SHEET OF REVISIONS

IMPROVEMENT PLANS FOR

SERVICE CENTER SECURITY GATE PROJECT
CALIFORNIACUPERTINOFile:

Scale:

Proj. Engr:

Checked:

Drawn:

Designed:

Date: 2.24.2023
RJL
LFH
RJL
RJL
APPR.CITY
DATEAPPR.DATE
DESIGN
BY
DESIGN
SAFETY OF ALL PERSONS AND PROPERTY; THAT THIS REQUIREMENT SHALL APPLY CONTINUOUSLY AND NOT BE LIMITED TO NORMAL WORKING HOURS; AND THAT THE CONTRACTOR

CONTRACTOR AGREES THAT HE SHALL ASSUME SOLE AND COMPLETE RESPONSIBILITY FOR JOB SITE CONDITIONS DURING THE COURSE OF CONSTRUCTION OF THIS PROJECT, INCLUDING

SHALL DEFEND, INDEMNIFY AND HOLD THE OWNER AND THE ENGINEER HARMLESS FROM ANY AND ALL LIABILITY, REAL OR ALLEGED, IN CONNECTION WITH THE PERFORMANCE OF WORK SAFETY OF ALL PERSONS AND PROPERTY; THAT THIS REQUIREMENT SHALL APPLY CONTINUOUSLY AND NOT BE LIMITED TO NORMAL WORKING HOURS; AND THAT THE CONTRACTOR

CONTRACTOR AGREES THAT HE SHALL ASSUME SOLE AND COMPLETE RESPONSIBILITY FOR JOB SITE CONDITIONS DURING THE COURSE OF CONSTRUCTION OF THIS PROJECT, INCLUDING ON THIS PROJECT, EXCEPTING FOR LIABILITY ARISING FROM THE SOLE NEGLIGENCE OF THE OWNER OR THE ENGINEER.

SHALL DEFEND, INDEMNIFY AND HOLD THE OWNER AND THE ENGINEER HARMLESS FROM ANY AND ALL LIABILITY, REAL OR ALLEGED, IN CONNECTION WITH THE PERFORMANCE OF WORK EST.1955

CUPERTINOCITY OF

SURVEYORSCONSTRUCTION MANAGERSCIVIL ENGINEERS
(415) 534-7070 www.freyerlaureta.com

AS SHOWN
328002
150 Executive Park Blvd
San Francisco, CA 94134
4 COVER SHEET SHEET C1
EST.1955

SERVICE CENTER SECURITY GATE

PROJECT
10555 MARY AVENUE

CUPERTINO, CALIFORNIA

INDEX OF DRAWINGS

ABBREVIATIONS
LEGEND
S
1 SITE MAP

VICINITY MAP
” ”

CITY OF CUPERTINO GENERAL NOTES
2/27/2023
Attachment D



 

  


 

 




 

 

  
  


 















 



































 



 







 



!




 
















 




 


"




 




 








 



!

 





 !"#

$



 













 








 %&!
$



 














 



! 

#



 



!
#



  








 







 







!


 
















#
! 


 
#!







 

#



 



!

 





 













 





!





 



!

 




 






'
 





(
!






 






#




#



 



!

 





 


 















!



 




!



 
























 








% %
 















)






 *+,-
./+,-
012
340-

5,.6,7-
0/83-
,9*43,7-
/:,- ";"#

)
)














 
 


<



=














$

<


















 



 

) 


 




 


  

)




 
 











 





 
$

 
 


<



=














$

<


















 



 

) 


 




 


  

)





)








 
 
 





 
 











 





 
$




 
 

 





 !

!""#
 
)
 











 
%



!
 
-
 




>

-
# !



 
-
&%!
! 
 






















 









 !










"






2023-103

ALDO CORRAL
(408)777-3269
2/24/2023
SAMPLE
AD- 1

CUPERTINO SERVICE CENTER

ADDRESS

CITY, CA

INWARD SWING GATE

PLAN VIEW
A&D Automatic Gate
And Access
810 WARRINGTON AVE.

REDWOOD CITY, CA 94063
(650) 365-8828

REVISIONS
DATE: 11/15/2021
DRAWN BY: J. BLANDINO
SCALE: 3/8" = 1' - 0"
JOB NO:

SHEET
Copyright © 2020 A&D Automatic Gate and Access.

Reproduction and distribution of these plans without
written permission is prohibited.

DESIGN 11/15/2021
REV. .01 00/00/2021
12XXX
1 INWARD SWING GATE
3/8" = 1' - 0"
KEY NOTES:

1. ALL CONDUIT & POWER WIRE TO
BE FURNISHED AND INSTALLED BY OTHERS.

2. CONDUIT SHOWN FOR REFERENCE ONLY,
ACTUAL LAYOUT BY OTHERS.

3. FINAL HOOK UP BY A&D

4. ACTUAL OPENING SIZE TO BE DETERMINED BY
FIELD VISIT AND MEASUREMENTS.

5. FINISH: TO BE DETERMINED

CONDUIT/LOOP LEGEND

HIGH VOLTAGE POWER

LOW VOLTAGE POWER

LOOPS & LEADS
GRID
CELLGATE 450 ON GOOSENECK
@ 18' BEFORE GATE LINE / FIRE KEY SWITCH

GATE LOOP SYSTEM

GATE OPERATOR

TYPICAL
6" x 6" POST / TAGMASTER LONG

RANGE READER/ PHOTO BEAM
PHOTO EYE5' FENCING
9' FENCING
1"" HIGH VOLTAGE CONDUIT
1" LOW VOLTAGE CONDUIT

OUTSIDE OBSTRUCTION LOOP

INSIDE OBSTRUCTION LOOP
4'-0" X 22'-0"

FREE EXIT LOOP
4'-0" X 22'-0"
4'-0" X 22'-0"

SHADOW LOOP
4'-0" X 22'-0"

SEE ELECTRICAL PLAN FOR

CONDUIT AND PULL BOX

LOCATIONS
(NOTE: PULL BOXES NOT

SHOWN ON THIS DRAWING)
WITH LIGHT. COMMUNICATION VIA CAT-5
CABLE FROM MAINTENANCE BUILDING.
1" POWER FOR LIGHTING
1" SPARE (FUTURE ELEC)

SEE ELECTRICAL

PLAN FOR

CONDUIT AND

PULL BOX

LOCATIONS
(NOTE: PULL

BOXES NOT

SHOWN ON THIS

DRAWING)
1" HIGH VOLTAGE CONDUIT
1" COMMUNICATION CONDUIT
1" SPARE (FUTURE ELEC)
1" POWER FOR LIGHTING
1" COMMUNICATION CONDUIT

SEE ELECTRICAL PLAN FOR

CONDUIT AND PULL BOX

LOCATIONS
(NOTE: PULL BOXES NOT

SHOWN ON THIS DRAWING)
1" COMMUNICATION
5' FENCING
(FIELD CONFIRM)
9' FENCING
(FIELD CONFIRM)

LOW VOLTAGE (COMM)
1/17/2023
SAMPLEAD.E- 1CUPERTINO SERVICE CENTERADDRESSCITY, CAINWARD SWING GATEO.S.L.I.A&D Automatic GateAnd Access810 WARRINGTON AVE.REDWOOD CITY, CA 94063(650) 365-8828REVISIONS DATE:11/15/2021DRAWN BY: J. BLANDINOSCALE: NOT TO SCALEJOB NO:SHEET Copyright © 2020 A&D Automatic Gate and Access.Reproduction and distribution of these plans withoutwritten permission is prohibited.

DESIGN11/15/2021REV. .0100/00/2021
12XXX
KEY NOTES:1. ALL CONDUIT & POWER WIRE TO BE FURNISHED AND INSTALLED BY OTHERS.2. CONDUIT SHOWN FOR REFERENCE ONLY, ACTUAL LAYOUT BY OTHERS.3. FINAL HOOK UP BY A&D4. ACTUAL OPENING SIZE TO BE DETERMINED BY FIELD VISIT AND MEASUREMENTS.5. FINISH: TO BE DETERMINEDCONDUIT/LOOP LEGENDHIGH VOLTAGE POWERLOW VOLTAGE POWERLOOPS & LEADSGRID 1 INWARD SWING GATE N.T.S.
9'14'14'5' ± 42'-6"2" 7'

LOW VOLTAGE (COMM)
1/17/2023

FENCING(FIELD

CONFIRM)

FENCING(FIELD

CONFIRM)