1 Attachment D

CITY OF CUPERTINO REGULATIONS FOR CONSTRUCTION, OPERATION, AND MAINTENANCE  OF SMALL  WIRELESS  FACILITIES  IN  THE PUBLIC  RIGHT  OF WAY (MUNICIPAL CODE CHAPTER 14.30)
SECTION 1.     PURPOSE AND INTENT
The  City  of  Cupertino  (“City”)  adopts  these  wireless  regulations  applicable  to  small wireless facilities (“Regulations”) to establish reasonable, uniform, and comprehensive standards and procedures for the implementation of Municipal Code Chapter 14.30. The standards and procedures set forth in these Regulations should be applied to protect and promote public health, safety, and welfare and balance the benefits that flow from robust, advanced wireless services with the City’s local values, which include without limitation the aesthetic character of the City, its neighborhoods, and community. The Regulations are  intended  to  establish  regulations  and  standards  for  small  wireless  facilities  unless specifically prohibited by applicable law.

SECTION 2.  DEFINITIONS
The definitions in this Section 2 are applicable to the terms, phrases, and words of these Regulations.  Undefined  terms,  phrases,  or  words  will  have  the  meanings  assigned  to them in the Municipal Code or 47 U.S.C. § 153, or if not defined in either therein, will have their ordinary meanings. If any definition assigned to any term, phrase, or word in this Section  2  conflicts  with  any  federal  or  state‐mandated  definition,  the  federal  or  state‐ mandated definition will control.
“Accessory equipment” means equipment other than antennas used in connection with a small wireless facility and includes “transmission equipment” as defined by the FCC in 47 C.F.R. § 1.6100(b)(8).
“Antenna” means the same as defined by the FCC in 47 C.F.R. § 1.6002(b). “Collocation” means the same as defined by the FCC in 47 C.F.R. § 1.6002(g). “CPUC” means the California Public Utilities Commission established in the California Constitution, Article XII, § 5, or its duly appointed successor agency. “Decorative  pole”  means  any  pole  that  includes  decorative  or  ornamental  features, design elements and/or materials intended to enhance the appearance of the pole or the right‐of‐way in which the pole is located.
“Director” means the Director of Public Works or their designee. “Eligible  facilities  request”  means  the  same  as  defined  by  the  FCC  in  47  C.F.R. § 1.6100(b)(3).
2 Attachment D

“FCC” means the Federal Communications Commission or its duly appointed successor agency.
“FCC Shot Clock” means the FCC’s presumptively reasonable time frame, accounting for  any  tolling  or  voluntary  extension,  or  unusual  circumstances  justifying  additional time, within which the City generally must act on a duly filed request for authorization in connection with a personal wireless service facility, as such time frame is defined by the    FCC. For small wireless facilities, the FCC Shot Clock is 60 days for collocations and 90 days for new structures.
“OTARD”  means  an  “over‐the‐air  reception  device”  and  includes  all  antennas  and antenna supports covered by 47 C.F.R. § 1.4000(a)(1).
“Personal wireless services” means the same as defined in 47 U.S.C. § 332(c)(7)(C)(i). “Personal  wireless  service  facilities”  means  the  same  as  defined  in  47  U.S.C. § 332(c)(7)(C)(i).
“Public right‐of‐way” or “right‐of‐way” means the same as defined in Municipal Code Section 14.30.020C(9).
“RF” means radio frequency or electromagnetic waves used for wireless communication. “Shot clock days” means calendar days counted toward the presumptively reasonable time under the applicable FCC Shot Clock. The term “shot clock days” does not include any calendar days on which the FCC Shot Clock is tolled due to incompleteness or other authorized pauses.
“Small wireless facility” or “small wireless facilities” means the same as defined by the FCC in 47 C.F.R. §    1.6002(l).
“Support structure” means a “structure” as defined by the FCC in 47 C.F.R. § 1.6002(m). “Underground district” means any area in the City within which overhead wires, cables, cabinets, and associated overhead equipment, appurtenances, and other improvements are either (1) prohibited by ordinance, resolution, or other applicable law; (2) scheduled to be relocated underground within 18 months from the time an application is submitted; or (3) primarily located underground at the time an application is submitted. “Wireless facility” or “facility” means small wireless facility and the same as defined in Municipal Code Section 14.30.020C(11).
“Wireless  ROW  permit”  means  the  same  as  defined  in  Municipal  Code  Section

14.30.020C(13).

SECTION 3.  APPLICABILITY
3 Attachment D

a. Wireless  Facilities.  Except  as  expressly  provided  otherwise,  the  provisions  in these  Regulations  shall  be  applicable  to  all  applications  and  requests  for authorization to construct, install, attach, operate, collocate, modify, reconstruct, relocate,  remove,  or  otherwise  deploy  small  wireless  facilities within the public rights‐of‐way within the City’s jurisdictional and territorial boundaries. b. Exemptions.  These  Regulations  shall  not  apply  to  any  facility  exempt  from Chapter 14.30 of the Municipal Code pursuant to Section 14.30.030B. c. Eligible Facilities Requests. Eligible facilities requests shall comply with Sections 4(b)‐(d), 4(h)‐(n), and 5(c)‐(d) and all applicable requirements of Section 8 to the extent  Section  8  applies  to  the  determination  of  what  constitutes  a  “substantial change”  under  47  C.F.R.  §  1.6100(c)(1)  but  shall  otherwise  be  exempt  from  the requirements of these Regulations; provided, however, that with regards to 4(i), the  applicant  will  have  the  option  of  providing  the  public  notice  affidavit  or paying City’s costs associated with City completing the noticing process detailed in 4(i) that otherwise is required of applicants.

SECTION 4.  APPLICATION AND REVIEW PROCEDURES
a. Application  Requirements  for  Wireless  ROW  Permits.   All  applications  for wireless  ROW  permits  must  comply  with  the  requirements  of  Municipal  Code Section 14.30.050 and the requirements of this Section 4. b. Application Form. The applicant shall submit a complete, duly executed wireless ROW permit application on the current City of Cupertino form. c. Application Fee. The applicant shall submit the applicable wireless ROW permit fee  established  by  City  Council  resolution.  If  no  application  fee  has  been established for the specified work, then the applicant must submit a signed written statement that acknowledges that the applicant will be required to reimburse the City for its reasonable costs incurred in connection with the application within 10 days after the City issues a written demand for reimbursement. d. Construction Drawings. The applicant shall submit true and correct construction drawings, prepared and signed by a licensed or registered engineer, that depict all the existing and proposed improvements, equipment and conditions related to  the proposed facility,  including without limitation all poles, posts,  pedestals, traffic signals,  towers,  streets,  sidewalks,  pedestrian  ramps,  driveways,  curbs,  gutters, drains,  handholes,  maintenance  holes,  fire  hydrants,  equipment  cabinets, antennas, cables, utilities, and trees and other landscape features. The construction drawings must: (1) contain cut sheets that contain the technical specifications for all  existing  and  proposed  antennas  and  accessory  equipment,  which  includes 4 Attachment D

without  limitation  the  manufacturer,  model  number  and  physical  dimensions; (2) depict the applicant’s preliminary  plan  for  electric,  including  the  anticipated locations  for all conduits, cables, wires, handholes, junctions, transformers, meters, disconnect switches, and points of connection; (3)  include locations for existing utility facilities within 50 feet of the footprint of work; and (4) demonstrate that proposed facility will be in full compliance with all applicable health and safety laws, regulations, or other rules, including without limitation all building codes, electric codes, local street and sidewalk standards and specifications, and public utility  regulations  and  orders.  All  pole  attachments  shall  be  shown  with  pole numbers.
e. Site Survey. The applicant shall submit a survey prepared, signed, and stamped by  a  licensed  engineer.  The  survey  must  identify   and  depict  all  existing boundaries, encroachments, and other structures within 75 feet from the proposed facility  and  any  new  improvements,  including  without  limitation  all  (1)  traffic lanes; (2) private properties and property lines; (3) above and below‐grade utilities and related structures and encroachments; (4) fire hydrants and other public safety infrastructure;  (5)  streetlights,  decorative  poles,  traffic  signals,  and  permanent signage;  (6)  sidewalks,  driveways,  parkways,  curbs,  gutters,  and  storm  drains; (7) benches,  bus  stops,  trash  cans,  mailboxes,  kiosks,  and  other  street  furniture; and (8) existing trees, planters, and other landscaping features. f. Photo  Simulations.  The  applicant  shall  submit  site  photographs  and  photo simulations  that  show  the  existing  location  and  proposed  wireless  facility  in context from at least two vantage points within the public streets or other publicly accessible  spaces,  together  with  a  vicinity  map  that  shows  the  location  of  the proposed  facility  and  the  photo  location  for  each  vantage  point.  At  least  one simulation must depict the wireless facility from a vantage point approximately 50 feet from the proposed support structure or location. The photo simulations and vicinity map shall be incorporated into the construction plans submitted with the application.
g. Identification of Alternative Locations. For a small wireless facility not proposed in a Tier 1 location preference under Section 7(a), the applicant shall provide an inventory of support structures and other feasible locations within 500 feet of the proposed location and explain the basis for the selection of the proposed location. h. RF  Compliance Report. The applicant shall submit an RF exposure  compliance report  that  certifies  that  the  proposed  wireless  facility,  both  individually and cumulatively  with  all  other  emitters  that  contribute  more  than  5%  to  the cumulative emissions in the vicinity (if any), will comply with applicable federal RF exposure standards and exposure limits. The RF report must be prepared and 5 Attachment D

certified by an engineer acceptable to the Director. The RF report must include the actual frequency bands and power levels (in watts effective radiated power) for all existing and proposed antennas at the proposed facility and exhibits that show the location and orientation of all transmitting antennas and the boundaries of areas with RF exposures in excess of the uncontrolled/general population limit (as that term is defined by the FCC) and also the boundaries of areas with RF exposures in excess of the controlled/occupational limit (as    that term is defined by the FCC).

Each such boundary shall be clearly marked and identified for every transmitting antenna at the proposed facility.
i. Public Notices. The applicant shall include with the application an affidavit that attests that notice has been posted at the site of the proposed facility and provided to property owners and residents of all property within a 300‐foot radius of the proposed facility pursuant to Municipal Code 14.30.050(D). The notices shall be posted  and  delivered  on  forms  approved  by  the  Director  and  must  contain:
(1) a general  description  of  the  proposed  wireless  facility;  (2)  the  applicant’s identification and contact information as provided on the application submitted to the City for interested parties to submit comments; (3) contact information for the  Public  Works  Department;  (4)  a  statement  that  the  Director  will  act  on  the application without a public hearing and that the owner or occupant may request to be notified of the Director’s decision; and (5) a general statement that the FCC requires the City to take final action on applications for wireless facilities within 60 days for collocations and 90 days for facilities on new support structures. The notice  should  provide  the  location,  date,  and  time  of  a  community  meeting,  if applicable. The notice shall be delivered in an envelope that prominently displays the  operator’s  logo  and  shall  prominently  display  the  text  “NEW  WIRELESS FACILITY  INFORMATION”  on  the  front  of  the  envelope.  The  applicant  shall maintain  (and  provide  to  the  Director,  at  the  Director’s  request)  (i) a  list  of recipients  of  the  public  notice;  (ii)  a  log  of  any  correspondence  to  or  from  the recipients of the notice prior to the City’s final decision on the application; and (iii) a list of recipients of the public notice who have requested to receive notice of the Director’s decision. The applicant shall copy the appropriate Public Works staff on all email correspondence with members of the public. The noticing period for this activity shall be 21 days from the date the letter is deposited with the United States Postal Service, pursuant to Municipal Code 14.30.050(D). No permit or approval for  the  wireless  facility  being  noticed  will  be  issued  during  the  noticing  period unless permit issuance is required by applicable state or federal law. j. Public  Access  to  Application  Information.  The  Director  shall  ensure  that information  regarding  the  location  and  status  of  all  wireless  ROW  permit applications is available on the City of Cupertino website. 6 Attachment D

k. Regulatory Authorization; Shot Clock Requirements. The applicant shall submit evidence of the applicant’s regulatory status under federal and California law to provide the services and construct the wireless facility proposed in the application.

The  application  must  state  whether  the  applicant  believes  state  or  federal  law requires action on the application within a specified time period. l. Property  Owner’s  Authorization.  The  applicant  shall  identify  the  support structure  for  the  wireless  facility  (including  any  identification  number)  and include written authorization from the support structure owner(s). m. Acoustic Analysis. The applicant shall submit an acoustic analysis prepared and certified by a California licensed engineer for the proposed wireless facility and all associated  equipment  including  all  environmental  control  units,  sump  pumps, temporary  backup  power  generators,  and  permanent  backup  power  generators demonstrating compliance with the applicable provisions of Chapter 10.48.  The acoustic analysis must include an analysis of the manufacturers’ specifications for all noise‐emitting equipment and a depiction of the proposed equipment relative to all adjacent property lines. Where no generator, mechanical fan, or other noise‐ emitting equipment is proposed for installation, the applicant may submit, in lieu of  an  acoustic  analysis,  evidence  from  the  equipment  manufacturer(s)  that demonstrates the ambient noise emitted from all the proposed equipment will not, both individually and cumulatively, exceed applicable noise standards. n. Structural Analysis. The applicant shall submit a report prepared and certified by a California‐licensed structural engineer (or other qualified personnel acceptable to  the  City)  that  certifies  (1)  the  underlying  pole  or  support  structure  has  the structural  integrity  and/or  capacity  to  support  all  the  proposed  equipment  and attachments; (2) the foundation has the capacity to support additional loading and to accommodate any modifications to the pole base and bolt pattern; and (3) any drilling  or  cutting  will  preserve  the  structural  integrity  of  the  pole.  Where  an applicant proposes to replace the pole and foundation, the applicant shall submit structural  drawings  and  calculations  prepared  and  certified  by  a  California‐ licensed structural engineer.
o. Community  Meeting.  The  City  strongly  encourages,  but  does  not  require, applicants  to  schedule,  notice,  arrange,  and  attend  a  pre‐submittal  community meeting with all interested members of the public. This voluntary, pre‐submittal public  meeting  does  not  cause  the  FCC  Shot  Clock  to  begin  running  and  is intended to give applicants the opportunity to hear from members of the public regarding proposed deployment. Applicants should bring any draft applications, plans,  maps,  presentations,  or  other  materials  to  facilitate  the  public’s understanding of the applicant’s proposal. The City seeks to encourage dialogue 7 Attachment D

that  may  allow  applicants  to  address  and  resolve  areas  of  concern  prior  to  the submittal of an application.
p. Pole Availability Requests. Before submitting an application, applicants seeking a permit to install a wireless facility on a City light pole are encouraged but not required to submit a pole availability request and reservation to the Department of Public Works, to determine whether the light pole is available for the proposed facility.  The  applicant  shall  explain  why  the  proposed  location  meets  the requirements of Section 7 of these Regulations. Each pole availability request shall include the following information:

1. A map showing the location of the streetlight pole that is the subject of the request.  This map should be in the form of a Google KMZ file or other file type that clearly shows the streetlight being indicated.

2. Information  on  the  equipment  and  layout  being  proposed  (e.g.,  all equipment  within  the  shroud,  equipment  on  the  pole  screened  by  signs, base enclosure, underground vault, or equipment on the pole situated to minimize views of equipment).

The  approval  of  a  pole  availability  request  does  not  constitute  approval  of  a wireless  ROW  permit  and  does  not  relieve  the  applicant  of  complying  with  all requirements of Chapter 14.30 and these Regulations.
q.  License  Agreement.  For  any  wireless  facility  proposed  to  be  installed  on  any structure owned or controlled by the City and located within the public rights‐of‐ way, the applicant shall submit an executed Small Cell License Agreement on a form  prepared  by  the  City  that  states  the  terms  and  conditions  for  such  non‐ exclusive  use  by  the  applicant.  Such  agreement  will  function  as  a  master agreement pursuant to which an Encroachment Agreement will be entered into between City and applicant which will detail the terms and conditions that will govern particular siting authorizations.
r. Peer and Independent Consultant Review. The Director may in their discretion select  and  retain  independent  consultant(s)  with  expertise  and  appropriate credentials in telecommunications, RF testing/compliance, electrical or fire safety, and/or  other  professional  consultation  services  as  deemed  appropriate  in connection  with  the  review  of  any  application  under  this  chapter.  Such independent  consultant  review  may  be  retained  on  any  issue  that  involves specialized or expert knowledge in connection with an application, including but not  limited  to  application  completeness  or  accuracy,  engineering  analysis,  or compliance with FCC radio frequency emissions limits. The Director may require that the independent consultant prepare written reports, testify at public meetings, 8 Attachment D

hearings and/or appeals, and attend meetings with City staff and/or the applicant.

Subject  to  applicable  law,  in  the  event  that  the  Director  elects  to  retain  an independent consultant in connection with any permit application, the applicant shall  be  responsible  for  the  reasonable  costs  in  connection  with  the  services provided,  which  may  include  without  limitation  any  costs  incurred  by  the independent  consultant  to  attend  and  participate  in  any  meetings  or  hearings.

Before the independent consultant may perform any services, the applicant shall tender  to  the  City  a  deposit  in  an  amount  equal  to  the  estimated  cost  for  the consultant’s services to be provided, as determined by the Director. The Director may request additional deposits as reasonably necessary to ensure sufficient funds are  available  to  cover  the  reasonable  costs  in  connection  with  the  independent consultant’s  services.  In  the  event  that  the  deposit  exceeds  the  total  costs  for consultant’s services, the Director shall promptly return any unused funds to the applicant after the wireless facility has been installed and passes a final inspection by  the  Director.  In  the  event  that  the  reasonable  costs  for  the  independent consultant’s services exceed the deposit, the Director shall invoice the applicant for the balance. The City shall not issue any wireless ROW permit to any applicant with any unpaid deposit requests or invoices.
s. Incomplete  Applications  Deemed  Withdrawn.  An  application  shall  be automatically  deemed  withdrawn  by  the  applicant  when  the  applicant  fails  to submit a substantive response to the Director within 180 calendar days after the Director deems the application incomplete by written notice unless the applicant demonstrates good cause for the delay. A “substantive response” must include, at a minimum, all the materials identified as incomplete in the written incomplete notice, unless the Director explicitly waives any materials.

SECTION 5.  DECISIONS
a. Decision  of  the  Director.  The  Director  shall  approve,  deny  (with  or  without prejudice),  or  conditionally  approve  an  application  for  a  wireless  ROW  permit within a sufficient time to allow for an appeal to the City Manager pursuant to Municipal Code Section 14.30.070.
b. Findings  for  Approval.  Except  for  eligible  facilities  requests,  any  approval  or conditional approval of an application for a wireless ROW permit shall include a written determination based on the findings set forth in Municipal Code Section

14.30.060(B). The findings shall include a determination that the proposed facility meets the requirements in these Regulations, including the following:
9 Attachment D

1. The proposed facility is either located in the “most preferred” location for a wireless facility (Section 7(a)) or that the requirements of Section 7(b) are satisfied.

2. The  proposed  facility  complies  with  all  applicable  design  standards (Section     8).

3. The  applicant  has  demonstrated  that  the  proposed  facility  will  be  in compliance with all applicable FCC regulations and guidelines for human exposure to RF emissions.
c. Eligible  Facilities  Requests.  Notwithstanding  Section  5(b),  the  Director  shall approve an eligible facilities request if the application meets the requirements set forth in 47 C.F.R. § 1.6100 and complies with all applicable state and federal laws and  regulations,  including  without  limitation  applicable  regulations  for  human exposure to RF emissions and all applicable building standards. The conditions of any permit previously issued for the eligible facility shall apply to the maximum extent permitted by federal and state law and regulations. d. Notice of Decision. Within five calendar days of the Director’s action on a wireless ROW permit application, the Director shall provide written notice to the applicant stating  the  reasons  for  approval,  conditional  approval,  or  denial  of  the  permit application.

SECTION 6.  CONDITIONS OF APPROVAL
a. Standard Conditions. All wireless ROW permits shall be subject to the following standard conditions of approval:

1. Permit Term. Each wireless ROW permit shall have a term of 10 years and shall automatically expire 10 years and one day from its issuance, unless a different term is set pursuant to a license agreement approved by the City Council.  Any  other  permit  or  approval  issued  in  connection  with  any collocation, modification, or other change to a permitted wireless facility, including  without  limitation  any  permits  or  other  approvals  deemed‐ granted or deemed‐approved under state or federal law, shall not extend the term of the permit unless expressly provided otherwise in such permit or  approval  or required  under  state  or  federal  law.  Nothing  in  this subparagraph  shall  extend  or  abridge  the  rights  of  permittee  under  any license agreement with the City or any other public agency or any private utility.

2. Permit Renewal. Not more than one year before a wireless ROW permit expires, the permittee may apply for renewal of the permit. The permittee 10 Attachment D

must demonstrate that the wireless facility complies with all conditions of approval of the permit and all applicable provisions in   Municipal Code and Regulations  that  exist  at  the  time  the  renewal  decision  is  rendered.  The Director  may  modify  or  amend  the  conditions   as  may  be  necessary  or appropriate  to  ensure  compliance  with  the  Municipal  Code,  these Regulations,  or  other  applicable  law.  Upon  renewal,  the  permit  will automatically expire 10 years and one day from the date of renewal unless expressly issued for a shorter duration. Nothing in this subparagraph shall extend or abridge the rights of permittee under any license agreement with the City or any other public agency or any private utility. The provisions of this  subparagraph  may  be  waived  or  modified  by  a  license  agreement approved by the City Council.

3. Build‐Out  Period.  A  wireless  ROW  permit  will  automatically  expire  six months  from  the  approval  date  (the  “build‐out  period”)  unless  the permittee  (i)  obtains  all  other  permits  and  approvals  required  to  install, construct, and/or operate the approved wireless facility, including without limitation  any  permit  or  approval  required  by  any  federal,  state,  or  local public  agency  with  jurisdiction  over  the  subject  property,  the  support structure,  or  the  wireless  facility,  and  (ii)  begins  construction  of  the permitted  facility  within  six  months  of  the  approval  date.  The  permittee may request in writing, and the City may grant in writing, one six‐month extension if the permittee submits substantial and reliable written evidence demonstrating  justifiable  cause  for  the  extension.  If  the  build‐out  period and/or any extension period expires, the permit shall be automatically void, but  the  permittee  may  resubmit  a  complete  application,  including  all application fees, for the same or a substantially similar facility.

4. Post‐Installation Certification. Within 30 calendar days after the permittee receives  the  final  inspection  or  completes  the  construction  and/or installation of a wireless facility, the permittee shall provide the  Director with documentation that the facility has been installed and/or constructed in  compliance  with  the  approved  construction  drawings  and  photo simulations. Such documentation shall include without limitation as‐built drawings,  GIS  data,  and  site  photographs.  Post‐installation  certification shall  include  compliance  with  any  provisions  of  a  license  agreement between  the  permittee  and  the  City  relating  to  the  measurement  of  RF emissions from a wireless facility.

5. Site Maintenance. The permittee shall comply with the provisions of the most  current  editions  of  the  City’s  Building  Code,  Plumbing  Code,  and 11 Attachment D

Electrical  Code;  any  applicable  construction  standards  adopted  by  the Department of Public Works; the facility’s specifications and plans; and any applicable  federal,  state,  or  local  statutes,  ordinances,  regulations, guidelines,  or  requirements.  The  permittee  shall  keep   the  site,  which includes  without  limitation  any  and  all  improvements,  equipment, structures,  access  routes,  fences,  and  landscape  features,  in  a  neat,  clean, and safe condition in accordance with the approved construction drawings and all conditions in the wireless ROW permit. The permittee shall keep the site  area  free  from  litter  and  debris  at  all  times.  The  facility  shall  be manufactured or treated to resist graffiti. The permittee,  at no cost to the City, shall monitor and abate any graffiti or other vandalism at the site.    The permittee  shall  make  reasonable  commercial  efforts  to  remove  graffiti within 72  hours  after  the  permittee  receives  notice  or  otherwise  becomes aware that such graffiti or other vandalism occurred.

6. Compliance  with  Laws.  The  permittee  shall  at  all  times  comply  with  all federal, state, and local statutes, regulations, orders, or other rules that carry the  force  of  law  applicable  to  the  permittee,  the  subject  property,  the wireless  facility,  and  any  use  or  activities  in  connection  with  the  use authorized in the wireless ROW permit (collectively, “laws”). The permittee expressly  acknowledges  and  agrees  that  this  obligation  is  intended  to  be broadly  construed  and  that  no  other  specific  requirements  in  these conditions  are  intended  to  reduce,  relieve,  or  otherwise  lessen  the permittee’s obligation to maintain compliance with all laws. No failure or omission  by  the  City  to  timely  enforce  compliance  with  any  applicable provision in the Municipal Code, these Regulations, any permit condition, or any applicable law or regulation shall be deemed to relieve, waive, or lessen the permittee’s obligation to comply in all respects with all applicable provisions in the Municipal Code, these Regulations, any permit condition, or any applicable law or regulation.

7. Construction  Activities.  Construction  shall  be  coordinated  with  other utility companies or applicants installing infrastructure in the right‐of‐way and shall be scheduled and conducted so as to minimize interference with public  use  of  the  right‐of‐way,  including  access  to  the  right‐of‐way  from private property. The permittee shall use all reasonable efforts to avoid any and  all  unreasonable,  undue,  or  unnecessary  adverse  impacts  on  nearby properties  that  may  arise  from  the  construction,  installation,  operation, modification,  maintenance,  repair,  removal,  and/or  other  activities  on  or about the site of the facility, including the public’s use of the right‐of‐way and  the  public’s  access  to  the  right‐of‐way  from  private  property.  The 12 Attachment D

permittee  shall  not  perform  or  cause  or  allow  others  to  perform  any construction,  installation,  operation,  modification,  maintenance,  repair, removal, or other work that involves heavy equipment or machines except during normal construction work hours authorized by the Municipal Code.

The  restricted  work   hours  in  this  condition  will  not  prohibit  any  work required to prevent an actual, immediate harm to property or persons or any work arising from an emergency declared by the City or other state or federal  government  agency  or  official  with  authority  to  declare  an emergency within the City. The Director may issue a stop work order for any activity that violates this condition in whole or in part. The permittee agrees to fully cooperate with the City in assisting the City to achieve its accommodation obligations under the Americans with Disabilities Act, the Fair Housing Act Amendments of 1988, and other applicable laws.

8. Inspections;  Emergencies.  The  permittee  expressly  acknowledges  and agrees  that  the  City’s officers,  officials,  staff,  agents,  contractors,  or  other designees  may  enter  onto  the  site  and  inspect  the  improvements  and equipment upon reasonable  prior notice to the permittee. Notwithstanding the prior sentence, the City’s officers, officials, staff, agents, contractors, or other designees may (i) at any time inspect the facility visually or with any remote sensing equipment and (ii) may, but will not be obligated to, enter the facility without prior notice to support, repair, disable, or remove any improvements or equipment in emergencies or when such improvements or equipment threatens actual, imminent harm to property or persons.  The permittee, if present, may observe the City’s officers, officials, staff, or other designees while any such inspection or emergency access occurs.

9. Permittee’s  and  Contractor’s  Contact  Information.  Within  10  days  from the final approval, the permittee shall furnish the City with accurate and up‐to‐date  contact  information  for  a  person  responsible  for  the  wireless facility,  which  includes  without  limitation  such  person’s  full  name,  title, direct  telephone  number,  mailing  address,  and  email  address.  The permittee shall keep such contact information up‐to‐date at all times and shall promptly provide the City with updated contact information if either the  responsible  person  or  such  person’s  contact  information changes.  In addition,  before  the  City  issues  any  permit  required  to  commence construction, the permittee shall furnish the City with accurate and up‐to‐ date contact information for the contractor responsible for the construction of the facility, including without limitation such person’s full name, title, direct telephone number, mailing address, and email address. 13 Attachment D

10. Performance  Bond.  Before  the  City  issues  any  permit  required  to commence construction in connection with the permit, the permittee shall post  a  performance  bond  from  a  surety  and  in  a  form  acceptable  to  the Director  in  an  amount  reasonably  necessary  to  cover  the  cost  to  remove, store,  and/or  dispose  of  the  improvements  and  restore  all  affected  areas based on a written estimate from a qualified contractor with experience in wireless  facility  removal.  The  written  estimate  must  include  the  cost  to remove,  reasonably  store,  and/or  dispose  of  all  equipment  and  other improvements, including without limitation all antennas,  radios, batteries, generators,  utilities,  cabinets,  mounts,  brackets,  hardware,  cables,  wires, conduits,  structures,  shelters,  towers,  poles,  footings,  and  foundations, whether  above  ground  or  below  ground,  constructed  or  installed  in connection with the wireless facility, plus the cost to completely restore any areas affected by the removal work to a standard compliant with applicable laws.  In  establishing  or  adjusting  the  bond  amount  required  under  this condition,  the  Director  shall  take  into  consideration  any  information provided by the permittee regarding the cost to remove, reasonably store, and/or  dispose  of  the  wireless  facility  to  a  standard  compliant  with applicable laws. The performance bond shall expressly survive the duration of the permit term to the extent required to effectuate a complete removal of the subject wireless facility in accordance with this condition.

11. Landscaping.  All  landscaping  shall  comply  with  the  requirements  of Section 8(e) of the Regulations. The permittee shall replace any landscape features damaged   or displaced by the construction, installation, operation, maintenance,  or  other  work  performed  by  the  permittee  or  at  the permittee’s direction on or about the facility.

12. Trenching  and  Excavation.  Any  excavation  and/or  trenching  activities shall not disturb   the root systems of trees measuring 24 inches or more in diameter. Protective fencing, consistent with City Standard Details, should be  installed  around  street  trees  within  or  adjacent  to  the  work  area  to prevent  damage  to  branches,  trunks,  or  root  systems.  If  any  cultural resources  are  discovered  during  excavation,  trenching,  or  other construction activities, work shall be stopped immediately, and the Director of Community Development shall be notified. Directional boring should be used instead of trenching whenever possible to minimize interference with vehicular traffic and may be required by the City when working in streets that  have  been  recently  resurfaced  or  resealed.  When  trenching  is necessary,  all  trenches  shall  be  covered  at  the  end  of  each  workday,  in compliance with City standards and policies regarding trench plates. The 14 Attachment D

total time that a trench may remain open in any segment of the road system should  not  exceed  one  week  unless  a  longer  time  period  is  expressly authorized by the Director.

13. Construction Hours and Noise Control. Noise‐producing site preparation and construction activities shall comply with Municipal Code Section 10.48 and any additional conditions of approval. All trucks and equipment shall use  the  best  available  noise  control  techniques  and  equipment  including improved  mufflers,  intake  silencers,  ducts,  engine  enclosures,  and  noise‐ reducing shields or shrouds. Impact tools such as jackhammers, pavement breakers,  and  noise  drills  shall  be  hydraulically  or  electrically  powered wherever  feasible  to  avoid  noise  associated  with  compressed  air  exhaust from  pneumatically  powered  tools.  When  the  use  of  pneumatic  tools  is unavoidable,  an  exhaust  muffler  shall  be  used  on  the  compressed  air exhaust to lower noise levels. External jackets shall be used on tools where feasible  to  achieve  noise  reductions.  To  the  extent  feasible,  quieter procedures,  such  as  drilling  instead  of  jack  hammering,  shall  be  used.

Stationary noise sources shall be located away from sensitive receptors to the  extent  feasible.  If  location  within  25  feet  of  homes,  schools, neighborhood  parks,  or  retail  businesses  is  necessary,  stationery  noise sources  shall  be  muffled  and  enclosed  with  temporary  sheds,  unless permitted  otherwise  by  the  Director  of  Public  Works.  Trucks  and  other vehicles  should  not  be  permitted  to  idle  when  waiting  at  or  near  the construction site.

14. Dust and Stormwater Control. Construction sites shall be watered at least twice  daily  if  necessary  to  control  dust  caused  by  site  preparation  and construction  activities.  Watering  intervals  shall  be  increased  whenever wind  speeds  exceed  15  miles  per  hour,  or  as  necessary  to  control  dust.

Where feasible, reclaimed water shall be used for this purpose. All trucks hauling  soil,  sand,  paving  materials,  and  other  loose  materials  shall  be covered or required to maintain at least two feet of space between the top of the load and the top of the trailer. Streets shall be swept at the end of each workday  if  soil,  sand,  or  other  material  has  been  carried  onto  adjacent paved  streets  or  sidewalks.  When  feasible,  streets  shall  be  swept  using reclaimed water. Best Management Practices shall be used to prevent oil, dirt,  or  other  materials  from  construction  equipment  or  activity  from washing  into  the  City  storm drainage system. Water discharge resulting from  both  construction  and  underground  facility  drainage  shall  comply with  National  Pollutant  Discharge  Elimination    System  (NPDES) regulations.
15 Attachment D

15. Cost Reimbursement. The permittee acknowledges and agrees that (i) the permittee’s  request  for  authorization  to  construct,  install,  and/or  operate the wireless facility will cause the City to incur costs and expenses; (ii) the permittee shall be responsible to reimburse the City for all costs incurred in connection  with  the  permit,  including  without  limitation  costs  related  to application  review,  permit  issuance,  site  inspection,  and  any  other  costs reasonably  related  to  or  caused  by  the  request  for  authorization  to construct, install, and/or operate the wireless facility; (iii) any application fees required for the application may not   cover all such reimbursable costs and that the permittee shall have the obligation to reimburse the City for all such costs 10 days after receipt of a written demand for reimbursement  and reasonable  documentation  to  support  such  costs;  and  (iv)  the  City  shall have  the  right  to  withhold  any  permits  or  other  approvals  in  connection with the wireless facility until and unless any outstanding costs have been reimbursed to the City by the permittee.

16. Rearrangement and Relocation. The permittee acknowledges that the City, in its sole discretion and at any time, may (i) change any street grade, width or location; (ii) add, remove, or otherwise change any improvements in, on, under, or along any street owned by the City or any other public agency, including  without  limitation  any  sewers,  storm  drains,  conduits,  pipes, vaults, boxes, cabinets, poles, and utility systems for gas, water, electric, or telecommunications;  and/or  (iii)  perform  any  other  work  deemed necessary, useful, or desirable by the City (collectively, “City work”). The City reserves the rights to do any and all City work without any admission on its part that  the  City  would  not  have  such  rights  without  the  express reservation in the wireless ROW permit. If the Director determines that any City  work  will  require  the  wireless facility to be rearranged, relocated,  or removed, the permittee shall at its sole cost and expense do or cause to be done all things necessary to commence such rearrangement, relocation, or removal, within 60 days of written request to do so and diligently prosecute such  work  to  completion,  subject  to  City’s  reasonable  cooperation  with regards to permitting and/or licensing approvals. If the permittee fails or refuses  to  either  permanently  or  temporarily  commence  to  rearrange, relocate, or remove the wireless facility within 60 days after receiving notice from  the  Director,  the  City  may  (but  will  not  be  obligated  to)  cause  the rearrangement, relocation, or removal to be performed at the permittee’s sole cost and expense. The City may exercise its rights to rearrange, relocate, or remove the permittee’s wireless facility without prior notice to permittee when the Director determines that City work is immediately necessary to 16 Attachment D

protect public health, safety or convenience. The permittee shall reimburse the City for all costs and expenses in connection with such work within 10 days after receiving a written demand for reimbursement and reasonable documentation to support such costs and expenses.

17. Reserved.

18. Electric  Meters.  The  permittee  shall  comply  with  all  electric  utility requirements  for  electric  meters  and  enclosures,  including  making  any necessary  upgrades  and/or  modifications  to  electrical  facilities  at  the permittee’s expense. The permittee shall obtain all required permits for the upgrade or modification of electric meters, enclosures, wiring, and/or other equipment and shall restore any affected areas to its original condition that existed prior to installation of the equipment. The permittee shall work to ensure  all  electric  meters  are  screened  from  public  view  or  shall  provide written  evidence  demonstrating  why  screening  of  an  electric  meter  is infeasible. The Director may in their discretion require modifications to the application materials to better disguise the meter or otherwise hide it from view.

19. Insurance.  The  permittee  shall  secure  and  maintain  commercial  general liability insurance, including bodily injury and property damage, with limits of $2,000,000 per occurrence and $4,000,000 in the aggregate, or as otherwise established by agreement, and shall have coverage at least as broad as the Insurance Service Office (ISO) Form No. CG 0001 or its successor; provided, however,  that  the  Director  may  consider  proof  of  adequate  insurance sufficient  to  satisfy  the  requirements  of  any  license  agreement  between permittee and the City as proof of compliance with this condition. The City, the  City  Council,  and  the  City’s  boards,  commissions,  officers,  and employees shall be included as an additional insureds under the permittee’s policy.

20. Indemnification. The permittee shall indemnify, defend, protect, and hold harmless the City, the City Council, and the City’s commission members, officers,  and  employees  from  and  against  any  and  all  claims,  demands, losses,  damages,  liabilities,  fines,  charges,  penalties,  administrative  and judicial proceedings, orders, judgments, all costs and expenses (collectively, “claims”)  incurred  in  connection  with  activities  authorized  under  the wireless ROW permit or in connection with the construction, operation, or maintenance of the wireless facility, except to the extent that any such claim arises solely from the negligence or willful misconduct of the City, the City Council, or the City’s commission members, officers, and employees. In the 17 Attachment D

event the City becomes aware of any claims, the City will use best efforts to promptly  notify  the  permittee  and  the  private  property  owner  (if applicable)  and  shall  reasonably  cooperate  in  the  defense.  The  permittee expressly  acknowledges  and  agrees  that  the  City  shall  have  the  right  to approve,  which  approval  shall  not  be  unreasonably  withheld,  the  legal counsel  providing  the  City’s  defense,  and  the  property  owner  and/or permittee (as applicable) shall promptly  reimburse the City for any costs and expenses directly and necessarily incurred by the City in the course of the  defense.  The  permittee  expressly  acknowledges  and  agrees  that  the permittee’s indemnification obligations under this condition are a material consideration that motivates the City to approve any wireless ROW permit and  that  such  indemnification  obligations  will  survive  the  expiration, revocation, or other termination of the wireless ROW permit.

21. Truthful and Accurate Statements. The permittee acknowledges that the City’s approval relies on the written and/or  oral statements by permittee and/or persons authorized to act on permittee’s behalf. In any matter before the City in connection with the wireless ROW permit or the infrastructure approved  under  the  permit,  neither  the  permittee  nor  any  person authorized  to  act  on  permittee’s  behalf  shall,  in  any  written  or  oral statement, recklessly or intentionally provide material factual information that  is  incorrect  or  misleading  or  intentionally  or  recklessly  omit  any material  information  necessary  to  prevent  any  material  factual  statement from being incorrect or misleading. Failure to comply with this paragraph may result in permit revocation and other enforcement action under these Regulations or the Municipal Code.

22. Permit  Revocation.  Wireless  ROW  permits  may  be  subject  to  revocation under  Municipal  Code  Section  14.30.080(A).  The  Director  may  initiate revocation  proceedings  when  the  Director  determines  that  a  wireless facility  is  not  in  compliance  with  any  applicable  law,  including  without limitation  the  conditions  of  any  permit  issued  in  connection  with  the construction,  operation,  or  maintenance  of  the  facility.  The  Director  shall provide the permittee with written notice identifying (i) the facility; (ii) the violation(s) to be corrected; and (iii) the timeframe in which the permittee must  correct  such  violation(s),  and  shall  notify  the  permittee  that,  in addition to all other rights and remedies the City may pursue, the City may initiate revocation proceedings for failure to correct such violation(s). The Director may revoke a permit if said violation(s) are not corrected within 30 days  of  the  date  of  the  notice,  or  within  the  timeframe  to  correct  such violation(s)  stated  in  the  notice,  whichever  is  longer.  The  permittee  may 18 Attachment D

appeal the decision of the Director to the City Manager within 10 days of service of the decision via first class mail. If a timely and complete request for appeal is submitted, the City Manager shall conduct an administrative hearing  within  30  days  of  receipt  of  the  appeal.  The  City  Manager  may decide the issues presented de novo. The City Manager’s decision following the hearing shall be in writing, shall explain the basis for the decision, and shall be served upon the permittee by first class mail, to the address stated on the request for appeal form. The written decision of the City Manager shall be the final decision of the City effective on the date of mailing.

23. Record  Retention.  The  permittee  shall  retain  all  records  related  to  the construction,  operation,  and  maintenance  of  the  wireless  facility throughout the permit term, including without limitation the wireless ROW permit  application,  the  wireless  ROW  permit,  the  approved  plans  and photo  simulations,  any  RF  calculations  and  RF  testing  reports,  and  any other  permits,  approvals,  memoranda,  documents,  papers,  and  other correspondence  entered  into  the  public  record  in  connection  with  the wireless  ROW  permit  or  wireless  facility  (collectively,  “records”).  If  the permittee does not maintain such records as required by this condition, any ambiguities  or  uncertainties  that  would  be  resolved  by  inspecting  the missing records will be construed against the permittee. The requirements in this condition shall not be construed to create any obligation to create or prepare any records not otherwise required to be created or prepared by these Regulations or other applicable laws or regulations. Compliance with the requirements in this condition shall not excuse the permittee from any other  similar  record‐retention  obligations  under  other  applicable  laws  or regulations.

24. Lessee/Operator Bound. Any lessee of the permittee and/or any operator of an antenna or other equipment installed at the facility shall be bound by all appliable conditions of the wireless ROW permit.  Any failure of such lessee  and/or  operator  to  comply  with  all  appliable  conditions  of  the wireless ROW permit shall be deemed to be permittee’s failure.

25. Successors and Assigns. The conditions, covenants,  promises, and terms contained in the wireless ROW permit shall bind and inure to the benefit of the City and permittee and their respective successors and assigns. Prior to any voluntary assignment or assumption of rights or obligations under the permit, the permittee shall notify the City in writing of the assignment or assumption and shall provide all contact information required pursuant to these Regulations.
19 Attachment D

b. Right  to  Modify  Permit.  The  City  expressly  reserves  the  right  to  review  and modify the conditions of the wireless permit in the event of any change in federal law  that  expands  the  City’s  authority  with  respect   to  the  placement,  design,  or operation of the wireless facility, and otherwise authorizes the City to modify the permit and related conditions. In the event of any such change in law, the Director may take actions consistent with the amended law. The permittee shall be entitled to notice and an opportunity to be heard prior to any changes made to the permit or  conditions  authorized  by  any  such  changes  to  federal  law.  Nothing  in  this paragraph shall be construed to limit any vested right conferred to the permittee under state or federal law.
c. Special Conditions. The Director may modify, add, or remove conditions to any wireless ROW permit as they deem necessary or appropriate to (1) protect and/or promote the public health, safety, and welfare; (2) tailor the standard conditions in paragraph (a) of this Section to the particular facts and circumstances associated with  the  deployment  of  a  wireless  facility;  and/or  (3)  ensure  that  the  proposed deployment  complies  with  the  Municipal  Code,  the  Regulations,  generally applicable  health  and  safety  requirements,  and/or  any  other  applicable  laws  or regulations. As required by applicable FCC regulations, the Director shall ensure that any different conditions applied to wireless facilities are no more burdensome than those applied to other similarly situated infrastructure deployments.

SECTION 7.  LOCATION STANDARDS
a. Location  Preferences.  The  preferred  locations  for  wireless  facilities  installed  in public rights‐of‐way,    ordered from most preferred to least preferred, are set forth as follows:

1. Locations  where  collocation  of  equipment  with  existing  wireless  facilities  is feasible within preferred facility tiers 2 through 7.

2. Locations within mixed use or non‐residential districts.

3. Locations within residential districts on or along boulevards (arterials), as shown on the circulation network of the General Plan.

4. Locations  within  residential  districts  on  or  along  avenues  designated  as major collector streets, as shown on the circulation network of the General Plan.

5. Locations  within  residential  districts  on  or  along  avenues  designated  as minor collector streets, as shown on the circulation network of the General Plan.
20 Attachment D

6. Other locations within residential districts.

7. Any location within 1,000 feet of an existing or proposed wireless facility serving the same carrier and/or network.

8. Any  location  within  100  feet  of  a  property  that  is  eligible  for  protection under the State Public Resources Code Section 5020.1(j).

9. Any location within 25 feet of an occupied structure, residential dwellings, or schools.

10. New standalone poles that serve only the wireless facility and which do not house City owned streetlights or other publicly owned facilities.

11. Installations on wooden utility poles.

12. Any location where strand‐mounted equipment of any kind is proposed.

If  more  than  one  location  qualifies  as  the  most  preferred  location  under subparagraphs  (2)‐(6),  the  most  preferred  location  shall  be  the  location  that  is furthest from any occupied residential unit. Except as provided in Section 7(b), no wireless facility may be installed at a location within 1,000 feet of an existing or proposed wireless facility serving the same carrier and/or network. b. Findings for Installation in a Less‐Preferred Location. A wireless facility shall be installed at the most‐preferred location within 500 feet of the proposed location consistent with Section 7a, and shall be located at least 1,000 feet from any existing or proposed wireless facility serving the same carrier and/or network unless (1) the  applicant  demonstrates  that  installation  of  the  facility  at  a  less  preferred location  is  required  by  applicable  state  or  federal  law,  or  (2)  the  Director determines based on clear and convincing evidence that installation of the facility at a less‐preferred location is necessary to protect public health, safety, or welfare, based on specific characteristics of the location of the proposed facility, or (3) any other more preferred location is deemed technically infeasible. At the request of the Director, the applicant shall provide signal strength analyses, coverage maps, and/or an analysis of preferred site locations in support of any request to install a wireless facility at a less‐preferred location under this subparagraph. c. Prohibited  Support  Structures. Wireless  facilities  shall not  be  permitted  on  the following support structures:

1. Decorative poles (including historic or ornamental streetlight poles).

2. Traffic signal poles, mast arms, cabinets, or related devices or structures. 21 Attachment D

3. New,  non‐replacement  wood  poles,  or  any  utility  pole  scheduled  for removal or relocation within 24 months from the time the Director acts on the wireless ROW permit application.
d. Encroachments  Onto  or  Over  Private  Property.  No  antennas,  accessory equipment, or other improvements may encroach onto or over any private or other property  outside  the  public  right‐of‐way  without  the  property  owner’s  written consent and property owner’s provision  of written waiver that releases, waives and holds harmless City from any injury to property or persons associated with such encroachment into or onto private property.
e. No Interference with Other Uses. Wireless facilities and any associated antennas, accessory equipment, or improvements shall not be located in any place or manner that would physically interfere with or impede any of the following:

1. The view of any traffic sign, streetlight, or other traffic control device or any other view lines necessary for the safety of vehicles, bicycles, or pedestrians.

2. Worker  access  to  any  above  ground  or  underground  infrastructure  for traffic  control,  streetlights,  or  public  transportation,  including  without limitation any curb control sign, vehicular traffic sign or signal, pedestrian traffic sign or signal, or barricade reflector.

3. Access  to  any  public  transportation  vehicles,  shelters,  street  furniture,  or other improvements at any public transportation stop.

4. Worker access to above ground or   underground infrastructure owned or operated by any public or private utility agency.

5. Access to any fire hydrant, water valve, or water main.

6. Access  to  any  doors,  gates,  passage  doors,  stoops,  or  other  ingress  and egress points to any building appurtenant to the right‐of‐way.

7. Access to wastewater stations.

8. Access to any fire escape or other ingress or egress for fire safety purposes.

9. Any  other  similar  service  or  facility  that  benefits  the  City  or  the  health, safety, or welfare of its residents.
f. Additional Placement Requirements. In addition to the other requirements of this Section  7,  the  Director  shall  consider  the  following  criteria  in  determining  the placement of a wireless facility.

1. The facility should be placed on existing structures where feasible. 22 Attachment D

2. The facility should be placed as close as possible to the property corners or the property line   between two parcels that abut the public right‐of‐way.

3. The  facility  should  not  be  placed  in  front  of  the  primary  entrance  to  a residence or retail business or at any other location where it would unduly interfere with the operation of a business, including blocking views of the entrance or display windows.

4. The facility should not be placed within any sight distance triangles at any intersections,  street corners,  driveways,  and/or  other  points  of  ingress  or egress, unless the facility fully complies with site distance standards.

5. The facility should not be placed in any location that obstructs illumination patterns for existing   streetlights.
g. Replacement Poles. All replacement poles shall be (1) located in the same position, or as close to the removed pole as possible; (2) aligned with the other existing poles along the public rights‐of‐way; and (3) substantially similar in height and width to the existing pole and compliant with all applicable standards and specifications promulgated by the Director.

SECTION 8.  DESIGN STANDARDS
a. Compliance with Health and Safety Regulations. All wireless facilities shall be designed, constructed, operated, and maintained in compliance with all generally applicable  health  and  safety  regulations,  including  without  limitation  all applicable regulations for human exposure to RF emissions. b. Finishes. All exterior surfaces shall be painted, colored, and/or wrapped in flat, non‐reflective hues that match the underlying support structure or blend with the primary background. All surfaces shall be treated with graffiti‐resistant sealant.

All finishes shall be subject to the Director’s prior approval. c. Noise. Wireless facilities shall comply with all applicable noise control standards and regulations in the Municipal Code Chapter 10.48 and shall not exceed, either on  an  individual  or  cumulative  basis,  the  noise  limit  in  the  applicable  district.

Backup  generators  shall  be  operated  during  periods  of  power  outages  or  for testing only and shall not be tested on weekends, holidays, or between the hours of 5:00 p.m. and 9:00 a.m.
d. Lights.  All  lights  and  light  fixtures  must  be  aimed  and  shielded  so  that  their illumination effects are directed downwards and confined within the public right‐ of‐way in a manner consistent with all standards and specifications promulgated by the Director. All antennas, accessory equipment, and other improvements with 23 Attachment D

indicator or status lights must be installed in locations and within enclosures that mitigate illumination impacts visible from publicly accessible areas. e. Trees  and  Landscaping.  Wireless  facilities  may  not  remove  or  displace  any existing tree or landscape features without the prior approval of the Director.  Each removed  or  displaced  tree  or  landscaping  feature  must  be  replaced  by  trees  or landscape features approved by the Director and consistent with Department of Community  Development  landscaping  requirements  or  Department  of  Public Works  requirements,  whichever  is  applicable.  Any  replacement  tree  must  be substantially the same size as the removed or a displaced tree unless approved by the  Director.  The  permittee  shall  at  all  times  be  responsible  to  maintain  any replacement landscape features.
f. Signs  and  Advertisements.  All  wireless  facilities  that  involve  RF  transmitters must include signage that, consistent with applicable state and federal regulatory requirements,  accurately  identifies  the  facility  owner/operator,  the owner/operator’s site name or identification number, and a toll‐free number to the owner/operator’s network operations center. Wireless facilities may not bear any other  signage,  logos,  or  advertisements  unless  expressly  approved  by  the  City, required by law, or recommended under FCC or other United States governmental agencies for compliance with RF emissions regulations. Signage shall be no larger than 6‐inches by 6‐inches unless required to be larger by law. g. Site  Security  Measures.  Wireless  facilities  may  incorporate  reasonable  and appropriate  site  security  measures,  such   as  locks  and  anti‐climbing  devices,  to prevent unauthorized access, theft, or vandalism.  The Director shall not approve any  barbed  wire,  razor  ribbon,  electrified  fences,  or  any  similarly  dangerous security measures.
h. Shrouding.  All  antennas  and  associated  cables,  jumpers,  wires,  mounts,  masts, brackets, and other connectors and hardware shall be installed within a shroud or radome unless shrouding is not feasible. For pole‐top antennas, the shroud must match published City standards for size. The antenna shall be finished in a flat, non‐reflective color to match the underlying support structure. i. Antenna Volume. If shrouding  pursuant to Paragraph (h) of this Section is  not feasible,  each  individual  antenna  associated  with  a  wireless  facility  shall  not exceed  three  cubic  feet  in  volume.  The  cumulative  volume  for  all  unshrouded antennas at a wireless facility shall  not exceed (1) three cubic feet in residential districts or (2) six cubic feet in nonresidential districts. 24 Attachment D

j. Overall Height. No antenna may extend more than five and one‐half feet above the  support  structure,  plus  any  minimum  separation  between  the  antenna  and other pole   attachments required by applicable health and safety regulations. k. Horizontal Projection. Horizontal projections are prohibited except where other designs  are  not  feasible.  Side‐mounted  antennas,  where  permitted,  shall  not project (1) more than 24 inches from the support structure unless a greater distance is required to comply with legal requirements imposed by the CPUC; (2) over any roadway  used  for  vehicular  travel;  or  (3)  over  any  abutting  private  property without written authorization of the property owner.
l. Accessory  Equipment  Volume.  The  cumulative  volume  for  all  accessory equipment  at  a  single  wireless  facility  shall  not  exceed  (1)  nine  cubic  feet  in residential  districts  or  (2)  12  cubic  feet  in  nonresidential  districts.  The  volume limits in this subsection do not apply to any undergrounded accessory    equipment. m. Undergrounded Accessory Equipment.

1. Where  Required.  Accessory  equipment  (other  than  any  electric  meter  or emergency  disconnect  switch  when  required  by  the  electrical  provider) shall be placed underground when proposed in any underground district.

The  Director  may  waive  the  requirement  to  underground  accessory equipment if the total volume of accessory equipment is less than 9 cubic feet and the location and design of wireless facility otherwise complies with the requirements of Sections 7 and 8.

2. Vaults.  All  undergrounded  accessory  equipment  must  be  installed  in  an environmentally  controlled  vault  that  is  load‐rated  to  meet  applicable standards  and  specifications.  Underground  vaults  located  beneath  a sidewalk must be constructed with a slip‐resistant cover. Vents for airflow shall be flush‐to‐grade when placed within the sidewalk. All vault lids shall be constructed from materials rated for heavy traffic and acceptable to the Director. Only non‐toxic sealants may be used.
n. Pole‐Mounted Accessory Equipment.

1. Preferred  Concealment  Techniques.  Applicants  shall  place  pole‐mounted accessory equipment in the least conspicuous position on the proposed pole and at the proposed location. All above ground wires and cables   shall be installed within the interior of the pole or radome unless it is not feasible to do  so.  If  pole‐mounted  accessory  equipment  must  be  installed  on  the exterior of the pole, the equipment shall be concealed behind street, traffic, 25 Attachment D

or  other  existing  signs  to  the  extent  that  such  installation  complies  with applicable public health and safety regulations.

2. Orientation. Unless placed behind a street sign or some other concealment that  dictates  the  equipment  orientation  on  the  pole,  pole‐mounted accessory equipment should be oriented away from prominent views and shall  not  substantially  obstruct  a  view  from  the  primary  living  area  of  a residence (e.g., oriented toward the street).

3. Horizontal Projection.  Pole‐mounted  accessory  equipment  shall not project (i) more  than  24  inches  from  the  pole  surface  unless a  greater  distance  is required to comply with legal requirements imposed by the CPUC; (ii) over any  roadway     used  for  vehicular  travel;  or  (iii)  over  any  abutting  private property without the written consent of the property owner and property owner’s  provision  of  written  waiver  that  releases,  waives  and  holds harmless City from any injury to property or persons associated with such encroachment  into  or  onto  private  property.  All  pole‐mounted  accessory equipment shall be mounted flush to the pole surface. If applicable state or federal  laws  or  regulations  preclude  flush‐mounted  equipment,  the separation gap between the pole and the accessory equipment shall be no greater than required to comply with such laws or regulations and shall be concealed to the Director’s satisfaction.

4. Minimum  Vertical  Clearance.  The  lowest  point  on  any  pole‐mounted accessory equipment shall be at least eight feet above ground level adjacent to  the  pole  unless  applicable  state  or  federal  law  or  regulations  impose  a different  requirement.  If  applicable  laws  or  regulations  require  any  pole‐ mounted accessory equipment component to be placed less than eight feet above ground level, the clearance from ground level shall   be no less than required to comply with such laws or regulations.
o. Ground‐Mounted or Base‐Mounted Accessory Equipment

1. Placement  of  Ground‐Mounted  Equipment.  Ground‐mounted  equipment  is prohibited  unless  approved  by  the  Director.   Any  approved  ground‐ mounted  equipment  cabinets  shall  be  placed  six  inches  behind  the sidewalk, at least two feet from the curb, and two feet from driveway and curb  edges.  Pedestals  must  be  at  least  three  feet  from  fire  hydrants.

Installations must leave a minimum horizontal clear space for the path of travel of at least six feet, unless otherwise approved by the Director. The Director may require more clear space for travel in heavily used commercial areas  to  provide  sufficient  room  for  pedestrian  traffic.  On  arterial  streets 26 Attachment D

outside  underground  districts,  proposed  ground‐mounted  accessory equipment  should  be  completely  shrouded  or  placed  in  a  cabinet substantially similar in appearance to existing ground‐mounted accessory equipment  cabinets.  On  non‐arterial  streets,  the  preferred  means  of concealment of ground‐mounted facilities are as follows:
(i) Within a landscaped parkway, median or similar location, behind or among new or existing landscape features and painted or wrapped in flat, natural colors to blend with landscape features. (ii) If landscaping concealment is not feasible, disguised as other street furniture  adjacent  to  the  support  structure,  such  as,  for  example, mailboxes, benches, trash cans, or information kiosks.

2. Ground‐Mounted  Equipment.  No  ground‐mounted  accessory  equipment cabinets will be permitted.

3. Fire Protection. The exterior walls and roof covering of all ground‐mounted accessory equipment cabinets and equipment shelters shall be constructed of  materials   rated  as  nonflammable  under  the  Uniform  Building  Code.

Openings  in  all  above  ground  equipment  shelters  and  cabinets  shall  be protected against penetration by fire and windblown embers to the extent feasible.
p. Strand‐Mounted  Wireless  Facilities.  Strand‐mounted  wireless  facilities  are prohibited unless approved by the Director. Where permitted, no more than one strand‐mounted wireless facility may be installed (1) on any single span between two poles or (2) directly   adjacent to any single pole. The Director shall not approve any  ground‐mounted  equipment  in  connection  with  a  strand‐mounted  wireless facility unless the ground‐mounted equipment consists of a remote power source used  to  power  multiple  strand‐mounted  wireless  facilities.  Strand‐mounted wireless facilities shall not exceed one cubic foot in total volume. All equipment and other improvements associated with a strand‐mounted wireless facility must comply  with  all  applicable  health  and  safety  regulations.  Any  accessory equipment mounted on the pole shall be finished to match the underlying pole. “Snowshoes” and other spooled fiber or cables are prohibited, unless approved by the Director.
q. Utilities Serving Wireless Facilities.

1. Overhead  Lines.  The  Director  shall  not  approve  any  new  overhead  utility lines in underground districts. In areas with existing overhead lines, new communication  lines  shall  be  “overlashed”  with  existing  communication 27 Attachment D

lines to the maximum extent feasible. No new overhead utility lines shall be permitted  to  traverse  any  roadway  used  for  vehicular  transit.  Existing overhead  lines  that  serve  a  City  streetlight  pole  proposed  to  support  a wireless  facility  shall  be  placed  underground  with  the  installation  of  the facility.

2. Vertical Cable Risers. All cables, wires, and other connectors must be routed through conduits within the pole or other support structure, and all conduit attachments,  cables, wires,  and other  connectors  must  be concealed  from public view.   To the extent that cables, wires, or other connectors cannot be routed  through  the  pole,  the  applicant  shall  route  them  through  a  single external conduit or shroud that has been finished to match the underlying pole.

3. Spools  and  Coils.  Excess  fiber  or  cable  shall  not  be  spooled,  coiled,  or otherwise  stored  on  the  pole  outside  equipment  cabinets,  vaults,  or shrouds. Fiber or cable placement on existing poles shall have a      minimum safety  slack  for  sway  and  wind.  Looped  fiber  storage  for  future  use  is prohibited.

4. Electric Meters. Wireless facilities shall use flat‐rate electric service or other method that obviates the need for a separate above‐grade electric meter. If flat‐rate  service  is  not  available,  applicants  may  install  a  shrouded  smart meter.  If  a  ground‐mounted  equipment  cabinet  is  authorized  by  the Director,  an  electric  meter  may  be  integrated  with  and  recessed  into  the cabinet. Separate ground‐mounted electric meter pedestals are prohibited unless they are required by the electric service provider. r. Existing  Conduit  or  Circuits.  The  Director  may  condition  the  issuance  of  a wireless ROW permit to require the use of existing vaults, utility holes, conduits, ducts,  manholes,  electric  circuits,  and/or  other  similar  facilities  whenever available. Access to any conduit and/or circuits owned by the   City shall be subject to  the  Director’s  prior  written  approval,  which  the  Director  may  withhold  or condition  as  the  Director  deems  necessary  or  appropriate  to  protect  the  City’s infrastructure, to prevent interference with the City’s municipal functions, and to protect public health and safety.
s. Alternative  Design  Standards.  An  applicant  may  propose  alternative  design standards, which may be considered by the Director on a case‐by‐case basis. The Director  may  approve  an  alternative  design  standard  only  if  (1)  the  applicant demonstrates that strict application of the design standards in this Section 8 would conflict  with  applicable  state  or  federal  law  or  regulations,  or  (2)  the  Director 28 Attachment D

determines based on clear and convincing evidence that a variance from the design standards set forth in this Section 8 is necessary to protect public health, safety, or welfare,  based  on  specific  characteristics  of  the  proposed  facility.  Any  variance from the design standards set forth in this Section 8 shall be allowed only to the extent necessary to comply with state or federal law or regulations or to protect public health, safety, or welfare.