ADDENDUM NO. I
Regnart Road Improvements Phase I
PROJECT N0. 2019-08
Bid Opening: June 15,2023 - 2:00 P.M.

Issue Date: June 1, 2023
The following revisions are hereby made to the above referenced project:

1. Add two documents:
a. . '2019-08 Regnart Road Improvements Phase lGeotechnical Report' b. '2019-08 Regnart Road Improvements Phase 1 Environmental Permit' No other changes were made to the Manual and Plan Set.

Only questions received in writing will be accepted for response. Send questions by e-mail to [email protected]@. Questions regarding this project should be sent to the attention of the designated project manager, Evelyn Moron no later than June 9, 2023, at 5:00 PM.

You must indicate receipt of this addendum on the last page of the Proposal. Failure to do so may cause rejection of your bid.

APPROVED BY: