposed requirements, and at tended the pre-bid conference, the undersigned Bidder hereby proposes and agrees to en ter into a contract to furnish all equipment, materials and labor necessary to complete all work described in the Bid Documents for the project under the supervision of the City Engineer of the C ity of Culver City for the sum set forth in the following schedule Sidewalk, Curb Ramp, and Driveway Approach Improvem ent Project, PZ- 428.

The undersigned further agrees, in case of award, t o execute the contract for the within described work and improvements, within ten (10) days following written notice of award of contract. All work to be done under this contract shall be completed w ithin Sixty (60) working days , beginning on the date stipulated in the written Notice to Proceed issued by the City Engineer.

Liquidated damages of $1,000 per calendar day shall be assessed based upon the a pplicable number of days noted above. The Contract Time shal l commence on the date the Contractor actually commences the Work or on the tenth (10th) day after the issuance of the Notice to Proceed, whichever comes first. The Contractor shall retain the right to fully complete (including Final Completion, Punch List Correction and project Close -Out) the Work in less days than established by above, however, neither shall a reduction or increase to the Contract Sum be made, if the Work is so fully completed in less days than established by this Section C-1, no Claim shall be made or granted for Compensable Delay, or any other increase in Contract Sum, if, for any reason, including SECTION C C-2

CITY OF CULVER CITY PZ-428 May 2026
but not limited to delay caused by the Owner, the C ontractor does not so fully complete the Work in less days than established herein.

(NOTE: All amounts and totals given in the Bid Sc hedule are subject to verification by the Owner.)

Sidewalk, Curb Ramp, and Driveway Approach Improvem ent Project, PZ-428

BID SCHEDULE

ITEM
NO. ITEM DESCRIPTION

ESTIMATED
QUANTITY UNIT Unit Cost TOTAL
ADA Sidewalk Repair Project
1 Mobilization/Traffic Control 1 LS $ $
2 Construction surveying, staking, and resetting ties
and monuments 1 LS $ $
3 Removal and Replacement of Uplifted Sidewalk at
Various Locations per Exhibit in Appendix A; 4” PCC
over 4” CMB

8431 SF $ $
4 Removal and Replacement of Driveway Approach at
Various Locations per Exhibit in Appendix A; 4” PCC
over 6” CMB
1208 SF $ $
5 Remove and replace PCC curb & gutter per SPPWC
Std. Plan no. 120-3 at Various Locations per Exhibit
A; over 6” CMB
98 LF $ $
6 Remove and reconstruct modified PCC curb ramp
over 6” CMB per Exhibit B
2 EA $ $
7 Remove and reconstruct cross gutter and spandrel
over 6” CMB per Exhibit B
1 LS $ $
8 Remove Existing Tree 7 EA $ $
Total Base Bid Amount (Bid Items 1-8)
TOTAL BID SCHEDULE IN WORDS (Bid items 1 - 8):

______________________________________________________________________________

NOTES:

1. THE CONTRACT WILL BE AWARDED TO THE RESPONSIBLE CONTRACTOR WHO SUBMITS

THE LOWEST TOTAL BASE BID AMOUNT WITH RESPONSIVE AN D RESPONSIBLE BID PROPOSAL.

2. THE PRIME CONTRACTOR SHALL PERFORM, WITH ITS OWN ORGANIZATION, CONTRACT WORK AMOUNTING TO AT LEAST 50% OF THE CONTRACT PRIC E.

The undersigned has carefully checked the above fig ures and understands that the City, or any officer thereof, will not be responsible for any errors or omissions on the part of the undersigned in submitting this bid. In case of a discrepancy between words and fig ures, the figures shall prevail, and in case of a discrepancy between unit prices and totals, the uni t prices shall prevail. The unit price amounts for each item shall include all indirect costs (i.e., permit fee, business license fee, mobilization, coordinat ion, supervision, overhead and profit, etc.), incidental work (i.e. traffic control, safety devices, protec tion of SECTION C C-3

CITY OF CULVER CITY PZ-428 May 2026
utilities, utility investigation and "pot holes," w ork necessary for the protection of life and limb, etc.) and other work required by the contract but not listed above.

2 RECEIPT AND ACKNOWLEDGMENT OF ADDENDUM

We acknowledge that the following addenda numbers have been received and have been examined as part of the Contract Documents. Failure to acknowledge any or all addenda or addendum may result the bid proposal being deemed a s non-responsive by the City.

Addenda Number Date Received Initials

3 CERTIFICATION

The undersigned Bidder certifies that:

1. Bidder has, by investigation of the site of the work and otherwise, understands the nature and location of the work and has fully informed the Owner as to all conditions and matters, which can in any way affect the work or cost thereof.

2. Bidder will cooperate fully with the Owner to e nsure the Owner's best interests are protected and the work expedited to completion. In the event of any disagreement, the City Engineer shall fully review the matter and provide a determination. His judgment shall be final and binding upon all parties concerned.

3. Where demolition is necessary for the proj ect described herein, the successfully awarded Contractor shall conform to the South Coast Air Qua lity Management District (S.C.A.Q.M.D.) Rule 1403, as amended. The Contract or shall mail the Rule 1403 Notification within five (5) calendar days after th e Notice to Commence Work is mailed by the Owner. Once the S.C.A.Q.M.D Rule 1403 Notifica tion has been post marked and mailed, the Contractor shall begin work no later th an fifteen (15) calendar days after the mailing date. The duration set for the completion of this project will begin on the date work actually commences by the Contractor. In any case, the work shall not begin later than twenty (20) days after the date in which the Owner mailed the Notification to Commence Work.

4. All bonds, certificates, endorsement forms shall be submitted at the time of the execution of the contract.

THE UNDERSIGNED BIDDER IS AWARE OF THE FACT THAT T HE OWNERRESERVESTHE

RIGHT TO REJECT ANY OR ALL BIDS BUT THAT IF A BID I S ACCEPTED, THE CONTRACT WILL BE AWARDED TO THE LOWEST RESPONSIBLE AND RESPO NSIVE BIDDER.

SECTION C C-4

CITY OF CULVER CITY PZ-428 May 2026
4 BIDDER INFORMATION

Name of Individual Bidder: ______________________ ___________________________

Bid Prepared By: ________________________________ _________________________

Business Address: _______________________________ ________________________

_________________________________________________ ______________________

Business Telephone Number: _______________________ ________________________

E-mail Address: __________________________________ ________________________

Contractor License No: ___________ Class: _______________________________

OR:

California Public Works Contractor Registration No: ___________

Name of Partnership Bidder: _____________________ ___________________________

Bid Prepared By: ________________________________ _________________________

Business Address: _______________________________ ________________________

E-mail Address: _________________________________ _________________________

Business Telephone Number: ______________________ _________________________

List Names and Business addresses of All Partners Below:

_________________________________________________ ______________________

_________________________________________________ ______________________

If the Bidder is a Corporation, list corporate inf ormation below:

Name of Corporate Bidder: _______________________ __________________________

By: _____________________________________________ _______________________ (Signature of President of Corporation)

By: _____________________________________________ _______________________ (Signature of Secretary of Corporation)

By: _____________________________________________ _______________________ (Signature of Treasurer of Corporation)

Business Address: ________________________________________________________

_________________________________________________ ______________________

Business Telephone Number: _______________________________________________

E-mail Address: _________________________________ _________________________

SECTION C C-5

CITY OF CULVER CITY PZ-428 May 2026
Corporation organized under laws of State of: ___ _______________________________

Contractor License No: _________ Class: __ _______________________________

5 DECLARATION OF BIDDER'S QUALIFICATIONS

Each Bidder must be properly licensed and must subm it the following information on this form. If necessary, include supplement information as a sepa rate package.

5.1 Authorization and Declaration

The undersigned hereby authorizes and requests an y person, firm or corporation to furnish any information requested by Owner or their designated representative in verification of the recitals comprising this Declaration of Bidder's Qu alifications. The undersigned declares under penalty of perjury that all of the qualificat ion information submitted with this form is true and correct and that this Declaration was executed in

________________________________________________ ______________________

(City, County) of California, on ________________ __________ (Date).

Signature: _______________________________________

Title (Printed): _____________________________________

5.2 Business Name, Address, Telephone Numbers (if different than Section C-4)

________________________________________________ ______________________

Business Name: _________________________________ ________________________

Business Address: ______________________________ _________________________

Business Telephone & E-mail Address: ___________ ___________________________

________________________________________________ ______________________

5.3 License

Bidders must be licenses in the State of Californi a as "A" or “C-8” Contractor.

Complete the information requested below.

___________________ __________ __ _________ _____________ License Number Class Date Issued Expiration Date

___________________ __________ __ _________ _____________ License Number Class Date Issued Expiration Date

___________________ __________ __ _________ _____________ License Number Class Date Issued Expiration Date

SECTION C C-6

CITY OF CULVER CITY PZ-428 May 2026

5.4 Surety

A. Indicate the names of all surety companies uti lized by Bidder in last five (5) years and state if the Surety(ies) bonding the Bidder's j obs have had to complete any part of Bidder's Contract (attach separate sheet if necessary).

Surety Name & Address Period Covered

Jobs Completed by Surety

Surety Name & Address Period Covered

Jobs Completed by Surety

B. If a Bid Guaranty (Section C-7) is provided in lieu of a Bid Bond (Section C-6), the Bidder shall attach a notarized statement from Sure ty(ies) proposed to be utilized on the project, indicating Bidder's total bonding c apacity and certifying that: (1) currently available bonding capacity exceeds $500,000 and (2) Surety(ies) will provide bonding in the event that Bidder is awarded the project.

C. Indicate below that the surety is licensed and admitted as a surety insurer in the State of California.

________________________________________________ ________________

________________________________________________ ________________ Surety Name and Address

______________________
Licensed & Admitted in CA
(Y/N)
________________________________________________ ________________ Surety Name and Address

______________________
Licensed & Admitted in CA
(Y/N)

________________________________________________ ________________ Surety Name and Address
______________________
Licensed & Admitted in CA
(Y/N)

D. Indicate below those projects with disputed am ounts in excess of $50,000 or portions of any such project, which have been termi nated by an Owner, Owner's representative, or other contracting party and whic h required completion by another party in the last five (5) years. State th e project Name, Location, Owner, with address and phone number, contract amount, and reason for disputed amount or termination (attach separate sheet if necessary.)

SECTION C C-7

CITY OF CULVER CITY PZ-428 May 2026
________________________________________________ ________________ Project Name and Location

Owner Contract Value

________________________________________________ ________________ Reasons for Disputed Amount or Termination

________________________
Disputed Amount

5.5 Insurance

A. Provide a statement from the Worker's Compensa tion carrier specifying Contractor's current Experience Modification Rate f or Worker's Compensation for the State of California. In addition, provide a li st of the above referenced ratings and corresponding company for the last three (3) years.

B. Provide statement from insurance carrier indic ating that the minimum scope and limits of insurance will be provided as required in Section D-4, of this document.

C. Indicate below that the surety is licensed and admitted as a surety insurer in the State of California.

________________________________________________ ________________ Ins. Co. Name and Address

___________________________
Licensed & Admitted in CA/Y/N

________________________________________________ ________________ Ins. Co. Name and Address

___________________________
Licensed & Admitted in CA/Y/N

5.6.1 Construction Experience

Furnish a list of at least three (3) similar (scope of work and cost) projects completed in the past five (5) years, two (2) of which must have been built in the State of California. Provide the following information for each project on the a ttached form. Copy additional forms as required.

i Project name and location

ii Contact name, address and telephone number for Own er & Architect/Engineer

iii Base and final contract amounts

iv Type of project and major project components. Pro vide approximate percent of construction cost associated with each c onstruction component.

SECTION C C-8

CITY OF CULVER CITY PZ-428 May 2026

v Date project was completed (i.e., date of filing o f Notice of Completion, etc.).

vi Indicate completion rate of projects by showing ini tial contract time, time extensions, and number of days that project was com pleted early or late, all expressed in calendar days.

SIMILAR PROJECTS FOR LAST FIVE (5) YEARS

1. Project Name and Location

Owner Engineer

Address and telephone

Project Components

Contract Amounts ($) Date Completed

2. Project Name and Location

Owner Engineer

Address and telephone

Project Components

Contract Amounts ($) Date Completed

3. Project Name and Location

Owner Engineer

Address and telephone

Project Components

Contract Amounts ($) Date Completed

SECTION C C-9

CITY OF CULVER CITY PZ-428 May 2026

4. Project Name and Location

Owner Engineer

Address and telephone

Project Components

Contract Amounts ($) Date Completed

5. Project Name and Location

Owner Engineer

Address and telephone

Project Components

Contract Amounts ($) Date Completed
.

5.7 Staff Roster/Functions

List all members of your staff that will be assign ed to or responsible for work on this project (except clerical) and show their job titles/functions. Include Company Officers.

______________________ _______________________ __ __ _____ Name Function Years Years
w/Firm Total

______________________ _______________________ __ ___ _____ Name Function Years Years
w/Firm Total

______________________ _______________________ __ ____ _____ Name Function Years Years
w/Firm Total

______________________ _______________________ __ ____ _____ Name Function Years Years
w/Firm Total

______________________ _______________________ __ ____ _____ Name Function Years Years
SECTION C C-10

CITY OF CULVER CITY PZ-428 May 2026
w/Firm Total

5.8 Arbitration and Litigation History

Indicate below all arbitration and/or litigation against bidder in the last five (5) years, includin g all claims by owners. Indicate yes or no (Y/N) which c laims were resolved against bidder in litigation or arbitration or which resulted against in any pay ment by the Bidder or its insurers/sureties or reduction in compensation on any Bidder. Failure t o provide this information on any contract undertaken in the past five (5) years may result in disqualification. Indicate final status (Resolved or Unresolved) of each claim. Attach separate sheet if necessary.

Project Name Amount of Claim

Nature of Claim Resolution (Y/N) F inal Status Against Bidder

Project Name Amount of Claim

Nature of Claim Resolution (Y/N) F inal Status Against Bidder

Project Name Amount of Claim

Nature of Claim Resolution (Y/N) F inal Status Against Bidder

SECTION C C-11

CITY OF CULVER CITY PZ-428 May 2026

6 BID BOND

KNOW ALL MEN BY THESE PRESENTS:

That we, _________________________________________ ______________, as Principal, and ___________________________________________________ ____, as Surety (Local Agent Contact Telephone Number , ________________ ), are held and firmly bound unto the Owner in the sum of Dollars
($___________________) to be paid to said Owner its successors and assigns, for which payment well and truly will be made, we bind ourselves, our heirs, executors, administrators, successors and assigns, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH:

That if the certain Bid of the above-bounden Princ ipal submitted for the following improvement project:

Sidewalk, Curb Ramp, and Driveway Approach Improvem ent Project, PZ-428

is accepted by the Owner through action of its leg ally constituted contracting authorities and if the above-bounden Principal, its heirs, executors, admi nistrators, successors and assigns shall duly enter into and execute a contract for such construc tion in strict accordance with the specifications and drawings on file at the office of the City Engineer, in the City Hall, Culver City, and shall execute and deliver the required Faithful Performance Bond and Payment Bond, and Insurance Certificates within ten (10) days after the date of notification by and from said Owner that said contract is ready for execution, then this obligation shall become nu ll and void; otherwise, it shall be and remain in full force and virtue.

IN WITNESS WHEREOF, we hereunto set our hands and seals this _______________________ day of _________________, 20 .

Signature

Surety

Title

By:

Company

SECTION C C-12

CITY OF CULVER CITY PZ-428 May 2026
7 BID GUARANTY

BID GUARANTY

Note: The following statement shall be used if ot her than a bid surety bond accompanies bid.

"Accompanying this proposal is a money order*, cer tified check*, cashier's check*, cash*, payable to the order of the Owner in the amount of Dollars ($ ______________ ____________________) which is ten percent (10%) of the total amount of t his bid. The proceeds of this bid guaranty shall become the property of said Owner provided this bid is accepted by said Owner, through action of its legally constituted contracting authorities, an d the undersigned fails to execute a contract and furnish the required bonds within the stipulated time. Otherwise, the proceeds of this bid guaranty shall be returned to the undersigned."

Signature

Title

Company

(*Delete the inapplicable words)

SECTION C C-13

CITY OF CULVER CITY PZ-428 May 2026
8 NONCOLLUSION DECLARATION

NONCOLLUSION DECLARATION

(To Be Executed By Bidder and Submitted With Bid)

The undersigned declares:

I am the __________________ of _______________ _______, the party making the foregoing bid.

The bid is not made in the interest of, or on beha lf of, any undisclosed person, partnership, company, association, organization, or corporation. The bid is genuine and not collusive or sham. The bidder has not directly or indirectly induced or solicited any other bidder to put in a false or sham bid. The bidder has not directly or indirectly colluded, con spired, connived, or agreed with any bidder or anyo ne else to put in a sham bid, or to refrain from bidding. The bidder has not in any manner, directly or indirectly, sought by agreement, communication, or conference w ith anyone to fix the bid price of the bidder or an y other bidder, or to fix any overhead, profit, or co st element of the bid price, or of that of any othe r bidder.

All statements contained in the bid are true. The b idder has not, directly or indirectly, submitted hi s or her bid price or any breakdown thereof, or the contents thereof, or divulged information or data relative thereto, to any corporation, partnership, company, associati on, organization, bid depository, or to any member or agent thereof, to effectuate a collusive or sham bid, and has not paid, and will not pay, any person or entity for such purpose.

Any person executing this declaration on behalf of a bidder that is a corporation, partnership, joint venture, limited liability company, limited liabili ty partnership, or any other entity, hereby represe nts that he or she has full power to execute, and does execute, this declaration on behalf of the bidder.

I declare under penalty of perjury under the laws of the State of California that the foregoing is true and correct and that this declaration is execu ted on ____________ [date], at ______________________ [city], ____________________ ____ [state].

Name:

Title:

Signature of Bidder

SECTION C C-14

CITY OF CULVER CITY PZ-428 May 2026
9 SUPPLEMENTARY BID FORMS, NO. 1

SUPPLEMENTARY BID FORM NO. 1

LISTING OF PROPOSED SUBCONTRACTORS

Sidewalk, Curb Ramp, and Driveway Approach Improvement Project, PZ-428

For portions of the Work equaling or exceeding 1/2 of one percent (0.5%) of the Base Bid, the undersigned Bidder proposes to use the subcontractors listed be low. Except as otherwise approved by the Owner, th e undersigned Bidder shall perform all other portions of the Work with his own forces.

Portion of the Work Subcontractor Name, Address, & License No. & Bid Number & $ amount of subcontracting work California Public Works Contractor Registration No:

The signature must Bidder:
be identical to that
shown on the Bid. By:

If additional sheets Its:
are required, you must
copy this form.

SECTION C C-15

CITY OF CULVER CITY PZ-428 May 2026
SUPPLEMENTARY BID FORM NO. 2

LISTING OF PROPOSED SUPPLIERS

Pursuant to INSTRUCTIONS TO BIDDERS for the work titled:

Sidewalk, Curb Ramp, and Driveway Approach Improvem ent Project, PZ-428

Portion of the Work Supplier’s Name and Address

-- End of Section --

CITY OF CULVER CITY PZ-428 May 2026

SECTION D

AWARD AND EXECUTION OF CONTRACT

AGREEMENT, BONDS AND INSURANCES

SECTION D PAGE D-1

CITY OF CULVER CITY PZ-428 May 2026

SECTION D - AWARD AND EXECUTION OF CONTRACT

1 SAMPLE AGREEMENT

CITY OF CULVER CITY

AGREEMENT WITH

Contractor

This Agreement is made and entered into by and betw een the City of Culver City (City) and Name of Contractor (Contractor)

WHEREAS, Contractor submitted its total base bid th e total lump sum for: Amount of Bid Dollars ($00.00) for the completion of the Name of Project (Project. No. P-) as further described in the Scope of Services; and

WHEREAS, Contractor represents it has that degree o f specialized expertise and holds all licenses necessary to practice and perform the service contemplated; and

WHEREAS, after reviewing all bids submitted and dec laring that the Contractor submitted the lowest responsible and responsive bid, City’s City Council, at its meeting of meeting date, awarded th e contract for the work to Contractor.

NOW, THEREFORE, THE PARTIES HERETO AGREE as follows :

SCOPE OF SERVICES

Contractor shall provide all services described in accordance with the Contract Documents, as defined below, relating to the Name of Project (Project. No. P-) and follow the work schedules defined therein.

CONTRACT DOCUMENTS

The documents comprising the entire agreement betwe en City and Contractor shall be collectively referred to as the “CONTRACT DOCUMENTS,” and shall consist of and include the following:

This Agreement – including:
 Contract Documents and Specifications for Name of Project (P-), Bid # ___ ;  All addenda setting forth any modifications or int erpretations of those documents, (Addenda by number and date: Addendum No. x dated xxx);
 Bid Proposal submitted by Contractor to City on or before DATE;  All documents incorporated into the foregoing;
 Schedule of Values, if applicable;
 List of Subcontractors;
 Labor and Materials Payment Bond;
 Faithful Performance Bond (including agent’s Power of Attorney for each Bond);  Non-Collusion Declaration (General and Subcontract or) ;  Certificates of Insurance;
 Change Orders;
 Notice to Proceed; and
 Notice of Completion

All the Contract Documents are intended to compleme nt one another, so that any work called for in one and not mentioned in another is to be performed as if mentioned in all documents.

SECTION D PAGE D-2

CITY OF CULVER CITY PZ-428 May 2026
The terms of this Agreement shall prevail over any inconsistent provision of the other Contract Documents.

The Contract Documents constitute the entire agreem ent between the parties and supersede any and all other writings and oral negotiations.

NOTICE

All notices given or required to be given pursuant to this Agreement shall be in writing and may be given by personal delivery, facsimile, overnight de livery, or by U.S. Mail. All written notices or correspondence sent pursuant to this paragraph will be deemed given to a party on whichever date occurs first; the date of personal delivery; the date of transmission, if sent by facsimile (with proof of transmission); the next business day following deposit with an ove rnight mail carrier; the fifth day following deposi t in the U.S. Mail, when sent by “first class mail.”

Notices required to be given to City shall be addressed as follows :

Yanni Demitri, P.E., T.E.

Public Works Director/City Engineer
Public Works Department
City of Culver City
9770 Culver Blvd.

Culver City, CA 90232

Notices required to be given to the Contractor shall be addressed as follows:

Contractor
Address

It shall be the duty of Contractor to notify all subcontractors of the above Notice provisions.

CONTRACT PRICE

For Contractor’s satisfactory completion of the sco pe of services, City shall pay Contractor a total sum of ($00.00).

EFFECTIVE DATE

The effective date of this agreement is the date it is signed on behalf of City. This Agreement shall remain in full force and effect until amended or te rminated; provided, that the indemnification and ho ld harmless provisions shall survive the termination.

IN WITNESS WHEREOF , the parties hereto have caused their names to be hereunto subscribed.

CONTRACTOR

Dated: By:
________________________
Its_______________________

By:
________________________
Its_______________________

SECTION D PAGE D-3

CITY OF CULVER CITY PZ-428 May 2026

CITY OF CULVER CITY, CALIFORNIA

Dated: By:

Odis Jones
City Manager

APPROVED AS TO CONTENT: APPROVED AS TO FORM:

Yanni Demitri, P.E., T.E. Heather S. Baker
Public Works Director/City Engineer City Attorney

SECTION D PAGE D-4

CITY OF CULVER CITY PZ-428 May 2026

2 LABOR AND MATERIALS PAYMENT BOND

KNOW ALL MEN BY THESE PRESENTS: that

WHEREAS , THE City of Culver City, County of Los Angeles, S tate of California, has awarded to:

hereinafter designated as the Principal, a contract for:

Sidewalk, Curb Ramp, and Driveway Approach Improvem ent Project, PZ-428

in the City of Culver City, California, which contract is incorporated wherein by this reference; and

WHEREAS , said Principal is required to furnish a bond in c onnection with said contract, providing that if said Principal or any of his or its Subcont ractors shall fail to pay for any materials, provis ions, equipment or supplies used in, upon or about the pe rformance of the work contracted to be done, or for any work or labor done thereon of any kind, the Surety on this bond will pay the same to extent hereinafter set forth;

NOW, THEREFORE, WE,

as Principal and

as Surety, are held and firmly bound unto the City of Culver City, hereinafter called the Owner in the sum of: _______________________________________________ ________ Dollars ($ _________________) lawful money of the United States of America for th e payment of which sum well and truly to be made, w e bind ourselves, our heirs, executors, administrator s and successors, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION IS SUCH THAT if said Principal, his or its heirs, executors, administrators, successors or assigns sh all fail to pay for any materials, provisions or ot her supplies used in, upon, for or about the performanc e of the work contracted to be done, or for any wor k or labor thereon of any kind, as required by the provisions of an act of the Legislature of the State of California entitled, "An Act to secure the payment of claims o r persons employed by Contractors upon public works , and the claim of persons who furnish materials, sup plies, teams, implements or machinery used or consumed by such Contractors in the performance of such work, and prescribing the duties of certain public officers with respect thereto," approved May 10, 19 19, as amended, and provided that the persons, companies or corporations so furnishing said materi als, provisions or other supplies, appliances or po wer used in, upon, for or about the performance of the work contracted to be executed or performed, or any person, company or corporation renting or hiring implements, machinery or power for or contributing to said work to be done, or any person who performs work or labor upon the same, or any person who supplies both work or labor upon the same, or any person who supplies both work and material therefor, shall have complied with the provision of said Act, then said Surety will pay the same in or to an amount not exceeding the amount herein above set forth, and also will pay in case suit is brought upon this bond, such reasonable attorneys' fees, as shall be fixed by the court, aw arded and taxed as in aforementioned Statute provid ed.

This bond shall inure to the benefit of any and all persons, companies, and corporations entitled to f ile claims under said Act, so as to give a right of act ion to them or their assigns in any suit brought up on this bond.

FURTHER, the said Surety for value received hereby stipulates and agrees that no change, extension of time, alteration or modification of th e contract documents or of the work to be performed thereunder shall in any way affect its obligations on this bond and it does hereby waive notice of any such SECTION D PAGE D-5

CITY OF CULVER CITY PZ-428 May 2026
change, extension of time, alteration or modifications of the contract documents or of work to be performed thereunder.

IN WITNESS WHEREOF, three (3) identical counterpar ts of this instrument, each of which shall for all purposes be deemed an original thereof, have be en duly executed by the Principal and Surety herein named, on the day of , 200 . The name and corporate seal of each corporate party being hereto affixed and these presents duly signed by its undersigned representative pursuant to authority of its governing body.

Principal

By:

Surety

By:

SECTION D PAGE D-6

CITY OF CULVER CITY PZ-428 May 2026
3 FAITHFUL PERFORMANCE BOND

FAITHFUL PERFORMANCE BOND

KNOW ALL MEN BY THESE PRESENTS: that

WHEREAS , the City of Culver City, in the County of Los Angeles, State of California, has awarded to:

herein designated as the Principal, a contract for the construction of

Sidewalk, Curb Ramp, and Driveway Approach Improvem ent Project, PZ-428

in the City of Culver City, California, which contract is incorporated herein by this reference; and

WHEREAS , said Principal is required under the terms of sai d contract to furnish a bond for the faithful performance of said contract;

NOW, THEREFORE, WE

as Principal and
as Surety, are held and firmly bound unto the City of Culver City, hereinafter called the Owner in th e sum of:

___________________________________________________ ______Dollars ($ ) lawful money of the United States of America for payment of which sum well and truly to be made we bind ourselves, our heirs, executors, administrators and successors, jointly and severally, firmly by these presents.

THE CONDITION OF THIS OBLIGATION is such that, if the hereby bound Principal, his o r its heirs, executors, administrators, successors or ass igns shall in all things stand to and abide by and well and truly keep and perform all the undertakings, te rms, covenants, conditions and agreements in the sa id contract and any alteration thereof, made as therein provided, all within the time and in the manner therein designated and in all respects according to their true intent and meaning, then this obligation shall become null and void; otherwise, it shall be and remain in full force and effect.

FURTHER , the said surety, for value received, hereby stipu lates and agrees that no change, extension of time, alteration or modification of th e contract documents or of the work to be performed thereunder, shall in any way affect its obligations on this bond, and it does hereby waive notice of any such change, extension of time, alteration or modificati on of the contract documents or of work to be perfo rmed thereunder.

IN WITNESS WHEREOF , three (3) identical counterparts of this instrument, each of which shall for purposes be deemed an original thereof, have been d uly executed by the Principal and Surety herein named on the day of , 20_ . The name and corporate seal of each corporate party being hereto affixed, and these presents duly signed by i ts undersigned representative pursuant to authority of its governing body.

Principal

By:

Surety
By:

SECTION D PAGE D-7

CITY OF CULVER CITY PZ-428 May 2026
4 INSURANCE REQUIREMENTS

A. Policy Requirements.

Contractor shall submit duly executed certificates of insurance by companies licensed to do business in the State of California, with a current A.M. Best’s rating of no less than -A:VIII (unless otherwise acceptable to the City), for the followin g policies:

1. Commercial General Liability . An occurrence based Commercial General Liability ("CGL") policy, at least as broad as ISO Form CG 0001, in t he minimum amount of $3,000,000 each occurrence, with not less than $6,000,000 in annua l aggregate coverage..

The CGL Policy shall have the following requirement s:

a. General Requirements . The policy shall provide coverage for personal i njury, bodily injury, death, accident and property damage and advertising injury, as those terms are understood in the context of a CGL policy . The coverage shall be utilized to satisfy, to the extent of the coverage limits, t he City’s self-insured retention under any other policy of insurance. The coverage shall not be excess or contributing with respect to the City’s self-insurance, commerci al liability insurance, or any pooled risk arrangements;

b. Automobile Liability . The policy shall provide the following Automobil e Liability coverage:

i. ISO Form Number CA 0001 covering any auto (Code 1), or if Contractor has no owned autos, hired (Code 8) and non-owned au tos (Code 9), with limits of no less than $1,000,000 per accident for bodil y injury and property damage.

Automobile liability coverage may be satisfied with a stand- alone policy or as a component of the CGL policy;

ii. ISO Form Number CA 0001 covering any auto (Code 1), or if Contractor has no owned autos, hired (Code 8( and n on-owned autos (Code 9), with limits of no less than $1,000,000 per accident for bodily injury and property damage. Automobile liability coverage may be satisf ied with a stand-alone policy or as a component of the CGL policy. The Automobile Liability policy shall be endorsed to include Transportation Pollution Liabil ity insurance, covering materials to be transported by Contractor pursuant to the contract. This coverage may also be provided on the Contractor’s Pollution Liability policy.

iii. Business Automobile Liability Insurance covera ge in the amount of $3,000,000, providing coverage for use of mobile eq uipment (i.e., heavy mobile equipment or vehicles primarily for use in an off-r oad environment), to the extend that (1) such mobile equipment will be used within the City limits or on City business, and (2) coverage for mobile equipment is not otherwise covered by the CGL policy listed in this Agreement.

c. Contractual Liability . The policy shall include coverage for liability undertaken by contract covering, to the maximum extent permitt ed by law, Contractor's obligation to indemnify the Indemnitees as required under this Agreement. The policy shall not contain an “Independent Negligence ” provision that would void or otherwise nullify the insurer’s obligation to de fend and indemnify the City of Culver City in the event that its independent negli gence is alleged or proven;

d. Ongoing Operations. The Policy shall include coverage for Completed Operations Endorsement, ISO Form CG2037, and Ongoin g Operations Endorsement, ISO Form CG2010; and

SECTION D PAGE D-8

CITY OF CULVER CITY PZ-428 May 2026
e. Additional Insured. The City of Culver City, its officers, officials, e mployees, and volunteers are to be covered as additional insu reds on the CGL policy with respect to liability arising out of work or op erations performed by or on behalf of the Contractor including materials, pa rts, or equipment furnished in connection with such work or operation s. General liability coverage can be provided in the form of an endorsem ent to the Contractor’s insurance (at least as broad as ISO Fo rm CG20 10 11 85, or both CG 20 10, CG 20 26, CG 20 33, or CG 20 38 and CG 20 37 forms if later revisions used). Endorsement required.

f. Severability of Interests (Cross-Liability) . A severability of interest provision must apply for all the additional insureds, ensurin g that Contractor’s insurance shall apply separately to each insured against whom a claim is made or suit is brought, except with respect to the insurer’s limit s of liability.

g. Modification to Aggregate. City reserves the rig ht to review and waive or modify the CGL aggregate requirement in the event that an adequate project specific policy and limits are provided.

2. Builder’s Risk . Contractor shall maintain the following builder’ s risk insurance:

i. Special Perils . Contractor may submit evidence of Builder’s Risk insurance in the form of an “All Risk” (Special Perils) coverage form, with lim its equal to the completed value of the project and no coinsurance penalty provisions shall be required. C overage shall name the City as a loss payee as thei r interest may appear.

ii. Course of Construction . Contractor may submit evidence of Builder’s Risk insurance in the form of Course of Construction coverage. Such cover age shall name City as a loss payee as their interest may appear. If the project does not involv e new or major reconstruction, at the option of Cit y, an Installation Floater may be acceptable. For such projects, a Property Installation Floater shall be obtained that provides for the improvement, remodel , modification, alteration, conversion or adjustment to existing buildings, structures, proce sses, machinery and equipment. The Property Installation Floater shall provide property damage coverage for any building, structure, machinery, equipment damaged, impaired, broken, or destroyed d uring the performance of the Work, including transit, installation, and testing at City’s site.

3. Pollution Liability Including Non-Owned Disposal Si te (NODS) Coverage . During the duration of this Agreement, Contractor shall mainta in Pollution Liability insurance covering both first party clean-up costs and third- party bodily injury, property damage liability, waste materials and debris transportation, clean up expense, and co verage for Non-Owned Disposal Sites with a limit no less than $2,000,000 per incident. If Pol lution policies are claims-made policies, Contractor shall agree to maintain coverage for two (2) years following completion of contract.

4. Workers’ Compensation Insurance . If the Agreement will have Contractor employees working within the City limits, Contractor shall maintain W orkers’ Compensation Insurance (Statutory Limits) and Employer’s Liability Insurance (with limits of at least one million dollars [$1,000,000] per accident.) Contractor shall submit to City, along with the cer tificate of insurance, a Waiver of Subrogation endorsement in favor of City, its officers, agents, employees and volunteers.

B. Waiver by City.

City may waive one or more of the coverages listed in Section A, above. This waiver must be express and in writing, and will only be made upon a showing by the Contractor that its operations in and with respect to City are not such as to impose liability within the scope of that particular cover age.

SECTION D PAGE D-9

CITY OF CULVER CITY PZ-428 May 2026
C. Additional Insurance Requirements.

1. Certificates of Insurance . Evidence of insurance shall be supplied on a sta ndard ACORD Certificate of Insurance form. All insurance requir ements must be indicated on said form;

2. Umbrella or Excess Policy . Contractor may use Umbrella or Excess Policies to provide the liability limits as required in this Agreement. Thi s form of insurance will be acceptable provided tha t all of the Primary and Umbrella or Excess Policies shal l provide all of the insurance coverages herein required, including, but not limited to, primary an d non-contributory, additional insured, Self-Insure d Retentions (SIRs), indemnity, and defense requireme nts. The Umbrella or Excess policies shall be provided on a true “following form” or broader cove rage basis, with coverage at least as broad as provided on the underlying Commercial General Liabi lity insurance. No insurance policies maintained by the Additional Insureds, whether primary or exce ss, and which also apply to a loss covered hereunder, shall be called upon to contribute to a loss until the Contractor’s primary and excess liab ility policies are exhausted.

3. Verification of Coverage . Contractor shall furnish City with original cer tificates, and all required amendatory endorsements or copies of the applicable policy language effecting coverage required by this Agreement. A statement on an insurance certifi cate will not be accepted in lieu of the actual endorsements required herein. Each insurance certif icate shall specifically identify this Agreement.

All certificates and endorsements are to be receive d by City and approved by the Risk Manager and City Attorney before work commences. However, failu re to obtain the required documents prior to the work beginning shall not waive Contractor’s obligat ion to provide them. City reserves the right to require complete, certified copies of all required insurance policies, including endorsements required by this Agreement at any time.

4. Subcontractors. Contractor shall require and verify that all its su bcontractors maintain insurance meeting all the requirements stated herei n, and Contractor shall ensure that the City is an additional insured on insurance required from subco ntractors. For CGL coverage subcontractors shall provide coverage with a format at least as br oad as CG 20 38 04 13.

5. Primary Coverage and Non-Contributory. For any claims related to this Agreement, Contractor’s insurance coverage shall be primary an d non-contributory and at least as broad as ISO CG 20 01 04 13 as respects the City, its officers, officials, employees, and volunteers. Any insurance or self-insurance maintained by the City of Culver City, its officers, officials, employees, or volunt eers shall be excess of the Contractor’s insurance and s hall not contribute with it. This requirement shall also apply to any Excess or Umbrella liability poli cies.

6. Self-Insured Retentions. Self-insured retentions must be declared to and app roved by the City.

The City may require the Contractor to purchase cov erage with a lower retention or provide proof of ability to pay losses and related investigations, c laim administration, and defense expenses within the retention. The policy language shall provide, o r be endorsed to provide, that the self-insured retention may be satisfied by either the named insu red or the City.

7. Waiver of Subrogation. Contractor hereby grants to City a waiver of any r ight to subrogation which any insurer of Contractor may acquire against City by virtue of the payment of any loss under such insurance. Vendor agrees to obtain any endorse ment that may be necessary to affect this waiver of subrogation, but this provision applies r egardless of whether or not the City has received a waiver of subrogation endorsement from the insure r.

8. Claims Made Policies. If any of the required policies provide coverage on a claims-made basis:
a. The retroactive date must be shown and must be b efore the date of this Agreement or the beginning of the Scope of Work set forth in this Ag reement. b. Insurance must be maintained, and evidence of in surance must be provided for at least five (5) years after completion of the Scope of Work set forth in this Agreement. c. If coverage is canceled or non-renewed, and not replaced with another claims-made policy form with a retroactive date prior to the effective date of this Agreement, Contractor must SECTION D PAGE D-10

CITY OF CULVER CITY PZ-428 May 2026
purchase “extended reporting” coverage for a minimu m of five (5) years after completion of the Scope of Work set forth in this Agreement.

9. Timely Notice of Claims. Contractor shall give City prompt and timely notic e of claims made or suits instituted that arise out of or result from C ontractor’s performance under this Agreement, and that involve or may involve coverage under any of t he required liability policies.

10. Notice of Cancellation/Change in Coverage. Contractor shall provide City with at least thirty (30) days prior written notice of any modification, redu ction or cancellation of any of the Policies requir ed in this Agreement, or a minimum of ten (10) days’ n otice for cancellation due to non-payment.

11. City Remedies for Non Compliance . If Contractor or any of its subcontractors fails to provide and maintain insurance as required herein, then Cit y shall have the right but not the obligation, to purchase such insurance, to terminate this agreemen t, or to suspend Contractor’s right to proceed until proper evidence of insurance is provided. Any amounts paid by City shall, at City’s sole option, be deducted from amounts payable to Contractor or r eimbursed by Contractor upon demand.

12. Special Risks or Circumstances . City reserves the right to modify these requirem ents at any time, including limits, based on the nature of the risk, prior experience, insurer, coverage, or other special circumstances .

-- End of Section –

SECTION E

CITY OF CULVER CITY PZ-428 May 2026

SECTION E

SPECIAL PROVISIONS

SUPPLEMENTS AND MODIFICATIONS TO
PART 1 (GENERAL PROVISIONS),
PART 4 (EXISTING IMPROVEMENTS) AND
PART 6 (TEMPORARY TRAFFIC CONTROL)
OF THE

THE STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTR UCTION 2024 EDITION

SECTION E PAGE E-1

CITY OF CULVER CITY PZ-428 May 2026

PART 1

GENERAL PROVISIONS

SECTION 1 – TERMS, DEFINITIONS, ABBREVIATIONS & SYM BOLS

Except as modified by the Special Provisions, Techn ical Provisions, Standard Drawings and the Project Plans, all work shall be in accordance with the Pro visions of the latest edition of the STANDARD SPECIFICATION FOR PUBLIC WORKS CONSTRUCTION (SSPWC) , including all Supplemental Amendments, as published by Building News, Inc., Lo s Angeles, California, which Specifications are hereinafter referred to as the Standard Specifications.

The herein stated Special Provisions supplement and revise the aforementioned standard Specifications.

Any reference to “Section” or “Subsection” in these Special Provisions shall refer to the aforemention ed Standard Specifications unless noted otherwise.

1-2 TERMS AND DEFINITIONS

In this subsection, substitute where applicable, or add the following:

Agency The City of Culver City, for which the work is being performed.

Board The City Council of the City of Culver City.

City The City of Culver City.

Engineer (or)
City Engineer The City Engineer of the City of Culver City or other person designated by the City Engineer acting either directly or through authorized agents.

Calendar Day All days beginning with the date speci fied in the Notice to Proceed, and ending with the date the City issues the Statement of Comp letion.

SECTION 2 – SCOPE OF THE WORK

2-1 WORK TO BE DONE Add the following:

The Bidder is required to examine carefully the sit e of work, Bid Proposal forms and all other Contract documents for the work contemplated. The Submission of a Bidder’s Proposal shall be considered conclusive evidence that the Bidder has investigated and is satisfied as to the conditions to be encountered, as to the character, quality and quantities of work to be performed and materials to be furnished, and as to the requirements of all the above documents.

2-2 PERMITS Add the following:

The Contractor shall secure all necessary permits f rom all governing agencies having authority over any portion of the work. The Contractor shall obtain and pay for all other permits.

The Contractor shall obtain, pay, and comply with all permits, including but not limited to the permits requirements as shown in the ”Instruction to Bidder s” part of this contract document, and give all notices necessary and incident to the due and lawful prosecution of the work and to the preservation of the public health and safety.

SECTION E PAGE E-2

CITY OF CULVER CITY PZ-428 May 2026
2-5 CONTRACTOR’S EQUIPMENT AND FACILITIES Add the following:

The routing of trucks with gross vehicle weight exc eeding 6,000 pounds through Culver City shall be subject to the provision of City Code Section 7.02.210 and the Contract Documents. Contractor shall submit a proposed haul route plan to the Engineer for approval. Said plan shall be approved prior to mobilization. The Contractor is advised that any violation of the California Vehicle Code and Culver City Code (such as truck routing, overweight, improper licensing, etc.) will result in citation and fines by the Police Departme nt. Contractor shall be responsible for the immediate cleanup of all spills of any nature resulting from his operation.

Parking of Contractor’s employee’s vehicles or any other vehicles not utilized in the construction activity will be restricted during construction and shall not take place in public parking areas outside of the construction zone, unless shown otherwise on the plan or unless by arrangement with the Engineer.

Any commercial vehicle, the laden or unladen weight of which exceeds six thousand (6,000) pounds, shall use the following streets designated as truck routes:

A. Adams Boulevard.

B. Centinela Avenue.

C. Culver Boulevard, between west City boundary and Sepulveda Boulevard.

D. Fairfax Avenue.

E. Higuera Street, between Hayden Avenue/Place and Jefferson Boulevard.

F. Jefferson Boulevard.

G. La Cienega Boulevard.

H. National Boulevard.

I. Sawtelle Boulevard, between Culver/ Washington o ff-ramp of the San Diego Freeway and Braddock Drive.

J. Sawtelle Boulevard, between Matteson Avenue and Venice Boulevard.

K. Sepulveda Boulevard.

L. Slauson Avenue, east of Jefferson Boulevard.

M. Venice Boulevard.

N. Washington Boulevard, east of La Cienega Bouleva rd.

Most direct route shall be used to and from the restricted street from the truck route. 2-5.2 Temporary Utility Services Add the following:

Contractor is responsible to obtain and pay for con struction water. Any water drawn from fire hydrant shall be coordinated through Golden State W ater Company (Contact telephone No. 310.838.1324) located at 10785 Washington Blvd in C ulver City.

2-8 EXTRA WORK Add the following:

Changes Authorized in Writing
All authorized alterations affecting the requiremen ts and information given on the approved plans shall be in writing. No changes shall be made on a ny original plan or drawing after the same has been approved by the Engineer. Deviations from the approved plans, as may be required by the exigencies of construction, will be determined in all cases by the Engineer and authorized in writing.

Protests
If the Contractor considers any work demanded of Contractor to be outside the requirements of the Contract, or if Contractor considers any instructio n, ruling or decision of the Inspector or Engineer to be unfair, Contractor shall within three (3) cal endar days after any such demand is made, or instruction, ruling or decision is given, state cle arly and in detail the Contractor’s objections and reasons therefore. Except for such protest and obj ections as are made of record, in the manner and within the time above stated, the Contractor shall be deemed to have waived and does thereby SECTION E PAGE E-3

CITY OF CULVER CITY PZ-428 May 2026
waive all claims for extra work, damages and extens ions of time on account of demands, instructions, rulings and decisions of the Public Works Director/City Engineer.

Upon receipt of any such protest from the Contracto r, the Engineer shall review the demand, instruction, ruling or decision objected to and sha ll promptly advise the Contractor, in writing, of Public Works Director/City Engineer’s final decisio n, which shall be binding on all parties, unless within the ten (10) calendar days thereafter the Contractor shall file with the Owner, a formal protest against said decision of the Public Works Director/ City Engineer. The Owner shall consider and render a final decision on any such protest within thirty (30) calendar days of receipt of same.

2-10 DISPUTED WORK Add the following:

All claims which do not exceed the sum of three hundred seventy-five thousand dollars ($375,000) shall be resolved pursuant to the provisions of Pub lic Contract Code Section 20104 through 20104.6, “Resolution of Construction Claims”.

Notice – The Contractor shall notify the Public Wor ks Director/City Engineer, in writing, of its intention to make claim. Claims pertaining to deci sions provided above for such other determinations by the Construction Manager shall be filed in writing to the Public Works Director/City Engineer prior to the commencement of such work. Written notice shall use the words “Notice of Potential Claim”. Such Notice of Potent ial Claim shall state the circumstances and the reasons for the claim, but need not state the amount.

Additionally, no claim for additional compensation or extension of time for a delay will be considered unless the above provisions are complied with. No claim filed after the date of final payment will be considered.

It is agreed that unless notice is properly given, the Contractor shall not recover costs incurred by it as a result of the alleged extra work, changed w ork or other situation which had proper notice been given would have given rise to right for addit ional compensation. The Contractor should understand that timely notice of potential claim is of great importance to the Public Works Director/City Engineer and Owner, and is not merely a formality. Such notice allows the Owner to consider preventative action, to monitor the Contra ctor’s increases costs resulting from the situation, to marshall facts, and to plan its affai rs. Such notice by the Contractor, and the fact th at the Public Works Director/City Engineer has kept account of the cost as aforesaid, shall not in any way be construed as proving the validity of the claim.

Records of Disputed Work – In proceeding with a disputed portion of the Work, the Contractor shall keep accurate records of its costs and shall make a vailable, to the Public Works Director/City Engineer, a daily summary of the hours and classifi cation of equipment and labor utilized on the disputed work, as well as a summary of any material s or any specialized services which are used.

Such information shall be submitted to the Public Works Director/City Engineer on a monthly basis, receipt of which shall not be construed as an authorization for or acceptance of the disputed work.

Submission of Claim Costs – Within 30 days after th e last cost of work for which the Contractor contends it is due additional compensation is incurred, but if costs are incurred over a span of more than 30 days, then within 15 days after the thirtieth day and every month thereafter, the Contractor shall submit to the Public Works Director/City Engi neer as best the Contractor is able its costs incurred for the claimed matter. Claims shall be m ade in itemized detail and should the Public Works Director/City Engineer be dissatisfied with format or detail of presentation, upon request for more or different information, the Contractor will promptly comply, to the satisfaction of the Public Works Director/City Engineer. If the additional co sts are in any respect not quantifiable with certainty, they shall be estimated as best can be done. In case the claim is found to be just, it shall be allowed and paid for as provided in the Standard Specification.

SECTION E PAGE E-4

CITY OF CULVER CITY PZ-428 May 2026
SECTION 3 – CONTROL OF THE WORK

3-5 INSPECTION Add the following:

The City Engineer, or his authorized agent, shall a t all times have access to work during construction, and shall be furnished with every rea sonable facility for ascertaining full knowledge regarding the process, workmanship, and character o r materials used and employed in the work.

Whenever required, the Contractor shall furnish to the City for test, and free of charge, samples of any one of the materials proposed to be used in the work. Said samples shall be delivered by the Contractor at the place within the City of Culver C ity designated by the City Engineer. Rejected material must be immediately removed from the work by the Contractor and shall not again be brought back to the site of the improvement.

The Contractor shall be responsible to reimburse the City for its actual inspection services cost for any work that is outside the normal working days or working hours (as defined by Section 6-3 of this Special Provisions) , if approved the by Engineer.

Twenty-Four Hour Notice
The Contractor shall give at least twenty-four (24) hours advance notice of the time when Contractor or Contractor’s subcontractor will start or resume the various units of operations of the work as per the contract, or resume said units of o perations when they have been suspended per the contract.

The above notice is to be directed to the City Engi neer through the Construction Manager, and is to be given during working hours (8 a.m. to 5 p.m.; closed alternate Fridays), exclusive of Saturday, Sunday or holidays for the purpose of permitting th e Engineer to make necessary assignments of the Engineer’s representative or inspector on the work.

Uncovering of Uninspected Work
Any work performed in conflict with said notice, wi thout the presence or approval of the inspector, or work covered up without notice, approval or consent may be rejected or ordered to be uncovered for examination at Contractor’s expense and shall b e removed at Contractor’s expense, if so ordered by the City Engineer or his/her representative or inspector on the work. Any unauthorized or defective work, defective material or workmanship or any deficient work that may be discovered shall be corrected immediately without extra charge even though it may have been overlooked in previous inspections and estimates.

3-6 THE CONTRACTOR’S REPRESENTATIVE Add the following:

When and as directed by the City Engineer, the Cont ractor shall attend all conferences and meetings which the City Engineer deems necessary fo r the proper progress of work under this contract.

3-7 CONTRACT DOCUMENTS

3-7.1. General Add the following:

Except as modified by the Special Provisions, Techn ical Provisions, Standard Drawings and the Project Plans, all work shall be in accordance with the Provisions of the latest edition of the STANDARD SPECIFICATION FOR PUBLIC WORKS CONSTRUCTIO N (SSPWC), including all Supplemental Amendments, as published by Building N ews, Inc., Los Angeles, California, which Specifications are hereinafter referred to as the Standard Specifications, and when applicable, the California Department of Transportation (Caltrans) Standard Specifications, latest edition, except the following:

SECTION E PAGE E-5

CITY OF CULVER CITY PZ-428 May 2026
Traffic Signal, Lighting, Pavement Striping and Markers, Roadside Sign Work

For roadside sign, traffic striping and pavement ma rking, pavement markers, and traffic signal and lighting work, the technical provisions provided within Section 56-2, “Roadside Signs,”, Section 84,” Traffic Stripes and Pavement Markings”, Section 85, “Pavement Markers”, and Section 86, “Signals, Lighting and E lectrical Systems,” of the State of California Department of Transportation (Caltrans) Standard Specifications, latest edition, hereafter “State Specification” or “State Standard Specification,” shall supersede related provisions of the SSPWC. Except as otherwise specified on the Plans or in these General or Technical Provisions, all work relating to traff ic signals and street lighting, including all equipment, materials, components, and the installation thereof, shall be in accordance with the latest edition of the State Standard Plans and Section 86, of the latest edition of the State Standard Specifications. The order of preced ence for said State Standard Plans shall be lower than that of the Special Provisions and Plans but higher than that of the Standard Plans and Specifications.

Work within Caltrans Right of Way

Shall conform to the approved plans and permit requirements.

Work within City of Los Angeles Right of Way

Shall conform to the approved plans and permit requirements.

If the contractor, in the course of the work, becom es aware of any claimed errors or omissions in the contract documents or in the City’s field work, it shall immediately inform the City Engineer.

The City Engineer shall promptly review the matter, and if he/she finds an error or omission has been made, he/she shall determine the corrective ac tions and advise the Contractor accordingly.

If the corrective work associated with an error or omission increase or decrease the amount of work called for in the Contract, the City shall issue an appropriate Change Order. After discovery of an error or omission by the Contractor, any related work performed by the Contractor shall be done at its risk unless authorized by the City Engineer.

Where applicable, the latest edition of the Uniform Building Code (UBC), and Amendments and the Culver City Municipal Code shall be adhered to.

Comply with the provisions for safety practices set forth in the “Manual of Accident Prevention on Construction”, published by the Associated General Contractors of America (AGC) 213/263-1500, and to comply with the State of California Occupational Safety and Health Act (Cal-OSHA).

3-8 SUBMITTALS Add the following:

Within fourteen (14) calendar days after the Award of Contract, the Contractor shall, at his or her expense, transmit by letter to the Engineer for review and acceptance, shop drawings and/or other available instructive and descriptive information f rom the manufacturer, when and as required by the Plans or Special Provisions, or requested by the Engineer. Shop drawings will normally not be required for standard items in common use for which adequate manufacturers’ literature is available.

The Contractor shall consecutively number, thorough ly check, approve and sign each Shop Drawing and transmit the Shop Drawings by letter to the Engineer for review. In the event that certain Shop Drawings are unacceptable to the City, they will be rejected by the Engineer. The Contractor shall thereafter, correct said drawings and resubmit same in quadruplicate within seven (7) calendar days.

In the event that in the process of development of the Shop Drawings, it is discovered that there are defects and/or errors on the Plans, resulting i n conflict between said Plans and the Shop SECTION E PAGE E-6

CITY OF CULVER CITY PZ-428 May 2026
Drawings, or if the Shop Drawings show variation fr om the Plans and/or Contract requirements because of standard shop practice or other reasons, the Contractor shall thoroughly describe and explain said defects and/or conflicts in his transmittal letter to the Engineer.

The Engineer's review of the Shop Drawings will be for general design and arrangement only, and shall not relieve the Contractor from responsibility for errors of any sort in the Shop Drawings or of the responsibility for executing the work in accord ance with the Contract. The Contractor shall be solely responsible for the correctness of the drawi ngs, for shop fits and field connections, and for the results obtained by use of such drawings. The Contractor shall verify and be fully responsible for all dimensions and job-site conditions affecting the work and shall be responsible for furnishing and installing the proper materials required by the Contract, whether or not indicated on the Shop Drawings when reviewed.

3-10 SURVEYING

3-10.1 General Revise the subsection and apply the following:

Unless specified otherwise in the Technical Provisions, the Contractor shall pay and provide usual and customary construction staking. The Contractor shall submit to the City for approval, the qualifications of the Licensed Land Surveyor prior to commencing the construction staking.

3-12 WORK SITE MAINTENANCE

3-12.1 General Add the following:

When and as often as required by the Engineer, the Contractor shall furnish and operate self- loading motor sweepers with spray nozzles, to keep paved areas affected by the work acceptably clean and dust free.

The Contractor shall remove graffiti from all work, materials, equipment, and signs within the project. Equipment, materials, or signs containing graffiti shall not be brought to the project. Any graffiti found on work, materials, equipment, or signs shall be cleaned or removed from the project within 24 hours from its discovery. The cost of gr affiti removal shall be borne by the Contractor, and shall be considered as being included in the various Contract items.

Upon project completion, the contractor shall remov e all dig-alert utility markings.

The Contractor shall have sole responsibility for providing security for his materials and equipment on and about the work site against theft and vandal ism at all times for the duration of the contract.

Contractor shall immediately replace all furniture, equipment, supplies, etc., which is being used or owned by the Owner or his/her designee at or on the project site or other areas under the security of the Contractor that is stolen, lost or damaged t hrough theft, vandalism, graffiti, Contractor’s negligence or any similar activity.

3-12.2 Air Pollution Control Add the following:

The Contractor shall comply with all air pollution control rules, regulations, ordinances and statutes which apply to any work performed pursuant to the C ontract, including any air pollution control rules, regulations, ordinances and statutes, specified in Section 11017 of the Government Code.

In the absence of any applicable air pollution cont rol rules, regulations, ordinances or statues governing solvents, all solvents, including but not limited to the solvent portions of paints, thinners, curing compounds, and liquid asphalt used on the Project shall comply with the applicable material requirements of the South Coast Air Quality Managem ent District (SCAQMD). All containers of paint, thinner, curing compound or liquid asphalt s hall be labeled to indicate that the contents fully comply with said requirements.

SECTION E PAGE E-7

CITY OF CULVER CITY PZ-428 May 2026

3-12.3 Noise Control Add the following:

The Contractor shall comply with all local sound co ntrol and noise level rules, regulations and ordinances which apply to any work performed pursua nt to the contract.

The noise level requirements shall apply to all equipment on the job or related to the job, including, but not limited to, trucks, transit mixers or trans ient equipment that may or may not be owned by the Contractor. Each internal combustion engine used for any purpose on the job shall be equipped with a muffler of a type recommended by the manufacturer. The noise level shall be in compliance with Chapter 9, Section 9.07 of the Culver City Municipal Code.

Residential Restrictions—

For residential zones, hours of work shall be limit ed, in accordance with the Culver City Municipal Code pertaining to Mechanical Noise or Construction Noise near Residential Zones, which prohibits:

(a) The use or operation of any automobile, motorcy cle, engine, machine or mechanical device, or other contrivance or facility, or the carrying o n of any trade or business, causing between the hours of 8:00 p.m. and 6:00 a.m., any loud or u nusual noise or sound, disturbing the peace of residents of a residentially zoned neighborhood.

(b) The use of any of the foregoing in constru ction or excavation work between the hours of 8:00 p.m. and 8:00 a.m., on weekday, or between the hour s of 7:00 p.m. and 9:00 a.m. on a Saturday, or between the hours of 7:00 p.m. and 10: 00 a.m. on a Sunday, which cause any loud or unusual noise or sound disturbing the peace of residents of a residentially zoned neighborhood.

Interference with Business Prohibited

Contractor must comply with Section 9.04.020(D) of the Culver City Municipal Code pertaining to Mechanical Devices, etc., Interfering with Business or Industrial Operations, which prohibits: The operation of any automobile, motorcycle, engine, ma chine or mechanical device or other contrivance or facility, or the carrying on of any trade or business, any loud or unusual noise or sound from which interferes with the transaction or conduct of any business or industrial operation in the surrounding area, unless the making of such noise is incident to the construction or repair of buildings or equipment or is otherwise necessary to the protection or preservation of the property from which such noise or sound emanates.

3-12.4.1 Storage of Equipment and Materials Add the following:

It shall be the Contractor’s responsibility to loca te any storage sites for materials and equipment needed and such sites must be approved in advance b y the City Engineer, and must be free of objectionable material. The Contractor must submit to the City Engineer for approval any and all agreement(s) between the Contractor and the propert y owner(s) of said storage site(s) and/or construction site(s) for approval prior to the star t of construction. Said agreement(s) must provide for the restoration of the site(s) by the Contractor prior to the filing of “Notice of Completion” by the City Engineer.

Stockpiling or storage of materials on any public right-of-way or parking areas will not be permitted without the approval of the Engineer. Materials spilled along or on said right-of-way or parking areas shall be removed completely and promptly. All stock pile and storage areas shall be kept in a safe, neat, clean, and orderly fashion, and shall be rest ored to equal or better than original condition upon completion of the work

SECTION E PAGE E-8

CITY OF CULVER CITY PZ-428 May 2026

3-12.6 Water Pollution Control Add the following:

The Contractor shall comply with the requirements o f Subsection 3-12.6 of the Standard Specifications and shall conduct his operations so as to prevent Portland cement, mud, silt or other materials from entering the surface drainage structures of the adjoining street and any underground storm drainage system. Contractor shall prepare and submit Storm Water Pollution Prevention Plan (SWPPP) prepared by qualified SWPPP developer for C ity’s approval. Once approved, the Contractor shall comply with the requirements of project specific Storm Water Pollution Prevention Plan (SWPPP).

In addition to complying with all applicable federa l, state and local laws and regulations, the Contractor shall take note of the NPDES (National P ollution Discharge Elimination System) Requirements. The Contractor shall take all precau tionary actions and implement all necessary BMPs to prevent sewer discharges to any portion of the storm drain conveyance system including discharge of pollutants from activities such as pav ing operations, concrete waste washouts, cold- milling, vehicle and equipment fueling from enterin g storm drain systems. At the minimum, the following shall be implemented:

1. Handle, store, and dispose of materials properly.

2. Avoid excavation and grading activities during wet weather.

3. Construct diversion dikes and drainage swales around working sites.

4. Cover stockpiles and excavated soil with secured tarps or plastic sheeting.

5. Develop and implement erosion control plans (if applicable).

6. Check and repair leaking equipment away from construction sites.

7. Designate a location away from storm drains for refueling.

8. Cover and seal catch basins if work in their vicinity may allow debris or deleterious liquids to enter.

9. Use vacuum with all concrete sawing operations.

10. Never wash excess material from aggregate, concrete, or equipment onto a street.

11. Catch drips from paving equipment with drip pans or absorbent material.

12. Clean up all spills using dry methods.

3-13 COMPLETION, ACCEPTANCE, AND WARRANTY

3-13.1 Completion Add the following:

Record drawings

At the beginning of the project, one print of each applicable drawing will be issued by the City for use in preparing record drawings.

Actual construction conditions shall be accurately and completely recorded on the prints as the project progresses. Contractor shall make complete, current, Record Drawings available for review by the City during the time the Contractor’s Application for Payment is being reviewed. Incomplete Record Drawings may delay approval of said Applicat ion. Upon completion of the work, the Contractor shall sign the record drawings and shall submit same to the City’s Inspector for checking and approval prior to the Notice of Completion is filed.

SECTION E PAGE E-9

CITY OF CULVER CITY PZ-428 May 2026

Completion Date: The project is considered complete and the counting of days for time of completion ends when the City’s Project Manager con firms in writing that the Contractor has completed the Work in accordance with the Contract, including completion of all physical work and punch list items, and cleanup work including removal of construction materials/equipment/signage, and does not including warranties or maintenance. Any documentation required in the Contract and by Law does not necessarily need to be furnished by the Contractor by completion date but must be received prior to final payment.

Final Acceptance Date: The date on which the City Council accepts the Work as complete.

The guarantees and agreements set forth hereof shall be secured by a surety bond. Said bond the Contractor may, at his option, provide for the faithful performance bond furnished under the contract to remain in force and effect for said amount until the expiration of said one year period.

Such repair and replacement shall be made promptly upon receipt of written notice from the Engineer. If the Contractor fails to make such repair and replacement promptly, the Engineer may cause the work to be done and the costs incurred thereby shall become the liability of the Contractor and his or her Surety.

If in the opinion of the Engineer, defective work c reates a dangerous condition or requires immediate correction or attention to prevent furthe r loss to the City or to prevent interruption of operations of the City, the City will attempt to gi ve the notice required by this article. If the Contractor cannot be contacted or does not comply with the Engineer’s request for correction within a reasonable time as determined by the Engineer, th e City may, notwithstanding the Provisions of this article, proceed to make such correction or pr ovide such attention, and the costs of such correction or attention shall be charged against the Contractor.

This article does not in any way limit the warranty on any items for which a longer warranty is specified or on any items for which a manufacturer gives a guarantee for a longer period, nor does it limit other remedies of the City in respect to l atent defect, fraud implied warranties, or assigned claims.

SECTION 4 – CONTROL OF MATERIALS

4-1 GENERAL Add the following:

No materials, supplies or equipment for the work u nder this Contract shall be purchased subject to any security agreement or other agreement by which an interest therein or any part thereof is retained by the seller or supplier. The Contractor warrants clear and good title to all materials, supplies and equipment installed and incorporated i n the work, and agrees upon completion of all work to deliver the premises, together with all imp rovements and appurtenances constructed or placed thereon by Contractor, to the Owner free from any claims, liens, encumbrances or charges, and further agrees that neither Contractor nor any person, firm or corporation furnishing any material or labor for any work covered by the Contr act shall have any right to a lien upon the premises or any improvement or appurtenance thereon , provided that this shall not preclude the Contractor from installing metering devices or other equipment of utility companies the title of which is commonly retained by the utility company. Nothing contained in this article, however, shall defeat or impair the right of such persons furnishing mate rials or labor under any bond given by the Contractor for their protection of any right under any law permitting such persons to look to funds due the Contractor in the hands of the Owner.

The provisions of this Section shall be inserted i n all subcontracts and material contracts, and notices of its provisions shall be given to all per sons furnishing materials for the work when no formal contracts are entered into for such materials.

SECTION E PAGE E-10

CITY OF CULVER CITY PZ-428 May 2026
4-2 PROTECTION Add the following:

Until acceptance of the Work, the Contractor shall have the charge and care of the Work and Materials to be used therein and shall bear the ris k of injury, loss, or damage, to any part thereof (regardless of whether partial payments have been m ade on such damaged portions of the Work) by the action of the elements or from any other cause, whether or not arising from the non-execution of the Work. The Contractor shall rebuild, repair and restore and make good all injuries, losses, or damages to any portions of the Work or materials oc casioned by any cause before its completion and acceptance and shall bear the expense thereof, except for such injuries, losses or damages as are directly and proximately caused by the acts of the Owner.

4-4 TESTING Add the following:

Unless otherwise called for hereinafter in these Sp ecial Provisions, all testing during construction will be performed by the City in such number and at such locations as deemed necessary by the Engineer to insure compliance with the Plans and Specifications; the cost of all initial testing will be borne by the City; the cost of all retesting will b e borne by the Contractor, and the amount due the City for said retesting will be deducted from the Contractor’s progress payments.

4-6 TRADE NAMES Add the following:

Wherever catalog numbers and specific brands or tra de names not preceded by designation “similar and equal” nor followed by the designation “or equal” are used in conjunction with a designated material, product thing, installation, o r service mentioned in these Specifications, to ensure compatibility with existing facilities, no substitutions will be favorably reviewed.

Within ten (10) working days from the date of bid o pening, the Contractor shall, at his expense, submit a written request to the Engineer for each d esired substitution, accompanied by complete descriptive information from the manufacturer, samp les as requested by the Engineer, complete detailed test results from a licensed independent testing laboratory of the City’s choice if requested by the Engineer, and if requested by the Engineer, an evaluation report from a qualified licensed professional engineer, all for final evaluation by the Engineer. If in the Engineer’s opinion, the requested substitution is of lesser quality or in v ariance with that specified, or if the information submitted is insufficient or incomplete, the reques ted substitution will be disallowed and the specified materials or equipment shall be furnished . Except as hereafter provided, no request for substitutions submitted, after the 10-working -day deadline specified will be considered.

If alternative named or substitutions are proposed by the Contractor and favorably reviewed by the City, the Contractor is responsible for providing at no additional cost to the Owner, any engineering designs, any electrical, mechanical, structural, or other related changes or testing that may be required to accommodate or provide the particular material or equipment the Contractor desires to use. Any deviation from the Specifications or the Drawings resulting from the type of material or equipment to be used shall not be the basis for any “extra charges” above and in excess of the original bid price of the work.

In addition the Contractor is responsible for all a dditional costs to the Owner, and its agents and representatives, for evaluation of data submitted b y the Contractor for alternative named or substitutions and any redesign necessary. The Owne r shall deduct said costs from the Contract monies due the Contractor.

In the event that a substitute is favorably reviewe d, fifty percent (50%) of all savings shall be credited to the Owner.

SECTION E PAGE E-11

CITY OF CULVER CITY PZ-428 May 2026
SECTION 5 – LEGAL RELATIONS AND RESPONSIBILITIES

5-1 LAWS AND REGULATIONS

The Contractor shall keep fully informed of all existing and future State and Federal laws and county and municipal ordinances and regulations which in any manner affect those engaged or employed in the work, or the materials used in the work, or which in any way affect the conduct of the work, and of all such orders and decrees of bodies or tri bunals having any jurisdiction or authority over the same. Contractor shall at all times observe an d comply with, and shall cause all his or her agents and employees to observe and comply with, al l such existing and future laws, ordinances, regulations, orders, and decrees of bodies or tribunals having any jurisdiction or authority over the work; and shall protect and indemnify the Owner, and all its officers and employees connected with the work, and including but not limited to the Public Works Director/City Engineer, against any claim or liability arising from or based on the violation of any such law, ordinance, regulation, order, or decree, whether by Contractor or Contractor’s employees.

If any discrepancy or inconsistency is discovered in the Plans, Drawings, Specifications, or Contract for the work in relation to any such law, ordinance, regulation, order or decree the Contractor shall forthwith report the same to the Engineer in writing.

5-7 SAFETY

5-7.2 Safety Orders, Add the following:

Safety Orders and Safety Control

The Contractor shall be solely and completely respo nsible for conditions of the job site, including safety of all persons and property during performan ce of the work. This requirement shall apply continuously and not be limited to normal working h ours. Safety provisions shall conform to U.S.

Department of Labor (OSHA), the California Occupati onal Safety and Health Act, and all other applicable Federal, State, County, and local laws, ordinances, codes, the requirements set forth below, and any regulations that may be detailed in other parts of these Contract Documents. Where any of these are in conflict, the more stringent requirements shall be followed.

No provision of the Contract Documents shall act to make the Owner, the Engineer or any other party than the Contractor responsible for safety. The Engineer shall not have authority for safety on the project. The Contractor shall indemnify, defend and hold harmless the Owner, Engineer, or other authorized representatives of the Owner, from and against any and all actions, damages, fines, suits and losses arising from the Contractor ’s failure to meet all safety requirements and/or provide a safe work site.

If death or serious injuries or serious damages are caused, the accident shall be reported immediately by telephone or messenger to both the E ngineer and the Owner. In addition, the Contractor must promptly report in writing to the E ngineer all accidents whatsoever arising out of, or in connection with, the performance of the Work whether on, or adjacent to, the Site, giving full details and statements of witnesses. The Contracto r shall make all reports as are, or may be, required by authority having jurisdiction, and perm it all safety inspections of the work being performed under this Contract.

If a claim is made by anyone against the Contractor or any subcontractor on account of any accident, the Contractor shall promptly report the facts in writing to the Engineer, giving full details of the claim.

Safety Program
The Contractor shall establish, implement, and main tain a written injury prevention program as required by Labor Code Section 6401.7. Before begi nning the Work the Contractor shall prepare and submit to the Engineer a Contractor Safety Program that provides for the implementation of all SECTION E PAGE E-12

CITY OF CULVER CITY PZ-428 May 2026
the Contractor’s safety responsibilities in connection with the Work at the site and the coordination of that program and its associated procedures and p recautions with the safety programs, precautions and procedures of each of its subcontra ctors and other prime Contractors performing work at the site. The Contractor shall be solely r esponsible for initiating, maintaining, monitoring, coordinating, and supervising all safety programs, precautions and procedures in connection with the Work and for coordinating its programs, precautions and procedures of the subcontractors and other prime contractors performing Work at the site . The Safety Program should contain all the necessary elements for the Contractor to administer its program on site.

The Contractor's compliance with requirements for s afety and/or the Engineer's review of the Contractor’s Safety Program shall not relieve or de crease the liability of the Contractor for safety.

The Engineer’s review of the Contractor’s Safety Pr ogram is only to determine if the above listed elements are included in the program.

Safety Supervisor
The Contractor shall appoint an employee as safety supervisor who is qualified and authorized to supervise and enforce compliance with the Safety Pr ogram. The Contractor shall notify the Engineer in writing prior to the commencement of wo rk of the name of the person who will act as the Contractor’s safety supervisor and furnish the safety supervisor’s resume to the Engineer.

The Contractor, will, through and with his Safety S upervisor, ensure that all of its employees and its subcontractors of any tier, fully comply with t he Project Safety Policies. The Safety Supervisor shall be a full time employee of the Contractor who se responsibility shall be for supervising compliance with applicable safety requirements on t he work site and for developing and implementing safety training classes for all job pe rsonnel. The Owner shall have the authority to request removal of the Contractor’s Safety Supervis or if that representative is judged to be improperly or inadequately performing the duties; however, this authority shall not in any way affect the Contractor's sole responsibility for performing this work safely, nor shall it impose any obligation upon the Owner to ensure the Contractor perform its work safely.

Safety and Protection
The Contractor shall take all necessary protection to prevent damage, injury and loss to:

All employees on the Project, employees of all sub contractors, and other persons and organizations who may be affected thereby;

All the Work and materials and equipment to be inc orporated therein, whether in storage on or off the site; and

Other property at the site or adjacent thereto, in cluding trees, shrubs, lawns, walks, pavements, roadways, structures, utilities and unde rground facilities not designated for removal, relocation or replacement in the course of construction.

The Contractor shall comply with all applicable law s and regulations of any public body having jurisdiction for the safety of persons or property or to protect them from damage, injury or loss and shall erect and maintain all necessary safeguards f or such safety and protection. The Contractor shall notify owners of adjacent property and of und erground facilities and utility owners when prosecution of the Work may affect them and shall cooperate with them in the protection, removal, relocation and replacement of their property. All injury or loss to any property caused, directly or indirectly, in whole or in part, by the Contractor, any subcontractor, supplier or any other person or organization part, by the Contractor, any subcontractor, supplier or any other person or organization directly or indirectly employed by any of them to p erform or furnish any of the Work or anyone for whose acts any of them may be liable, shall be reme died by the Contractor. The Contractor’s duties and responsibilities for the safety and prot ection of the Work shall continue until such time as all the Work is completed and the Owner has issu ed a notice of final completion to the Contractor.

SECTION E PAGE E-13

CITY OF CULVER CITY PZ-428 May 2026

Safety Emergencies
In emergencies affecting the safety or protection o f persons or the Work or property at the site or adjacent thereto, the Contractor, without special i nstruction or authorization from the Engineer, is obligated to act to prevent threatened damage, inju ry or loss. The Contractor shall give the Engineer prompt written notice if the Contractor be lieves that any significant changes in the Work or variations from the Contract have been caused th ereby.

Safety Violations
Should the Contractor fail to correct an unsafe con dition, the Engineer shall immediately notify the Owner of the Contractor’s failure to correct the un safe condition. The Owner shall then notify the Contractor through the Engineer that the unsafe condition must be corrected or the work in question will be stopped until the condition is corrected to the satisfaction of the Owner. No extension of time or additional compensation will be granted as a result of any stop order so issued.

The Owner shall have the authority to require the r emoval from the project of the foreman and/or superintendent in responsible charge of the work wh ere safety violations occur.

Equipment Safety Provisions
The completed Work shall include all necessary perm anent safety devices, such as machinery guards and similar ordinary safety items, required by the State and Federal (OSHA) industrial authorities and applicable local and national codes . Further, any features of the Work, including Owner-selected equipment subject to such safety reg ulations shall be fabricated, furnished, and installed in compliance with these requirements. A ll equipment furnished shall be grounded and provided guards and protection as required by safet y codes, and where vapor-tight or explosion- proof electrical installation is required by safety codes, this shall be provided. Contractors and manufacturers of equipment shall be held responsibl e for compliance with the requirements included herein. The Contractor shall notify all e quipment suppliers and subcontractors of the provisions of this paragraph.

On-Site Copies Required
The Contractor shall have at the work site copies o r suitable extracts of: Construction Safety Orders, and General Industrial Safety Orders issued by the State Division of Industrial Safety.

Compliance Required
Contractor shall comply with provision of these and all other applicable laws, ordinances, and regulations, including but not limited to the Occupational Safety and Health Act of 1970 and current amendments, if any, to which particular attention is directed.

Clearance from Power Lines

To help prevent injuries and electrical service int erruptions, Contractors are reminded CAL/OSHA requires tools, machinery equipment, apparatus, mat erials, or supplies must be kept at least 10 feet from voltage lines energized at 50,000 volts o r less and even greater distances for lines in excess of 50,000 volts. In addition, the Penal Cod e of the State of California, Section 385, makes it a misdemeanor to violate certain clearances from high voltage lines.

Prior to starting work in which the aforementioned clearances will be impaired, it will be necessary to contact the Southern California Edison (SCE) Com pany Business Office nearest the proposed work location and request assistance. SCE will tak e appropriate action to assist in maintaining required clearances. Such action will be at Contra ctor’s expense. Sufficient lead time to permit planning and scheduling of any necessary work will be required.

Special Hazardous Substance and Process

SECTION E PAGE E-14

CITY OF CULVER CITY PZ-428 May 2026
Contractor acknowledges that Contractor is aware of and in compliance with the provisions of the Hazard Communication Standards (California Administ rative Code, Title 8, Section 4194).

Contractor shall, at the request of the Owner, demo nstrate that Contractor is in complete compliance with the Hazard Communication Standards.

In addition, Contractor shall, at the request of th e Public Works Director/City Engineer, provide to the Owner a Material Safety Data Sheet for any prod uct handled or used by the Contractor on Owner property or in an area where an Owner’s emplo yee is working.

SECTION 6 – PROSECUTION AND PROGRESS OF THE WORK

6-1 CONSTRUCTION SCHEDULE AND COMMENCEMENT OF WORK Add the following:

The Contractor must provide to the Engineer’s Repre sentative within five (5) days after receiving the “Notice to Proceed”, a Critical Path Method (CP M) construction schedule in the format of a Gantt Chart and revised schedules thereafter as req uired by the Engineer when the Contractor’s activities differ or are expected to differ from the latest existing schedule.

In addition, unless otherwise notified by the Engi neer, the Contractor shall submit a detailed “two- week look-ahead” schedule bi-weekly, including a br ief narrative report, showing the activities or portions of activities completed and look ahead dur ing the reporting period. The report shall state the percentage of the work completed and scheduled, the remaining duration, and the progress along the critical path in terms of days ahead or b ehind the allowable dates as of the report date.

Any changes made by the Contractor to the schedule shall be listed.

If, in the opinion of the Construction Manager, th e project is behind schedule, the Contractor shall also submit a narrative report with each updated an alysis which shall include but not be limited to a description of current and anticipated problem ar eas, delaying factors and their impact, and an explanation of corrective actions taken or proposed.

If requested by the Contractor, Notice To Procure E quipment and Material may be issued prior to the Notice to Proceed with construction.

6-3 TIME OF COMPLETION

6-3.1 general add the following:

The following days have been designated as holidays by the City of Culver City:

New Year’s Day January 1
Martin Luther King, Jr. Day 3
rd Monday in January
Memorial Day Last Monday in May
Independence Day July 4
Labor Day 1
st Monday in September
Thanksgiving 4 th Thursday in November
Day after Thanksgiving
Christmas Day December 25

In addition, Culver City observes a “Holiday Slowdown” during which construction activities are prohibited in Public right-of-way. On arterial streets and commercial streets, Holiday slowdown will be observed from:

1. Wednesday before Thanksgiving until Sunday the s ame week

2. Christmas Eve until January 2
nd .

SECTION E PAGE E-15

CITY OF CULVER CITY PZ-428 May 2026
During the slowdown, the Contractor shall maintain job site and public safety and schedule to perform work outside the public right-of–way. No ti me extension will be granted due to the failure of the Contractor to schedule the work appropriately.

Add the following subsection:

6-3.3 Work Hours

The Contractor’s working hours shall be limited to the hours between 8:00 A.M. and 5:00 P.M.

Monday through Friday, excluding recognized holiday s. Workdays are defined in Section 6-7.2 of the Standard Specifications and as modified above. The Contractor shall not do any construction activity outside of the work hours, including but n ot limited to demolition, removal, construction, or material staging or delivery.

Work hours other than normal work hours will not be allowed without prior consent of the City Engineer.

For work performed at night, the Contractor shall p rovide adequate lighting for proper prosecution of the work for the safety of the workers and the public, and for proper inspection.

Work in Caltrans Right of Way may have more restricted working/lane closure hours. The contractor shall adhere to all Caltrans encroachment permit requirements.

6-4 DELAYS AND EXTENSION OF TIME Add the following:

The Contractor shall retain the right to fully complete (include final completion, punch list and project close out) the Work in less days than established b y the contract agreement. However, neither shall a reduction or increase to the Contract Sum be made, if the Work is so fully completed in less days than established by the contract agreement nor shall a Claim be made or granted for Compensable Delay, or any other increase in Contrac t Sum, if, for any reason, including but not limited to delay caused by owner, the Contractor do es not so fully complete the Work in less days than established herein.

When the Contractor foresees a delay in the prosecution of the Work and, in any event, immediately upon the occurrence of a delay, the Contractor shall notify the Public Works Director/City Engineer in writing of the probability of the occurrence and the estimated extent of the delay, and its cause.

The Contractor shall take immediate steps to prevent, if possible, the occurrence or continuance of the delay. The Contractor agrees that no claim shall be made for delays which are not called to the attention of the Public Works Director/City Engineer at the time of their occurrence.

Non-excusable delays in the prosecution of the Work shall include delays which could have been avoided by the exercise of care, prudence, foresight, and diligence on the part of the Contractor or its subcontractors, at any tier level, or suppliers.

Only the physical shortage of material, caused by unusual circumstances, will be considered under these provisions as a cause for extension of time, and no consideration will be given to any claim that material could not be obtained at a reasonable , practical, or economical cost or price, unless it is shown to the satisfaction of the Public Works Director/City Engineer that such material could have been obtained only at exorbitant prices entire ly out of line with current rates, taking into account the quantities involved and usual practices in obtaining such quantities. A time extension for shortage of material will not be considered for material ordered or delivered late or whose availability is affected by virtue of the mishandli ng of procurement. The above provisions apply equally to equipment to be installed in the work.

SECTION E PAGE E-16

CITY OF CULVER CITY PZ-428 May 2026

6-6 SUSPENSION OF WORK Add the following:

If the Contractor fails to correct defective or una uthorized work as required by the Contract Documents or fails to carry out the Work in accorda nce with the Contract Documents or any other applicable rules and regulations, the Owner, by a w ritten order of the Owner’s representative or signed personally by an agent specifically so empow ered by the Owner, in writing, may order the Contractor to stop the work, or any portion thereof , until the cause for such order has been eliminated; however, this right of the Owner to sto p the Work shall not give rise to any duty on the part of the Owner to exercise this right for the benefit of the Contractor or any other person or entity.

All delays in the Work occasioned by such stoppage shall not relieve the Contractor of any duty to perform the Work or serve to extend the time for it s completion. Any and all necessary corrective work done in order to comply with the Contract Docu ments shall be performed at no cost to the Owner.

In the event that a suspension of Work is ordered, as provided in this paragraph, the Contractor, at its expense, shall perform all work necessary to pr ovide a safe, smooth, and unobstructed passageway through construction for use by public, pedestrian, and vehicular traffic, during the period of such use by suspension. Should the Contractor fail to perform the Work as specified, the Owner may perform such work and the cost thereof ma y be deducted from monies due the Contractor under the Contract.

The Owner shall also have authority to suspend the Work wholly or in part, for such period as the Owner may deem necessary, due to unsuitable weather , or to such other conditions as are considered unfavorable for the suitable prosecution of the Work. Such temporary suspension of the Work will be considered justification for time extensions to the Contract in an amount equal to the period of such suspension if such suspended wor k includes the current critical activity on the latest favorably reviewed progress schedule.

6-7 TERMINATION OF THE CONTRACT FOR DEFAULT Add the following:

The Contract may be canceled by the Owner without l iability for damage when, in the Owner’s opinion, the Contractor is not complying in good fa ith, has become insolvent, or has assigned or subcontracted any part of the work without the Owner’s consent. In the event of such cancellation, the Contractor will be paid the actual amount due b ased on the quantity of work satisfactorily completed at the time of cancellation, less damages caused to the Owner by acts of the Contractor causing the cancellation. The Contractor, in havi ng tendered a bid, shall be deemed to have waived any and all claims for damages because of cancellation of the Contract for any such reason.

If the Owner declares the Contract canceled, for an y of the above reasons, written notice to that effect shall be served upon the Surety. The Surety shall, within five (5) working days, assume control and perform the work as successor to the Contractor.

If the Contractor fails to begin delivery of materi al and equipment, to commence work within the time specified, to maintain the rate of delivery of material, to execute the work in the manner and at such locations as specified, or fails to maintai n a work program which will ensure the Owner’s interest or, if the Contractor is not carrying out the intent of the Contract, the Public Works Director/City Engineer’s written notice may be serv ed upon Contractor, and the Surety on Contractor’s faithful performance bond, demanding s atisfactory compliance with the Contract.

If the Contractor or Contractor’s Surety does not c omply with such notice within five (5) working days after receiving it, or after starting to compl y fails to continue, the Owner may exclude the Contractor from the premises and take possession of all material and equipment, and complete the work by Owner forces or by letting the unfinished w ork to another contractor, or by a combination of such methods. In any event, the cost of complet ing the work will be charged against the Contractor and Contractor’s Surety, and may be dedu cted from any money due or becoming due from the Owner. If the sums under the Contract are insufficient for completion, the Contractor or Surety shall pay to the Owner within five (5) worki ng days after the completion, all costs in excess of the Contract price.

SECTION E PAGE E-17

CITY OF CULVER CITY PZ-428 May 2026
If the Surety assumes any part of the work, Surety shall take the Contractor’s place in all respects for that part, and shall be paid by the Owner for a ll work performed by Surety in accordance with the Contract. If the Surety assumes the entire Con tract, all money due the Contractor at the time of Contractor’s default shall be payable to the Sur ety as the work progresses subject to the terms of the Contract.

The provisions of this Section shall be in addition to all other rights and remedies available to the Owner under law.

6-8 TERMINATION OF THE CONTRACT FOR CONVENIENCE Add the following:

The Owner may terminate the Contract at its own discretion or when conditions encountered during the work make it impossible or impracticable to pro ceed, or when the Owner is prevented from proceeding with the Contract by law, or by official action of a public authority. The Contractor will be compensated for works satisfactorily completed u p to the date of termination of the contract by the Owner.

If all or any part of the work shall be damaged or destroyed by war, or acts of foreign aggression, fire, storm, lighting, flood, earthquake, settlemen t of defective soil, expansion or contraction, cracking or deflection, tidal wave, water, oil (surface or subsurface), mob violence or other casualty before the final completion of the work, the Contra ctor, upon notice from the Owner, shall resume construction and proceed in accordance with the Pla ns and Specifications. Provided that such damage or destruction was not caused by any conditi on related to Contractor’s non-conformance with the provisions of these contract documents, th e Owner will bear the total cost of removing and/or replacing all damaged and/or destroyed work. However, if the Owner exercises its option to abandon the project because of damage or destruc tion to the work by any of the above- mentioned causes, Owner may terminate this Contract upon three days’ notice to the Contractor.

Within 30 days after the date of such termination, the Contractor shall be paid all actual costs of the work to the date of termination for which it had not been previ’usly paid.

If the owner abandons the project, the owner shall have the right, at any time, to terminate this Contract by notice to the Contractor, in which event, the owner shall pay the contractor pro rata for all work actually provided up to the date of such n otice, for which it had not been previously paid, and the Owner shall have no further liability or obligations under this contract.

6-9 LIQUIDATED DAMAGES. Delete the entire subsection and substitute the following:

Failure of the Contractor to complete the Work within the time allowed will result in damages being sustained by the Agency. Such damages are, and will continue to be, impracticable and extremely difficult to determine. For each consecutive calend ar day in excess of the time specified for completion of the Work, as adjusted in accordance with 6-6, the Contractor shall pay to the Agency, or have withheld from moneys due it, the sum of $1,000 . Execution of the contract under these Specifications shall constitute agreement by the Ag ency and Contractor that $1,000 per calendar day is the minimum value of the costs and actual da mage caused by failure of the Contractor to complete the Work within the allotted time. Such s um is liquidated damages and shall not be construed as a penalty, and may be deducted from pa yments due the Contractor if such delay occurs.

In addition to the liquidated damages specified, if the Contractor fails to complete the work within the time specified for completion, plus any authori zed time extensions, the Agency shall have the right to charge to the Contract all or any part, as it may deem proper, of the actual costs of inspection, supervision and other overhead expenses that are directly chargeable to the project and that accrue after the expiration of such specif ied time for completion plus authorized extensions. This charge will be addition to the payment of liquidated damages.

SECTION E PAGE E-18

CITY OF CULVER CITY PZ-428 May 2026
6-10 LEGAL ACTIONS AGAINST THE CITY Add the following subsection:

In the event litigation is brought against the City concerning compliance by the City with State or Federal laws, rules or regulations applicable to hi ghway work, the provisions of this section shall apply.

a. If, pursuant to court order, the City prohibits the Contractor from performing all or any portion of the work, the delay will be considered a right of way delay within the meaning of Subsection 6-6 of the Standard Specification unless the contract is terminated as hereinafter provided, in which event compensation payable to th e Contractor shall be determined in accordance with said termination provisions.

b. If, pursuant to court order (other than an order to show cause) the City is prohibited from requiring the Contractor to perform all or any port ion of the work, the City may, if it so elects, eliminate the enjoined work pursuant to Section 3 o f the Standard Specifications or terminate the contact in accordance with Subsections 6-3 and 6-5 of the Standard Specifications.

c. If the final judgment in the action prohibits the City from requiring the Contractor to perform all or any portion of the work, the City will eithe r eliminate the enjoined work pursuant to Sections 3 of the Standard Specifications or terminate the Contract in accordance with Subsections 6-3 and 6-5 of the Standard Specifications.

d. Termination of the Contract and the total compensat ion payable to the Contractor in the event of termination shall be governed by the following:

(1) The Engineer will issue the Contractor a writte n notice specifying that the Contract is to be terminated. Upon receipt of said written notice and, except as otherwise directed in writing by the Engineer, the Contractor shall:

a. Stop all work under the contract, except that sp ecifically directed to be completed prior to acceptance.
b. Perform work the Engineer deems necessary to sec ure the project for termination. c. Remove equipment and plan from the site of the w ork. d. Take such action as is necessary to protect mate rials from damage. e. Notify all Subcontractors and suppliers that the contract is being terminated and that their contracts of orders are not to be further performed unless otherwise authorized in writing by the Engineer.
f. Provide the Engineer with an inventory list of a ll materials previously produced, purchased or ordered from suppliers for use in the work and not yet used in the work, including its storage location and such other information as the Engineer may request.
g. Dispose of materials not yet used in the work as directed by Engineer. It shall be the Contractor’s responsibility to provide the City with good title to all materials purchased by the City hereunder, including materials for which partial payment has been made as provided in Subsection 9-3.2 of the Standard Specifications, and with bills of sale or other documents of title for such materials. h. Subject to the prior written approval of the Eng ineer, settle all outstanding liabilities and all claims arising out of subcontracts or order s for materials terminated hereunder. To the extent directed by the Engineer, the Contractor shall assign to the City all the right title and interest of the Contractor under subcontracts or orders for materials terminated hereunder.
i. Furnish the Engineer with the documentation requ ired to be furnished by the Contractor under the provisions of the contract inc luding, on projects as to which Federal funds are involved, all documentation requi red under the Federal requirements included in the contract.
j. Take such other actions as the Engineer may dire ct.

SECTION E PAGE E-19

CITY OF CULVER CITY PZ-428 May 2026

(2) Acceptance of the Contract as hereinafter speci fied shall not relieve the Contractor of responsibility for damage to materials except as follows:

A. The Contractor’s responsibility for damage to ma terials for which partial payment has been made as provided in Subsection 9-3.2 of the Standard Specifications, and for materials furnished by the City for use in the work and unused, shall terminate when the Engineer certifies that such materials have been stored in the manner and at the locations he has directed.

B. The Contractor’s responsibility for damage to ma terials purchased by the City subsequent to the issuance of the notice that the c ontract is to be terminated shall terminate when title and delivery of the materials has been taken by the City.

C. When the Engineer determines that the Contractor has completed the work under the contract directed to be completed prior to term ination and such other work as may have been ordered to secure the project for ter mination, he will recommend that the Engineer formally accept the Contract, and immediately upon and after such acceptance by the Engineer, the Contractor will not be required to perform any further work thereon and shall be relieved of his contractual responsibilities for injury to persons or property which occurs after the forma l acceptance of the project by the Engineer.

(3) The total compensation to be paid to the Contra ctor shall be determined by the Engineer on the basis of the following:

a. The reasonable cost to the Contractor, without p rofit, for all work performed under the contract, including mobilization, demobil ization and work done to secure the project for termination. Reasonable cos t will include a reasonable allowance for project overhead and general administ rative overhead not to exceed a total of seven percent (7%) of direct costs of such work.

When in the opinion of the Engineer, the cost of a contract item of work is excessively high due to costs incurred to remedy or replace defective or rejected work, the reasonable cost to be allowed will be the estimated reasonable cost of performing such work in compliance with the require ments of the Plans and Specifications and the excessive actual cost shall be disallowed.

b. A reasonable allowance for profit on the cost of the work performed as determined under Subsection (a), provided the Contr actor establishes to the satisfaction of the Engineer that it is reasonably probable that he would have made a profit had the contract been completed and p rovided further that the profit allowed shall in no event exceed four percent (4%) of said cost.

c. The reasonable cost to the Contractor of handlin g material returned to the vendor, delivered to the City or otherwise disposed of as directed by the Engineer.

d. A reasonable allowance for the Contractor’s admi nistrative costs in determining the amount payable due to termination of the contract.

All records of the Contractor and his Subcontractor s, necessary to determine compensation in accordance with the provisions of this section, sha ll be open to inspection or audit by representatives of the City at all times after issu ance of the notice that the contract is to be terminated and for a period of three years, and such records shall be retained for that period.

After acceptance of the work by the Engineer, the E ngineer may make payments on the basis of interim estimates pending issuance of the Final Estimate when in his opinion the amount thus paid, SECTION E PAGE E-20

CITY OF CULVER CITY PZ-428 May 2026
together with all amounts previously paid allowed, will not result in total compensation in excess of that to which the Contractor will be entitled. All payments, including payment upon the Final Estimate shall be subject to deduction for prior payments and amounts, if any, to be kept or retained under the provisions of the contract.

The provisions of this section shall be included in all subcontracts.

SECTION 7 – MEASUREMENT AND PAYMENT

7-3 PAYMENT

7-3.1 General. Add the following:

Payment for cost of work to comply with the General Provisions of the Standard Specification for Public Works Construction and as modified by this C ontract shall be included in the various bid items, and no additional payment will be made.

Bid prices provided on the appropriate Bid Form wil l remain in force as Unit Prices under the Contract Documents until the Contract has been fully performed. No cost escalation is allowed due to material price increase for the term of the project.

When an item of work is not listed in the “bid sche dule” in the bid proposal, the cost of such work shall be considered to be included in the cost of t he other Work that is listed. The Contractor is to provide all labor, material, and equipment necessar y to complete the Project in accordance with the plans and specifications including, but not limited to the following:

a. All “Special Provisions” work required to comple te the Project in a safe and orderly manner including, but without being limited to, saf ety measures, hoists, flagmen, clean-up, barricades, fences, temporary utilities, utility fees and charges, parking for the Contractor’s and Subcontractor’s personnel, and temporary facilities as may apply to this Work;

b. All insurance in accordance with the insurance r equirements of the Contract;

c. Maintain and update current record drawings on-s ite. Upon project completion provide the Owner a legible set of record drawings, operati on and maintenance manuals, warranties, and guarantees;

d. All permits required;

e. Construction schedule indicating material lead t imes, shop drawings, order dates, start and end dates, milestone dates. The schedule shall be updated monthly;

f. Monthly project status report; Attend weekly pro ject meetings;

g. All engineering, testing and inspection costs fo r defective work, and work performed outside of the work hours set forth in Section 6-7 of the Special Provisions;

SECTION E PAGE E-21

CITY OF CULVER CITY PZ-428 May 2026
h. Repair or replace all existing improvements (pub lic or private) damaged by the Contractor. The Contractor is responsible to provi de evidence of pre-existing conditions;

i. All scheduling of utility connections turn on/of f including but not limited to electrical services (for street lighting, traffic signals, and irrigation controllers) and water meters.

j. All construction survey/staking necessary to set grade for all improvements. The survey provider shall be appropriately licensed by the State of California and is subject to approval by the Owner;

k. Watchman or security service, as necessary;

l. Perimeter fencing of work zones and staging area as necessary for public safety and protection of equipment and materials;

m. Dust control, street cleaning, and protection an d/or replacement of existing surfaces or properties;

n. Submittal Log of all submittals required to the Owner including but not limited to SWPPP, material, products, concrete testing data, b atch plant testing data, shop drawings and traffic control and phasing plans. Sa id log shall be updated for each weekly project meeting.

All costs for the preceding shall be included in the other items for which bids are entered.

The City may keep any monies which would otherwise be payable at any time hereunder and apply the same, or so much as may be necessary therefore, to the payment of any expense, losses or damages, as determined by the Engineer, incurred by the City, for which the Contractor is liable under the Contract.

Other Withholds

In addition to the amount which the Owner may other wise retain under the Contract, the Owner may withhold a sufficient amount or amounts of any payment or payments otherwise due the Contractor, as in its judgment may be necessary to cover:

a. Payments which may be past due and payable for j ust claims against the Contractor or any subcontractor for labor or materials furnished for the performance of this Contract.

b. Defective work not remedied.

c. Failure of the Contractor to make proper payment s to its subcontractors or suppliers.

d. A reasonable doubt that the Contract can be comp leted for the balance remaining.

e. Damage to another Contractor or third party, or to private or City property.

f. Failure of the Contractor to keep its work progr essing in accordance with its progress schedule or maintaining current Record Drawings.

SECTION E PAGE E-22

CITY OF CULVER CITY PZ-428 May 2026
g. The Owner’s costs for the Contractor’s failure t o complete work within the allowed time.

h. Cost of insurance arranged by the Owner due to c ancellation or reduction of the Contractor’s insurance.

i. Failure of the Contractor to make proper submiss ions, as herein specified.

j. Failure to submit, revise, resubmit, or otherwis e conform to the requirements herein for preparing and maintaining a construction schedule.

k. Payments due the Owner from the Contractor.

l. Provisions of law that enable or require the Own er to withhold such payments in whole or in part.

The Owner in its discretion may apply any withheld amount or amounts to the payment of valid claims. In so doing, the Owner shall be deemed the agent of the Contractor, and any payment so made by the Owner shall be considered as a payment made under the Contract by the Owner to the Contractor, and the Owner shall not be liable to the Contractor for such payment made in good faith. Such payments may be made without prior judicial determination of the claim or claims. The Owner will render to the Contractor a proper accoun ting of such funds disbursed in behalf of the Contractor.

Pursuant to Public Contract Code Section 22300, for monies earned by the Contractor and withheld by the Owner to ensure the performance of the Contract, the Contractor, may, at its option, choose to substitute securities meeting the requirements o f said Public Contract Code Section 22300.

There would be an associated administrative charge of $75 per each Contractor’s Progress Invoice.

7-3.2 Partial and Final Pay Quantities. Add the following:

When the estimated quantities for a specific portio n of the work are designated as a final payment quantities, said estimated quantities shall be the final quantities for which payment for such specific portion of the work will be made unless the dimensi ons of said portions of the work shown on the plans are revised by the Engineer. If such dimensio ns are revised and such revisions result in an increase or decrease in the quantities of such work, the final quantities for payment will be revised in the amount represented by the changes in the dim ensions. The estimated quantities for such specified portion of the work shall be considered a s approximate only, and no guarantee is made that the quantities which can be determined by comp utations made based on the details and dimensions shown on the plans will equal the estima ted quantities. No allowance will be made in the event that the quantities based on computations do not equal the estimated quantities. .
7-3.3 Delivered Materials Add the following:

Unless included in the Bid Schedule, or unless othe rwise called for in Technical Provisions, no payment will be made for materials or equipment delivered but not yet incorporated in the work.

7-4 PAYMENT OF EXTRA WORK

7-4.1 General Add the following:

The Contractor shall not perform any extra work prior to written authorization from the E ngineer.

SECTION E PAGE E-23

CITY OF CULVER CITY PZ-428 May 2026
7-4.2.3 Tool and Equipment Rental Revise the statement in the subsection and apply the following :

Regardless of ownership, the rates to be used in de termining equipment rental costs shall not exceed listed rates according to California State T ransportation Authority (CalTrans) “Labor Surcharge and Equipment Rental Rates (Cost of Equip ment Ownership)”, at the time the Extra Work is performed.

7-4.3 Markup Delete the entire paragraph and substitute the following:

Work by Contractor When extra work is to be paid for on a force accoun t basis, the labor, materials, equipment rental and other items of expe nditures, the percentage of markup applied to the Contractor’s direct cost for all overhead and profit shall be as follows:

(1) Labor…......................................... .... 12 (2) Materials…..................................... .. 12 (3) Equipment Rental…......................... 12
(4) Other Items and Expenditure…........ 12

Work by Subcontractor. When all or any part of the extra work is performed by a Subcontractor, the markup established above in this section shall be applied to the Subcontractor’s actual cost of such work. A markup of 10 percent on the first $5,0 00 of the subcontracted portion of the extra work and a markup of 5 percent on work added in excess of $5,000 of the subcontracted portion of the extra work may be added by the Contractor.

To the sum of the costs and markups provided for in this section, 1% shall be added as compensation for bonding.

7-4.4 Daily Reports By Contractor Add the following:

Material charges shall be substantiated by valid co pies of vendor’s invoices. Such invoices shall be submitted with the daily extra work reports, or if not available, they shall be submitted with subsequent daily extra work reports. When these da ily extra work reports are agreed upon and signed by both parties, said reports shall become the basis of payment for the work performed.

SECTION 8 – FACILITIES FOR AGENCY PERSONNEL

Facilities for Agency Personnel is not required on this project unless specified otherwise in the Tech nical Provisions.

SECTION E PAGE E-24

CITY OF CULVER CITY PZ-428 May 2026
PART 4

EXISTING IMPROVEMENTS

SECTION 400 PROTECTION AND RESTORATION

400-1 General Add the following subsection:

The Contractor shall examine all adjoining premises (including for the purposes hereof, streets and sidewalks) and buildings, and ascertain, before beginning work, the depth of cellars, materials and construction of buildings and all existing conditio ns of such premises and the buildings thereon, and shall be governed thereby for the necessary, th orough, safe and satisfactory execution of all work called for herein, whether indicated on Plans and/or specified, or not, and all work and protective measures necessary to keep and leave the said premises and buildings in the same condition as they were before commencing work shall be done without any addition to the Contract Price. Wherever any parts of the existing adjoining buildings interfere with or are interfered with by the work to be performed hereunder, the Contractor shall make whatever changes necessary thereby, whether shown on the Plans, called for in the Specifications, or not shown or not called for. The Contractor, before commencing work on the premises, shall, if he sees fit, make a written report of the conditions as found at that time, not ing particularly any defects in evidence, taking photographs of the exteriors, and, if necessary, ph otographs of interiors, and shall deliver to the Owner a copy of the written report of the examinati on and copies of photographs with the date of taking thereon. The Contractor shall invite the Ow ner and the owners of the respective properties and buildings to join with them in the examination of the premises and buildings. The Owner may, at its option, be present during the examination. If the Contractor fails to make the examination and report as herein specified, it will be deemed t hat the adjoining buildings and premises are in good condition, and all claims for damages, repairs and replacements must be treated by the Contractor on the basis that the buildings and premises were in good condition before work began.

The Contractor shall shore up, brace, underpin, secure, and protect all foundations, improvements, and other parts of existing structures adjacent to the work site, which may in any way be affected by excavation or other operations in connection with the work to be performed under this contract.

The Contractor shall be responsible for giving all required notices to any joining property owner or other party before commencement of work.

SECTION 401 REMOVAL

401-1 General Add the following subsection:

Solid waste handling and recyclable waste material handling shall be performed exclusively by the City or its authorized agents. The City Council may regulate, by ordinance or resolution, all aspects of solid waste handling and recyclable material han dling, including but not limited to, frequency of collection, means of collection and transportation, level of serves, charges, fees, and nature, location and extent of providing solid waste handling services.

The City of Culver City provides waste disposal and recycling services for all construction & demolition projects within city limits in accordanc e with CCMC 5.01.010. As part of The City of Culver City's permitting process, the information provided will assist in establishing waste disposal and recycling services account and initiate waste c ollection, processing and disposal services for materials generated for the duration of the project. For further information such as roll-off bin rates, contact the Sanitation Division at (310) 253-6400.

Contractor shall divert a minimum of seventy-five percent (75%) of the construction and demolition debris resulting from the work per CCMC 15.02.1140. The Contractor shall uploaded monthly hauler tickets to the Green Halo System at the end of each month. Before starting work, contractors must register the project in Green Halo, submit a w aste management plan, and coordinate all hauling services through Culver City’s Environmental Programs and Operations Division.

SECTION E PAGE E-25

CITY OF CULVER CITY PZ-428 May 2026

The City utilizes the Green Halo System for trackin g the construction and demolition waste management process. Upon project award, the Contrac tor will be directed to the Green Halo website to continue the Waste Management Application process. Once the application is submitted, the Contractor shall receive separate email notific ations directly from Green Halo to activate the account. Confirmation emails shall be forwarded to the City's Project Manager. A case will be created to monitor the construction and demolition recycling activities of your project. The Contractor shall not commence work until the Green Halo application is complete. A monthly "C&D Administration Fee" (See Appendix D – Public Works Department Environmental Programs & Operations: Service Agreement and C&D Fee Schedules) will apply for the duration of the project.

All waste tickets must be uploaded to the Green Hal o account, and full compliance is required to receive final inspection approval and close out the project.

If you have any questions regarding C&D requirement s, please contact Jezenia Aguirre at [email protected] .

The bidders shall estimate quantities of all Constr uction and Demolition waste for the project and obtain approval for any self-hauling operations fro m Culver City’s Environmental Programs and Operations Division.

The cost to comply with the City’s Construction and Demolition Waste Management Plan shall be included in the unit or lump sum prices for the app licable items of work listed in the Bidder’s Proposal and no additional compensation will be allowed.

SECTION 402 – UTILITIES

402-1 LOCATION

402-1.1 General Add the following:

Prior to performing any excavation, the Contractor shall determine, by potholing, the location and depth of all utilities, including service connectio ns, which have been marked by the respective owners and which may affect or be affected by its operations. The Contractor shall pothole all utility crossings on public streets. The Contractor shall v erify depth of all service utility crossings under sidewalk. Contractor shall locate all existing util ities, including storm and sewer main and laterals, within the project vicinity and shall exercise due care to ensure that existing utility facilities are not damaged during his operations. The existence of sewer mains or storm drains is evidenced by the manhole structures and catch basins. When in doubt , the Contractor shall contact the utility operator concerned before proceeding further.

Pipelines, conduits and other facilities may be buried within the limits of the work or adjacent thereto and may or may not be shown or indicated on the Plans. The Public Works Director/City Engineer possesses records of certain utility facilities loc ated within the public right-of-way. These records are available for inspection by the Contractor at t he Engineer’s Office. In making these records available, the Owner does not warrant or guarantee the accuracy or completeness of the information contained therein and does not represen t that the facilities shown on said records actually exist at the locations shown or elsewhere or that the Contractor may not encounter facilities not identified in said records. The sewer service laterals are owned by the property owners and will not be marked by the City. Sewer system atlas sheet is available upon request for contractor’s reference. However, the City shall not guarantee th e accuracy of the information. It shall be the Contractor’s responsibility to locate and pothole a ll laterals. The Contractor at its expense shall repair sewer laterals that are damaged as the result of contractor’s activities.

At signalized intersections with Red Light Enforcem ent Camera Systems, the Contractor shall coordinate with the Red Light Enforcement Camera ma nufacture and/or maintenance company to identify the substructure (e.g. conduit runs) and for notification of work prior to construction.

SECTION E PAGE E-26

CITY OF CULVER CITY PZ-428 May 2026

The Contractor shall immediately notify the Enginee r of any potential conflict with the proposed improvements. The cost of repair to any utility da maged by the contractor due to failure to determine location and depth as required herein sha ll be borne by the Contractor. Full compensation for determining location and depth of utilities shall be considered as included in the prices bid for other items of work, and no additional compensation will be allowed.

402-2 PROTECTION Add the following:

The contractor shall protect in place all existing sewer, storm drain, and other utility manhole lids and covers, water meter boxes and covers, gas meter boxes and covers, valve covers, etc. to grade unless specifically designated for adjustment by others on the Plans. Payment for adjustment of said items to grade shall be considered as part of related bid items for which payment is made and no separate payment will be made theref ore.

For Ting Fiber Utility:

Protect in Place underground utilities, including T ing Fiber Utility that is approximately 6” below street surface. Ting Utility is generally located a long the edge of the gutter, on both sides of the street.

If the conduit is fully exposed in a working section but not going to be affected, a layer of sand is placed between the conduits and the material being laid to prevent it from sticking or melting the conduit. The Contractor is responsible if the conduit is hit or the fiber is damaged.

SECTION E PAGE E-27

CITY OF CULVER CITY PZ-428 May 2026
PART 6

TEMPORARY TRAFFIC CONTROL

SECTION 600 ACCESS

600-1 General Add the following:

Traffic and access, including but not limited to ve hicular and pedestrian traffic controls, maintenance of vehicular and pedestrian access, det ours, and street closures, shall be in accordance with Subsection 7-10, of the latest edit ion of the Standard Specifications for Public Works Construction, including all its subsequent am endments; the latest edition of the Work Area Traffic Control Handbook (“WATCH”) as published by the Building News, Inc., and the following Special Provisions. In the event of conflict, the Special Provisions shall take precedence over the Work Area Traffic Control Handbook (“WATCH”) and th e Standard Specifications, and the Work Area Traffic Control Handbook (“WATCH”) shall take precedence over the Standard Specifications.

The Contractor is solely responsible for the traffic control safety of pedestrians and vehicles on the public right-of-way within the Contractor’s work ar ea. The Contractor shall hold harmless and indemnify the Owner, and each of its officers and e mployees, for any and all damages to persons and property due to the Contractor’s failure to maintain adequate traffic control and safety. It is the affirmative duty of the Contractor to maintain all of his traffic control devices on the project at al l times, including night and/or weekends.

The Contractor shall notify by printed notice, the occupants of all properties within the construction zone of any access, parking and circulation restric tions and limitations that will be created by the construction at least 7 calendar days in advance of the commencement of construction. This notice shall be prepared by the City of Culver City, but be distributed by the Contractor.

No closure of any street shall be allowed unless pr ior written permission is obtained from the City Engineer. If permission to close a street is grante d, then the Contractor is required to notify in writing at least five (5) working days in advance o f street closures, all emergency services, and school bus services shall be notified by the contra ctor in writing of the locations, time, and date of the closures. In case of schedule changes, the eme rgency services, etc., shall be notified by telephone at least two (2) days in advance of the street closure.

Business Access
Pedestrian and vehicular access shall be maintained to businesses fronting the Work except when construction of areas immediately fronting a business entrance precludes such access. Contractor shall notify affected business three (3) business days in advance of construction.

Contractor shall make provisions for deliveries to business including temporary loading zones

Convenient and safe pedestrian access to occupied r esidential and business property shall be maintained at all times. Access to mailboxes must b e maintained at all times such that the postal delivery service is not- interrupted. Trash pick-up service shall not be interrupted. Access to vacant and unused property may be restricted when approved by the Engineer. Both vehicular and pedestrian access shall be maintained at all times to all other property except as otherwise specifically authorized in writing by the City’s Engineer.

Temporary No Parking

The Contractor shall notify in writing residents of property adjoining the location of the work at least forty-eight (48) hours before the start of construction on that street. The Contractor is responsible for posting “temporary no-parking” signs at least forty-eight (48) hours before using the parking lane for construction purposes. T he Contractor shall be responsible for furnishing, posting, and removing temporary “No Par king” and “No Driving” signs (as applicable) along project streets. Signs shall be posted on each side of the street with a SECTION E PAGE E-28

CITY OF CULVER CITY PZ-428 May 2026
maximum of 200 feet between signs. When necessary, the Contractor shall furnish posts.

Pursuant to City requirements, “Temporary No Parking” signs must be posted and verified by the Culver City Police Department 48 hours prior to beginning of construction.

The Contractor shall coordinate with postal authori ties for the temporary relocation of mailboxes.

Contractor shall provide signage directing pedestri an and vehicular traffic to temporary mailbox locations.

In the case of work requiring excavation of the roa dway which may interfere with the use by residents or businesses of their driveways, suitabl e provisions shall be made by the Contractor at such time as the exigencies of construction may dem and a temporary blocking of said driveways.

Efforts shall be made by the Contractor to minimize the duration of said blocking and to notify the residents of this need well in advance. Further, th e Contractor shall provide access to each residential or commercial establishment each evenin g. Any trench or excavation in the street or alley which remains open after work hours shall be covered by steel plates.

SECTION 601 TEMPORARY TRAFFIC CONTROL FOR CONSTRUCT ION AND

MAINTENANCE WORK ZONES

601-2 Traffic Control Plans (TCP) Add the following:

On all Arterial streets or other streets as required in the Technical Provisions, The Contractor shall submit detailed Traffic Control Plans (TCP) on 24” x 36” sheet which shall clearly show and describe all proposed lights, warning signs, barricades, del ineators, temporary lane markings, temporary traffic signals or signs, and any and all other fac ilities proposed to be installed. TCP shall be prepared by a Registered Civil or Traffic Engineer and shall show all lane closures, restrictions, tapers, and other disruptions of normal traffic flo w, including pedestrian and vehicular detours. A schedule shall be included. TCP shall be submitted to the Engineer for approval no later than two (2) weeks after the award of contract. It shall be the Contractor’s responsibility to immediately revise the TCP at the direction of the Engineer, an d the Contractor hereby agrees that such Plan shall be strictly adhered to, and the Contractor he reby understands and agrees that its failure to provide any facility or device as shown on the TCP, or its deviation from said Plan, shall constitute a breach of contract. Traffic control set up in the field shall be inspec ted and approved by the City Engineer’s Representative prior to commencement of any construction activity.

-- End of Section --

CITY OF CULVER CITY PZ-428 May 2026

SECTION F

TECHNICAL SPECIFICATIONS
SECTION F PAGE F-1

CITY OF CULVER CITY PZ-428 May 2026

BID ITEM No 1. MOBILIZATION/TRAFFIC CONTROL

The scope of the work shall include the obtaining of all bonds, insurance; moving onto the site of all project work areas and equipment; and the furnishing of oth er construction facilities; all as required for the proper performance and completion of the Work. Mobilizatio n shall include but not be limited to the following principal items:

1. Notification to adjacent businesses and residenc es. Contractor will be required to print and distribute a 7-day advance notice to each business and residence that may be impacted by the construction. Submit the notices to the City for ap proval . Notices shall be received at least 7 days prior, but not more than 14 days. The Contractor sh all provide a list to the City Project Manager of all addresses notified.

2. The movement of personnel, equipment, supplies a nd incidentals to the project site.

3. Furnishing, installing, and maintaining all stor age yards or sheds required for temporary storage of products, equipment, or materials that have not yet been installed in the Work. Construction yard:

As specified in the Special Provisions 3-12.4.1, th e contractor is responsible for locating the construction yard for its construction operation. T he contractor shall provide lease agreement and insurance prior to use any rented lot.

4. Confined space entry to excavations.

5. Have the Contractor’s superintendent or foreman at the job site full time.

6. Submittal of required construction schedule as s pecified. Construction schedule shall be kept up- to-date throughout the duration of the project. Unless otherwise confirmed by the Project Manager, the schedule at the start of the week shall be used to coordinate with other Departments and City Staff for that work week. Inspections must be sched uled at least 24 hours in advance.

7. All submittals as required in the specifications .

8. Submit work site exhibits for each job location, showing items including but not limited to equipment placement, materials storage, temporary restroom pl acement, demolition and construction debris disposal location, etc.

9. In addition, Mobilization shall include all item s required to conform to project site management efforts, including Best Management Practices (BMPs) per the 2024 Construction BMP Handbook.

BMP’s shall include all labor, work and materials n ecessary to plan and implement BMPs into the project. BMPs shall include methods and materials t o provide safety and protection throughout construction. Designated plans may be required to b e submitted to and approved by the Engineer prior to beginning construction.

Mobilization includes all work necessary to mobilize and demobilize forces, equipment, transportation, and materials; obtain bonding, insurance, permits, lice nses; and other work as necessary to prepare for constructing the work.

All submittals shall be submitted no later than two weeks after the contract award.

TRAFFIC CONTROL

Traffic Control shall conform to the provisions of Sections 7-8 and 7-10 of the Standard Specification s and Special Provisions of this specification, and the c ontractor shall at its cost prepare and obtain appr oved traffic control plans, and the implementation thereof.

The CONTRACTOR shall submit an engineered traffic c ontrol plan for review and approval for work if performed on arterial streets.

The CONTRACTOR shall provide all traffic controls n ecessary to provide for the safe and expeditious movement of traffic, motorized and non-motorized (i ncluding pedestrian traffic), through the construct ion zones, as well as those necessary to provide for the safety of the work force performing the construction.

The CONTRACTOR shall provide adequate pedestrian and vehicular traffic controls for the duration of the work in accordance with the Contract Documents including Subsection 7-10 of the SSPWC, the Work Area SECTION F PAGE F-2

CITY OF CULVER CITY PZ-428 May 2026
Traffic Control Handbook (WATCH), Caltrans' Manual of Traffic Controls for Construction and Maintenance Work Zones (Chapter 5 of the Traffic Manual, hereafter "Manual of Traffic Controls"), and the City of Culver City.

The CONTRACTOR shall include any temporary pavement necessary for the safe and expeditious movement of traffic.

Unless otherwise approved by the City Engineer, the Contractor shall coordinate access for resident s and businesses within the project limits . Any closure of access or drive approach shall be immediately restored when construction operation requiring the closure is completed. In addition, the Contractor shall comply with to the following:

 Where a resident or a business has a drive approac h that is at least 22 feet wide, the construction in the area shall be done in halves in order to maintain continuous access.  Where a resident or business has more than one two -way drive, continuous access to at least one two-way drive approach shall be maintain at all times.
 The Contractor shall construct temporary ramps at excavated areas and utilize other construction methods, such as temporary backfilling areas and la ying temporary AC pavement, in order to maintain continuous access in the construction zone.
 For arterial streets, unless otherwise directed by the Engineer, one lane in each direction must be maintained at all times and where possible, a left-turn lane at intersection during construction.

LANE CLOSURE HOURS ALLOWED:

Normal working hours/lane closure hours on arterial streets are from 9:00 a.m. to 3:30 p.m.

SIGNS

All excavations required for the purpose of installing traffic control signs, including construction area signs, shall be performed by hand methods without the use of power equipment, except that power equipment may be used if it is determined there are not utili ty facilities in the area of the proposed holes.

CONTRACTOR shall notify Underground Service Alert - Southern California (USA) at 800/422-4133 at least 2 working days, but no more than 14 calendar days, prior to commencing any excavation for said signposts.

All signage conflicting with required traffic control signage shall be removed or suitably covered. Said signs shall be replaced unless designated for removal or relocation on the Plan.

This item shall include the temporary relocation of existing signs as necessary. Additionally, signs shall be posted directing pedestrians to detour safely around construction work.

PAYMENT

Payment for BID ITEM NO. 1 – MOBILIZATION/TRAFFIC CONTROL shall be at the contract lump sum (LS) price and shall include full compensation for all labor, materials, tools, equipment, and inciden tals necessary to do all the work thereof including, but not limited to mobilization (including various subcontractors for multiple mobilizations as necessary), traffic control plans, traffic detour and traffic control.

Payment on this lump sum bid item shall be made wit h each progress payment in direct proportion to the amount of the total contract amount earned to date.

BID ITEM NO. 2 – CONSTRUCTION SURVEY, STAKING, RESE TTING SURVEY TIES AND

MONUMENTS

Construction Survey, Staking, and Reset Survey Ties and Monuments shall include all labor, equipment, materials, incidentals and work necessary to survey the work to conform to the plan lines and limits, provide SECTION F PAGE F-3

CITY OF CULVER CITY PZ-428 May 2026
grades, establish pavement grades, match existing conditions, and otherwise lay out the work as necessary for construction per the Plans or as directed by the City Engineer or Public Works Inspector.

The contractor shall also inspect for the presence of all survey monuments prior to construction, noti fy the City Engineer, and reset the location after constru ction. This work shall be done by and under the supervision of a Licensed Professional Land Surveyo r, licensed in the State of California. The scope o f survey monument preservation and re-setting will consist of, but not be limited to, performing a field review to determine the total number of survey monuments w hich would need to be re-set; for those survey monuments or property corner which need to be re-set, check existing ties and set new ties for each point; following construction of the improvements, re-set each monument. Survey markers exist at 9025 Lucerne Ave, 4240 Madison Ave, 4391 Mentone Ave, 4397 Mentone Ave, 3938 Tuller Ave, 11210 Huntley Pl, 11215 Huntley Pl, 5427 Emporia Ave.

PAYMENT

Payment for BID ITEM NO. 2 – CONSTRUCTION SURVEY, STAKING, RESETTING SURVEY TIES AND MONUMENTS ; shall be at the contract lump sum (LS) price and shall include full compensation for all labor, materials, tools, equipment, and incidentals necessary to do all the work thereof.

BID ITEM NO. 3 – REMOVAL AND REPLACEMENT OF UPLIFTE D SIDEWALK AT VARIOUS LOCATIONS PER APPENDIX A; 4” PCC OVER 4” CMB

GENERAL

Removal and disposal of existing sidewalk and other material shall comply with Section 300 of the Standard Specifications and the guidelines described herein. Limits of the construction shall be marked by the City Representative at each site prior to removal. Said removal shall be adequate to replace sidewalk in a manner such that the sidewalk surface will have a s traight grade when connecting the existing walk on either side of the walk length to be constructed (which was raised by tree roots). All debris shall be disposed of properly and in accordance with local codes and ordinances. All materials to be removed shall be disposed of outside the right-of-way as specified i n subsection 300-2 of SSPWC. Pavements shall be removed to neatly sawed edges as specified in subse ction 300-2.9 of SSPWC. Debris shall be removed same-day and not left at job site or in public righ t of way. Removals of existing PCC improvements sha ll include any existing base and/or subbase materials to a depth necessary for the placement of CMB under proposed PCC improvements.

Locations, dimensions and depths of PCC sidewalk re movals per Exhibit in Appendix A .

All materials to be removed shall be disposed of ou tside the right-of-way as specified in subsection 3 00-2 of SSPWC. Pavements shall be removed to neatly saw ed edges as specified in subsection 300-2.9 of SSPWC. Removals shall comply with the Special Provisions p er Section 401-1, page E-24 & E-25.

Debris shall be removed same-day and not left at job site or in public right of way.

The cost to comply with the City’s Construction and Demolition Waste Management Plan shall be included in the unit or lump sum prices for the applicable i tems of work listed in the Bidder’s Proposal and no additional compensation will be allowed.

Failure to comply with any of the provisions of the CCMC may result in forfeiture of the Performance Security Deposit.

EXCAVATION/TREE ROOT TRIMMING

The Contractor shall coordinate with the City Arborist for recommendations related to the health and stability of any trees prior to commencing work, including ro ot trimming, grinding and/or removal. The Contracto r shall coordinate a schedule with the City Arborist, Inspector, and Engineer for the City Arborist to r eview trees prior to commencing work. If the Contractor c hooses, the Contractor may provide a certified arbo rist at no additional cost to the City to review trees a nd provide a report for the City Engineer to review in lieu SECTION F PAGE F-4

CITY OF CULVER CITY PZ-428 May 2026
of the City Arborist. The City Engineer must provid e approval of the report prior to commencing work o n trees and tree roots. All equipment used in tree ro ot trimming must be sterilized, with bleach or anot her solution approved by the City Arborist, prior to advancing to the next tree.

Bid item consists of removing the existing damaged sidewalks. All exposed roots are to be trimmed to 4" (minimum) below the elevation of the bottom of prop osed 4" thick concrete sidewalk. The root removal areas are to have soil replaced with 4” crushed mis cellaneous base. All base material shall be clean and compacted in place, at 95% compaction, satisfactory to the City Engineer or his designee. In the event that removal of roots for sidewalk leveling might destab ilize any tree(s), a narrower (36 inch minimum widt h) sidewalk shall be constructed to meander the tree(s ) at the direction of City Engineer and City Arbori st.

After completion of sidewalk work, all areas will b e cleaned up; soil elevation adjacent to walks shal l be flush with the (straight graded) sidewalk elevation.

IRRIGATION SYSTEM PROTECTION

In areas where irrigation systems exist, they shall be protected in place or removed and replaced if damaged during construction. This work shall be done on the same day the system is damaged so that no damage is done to any landscaped areas. Schedule 40 PVC pipe is to be used in like size o f system being replaced. This shall be done only where needed for construction of sidewalks. Replace all sprinkler heads with type removed; adjust for yard areas to ensure adequate overspray to adjacent sprinklers. This work shall be completed as part of sidewalk construction and no separate payment will be made for sprinkler repairs related to any construction and no separate payment will be made. In the event an adjacent property owner claims that the irrigation systems were damaged by the contractor during the project, the contractor will be responsible for appeasing and satisfying the property owner at no additional cost to the City.

SIDEWALK CONSTRUCTION

New sidewalk grade shall be flush with existing sid ewalk on either side of the areas to be removed and replaced. All sidewalks shall be constructed to dra in so that no low spots are constructed where puddl ing or ponding might occur. Cross slopes shall match e xisting sidewalks that are to remain on either side of the reconstructed areas.

The sidewalks shall be constructed in accordance wi th Section 200-2.4 and Section 303 of the Standard Specifications, and as shown in APWA Standard Plans . Sidewalks shall be 4" thick over 4” crushed miscellaneous base (CMB). Construction of this item shall be coordinated with all other construction activities. For the existing structures to be remo ved, all edges shall be saw-cut. All fresh P.C.C. surfaces shall be protected from weather and from graffiti. Any damaged P.C.C. surfaces shall be repaired or at no additional cost to the City.

Concrete shall be Class 520-C-2500

To minimize inconvenience to traffic and the public in general, the Contractor shall schedule the conc rete placement to be completed no later than three (3) working days after the remo val operations . Safe and adequate pedestrian and vehicular movement at a nd around all construction sites shall be provided and maintained at all times. Approved barriers and signs (traffic flagging personnel, if necessary), shall be furnished and utilized by the Contractor. All work mentioned above shall be included in the unit pric e for this bid items.

PAYMENT

Payment for BID ITEM NO. 3 – REMOVAL AND REPLACEMENT OF UPLIFTE D SIDEWALK AT VARIOUS LOCATIONS PER APPENDIX A; 4” PCC OVER 4” CM B ; shall be per square foot (SF) of concrete placed and shall include full compensation for all labor, materials, tools equipment, transportation and incidentals necessary to do all the work involved thereof, complete, in place, and accepted.

SECTION F PAGE F-5

CITY OF CULVER CITY PZ-428 May 2026

BID ITEM NO. 4 – REMOVAL AND REPLACEMENT OF DRIVEWA Y APPROACH AT VARIOUS LOCAITONS PER EXHIBIT IN APPENDIX A; 4” PCC OVER 6” CMB

GENERAL

Removal and disposal of existing driveway and other material shall comply with Section 300 of the Standard Specifications and the guidelines described herein. Limits of the construction shall be marked and verified by the City Representative at each site prior to re moval. Said removal shall be adequate to replace driveway in a manner such that the driveway surface will have a straight grade when connecting the existing improvements on either side of the driveway to be constructed. All debris shall be disposed of properly and in accordance with local codes and ordinances. All materials to be removed shall be disposed of outsid e the right-of-way as specified in subsection 300-2 of SSPWC. Pavements shall be removed to neatly sawed edges as specified in subsection 300-2.9 of SSPWC. Debris shall be removed same-day and not left at job site or in public right of way. Removals of existing PCC improvements shall include any existing base and/or subbase materials to a depth necessary for the placement of CMB under proposed PCC improvements.

Locations, dimensions and depths of PCC driveway re movals per Exhibit in Appendix A .

All materials to be removed shall be disposed of ou tside the right-of-way as specified in subsection 3 00-2 of SSPWC. Pavements shall be removed to neatly saw ed edges as specified in subsection 300-2.9 of SSPWC. Removals shall comply with the Special Provisions p er Section 401-1, page E-24 & E-25.

Debris shall be removed same-day and not left at job site or in public right of way.

The cost to comply with the City’s Construction and Demolition Waste Management Plan shall be included in the unit or lump sum prices for the applicable i tems of work listed in the Bidder’s Proposal and no additional compensation will be allowed.

DRIVEWAY APPROACH CONSTRUCTION

The driveway approach shall be constructed in accor dance with Section 200-2.4 and Section 303 of the Standard Specifications, and as shown in APWA Stand ard Plans. Driveway approach shall be 8" thick P.C.C. over 6” crushed miscellaneous base (CMB). Co nstruction of this item shall be coordinated with a ll other construction activities. For the existing structures to be removed, all edges shall be saw-cut. All fresh P.C.C. surfaces shall be protected from weather and from graffiti. Any damaged P.C.C. surfaces shall be repaired or at no additional cost to the City.

Concrete shall be Class 560-C-3250.

To minimize inconvenience to traffic and the public in general, the Contractor shall schedule the conc rete placement to be completed no later than three (3) working days after the remo val operations . Safe and adequate pedestrian and vehicular movement at a nd around all construction sites shall be provided and maintained at all times. Approved barriers and signs (traffic flagging personnel, if necessary), shall be furnished and utilized by the Contractor. All work mentioned above shall be included in the unit pric e for this bid items.

Ting Fiber utility is located throughout the City a pproximately 6” to 12” deep. Contractor shall prote ct this utility in place. In the event the conduit or fiber line is damaged by the Contractor, the Contractor shall bear all costs for the repair or replacement of the util ity. The contractor shall meet with the City’s repr esentative in the field to verify the designated area of AC sl otcut to be excavated and reconstructed as shown on the plans. Asphalt concrete pavement shall conform to t he provisions of Section 203 and 302 of the Standar d Specifications, and shall be constructed to the lim its to match existing adjacent surface. The excavat ed area shall be properly prepared per provisions of S ection 302-5 of SSPWC for the construction of the A C pavement. Upon excavation and removal, the top laye r 6 inches of subgrade soil shall be compacted to 95% of maximum density prior to placing CMB or pavi ng. Asphalt Concrete shall be Type C2 PG-64-40 mix. The allowable placement of AC at 4” maximum pe r lift. Contractor to furnish and place 6” AC deepl ift slot pave over compacted CMB, as specified on Exhib its in Appendix B.

SECTION F PAGE F-6

CITY OF CULVER CITY PZ-428 May 2026

PAYMENT

Payment for BID ITEM NO. 4 – REMOVAL AND REPLACEMENT OF DRIVEWA Y APPROACH AT VARIOUS LOCAITONS PER EXHIBIT IN APPENDIX A; 4” PCC OVER 6” CMB ; shall be per square foot (SF) and shall include full compensation for all l abor, materials, tools equipment, transportation an d incidentals necessary to do all the work involved thereof, complete, in place, and accepted.

BID ITEM NO. 5 –REMOVE AND REPLACE PCC CURB & GUTTE R PER SPPWC STD NO. 120-3 AT

VARIOUS LOCATIONS

This contract bid item shall comply with Section 30 0- 2 “Unclassified Excavation” and Section 401 “Removal” of the Standard Specifications and these Special Provisions for demolition, roadway excavation and removal. Contractor to determine quantities of excavation and removals per information on plans an d cross sections as shown in Appendix A.

All materials to be removed shall be disposed of o utside the right-of-way as specified in subsection 300-2 of SSPWC. Pavements shall be removed to neatly saw ed edges as specified in subsection 300-2.9 of SSPWC. Removals shall comply with the Special Provisions p er Section 401-1, page E-24 & E-25.

Debris shall be removed same-day and not left at job site or in public right of way.

The contractor shall meet with the City’s represen tative in the field to verify the designated limits of curb and gutter to be removed and reconstructed as shown on the plans. Said removal shall be adequate to construct proposed improvements in a manner such th at the finished surface will have a straight grade when connecting the existing improvements. Removals of existing PCC improvements shall include any existing base and/or subbase materials to a depth n ecessary for the placement of CMB under proposed PCC improvements. Construction of proposed improvem ents shall be in a manner such that the finished surface will have a straight grade when connecting to the existing improvements.

Locations, dimensions and depths of PCC curb & gutt er removals per Exhibit in Appendix A .

PCC concrete pavement shall conform to the provisio ns of Section 201 and 303 of the Standard Specifications, and shall be constructed to the lim its to match existing adjacent surface. Concrete sh all be Class 560-C-3250.

Ting Fiber utility is located throughout the City a pproximately 6” to 12” deep. Contractor shall prote ct this utility in place. In the event the conduit or fiber line is damaged by the Contractor, the Contractor shall bear all costs for the repair or replacement of the util ity. The contractor shall meet with the City’s repr esentative in the field to verify the designated area of AC sl otcut to be excavated and reconstructed as shown on the plans. Asphalt concrete pavement shall conform to t he provisions of Section 203 and 302 of the Standar d Specifications, and shall be constructed to the lim its to match existing adjacent surface. The excavat ed area shall be properly prepared per provisions of S ection 302-5 of SSPWC for the construction of the A C pavement. Upon excavation and removal, the top laye r 6 inches of subgrade soil shall be compacted to 95% of maximum density prior to placing CMB or pavi ng. Asphalt Concrete shall be Type C2 PG-64-40 mix. The allowable placement of AC at 4” maximum pe r lift. Contractor to furnish and place 6” AC deepl ift slot pave over compacted CMB, as specified on Exhib its in Appendix B.

To minimize inconvenience to traffic and the public in general, the Contractor shall schedule the conc rete placement to be completed no later than three (3) working days after the remo val operations . Safe and adequate pedestrian and vehicular movement at a nd around all construction sites shall be provided and maintained at all times. Approved barriers and signs (traffic flagging personnel, if necessary), shall be furnished and utilized by the Contractor. All work mentioned above shall be included in the unit pric e for this bid items.

Payment for BID ITEM NO. 5 –REMOVE AND REPLACE PCC CURB & GUTTER PER SPPWC STD NO. 120-3 AT VARIOUS LOCATIONS shall be at the contract bid item price per linear foot (LF) price and shall SECTION F PAGE F-7

CITY OF CULVER CITY PZ-428 May 2026
include full compensation for all labor, materials, tools, equipment, transportation, and incidentals necessary to do all the work involved thereof complete, in place and accepted.

BID ITEM NO. 6 – REMOVE AND RECONSTRUCT MODIFIED PC C CURB RAMP OVER 6” PER

EXHIBIT B

Scope under this bid item includes removal of exist ing sidewalks and/or curb ramps and construction of new curb ramps as shown in the Exhibit in Appendix B. Scope includes:

 Removal of existing PCC improvements.
 Construction of PCC curb ramp per APWA Greenbook S tandard  Ramp shall be 4 inches PCC over 6 inches of crushe d miscellaneous base (CMB).  Concrete shall be Class 520-C-2500.
 Procurement and installation of detectable truncat ed domes

The work shall include formwork, concrete material, curing, protection testing, adjustment to match existing improvements. Refer to APPENDIX B for location.

Removal and disposal shall be according to the requirements as described in Section E, Special Provisions.

The cost to comply with the City’s Construction and Demolition Waste Management Plan shall be included in the unit or lump sum prices for the applicable i tems of work listed in the Bidder’s Proposal and no additional compensation will be allowed.

Failure to comply with any of the provisions of the CCMC may result in forfeiture of the Performance Security Deposit.

The contractor shall meet with the City’s represent ative in the field to verify the designated area of AC slotcut to be excavated and reconstructed as shown on the plans. Asphalt concrete pavement shall conform to the provisions of Section 203 and 302 of the Sta ndard Specifications, and shall be constructed to t he limits to match existing adjacent surface. The exca vated area shall be properly prepared per provision s of Section 302-5 of SSPWC for the construction of the AC pavement. Upon excavation and removal, the top layer 6 inches of subgrade soil shall be compacted to 95% of maximum density prior to placing CMB or paving. Asphalt Concrete shall be Type C2 PG-64-40 mix. The allowable placement of AC at 4” maximum per lift. Contractor to furnish and place 6” AC dee plift slot pave over compacted CMB, as specified on Exhibits in Appendix B.

PAYMENT

Payment for BID ITEM NO. 6 – REMOVE AND RECONSTRUCT MODIFIED PCC CURB RAMP OVER 6” PER EXHIBIT B; shall be per each (EA) and shall include full comp ensation for all labor, formwork, traffic control, materials, tools equipment, transportation , and incidentals necessary to do all the work invo lved thereof, complete, in place, and accepted.

BID ITEM NO. 7 – REMOVE AND RECONSTRUCT PCC CROSS G UTTER AND SPANDREL OVER 6”

CMB PER EXHIBIT IN APPENDIX B

This bid item includes the construction of PCC cros s gutter and spandrel as depicted on the Exhibit in Appendix B. The gutter and spandrel shall be constructed in accordance with Section 200-2.4 and Section 303 of the Standard Specifications, and as shown in 2021 APWA Standard Plan 122-3 and details in Appendix C. The cross gutter and spandrel shall be 8" PCC over 6” crushed miscellaneous base (CMB).

The PCC edge of cross gutter and spandrel shall match grade with adjacent pavement at all edges of cross gutter and spandrel. All fresh P.C.C. surfaces shal l be protected from weather and from graffiti. Any damaged P.C.C. surfaces shall be repaired at no add itional cost to the City. Concrete shall be Class 560- C-4000. Steel plates shall be in place to protect P CC until cross gutter and spandrel have reached des ign strength.

SECTION F PAGE F-8

CITY OF CULVER CITY PZ-428 May 2026

Ting Fiber utility is located throughout the City a pproximately 6” to 12” deep. Contractor shall prote ct this utility in place. In the event the conduit or fiber line is damaged by the Contractor, the Contractor shall bear all costs for the repair or replacement of the util ity. The contractor shall meet with the City’s repr esentative in the field to verify the designated area of AC sl otcut to be excavated and reconstructed as shown on the plans. Asphalt concrete pavement shall conform to t he provisions of Section 203 and 302 of the Standar d Specifications, and shall be constructed to the lim its to match existing adjacent surface. The excavat ed area shall be properly prepared per provisions of S ection 302-5 of SSPWC for the construction of the A C pavement. Upon excavation and removal, the top laye r 6 inches of subgrade soil shall be compacted to 95% of maximum density prior to placing CMB or pavi ng. Asphalt Concrete shall be Type C2 PG-64-40 mix. The allowable placement of AC at 4” maximum pe r lift. Contractor to furnish and place 6” AC deepl ift slot pave over compacted CMB, as specified on Exhib its in Appendix B.

Dowel into existing gutter with 2 #4 bars (24” long) 12” into existing cross gutter at equal spacing.

PAYMENT

Payment for BID ITEM NO. 7 – REMOVE AND RECONSTRUCT PCC CROSS GUTTER AND SPANDREL OVER 6” CMB PER EXHIBIT IN APPENDIX B ; shall be per square footage (SF) and shall includ e full compensation for all labor, materials, tools equipm ent, transportation and incidentals necessary to do all the work involved thereof, complete, in place, and accepted.

BID ITEM NO. 8 – REMOVE EXISTING TREE

Scope under this bid item includes removal of exist ing trees during construction. City Arborist, or li censed arborist chosen by contractor and approved by the C ity, reviews tree roots to determine tree health an d viability after sidewalk removals have been complet e. Therefore, tree locations may not always be know n prior to sidewalk removal activities, and tree quan tity is to be determined. This bid item is to estim ate the removal of trees 18” to 48” in diameter. The exact tree size, location and species will be known durin g construction. Trees shall be removed and stumps shall be grinded 36” below proposed finished grade.

Removals shall comply with the Special Provisions per Section 401-1, page E-24 & E-25. Debris shall be removed same-day and not left at job site or in public right of way.

PAYMENT

Payment for BID ITEM NO. 8 – REMOVE EXISTING TREE ; shall be per unit quantity (EA) and shall include full compensation for all labor, formwork, traffic control, materials, tools equipment, transportation , and incidentals necessary to do all the work involved thereof, complete, in place, and accepted.

=================================================== ============================= -End of Section F-

CITY OF CULVER CITY PZ-428 May 2026

APPENDIX A

Sidewalk, Curb Ramp, and Driveway Approach Exhibit
# Location Width (FT) Length (FT) SF
1 3318 Helms Ave 4 44 176 63
2 9025 Lucerne Ave 4 64 256
3 4137 Duquesne Ave 4 45 180
4 4017 Lincoln Ave 5 27 135
5 4023 Lincoln Ave 5 23 115
6 4077 Lincoln Ave 5 10 50
7 9929 Braddock Dr 4 17 68
8 9999 Braddock Dr 5 35 175
9 4125 Madison Ave 5 10 50
10 4131 Madison Ave 5 5 25
11 4234 Madison Ave 5 30 150
12 4240 Madison Ave 5 13 65
13 4224 Madison Ave 5 13 65
14 4385 Mentone Ave 4 44 176 91
15 4391 Mentone Ave 4 53 212 91
16 4397 Mentone Ave 4 54 216 91
17 4401 Mentone Ave 4 40 160
18 10728 Oregon Ave 4 20 80
19 10731 Oregon Ave 4 32 128
20 10737 Oregon Ave 4 23 92
21 10740 Oregon Ave 4 5 20
22 5175 Jordan Way 5 10 50
23 3864 Girard Ave 4 30 120
24 3873 Girard Ave 5 29 145
25 3872 Huron Ave 5 23 115
26 3911 Huron Ave 5 9 45
27 11116 Matteson Ave 4 26 104 10
28 11051 Matteson Ave 4 33 132
29 3944 Tuller Ave 4 44 176
30 3938 Tuller Ave 4 19 76
31 3934 Tuller Ave 4 39 156
32 11049 Barman Ave 5 35 175 53 140
33 4178 Center St 4 25 100
34 4182 Center St 4 5 20
35 4046 Minerva Ave 4 18 72
36 4253 Coolidge Ave 4 18 72
37 4248 Coolidge Ave 4 13 52
38 4252 Coolidge Ave 4 23 92
39 11231 Braddock Dr 5 28 140
40 11224 Braddock Dr 5 12 60
41 11266 Garfield Ave 4 28 112
42 11210 Huntley Pl 4 31 124 82
43 11214 Huntley Pl 4 17 68 46
44 11216 Huntley Pl 4 9 36 46
Sidewalk Removal & Replacement Curb LF DWY
SF
45 11213 Huntley Pl 4 13 52
46 11215 Huntley Pl 4 31 124
47 11225 Huntley Pl 4 26 104
48 11245 Huntley Pl 4 35 140
49 11115 McDonald St 4 26 104
50 11131 McDonald St 4 8 32
51 11207 Culver Park Dr 4 11 44
52 11219 Patom Dr 4 33 132 45
53 11220 Patom Dr 4 20 80
54 11225 Patom Dr 4 35 140 126
55 11226 Patom Dr 0 72
56 11231 Patom Dr 4 8 32 42
57 5450 Diller Ave 4 46 184
58 11453 Patom Dr 4 8 32
59 11493 Patom Dr 4 38 152
60 11505 Patom Dr 4 61 244
61 11219 McDonald St 4 33 132
62 11266 McDonald St 4 42 168
63 11273 McDonald St 4 32 128
64 5140 Purdue Ave 4 35 140
65 11659 McDonald St 4 60 240 35 273
66 5427 Emporia Ave 4 49 196
67 6400 Green Valley 5 199 995
Total 8431 98 1208

CITY OF CULVER CITY PZ-428 May 2026

APPENDIX B

Hillside Cemetery Entrance Exhibit

Appendix B – Hillside Cemetery Entrance Exhibit

Appendix B – Hillside Cemetery Entrance Exhibit

Appendix B – Hillside Cemetery Entrance Exhibit

Appendix B – Hillside Cemetery Entrance Exhibit

Appendix B – Hillside Cemetery Entrance Exhibit

Appendix B – Hillside Cemetery Entrance Exhibit

Appendix B – Hillside Cemetery Entrance Exhibit

Appendix B – Hillside Cemetery Entrance Exhibit

Appendix B – Hillside Cemetery Entrance Exhibit

Appendix B – Hillside Cemetery Entrance Exhibit

Appendix B – Hillside Cemetery Entrance Exhibit

Appendix B – Hillside Cemetery Entrance Exhibit

Appendix B – Hillside Cemetery Entrance Exhibit

Appendix B – Hillside Cemetery Entrance Exhibit

Appendix B – Hillside Cemetery Entrance Exhibit

Appendix B – Hillside Cemetery Entrance Exhibit

Appendix B – Hillside Cemetery Entrance Exhibit

Appendix B – Hillside Cemetery Entrance Exhibit

Appendix B – Hillside Cemetery Entrance Exhibit

Appendix B – Hillside Cemetery Entrance Exhibit

CITY OF CULVER CITY PZ-428 May 2026

APPENDIX C

Construction Standard Details

CITY OF CULVER CITY PZ-428 May 2026

APPENDIX D
Public Works EPO: Services Agreement and C&D Fees

CITY OF CULVER CITY PZ-428 May 2026

APPENDIX E
Fiber Line Microtrench Detail

CORBEL CONFIDENTIAL

NOT TO SCALE

CITY OF CULVER CITYDEPARTMENT OF PUBLIC WORKSENGINEERING DIVISION

MICROTRENCHING

EXISTING BASE
1" MIN TO 2"

MAX WIDTH

INSTALLED

CONDUIT

CORBEL TRENCH FILL

OVER A THIN LAYER OF

PEA GRAVELBOTTOM

OF TRENCH
NOTES:

ALL WORK SHALL BE CONSTRUCTED IN ACCORDANCE TO THE LATEST STANDARD SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION (SSPWC) "GREENBOOK".

GENERAL

1. MICRO-TRENCHING SHALL ONLY BE USED TO INSTALL TELECOMMUNICATION CONDUITS.

CONTRACTOR SHALL CONTACT UNDERGROUND SERVICE ALERT (U.S.A) AT LEAST 48 HOURS PRIOR TO START OF WORK AT 8-1-1, OR TOLL FREE AT 1-800-422-4133. THE CONTRACTOR SHALL FURTHER SUPPLEMENT THE FINDINGS OF U.S.A. TO

DETERMINE THE EXACT LOCATIONS AND DEPTHS OF ALL UTILITIES BY USING A MOBILE GROUND PENETRATING RADAR SYSTEM. THE CONTRACTOR SHALL POTHOLE ALL CROSSING UTILITIES AND PARALLEL UTILITIES WITHIN 18-INCHES OF THE PROPOSED ALIGNMENT TO A DEPTH OF 6-INCHES BELOW THE BOTTOM OF THE MICRO-TRENCH, TO DETERMINE THE EXISTING UTILITY ALIGNMENT AND ELEVATION. POTHOLES SHALL BE IMMEDIATELY BACKFILLED AND COMPACTED IN ACCORDANCE WITH THE SPECIFICATIONS OR RESTORED AS DIRECTED BY THE ENGINEER.

4. IF EXISTING UTILITIES ARE DAMAGED, THE CONTRACTOR SHALL IMMEDIATELY NOTIFY THE INSPECTOR, ENGINEER AND

UTILITY OWNER TO PERFORM THE REPAIRS PROMPTLY ACCORDING TO THEIR REQUIREMENT AND PER ASSOCIATED CITY PERMITS.

SHEET 1 OF 2 SHEETS

APPROVED

CHECKED

PREPARED

STANDARD PLAN

MICROTRENCHING SECTION
(INTEGRAL CURB AND GUTTER SHOWN)

EXISTING ASPHALT

CONCRETE PAVEMENT

THICKNESS VARIESRECOMMENDATIONS
12"
1/13/2021

2. ANY VARIATION TO THIS STANDARD WILL REQUIRE APPROVAL BY THE CITY AS PART OF THE RIGHT-OF-WAY PERMIT APPLICATION.

3. THE CONTRACTOR SHALL IDENTIFY ALL EXISTING UTILITIES, INCLUDING SERVICE CONNECTIONS IN THE FIELD. THE

TRENCH CAP WITH
FASTPATCH 8400 PER

MANUFACTURER'S

EXISTING CURB

AND GUTTER

NATIVE MATERIAL

CITY OF CULVER CITYDEPARTMENT OF PUBLIC WORKSENGINEERING DIVISION

MICROTRENCHING

LIMITS OF REMOVALS, TRENCH WIDTH, AND LOCATION

5. THE MICRO-TRENCH SHALL BE CONSTRUCTED WITH CONTINUOUS UNIFORM STRAIGHT AND NEAT EDGES ADJACENT TO CURB OR GUTTER EDGE.

6. MICRO-TRENCH ALIGNMENTS SHALL CONSIST OF RUNS PARALLEL TO THE CENTERLINE OF THE STREET. STREET CROSSING MAY BE DONE PROVIDED THE ALIGNMENT IS PERPENDICULAR TO THE STREET CENTERLINE TO THE EXTENT POSSIBLE.

7. THE MICRO-TRENCH WIDTH SHALL BE A MINIMUM OF 1-INCH AND A MAXIMUM OF 2-INCHES.

8. MICRO-TRENCHING MAY BE PERMITTED UPON THE ENGINEER'S DISCRETION ON SPECIAL PAVEMENTS SUCH AS DECORATIVE ASPHALT PAVING, AND THROUGH EXITING IMPROVEMENTS SUCH AS PERPENDICULAR TO SPEED BUMPS. SPECIAL PAVEMENT AND EXISTING IMPROVEMENTS SHALL BE RESTORED IN KIND AS APPROVED BY THE ENGINEER. HOWEVER, MICRO-TRENCHING

THROUGH EXISTING CURB, GUTTER, CROSS GUTTER, BUS PAD, SIDEWALK, FLOATING CURB EXTENSION, BUS BULB, TRUCK PILLOW, RAISED CROSSWALK, ISLAND, MINI-ROUNDABOUT, OR SIMILAR ELEMENTS IS NOT PERMITTED.

11. ANCHORS/SPACERS SHALL BE PLACED AT A MAXIMUM OF 10-FEET APART ALONG THE ALIGNMENT TO ENSURE THE CONDUIT DOES

NOT RISE FROM THE BOTTOM OF THE MICRO-TRENCH AND DOES NOT TOUCH THE WALLS OF THE MICRO-TRENCH DURING INSTALLATION.

VAULTS AND SERVICE CONNECTIONS:

SETTLED OR DAMAGED. REMOVAL LIMITS OF SIDEWALK SHALL FOLLOW APPLICABLE STANDARDS AND REQUIREMENTS AS

IDENTIFICATION
SHEET 2 OF 2 SHEETS

APPROVED

CHECKED

PREPARED

STANDARD PLAN
APPROVED BY THE ENGINEER. SIDEWALK SHALL BE REPLACE FROM SCORELINE TO SCORELINE. 1/13/2021

12. TRENCH LOCATION SHALL BE AT EDGE OF CURB AND GUTTER OUTSIDE OF THE DIRECT PATH OF TRAFFIC PER CROSS SECTION. PAVEMENT SURFACE RESTORATION NEAR BOTTOM OF ACCESS RAMPS SHALL BE FLUSH WITH EDGE OF GUTTER (NO LIP). THE LOCATION OF MICRO- TRENCH IN RELATION TO THE CURB AND GUTTER SHALL NOT DEVIATE ALONG ITS ALIGMENT UNLESS OTHERWISE APPROVED BY THE CITY.

10. THE INVERT OF THE CONDUIT SHALL BE INSTALLED AT DEPTH OF 12-INCHES BELOW THE EXISTING AC PAVEMENT SURFACE.

16. CONNECTION TO SERVICE LATERALS, JUNCTION BOXES, ETC., SHALL BE DONE SUCH THAT CURB AND GUTTER IS NOT DISTURBED,

17. THE TOP OF ALL VAULTS WHETHER IN THE SIDEWALK OR PARKWAY SHALL BE FLUSH TO ADJACENT GRADE.

13. IF MICRO-TRENCH CONFLICTS WITH SPANDREL, CROSS GUTTER, OR PCC STREET PAVEMENT, THE ENTIRE SECTION SHALL BE REPLACED JOINT TO JOINT PER CITY OF CULVER CITY STANDARD OR AS OTHERWISE APPROVED BY THE CITY ENGINEER.

14. PLACE TOP 1/4 INCH WITH STERLING LLOYD SAFETRACK MTI OR APPROVED EQUAL (COLOR TO MATCH EXISTING GRADE).

15. ONLY ONE MICRO-TRENCH PER SIDE OF THE STREET IS ALLOWED.

9. MICRO-TRENCH SHALL HAVE A COVER OF 8-INCH MINIMUM.

18. EACH MICRO-TRENCH SHALL BE IDENTIFIED WITH A METAL IDENTIFICATION TAG LISTING THE OWNER, YEAR OF CONSTRUCTION, AND INCLUDE THE WORDS "NOT A SURVEY POINT". IF THE WORK IS MORE THAN 50 FEET IN LENGTH, PLACE THE TAG NEAR EACH END OF THE MICRO-TRENCH AND AT INTERVALS NOT TO EXCEED 50 FEET.

19. INSTALL 3 INCHES WIDE (FOLDED) MARKINGS SERVICES INCORPORATED (MSI) OR APPROVED EQUAL NON-DETECTABLE WARNING IDENTIFICATION TAPE PER APWA COLOR CODE SPECIFICATION, 3 INCHES MAXIMUM ABOVE CONDUIT.

20. INSTALL 18 AWG INSULATED TRACER COPPER WIRE AT THE BOTTOM OF THE TRENCH OR APPROVED EQUAL. ANY VARIATION OF THE DETECTABLE TRACER WIRE WILL REQUIRE CITY ENGINEER APPROVAL.