PUBLIC WORKS DEPARTMENT
CITY HALL
10300 TORRE AVENUE • CUPERTINO, CA 95014-5732
TELEPHONE: (408) 777-3354
CUPERTINO.GOV
CITY COUNCIL STAFF REPORT
Date: May 5, 2026
Subject
Fiscal Year (FY) 2026-2027 projects proposed to receive funding under the Road Maintenance and Rehabilitation Account (RMRA) established by Senate Bill (SB) 1; proposed funding of $1,692,995 in SB 1 revenues.
Recommended Action
Adopt Resolution No. 26-XXX (Attachment A) establishing a list of projects proposed to be funded by $1,692,995 of SB 1 revenues, estimated to be received in FY 2026-2027.
Reasons for Recommendation and Available Options
The Road Repair and Accountability Act, better known as SB 1, requires cities and counties to annually adopt a resolution establishing a list of projects that will receive Road Maintenance and Rehabilitation Account (RMRA) revenue each fiscal year. A copy of the certified resolution must be submitted to the State of California (State) by June 30, 2026. To satisfy the requirement, the project list must include a description and general location of each proposed project, the proposed schedule for the project’s completion, and the estimated life of the proposed improvements.
Though the primary purpose of the Road Repair and Accountability Act is to address deferred maintenance on local streets and roads, projects that address road safety are also eligible to receive funds. Section 2030 of the California Streets and Highway code says RMRA funds can be used for:
A. Road maintenance and rehabilitation.
B. Safety projects.
C. Railroad grade separations.
D. Complete street components, including active transportation purposes, pedestrian and bicycle safety projects, transit facilities, and drainage and stormwater capture projects in conjunction with any other allowable project.
E. Traffic control devices.
“A city or county may spend its apportionment of funds under the program on transportation priorities other than those allowable pursuant to this chapter if the city’s or county’s average Pavement Condition Index (PCI) meets or exceeds 80.” (Section 2037 of the California Streets
and Highway code.) The City’s current PCI is 80, and the FY 2026-2027 Pavement Maintenance projects (both Phase 1 and Phase 2) are anticipated to maintain the City’s PCI at 82.
The State distributes RMRA revenues to cities and counties monthly. To continue to receive these funds, each city and county must submit a FY 2026-2027 project list before the end of FY 2026. The City of Cupertino will receive an estimated amount of $1,692,995 of RMRA revenues in FY 25-26. The recommended list of projects for FY 2026-2027 is as follows:
1. 2026 Pavement Maintenance Phase 2 Project
2. 2027 Pavement Maintenance Phase 1 Project
3. 2027 Pavement Maintenance Phase 2 Project
This project list does not limit the City’s flexibility to fund projects based on local priorities, provided that funds are only expended on projects that are consistent with SB 1 eligibility requirements. Staff will document any variation between proposed projects and completed projects through the annual reporting processes established under SB 1.
Sustainability Impact
Maintaining and preserving the local streets and road system in good condition will reduce drive time and traffic congestion. This leads to reduced vehicle emissions, helping the City achieve air quality and greenhouse gas emission reduction goals.
Fiscal Impact
By adopting this Resolution, the City will be eligible to receive an estimated $1,692,995 from SB 1 in FY 2026-2027 to help fund the Pavement Management Program Projects. Revenues will be deposited into account 270-85-821 440-437 (Intergovernmental SB1 Road Maintenance/Rehabilitation). These revenues are included in the FY 2026-2027 Proposed Budget.
City Work Program (CWP) Item/Description
None
Council Goal
Quality of Life, Transportation
California Environmental Quality Act
The proposed Pavement Maintenance Projects are exempt from CEQA under California Code Regulations Section 15301(c) (maintenance of existing streets). _____________________________________
Prepared by: Jo Anne Johnson, Public Works Project Manager Reviewed by: Chad Mosley, Director of Public Works
Floy Andrews, Interim City Attorney
Approved for Submission by: Tina Kapoor, City Manager
Attachments:
A – Draft Resolution