RESOLUTION NO. ____

A RESOLUTION OF THE CUPERTINO CITY COUNCIL
APPROVING AN ARCHITECTURAL AND SITE APPROVAL PERMIT TO
DEMOLISH APPROXIMATELY 44,000 SQ. FT. OF EXISTING COMMERCIAL SPACE AND THE CONSTRUCTION OF THREE MIXED‐USE BUILDINGS WITH
APPROXIMATELY 41,268 SQ. FT. OF COMMERCIAL SPACE AND 206 CONDOMINIUM UNITS AND REQUESTING A DENSITY BONUS, AND DENSITY BONUS WAIVERS FOR HEIGHT, SETBACKS, AND COMMON OPEN SPACE LOCATED AT 10145 N. DE ANZA BLVD, 10118 BANDLEY DRIVE (APN: 326‐34‐066, 326‐34‐043)

SECTION I:  PROJECT DESCRIPTION
Application No.:  ASA‐2022‐001
Applicant:   Larry Wang (Tectonic Builders Corp.)
Property Owner:  De Anza Venture, LLC
Location:  10145 N. De Anza Blvd, 10118 Bandley Drive (APN: 326‐34‐066, 326‐ 34‐043)

SECTION II:  FINDINGS FOR ARCHITECTURAL AND SITE APPROVAL:

WHEREAS, the Planning Commission of the City of Cupertino received an application for an Architectural and Site Approval Permit as described in Section I of this resolution; and
WHEREAS, after consideration of evidence contained in the entire administrative record, at the public hearing on September 6, 2016, the City Council adopted Resolution No. 16‐ 091, adopting a Mitigated Negative Declaration for the Marina Development; and WHEREAS,  environmental  analysis  and  peer  reviews  were  conducted  by  Placeworks, Inc.  pursuant  to  the  requirements  of  CEQA,  finding  that  no  new  or  substantially increased significant environmental effects; and
WHEREAS, on November 10, 2022 the Planning Commission recommended on a 5‐0 vote that the City Council adopt the Addendum to the Mitigated Negative Declaration (EA‐ 2015‐05)  and  approve  the  Development  Permit  (DP‐2022‐001)  in  substantially  similar form to the Resolution presented (Resolution No. 6964), approve the Architectural and Site  Approval  Permit  (ASA‐2022‐002)  in  substantially  similar  form  to  the  Resolution presented(Resolution  No.  6965),  approve  the  Tree  Removal  Permit  (TR‐2022‐026)  in substantially similar form to the Resolution presented (Resolution No. 6967) and approve the Vesting Tentative Map  (TM‐2022‐003), in substantially similar form to the Resolution presented (Resolution No. 6966); and
WHEREAS, all necessary public notices having been given as required by the Procedural Ordinance  of  the  City  of  Cupertino  and  the  Government  Code,  and  the  Planning Commission  held  at  least  one  public  hearing  in  regard  to  this  application,  and  on December 6, 2022 the City Council held a public hearing to consider the Development Permit; and
WHEREAS, the City Council of the City of Cupertino is the decision‐making body for this Resolution; and
WHEREAS, the applicant has met the burden of proof required to support the application for a Architectural and Site Approval Permit.

WHEREAS, the analysis in the Addedum prepared by Placeworks, Inc. indicates that the proposed  project  would  not  require  major  revisions  to  the  Mitigated  Negative Declaration  adopted  on  September  6,  2016,  due  to  new  or  substantially  increased significant environmental effects. Furthermore, there have been no substantial changes with  respect  to  the  circumstances  under  which  these  minor  modifications  would  be undertaken  that  would  require  major  revisions  of  the  Adopted  Mitigation  Negative Declaration due to new or substantially increased significant environmental effects, and there  has  been  no  discovery  of  new  information  of  substantial  importance  that  would trigger or require major revisions to the Mitigated Negative Declaration due to new or substantially increased significant environmental effects.

WHEREAS,  the  adopted  Mitigated  Negative  Declaration  adequately  identifies  all environmental effects and adequate mitigation measures for the proposed modifications to the previously approved project. Therefore, no subsequent or supplemental Mitigated Negative Declaration is required prior to approval of the proposed project.

WHEREAS, the City Council finds as follows with regard to this application:

1. The proposal, at the proposed location, will not be detrimental or injurious to property or  improvements  in  the  vicinity,  and  will  not  be  detrimental  to  the  public  health, safety, general welfare, or convenience;
Given  that  the  project  is  consistent  with  the  General  Plan  and   Zoning  Ordinance;  all mitigation measures identified in the Initial Study/Mitigated Negative Declaration addendum that  are  within  the  responsibility  and  jurisdiction  of  the  City  have  been  adopted  and incorporated into the project to mitigate potential impacts to a less than significant level, the project will not be detrimental or injurious to property or improvements in the vicinity, and will not be detrimental to the public health, safety, general welfare, or convenience.

2. The proposal is consistent with the purposes of Chapter 19.168, the General Plan, any specific plan, zoning ordinances, applicable planned development permit, conditional use permits, variances, subdivision maps or other entitlements to use which regulate the subject property including, but not limited to, adherence to the following specific criteria:
a) Abrupt changes in building scale should be avoided. A gradual transition related to height and bulk should be achieved between new and existing buildings.

The proposed project is a redevelopment of a commercial site with three mixed‐use  multi‐ story high‐density structures. The development is surrounded by multi‐storied structures with the Aloft Hotel to the north and an Apple office building adjacent to the south. The site  is  bordered  by  multi‐story  structures  primarily,  with  some  taller  single  story structures  (Apple  Cafeteria)  to  the  north.  There  are  other  single  story  commercial structures across  N.  De  Anza  Blvd,  to  the  east,  which  are over  100  feet  away from  the proposed structures. There is landscaping proposed at the perimeter which will help mask some  of  the  bulk  of  the  proposed  buildings.  There  are  also  two  taller  four  story  office building  located  directly  south‐east  of  the  proposed  project.  While  the  remaining  four structures on the site are single story, these are commercial buildings, and the proposed structures  are  between  10  feet  and  25  feet  from  the  existing  buildings  with  adequate landscaping buffer and existing trees.
b) In  order  to  preserve  design  harmony  between  new  and  existing  building  and  in order to preserve and enhance property values, the materials, textures and colors of new building should harmonize with adjacent development by being consistent or  compatible  with  design  and  color  schemes  with  the  future  character  of  the neighborhoods and purposes of the zone in which they are situated. The location, height  and  materials  of  walls,  fencing,  hedges  and  screen  planting  should harmonize with adjacent development. Unsightly storage areas, utility installations and unsightly elements of parking lots should be concealed. The planting of ground cover or various types of pavements should be used to prevent dust and erosion, and  the  unnecessary  destruction  of  existing  healthy  trees  should  be  avoided.

Lighting  for  development  should  be  adequate  to  meet  safety  requirements  as specified by the engineering and building departments, and provide shielding to prevent spill‐over light to adjoining property owners.

The  design  quality  of  the  development  is  consistent  with  the  high‐quality  standards encouraged by City Staff. The mixed‐use buildings meet the design qualities of a Modern design  development.  The  architectural  style  is  consistent  throughout  the  development.

Further, the planting plan is consistent with the intent of the Heart of the City Specific Plan guidelines. Unsightly uses such as loading and trash pickup have been placed within the buildings away from view of neighboring uses. Utility installation has been designed to  be  screened  by  landscaping  and  or  incorporated  into  the  building  design.  The  final lighting  for  the  development  will  be  reviewed  as  part  of  the  review  of  the  project construction documents to ensure that they meet safety requirements while avoiding spill‐ over light to adjacent properties.
c) The  number,  location,  color,  size,  height,  lighting  and  landscaping  of  outdoor advertising signs and structures shall minimize traffic hazards and shall positively affect  the  general  appearance  of  the  neighborhood  and  harmonize  with  adjacent development; and
Signage approval is not included in this application.
d) With  respect  to  new  projects  within  existing  residential  neighborhoods,  new development should be designed to protect residents from noise, traffic, light and visually intrusive effects by use of buffering, setbacks, landscaping, walls and other appropriate design measures.

The  project  does  not  abut  any  existing  residential  development.  The  multi‐family development to the north‐east of the project site, across Alves, will be buffered from any impacts because the project has been designed to plant further street tress along the frontage and has been designed with adequate parking on‐site. The buildings have been designed with setbacks from the curb line as required by the General Plan and Heart of the City Specific Plan.

NOW, THEREFORE, BE IT RESOLVED:

That  after  careful  consideration  of  maps,  facts,  exhibits,  testimony  and  other  evidence submitted in  this  matter  and  the  MND  Addendum,  subject  to  the  conditions  which  are enumerated in this Resolution, beginning on PAGE 4 herein, and subject to the conditions contained in all other Resolutions approved for this Project, The application for an Architectural and Site Approval, Application No. ASA‐2022‐001, is hereby approved, and that the subconclusions upon which the findings and conditions specified  in  this  Resolution  are  based  are  contained  in  the  Public  Hearing  record concerning Application no. ASA‐2022‐001 as set forth in the Minutes of the City Council Meeting of December 6, 2022 Meeting, and are incorporated by reference as though fully set forth herein.

SECTION  III:   CONDITIONS  ADMINISTERED  BY  THE  COMMUNITY DEVELOPMENT DEPT.

1. APPROVED EXHIBITS
Approval is based on the plan set dated July 27, 2022 consisting of 91 sheets labeled as Marina Plaza, A0.0 – A11.0, T‐01 – T‐03, C0.1 – C4.3, JT‐1 – JT‐3, L1.01 – L3.05, and  TR0.1 – TR0.9, drawn by Tectonic Builders, Giuliani & Kull, Vizion Utility, and JETT Landscaping, except as may be amended by conditions in this resolution.

2. ACCURACY OF PROJECT PLANS
The applicant/property owner is responsible to verify all pertinent property data including  but  not  limited  to  property  boundary  locations,  building  setbacks, property  size,  building  square  footage,  any  relevant  easements  and/or construction records. Any misrepresentation of any property data may invalidate this approval and may require additional review.

3. CONCURRENT APPROVAL CONDITIONS
The conditions of approval contained in file nos. TR‐2022‐026, TM‐2022‐003, and DP‐ 2022‐001 shall applicable to this approval.

4. ANNOTATION OF THE CONDITIONS OF APPROVAL
The conditions of approval set forth shall be incorporated into and annotated on the first page of the building plans.

5. FINAL ARCHITECTURAL DETAILS AND EXTERIOR BUILDING MATERIALS The  final  building  exterior  plan  shall  closely  resemble  the  details  shown  on  the original  approved  plans. The  final  building  design  and  exterior  treatment  plans (including  but  not  limited  to  details  on  exterior  color,  materials,  architectural treatments,  doors,  windows,  lighting  fixtures,  and/or  embellishments)  shall  be reviewed and approved by the Director of Community Development prior to issuance of building permits and through an in‐field mock‐up of colors prior to application to ensure quality and consistency. Any exterior changes determined to be substantial by the Director of Community Development shall either require a modification to this permit or a new permit based on the extent of the change.

6. LANDSCAPE INSTALLATION REPORT
The project is subject to all provisions delineated in the Landscape Ordinance (CMC, Chapter  14.15).   A  landscape  installation  audit  shall  be  conducted  by  a  certified landscape  professional  after  the  landscaping  and  irrigation  system  have  been installed.  The  findings  of  the  assessment  shall  be  consolidated  into  a  landscape installation report.

The  landscape  installation  report  shall  include,  but  is  not  limited  to:  inspection  to confirm  that  the  landscaping  and  irrigation  system  are  installed  as  specified  in  the landscape and irrigation design plan, system tune‐up, system test with distribution uniformity, reporting overspray or run‐off that causes overland flow, and preparation of an irrigation schedule.

The  landscape  installation  report  shall  include  the  following  statement:  “The landscape and irrigation system have been installed as specified in the landscape and irrigation design plan and complies with the criteria of the ordinance and the permit.”

7. LANDSCAPE AND IRRIGATION MAINTENANCE
Per the Landscape Ordinance (CMC, Chapter 14.15), a maintenance schedule shall be established  and  submitted  to  the  Director  of  Community  Development  or  his/her designee,  either  with  the  landscape  application  package,  with  the  landscape installation report, or any time before the landscape installation report is submitted. a. Schedules should take into account water requirements for the plant establishment period and water requirements for established landscapes. b. Maintenance shall include, but not be limited to the following: routine inspection; pressure testing, adjustment and repair of the irrigation system; aerating and de‐ thatching turf areas; replenishing mulch; fertilizing; pruning; replanting of failed plants; weeding; pest control; and removing obstructions to emission devices. c. Failed plants shall be replaced with the same or functionally equivalent plants that may  be  size‐adjusted  as  appropriate  for  the  stage  of  growth  of  the  overall installation.  Failing  plants  shall  either  be  replaced  or  be  revived  through appropriate  adjustments  in  water,  nutrients,  pest  control  or  other  factors  as recommended by a landscaping professional.

8. LANDSCAPE PROJECT SUBMITTAL
Prior  to  issuance  of  building  permits,  the  applicant  shall  submit  a  full  Landscape Documentation  Package,  per  sections  14.15.050  A,  B,  C,  and  D  of  the  Landscape Ordinance,  for  projects  with  landscape  area  500  square  feet  or  more  or  elect  to submit a Prescriptive Compliance Application per sections 14.15.040 A, B, and C for projects  with  landscape  area  between  500  square  feet  and  2,500  square  feet.  The Landscape Documentation Package or Prescriptive Compliance Application shall be reviewed  and  approved  to  the  satisfaction  of  the  Director  of  Community Development prior to issuance of building permits, and additional requirements per sections 14.15.040 D, E, F, and G or 14.15.050 E, F, G, H, and I will be required to be reviewed and approved prior to final inspections.

9. SOIL ANALYSIS REPORT
A  soils  analysis  report  shall  document  the  various  characteristics  of  the  soil  (e.g. texture,  infiltration  rate,  pH,  soluble  salt  content,  percent  organic  matter,  etc)  and provide  recommendations  for  amendments  as  appropriate  to  optimize  the productivity and water efficiency of the soil.

The  soil  analysis  report  shall  be  made  available  to  the  professionals  preparing  the landscape and irrigation design plans in a timely manner either before or during the design process. A copy of the soils analysis report shall be submitted to the Director of Community Development as part of the landscape documentation package.

10. LANDSCAPE AND IRRIGATION PLANS
The applicant shall submit detailed landscape and irrigation plans to be reviewed and approved  by  Community  Development  prior  to  issuance  of  building  permits.   The landscape plan shall include water conservation and pesticide reduction measures in conformance  with  Chapter  14.15,  Landscape  Ordinance,  and  the  pesticide  control measures  referenced  in  Chapter  9.18,  Stormwater  Pollution  Prevention  and Watershed Protection, of the Cupertino Municipal Code.

11. SIGN PROGRAM
A sign program is required for this project.   The sign program shall be approved by the Director of Community Development prior to issuance of sign permits.

12. SITE IMPROVEMENTS
All proposed site improvements shall be completed prior to final occupancy of any structures approved in conjunction with the project.

13. TRANSFORMERS
Electrical transformers, telephone cabinets and similar equipment shall be placed in underground  vaults.   The  developer  must  receive  written  approval  from  both  the Public  Works  Department  and  the  Community  Development  Department  prior  to installation  of  any  above  ground  equipment.   Should  above  ground  equipment  be permitted by the City, equipment and enclosures shall be screened with fencing and landscaping  such  that  said  equipment  is  not  visible  from  public  street  areas,  as determined by the Community Development Department.  Transformers shall not be located in the front or side building setback area.

14. TREE PROTECTION
As part of the demolition or building permit drawings, a tree protection plan shall be prepared by a certified arborist for the trees to be retained.  In addition, the following measures shall be added to the protection plan:
 For  trees  to  be  retained,  chain  link  fencing  and  other  root  protection  shall  be installed around the dripline of the tree prior to any project site work.  No parking or vehicle traffic shall be allowed under root zones, unless using buffers approved by the Project Arborist.
 No trenching within the critical root zone area is allowed.  If trenching is needed in the vicinity of trees to be retained, the City’s consulting arborist shall be consulted before any trenching or root cutting beneath the dripline of the tree.  Wood chip mulch shall be evenly spread inside the tree projection fence to a four‐ inch depth.
 Tree protection conditions shall be posted on the tree protection barriers.  Retained trees shall be watered to maintain them in good health.  A covenant on the property shall be recorded that identifies all the protected trees, prior to final occupancy.

The tree protection measures shall be inspected and approved by the certified arborist prior to issuance of building permits. The City’s consulting arborist shall inspect the trees to be retained and shall provide reviews prior to issuance of demolition, grading or  building  permits.   A  report  ascertaining  the  good  health  of  the  trees  mentioned above shall be provided prior to issuance of final occupancy.

15. UTILITY STRUCTURE PLAN
Prior to issuance of building permits, the applicant shall work with staff to provide a detailed utility plan to demonstrate screening or undergrounding of all new utility structures [including, but not limited to backflow preventers (BFP), fire department connections (FDC), post‐indicator valves (PIV), and gas meters] to the satisfaction of the  Director  of  Community  Development,  Public  Works,  Fire  Department,  and applicable utility agencies.

16. CONSULTATION WITH OTHER DEPARTMENTS
The applicant is responsible to consult with other departments and/or agencies with regard  to  the  proposed  project  for  additional  conditions  and  requirements.   Any misrepresentation  of  any  submitted  data  may  invalidate  an  approval  by  the Community Development Department.

17. INDEMNIFICATION
As part of the application, to the fullest extent permitted by law, the applicant shall agree  to  indemnify,  defend  with  the  attorneys  of  the  City’s  choice,  and  hold harmless  the  City,  its  City  Council,  and  its  officers,  employees,  and  agents (collectively,  the  “indemnified  parties”)  from  and  against  any  liability,  claim, action,  cause  of  action,  suit,  damages,  judgment,  lien,  levy,  or  proceeding (collectively referred to as “proceeding”) brought by a third party against one or more of the indemnified parties or one or more of the indemnified parties and the applicant related to any Ordinance, Resolution, or action approving the project, the  related  entitlements,  environmental  review  documents,  finding  or determinations, or any other permit or approval authorized for the project. The indemnification  shall  include  but  not  be  limited  to  damages,  fees,  and  costs awarded against the City, if any, and cost of suit, attorneys’ fees, and other costs, liabilities,  and  expenses  incurred  in  connection  with  such  proceeding  whether incurred  by  the  Applicant,  the  City,  or  the  parties  initiating  or  bringing  such proceeding.

The  applicant  shall  agree  to  (without  limitation)  reimburse  the  City  its  actual attorneys’ fees and costs incurred in defense of the litigation. Such attorneys’ fees and  costs  shall  include  amounts  paid  to  the  City’s  outside  counsel  and  shall include City Attorney time and overhead costs and other City staff overhead costs and  any costs directly related to  the litigation reasonably incurred by City.  The applicant  shall  likewise  agree  to  indemnify,  defend,  and  hold  harmless  the indemnified  parties  from  and  against  any  damages,  attorneys’  fees,  or  costs awards, including attorneys’ fees awarded under Code of Civil Procedure section 1021.5, assessed or awarded against the indemnified parties. The Applicant shall cooperate with the City to enter a Reimbursement Agreement to govern any such reimbursement.

The Applicant shall agree to (without limitation) reimburse the City for all costs incurred in additional investigation or study of, or for supplementing, redrafting, revising, or amending, any document (such as an Environmental Impact Report, negative declaration, specific plan, or general plan amendment) if made necessary by  proceedings  challenging  the  project  approvals  and  related  environmental review, if the applicant desires to continue to pursue the project.

The Applicant shall agree that the City shall have no liability to the Applicant for business interruption, punitive, speculative, or consequential damages.

18. NOTICE OF FEES, DEDICATIONS, RESERVATIONS, OR OTHER EXACTIONS The  Conditions  of  Project  Approval  set  forth  herein  may  include  certain  fees, dedication requirements, reservation requirements, and other exactions.  Pursuant to Government Code Section 66020(d) (1), these Conditions constitute written notice of a  statement  of  the  amount  of  such  fees,  and  a  description  of  the  dedications, reservations,  and  other  exactions.   You  are  hereby  further  notified  that  the  90‐day approval period in which you may protest these fees, dedications, reservations, and other exactions, pursuant to Government Code Section 66020(a), has begun.   If you fail to file a protest within this 90‐day period complying with all of the requirements of Section 66020, you will be legally barred from later challenging such exactions.

PASSED  AND  ADOPTED  at  a  regular  meeting  of  the  City  Council  of  the  City  of Cupertino this 6th day of December, 2022, by the following vote:

Members of the City Council

AYES:

NOES:

ABSENT:

ABSTAIN:

SIGNED:

________
Darcy Paul, Mayor
City of Cupertino

________________________
Date
ATTEST:

________________________

Kirsten Squarcia, City Clerk

________________________
Date