Cities Index.
H - CIP Projects Status May 2023

Cupertino City Council
May 16, 2023

Document
H - CIP Projects Status May 2023
Meeting
May 16, 2023
Body
Cupertino City Council
Pages
12
Original file
218 KB
Text extracted from the city's file for reading and search. Open the original on legistar.granicus.com. That file is the official record.

CIP PROJECT UPDATE
Program Overview, Accomplishments & Status

The Capital Improvement Program (CIP) Administration Division provides design and construction administration for all capital improvement projects including streets, sidewalks, storm drainage, buildings, parks, bicycle and pedestrian improvements and other public facilities.

The Division ensures that all public improvements are designed and constructed in accordance with community expectations and City standards. The Division places safety of the public, City employees, and workers as the highest priority in the delivery of capital projects.

May 2023; Q3 FY2022 - 2023

Status of Current CIP Projects
The categories below directly correlate to the categories in the FY22-27 CIP Schedule. Furthermore, the projects are color- coded to illustrate the type of project. These ‘types’ are somewhat intuitively, rather than effectively ascribed to the projects, as many projects would fall into multiple categories.

Facilities related CIP Projects (orange) – 5 active projects, 4 queued Streets and Grounds related CIP Projects (red) – 5 active projects, 2 completed, 1 queued Traffic, Bike and Pedestrian related CIP Projects (blue) – 9 active projects, 4 completed, 2 queued Parks and Recreation System related CIP Projects (green) - 9 active projects, 4 completed, 2 queued

Total:
25 active projects, 12 completed, 10 in the queue (paused).

ACTIVE PROJECTS
Project Title Description Current Phase Scheduled
Completion
Status/Notes
Bicycle
Boulevard
Interim
Improvements,
Ph. 3
Improvements from
2016 Bicycle
Transportation
Plan.

Design TBD Phase 3 outreach and design in
progress.

Page 2 ends

ACTIVE PROJECTS (continued)
Project Title Description Current Phase Scheduled
Completion
Status/Notes
Civic Center
Parking
Analysis
Analyze the parking
requirement for the
Civic Center.

Implement
mitigation measures
identified in 2018
report.

Feasibility/
Report,
Implementation
Ongoing,
Book Drop
lane
completed
Torre Avenue Book Drop
completed Summer 2022. New
project planned: additional
surface parking spaces behind
Community Hall. Implementation
of mitigation measures dependent
upon increased staff parking
demands at City Hall.

DeAnza Blvd
Buffered Bike
Lanes
Restripe De Anza
Blvd to include a
painted buffered
zone between the
existing bike lane
and the vehicle
lanes.

Design Summer
2023
Design Process underway
Tamien Innu
Trail – East &
Central
Segments
(Externally
Funded) 1
Design and
construct an off-
street bicycle and
pedestrian facility
parallel to the I-280
HWY, from De
Anza Blvd. Wolfe
Road (Central),
from Wolfe Rd. to
Vallco Parkway
(East)
Design Spring 2024
for East
segment;
Fall 2024 for
Central
Segment
Design phase for Central
segment will pause now that
IS/MND is underway; East
segment will continue into Final
Documentation, Bid and
Construction.

McClellan Road
Separated Bike
Corridor, Phase
3 (Externally
Funded, in
part)
Improve pedestrian
and bicycle safety
by reconfiguring the
intersection and
vehicle movements.

Bid Summer
2023
Bids for Construction received
and were greater than
Engineer’s Estimate.

School Walk
Audit
Implementation
(Externally
Funded, in
part)
Construct
infrastructure
related
improvements
around schools that
were identified as
part of the
comprehensive
School Walk Audit
study.

Ongoing/
Construction
Ongoing
P

Page 3 ends

r ACTIVE PROJECTS (continued) on Current Phase Scheduled Completion Status/Notes Project Title Description Current Phase Scheduled
Completion
Status/Notes
Stevens Creek
Boulevard CL
IV Bikeway -
Phase 2 –
Design &
Construction
(Externally
Funded, in
part) 2
Design and
Construction of the
separated bikeway
along Stevens Creek
Blvd from Wolfe
Road to DeAnza
Blvd (2A) and De
Anza Blvd to US-85
(2B).

Design/Bid 2024 Phase 2A Construction will be
posted for public bid process in
in late Summer 2023 . Phase 2B
Design is underway.

Stevens Creek
Boulevard CL
IV Bikeway –
Bandley Drive
(Externally
Funded, in
part)
Signal upgrades at
Bandley Drive.

Design/Bid 2024 This work is combined with
Construction of Phase 2B of the
SCB bikeway project. Phase 2B
Design is underway.

Traffic Calming Funding to respond
to citizen requests
for traffic calming to
reduce vehicle
speeds, improve
pedestrian and bike
safety.

Ongoing Ongoing Ongoing; responding to resident
concerns when they occur.

ADA
Improvements
(Multi-year
funding)
This is an ongoing
program funded
annually to improve
accessibility at all
public facilities
throughout the
City.

Design Ongoing Undertaking improvements at
Wilson Park, Wintergreen Dr.
entrance.

City Hall and
Community
Hall
Improvements
(Programming
and Feasibility)
Programming,
Feasibility and
Community
Outreach to form
the basis of a
renovation strategy
for the buildings.

Feasibility/
Report
N.A. Meetings with City Hall Project
Subcommittee are complete.

Page 4 ends

ACTIVE PROJECTS (continued)
Project Title Description Current Phase Scheduled
Completion
Status/Notes
City Hall
Annex (10455
Torre Avenue
Improvements)
Program, plan and
build facility
improvements
required for interim
facility to
accommodate staff
while City Hall is
remodeled, as well
as the long-term use
of this facility.

Design Fall 2024 Design process underway. EOC
scope added to the project in
October 2022.

Citywide
Building
Condition
Assessment
Implementation
& Report
Update
Implement
recommendations
identified as a
priority in the
Comprehensive
Facility Condition
and Use
Assessment.

Construction/
Ongoing,
Sports Center Fire Panel
Replacement: work is complete,
awaiting final inspection. 2018
Report Update/Dashboard
creation: research and report
generation underway.

Library
Expansion
Project
Develop a design
and construct a
5600 SF addition to
the existing Library
building.

Building:
complete.

Donor wall and
Landscaping
are active .
2023
Building Construction is
complete. Donor wall final
panels fabrication and
installation is underway.

Landscaping project paused due
to staff availability .

All Inclusive
Play Area &
Adult Assistive
Bathroom
Facility
(Jollyman Park)
(Externally
Funded, in
part) 3
At Jollyman Park,
Design and
construct an all-
inclusive
playground and an
adult-assistive
bathroom facility
adjacent to the new
AIPG.

Design Summer
2024
Design process nearing
completion. Bid and permit
phase will follow.

Annual
Playground
Replacement
(Multi-year
funding)
Replacement of
older playground
equipment that is
dated and worn.

Creekside Tot
Lot - Complete
Ongoing Creekside Tot Lot construction
complete; opened in October
2022. Creekside School-Age
playground design in process;
reviewed at May 2023 Parks &
Rec Commission. Grant funding
received for additional [smaller]
playgrounds – in process.

Page 5 ends

ACTIVE PROJECTS (continued)
Project Title Description Current Phase Scheduled
Completion
Status/Notes
Blackberry
Farm Pool
Improvements
Make
improvements to
the pools and
facility related to
safety,
accessibility, and
maintenance.

Bid, Permit Winter 2023 Bid process is underway.

Construction is scheduled to
begin in Fall 2023.

Blackberry
Farm Golf
Renovation /
Alternative
Use Study
Study to determine
options for the BBF
Golf Course: minor
repairs or
alternative use
(‘natural habitat’).

Report is complete,
Council
presentation/process
in progress.

Consultants’ reports and
Public comments are
compiled. Report delivered to
Joint Commission (Parks &
Rec, Bicycle/Ped,
Sustainability) on 8/08/2022.

Awaiting opportunity to
present to Council for further
action (July 2023) .

Citywide
[Satellite]
Community
Garden
(Wilson Park)
Develop a program
to establish
community
gardens
throughout the
City.

Construction Late Spring
2023
Construction is underway;
scheduled for completion in
Summer 2023.

Full-sized
Outdoor
Basketball
Court (Wilson
Park)
(Externally
Funded, in
part)
Install a full-size
basketball court at
a park, following
the Parks and
Recreation System
Master Plan.

Bid Summer
2023
Construction is underway;
scheduled for completion in
June 2023.

Page 6 ends

ACTIVE PROJECTS (continued)
Project Title Description Current Phase Scheduled
Completion
Status/Notes
Lawrence -
Mitty Park and
Trail Plan
Develop a Master
Plan for a
proposed
neighborhood park
located on several
acres of land
adjacent to
Saratoga Creek,
near the
intersection of
Lawrence
Expressway and
Mitty Way.

Design Winter 2025 The community
vision/outreach phase is
complete for the conceptual
design phase. The final
conceptual layout will be
developed in early 2023,
followed by environmental
clearance (CEQA) work. Final
design and permitting will
begin in late 2023.

Construction is anticipated to
begin in late 2024 and be
completed in late 2025.

Memorial Park
- Specific Plan
Design
Following the
findings of the
Master Plan
process, develop a
conceptual design
for Phase One
features and
amenities.

Design Fall 2023 Public input received;
conceptual design
alternatives developed.

Design plans and reports are
in process.

Park Amenity
Improvements
(Multi-year
funding)
Funding for
various park
amenities such as
benches, hydration
stations, outdoor
table tennis,
cornhole, shade
structures,
pickleball striping,
etc.

Construction Ongoing 8 hydration stations have
been installed at various
parks. Outdoor table tennis
tables have been installed at
Jollyman Park and Wilson
Park. Pickleball striping
completed at court 2 at
Memorial Park.

Page 7 ends

ACTIVE PROJECTS (continued)
Project Title Description Current Phase Scheduled
Completion
Status/Notes
City Bridge
Maintenance
Repairs
(Externally
Funded, in
part)
Repair 5 bridges as
recommended in
the Caltrans Bridge
Report along with
additional
improvements to
prolong the useful
life of the bridges.

Advertise/Bid Summer
2023
Construction documents have
been completed. The project is
ready to be advertised for bid in
early 2023 and work completed
by summer 2023. The work is
partially funded (80%) through
the Bridge Preventative
Maintenance Program, a
federally funded program.

City Lighting
LED Transition
Assessment
Develop a strategy
to transition the
City's streetlight
infrastructure, and
other City operated
lights, from
induction to LED
fixtures to meet the
“Dark Sky”
requirements and
reduce light
pollution
Feasibility/
Report
Under
Review
Survey is complete. Council
requested revisions to the report.

This work is underway.

Pumpkin and
Fiesta Storm
Drain Project,
Phase 1 & 2
Design storm
drainage
improvements at
Pumpkin Drive,
Fiesta Lane, as
identified in the
Storm Drain Master
Plan.

Phase 1-
Advertise/Bid;
Phase 2-Design
Phase 1-
Summer
2023; Phase
2- TBD
Design is complete for Phase 1
and will be constructed
spring/summer 2023.

Preliminary site analysis and
design for Phase 2 will start in
early 2023.

Regnart Road
Improvements,
Phase 1
Phase 1 will
construct a
retaining wall to
stabilize the road
slope to the creek
from Sta 28+40 to
29+80 (approx. 140
LF).

Design, Permits 2023 Phase 1 design is complete .

Environmental permitting is
complete, and the project team is
getting ready to post the bid
documents so that construction
can begin in the Summer/Fall
2023.

Street Light
Installation -
Annual Infill
(Multi-year
funding)
Design and install
streetlights on an as
needed basis.

Complete Ongoing Installations for this fiscal year
are ongoing . Year 3 of 5.

Page 8 ends

COMPLETED PROJECTS (or nearly complete)
Project Title Description Current Phase Scheduled
Completion
Status/Notes
Bicycle
Boulevard
Interim
Improvements,
Ph. 2
Improvements from
2016 Bicycle
Transportation Plan.

Construction March 2023 Completion expected in
February/March 2023.

Homestead/De
Anza – Design
&
Construction 4
Modify traffic signal
to relocate median-
mounted mast arm
poles to the corners.

Complete December
2022

Regnart Creek
Trail Fencing
Construction of
privacy fencing
along properties
abutting Regnart
Creek trail.

Construction March 2023
The Regnart Creek Trail opened
in March 2023. The fencing
project team is working on some
minor final items.

Stelling and
Alves
Crosswalk
Installation
Install a crosswalk
and pedestrian-
actuated RRFB
across Stelling at the
north leg of the
intersection with
Alves Drive.

Complete October
2022

Annual
Playground
Replacement 5
Replacement of older
playground
equipment that is
dated and worn.

Creekside Tot
Lot - Complete
Creekside Tot Lot construction
complete; opened in October 2022.

Memorial Park
- Pond
Repurposing
Design and
construct Memorial
Park improvements,
specifically
addressing the
immediate state of
the drained ponds.

Construction April 2023
Operations and Maintenance
phase is underway to establish
the plantings before opening.

Silicon Valley APWA selected
this project as one of the winners
of its 2023 Award Program.

Page 9 ends

COMPLETED PROJECTS (continued)
Project Title Description Current Phase Scheduled
Completion
Status/Notes
Sports Center
Community
Needs Analysis
Evaluate the
potential long-term
needs of the facility,
the cost of
renovations and
repairs and the cost
effectiveness of
those
improvements.

Complete
P&R staff performed some
analysis and determined short-
term improvements/repairs.

Tree Inventory
- Stevens Creek
Corridor
Inventory and map
City-owned trees
that are within the
Stevens Creek
Corridor, including
the BBF golf course.

Feasibility/
Report
February
2023
Survey is complete, report under
review by staff.

Retaining Wall
Repair -
Cordova Road
Replace failing
retaining wall
lagging with City
forces.

Complete Construction completed Summer
2022.

Sidewalk
Improvements
- Orange &
Byrne
Acquire right-of-
way as needed,
initiate design and
construction of
sidewalks where
there are gaps, as
well as curb, gutter,
and drainage
improvements.

Complete Fall 2022
Byrne Avenue improvements
were completed in 2019. Civil
work (sidewalk, curb, .and
gutter) is complete on Orange
Avenue. Utility pole relocations
on Orange Avenue will be
performed by the utility
companies (PG&E, AT&T,
Comcast) in 2023.

Page 10 ends

PROJECTS IN THE QUEUE
Project Title Description Current Phase Scheduled
Completion
Status/Notes
Tamien Innu
Trail - West
Segment
Design and
construct an off-
street bicycle and
pedestrian facility
parallel to the I-280
HWY, from the Don
Burnett Bicycle –
Pedestrian Bridge to
De Anza Blvd.

Deferred
This segment will be on hold
until the other segments are
designed.

McClellan
Road
Separated Bike
Corridor -
Byrne Ave to
Imperial Ave,
Phase 4
Design and
construct separated
bike lanes on
McClellan Rd. from
Imperial Ave to
Byrne Ave.

Deferred Phase 4 on hold until ROW’s are
acquired.

Electric Vehicle
Parking
Expansion
Expansion of the
existing level 2
charging ports at
municipal
properties from
twelve (12) ports to
thirty-two (32)
ports. In addition,
install five (5) level
3 (DC Fast
Charging) ports.

RFQ
Project paused due to staff
availability.

Previously identified grant
fundings are unavailable. Scope
revision is necessary and
underway. RFQ process (not
RFP/Bid) approved by Council
on 11/01/2022.

Interim City
Hall
Establish an interim
facility to
accommodate City
Staff if existing City
Hall were to be
replaced or
significantly
remodeled.

Deferred
This funding will be required to
provide City Hall services while
the building is under
construction.

Page 11 ends

DEFERRED PROJECTS (continued)
Project Title Description Current Phase Scheduled
Completion
Status/Notes
QCC Multi-Site
Sustainable
Infrastructure
Upgrade
Develop
recommendation for
Council on a
complete facility
upgrade for heating
and cooling system,
emergency power
system, and
renewable energy.

RFQ 2024
Project paused due to staff
availability.

The RFQ process for energy
service companies (ESCOs) to
perform audit and initiate
improvements was completed.

Award of Contract will come to
City Council in early 2023.

Stocklmeir,
Bryne and
Blesch:

Inspection
Reports and
Analysis
Instigate property
inspection reports
and work with
outside consultants
to develop initial
use and business
strategies
appropriate for the
three residential
properties owned
by the City.

Feasibility
Study
Summer
2023
Project paused due to staff
availability.

Memorial Park
- Amphitheater
Improvements
Design and
construct Memorial
Park improvements,
specifically
addressing the
needs of the
Amphitheater.

RFQ 2024 Project paused due to staff
availability.

Page 12 ends

DEFERRED PROJECTS (continued)
Project Title Description Current Phase Scheduled
Completion
Status/Notes
Stevens Creek
Corridor Park
Chain Master
Plan
Study the various
uses of public lands
along Stevens Creek
for optimal public
use and operation
and develop a
master plan.

Deferred
On hold, pending completion of
Blackberry Farm Golf
Renovation/ Alternative Use
Study
City Lighting
LED
Improvements
Implement the
transition of City's
streetlight
infrastructure from
induction and other
fixtures to LED
fixtures to meet the
"Dark Sky"
Ordinance
requirements and
reduce light
pollution and
energy cost.

Deferred Awaiting finalization of LED
report before initiating this work.

Notes:

1. Previously listed as two projects: I-280 Trail – East and I-280 Trail Central Segments.

Name change to
“Tamien Innu”also updated.

2. Previously listed as two projects: Stevens Creek Boulevard CL IV Bikeway - Phase 2 – Design, Stevens Creek Boulevard CL IV Bikeway - Phase 2 – Construction.

3. Previously listed as two projects: All Inclusive Play Area, and AIPG Adult Assistive Bathroom Facility (Jollyman Park).

4. Previously listed as two projects: Homestead/De Anza Design, and Homestead/De Anza Construction.

5. Annual Playground Replacement project is listed in both Active and Completed Projects. The project is ongoing and additional playgrounds are planned to be initiated, but this also notes that one playground was completed in this fiscal year.:

6. Previously listed as two projects:

7. Previously listed as two projects:

← All documents from this meeting