Draft - June 16, 2026

PUBLIC WORKS DEPARTMENT
Roger Lee, Director

CITY HALL
10300 TORRE AVENUE ~ CUPERTINO, CA 95014-3266
(408) 777-3354 ~ FAX (408) 777-3333
CUPERTINO.ORG

CAPITAL IMPROVEMENT PROGRAMS
FY 2026-2027
Chad Mosley, Director
FY 26-27 CIP BOOK Page i

Capital Improvement Programs Fiscal Year 2026 – 2027
and 5-Year Plan

Table of Contents

Section Page #

1. Introduction Letter 1

2. Program Summary 4
A. Mission Statement 4
B. Background Information 4
C. Capital Improvement Program Development Process 4

1. Process Overview 5

2. Timeline 6
D. Project Priorities 7

1. Guiding Principles 7

2. Prioritization Process 7
E. Project Categories 8
F. GAAP Statement 9
G. Capital Budgeting Process 9
H. Funding Sources 9
I. Technological Innovations 10
J. Debt Issuance 12

3. New Projects, Additional Funding, and Five-Year Plan 13 A. FY 26 -27 New Projects and Additional Funding 13
B. Five -Year Plan 16
C. City Hall Improvements Project 18

4. Program Status Report 19
A. Overview 19
B. Achievements – Completed Projects 19
C. Current Projects 21

1. Facilities Projects 22

2. Parks and Recreation Projects 27

3. Streets and Infrastructure Projects 30

4. Transportation Projects 34

5. Sustainability and Energy Projects 38
D. Summary 39

5. Project Narratives 43
A. New Projects 44
B. Current Projects 55

FY 26-27 CIP BOOK Page ii

1. Facilities Projects 56

2. Parks and Recreation Projects 67

3. Streets and Infrastructure Projects 76

4. Transportation Projects 87

5. Sustainability and Energy Projects 104
C. Completed Projects 109

6. Glossary 113

7. Index 116

8. Appendix 118
A- CIP Policy 118
B – Fund Types 124
C – CIP Prioritization Process 127
D – FY 26-27 CIP Prioritization Matrix 136

Capital Improvement Programs Fiscal Year 2026 – 2027 and 5-Year Plan

July 1, 2026 (June 16, 2026 Draft)

Introduction

Honorable Mayor and members of the City Council:

We are pleased to present the City’s Capital Improvement Program (CIP), which outlines the planning, funding, and delivery of infrastructure investments that support Cupertino’s service delivery and long-term community priorities. This document provides a comprehensive overview of both active and new projects and reflects the City’s continued commitment to maintaining critical infrastructure in a fiscally responsible manner.

The Fiscal Year (FY) 2026–2027 CIP was developed in coordination with the City’s broader budget strategy and aligns with the City Council’s Strategic Vision and Work Program. As with the operating budget, this year’s CIP reflects a disciplined approach to resource allocation amid ongoing financial uncertainty. The City continues to balance infrastructure needs with its commitment to maintaining strong reserves and delivering essential services.

In recent years, the City has faced a range of fiscal challenges, including rising costs and increased demands on the General Fund. As noted in the City Manager’s budget message, the proposed increases to the Santa Clara County Sheriff’s contract represent significant and ongoing financial pressure. These constraints directly influenced the scope and pacing of the CIP, requiring a continued focus on core infrastructure and essential capital needs.

Historically, the City has relied on General Fund transfers to the Capital Reserve to support long-term infrastructure investments. Over the past five fiscal years, these contributions have varied due to broader budget conditions:
• FY 26–27: $2,000,000
• FY 25–26: $2,000,000
• FY 24–25: $0
• FY 23–24: $0
FY 26–27 CIP Book Page 2
• FY 22–23: $2,500,000

For FY 26–27, the CIP includes a total of $2,000,000 in General Fund support, reflecting the City’s continued caution regarding capital spending amid ongoing fiscal uncertainty. In addition, $600,000 in Developer In-Lieu Fees is included as part of the CIP to support eligible improvements. Consistent with prior Council direction, $4,730,000 will be transferred from the Capital Reserve to complete construction of the City Hall Annex/Emergency Operations Center (EOC) project at 10455 Torre Avenue. While the General Fund contribution remains modest, reinforcing the City’s disciplined financial posture, the use of the Capital Reserve demonstrates the City’s and Council’s commitment to advancing priority civic infrastructure. This approach is consistent with longer-term planning assumptions, which currently contemplate a potential future investment of approximately $55 million from the Future Use Fund to address the renovation or replacement of the structurally deficient City Hall facility.

The CIP continues to be funded through a combination of City revenues and external sources, including grants and dedicated funds. Because many projects span multiple years, funding is carried forward until project completion. Upon completion, any remaining balances are returned to their original funding source or to the Capital Reserve, reinforcing the City’s commitment to prudent financial stewardship.

To further strengthen the CIP, the City enhanced its project prioritization process for FY 26– 27 by formalizing a process framework supported by objective scoring criteria. This updated approach is designed to ensure that capital investments are evaluated and ranked in a transparent, consistent, and defensible manner across all departments. Collectively, these criteria balance critical considerations such as safety, regulatory compliance, fiscal responsibility, community impact, and alignment with City Council priorities. The resultant scoring matrix promotes a balanced consideration of the projects as part of the annual program evaluation. While this process provides a prioritized ranking of projects, it does not preclude the City from advancing other projects that it determines are necessary. The enhanced framework also remains flexible, allowing the City to adapt to evolving conditions while improving its ability to make informed, data-driven capital planning decisions.

Consistent with the City’s overall budget strategy, the CIP reflects a continued “back to basics” approach. Investment is prioritized toward maintaining and rehabilitating existing public assets, improving safety, and supporting essential services. Projects that introduce new amenities or require ongoing operational funding were carefully evaluated and, in many cases, deferred in order to preserve long-term fiscal sustainability.

While the City’s financial position remains stable, continued cost pressures and economic uncertainty will require ongoing caution in the near term. As a result, the CIP is expected to maintain its current focus on core infrastructure for the foreseeable future, with future expansion dependent on improvements in the City’s fiscal outlook.

FY 26–27 CIP Book Page 3

The CIP represents a collective effort across departments and reflects the dedication of City staff to maintain and enhance Cupertino’s infrastructure systems. Through careful planning, coordination, and financial management, the City will continue to deliver capital projects that support a safe, functional, and resilient community.

In summary, the FY 26–27 Capital Improvement Program reflects the City’s continued commitment to disciplined financial management and strategic investment in core infrastructure. In light of ongoing fiscal pressures and uncertainty, the City will continue to emphasize a “back to basics” approach over the next five years, prioritizing essential repairs, lifecycle maintenance, and improvements to existing assets. At the same time, targeted investments, such as the City Hall Annex/EOC project, demonstrate the City’s commitment to advancing critical civic infrastructure and planning for long-term needs. The enhanced prioritization framework further strengthens the City’s ability to allocate limited resources in a transparent and data-driven manner. While the CIP will remain focused on foundational services for the foreseeable future, the City will continue to evaluate opportunities to expand the program as financial conditions improve and resources allow.

Respectfully submitted,

Chad Mosley
Director of Public Works
Susan Michael
Capital Improvement Programs Manager

FY 26–27 CIP Book Page 4
Capital Improvement Programs Fiscal Year 2026 – 2027
and 5-Year Plan

Program Summary

Mission Statement
The City of Cupertino’s Capital Improvement Program (CIP) strategically plans and delivers infrastructure investments that maintain public assets, support community priorities, and ensure long-term fiscal sustainability, providing safe, reliable, and resilient infrastructure for current and future residents.

Background Information
A capital improvement project is defined as a project that enhances, restores, or extends the useful life of a physical asset, or adapts it for a new or different use. The CIP Division within the Department of Public Works is responsible for the planning, design, procurement, and construction management of all CIP projects. These projects encompass a wide range of public infrastructure, including streets, sidewalks, storm drainage systems, buildings, parks, and bicycle and pedestrian facilities. The division ensures that all public improvements are delivered in alignment with community expectations and in compliance with City and State of California regulations. Protecting public health and safety remains the highest priority in the planning and execution of all CIP projects.

The City undertakes various types of projects, and not all capital-related work is included in the CIP. What distinguishes a CIP project from maintenance efforts, Special Projects, or City Work Program (CWP) initiatives is the requirement for professional design services. These services typically involve specialized expertise, technical analysis, and formal documentation. Routine maintenance tasks—such as street resurfacing or sidewalk patching—are not considered CIP projects and are instead funded and managed through the City’s Operations Budget.

While most CIP projects focus on the design and construction of public infrastructure, some may involve preliminary planning efforts—such as feasibility studies or other technical assessments—that also require design and engineering input. In such cases, these planning- related efforts may be classified as CIP projects. These general guidelines vary depending on the specifics of each project.

Capital Improvement Program Development Process
The City of Cupertino’s CIP is developed through a structured, collaborative process that includes department input, technical evaluation, prioritization, and policy direction. This process ensures that capital investments are strategically planned, fiscally responsible, and aligned with the City’s long-term goals and community priorities.

FY 26–27 CIP Book Page 5
The CIP functions as a multi-year planning tool, identifying and funding infrastructure projects while balancing available resources with service demands and asset needs.

Process Overview
The Capital Program Development Process consists of the following key phases:

1. Project Identification and Department Input

2. Staff Review and Technical Evaluation

3. Project Prioritization and Funding Alignment

4. City Manager Review and Recommended CIP

5. Commission Review and Public Input

6. Planning Commission Review (General Plan Consistency)

7. City Council Review and Adoption
This framework reflects best practices for capital planning, including the use of defined project lists, cost estimates, prioritization criteria, and multi-year funding strategies.

Project Identification and Department Input
City departments identify and submit capital project requests based on:
• Asset condition and lifecycle needs
• Operational and service level requirements
• Regulatory or safety mandates
• Community input and emerging priorities
• Adopted master plans and Council direction
Each request includes scope, schedule, cost estimates, and justification, ensuring a comprehensive inventory of capital needs.

Staff Review and Technical Evaluation
Public Works staff review all submitted projects to:
• Confirm eligibility and refine project scope
• Validate cost estimates and schedules
• Evaluate feasibility and coordination with other projects • Identify potential funding sources and constraints
• Assess operating and maintenance impacts
• Ensure projects align with City Master Plans and the General Plan This step ensures that projects are well-defined, implementable, and consistent with City standards and financial policies.

Project Prioritization and Funding Alignment
Projects are then evaluated using a criteria-based framework to determine relative priority and funding readiness. (See
Project Priorities section below for detailed
methodology.) Projects are then aligned with available and projected funding sources across the multi-year CIP, ensuring a balanced and fiscally sustainable program.

FY 26–27 CIP Book Page 6
City Manager Review and Recommended CIP
The City Manager reviews the prioritized list of capital projects and proposed funding plan to ensure alignment with Citywide goals, financial policies, and available resources. This step balances competing needs across departments, considering both near-term infrastructure priorities and long-term fiscal sustainability. Adjustments may be made to project timing, scope, or funding to reflect policy direction and budget constraints. The outcome of this review is a Recommended CIP, which serves as the basis for Commission, Planning Commission, and City Council consideration.

Commission Review and Public Input
Following staff evaluation, projects are presented to applicable City commissions based on subject matter, such as transportation, parks, and sustainability. Commissions provide advisory input on project scope, priorities, and potential community impacts, helping to refine projects and ensure alignment with community values and adopted policies. This step enhances transparency and incorporates public perspectives early in the process.

Planning Commission Review (General Plan Consistency)
The Planning Commission reviews the proposed CIP to determine consistency with the City’s General Plan, as required by State law. This review ensures that planned capital investments support the City’s long-range land use, mobility, infrastructure, and environmental goals. The Commission provides a formal finding of consistency prior to final consideration by the City Council.

City Council Review and Adoption
The City Council reviews the Recommended CIP through public hearings as part of the annual budget process. The Council may modify project priorities, funding allocations, or schedules based on policy direction and community input. Upon adoption, the first year of the CIP becomes the City’s approved Capital Improvement Program Budget, while subsequent years serve as a planning framework to guide future investment decisions and are updated annually.

Timeline
The CIP is prepared annually in coordination with the City’s budget cycle:
• Fall/Winter: Department submissions and initial review • Winter/Spring: Staff evaluation, prioritization, and funding analysis • Spring: Preparation of Recommended CIP and Commission review • Late Spring: Planning Commission finding of General Plan Consistency and City Council review
• June: CIP adoption with the annual budget

FY 26–27 CIP Book Page 7
Project Priorities
The CIP prioritization process is designed to help the City of Cupertino transparently, consistently, and defensibly rank capital projects across departments. The framework balances safety, regulatory compliance, fiscal responsibility, community benefit, and City Council strategic priorities, while remaining flexible enough to adapt to changing conditions.

Guiding Principles:

The prioritization process should be:
• Transparent - Provide clear criteria and scoring that can be explained to decision makers and the Public.
• Equitable – Considers community-wide benefit and underserved populations • Data Driven – Based on measurable impacts where possible • Strategically Aligned – Supports adopted plans, policies, and Council goals • Financially Responsible – Accounts for lifecycle cost and funding availability

Prioritization Process
To further strengthen the CIP, the City has enhanced its program development by formalizing the CIP Prioritization Process, which includes a framework supported by objective scoring criteria. This updated approach is designed to ensure that capital investments are evaluated and ranked in a transparent, consistent, and defensible manner across all departments. The framework incorporates weighted prioritization categories as follows:
• Health and Safety (30%)
• Regulatory and Legal Mandates (15%)
• Asset Condition and Infrastructure Risk (15%)
• Climate Resilience and Sustainability (5%)
• Strategic Alignment (10%)
• Community Benefit and Equity (5%)
• Financial Leverage and Cost Effectiveness (15%)
• Project Readiness and Deliverability (5%)

The highest priority is given to projects that address public health and safety and to protect public and private property.

Staff evaluates and prioritizes new project proposals based on the factors listed above. The highest priority is given to projects that address public health and safety and that protect public and private property. Other factors, including available funding and resources to complete the project, are then considered within the context of other City goals.

A matrix of proposed CIP projects is developed using the criteria and factors listed. After the matrix is developed and adjusted, it is further evaluated within the context of current budget and staffing resources. This matrix is shared with Council and the Community, prior FY 26–27 CIP Book Page 8
to budget discussions, as a communication tool to facilitate the broader conversation of which projects are appropriate and required for the next fiscal year’s CIP.

Proposed and existing projects are reviewed in the context of fiscal responsibility and capacity to confirm that initiating and/or continuing the project is the best course of action.

All existing projects are also re-reviewed annually for prioritization.

As a result of this years annual review of existing projects, the City recommended that all existing projects be retained with their current level of funding.

Project Categories
The City of Cupertino’s CIP organizes projects into defined Project Categories to ensure consistency in planning, prioritization, and reporting. Grouping projects by asset category improves transparency, supports data-driven decision-making, and aligns investments with the City’s infrastructure systems and community priorities. The Project Categories reflect industry best practices and are consistent with the asset-based categories commonly used in municipal capital programs, including facilities, transportation, utilities, and equipment.

Facilities
Facilities projects include the construction, expansion, renovation, and major maintenance of City-owned buildings and structures. These projects ensure that public facilities remain safe, functional, and responsive to community needs.

Examples include:
• Civic buildings (City Hall, Service Center)
• Library and community facilities
• Major building system replacements (HVAC, roofing, accessibility upgrades, fire alarms)

Parks and Recreation
Parks and Recreation projects enhance and maintain the City’s parks, open space, and recreational amenities, supporting community health and quality of life.

Examples include:
• Park development and renovation
• Playgrounds, sports courts, and fields
• Pathways, landscaping, and irrigation systems
• Park amenity improvements and accessibility upgrades

Transportation
Transportation projects improve the safety, efficiency, and connectivity of the City’s multimodal transportation network.

Examples include:
• Bicycle and pedestrian facilities (bike lanes, sidewalks, trails) • Traffic signals and intelligent transportation systems • Roadway safety improvements and corridor enhancements FY 26–27 CIP Book Page 9
• Traffic calming projects

Streets and Infrastructure
Streets and Infrastructure projects focus on maintaining and improving the City’s core infrastructure systems, including roadway surfaces and stormwater conveyance systems.

Examples include:
• Bridge and structural improvements
• Storm drain systems, culverts, and outfalls
• Flood mitigation and drainage system upgrades

Sustainability and Energy
Sustainability and Energy projects support the City’s environmental goals and reduce long-term operational costs through energy efficiency and climate resilience.

Examples include:
• Renewable energy systems (e.g., photovoltaic installations) • Electric vehicle charging infrastructure
• Energy-efficient facility upgrades (LED lighting, building systems) • Climate adaptation and resilience improvements

GAAP Statement
The City prepares the CIP separately from the annual Operating Budget to provide a more detailed description of the City’s infrastructure needs, capital priorities, funding sources, and planned improvements. This CIP uses accounting methods consistent with Generally Accepted Accounting Principles (GAAP) in the United States of America, as established by the Governmental Accounting Standards Board (GASB), and follows standards established by the California Society of Municipal Finance Officers (CSMFO).

Capital Budgeting Process
Key capital revenue estimates are based on historical trends, current year actual revenues, adopted fee schedules, grant award notifications, and discussions with funding agencies.

Estimates for recurring revenues are projected using recent collections and anticipated economic conditions, while grant revenues are included when funding has been awarded or is reasonably expected to be received. Capital projects are budgeted on a project-by-project basis, and appropriations approved by the City Council remain in effect until the project is completed or formally closed.

Funding Sources
Cupertino’s CIP is funded through a combination of local revenues, restricted special revenues, reserves, developer-related fees, and external grant funds. Funding is matched to the purpose and eligibility of each project so that limited discretionary resources can be focused on the City’s highest organizational priorities. Consistent with the City’s current strategic direction, the CIP emphasizes fiscal resilience, protection of public health and safety, preservation of existing infrastructure, emergency preparedness, mobility and FY 26–27 CIP Book Page 10
transportation safety, parks and recreation asset stewardship, and sustainability investments that reduce long-term operating costs.The list below describes the primary sources of funding for the CIP. Refer to Appendix B – Fund Types for additional information.

• General Fund and Capital Reserve: These are the City’s most flexible local sources and are used primarily for core infrastructure needs, facility rehabilitation, emergency preparedness projects, and other high-priority capital investments where no dedicated outside funding is available. Their use reflects the City’s emphasis on fiscal discipline, asset preservation, and advancing essential civic infrastructure. • Developer Fees and In-Lieu Contributions: Developer-related revenues, including eligible in-lieu or impact fee proceeds, help fund improvements needed to support growth and offset development impacts. These sources are typically directed toward transportation, park, and other infrastructure improvements consistent with the legal restrictions of the fee program and the City’s goal of aligning growth with infrastructure capacity.
• Transportation Special Revenues: Restricted transportation revenues—such as gas tax and road maintenance funds, transportation sales tax allocations, and other formula-based sources—support street rehabilitation, pavement preservation, traffic safety, bicycle and pedestrian improvements, and related mobility projects. These funds help advance the City’s priorities for public safety, system reliability, and multimodal connectivity.
• Grant Funding: Federal, State, regional, and county grants are an important source of leverage for eligible projects, particularly for transportation safety, active transportation, sustainability, and resilience improvements. The City actively pursues grant opportunities to stretch local dollars, accelerate priority projects, and improve overall cost effectiveness.
• Dedicated and Restricted Funds: Certain projects may also be supported by dedicated revenues or special-purpose funds that can only be used for specific capital purposes. These sources are applied where eligible to ensure compliance with funding restrictions while supporting the City’s broader infrastructure and service objectives.

By using the most appropriate funding source for each project, the City can maintain a balanced and sustainable CIP over multiple years. This funding approach supports Cupertino’s organizational priorities by directing flexible resources to the most critical needs, maximizing external funding where available, and reinforcing a “back to basics” capital strategy centered on safety, infrastructure reliability, responsible stewardship of public assets, and long-term financial sustainability.

Technological Innovations
The City of Cupertino utilizes current computer technologies and data-driven tools in the development, analysis, and production of its CIP. These tools enhance coordination across departments and improve data accuracy throughout the capital planning process.

FY 26–27 CIP Book Page 11

Document Development and Production
The CIP document is developed using standardized templates, spreadsheet-based models and planning tools, and document management tools that support consistency, efficiency, and collaboration. These tools allow for the integration of project data, financial information, and narrative content, ensuring the CIP remains accurate, accessible, and regularly updated.

Geographic Information Systems (GIS)
GIS data is used to support capital planning and project coordination. GIS mapping enables staff to:
• Identify project locations and infrastructure systems • Evaluate spatial relationships and service gaps
Maps included in the CIP are developed using GIS data layers such as streets, facilities, parks, and storm drainage systems, providing a clear and visual representation of the City’s capital investments.

Budget Development and Financial Tools
The City utilizes its municipal financial system, along with spreadsheet-based models and planning tools, to develop the CIP and Capital Budget. These tools support:
• Multi-year revenue and expenditure forecasting
• Evaluation of funding sources, including General Fund, grants, and developer fees • Analysis of project costs, timing, and cash flow
• Assessment of long-term fiscal impacts
The integration of the CIP with the City’s financial system ensures consistency between the capital program and the annual operating budget, supporting sound financial planning and reporting.

Data-Driven Analysis and Asset Management
Cupertino applies data-driven tools to identify infrastructure needs and inform project prioritization. These include:
• Infrastructure condition assessments to identify building repair and replacement needs
• Asset tracking and lifecycle analysis to evaluate infrastructure performance over time
These tools support objective, evidence-based decision making and help ensure that capital investments are prioritized based on risk, condition, and service impact.

//

//

//

//
FY 26–27 CIP Book Page 12
Debt Issuance
The City currently maintains debt obligations related to Certificates of Participation issued for City Hall, Community Hall, and the Library. The City is expected to complete these debt payments by FY 29–30 and will continue to pay approximately $2.7 million annually in principal and interest until that time. These payments are funded through transfers from the General Fund to the Debt Service Funds. While the City maintains these existing debt obligations, no current or new Capital Improvement Program projects included in this document will be debt-funded.

FY 26–27 CIP Book Page 13
Capital Improvement Programs Fiscal Year 2026 – 2027
and 5-Year Plan

New Projects, Additional Funding, and Five-Year Plan

FY 26 -27 New Projects and Additional Funding
The Fiscal Year (FY) 26–27 CIP adds five new projects and additional funding for two existing projects as part of the FY 26-27 budget year. Identified through the City’s annual capital planning and prioritization process, these additions to the program reflect the City’s continued “back to basics” approach to infrastructure investment, while continuing to address high-priority infrastructure needs, maintain momentum on active projects, and advance select new investments that align with available funding, project readiness, and City organizational priorities. The sections that follow provide a summary of the recommended scope, funding, and rationale for each project.

TABLE - NEW & ADDITIONALLY FUNDED CIP PROJECTS
Project name Project Description FY 26 -27
Funding

INTERNAL
Funding

EXTERNAL
Funding
BBF Golf Course
Pro Shop
Renovation
Interior renovation to improve
functionality and code
compliance.
120,000 120,000 0
Blesch Property
Improvements
Demolition of the existing
residential building, replace with
minimal grading, natural habitat
and modest pathway[s].

TBD TBD TBD
Memorial Park
Pickleball Sound
Attenuation
Provide sound attenuation and a
new structurally reinforced
fence.
150,000 150,000 0
Sports Center
Courts
Resurfacing
Resurfacing the courts to
provide safe and consistent
surfaces.
210,000 210,000 0
SCB/SR 85 NB
ramp Intersection
improvements
Improve traffic conditions for all
users at this intersection.

Developer In-Lieu fees funded.
600,000 0 600,000
City Hall Annex *Additional Funding for existing
project.

Renovation of 10455 Torre
Avenue site to include the City’s
Emergency Operations Center
(EOC), and workplace for use as
interim City Hall.
5,000,000 5,000,000 0

FY 26–27 CIP Book Page 14
Facilities
Condition
Assessment
Implementation
(FCA)
*Additional Funding for existing
project.

Implement priority
recommendations identified in
the Facility Condition
Assessment reports.
1,250,000 1,250,000 0

subtotal 7, 330 ,000 6, 730 ,000 600,000
Table Note: Green field indicates Parks and Recreation category projects, gold field indicates Facilities projects, blue field represents Transportation category projects, orange field indicates Streets and Infrastructure projects, and magenta field indicates Sustainability and Energy category projects.

BBF Golf Course Pro Shop Renovation
The Blackberry Farm Golf Course Pro Shop serves more than 40,000 golfers annually and is central to the visitor experience. However, the facility has not been comprehensively renovated in many years and is now outdated, inefficient, and out of alignment with current accessibility and building standards. This project proposes a full renovation to improve functionality, safety, and customer service. The upgrades will address deferred maintenance, reduce operational and safety risks, and ensure the pro shop reflects the level of service and accessibility expected of a City-owned facility.

Blesch Property Improvements
The Blesch property is an approximately 28,000 square foot parcel, currently developed with a single-family residence. While the structure has been used for auxiliary City purposes since acquisition, it is not suitable for use as a public facility. Significant repairs, accessibility improvements and reconfiguration would be required for any public use. Additionally, the site is located within the Federal Emergency Management Agency (FEMA) Flood Zone AE, with more than half of the property situated within the designated floodway. Being in a FEMA designated floodplain results in constraints which substantially limit the feasibility of maintaining or constructing vertical structures on the site and impose additional regulatory requirements, review timelines, and costs for any building construction. This project proposes to demolish the existing residential building and infill the site with low-level native plantings and modest pathways.

Public Works will analyze the project based on the direction provided by City Council and will return to City Council with a cost estimate for a budget request to begin the project in earnest.

Memorial Park Pickleball Sound Attenuation
Adjacent to the pickleball courts within Memorial Park, neighboring residents have concerns about the degradation of the acoustic environment of their residences. Pickleball is very popular and generates great community. By providing sound attenuation to mitigate the noise, we hope to create a better environment for all. After an initial acoustical analysis, this project will provide sound attenuation measures at the Memorial Park Pickleball courts.

The installation of the sound panels will require a new structurally-reinforced fence.

FY 26–27 CIP Book Page 15

Sports Center Courts Resurfacing
The tennis court surfaces have deteriorated due to extended use and weather exposure and are now beyond their typical five- to seven-year lifespan (last resurfaced in 2016).

Resurfacing will prevent further damage, reduce liability, and avoid more costly repairs in the future. This project will resurface all courts at the Sports Center to maintain a suitable and safe playing environment.

SCB/SR 85 NB ramp Intersection improvements
At the intersection of Stevens Creek Boulevard and SR 85’s northbound ramp, the existing high-speed on-ramp creates safety risks for bicyclists and pedestrians. The improvements include a tighter ramp turn, dedicated signal phasing, a separated bike lane, and a protected pedestrian crossing to significantly improve safety. These improvements were required as part of the Westport development, but Caltrans Permitting delays prevented their completion, leading the City to collect in-lieu funds to complete the project. The project now requires final design completion and Caltrans permit approval before proceeding.

The project includes design, construction, and project management for improvements at the intersection. Improvements include a separated Class IV bike lane, a tightened right-turn on-ramp, and traffic signal upgrades providing protected movements for vehicles, bicyclists, and pedestrians. The project will retain a civil engineering consultant to finalize design and obtain necessary Caltrans approvals.

City Hall Annex: Additional Funding
The proximity of this property to the Civic Center, and its central location within the City, lends itself to numerous uses, including a satellite and/or interim City Hall facility. Overall, the project scope includes programming, planning and building facility improvements to facilitate short-term and long-term use[s] of the building. Emergency Operations Center (EOC) program and requirements were added to the scope of this project in late 2022.

The $5,000,000 in additional funds will enable the design and construction to proceed in line with the projected costs of the project. Public Works will return to City Council once construction bids are received, to award the project.

Facilities Condition Assessment (FCA) Implementation: Additional Funding The 2017/18 FCA report and the 2022 FCA report assessed the condition of nearly every City-owned facility. Several projects were identified as high priority facilities with significant deficiencies that need to be addressed to avoid costly repairs and extended service interruptions. This ongoing initiative to implement projects from the prioritized recommendations of the reports addresses all but one of the the Priority One projects listed.

The remaining project is planned to be part of FY 27-28 CIP proposal. Refer to the “Program Status Report”section of this document, for additional information on the FY 26-27 projects planned.

FY 26–27 CIP Book Page 16
Fiscal Impact
The FY 26-27 CIP’s new and annually funded projects require an allocation of $6,730,000 from Capital Reserve and General Fund, and $600,000 from Developer In-Lieu fees previously collected. The annual transfer from the General Fund is planned at $2,000,000.

The remaining $4,730,000 can be accommodated by the Capital Reserve.

TABLE – FISCAL IMPACT FY 26-27 CIP FUNDING
Fund/Description Amount
FY 26 -27 CIP New & Additionally funded
projects
$7,330,000
FY 26-27 Developer In-Lieu funds ($600,000)
City Funds required $6,730,000
General Fund Annual Transfer to CIP ($2,000,000)
Capital Reserve Required $4,730,000

Capital Reserve Accounting Amount
Capital Reserve (2/21/26) $10,243,497
Capital Reserve Required $4,730,000
Required Minimum Reserve maintained $5,000,000
Capital Reserve Available (beyond min.) $513,497

Five-Year Plan
Building upon the five-year plans of previous years, as well as input from stakeholders, the updated five-year CIP plan is included below.

TABLE - FY 26-27 CIP FIVE-YEAR PLAN
Projec t FY 26 -27
Funding
Year 2
FY 27-28
Projected
Cost
Year 3
FY 28-29
Projected
Cost
Year 4
FY 29-30
Projected
Cost
Year 5
FY 30-31
Projected
Cost
City Hall Annex
(Additional Funding)
5,000,000
FCA Implementation
(Additional Funding)
1,250,000 1,300,000

BBF Golf Course Pro
Shop Renovation
120,000
Blesch Property
Improvements
TBD
Memorial Park
Pickleball Sound
Attenuation
150,000
Sports Center Courts
Resurfacing
210,000
FY 26–27 CIP Book Page 17
SCB/SR 85 NB ramp
Intersection
improvements
600,000
ADA Improvements
(Annually funded)

100,000 110,000 120,000 125,000
Outfalls Repairs
(Annually funded)

600,000 300,000 600,000 600,000
BBF Golf Renovation:
minimal repairs

1,580,150

Park Shade
Structures (5)
1,000,000 500,000
totals 7,330,000 2,000,000 1,990,150 1,720,000 1,225,000 City Hall
Improvements*
46,353,570 5,017,464
7,330,000 48 ,353 ,570 7,007 ,614 1,720,000 1,225,000 Table Notes:

1. Green field indicates Parks and Recreation category projects, gold field indicates Facilities projects, blue field represents Transportation category projects, orange field indicates Streets and Infrastructure projects, and magenta field indicates Sustainability and Energy category projects.

2. Current annual CIP funding is budgeted at $2 million/year. Proposed annual CIP funding that exceeds $2 million/year requires additional funds beyond the $2 million annual funding being allocated to the program. Where possible, staff will search for external funding to supplement projects.

3. Project estimates may be refined prior to future requests for funding. Escalation factors are applied to cost estimates in future years.

4. *The Accounting for the five-year plan of the City Hall Improvements project is a separate line item as it will most likely be funded from the Future Use Fund, whereas the remainder of the CIP will most likely be funded from the Capital Reserve and/or the General Fund.

Based on current economic forecasts, the City’s baseline CIP funding for the foreseeable future is estimated at approximately $2,000,000 annually. The five-year CIP has been structured to align with this funding level, with these base funds continuing to support smaller priority projects focused on health and safety and the rehabilitation of existing infrastructure.

However, two significant Council-directed initiatives, the City Hall Annex and the City Hall Improvements project, require funding beyond the base program. Accordingly, the FY 26– 27 budget includes an additional $4,730,000 from the Capital Reserve to support the City Hall Annex project. In addition, a total of $51,371,034 will be proposed in FY 27–28 and FY 28–29 from the Future Use Fund to complete the City Hall Improvements project.

FY 26–27 CIP Book Page 18
City Hall Improvements project
In December 2025, City Council approved the scope and increased funding for the City Hall Improvements project. In the December 16, 2025 staff report, the projected expenditures and encumbrances (e.g. contracts) for the renovation project were distributed over the next five fiscal years:

TABLE - CITY HALL IMPROVEMENTS PROJECTED SPENDING (12/16/25) FY 25 -26 FY 26 -27 FY 27 -28 FY 28 -29 FY 29 -30 totals Projected
Expenditures
$793,824 $1,329,109 $7,704,743 $22,501,089 $22,042,269 $54,371,034 Projected
Encumbrances
$1,555,777

$3,824,198 $43,973,600 $5,017,464 $ 0 $54,371,034

Using those figures and considering the project’s currently approved funding of $3 million, the five-year plan for that project aligns as indicated in the table below.

TABLE - CITY HALL IMPROVEMENTS FIVE-YEAR PLAN
Project/ Current
Funding
FY 26 -27
Funding
Year 2
FY 27-28
Projected
Cost
Year 3
FY 28-29
Projected
Cost
Year 4
FY 29-30
Projected
Cost
Year 5
FY 30-31
Projected
Cost
City Hall

$3,000,000* $46,353,570 $5,017,464 $0 $0
*The funding available for the City Hall project before FY25-26 was $500,000 and an additional $2,500,000 was approved in December 2025 for a total of $3,000,000. Years 2-5 have yet to be approved.

Going forward, funding for the City Hall project is expected to be drawn primarily from the Future Use Fund, as discussed in December 2025. For clarity, the project is shown here as a separate line item. However, years 2–5 are anticipated to have significant impacts on the CIP, both financially and in terms of staffing resources.

Summary
In summary, the FY 26-27 CIP includes two major projects previously approved by City Council, along with long-deferred improvements to existing City facilities. The five-year plan prioritizes rehabilitation of aging infrastructure, investments that extend asset life cycles, and capital improvements that support public health, safety, and overall community well-being.

FY 26–27 CIP Book Page 19
Capital Improvement Programs Fiscal Year 2026 – 2027
and 5-Year Plan

Program Status Report

Overview
This section provides a status report on the existing and completed projects, broken into five categories of projects for ease of discussion. Allocation of projects into a category does not have direct financial implications and many projects could be placed into more than one category. However, the classifications are useful for reviewing the distribution of capital funds by asset types. Wherever possible, color coding is used to illustrate the project category, as indicated in the list below.

CATEGORY LEGEND:
1 Facilities: Yellow
2 Parks and Recreation: Green
3 Streets and Infrastructure: Orange
4 Transportation: Blue
5 Sustainability and Energy: Maroon

Within each category’s section, you will find
A. Funding Summary Table,
B. Status and Prioritization of Existing Projects, and C. Annual Progress [projections for five-year period].

Achievements – Completed Projects
In spite of limited resources in the past year, the CIP Division has successfully completed three projects and three additional projects as part of the FCA Implementation project.

Projects completed in FY 25-26, or which are scheduled for completion this year include:
• All-Inclusive Play Area & Adult-Assistive Bathroom Facility at Jollyman Park • City Lighting LED improvements
• Bridge Preventative Maintenance Program (BPMP)
• FCA: Senior Center Fire Alarm System Upgrade
• FCA: Quinlan Community Center Chiller replacement
• FCA: Quinlan Community Center and Sports Center flat roofs replacements*

Staff anticipates that these projects will underspend their respective budgets by approximately $1,000,000. These underspent funds will be returned to the Capital Reserve (or other appropriate accounts based on the original source of any restricted funds). Public Works and Finance staff work together as part of the year-end process to close out completed projects, presenting this information as part of the first quarter report for the following fiscal year.

FY 26–27 CIP Book Page 20

TABLE – FY 25-26 COMPLETED CIP PROJECTS
Cat. Project name Project
Description
Year
Initiated
City
Funding
Grant
Funding
Developer
Funds
Project
Budget
Remaining
Funds*
P All Inclusive
Play Area &
Adult-Assistive
Bathroom
Facility
(Jollyman Park)
At Jollyman Park,
Design and
Construct an all-
inclusive
playground.
(Externally Funded,
in part)
FY18 -19 1,230,000 4,891,999 381,035
SCC AIPG grant FY18 -19 1,448,201
CA P&R grant FY21 -22 1,000,000
PG&E donation FY21 -22 25,000
CAP Allocation FY22 -23 652
City: Adult -assistive
bathroom added
FY22 -23 850,000
Art In -lieu fees FY23 -24 338,146
ST City Bridge
Maintenance
Repairs Project
(Bridge
Preventive
Maintenance
Program, or
BPMP)
Repair of five City
bridges as
recommended in
the Caltrans Bridge
Report along with
additional
improvements to
prolong the useful
life of the bridges.

FY15 -16 165,000 2,186,173 213,559
City Funding FY16 -17 535,000
FHWA FY16 -17 571,151
CAP Allocation FY22 -23 10,068
FHWA FY22 -23 716,296
FHWA FY23 -24 95,227
FHWA FY24 -25 510,521
City Funding FY24 -25 300,000
City Funding FY24 -25 1,176,105
ST City Lighting
LED
Improvements
Transition of City's
streetlight
infrastructure to
LED fixtures to
reduce light
pollution and
energy cost.
(Partially grant
funded)
FY21 -22 50,000 1,350,000 403,087
City Funding FY22 -23 1,300,000
EECBG grant FY23 -24 125,790
3 subtotal 5,616,825 4,467,186 363,146 8,428,172 997,682 *Table Note: The funds indicated in the “Remaining Funds” column are a calculation based on the transactions to date as of February 2026, not including contract encumbrances which may not yet be expensed.

FY 26–27 CIP Book Page 21
Current Projects
The Fiscal Year (FY) 25-26 Capital Improvement Program (CIP) included 24 projects, and three additional projects that were successfully completed. The CIP continues to advance previously approved, strategically-aligned projects and prioritizes safety through the repair and revitalization of existing infrastructure to preserve City facilities. The magnitude of projects also considers the current staffing levels and ensures that future projects are planned in a way that aligns with available resources for effective execution.

TABLE – FY 25-26 CIP PROJECTS LIST
F1 ADA Improvements (Annually funded)
F2 Facilities Condition Assessment (FCA) Implementation F3 City Hall Annex
F4 City Hall Improvements
F5Q Library Expansion Project: landscaping & courtyard P1 Lawrence Mitty Park and Trail Plan
P2 MRP West Parking Lot Improvements (Habitat monitoring) P3Q Annual Playground Replacement
P4Q Park Amenity Improvements
ST1 Outfalls Repairs
ST2 Vai Avenue Outfall
ST3 Stevens Creek Bridge Repair
ST4 McClellan Road Bridge Reconstruction
ST5 Street Light Installation - Annual Infill (Annually funded) T1 Stevens Creek Blvd CL IV Bikeway - Phase 2 Design & Phase 2A Construction T2 Roadway Safety Improvements (HSIP)
T3 Tamien Innu - East Segment
T4Q Tamien Innu - Central Segment
T5Q Tamien Innu - West Segment
T6Q Stevens Creek Blvd CL IV Bikeway - Phase 2B Construction T7Q Stevens Creek Blvd CL IV Bikeway - Bandley Dr. Signal T8Q School Walk Audit Implementation
SU1 Electric Vehicle Charging Station (EVCS) expansion - Service Center SU2 Photovoltaic Systems Design & Installation

Facilities Projects
Funding Summary
There are four funded and active Facilities projects, and one other funded project in the queue. (Yellow highlights new projects/funding, green highlights funding added during Q2 or Q3 of FY 25-26. Red text indicates grant funding that requires acceptance by Council).

Two projects received additional funding with the FY 26-27 budget and one project received additional funding within the FY 25-26 budget year.

FY 26–27 CIP Book Page 22

TABLE 1 –FACILITIES PROJECTS, FUNDING SUMMARY
# Project name Project
Description
Year
Initiated
City
Funding
Grant
Funding
Developer
Funds
Project
Budget
Remaining
Funds*
F1 ADA
Improvements
(Annually
funded)
Ongoing program to
improve
accessibility at all
public facilities
throughout the City.
(annually funded)
FY15 -16 865,000 979,984 301,993
CAP Allocation FY22 -23 4,984
City Funding FY25 -26 110,000
F2 Citywide
Facilities
Condition
Assessment
Implementation
(FCA)
Implement priority
projects identified
in the FCA reports.

FY18 -19 1,000,000 4,613,782 2,383,423
CAP Allocation FY22 -23 6,470
City funding FY23 -24 1,000,000
CDBG FY23 -24 367,951
CDBG (budget
mod. required)
FY24 -25 49,361
City Funding FY25 -26 940,000
City Funding FY26 -27 1,250,000
F3 City Hall Annex Renovation of
10455 Torre Avenue
site to include the
City’s Emergency
Operations Center
(EOC), and
workplace for use
as interim City Hall.

FY21 -22 3,000,000 8,025,000 2,566,456
City Funding FY21 -22 25,000
City Funding FY26 -27 5,000,000
F4 City Hall
Improvements
Renovation of the
existing City Hall
building with
upgrades to the
infrastructure and
interior workplace
environment.

FY21 -22 500,000 3,000,000 2,918,681
City Funding FY25 -26 2,500,000
F5Q Library
Expansion
Project
(landscaping
and other misc.
scope)
Grant funding (CPF,
Ro Khanna)
planned to
complete the
courtyard and
landscaping scopes
of work initiated
FY19 -20 8,705,438 9,705,438 1, 391,912
FY 26–27 CIP Book Page 23
with the 2022 -23
project.

CPF (budget mod.
required)
FY24 -25 1,000,000
5 subtotal 24,906,892 1,417,312 0 26,324,204 9,562,464 *Table Note: The funds indicated in the “Remaining Funds” column are a calculation based on the transactions to date as of February 2026, not including contract encumbrances not yet expensed.

Also, it does not fully account for the amount of grant funds that are expensed/received to date. If the project were to be defunded, for example, a more thorough accounting of the funds remaining on the project would be required.

Status and Prioritization of Existing Projects
F1. ADA Improvements: Public agencies in California are required to have ongoing programs to remove barriers to facilities, improving accessibility to entrances, bathrooms, parking, etc. This fund is applied to ongoing improvements in playgrounds, parks, and buildings.

Prioritization : Ongoing improvements to City facilities are necessary to ensure compliance with ADA laws. These projects are a priority in terms of Health and Safety, Regulatory/Legal Mandates, and Asset Conditions.

F2. Facilities Condition Assessment Project (FY 26-27 additional funding): In 2018 the “Comprehensive Facility Condition and Use Efficiency Assessment” report was completed.

This report was updated in 2022 by the “Facility Condition Assessment” (FCA). The FCA reviewed 48 facilities at 24 locations. The report identified $28.8 million of renewal projects, with $4 million in priority one projects in 2022 costs. The 2022 FCA report explained that “…conditions in this [priority one] category require immediate action to: a) correct a cited safety hazard, b) stop accelerated deterioration, and/or c) return a facility to operation.

Deficiencies in this category should be addressed in 0-12 Months.” That was almost five years ago.

The highest-priority projects include upgrades to life-safety systems and HVAC improvements. Other safety upgrades listed as Priority 1 are included in the work plan below. With the exception of the Library Fire Alarm System (FAS) planned for FY27-28, this completes the list of Priority One projects from the FCA Reports. Priority Two and other priorities remain and require further evaluation in context of current facility conditions.

Since the updated report was issued, the completed projects are:
• Sports Center Fire Control Center panel replacement
• Sports Center Seismic Retrofit
• Senior Center Fire Alarm System (FAS) upgrade (CDBG funding) • Quinlan Community Center (QCC) AC Chiller replacements

The following projects have been initiated:
• Sports Center Locker and Shower rooms improvements, design phase • Sports Center and QCC Flat Roof replacements
FY 26–27 CIP Book Page 24
• Senior Center Flat Roof Replacement and HVAC upgrades (CDBG) • QCC HVAC controls repairs

These projects will be initiated and/or completed in FY25-26:
• Creekside Park Recreation Building FAS
• Monta Vista - Pre-School Building FAS
• Monta Vista - Gymnastics Building FAS
• Service Center Administration Building FAS
• Sports Center FAS

These projects will be initiated in FY 26-27:
• Sports Center Locker and Shower rooms improvements, Construction • Misc. HVAC equipment upgrades at the Traffic Maintenance buildings, Service Center, BBF Pools, and Community Hall
• Flat Roof replacements at Monta Vista Pre-School and Gymnastics Buildings

This project is planned for FY 27-28 as part of the CIP 5-year plan:
• Library FAS

TABLE 3 – FCA PROJECT FISCAL SUMMARY

FY19-26 FUNDING:

FY19 City funds $1,000,000
FY23 CAP funds $6,470
FY24 City funds $1,000,000
FY24 CDBG grant (Senior Center) $367,951
FY25 CDBG grant (Senior Center) $55,469
FY26 City Funds $940,000
subtotal (a) $3,369,890

Completed Projects:

Completed FY19 -25 FCA Projects $583,991
QCC Chillers Replacement $211,500
Senior Center FAS Upgrade (CDBG) $367,951
subtotal (b) $1,163,442

Current Projects:

Sports Center Roof + QCC Flat Roofs $715,000
Senior Center Flat Roofs (est.) $200,000
Senior Center HVAC replacement (CDBG) $49,361
Sports Center Shower Rooms – Design only $59,000
QCC HVAC controls repairs (est.) $140,000
Monta Vista - Pre -School Bldg. FAS (est.) $75,000
Creekside Park Recreation Bldg. FAS (est.) $40,500
Monta Vista - Gymnastics Bldg. FAS (est.) $225,000
Service Center Administration Bldg. FAS (est.) $175,000 FY 26–27 CIP Book Page 25
Sports Center Bldg. FAS (est.) $375,000
subtotal (c) $2,053,861
Uncommitted project funds (a -b-c): $152,587

FY 26 -27 FCA Projects:

Sports Center Shower Rooms - Construction $950,000

Misc. HVAC upgrades: Traffic Maint. Bldgs.,
Service Center, BBF Pools, and Community Hall $100,000

Flat Roofing @ 2 Monta Vista Bldgs. $200,000
subtotal (c) $1,250,000
FY 26 -27 City funding $1,250,000

FY27 -28 FCA Projects:

Library FAS $1,300,000
$1,300,000

Prioritization: The FCA projects are critical health and safety improvements to existing facilities. Most of the improvements will decrease the City’s energy usage and thus reduce utility costs. These projects are a priority in terms of Health and Safety, Sustainability, and Asset Conditions.

F3. City Hall Annex (FY 26-27 additional funding): The City Hall Annex property was purchased in 2021, and the renovation project for the facility was funded at $3M in FY21-22.

The proximity of this property to the Civic Center, and its central location within the City, lends itself to numerous uses, including the permanent home of the Emergency Operations Center (EOC) and interim or long-term uses as a satellite City Hall facility. The program centers on providing a permanent EOC, the public-facing Permit Center, and community meeting rooms.

The permit and construction documents are in development, the bid process will occur in Summer/Fall 2026, with construction scheduled to begin soon after.

Prioritization: Renovation of 10455 Torre will provide (a) a permanent location for the City’s Emergency Operations Center and (b) interim workplace and community meeting rooms for City Hall functions while City Hall is being renovated. These serve the community Health and Safety, and provide Community Benefit.

F4. City Hall (FY 25-26 additional funding): In December 2025, City Council approved the scope and increased funding for the City Hall Improvements project. It was decided that the scope of work will include:
a. Risk Category IV Renovation of Structural System
b. Maintain Current Footprint: Reconfigure Interior, no vertical or horizontal expansion
c. No Parking Expansion
d. Upgrades to Infrastructure and Accessibility

FY 26–27 CIP Book Page 26
The budget has been revised to include an additional $2,500,000. The renovation and related expenses are now estimated at $54.5 million over a five-year period. The currently allocated $3 million will support contracts with a Bridging Architect and a Construction/Design Management firm to advance schematic design and further evaluate cost and scope options.

Staff anticipates the procurement of a Design-Build entity in the latter part of 2027.

Going forward, funding for the City Hall project is expected to be drawn primarily from the Future Use Fund, as discussed in December 2025. Years 2–5 are anticipated to have significant impacts on the CIP, both financially and in terms of staffing resources.

Prioritization: Renovation of the City Hall building will address Health and Safety and Asset Condition criterion by significantly upgrading the seismic capacity of the structure, provides Community Benefit by improvements to services and meeting facilities, and addresses Sustainability goals by the substantial improvements to energy-efficient appliances.

F5Q. Cupertino Library Expansion (queued): The Library Expansion project was completed in 2022 except for improvements to the interior courtyard and exterior landscaping. A Community Program Funding (CPF) grant was successfully applied for through Representative Ro Khanna’s office. In FY24-25, the agreement was finalized and work can be re-initiated when staffing resources and coordination with SCC Library District are in place.

Prioritization: The Library Expansion project is a great community benefit, and the improvements to the landscaping, courtyard, and other systems will further those goals.

Annual Progress
FY 26-27: A few existing CIP projects are nearing completion, including the Stevens Creek Blvd Class IV Bike Lanes, Phase 2A, the Photovoltaic Systems Installation, and the Electric Vehicle Charging Station (EVCS) expansion - Service Center, which will allow staff to focus on other existing project initiatives, as well as to redouble efforts on the City Hall Annex and City Hall Improvement projects. FY 26-27 will result in renewed focus on these two projects, as well as the Tamien Innu and Lawrence-Mitty Park and Trail Projects.

FY 27-28: CIP will request additional funding to replace the FAS in the Cupertino Library building. In this fiscal year we may be able to coordinate these projects with infrastructure improvements at the Library to electrify the appliances, improve energy efficiency, and increase the resiliency of the facility to better serve the community as a cooling/heating center. Public Works (PW) staff is currently working with Santa Clara County Library District (SCCLD) and the Santa Clara County (SCC) to develop a program and technical requirements for this initiative.

FY 27-28 and onwards: addressing the highest priority projects in the FCA will be ongoing for both CIP and the Operations staff. More roof repairs are needed and FAS, HVAC systems, and other critical systems need improvements. The FCA project may help to FY 26–27 CIP Book Page 27
address additional improvements to the various Recreation facilities (Sports Center, McClellan Ranch Preserve, Blackberry Farm, Senior Center, Quinlan Community Center) that could improve accessibility and infrastructure, advancing safety, functionality, and revenue-generating capacity of these facilities.

The CIP welcomes the opportunity to take on projects to renovate or replace City Hall and the City Hall Annex. These are significant investments, both financially and on staffing resources, that must be considered in conjunction with the overall City annual budget and financing options. If these projects do have the support of Council and the community, CIP will require an additional senior-level full-time employee (FTE) to manage those projects.

Parks and Recreation Projects
Funding Summary
There are two funded and active Parks projects, three new projects for FY 26-27, one new project for FY 26-27 with funding to be determined, and two other funded projects that are in the queue. (Yellow highlights new projects/funding).

TABLE – PARKS AND RECREATION PROJECTS, FUNDING SUMMARY
# Project name Project
Description
Year
Initiated
City
Funding
Grant
Funding
Developer
Funds
Project
Budget
Remaining
Funds*
P1 Lawrence -Mitty
Park and Trail
Plan

*Annexing Costs
were $2,330,085
Design and
construct a new
park and trail
extension. Located
on 7.8 acres
adjacent to
Saratoga Creek,
near the
intersection of
Lawrence
Expressway and
Mitty Way.

FY18 -19 8,270,994 9,181,084 5,756,750
CAP Allocation FY23 -24 90
Berm Clean -up FY23 -24 910,000
P2 MRP West
Parking Lot
Improvements
(Habitat
monitoring
continues to
2028)
Design and
construct a new
“green” meadow-
style parking lot
that is compatible
with the creek
environment at
McClellan Ranch
West, which was
designed to have
minimal impact to
the site. *Only
habitat monitoring
is active.

FY16 -17 400,000 1,166,307 28,513
FY 26–27 CIP Book Page 28
City Funding FY17 -18 550,000
City Funding FY18 -19 65,000
City Funding FY19 -20 37,276
CAP Allocation FY20 -21 17,406
City Funding FY20 -21 39,200
City Funding FY22 -23 57,425
P3Q Annual
Playground
Replacement
Replacement of
older playground
equipment that is
dated and worn.
(5yrs funding x
$300K)
FY20 -21
to FY24-
25 1,500,000 1,500,000 916,329
P4Q Park Amenity
Improvements
Funding for various
park amenities
such as benches,
hydration stations,
outdoor table
tennis, cornhole,
shade structures,
pickleball striping,
etc. (3yrs funding x
$200K)
FY20 -21
to FY22-
23 600,000 600,000 351,422
4 subtotal 12, 447 ,391 0 0 12, 447 ,391 7, 533,014 P5 BBF Golf Course
Pro Shop
Renovation
Interior renovation
to improve
functionality and
code compliance.

FY26 -27 120,000 120,000 120,000
P6 Blesch
Residence
Improvements
Demolition of the
existing residential
building, replace
with minimal
grading, natural
habitat and modest
pathway[s].

FY26 -27 TBD TBD NA
P7 Memorial Park
Pickleball Sound
Attenuation
Provide sound
attenuation and a
new structurally
reinforced fence.

FY26 -27 150 ,000 150 ,000 150 ,000
P8 Sports Center
Courts
Resurfacing
Resurfacing the
courts to provide
safe and consistent
surfaces.

FY26 -27 210,000 210,000 210,000
8 total 12,927,391 0 0 12,927,391 7, 533,014
*Table Note: The funds indicated in the “Remaining Funds” column are a calculation based on the transactions to date as of February 2026, not including contract encumbrances not yet expensed.

Also, it does not fully account for the amount of grant funds that are expensed/received to date. If the project were to be defunded, for example, a more thorough accounting of the funds remaining on the project would be required.

Status and Prioritization of Existing Parks and Recreation Projects FY 26–27 CIP Book Page 29
P1. Lawrence-Mitty Park and Trail Plan: In July 2024, City Council approved the Conceptual Design of the project and adopted the Initial Study/Mitigated Negative Declaration (IS/MND). Construction/Permitting documents (PS&E, or “Plans, Specifications and Estimates”) were developed to 60% completion for use in the Regulatory/ Environmental Permitting phase. The project team is working to secure the requirements for the habitat from Department of Environmental Health and Army Corp of Engineers. The milestone schedule is indicated below.

Regulatory Permitting December 2025 to June 2026
Construction Documents (95% PS&E) July 2026 to Augu st 2026 Bid and Permitting (including 100% PS&E) September 2026 to November 2026 Construction December 2026 to November 2027

Prioritization: The design and engineering team is under contract (i.e., encumbered) through the completion of construction, and substantial investment has already been made to address the site’s regulatory and environmental requirements through the CEQA process. Project funding is secured through a developer agreement, which would need to be revisited if defunding is considered. This project is a high priority in Climate Resilience and Sustainability, Strategic Alignment [with the General Plan and Parks and Recreation System Master Plan], and Community Benefit and Equity.

P2. MRP West Parking Lot Improvements (Habitat monitoring continues to 2027): The habitat monitoring at the McClellan Ranch Preserve west parking lot is a requirement of the project’s California Department of Fish and Wildlife permit. The parking area project was completed in 2019. The habitat monitoring will continue until 2027. This year’s report noted that all criteria are met or exceeded: “Native vegetation appears to be establishing well and is particularly successful in the center of the mitigation area. … Other plants that are showing vigorous growth throughout the mitigation area … The irrigation system appears to have served its purpose, allowing plants to naturalize and expand. …WRA recommends that the City continue its weed treatment plan in the areas outside of the cages to maintain a low cover by undesirable weeds.”
Prioritization: This project is a high priority in Regulatory/Legal Mandates, Climate Resilience and Sustainability, and Community Benefit and Equity.

P3Q. Annual Playground Replacement: Staffing capacity has resulted in temporary delays to these replacement projects. It is anticipated that the next phase of replacements will begin during FY 26-27. Varian Park, Little Rancho Park and Canyon Oak Park are targets for improvements.

Prioritization: The Playground Replacement project could be defunded since we are not in-contract presently, but the need to replace our aging playgrounds persists as an ongoing safety concern. If not replaced, many playgrounds will need to be closed, at least in part. These projects are a priority in terms of Health and Safety, Regulatory/Legal Mandates, and Asset Condition and Infrastructure Risk.

FY 26–27 CIP Book Page 30
P4Q. Park Amenity Improvements: The Park Amenity Improvements project continues to supply new benches, picnic tables, and other vital features to parks as required.

Prioritization: The Park Amenity Improvements project could be defunded but has been a valuable resource to address needed improvements and community requests/concerns in our parks. These projects are a priority in terms of Health and Safety, Regulatory/Legal Mandates, and Asset Condition and Infrastructure Risk.

Upcoming Initiatives
FY 26-27: Lawrence-Mitty Park and Trail project and MRP West Parking Habitat monitoring continues. The four new projects would be initiated. Work on the design, procurement, and installation of new equipment at playgrounds could resume in the Summer of 2027.

FY 27-28: Lawrence-Mitty Park and Trail project and MRP West Parking Habitat monitoring projects will be completed in this fiscal year. Work on the Playgrounds replacements can continue. Improvements at the Blesch Property can be initiated.

FY 28-29: Initiating the improvements to the irrigation system at the Blackberry Farm golf course is also a priority to improve efficient use of our water resources.

FY 29-30 and FY 30-31: Blackberry Farm golf course irrigation system improvements will continue into this fiscal year. Providing Shade Structures at various park locations was a Council-stated priority in years past, and improving shade opportunities is a priority of the Parks and Recreation System Master Plan. Staff will continue to pursue grant funding for these amenities.

Streets and Infrastructure Projects
Funding Summary
There are five funded and active CIP projects that are considered Streets and Infrastructure projects.

TABLE - STREETS AND INFRASTRUCTURE PROJECTS, FUNDING SUMMARY # Project name Project
Description
Year
Initiated
City
Funding
Grant
Funding
Developer
Funds
Project
Budget
Remaining
Funds*
ST1 Outfalls Repairs Following the
recommendations
of the 2024 Outfalls
Report
FY25 -26 950,000 950,000 950,000
City Funding FY25 -26 950,000
FY 26–27 CIP Book Page 31
ST 2 Vai Avenue
Outfall
Investigate, design,
and replace
existing failing 36”
corrugated metal
pipe (CMP) storm
drain line with new
reinforced concrete
pipe (RCP) or high-
density
polyethylene
(HDPE) pipe.

FY24 -25 490,000 490,000 434,804
ST 3 Stevens Creek
Bridge Repair
Stevens Creek Blvd
Bridge over Stevens
Creek. Prepare
feasibility study and
PS&E to determine
and implement
appropriate scour
countermeasures.
(Externally Funded,
in part)
FY23 -24 172,000 860,000 771,982
FHWA highway
Bridge Program
grant
FY23 -24 688,000
ST 4 McClellan Road
Bridge
Replacement
Removal and
replacement of the
bridge on
McClellan Road
near the entrance
to McClellan Ranch
Preserve.
(Externally Funded -

CA DOT)
FY23 -24 5,000,000 5,850,000 #######
CPF (Budget Mod.

Required)
FY24 -25 850,000
ST 5 Street Light
Installation -
Annual Infill
Infill of streetlights
as requested by
residents. (Annually
funded)
FY17 -18 430,000 430,536 138,882
CAP Allocation FY22 -23 536
5 subtotal 2,992,536 6,538,000 0 8,580,536 8,145,668 *Table Note: The funds indicated in the “Remaining Funds” column are a calculation based on the transactions to date as of February 2026, not including contract encumbrances not yet expensed.

Also, it does not fully account for the amount of grant funds that are expensed/received to date. If the project were to be defunded, for example, a more thorough accounting of the funds remaining on the project would be required.

Status and Prioritization of Existing Streets and Infrastructure Projects ST1. Outfalls Repairs : The purpose of the 2024 Storm Drain Outfall Condition Assessment report was to inventory the storm drain assets and to determine necessary improvements and maintenance activities for the outfall pipes and structures. The City maintains 175 FY 26–27 CIP Book Page 32
outfall pipe segments, totaling approximately 17,051 feet, within the storm drain network.

The outfall pipes discharge urban rainfall runoff from the City’s storm drain system into various creeks/channels managed by the Santa Clara Valley Water District (Valley Water).

The report documented observations of the condition of outfall pipes, along with their corresponding outfall structure, and nearest upstream structure. The primary assessment method for the pipeline segments and outfall structures consisted of closed circuit television (CCTV), visual examinations and documentation through photographs.

The report assessed 205 pipe segments across 175 sites. 31% show structural defects with significant defect grades (NASCO grades 4 and 5). 19% have significant defects that affect operations and maintenance. Most of the defective pipes were CMP outfall pipes that were installed consistent with Valley Water specifications for outfall pipes which were in place at the time of installation. Grade 3, 4, and 5 defects were common in pipelines that were constructed from corrugated metal pipe (CMP). This is due to the susceptibility of CMP to corrosion, which leads to holes developing in the pipes. Though not as common, several CMP pipelines also showed signs of deformation.

The report also assessed the condition of 117 outfall structures. Most of the structures were in good to moderate condition. Of the 117 outfalls structures three were in level 5 defective condition, and three were in level 4 defective condition. The City will coordinate with Valley Water to plan for the most efficient and cost-effective manner in repairing these outfall structures.

This will be an ongoing project to improve the conditions of the infrastructure.

Prioritization : The Community’s health and safety depends on a functional stormwater system.

ST2. Vai Avenue Outfall : Vai Avenue Outfall repair was completed, however replacement of the Outfall remains a priority. Staff is coordinating with Valley Water on permanent repairs as part of their CIP project to stabilize Regnart Creek in this reach. This will create efficiencies in permitting and ensure a repair that is compatible with Valley Water’s efforts Prioritization : The Community’s health and safety depends on a functional stormwater system.

ST3. Stevens Creek Bridge Repair :

Investigative work for this project has been completed, and staff are actively coordinating with the City’s engineering team and Caltrans to determine the most feasible implementation option. The bridge has been identified as “scour critical” in its biennial bridge inspection report, underscoring the need for timely improvements. Notably, the project is largely supported by external funding, with approximately 80% of costs anticipated to be covered through Caltrans funding programs.

ST4. McClellan Road Bridge Reconstruction : The City has executed a contract with a structural engineering firm to assess the current conditions, provide design alternatives, and develop the necessary design, documentation and cost estimates. Once this documentation FY 26–27 CIP Book Page 33
is completed, the project will have an increased likelihood of securing additional grant funding to complete construction the project.

Cupertino. The City has secured $5,850,000 in external funding for the project, with an additional $3,000,000 estimated to complete improvements. Staff will continue to pursue additional external funding opportunities to fully fund the project.

ST5. Street Light Installation - Annual Infill :

There are locations within the city where residents have requested additional streetlighting to improve visibility. These requests are evaluated by staff for consistency with the City’s established spacing policy, and, where appropriate, are incorporated into future installation plans. Current efforts are focused on advancing new streetlight installations in the East Estates Drive, West Estates Drive, and Lindenbrook Lane neighborhood.

Annual Progress
FY 26-27: The City expects to have studied options to determine the scope of work for the repairs of Stevens Creek Bridge, by the end of 2025. The engineering team for the McClellan Road Bridge project is identified and contractually engaged. Engineering work and funding resourcing will continue for the Stevens Creek and McClellan Road bridge projects.

FY 27-28: Work on the first three outfall projects should be complete in this fiscal year, and the City expects to propose additional outfall projects to address priority projects from the outfall assessment report.

FY 28-29:

Ongoing efforts on the bridge projects is anticipated. Additional priority outfall repairs are planned for initiation, focusing on locations identified through recent assessments as having the greatest need for rehabilitation to ensure continued system reliability and proper stormwater conveyance.

FY 29-30 and FY 30-31: Engineering and environmental analysis will continue for both bridge projects. Additional outfall repair projects are anticipated.

//

//

//

//

FY 26–27 CIP Book Page 34
Transportation Projects
Funding Summary
There are three funded and active Transportation projects, one new project for FY 26-27, and five other funded projects that are in the queue. (Yellow highlights new projects/funding).

TABLE - TRANSPORTATION PROJECTS, FUNDING SUMMARY
# Project name Project
Description
Year
Initiated
City
Funding
Grant
Funding
Developer
Funds
Project
Budget
Remaining
Funds*
T1 Stevens Creek
Blvd CL IV
Bikeway Phase
2A
Design and
Construction of the
separated bikeway
along Stevens
Creek Blvd from
Wolfe Road to
DeAnza Blvd.
(Externally Funded,
in part)
FY20 -21 350,000 2,385,782 2,135,377
Construction, City
Funding
FY21 -22 2,000,000
CAP Allocation FY22 -23 35,782
OBAG FY24 -25 807,000
SB1 FY24 -25 693,000
T2 Roadway Safety
Improvements -
HSIP
High Friction
pavement
treatment and
speed feedback
signage added to
seventeen
locations.
(Externally Funded,
in part)
FY24 -25 356,180 3,561,800 3,513,115
HSIP Grant FY24 -25 3,205,620
T3 Tamien Innu -
East Segment
Design and
construct an off-
street bicycle and
pedestrian facility
parallel to the I-280
HWY, from Wolfe
Rd. to Vallco
Parkway (Externally
Funded & Apple)
FY20 -21 600,000 2,536,000 2,001,081
VTA Measure B FY21 -22

1,936,000
FY 26–27 CIP Book Page 35
T4Q Tamien Innu -
Central Segment
Design and
construct an off-
street bicycle and
pedestrian facility
parallel to the I-280
HWY, from De Anza
Blvd. to Wolfe Road
(Externally Funded -
Apple)
FY20 -21 600,000 4,785,000 See East
Segment
VTA Measure B,
Design
FY20 -21 460,000
VTA Measure B,
Construction
FY20 -21 3,725,000
T5Q Tamien Innu -
West Segment
Design and
construct an off-
street bicycle and
pedestrian facility
parallel to the I-280
HWY, from the Don
Burnett Bicycle –
Pedestrian Bridge
to De Anza Blvd.
(Externally Funded -
Apple)
FY20 -21 600,000 600,000 600,000
T6Q Stevens Creek
Blvd CL IV
Bikeway Phase
2B Construction
Construction of the
separated bikeway
along Stevens
Creek Blvd from De
Anza Blvd to US-85.

This includes signal
upgrades at
Bandley Drive.

FY20 -21 0 0
T7Q Bandley
Intersection
Signal upgrades at
Bandley Drive.

Scope of work will
be included in SCB
Phase 2B for
efficiency.
(Externally Funded,
in part)
FY18 -19 150,090 142,210
In -Lieu funds FY18 -19 25,658
City funding FY18 -19 124,432
FY 26–27 CIP Book Page 36
T8Q School Walk
Audit
Implementation
Construct
infrastructure-
related
improvements
around schools that
were identified as
part of the
comprehensive
School Walk Audit
study. (Externally
Funded - Apple)
FY18 -19 250,000 1,472,517 24,338
Apple Funding FY19 -20 1,221,863
CAP Allocation FY22 -23 654
8 subtotal 3,117,048 10,826 ,620 3,047,521 15,491,189 13,986,831 T9 SCB/SR 85 NB
ramp
Intersection
improvements
Improve traffic
conditions for all
users at this
intersection.

Developer In-Lieu
fees funded.

FY26 -27 0 600,000 600,000
Dev In -Lieu fees FY26 -27 600,000
9 total 3,117,048 10,826 ,620 3, 647,521 16,091,189 14,586,831 *Table Note: The funds indicated in the “Remaining Funds” column are a calculation based on the transactions to date as of February 2026, not including contract encumbrances not yet expensed.

Also, it does not fully account for the amount of grant funds that are expensed/received to date. If the project were to be defunded, for example, a more thorough accounting of the funds remaining on the project would be required.

Status and Prioritization of Existing Projects
T1. The Stevens Creek Boulevard Class IV Bikeway, Phase 2A project is under construction.

Prioritization: Stevens Creek Boulevard Class IV Bikeways is the top priority from the Bicycle Transportation plan, and a Tier One priority of the Pedestrian Transportation Plan – improving vehicular, bicyclist and pedestrian safety along one of Cupertino’s busiest arteries was considered a highly important project. Construction of Phase 2A (Wolfe Road to De Anza Boulevard) is underway.

T2. Roadway Safety Improvements project (HSIP) documents are ready for the City to advertise the project for bid and construction. Once awarded, the construction time is anticipated to be complete before the end of the calendar year.

Prioritization: The Roadway Safety Improvements project is grant funded with local matching funds. Roadway improvements provide health and safety benefits as well as economic benefit to the community.

T3, T4Q and T5Q. Tamien Innu East, Central and West Trail Segments: For the East trail segment, design phase is conceptually approved by the adjacent property owner and Valley Water. The project team is developing the engineer’s bidding and construction drawings FY 26–27 CIP Book Page 37
and specifications. The Central and West segments of the trail will re-enter design phase once the East segment is substantially complete.

Prioritization: The Tamien Innu project, specifically the East segment, has been delayed due to efforts to address physical constraints and Valley Water requirements during the design phase. The design is now progressing. It is funded entirely by developer and donation funds and grants.

T6Q and T7Q. The Stevens Creek Boulevard Class IV Bikeway, Phase 2B project and Bandly Drive Signal Improvements is 95% complete in the design phase. The City will search for external funding options prior to commencing with bidding and construction.

Prioritization: Phase 2B (De Anza Boulevard to Mary Avenue) is 95% designed and ready to bid, but the funding for construction, external funding and/or internal funding, will require reconsideration by City Council. Bandley Intersection improvements, a portion of Phase 2B are partially funded by Developer In-Lieu fees from FY18-19.

T8Q. School Walk Audit Implementation’s Tier 3 projects at Hyannisport Drive and Tantau/Barnhart are initiated. Implementation will be a priority after the school year.

Prioritization: Cupertino Safe Routes to School (SR2S) worked with each public school in Cupertino to develop a list of infrastructure improvements called the Walk Audit Report. The projects resulting from the Audit report will make walking and biking safer, and drop-off and pick-up smoother.

Annual Progress
FY 26-27: Stevens Creek Boulevard (SCB) Phase 2A will be completed before the end of calendar year 2026. Phase 2B, including work at Bandley Intersection, is not currently scheduled for the 5-year CIP.

Design for the Roadway Safety Improvements project is anticipated to be completed this calendar year, with construction initiation anticipated in summer 2026.

Tamien Innu, East segment design, will be finalized by summer 2026, and bidding and construction can begin soon after. Once construction is initiated on the East segment, design on the Central segment can resume.

FY 27-28: Work on SCB Phase 2B may restart if external funding can be acquired. The remaining School Walk Audit Implementation projects are planned to be completed.

Tamien Innu Central Segment is anticipated to be in the design phase. The City expects the Active Transportation Plan to be completed, adopted, and will inform future CIP planning efforts.

FY 28-29, FY 29-30 and FY 30-31: Potential transportation projects are anticipated based on information from the approved ATP.

FY 26–27 CIP Book Page 38

Sustainability and Energy Projects
Funding Summary
There are two currently funded and active Sustainability projects. One project was awarded grant funds during the FY 25-26 budget cycle, indicated with a green highlight.

TABLE–SUSTAINABILITY AND ENERGY PROJECTS, FUNDING SUMMARY # Project name Project
Description
Year
Initiated
City
Funding
Grant
Funding
Developer
Funds
Project
Budget
Remaining
Funds*
SU1 EVCS expansion -
Service Center
The construction of
electric vehicle
charging station
(EVCS)
infrastructure for
the electrification
of the City’s fleet.

FY24 -25 560,000 785,230 775,585
SVCE grant funding FY25 -26 225,230
SU2 Photovoltaics
Systems Design
& Installation
This project will
design-build PV
systems at three
locations: Quinlan
Community Center,
Cupertino Sports
Center, and
Community Hall.

FY24 -25 6,300,000 6,300,000 5,513,958
2 subtotal 6,860,000 225,230 0 7,085,230 6,289,543 *Table Note: The funds indicated in the “Remaining Funds” column are a calculation based on the transactions to date as of February 2026, not including contract encumbrances not yet expensed.

Also, it does not fully account for the amount of grant funds that are expensed/received to date. If the project were to be defunded, for example, a more thorough accounting of the funds remaining on the project would be required.

Status and Prioritization of New and Existing Sustainability Projects SU1. EVCS expansion - Service Center project is under construction.

Prioritization: The EVCS expansion at Service Center project is necessary for the ongoing electrification of the City’s fleet. This project is currently funded and supported through SVCE.

SU2. Photovoltaics Systems Design & Installation project is under construction. The installations at Sports Center and Community Hall are complete. Construction at the Quinlan Community Center Alves parking is scheduled for October 2026 completion.

Prioritization: The project is under construction and will reduce the City’s utility costs once initiated.

Projected Progress of the Projects
In the next five years, the broad sustainability goals for City facilities focus on:

FY 26–27 CIP Book Page 39
1) Reducing overall energy use through efficiency improvements to equipment controls and building envelopes.
2) Moving away from using natural gas to power heating and cooling equipment and look for opportunities to electrify equipment wherever possible, especially where PV systems exist.
3) Improve the HVAC and power capabilities of the Library and Quinlan Community Center to serve as Resiliency Centers, enabling reliable shelter in the event of extreme heat, cold, or poor air quality.
4) Meet the water conservation requirements of AB 1572 for non-functional turf.

Projects required to achieve these goals can be categorized into (a) large facility-wide projects or (b) smaller equipment-specific projects, and would be further subdivided into either CIP projects that require engineering support, or those Special Projects/Maintenance efforts implemented by the Facilities division of Public Works. The larger facility-wide projects have been captured above in the “Unfunded Sustainability Projects” table, but smaller equipment-specific projects may occur when replacement becomes a necessity or as funding opportunities arise.

Working in partnership with BayREN, the Sustainability group identified several rebate opportunities that may fund water heater or other smaller equipment replacements.

BayREN also identified equipment run-time trimming recommendations that may have short-term energy and cost savings. Additionally, the City is part of a regional coalition of several jurisdictions seeking to work together to pursue grant funding for Resiliency Center upgrades across the county.

Given the various approaches described above and uncertain funding, Sustainability staff will continue to work with CIP and Facilities staff to coordinate on potential projects, pursue.

Summary - CIP Funding for FY 26-27
TABLE – CIP FUNDING BY PROJECT
# Project City
Funding
Grant
Funding
Developer
Funds
Project
Budget
F1 ADA Improvements (Annually
funded)
979,984 0 0 979,984
F2 Facilities Condition Assessment
(FCA) Implementation
*Includes FY 26-27 funding
4,196,470 417,312 0 4,613,782
F3 City Hall Annex
*Includes FY 26-27 funding
8,025,000 0 0 8,025,000
F4 City Hall Improvements 3,000,000 0 0 3,000,000
F5Q Library Expansion Project:
landscaping & courtyard
8,705,438 1,000,000 0 9,705,438
P1 Lawrence Mitty Park and Trail
Plan
9,181,084 0 0 9,181,084
FY 26–27 CIP Book Page 40
P2 MRP West Parking Lot
Improvements (Habitat
monitoring)
1,166,307 0 0 1,166,307
P3Q Annual Playground Replacement 1,500,000 0 0 1,500,000 P4Q Park Amenity Improvements 600,000 0 0 600,000
ST1 Outfalls Repairs 950,000 0 0 950,000
ST2 Vai Avenue Outfall 490,000 0 0 490,000
ST3 Stevens Creek Bridge Repair 172,000 688,000 0 860,000 ST4 McClellan Road Bridge
Reconstruction
5,850,000 0 5,850,000
ST5 Street Light Installation - Annual
Infill (Annually funded)
430,536 0 0 430,536
T1 Stevens Creek Blvd CL IV Bikeway
- Phase 2 Design & Phase 2A
Construction
2,385,782 1,500,000 0 2,385,782
T2 Roadway Safety Improvements
(HSIP)
356,180 3,205,620 0 3,561,800
T3 Tamien Innu - East Segment 0 1,936,000 600,000 2,536,000 T4Q Tamien Innu - Central Segment 0 4,185,000 600,000 4,785,000 T5Q Tamien Innu - West Segment 0 0 600,000 600,000
T6Q Stevens Creek Blvd CL IV Bikeway
- Phase 2B Construction
0 0 0 0
T7Q Stevens Creek Blvd CL IV Bikeway
- Bandley Dr. Signal
124,432 0 25,658 150,090
T8Q School Walk Audit
Implementation
250,654 0 1,221,863 1,472,517
SU1 Electric Vehicle Charging Station
(EVCS) expansion - Service
Center
560,000 225,230 0 785,230
SU2 Photovoltaic Systems Design &
Installation
6,300,000 0 0 6,300,000
Subtotal 49,373,867 19,007,162 3,047,521 69,928,550 FY 26 -27 NEW PROJECTS
P5 BBF Golf Course Pro Shop
Renovation
120,000 0 0 120,000
P6 Blesch Residence Improvements TBD 0 0 0
P7 Memorial Park Pickleball Sound
Attenuation
150,000 0 0 150,000
P8 Sports Center Courts Resurfacing 210,000 0 0 210,000 T9 SCB/SR 85 NB ramp Intersection
improvements
0 0 600,000 600,000
FY 26 -27 Total 49,853,867 19,007,162 3,647,521 71,008,550

FY 26–27 CIP Book Page 41
TABLE – FUNDING DISTRIBUTION BY FUND TYPE
For Existing and New Projects Only
Funds FY 26 -27 FY 25 -26 FY 24 -25 FY 23 -24 FY 22 -23 Sub total :

FY22 to 16
Totals
Tax Supported Funds
Capital Improvement
Fund (General Fund) –
420
2,000,000 2,000,000 7,750,000 2,482,000 652,425 19,051,330 33,935,755 Capital Reserve
(General Fund) – 429
4,730,000 0 4,730,000
Stevens Creek Corridor
Park Capital Projects –
427
0 0
Special Revenue Funds
Storm Drain
Improvement Fund -
210
0 0
Park Dedication Fund -
280
0 0
Transportation Fund –
270
356,180 0 356,180
Transportation Impact
Fee – 271
0 0
Housing & Community
Development -260
0 0
Enterprise Funds
Blackberry Farm Golf
Course Fund - 560
0 0
Sports Center Fund -
570
0 0
Recreation Programs
Fund - 580
0 0
Funds (Continued) FY 26 -27 FY 25 -26 FY 24 -25 FY 23 -24 FY 22 -23 Sub total :

FY22 to 16
Totals
External Funding
CAP Allocation 65,922 0 65,922
SVCE grant (Service Ctr
EVCS)
225,230 0 225,230
Apple Funding (Tamien
Innu & School Walk)
3,021,863 3,021,863
Developer In -Lieu fees
(Bandley + LMPT)
600,000 8,296,652 8,896,652
VTA Measure B (Design,
Central)
460,000 460,000
VTA Measure B
(Construction, Central &
East)
5,661,000 5,661,000
HSIP 3,205,620 0 3,205,620
FY 26–27 CIP Book Page 42
OBAG (SCB Ph 2A) 807,000 0 807,000
SB1 (SCB Ph 2A) 693,000 0 693,000
CA DOT grant
(SCBridge)
5,000,000 0 5,000,000
CPF (SCBridge &
Library)
1,850,000 0 1,850,000
FHWA (SCBridge) 688,000 0 688,000
Future Use Fund (CH) 2,500,000 0 2,500,000
CDBG grant (FCA) 49,361 367,951 0 417,312
totals 7,330,000 4,725,230 14,711,161 8,537,951 718,347 36,490,845 72,513,534 Completed Projects
Capital Improvement
Fund (General Fund) –
420 (LED, JAIPG)
2,150,000 1,280,000 3,430,000
Transportation Fund –
270 (BPMP)
1,476,105 700,000 2,176,105
CAP Allocation -
Completed projects
(JAIPG & BPMP)
10,720 0 10,720
EECBG (LED project) 125,790 0 125,790
FHWA (BPMP) 510,521 95,227 716,296 571,151 1,893,195 Art In -Lieu (JAIPG) 338,146 0 338,146
PG&E donation (JAIPG) 25,000 25,000
CA Parks & Rec
Specified grant (JAIPG)
1,000,000 1,000,000
SCC AIPG grant (JAIPG) 1,448,201 1,448,201
totals 0 0 2,112,416 433,373 2,877,016 5,024,352 10,447,157

FY 2026 – 2027 CIP Book Page 43

Capital Improvement Programs Fiscal Year 2026 – 2027
and 5-Year Plan

CIP Project Narratives

CIP FY26-27  5-YEAR PLAN

PROJECT NARRATIVES
PAGE 1

TABLE OF CONTENTS
A. New
B. Current
 Facilities
 Parks
 Streets
 Transportation
 Sustainability
C. Completed
FY25-26 CIP proposal and 5-year Plan Council Meetin g 4/02/2025 Page 30 of 34

INSERT SECTION PAGE (GRAPHICS!)

A. NEW PROJECTS
City of Cupertino
CIP FY26-27  5-YEAR PLAN

PROJECT NARRATIVES
PAGE 1
CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
Blackberry Farm Pro Shop Renovation page 1

FY 26-27 City Funding $ 120,000

Total Funding $ 120,000
City Funding FY 26-27 $ 120,000
External Funding $ 0
Remaining Funds (Feb 2026) N.A.

Funding Source Capital Reserve/GF
Approved [Master] Plan N.A.

Project Category Parks & Recreation
Project Type Design & Construction
Origin of Request Parks & Recreation
FY Initiated FY 26-27 (pending)

Project Description
The Blackberry Farm Golf Course Pro Shop serves more than 40,000 golfers annually and is central to the visitor experience. However, the facility has not been comprehensively renovated in many years and is now outdated, inefficient, and out of alignment with current accessibility and building standards. This project prop oses a full renovation to improve functionality, safety, and customer service, including a new service counter, replacement of worn finishes, ADA upgrades, and modernization of the existing electrical system to meet current code requirements.

Project Justification
Renovating the pro shop is necessary to bring the facility up to the City’s ADA, electrical, and saf ety standards, improve functionality for staff, and enhance the overall experience for golfers. The proposed upgrades will address deferred maintenance, reduce operational and safety risks, and ensure the pro shop reflects the level of service and accessibility expected of a City-owned facility. It is important to note that the pro shop was not in cluded in the 2018 Facility Condition Assessment Report.

Prioritization Total Points: 280

Health & Safety 4 The facility is in poor condition and requires electrical upgrades.

The outdated systems will be modernized to meet current code and operational needs.

Regulatory / Legal Mandate 3 ADA and electrical upgrades are needed.

Asset Condition & Infrastructure
Risk
5 The antiquated pro shop requires significant renovation, including electrical upgrades. Planned improvements include a new service counter, replacement of worn flooring and ceiling materials, and ADA accessibility upgrades.

Climate Resilience & Sustainability 0 N.A.

Strategic Alignment 0 The facilities at the Golf Course, including the Pro Shop, were not included in the 2018 Facility Condition Assessment Report.

Community Benefit & Equity 4 The Blackberry Farm Golf Course Pro Shop serves over 40,000 golfers annually and is central to the visitor experience, but staff regularly receive complaints about its deteriorating condition.

Financial Leverage & Cost
Effectiveness
2 Facility improvements will decrease operational time and effort.

Project Readiness 2 Scope schematically defined. RFP/Bid procurement process required to secure contractor to complete the work.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
Blackberry Farm Pro Shop Renovation page 2 Operating Budget Impacts Annual Estimated Impact: $0
Negligible anticipated impact to operating budget.

Funding Information
No grant funding

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 0
Other External Sources $ 0

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
T.B.D. N.A. $120,000

Projected Schedule/5-year Plan Information
Renovation work can be completed within one fiscal year.

Item/Phase Timeline for Completion Notes
Project Initiation July 2026
Consultant Procurement September 2026
Planning/Pre-Design November 2026
Design October 2026
Permitting & Environmental Clearance December 2026
Construction Bid January 2027
Contract Award and Contracting March 2027
Construction April 2027
Post-Construction/Close-out May 2027

Project Location

22100 Stevens Creek Boulevard

Project Contact
Susan Michael, CIP Manager
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
Blesch Property Improvements page 1

FY 26-27 City Funding TBD

Total Funding TBD
City Funding FY 26-27 TBD
External Funding TBD
Remaining Funds (Feb 2026) N.A.

Funding Source Capital Reserve/GF
Approved [Master] Plan General Plan
Project Category Parks & Recreation
Project Type Design & Construction
Origin of Request Public Works, Council
FY Initiated FY 26-27 (pending)

Project Description
Demolition of the existing residential building to be replaced with minimal grading , natural habitat and modest pathway[s]. The initial phase will develop preliminary cost estimates for demolition of the existing structure, conceptual planning, design and engineering of the site, and construction of the improvements.

Project Justification
The Blesch property is an approximately 28,000 square foot parcel, currently developed with a single-family residence.

While the structure has been used for auxiliary City purposes since acquisition, it is not suitable for use as a public facility. Significant repairs, accessibility improvements and reconfiguration would be required for any public use.

Additionally, the site is located within the Federal Emergency Management Agency (FEMA) Fl ood Zone AE, with more than half of the property situated within the designated floodway. Being in a FEMA designated floodplain results in constraints which substantially limit the feasibility of maintaining or constructing vertical structures on the site and impose additional regulatory requirements, review timelines, and costs for any building construction.

Prioritization Total Points: 345

Health & Safety 5 The facility is in poor condition and unsuitable for public use.

Regulatory / Legal Mandate 1 Removing the residential building from the flood plain will bring the parcel in compliance with FEMA and CMC zoning.

Asset Condition & Infrastructure
Risk
5 Removing the structure will improve maintenance requirements for the property.

Climate Resilience & Sustainability 5 Decreasing the built environment and increasing the natural habitat will provide climate resilience and decrease flood liability.

Strategic Alignment 5 The PRSMP notes this site is a “pollinator garden” opportunity.

Community Benefit & Equity 3 The planned improvements will make the site available to the public.

Financial Leverage & Cost
Effectiveness
1 The Site improvements will decrease operational time and effort.

Project Readiness 0 Scope is under development.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
Blesch Property Improvements page 2 Operating Budget Impacts Annual Estimated Impact: $39,000 When this park is completed, and ongoing maintenance efforts are added to operations, operating costs will increase for the Grounds Division. Ongoing needs are estimated at 0.2 FTE for Grounds ($ 34,000), along with increased expenditures for maintenance supplies estimated at $5,000 annually. An initial establishment period of 5 years may see increased staff time and expenditures.

Funding Information
No information at this time.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants TBD
Other External Sources TBD

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
T.B.D. N.A. TBD

Projected Schedule/5-year Plan Information
Depending on the scope and budget of the project, it is projected to last approximately two years.

Item/Phase Timeline for Completion Notes
Project Initiation July 2026
Consultant Procurement August 2026
Planning/Pre-Design October 2026
Council review of Scope and Budget January 2027
Design and Engineering January - June 2027
Construction Bid July 2027
Contract Award and Contracting September 2027
Construction January 2028
Post-Construction/Close-out September 2028

Project Location

22050 Stevens Creek Boulevard

Project Contact
Susan Michael, CIP Manager
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
Memorial Park Pickleball Sound Attenuation page 1

FY 26-27 City Funding $ 150,000

Total Funding $ 150,000
City Funding FY 26-27 $ 150,000
External Funding $0
Remaining Funds (Feb 2026) N.A.

Funding Source Capital Reserve/GF
Approved [Master] Plan N.A.

Project Category Parks & Recreation
Project Type Design & Construction
Origin of Request Public Works
FY Initiated FY 26-27 (pending)

Project Description
Provide sound attenuation measures at the Memorial Park Pickleball courts. The sound panels will require a new reinforced fence.

Project Justification
Neighboring residents have concerns about the degradation of the acoustic environment of their residences. Pickleball is very popular and generates great community. By providing sound attenuation to mitigate the n oise, we hope to create a better environment for all.

Prioritization Total Points: 255

Health & Safety 4 Sound dampening measures will provide acoustic improvement for the neighboring residences.

Regulatory / Legal Mandate 3 Increasing the structural capacity of the fence is required to hold the sound panels.

Asset Condition & Infrastructure
Risk
3 The facilities are in good shape, but the sound quality is not addressed/.

Climate Resilience & Sustainability 0 N.A.

Strategic Alignment 0 Master Plans do not prescribe this work - this is a facility improvement that has an engineering component.

Community Benefit & Equity 4 By providing sound attenuation to mitigate the sound of the pickleball play, we hope to create a better environment for residents and players.

Financial Leverage & Cost
Effectiveness
1 The improvements will reduce risk.

Project Readiness 2 Cost estimates have been obtained.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
Memorial Park Pickleball Sound Attenuation page 2 Operating Budget Impacts Annual Estimated Impact: $3,000 Replacement costs of approximately $45,000 every 15 years.

Funding Information
No grant funding.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 0
Other External Sources $ 0

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
T.B.D. N.A. $ 150,000

Projected Schedule/5-year Plan Information
Work can be completed within the fiscal year.

Item/Phase Timeline for Completion Notes
Project Initiation July 2026
Consultant Procurement N.A.

Planning/Pre-Design N.A.

Design N.A.

Permitting & Environmental Clearance N.A.

Construction Bid August 2026
Contract Award and Contracting November 2026
Construction February 2027
Post-Construction/Close-out May 2027

Project Location

Memorial Park

Project Contact
Susan Michael, CIP Manager
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
Sports Center Courts Resurfacing page 1

FY 26-27 City Funding $210,000

Total Funding $210,000
City Funding FY 26-27 $210,000
External Funding $0
Remaining Funds (Feb 2026) N.A.

Funding Source Capital Reserve/GF
Approved [Master] Plan N.A.

Project Category Parks & Recreation
Project Type Design & Construction
Origin of Request Parks & Recreation
FY Initiated FY 26-27 (pending)

Project Description
Resurface all tennis courts and Sport Court at the Sports Center to maintain a suitable and safe playing environment.

Project Justification
The tennis court surfaces have deteriorated due to extended use and weather exposure and are now b eyond their typical five- to seven-year lifespan (last resurfaced in 2016). Resurfacing will prevent further dama ge, reduce liability, and avoid more costly repairs in the future.

Prioritization Total Points: 300

Health & Safety 4 While the courts are not currently unsafe, these conditions create uneven playing surfaces that may pose a tripping hazard if allowed to worsen. Timely resurfacing will mitigate these emerging risks and preserve safe, consistent playing conditions for the community.

Regulatory / Legal Mandate 3 Courts must be maintained to meet safety standards.

Asset Condition & Infrastructure
Risk
5 The tennis courts have not been resurfaced in approximately ten years and are showing signs of surface fatigue, including cracking that has continued to develop and expand.

Climate Resilience & Sustainability 0 N.A.

Strategic Alignment 0 Master Plans do not prescribe this work - this is required maintenance that has an engineering component.

Community Benefit & Equity 4 Staff have observed an increase in user complaints related to cracking and surface conditions on multiple tennis courts.

Feedback indicates growing concern about playability and surface consistency, particularly as cracking becomes more noticeable over time.

Financial Leverage & Cost
Effectiveness
2 Timely resurfacing will assist in keeping resurfacing and maintenance costs down. As courts continue to degrade (e.g. worsening/deepening and developing cracks) repair and
resurfacing becomes more expensive.

Project Readiness 2 Scope defined. RFP/Bid procurement process required to secure contractor to complete the work.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
Sports Center Courts Resurfacing page 2 Operating Budget Impacts Annual Estimated Impact: $0
No anticipated impact to operating budget.

Funding Information
No grant funding.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 0
Other External Sources $ 0

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
T.B.D. N.A. $210,000

Projected Schedule/5-year Plan Information
Once procurement is completed, resurfacing work expected to be completed within a month.

Item/Phase Timeline for Completion Notes
Project Initiation July 2026
Consultant Procurement N.A.

Planning/Pre-Design N.A.

Design N.A.

Permitting & Environmental Clearance N.A.

Construction Bid August 2026
Contract Award and Contracting November 2026
Construction December 2026
Post-Construction/Close-out January 2027

Project Location

21111 Stevens Creek Boulevard

Project Contact
Susan Michael, CIP Manager
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
Stevens Creek Blvd/State Route 85 NB Ramp Intersection
Improvements page 1

FY 26-27 City Funding $ 0

Total Funding $ 600,000
City Funding FY 26-27 $ 0
External Funding $ 600,000
Remaining Funds (Feb 2026) N.A.

Funding Source Westport cond. of dev.,
Dev. In-Lieu
Approved [Master] Plan BTP
Project Category Transportation
Project Type Design & Construction
Origin of Request Public Works
FY Initiated FY 26-27 (pending)

Project Description
The project includes design, construction, and project management for improvements at the Stev ens Creek Boulevard/northbound SR-85 on-ramp intersection. Improvements include a separa ted Class IV bike lane, a tightened right-turn on-ramp, and traffic signal upgrades providing protected movements for vehicles, b icyclists, and pedestrians. The project will retain a civil engineering consultant to finalize design and o btain necessary Caltrans approvals.

Project Justification
The existing high-speed on-ramp creates safety risks for bicyclists and pedestrians. Proposed improvements include a tighter ramp turn, dedicated signal phasing, a separated bike lane, and a protected pedestrian crossing to significantly improve safety. These improvements were required as part of the Westport development, but Caltran s Permitting delays prevented their completion, leading the City to collect in-lieu funds to complete the proj ect. The project now requires final design completion and Caltrans permit approval before proceeding.

Prioritization Total Points: 275

Health & Safety 3 The project reduces known safety issues for drivers, bicyclists and pedestrians.

Regulatory / Legal Mandate 0 This project is not code-required.

Asset Condition & Infrastructure
Risk
2 Improvements to the multimodal crossings at the intersection are overdue.

Climate Resilience & Sustainability 1 Minor efficiency improvements in equipment.

Strategic Alignment 4 The 2016 Bicycle Transportation Plan identified improvements on Stevens Creek Boulevard as the highest priority.

Community Benefit & Equity 3 This intersection is heavily trafficked, and improvements will have a positive impact on all modes of transportation through it.

Financial Leverage & Cost
Effectiveness
5 The project is funded entirely by the Westport development project’s Developer In -Lieu fees
.

Project Readiness 4 Design is substantially complete, but Caltrans approval and permitting are still required.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
Stevens Creek Blvd/State Route 85 NB Ramp Intersection
Improvements page 2 Operating Budget Impacts Annual Estimated Impact: $0
Negligible anticipated impact to operating budget.

Funding Information
The project is funded entirely by the Westport development project ’s Developer In -Lieu fees.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 0 $0
Other External Sources $ 150,000 $ 450,000

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
T.B.D. N.A. $ 150,000 $ 450,000

Projected Schedule/5-year Plan Information
Renovation work can be completed within two years, pending Caltrans approvals.

Item/Phase Timeline for Completion Notes
Project Initiation September 2026
Consultant Procurement September 2026
Planning/Pre-Design September 2026
Design October 2026 Substantial Design completed (Feb. 2026) Permitting & Environmental Clearance September 2027 Approval and permitting from Caltrans is required since Caltrans owns the right-of-way
where these improvements are being planned.

Construction Bid November 2027
Contract Award and Contracting February 2028
Construction March – June 2028
Post-Construction/Close-out June 2028

Project Location

Intersection of Stevens Creek
Boulevard and State Route 85,
Northbound Ramp

Project Contact
Susan Michael, CIP Manager
[email protected]

FY25-26 CIP proposal and 5-year Plan Council Meetin g 4/02/2025 Page 30 of 34

INSERT SECTION PAGE (GRAPHICS!)

B. CURRENT PROJECTS
City of Cupertino
CIP FY26-27  5-YEAR PLAN

PROJECT NARRATIVES
PAGE 1
FY25-26 CIP proposal and 5-year Plan Council Meetin g 4/02/2025 Page 2 of 34

INSERT SECTION PAGE (GRAPHICS!)

FACILITIES PROJECTS
City of Cupertino
CIP FY26-27  5-YEAR PLAN

PROJECT NARRATIVES
PAGE 1
CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
ADA Improvements page 1 Annually Funded
Total Funding $ 979,984
(~$100K annually)

City Funding $ 979,984
External Funding $ 0
Remaining Funds (Feb 2026) $ 301,993
Funding Source Capital Reserve
Approved [Master] Plan ADA Transition Plan
Project Category Facilities
Project Type Design & Construction
Origin of Request Public Works
Budget Unit 420-99-007, PVAR 002
FY Initiated FY 15-16

Project Description
This is an ongoing initiative funded annually to improve accessibility at all public fa cilities throughout the City.

Project Justification
An update of the City’s ADA Transition Plan was completed in April 2015. The plan identifies improvements needed and priorities to achieve compliance with ADA in public buildings, parks, and the public right of way.

Prioritization Total Points: 380

Health & Safety 4 Improvements to Facilities and ROW decreases risk and liability and promotes Community well-being. Enhanced accessibility allows for increased engagement for the residents.

Regulatory / Legal Mandate 5 State and Federal laws require Cities maintain a plan to update facilities and make progress on that plan.

Asset Condition & Infrastructure
Risk
3 Improvements to Facilities and ROW decreases risk and liability and promotes Community well-being.

Climate Resilience & Sustainability 1 Increasing accessibility is more sustainable, best practice.

Strategic Alignment 5 This work aligns with the ADA Transition plan and the General Plan.

Community Benefit & Equity 5 Improved accessibility throughout the City allows for increased engagement across neighborhoods and age ranges, and promotes mobility for more of the population.

Financial Leverage & Cost
Effectiveness
3 It is cost effective to improve these facilities and remain compliant with laws.

Project Readiness 3 Areas of work have been identified in the ADA Transition Plan.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
ADA Improvements page 2 Operating Budget Impacts Annual Estimated Impact: $0
No anticipated impact to operating budget.

Funding Information
This ongoing project began in FY15-16. The City has contributed to the project fund ann ually, ranging from $75K to $110K.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 0
Other External Sources $ 0

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
420-99-007, PVAR 002 $664,476 $110,000 $120,000 $120,000 $120,000 $120,000

Projected Schedule/5-year Plan Information
This is an ongoing program, funded annually, to improve accessibility at all public facilities throughout the City.

Item/Phase Timeline for Completion Notes
All Phases Ongoing The work at different sites varies in scope and schedule.

Project Location

Various

Project Contact
Susan Michael, CIP Manager
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
Facilities Condition Assessment (FCA) Implementation page 1 Ongoing initiative to address Facilities Deficiencies
Proposed FY26-27 City
Funding
$ 1,250,000

Total Funding $ 4,564,421
City Funding (Existing) $ 2.946,470
City Funding FY26-27 $ 1,250,000
External Funding $ 417,312
Remaining Funds (Feb 2026) $ 2,383,423
Funding Source Capital Reserve/GF
Approved [Master] Plan General Plan
Project Category Facilities
Project Type Design & Construction
Origin of Request Public Works
FY Initiated FY 18-19

Project Description
Ongoing initiative to implement projects from the prioritized recommendations of the 2017/18 “Comprehensive Facility Condition and Use Assessment” and the “2022 Facility Condition Assessment” (FCA) reports.

Project Justification
The 2017/18 FCA report and the 2022 FCA report assessed the condition of nearly ev ery City owned facility. Several projects were identified as high priority facilities with significant deficiencies that need to be addre ssed to avoid costly repairs and extended service interruptions.

Prioritization Total Points: 355

Health & Safety 4 Improving the facilities through these projects directly advances the health and safety of the users.

Regulatory / Legal Mandate 3 In many cases the projects bring the systems up to current code compliance.

Asset Condition & Infrastructure
Risk
4 The facilities are dilapidated such that the 2018/2022 report called these critical projects.

Climate Resilience & Sustainability 4 Improving the facilities with more energy efficient infrastructure addresses CAP goals.

Strategic Alignment 3 Providing safe facilities is of great importance in the General Plan.

Community Benefit & Equity 2 Having facilities with functioning HVAC, water and non-leaking roofs benefits the community.

Financial Leverage & Cost
Effectiveness
4 Some grant funding has been identified. The cost effectiveness of the more energy efficient and updated systems will be realized immediately.

Project Readiness

2 In some cases, drawings are available.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
Facilities Condition Assessment (FCA) Implementation page 2 Operating Budget Impacts Annual Estimated Impact: $0
Replacement of aging equipment with energy-efficient systems, and targeted building upgrades is ex pected to reduce both maintenance and energy costs. These improvements are not anticipated to require additional staffing or ongoing material costs once implemented.

Funding Information
This initiative began in FY18-19 and received additional City funding in FY23-24. CDBG grant funds were received for work on the Senior Center property, in FY23-24 and FY24-25. Future use of CDBG is lim ited to a few eligible City sites.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 367,951 T.B.D.

Other External Sources $ 0

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
420-99-063 900-905, BAI 001 $ 930,998 $ 3,000,000 $ 1,600,000 $ 300,000

Projected Schedule/5-year Plan Information
Multiple facilities with varying scopes.

Project Timeline for Completion Notes
Completed projects N.A. Senior Center FAS upgrade, Quinlan (QCC) AC Chiller replacements, replacement of two
flat roofs at Sports Center and QCC, Sports
Center Fire Control Center panel replacement
and the Sports Center Seismic Retrofit

Sports Center Locker and Shower rooms
improvements
June 2027 Permitting nearing completion, Bidding
process will initiate in Summer 2026.

Construction may be 6-8 months duration
Misc. HVAC equipment upgrades Traffic
Maintenance Bldg, Service Center, BBF
Pools, QCC, Community Hall)
December 2027 Competitive procurement process will require staggering the projects.

Flat Roof replacements: QCC and Sports
Center
Fall 2027 Bidding is complete, award of GC contract
and construction follows.

Flat Roof replacements: Monta Vista (2),
Senior Center
Spring 2028 Procurement can initiate after the completion of (2) current roof projects.

FAS upgrades: Monte Vista (2) and
Service Center
June 2028 Design and Procurement will be initiated in
FY26-27.

Library FAS TBD Planned for initiation in FY27-28

Project Location
Various
Project Contact
Susan Michael, CIP Manager, [email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
City Hall Annex page 1 10455 Torre Avenue Improvements
Proposed FY26-27 City
Funding
$ 5,000,000

Total Funding $ 8,025,000
City Funding (Existing) $ 3,025,000
City Funding FY26-27 $ 5,000,000
External Funding $ 0
Remaining Funds (Feb 2026) $ 2,566,456
Funding Source Capital Reserve/GF
Approved [Master] Plan General Plan
Project Category Facilities
Project Type Design & Construction
Origin of Request Public Works
FY Initiated FY 21-22

Project Description
Program, plan and build facility improvements to facilitate short-term and long-te rm use[s] of the building. The scope of work will include programming, planning, design, and construction. Emergency Operations Center (EOC) program and requirements added to the scope of this project in late 2022.

Project Justification
The proximity of this property to the Civic Center, and its central location within the City, lends itself to numerous uses, including a satellite and/or interim City Hall facility.

Prioritization Total Points: 400

Health & Safety 5 Providing EOC services for residents is essential.

Regulatory / Legal Mandate 3 The building must be brought up to code (building, etc.) for use as a City Facility.

Asset Condition & Infrastructure
Risk
3 The building is stable, but the interior is dated to the mid-70’s and has some hazmat remediation is required.

Climate Resilience & Sustainability 3 The updated facility will be much more energy efficient than the existing systems can provide.

Strategic Alignment 5 Council’s CWP made this a priority project.

Community Benefit & Equity 5 The residents will benefit from the EOC, the continuation of City services, and conference rooms in the public area.

Financial Leverage & Cost
Effectiveness
3 The City has committed to funding the project.

Project Readiness 5 The construction documents are 60% complete.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
City Hall Annex page 2 Operating Budget Impacts Annual Estimated Impact: $128,000 When this facility is completed and maintenance added to operations, operating costs will increase for the Facilities and Grounds Divisions. Ongoing needs are estimated at 0.20 FTE for Grounds and 0.20 FTE for Facilities ($68,000), along with increased expenditures for maintenance supplies and janitorial services estimated a t $60,000 annually.

Funding Information
When the CH Annex/EOC project was re-activated, it was noted that the projected project costs would be $8 million.

The FY26-27 funding will be a placeholder in the annual budget until construction bids are received.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 0
Other External Sources $ 0

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
420-99-248, CIV 010 $ 669,035 $ 7,130,965 $200,000

Projected Schedule/5-year Plan Information
Construction documents continues into Summer 2026, followed by a concurren t permitting phase extending to September 2026. Construction is planned for December 2026 to Summer 2027, targeting occupancy in July 2027.

Item/Phase Timeline for Completion Notes
Project Initiation FY21-22, reinitiated in
October 2025
Re-mobilization of the Design team
Design and Documentation Currently In Progress
Permitting June – Sept 2026
Construction Bid October – Nov 2026
Contract Award and Contracting December 2026
Construction December 2026 – July
2027
Construction schedule will be estimated by
GC, once contracted.

Post-Construction/Close-out July - Sept 2027

Project Location

10455 Torre Avenue

Project Contact
Susan Michael, CIP Manager
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
City Hall Improvements page 1

Total Funding $ 3,000,000

City Funding $ 3,000,000
External Funding $ 0
Remaining Funds (Feb 2026) $ 2,918,681
Funding Source Capital Reserve, GF
Approved [Master] Plan CCMP, GP
Project Category Facilities
Project Type Design & Construction
FY Initiated FY 21-22

Project Description
Program, plan and build facility improvements at the existing City Hall building site. The scope of work will include programming, planning, design, and construction. The Emergency Operations Center (EOC) moves to another facility, but this facility is planned as a “Risk Category IV” Essential Services facility as part of the structural system upgrades .

Project Justification
The existing building does not meet current or projected needs for workplace or meeting spaces; all infrastructure systems (structural HVAC, etc.) are well beyond their useful life and require full replacement. Improvements to the existing building, whether in the form of a renovation project or a new City Hall facility, are the highest priority for the health and safety of staff and the community.

Prioritization Total Points: 410

Health & Safety 5 Improvements to the infrastructure will increase the health and safety of staff and visitors.

Regulatory / Legal Mandate 3 These significant improvements to the facility require a compliance with current building codes.

Asset Condition & Infrastructure
Risk
5 Most of the building systems are well beyond their useful life.

Climate Resilience & Sustainability 4 Upgrades to the utilities and passive energy systems will decrease energy usage significantly.

Strategic Alignment 5 One of the main tenants of the General Plan is to ‘ensure fiscal self-reliance’ to protect the City's ability to deliver essential, high- quality municipal services and facilities to the community.

Community Benefit & Equity 3 The improved facility will act as a business hub, communal meeting place and strategic center for the residents.

Financial Leverage & Cost
Effectiveness
3 While the cost of the renovations is notable, the improved energy efficient will also be notable.

Project Readiness 2 Preliminary structural and programming analysis has been completed, to form the foundation of an implementation plan.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
City Hall Improvements page 2 Operating Budget Impacts Annual Estimated Impact: $0
Replacement of aging equipment with energy-efficient systems, and targeted building upgrades is ex pected to reduce both maintenance and energy costs. These improvements are not anticipated to require additional staffing or ongoing material costs once implemented.

Funding Information
The total projected cost for the Project is approximately $54.5 million. While contracts ( encumbrances) will be executed in the early fiscal years, actual spending will occur throughout the duration of the Project. The initial $3 million budget is earmarked for Bridging Architect and PM/CM contract encumbrances.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants, External Sources $ 0

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
420-99-250, CIV 011 $ 81,319 $ 2,193,681 $ 7,725,000 $ 22,500,000 $ 22,000,000 $ 0

Projected Schedule/5-year Plan Information
The renovation is expected to be a five year process.

Item/Phase Timeline for Completion Notes
Bridging Architect: RFP process, execute
contract
Current Phase
Bridging Architect: Design &
Documentation
March 2027
Design-Build Entity: RFQ and RFP,
execute contract
August 2027
Design-Build Entity: Design &
Documentation, Permitting
April 2028
Design-Build Entity: Submittals &
Procurement
July 2029
Design-Build Entity: Construction June 2030
Design-Build Entity: FF&E and Move-In August 2030

Project Location

10300 Torre Avenue

Project Contact
Susan Michael, CIP Manager
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
Library Expansion page 1

Total Funding $ 9,705,438
City Funding FY26-27 $ 8,705,438
External Funding $ 1,000,000
Remaining Funds (Feb 2026) $ 1,391,912
Funding Source Capital Reserve/GF
Approved [Master] Plan N.A.

Project Category Facilities
Project Type Design and Construction
FY Initiated FY 19-20

Project Description
Update existing landscape areas adjacent to the Cupertino Library incorporating appropriate drough t resistant plantings, pedestrian amenities including seating and shade structures, and other features to encou rage community activation of the Civic Center. Grant funding awarded in 2024 can be applied to install ation of a photovoltaic system, battery back-up, extension of an electrical service to Library Field, completing constructio n of exterior improvements such as the landscaping scope of work, parking and pedestrian improvements, improvements to the drainage and irrigation systems and water conservation efforts.

Project Justification
Some of the areas in and around the Cupertino Library lack appeal and appropriate facilities for residents who use the library and the Civic Center space. Providing more usable and efficient infrastructure, as well as b etter landscaping, will improve the positive experience of visiting the library and Civic Center.

Prioritization Total Points: 280

Health & Safety 2 Improvements to the bioretention areas will improve community health and safety.

Regulatory / Legal Mandate 1 Code requirements must be met for these improvements.

Asset Condition & Infrastructure
Risk
3 The courtyard and exterior landscaping is presently difficult to maintain and improvements can increase effective habitat.

Climate Resilience & Sustainability 5 Increase the native plantings and improvements to the bioretention areas will increase resiliency and sustainability.

Strategic Alignment 5 Civic Center Master Plan has an effective and beautiful Library at its core.

Community Benefit & Equity 5 The Library is one of the most used facilities in Cupertino.

Improvements directly affect the Community.

Financial Leverage & Cost
Effectiveness
5 The remaining work is almost entirely grant funded.

Project Readiness 5 The designs are completed, only requiring minor adjustments.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
Library Expansion page 2 Operating Budget Impacts Annual Estimated Impact: $16,000 When these improvements are completed and new maintenance activities are added to operation s, operating costs will increase for the Grounds Division. Ongoing needs are estimated at 0.1 FTE for Grounds ( $17,000). However, a small decrease in expenditures is anticipated due to improved irrigation of the area.

Funding Information
The grant funding must be expensed by 2030. The Library Expansion project completed the building scope of work, except the courtyard renovations and exterior landscaping, in 2022. The federal grant facilita ted by Ro Khanna’s office was awarded in 2024. The grant must be used for work that has not yet been completed.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 1,000,000
Other External Sources $ 0

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
420-99-077, CIV 007 $ 8,312,128 $ 500,000 $ 893,310

Projected Schedule/5-year Plan Information
Landscaping of the building perimeter and courtyard is designed, documented, and read y for a public bid process.

Additional scope under consideration (building electrification, extending electrical junctions to Library field, etc.) will require supplementary engineering and documentation. Staffing needs are deferring this work.

Item/Phase Timeline for Completion Notes
Project Initiation January 2027
Consultant Procurement January 2027 New Contracts must be executed.

Design March 2027 Landscape plans and specifications were completed in 2023. Re-visiting the priorities
will be a part of the renewed design process.

Permitting & Environmental Clearance June 2027 Building permits will be required.

Construction Bid August 2027
Contract Award and Contracting September 2027
Construction April 2028
Post-Construction/Close-out May 2028

Project Location

10800 Torre Avenue

Project Contact
Susan Michael, CIP Manager
[email protected]

FY25-26 CIP proposal and 5-year Plan Council Meetin g 4/02/2025 Page 10 of 34

INSERT SECTION PAGE (GRAPHICS!)

PARKS AND RECREATION PROJECTS
City of Cupertino
CIP FY26-27  5-YEAR PLAN

PROJECT NARRATIVES
PAGE 1
CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
Lawrence Mitty Park and Trail Plan page 1

Total Funding $ 9,181,084
City Funding $ 9,181,084
External Funding $ 0
Remaining Funds (Feb 2026) $ 5,756,750
Funding Source Dev In-Lieu, Gen. Fund
Approved [Master] Plan PRSMP
Project Category Parks & Recreation
Project Type Design & Construction
FY Initiated FY 18-19

Project Description
Design and Construct (with programming, public outreach and environmental studies) a neighborhood park located on several acres of land adjacent to Saratoga Creek, near the intersection of Lawrence Expressway and Mitty Way.

Project Justification
The City is under-served for neighborhood parks to meet the level of service goal of the City’s General Plan. The east side of the City is particularly under-served. The design process is underway, after a conceptual design process with an enhanced public outreach component. Adding this park is important for the residents on this side of the city.

Prioritization Total Points: 285

Health & Safety 2 Adding outdoor activity spaces benefits the health of the community.

Regulatory / Legal Mandate 1 Stormwater management, habitat preservation and other environmental regulations are primary on this project.

Asset Condition & Infrastructure
Risk
2 The site is a hardscaped staging area for highway construction projects. Adding a park and trail will have a positive impact.

Climate Resilience & Sustainability 5 Adding outdoor activity spaces and natural environments benefits the resilience and sustainability of the community.

Strategic Alignment 5 This project is squarely aligned with the Parks and Recreation System Master Plan.

Community Benefit & Equity 5 Adding a park and trail benefits the health of the community.

This will also add amenities to the east side of Cupertino.

Financial Leverage & Cost
Effectiveness
4 The project is funded by Developer Funds.

Project Readiness 4 The design and permitting are underway.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
Lawrence Mitty Park and Trail Plan page 2 Operating Budget Impacts Annual Estimated Impact: $ 300,000 When this park is completed, and ongoing maintenance efforts are added to operations, operating costs will increase for the Grounds Division. Ongoing needs are estimated at 1.5 FTE for Grounds ($ 250,000), along with increased expenditures for maintenance supplies estimated at $50,000 annually. An initial establishment period of 5 years may see increased staff time and expenditures.

Funding Information
In FY18-19, Apple fees for their project development were applied to the purchase, annexa tion, and development of this park ($8,270,994). The purchase and annexation costs were approximately $2,330,085. In FY23-24, additional operational funds were secured to reduce the existing berms on site. The berms reduction can occur once the design is more established.

External Funding
Pre-2026-27 2026-27 2027-28 2028-29 2029-30
Grants $ 0
Other External Sources $ 8,270,994

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
280-99-009, P LM 001 $ 3,424,334 4,750,000 1,006,750

Projected Schedule/5-year Plan Information
Land was acquired in September 2020. Design process underway. Due to the extent of environmental permitting required, the project is expected to remain active until the Spring of 2027.

Item/Phase Timeline for Completion Notes
Project Initiation, Consultant
Procurement, Planning/Pre-Design
Completed
Design and Documentation Current Phase
Permitting & Environmental Clearance June 2026
Construction Bid October 2026
Contract Award and Contracting November 2026
Construction December 2026
Post-Construction/Close-out March 2027

Project Location

Near Lawrence Expressway
and Mitty Avenue
Project Contact
Susan Michael, CIP Manager
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
McClellan Ranch - West Parking Lot Improvement page 1 Mitigation Measure Monitoring & Reporting
Total Funding $ 1,069,682
City Funding $ 1,069,682
External Funding $ 0
Remaining Funds (Feb 2026) $ 28,513
Funding Source Capital Reserve/GF
Approved [Master] Plan PRSMP
Project Category Parks & Recreation
Project Type Design & Construction
FY Initiated FY 16-17

Project Description
The riparian mitigation site between the parking lot and Stevens Creek was planted in 2 018 and replanted in 2023.

Performance Monitoring and reporting is required for five years, starting in 2023.

Project Justification
The McClellan Ranch West site was used informally for staff and overflow parking without a sui table, stable surface, and which is not available for use during wet weather due to mud. The opening of the Enviro nmental Education Center in 2015 increased the parking demand at McClellan Ranch Preserve. The removal of the S imms house on the site allowed for the installation of the additional needed parking with a suitable parking surface. This mitigation measure performance monitoring and reporting is required to continue to meet the requirements o f the Lake or Streambed Alteration Agreement (LSAA; Notification No. 1600-2018-0207-R3) issued by the California Department of Fish and Wildlife (CDFW) on December 14, 2018.

Prioritization Total Points: 290

Health & Safety 0 N.A.

Regulatory / Legal Mandate 5 Habitat improvements were required for installation of the parking area.

Asset Condition & Infrastructure
Risk
1 Climate Resilience & Sustainability 5 Native plantings.

Strategic Alignment 5 Aligned with the Parks and Recreation System Master Plan

Community Benefit & Equity 5 Adding natural environment benefits the community.

Financial Leverage & Cost
Effectiveness
5 Funding is entirely in place for habitat monitoring.

Project Readiness 5 Habitat monitoring is close to completion.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
McClellan Ranch - West Parking Lot Improvement page 2 Operating Budget Impacts Annual Estimated Impact: $0
No anticipated impact to operating budget.

Funding Information
This project received City funding in FY16-17, FY17-18 and FY18-19. The monies tha t remain fund the mitigation measure performance monitoring and reporting required by the LSAA permit.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 0
Other External Sources $ 0

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
420-99-030, MRW 002.04.00 $ 1,041,169 $7500 $7500

Projected Schedule/5-year Plan Information
The mitigation measure performance monitoring and reporting will continue until 20 27.

Item/Phase Timeline for Completion Notes
Project Initiation to Construction Complete
Post-Construction Habitat Monitoring 2027

Project Location

22241 McClellan Road
Project Contact
Susan Michael, CIP Manager
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
Annual Playground Replacement page 1 Replace Equipment and Improve Accessibility
Total Funding $ 1,500,000
City Funding $ 1,500,000
External Funding $ 0
Remaining Funds (Feb 2026) $ 916,329
Funding Source Capital Reserve/GF
Approved [Master] Plan PRSMP
Project Category Parks & Recreation
Project Type Design & Construction
FY Initiated FY 20-21

Project Description
Replacement of antiquated playground equipment for improved safety and inclusivity.

Project Justification
The playgrounds at several City parks are almost 20 years old, and many have different levels of safety issues. This project allows for the replacement of the equipment on an annual replacement schedule. This pr oject has been a valuable resource to address safety concerns at our playgrounds. Playgrounds improved to date incl ude two playgrounds at Creekside Park.

Prioritization Total Points: 395

Health & Safety 4 Providing safe play equipment is a very high priority.

Regulatory / Legal Mandate 3 Some accessibility requirements and other building codes do apply.

Asset Condition & Infrastructure
Risk
5 Many of the playground equipment parts are no longer available for repairs.

Climate Resilience & Sustainability 5 Improvements to the playgrounds creates more sustainable spaces, preventing the unnecessary degradation of the parks.

Strategic Alignment 5 Aligned with the Parks and Recreation System Master Plan.

Community Benefit & Equity 5 Improvements to the playgrounds are a direct benefit to the community as a public recreation facility.

Financial Leverage & Cost
Effectiveness
3 Funding is in place. Improvements to these amenities reduces repair costs.

Project Readiness 2 Playgrounds in need of replacement have been identified.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
Annual Playground Replacement page 2 Operating Budget Impacts Annual Estimated Impact: $0
No anticipated impact to the Operating Budget.

Funding Information
This initiative began in FY20-21 and was funded for five years.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 0
Other External Sources $ 0

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
420-99-085, PVAR 010 $ 583,671 $ 400,000 $ 400,000 $ 116,329

Projected Schedule/5-year Plan Information
This was an ongoing 5-year program, funding termed out in FY 24-25.

Item/Phase Timeline for Completion Notes
Project Initiation - Varian March 2027
Consultant Procurement May 2027
Planning/Pre-Design August 2027
Design and Documentation October 2027
Permitting & Environmental Clearance November 2027
Construction Bid, Contract Award and
Contracting
December 2027
Construction January - May 2028
Post-Construction/Close-out May 2028

Project Location

Various
Project Contact
Susan Michael, CIP
Manager
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
Park Amenity Improvements page 1

Total Funding $ 600,000

City Funding $ 600,000
External Funding $ 0
Remaining Funds (Feb 2026) $ 351,422
Funding Source Capital Reserve/GF
Approved [Master] Plan PRSMP
Project Category Parks & Recreation
Project Type Design & Construction
FY Initiated FY 20-21

Project Description
Funding for various park amenities such as benches, hydration stations, outdoor table tennis, cornhole, shade (structures and/or trees), dog-off-leash, pickleball striping, etc.

Project Justification
Residents requested upgrades to the Park amenities, and this program provides the funding and staffing for the procurement and implementation. The project has been a valuable resource to address commu nity concerns in our parks.

Prioritization Total Points: 245

Health & Safety 1 Improvements to the park amenities creates more effective activity spaces.

Regulatory / Legal Mandate 1 Some accessibility requirements and other building codes do apply.

Asset Condition & Infrastructure
Risk
3 The parks have many outdated amenities.

Climate Resilience & Sustainability 5 Improvements to the park amenities creates more sustainable spaces

Strategic Alignment 5 Aligned with the Parks and Recreation System Master Plan.

Community Benefit & Equity 5 Improvements to the park amenities are a direct benefit to the community.

Financial Leverage & Cost
Effectiveness
3 Funding is in place. Improvements to these amenities reduces repair costs.

Project Readiness 2 The list of amenities was provided by the PRSMP and the P&R Commission.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
Park Amenity Improvements page 2 Operating Budget Impacts Annual Estimated Impact: $0
Negligible anticipated impact to operating budget.

Funding Information
This initiative began in FY20-21 and was funded for three years.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 0
Other External Sources $ 0

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
420-99-086, PVAR 011 $ 248,578 $ 50,000 $ 125,000 $ 125,000 $ 51,422

Projected Schedule/5-year Plan Information
The existing Park sites’ Amenities were evaluated by staff and the Parks and Recreation Commission, and a prioritization schedule developed. Installations are underway.

Item/Phase Timeline for Completion Notes
All Phases 2030 Ongoing initiative

Project Location

Various

Project Contact
Susan Michael, CIP Manager
[email protected]

FY25-26 CIP proposal and 5-year Plan Council Meetin g 4/02/2025 Page 17 of 34

INSERT SECTION PAGE (GRAPHICS!)

STREETS AND INFRASTRUCTURE PROJECTS
City of Cupertino
CIP FY26-27  5-YEAR PLAN

PROJECT NARRATIVES
PAGE 1
CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
Storm Drain Outfalls Repairs page 1 Priority projects from 2024 Outfalls report
Total Funding $ 950,000

City Funding $ 950,000
External Funding $ 0
Remaining Funds (Feb 2026) $ 950,000
5-year Funding Total TBD
Funding Source Capital Reserve/GF
Approved [Master] Plan SDMP and 2024 Outfalls
Report
Project Category Streets & Infrastructure
Project Type Design & Construction
FY Initiated FY 25-26

Project Description
The 2024 Storm Drain Outfall Condition Assessment report assessed 205 pipe segments across 1 75 sites. Of the 117 outfalls three were in level 5 defective condition, and three were in level 4 defective condition. The FY25-26 funding requested will address the three outfalls that have the most severe damage and present as imminent failures. In following years, additional funding will be requested to address deficiencies noted in the report.

The three locations for FY25-26 are: #SWPP398 is an 48-inch diameter corrugated metal pipeline (CMP) near the vicinity of Whitney Way and Pacific Drive, #SWPP1546 is an 15-inch diameter corrugated metal pipeline (CMP) near the vicinity of Richwood Court and Miller Avenue, and #SWPP3360 is an 30-inch diameter corrugated metal pipeline (CMP) near the vicinity of Finch Avenue and Stevens Creek Boulevard. All three show signs of corrosion and need to be rehabilitated.

Project Justification
The Storm Drain Outfall Condition Assessment Project completed in 2024 identified multiple st ructural defects of existing storm drain pipelines that need to be rehabilitated. These defects pose a significant risk t o the integrity of the storm drain system. Addressing the issues through timely rehabilitation is crucial to maintai n the functionality of the system. This project will mitigate the outfalls’ defects to prevent further deterioration of the pipelines. The project is of high importance to address the risk of pipeline failure

Prioritization Total Points: 305

Health & Safety 4 Improvements to the storm water infrastructure contribute to health and safety.

Regulatory / Legal Mandate 3 Environmental permitting is required. Maintenance of the City’s SW infrastructure is mandated by the State and County.

Asset Condition & Infrastructure
Risk
4 Many of the outfall are nearing failure.

Climate Resilience & Sustainability 4 Improvements to the SW system will have a positive effect on the surrounding habitat.

Strategic Alignment 3 Aligned with the Storm Drain Master Plan.

Community Benefit & Equity 2 Improvements to the storm water infrastructure contribute to health and safety

Financial Leverage & Cost
Effectiveness
4 Working with Valley Water for increased effectiveness.

Project Readiness 2 Report completed, analyzing the City’s outfalls.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
Storm Drain Outfalls Repairs page 2 Operating Budget Impacts Annual Estimated Impact: $0
There are no anticipated impacts to the Operating Budget except reduced maintenance/repair costs.

Funding Information
Funding source for this project will be from either General Fund or Stormwater Fund. No grant funds are presently available.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 0
Other External Sources $ 0

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
420-99-276, ST 070 $ 0 $ 950,000 $ 600,000 $ 300,000 $ 600,000 $ 600,000

Projected Schedule/5-year Plan Information
It is estimated that the construction of the first three outfall repairs can be completed within a year.

Item/Phase Timeline for Completion Notes
Project Initiation Completed
Consultant Procurement TBD Working with Valley Water in conjunction with their CIP work.

Planning, Design and Documentation TBD
Permitting & Environmental Clearance TBD
Construction Bid, Award, Contract TBD
Construction TBD
Post-Construction/Close-out TBD

Project Location

Various
Project Contact
Susan Michael, CIP Manager
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
Vai Avenue Outfall page 1

Total Funding $ 490,000
City Funding $ 490,000
External Funding $ 0
Remaining Funds (Feb 2026) $ 434,804
Funding Source Capital Reserve, SD fund
Approved [Master] Plan SDMP
Project Category Streets & Infrastructure
Project Type Design & Construction
FY Initiated FY 24-25

Project Description
Investigate, design, and replace existing failing 36” corrugated metal pipe (CMP) storm drain l ine with new reinforced concrete pipe (RCP) or high-density polyethylene (HDPE) pipe.

Project Justification
In December 2023, the City was made aware of damage to this storm drain outfall. The City operates and maintains the storm drain facilities throughout Cupertino. The storm drain pipe in question has corroded, undermined the creek bank, and needs to be replaced before further erosion and property damage occurs. Replacement of the pipe is necessary to ensure proper operation to protect public and private property and safety.

Prioritization Total Points: 305

Health & Safety 4 Improvements to the storm water infrastructure contribute to health and safety.

Regulatory / Legal Mandate 3 Environmental permitting is required. Maintenance of the City’s SW infrastructure is mandated by the State and County.

Asset Condition & Infrastructure
Risk
4 The outfall failed. The repair will last a few seasons.

Climate Resilience & Sustainability 1 Improvements to the SW system will have a positive effect on the surrounding habitat.

Strategic Alignment 2 Aligned with the Storm Drain Master Plan.

Community Benefit & Equity 3 Improvements to the storm water infrastructure contribute to health and safety

Financial Leverage & Cost
Effectiveness
2 Working with Valley Water for increased effectiveness.

Project Readiness 2 Report completed, analyzing the City’s outfalls.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
Vai Avenue Outfall page 2 Operating Budget Impacts Annual Estimated Impact: $0
No anticipated impact to operating budget.

Funding Information
The initial repair used approximately $55,000. The proposed budget will enable design, cons truction, and environmental permitting of the CMP replacement. Storm Drain funds (210) will be used if avail able.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 0
Other External Sources $ 0

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
420-99-275, ST 065 $ 55,196 $ 434,804

Projected Schedule/5-year Plan Information
The outfall was patched with a new section of CMP as a quick fix in October 2024. The repair should la st one or two rainy seasons, then we can pursue full replacement of the CMP that has eroded. Site access is difficult and will require environmental permitting.

Item/Phase Timeline for Completion Notes
Project Initiation
Consultant Procurement
Planning, Design and Documentation
Permitting & Environmental Clearance
Construction Bid, Award, Contract
Construction
Post-Construction/Close-out

Project Location

Various
Project Contact
Susan Michael, CIP Manager
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
Stevens Creek Bridge Repairs page 1 Improve structural foundations
Total Funding $ 860,000

City Funding $ 172,000
External Funding $ 688,000
Remaining Funds (Feb 2026) $ 771,982
Funding Source Capital Reserve/GF,
Grants
Approved [Master] Plan General Plan
Project Category Streets & Infrastructure
Project Type Design & Construction
FY Initiated FY 23-24

Project Description
Repairs to the bridge supports to include countermeasures to scouring (undermining) of the support bases.

Project Justification
The design of the existing bridge utilizes mat foundations for the bridge supports that have started to become undermined. This project will perform modifications to create a firm structural footing for the supports. The condition of the support foundations has been noted in recent biennial bridge inspection reports and the repairs are recommended by Caltrans. The repair work is funded by the FHWA Highway Bridge Program for 88.53% of the design and construction costs. Improving the safety of our City bridges is a leading priority. Grant funding has been secured which enables the project team to proceed with preliminary engineering. The enginee ring firm is in contract with the City. This will provide insight into final scope and costs.

Prioritization Total Points: 380

Health & Safety 5 Having a safe and efficient bridge over Stevens Creek is important to the Community.

Regulatory / Legal Mandate 3 Maintaining a functional arterial roadway is a Federal, State and County mandate.

Asset Condition & Infrastructure
Risk
4 The FHWA report determine that repairs to the Bridge are critical.

Climate Resilience & Sustainability 1 Improvements to the Bridge will modestly increase sustainability and community resiliency.

Strategic Alignment 2 Having safe, attractive and well-maintained facilities for walking, bicycling, transit and automobile is a General Plan goal.

Community Benefit & Equity 3 Having a safe and efficient bridge over Stevens Creek is important to the Community.

Financial Leverage & Cost
Effectiveness
5 Grant funding has been secured.

Project Readiness 2 The FHWA bridge inspection reports form the basis of the conceptual design.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
Stevens Creek Bridge Repairs page 2 Operating Budget Impacts Annual Estimated Impact: $0
No anticipated impact to operating budget.

Funding Information
FHWA funding was awarded for this project. Funding for the design phase is currently programm ed in the FTIP for the 2023/24 FFY and construction funding is programmed for ‘beyond 2025/26. ’ Staff will continue to work with Caltrans to identify opportunities to make construction funds available sooner to minimize time f rom end of design to the start of construction.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 688,000
Other External Sources $ 0

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
420-99-267, ST 063. $ 88,018 $250,000 521,982

Projected Schedule/5-year Plan Information
Engineering consultants have initialized the preliminary design phase of the project. Once the scope of work required is more defined, a projected schedule will be developed.

Item/Phase Timeline for Completion Notes
Project Initiation Completed
Consultant Procurement Completed
Planning/Pre-Design Current Phase 6 Months
Design and Documentation TBD 12 Months
Permitting & Environmental Clearance TBD 18 Months
Bid, Contract Award and Execution TBD 3 Months
Construction TBD 6 Months
Post-Construction/Close-out TBD 3 Months

Project Location

22120 Stevens Creek Blvd.

Project Contact
Susan Michael, CIP Manager
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
McClellan Road Bridge Reconstruction page 1

Total Funding (projected) $ 8,000,000

City Funding $ 0
External Funding $ 5,850,000
Remaining Funds (Feb 2026) $ 5,850,000
Funding Source Capital Reserve/GF,
Grants
Approved [Master] Plan General Plan
Project Category Streets & Infrastructure
Project Type Design & Construction
FY Initiated FY 24-25

Project Description
Repair or Reconstruction of the bridge on McClellan Road near the entrance to McClella n Ranch Preserve.

Project Justification
The existing bridge was constructed in 1920 and is beyond its design life. It does not meet current requirements for pedestrian access and lacks the width to facilitate bicycle lanes. A reconstructed bridge will enhance pedestrian facilities. $5.85M in grant funding has been secured. Approximately $2.2M in funding is still r equired. Priority for Safety criteria, following recommendations from inspection reports issued by Caltrans. CIP is sta rting preliminary design in FY 24-25 to support efforts to obtain additional grant funding.

Prioritization Total Points: 380

Health & Safety 5 Having a safe and efficient bridge over Stevens Creek is important to the Community.

Regulatory / Legal Mandate 3 Maintaining a functional arterial roadway is a Federal, State and County mandate.

Asset Condition & Infrastructure
Risk
4 The FHWA report determine that repairs to the Bridge are critical.

Climate Resilience & Sustainability 1 Improvements to the Bridge will modestly increase sustainability and community resiliency.

Strategic Alignment 2 Having safe, attractive and well-maintained facilities for walking, bicycling, transit and automobile is a General Plan goal.

Community Benefit & Equity 3 Having a safe and efficient bridge over Stevens Creek is important to the Community.

Financial Leverage & Cost
Effectiveness
5 Grant funding has been secured.

Project Readiness 2 The FHWA bridge inspection reports form the basis of the conceptual design.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
McClellan Road Bridge Reconstruction page 2 Operating Budget Impacts Annual Estimated Impact: $0
No anticipated impact to operating budget.

Funding Information
Design and construction will require approximately $8M in funding. Staff proposes to utilize the existing grant funding to initiate preliminary engineering design which will provide further opportunities to apply f or grants to complete the project funding.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 5,850,000
Other External Sources $ 0

Expenditure Schedule/5-year Plan Information
Annual Expenditures
(GL#)
2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
2031-32
Projected
420-99-273, ST 066 $ 0 $ 0 $ 0 $ 500,000 $ 600,000 $600,000 $6,300,000

Projected Schedule/5-year Plan Information
Design and Construction will be a multi-year endeavor, requiring environmental permits an d Caltrans approvals for both design and construction procurement.

Item/Phase Timeline for Completion Notes
Project Initiation Completed
Consultant Procurement Completed
Planning/Pre-Design Current Phase 9 Months
Design and Documentation TBD 24 Months
Permitting & Environmental Clearance TBD 18 Months
Bid, Contract Award, and Execution TBD 6 Months
Construction TBD 12 Months
Post-Construction/Close-out TBD 6 Months

Project Location

Near 22211 McClellan Road
Project Contact
Susan Michael, CIP Manager
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
Streetlight Installation – Annual Infill page 1

Total Funding $ 430,536
City Funding $ 430,536
External Funding $ 0
Remaining Funds (Feb 2026) $ 138,882
Funding Source GF
Approved [Master] Plan General Plan
Project Category Streets & Infrastructure
Project Type Design & Construction
FY Initiated FY 17-18

Project Description
Design and install streetlights on an as needed basis, to infill lights and poles when requested by residents.

Project Justification
There are areas of the city where streetlight spacing is insufficient to meet current standards for illuminat ion. Several locations are identified annually for infill with one or two lights. This annual appropria tion allows these deficiencies to be readily addressed. Providing these services and fixtures for resident safety and welfare is im portant.

Prioritization Total Points: 220

Health & Safety 3 Community requests for enhanced lighting improves safety in the neighborhoods.

Regulatory / Legal Mandate 1 Outdoor lighting standards will be applied.

Asset Condition & Infrastructure
Risk
1 The streetlight infrastructure is in generally good condition; however, several streetlights have not yet been installed.

Climate Resilience & Sustainability 2 New fixtures are efficient and long-lasting.

Strategic Alignment 3 Providing a safe multimodal environment aligns with the General Plan, Bike and Pedestrian Transportation plans.

Community Benefit & Equity 2 The streetlights installed will come directly from the community.

Financial Leverage & Cost
Effectiveness
2 Funding is in place to meet the need.

Project Readiness 4 The work can be done inhouse.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
Streetlight Installation – Annual Infill page 2 Operating Budget Impacts Annual Estimated Impact: $0
Negligible anticipated impact to operating budget.

Funding Information
This initiative began in FY17-18 and has been funded annually for a total of $430,000 as of February 2025. Most years had allocations of $75,000 per year. This amount was reduced in recent years to be $35,000. No request for additional funds in FY25-26. This may move to become Streets division “Special Project” in FY26-27.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 0
Other External Sources $ 0

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
420-99-056, ST 024 $ 291,654 $ 50,000 $ 50,000 $ 50,000 $ 50,000 $ 50,000

Projected Schedule/5-year Plan Information
Ongoing program.

Item/Phase Timeline for Completion Notes
All Phases N.A. This is an ongoing initiative.

Project Location

Various
Project Contact
Susan Michael, CIP Manager
[email protected]

FY25-26 CIP proposal and 5-year Plan Council Meetin g 4/02/2025 Page 24 of 34

INSERT SECTION PAGE (GRAPHICS!)

TRANSPORTATION PROJECTS
City of Cupertino
CIP FY26-27  5-YEAR PLAN

PROJECT NARRATIVES
PAGE 1
CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
Stevens Creek Blvd Class IV Bikeway – Phase 2A page 1 Separated Bikeway and Signal Upgrades
Total Funding $ 2,385,782
City Funding $ 2,385,782
External Funding $ 807,000 (OBAG)
External Funding $ 693,000 (SB1)
Remaining Funds (Feb 2026) $ 2,135,377
Funding Source Grants, GF
Approved [Master] Plan BTP
Project Category Transportation
Project Type Design & Construction
FY Initiated FY 20-21

Project Description
Phase 2A includes design and construction of the separated bikeway along Stevens Creek Blvd (SCB ) from Wolfe Road to De Anza Blvd. Improvements include traffic signal modifications at Wolfe Road and De Anza Blvd to provide separate bicycle phasing.

Project Justification
The 2016 Bicycle Transportation Plan identifies improvements needed and priorities to enhance and promote safer bicycle transportation in the City. The number one priority of the Plan was to provide a separa ted Class IV bicycle lane on Stevens Creek Blvd. This project is the second phase to address that priority. Improvin g vehicular, pedestrian and bicyclist safety is a primary concern. The Bike Transportation plan named this the first priority, and the Pedestrian Transportation assigned this Tier 1 priority

Prioritization Total Points: 285

Health & Safety 3 This project promotes safer bicycle transportation in the City.

Regulatory / Legal Mandate 1 Traffic/Roadway regulations will be respected.

Asset Condition & Infrastructure
Risk
2 The current bike lanes and signals are in need of improvements

Climate Resilience & Sustainability 3 Promoting bicycling encourages climate resilience and sustainability.

Strategic Alignment 5 This is the number one priority of the 2016 Bicycle Transportation Plan.

Community Benefit & Equity 3 Bikeways that are safer protect vehicular, pedestrian and bicycle users.

Financial Leverage & Cost
Effectiveness
3 Grant funding is in place.

Project Readiness 5 Construction is underway.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
Stevens Creek Blvd Class IV Bikeway – Phase 2A page 2 Operating Budget Impacts Annual Estimated Impact: $42,000 When this improvement is completed, and ongoing maintenance efforts are added to operations, operating costs will increase for the Streets Division. Ongoing needs are estimated at 0.1 FTE for Streets ($1 7,000), along with increased expenditures for maintenance supplies estimated at $25,000 annually. Additional efforts associated with cleaning of lanes and replacement of reflective markers..

Funding Information
External grant funding has been secured for this project (OBAG and SB1 funding) and this will be used to reduce the City’s costs on Phase 2A. The remainder of the funds allocated by the City for Phase 2 will be used on Phase 2B.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 1,500,000
Other External Sources $ 0

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
40-99-036, ST 053, ST 059 $ 250,405 $ 2,000,000

Projected Schedule/5-year Plan Information
Design and Documentation, and community outreach for Phase 2A (Wolfe Road to De Anza Blvd.) is complete. The construction contract for Phase 2A was awarded in February 2025. Construction will be complete before the end of the calendar year. See Phase 2B project narrative for more information on the subsequent work on this project.

Item/Phase Timeline for Completion Notes
Project Initiation, Consultant
Procurement, Design and Documentation,
Bid, Contract Award and Execution
Completed
Construction Summer 2026
Post-Construction/Close-out Summer 2026

Project
Location

SCB – Wolfe
Road/Miller Avenue to
De Anza Boulevard
Project
Contact

Susan Michael, CIP
Manager
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
Roadway Safety Improvements page 1 High Friction Pavement and Speed Feedback Signage
Total Funding $ 3,561,800
City Funding $ 356,180
External Funding $ 3,205,620 (HSIP)
Remaining Funds (Feb 2026) $ 3,513,115
Funding Source Capital Reserve, Grant
Approved [Master] Plan GP
Project Category Transportation
Project Type Design & Construction
FY Initiated FY 24-25

Project Description
High Friction pavement treatment and speed feedback signage added to seventeen locations within the City. Roadway segments include sections of: De Anza Blvd, Homestead Rd, Bollinger Rd, Wolfe Rd, McClellan Rd, Bubb Rd, Mariani Ave, Tantau Ave, Mary Ave, Blaney Ave, Rainbow Dr, Miller Ave, Stelling Rd, Valley Green Dr, and Calvert Dr.

Project Justification
Improves safety on roadway segments by reducing unsafe speed violations and rear end collision b y implementing dynamic/variable speed warning signs at the curves along the corridor and improving pavement friction. Thi s scope of work supports the Local Roadway Safety Plan (LRSP), which identifies transportation saf ety improvement needs for all ages, abilities, and modes of transportation for the purpose of reducing fatal and severe injury collisions. In July 2023, City Council accepted state funding from the Highway Safety Improvement Program (HSIP) grant for safety improvements on 17 roadway segments in the City of Cupertino. $3.2M in grant funding has be en secured, 10% matching funding required by the City. Priority for Safety criteria.

Prioritization Total Points: 290

Health & Safety 4 The aim of this project is to create safer driving conditions for vehicular traffic.

Regulatory / Legal Mandate 1 One aspect of this project is to encourage drivers to be aware and observant of the speed limits.

Asset Condition & Infrastructure
Risk
1 This project was not motivated by pavement conditions but rather additional surface treatment and updated signage.

Climate Resilience & Sustainability 2 Improved pavement may increase the durability of the road surface, progressing sustainability.

Strategic Alignment 2 Safer roads address the General Plan goals for the transportation infrastructure.

Community Benefit & Equity 2 The aim of this project is to create safer driving conditions for vehicular traffic, benefitting the community.

Financial Leverage & Cost
Effectiveness
5 The project is funded by grants.

Project Readiness 5 The design is fully documented and working towards construction.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
Roadway Safety Improvements page 2

Operating Budget Impacts Annual Estimated Impact: $18,500 When this improvement is completed, and ongoing maintenance efforts are added to operations, operating costs will increase for the Streets Division. Ongoing needs are estimated at 0.05 FTE for Streets ($ 8,500), along with increased expenditures for maintenance supplies estimated at $10,000 annually. Additional efforts associated with maintenance and replacement of signs and modified paving surfaces.

Funding Information
Funding will be applied to design and construction.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 3,205,620
Other External Sources $ 0

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
270-99-271, ST 068 $ 48,685 $ 3,513,115

Projected Schedule/5-year Plan Information
The project is ready to Bid. The construction can be completed in winter 2026.

Item/Phase Timeline for Completion Notes
Project Initiation, Consultant Procurement Completed
Design and Documentation 95% complete
Bid, Contract Award and Execution Summer 2026 3 – 6 months in duration Construction Fall - Winter 2026
Post-Construction/Close-out TBD

Project Location

Various. Roadway segments
include sections of: De Anza
Blvd, Homestead Rd, Bollinger
Rd, Wolfe Rd, McClellan Rd,
Bubb Rd, Mariani Ave, Tantau
Ave, Mary Ave, Blaney Ave,
Rainbow Dr, Miller Ave,
Stelling Rd, Valley Green Dr,
and Calvert Dr

Project Contact
Susan Michael, CIP Manager
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
Tamien Innu, East Segment page 1 East Segment of the Trail
Total Funding $ 2,536,000
City Funding $ 0
External Funding $ 600,000 (Apple)
External Funding – Constrn. $ 1,936,000 (VTA Meas B)
Remaining Funds (Feb 2026) $ 2,001,081
Funding Source Dev, Grant
Approved [Master] Plan BTP, PTP
Project Category Transportation
Project Type Design and Construction
FY Initiated FY 20-21

Project Description
Design and Construction of an off-street bicycle and pedestrian trail parallel to the existing I-280 and Junipero Serra Channel from Vallco Parkway to Wolfe Road. The central segment runs from Wolfe Road t o De Anza Boulevard, and the west segment would run from De Anza Boulevard to Mary Avenue.

Project Justification
Highly prioritized in the 2016 Bicycle Transportation Plan, the Tamien Innu is one of the trail segments that would make up “The Loop” to provide an off-street bicycle and pedestrian facility that runs parallel to the existing Junipero Serra Channel and Calabazas Creek and would provide a connection between the Don Burnett Bicycle – Pedestrian Bridge and Vallco Parkway when all the sections are completed. Facilitating alternative means of transp ortation is a valuable resource for the City and its businesses.

Prioritization Total Points: 300

Health & Safety 3 These trails will increase connectivity, advancing healthy outdoor engagement.

Regulatory / Legal Mandate 1 Engagement with environmental agencies is a large factor in the success of this project.

Asset Condition & Infrastructure
Risk
1 A maintenance road is in place, forming the basis of the design.

Climate Resilience & Sustainability 4 These trails will increase connectivity, advancing healthy outdoor engagement.

Strategic Alignment 5 This project is highly prioritized in the 2016 Bicycle and Pedestrian Transportation Plans.

Community Benefit & Equity 2 These trails will increase connectivity, advancing healthy outdoor engagement and multimodal opportunities for the Community.

Financial Leverage & Cost
Effectiveness
5 The project is funded entirely by grants and other external funding.

Project Readiness 5 The East segment design is nearing completion.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
Tamien Innu, East Segment page 2 Operating Budget Impacts Annual Estimated Impact: $60,000 When this improvement is completed, and ongoing maintenance efforts are added to operations, operating costs will increase for the Trees Division. Ongoing needs are estimated at 0.25 FTE for Trees ($4 5,000), along with increased expenditures for maintenance supplies estimated at $15,000 annually..

Funding Information
Developer funding was contracted in FY18-19, and Council added the project to the CIP in FY20 -21. VTA Measure B funding has been awarded.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 1,936,000
Other External Sources $ 600,000

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
420-99-036, ST 050 $ 534,919 $ 300,000 $ 1,036,000

Projected Schedule/5-year Plan Information
Schematic design for both the Central and East segments has been submitted f or environmental review. Construction and permitting documentation for the East segment are underway. The Central segment design a nd construction will progress once the first segment enters construction, and the environmental report is reviewed.

Item/Phase Timeline for Completion Notes
Project Initiation, Consultant Procurement Completed
Design and Documentation 60% complete Valley Water reviews and approvals have extended the project considerably.

Environmental/Regulatory Permitting July 2027 Environmental Permitting can be lengthy process
Bid, Contract Award and Execution October 2027
Construction April 2028
Post-Construction/Close-out July 2028

Project Location

Runs parallel to I-280 and the
existing Junipero Serra Channel
and Calabazas Creek, from
Vallco Pkwy to Wolfe Road.

Project Contact
Susan Michael, CIP Manager
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
Tamien Innu, Central Segment page 1 Central Segment of the Trail
Total Funding $ 4,785,000
City Funding $ 0
External Funding $ 600,000 (Apple)
External Funding - Design $ 460,000 (VTA Meas B)
External Funding - Cnstrn $ 3,725,000 (VTA Meas B)
Remaining Funds (Feb 2026) $ 4,578,225
Funding Source Dev, Grant
Approved [Master] Plan BTP, PTP
Project Category Transportation
Project Type Design & Construction
FY Initiated FY 20-21

Project Description
Design and Construction of an off-street bicycle and pedestrian trail parallel to the existing I-280 and Junipero Serra Channel from Wolfe Road to De Anza Boulevard. The east segment runs from Vallco Parkway to Wolfe Road, and the west segment would run from De Anza Boulevard to Mary Avenue.

Project Justification
Highly prioritized in the 2016 Bicycle Transportation Plan, the Tamien Innu is one of the trail segments that would make up “The Loop” to provide an off-street bicycle and pedestrian facility that runs parallel to the existing Junipero Serra Channel and Calabazas Creek and would provide a connection between the Don Burnett Bicycle – Pedestrian Bridge and Vallco Parkway when all the sections are completed. Facilitating alternative means of transp ortation is a valuable resource for the City and its businesses.

Prioritization Total Points: 300

Health & Safety 3 These trails will increase connectivity, advancing healthy outdoor engagement.

Regulatory / Legal Mandate 1 Engagement with environmental agencies is a large factor in the success of this project.

Asset Condition & Infrastructure
Risk
1 A maintenance road is in place, forming the basis of the design.

Climate Resilience & Sustainability 4 These trails will increase connectivity, advancing healthy outdoor engagement.

Strategic Alignment 5 This project is highly prioritized in the 2016 Bicycle and Pedestrian Transportation Plans.

Community Benefit & Equity 2 These trails will increase connectivity, advancing healthy outdoor engagement and multimodal opportunities for the Community.

Financial Leverage & Cost
Effectiveness
5 The project is funded entirely by grants and other external funding.

Project Readiness 5 The East segment design is nearing completion. This will form the basis of the Central segment design.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
Tamien Innu, Central Segment page 2 Operating Budget Impacts Annual Estimated Impact: $ 115,000 When this improvement is completed, and ongoing maintenance efforts are added to operations, operating costs will increase for the Trees Division. Ongoing needs are estimated at 0.50 FTE for Trees ( $85,000), along with increased expenditures for maintenance supplies estimated at $30,000 annually.

Funding Information
Developer funding was contracted in FY18-19, and Council added the project to the CIP in FY20 -21. VTA Measure B and TDA3 funding has been awarded.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 4,185,000
Other External Sources $ 600,000

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
420-99-036, ST 046 $600,000 $4,185,000

Projected Schedule/5-year Plan Information
Schematic design for both the Central and East segments have been submitted for environmental review. Construction and permitting documentation for the East segment are underway. The Central segment design a nd construction will progress once the East segment enters construction, and the environmental report is reviewed.

Item/Phase Timeline for Completion Notes
Project Initiation, Consultant Procurement Completed
Design and Documentation 30% complete Schematic Design formed the basis of the CEQA report.

Environmental/Regulatory Permitting July 2028 12 months duration Bid, Contract Award and Execution October 2028 3 months duration Construction April 2029 6 months duration
Post-Construction/Close-out July 2029 3 months

Project Location

Runs parallel to I-280 and the
existing Junipero Serra Channel
and Calabazas Creek, from
Wolfe Road to De Anza Blvd.

Project Contact
Susan Michael, CIP Manager
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
Tamien Innu, West Segment page 1 West Segment of the Trail
Total Funding $ 600,000
City Funding $ 0
External Funding $ 600,000 (Apple)
Remaining Funds (Feb 2026) $ 600,000
Funding Source Dev.

Approved [Master] Plan BTP, PTP
Project Category Transportation
Project Type Design & Construction
FY Initiated FY 20-21

Project Description
Design and Construction of an off-street bicycle and pedestrian trail parallel to the existing I-280 and Junipero Serra Channel from De Anza Boulevard to Mary Avenue. The east segment runs from Vallco Parkway to Wo lfe Road, and the central segment runs from Wolfe Road to De Anza Boulevard.

Project Justification
Highly prioritized in the 2016 Bicycle Transportation Plan, the Tamien Innu is one of the trail segments that would make up “The Loop” to provide an off-street bicycle and pedestrian facility that runs parallel to the existing Junipero Serra Channel and Calabazas Creek and would provide a connection between the Don Burnett Bicycle – Pedestrian Bridge and Vallco Parkway when all the sections are completed. Facilitating alternative means of transp ortation is a valuable resource for the City and its businesses.

Prioritization Total Points: 300

Health & Safety 3 These trails will increase connectivity, advancing healthy outdoor engagement.

Regulatory / Legal Mandate 1 Engagement with environmental agencies is a large factor in the success of this project.

Asset Condition & Infrastructure
Risk
1 A maintenance road is in place, forming the basis of the design.

Climate Resilience & Sustainability 4 These trails will increase connectivity, advancing healthy outdoor engagement.

Strategic Alignment 5 This project is highly prioritized in the 2016 Bicycle and Pedestrian Transportation Plans.

Community Benefit & Equity 2 These trails will increase connectivity, advancing healthy outdoor engagement and multimodal opportunities for the Community.

Financial Leverage & Cost
Effectiveness
5 The project is funded entirely by grants and other external funding.

Project Readiness 5 The East segment design is nearing completion. This will form the basis of the Central segment design.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
Tamien Innu, West Segment page 2 Operating Budget Impacts Annual Estimated Impact: $ 115,000 When this improvement is completed, and ongoing maintenance efforts are added to operations, operating costs will increase for the Trees Division. Ongoing needs are estimated at 0.50 FTE for Trees ($8 5,000), along with increased expenditures for maintenance supplies estimated at $30,000 annually.

Funding Information
Developer funding was contracted in FY18-19, and Council added the project to the CIP in FY20 -21..

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 0
Other External Sources $ 600,000

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
420-99-036, ST 051 $600,000

Projected Schedule/5-year Plan Information
Schematic design for both the Central and East segments have been submitted for environmental review. Construction and permitting documentation for the East segment are underway. The Central segment design a nd construction will progress once the first segment enters construction, and the environmental report is reviewed.

Item/Phase Timeline for Completion Notes
Project Initiation, Consultant Procurement Completed
Design and Documentation TBD 9 Months
Environmental/Regulatory Permitting TBD 12 Months
Bid, Contract Award and Execution TBD 3 Months
Construction TBD 6 Months
Post-Construction/Close-out TBD 3 Months

Project Location

Runs parallel to I-280 and the
existing Junipero Serra Channel
and Calabazas Creek, from De
Anza Blvd. to Mary Avenue.

Project Contact
Susan Michael, CIP Manager
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIV E
Stevens Creek Blvd Class IV Bikeway – Phase 2B page 1 Separated Bikeway and Signal Upgrades
Total Funding $ 0
City Funding $ 0
External Funding $ 0
Remaining Funds (Feb 2026) N.A.

Funding Source TBD
Approved [Master] Plan BTP
Project Category Transportation
Project Type Design & Construction
FY Initiated FY 20-21

Project Description
Phase 2B includes design and construction of the separated bikeway along Stevens Creek Blvd (SCB) from De Anza Blvd. to Highway 85. Project will include traffic signal modifications at De Anza Blvd and Stelling Ro ad to reduce conflicts between bicyclists and vehicle. *Note: SCB Phase 2A and 2B were jointly funded in de sign. SCB Bikeway Phase 2B and Bandley Drive Signal Upgrade projects are combined in design and construction to increase efficiency, however funding is noted separately because the Bandley intersection project is funded with DIL fees.

Project Justification
The 2016 Bicycle Transportation Plan identifies imp rovements needed and priorities to enhance and prom ote safer bicycle transportation in the City. The highest priority project of the Plan was to provide a separate d Class IV bicycle lane on Stevens Creek Blvd. This project is the third phase to address that priority. Improving vehicu lar, pedestrian and bicyclist safety is a primary concern.

Prioritization Total Points: 275

Health & Safety 3 This project promotes safer bicyc le transportation in the City.

Regulatory / Legal Mandate 1 Traffic/Roadway regula tions will be respected.

Asset Condition & Infrastructure
Risk
2 The current bike lanes and signals are in need of improvements

Climate Resilience & Sustainability 1 Promoting bic ycling encourages climate resilience and sustainability.

Strategic Alignment 5 This is the number one priori ty of the 2016 Bicycle Transportation Plan.

Community Benefit & Equity 3 Bikeways that are safe r protect vehicular, pedestrian and bicycle users.

Financial Leverage & Cost
Effectiveness
3 Grant funding can be secured.

Project Readiness 5 Design documentation is 95% com plete.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIV E
Stevens Creek Blvd Class IV Bikeway – Phase 2B page 2

Operating Budget Impacts Annual Estimated Impact: $ 42,000 When this improvement is completed, and ongoing mai ntenance efforts are added to operations, operating costs will increase for the Streets Division. Ongoing needs are estimated at 0.1 FTE for Streets ($17,000), alon g with increased expenditures for maintenance supplies estimated at $25,000 annually. Additional efforts associated wit h cleaning of lanes and replacement of reflective markers.

Funding Information
*External grant funding has been secured for Phase 2A of this project and this will be used to reduce the City’s costs on Phase 2A. The remainder of the funds allocated b y the City for Phase 2 will then be used on Phase 2 B. External funding may be available for Phase 2B.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 0
Other External Sources $ 0

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
420-99-036, ST 053, ST 059 TBD TBD

Projected Schedule/5-year Plan Information
Design and Documentation of Phase 2B and the Bandle y project is 95% complete. The project will be perm itted, bid, and constructed once Phase 2A is complete.

Item/Phase Timeline for Completion Notes
Project Initiation, Consultant Procurement Completed
Design and Documentation 95% complete
Bid, Contract Award and Execution TBD 3 – 6 months in duration Construction TBD
Post-Construction/Close-out TBD

Project
Location

SCB – De Anza
Boulevard to Hwy 85

Project
Contact

Susan Michael, CIP
Manager
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
Bandley Drive Signal Upgrades page 1 Traffic and Signal Upgrades
Total Funding $ 150,090
City Funding $ 124,432
External Funding $ 25,658
Remaining Funds (Feb 2026) $ 142,210
Funding Source Dev In-Lieu, GF
Approved [Master] Plan BTP
Project Category Transportation
Project Type Design and Construction
FY Initiated FY 18-19

Project Description
Upgrades to the traffic signal at Bandley Dr. and Stevens Creek Blvd. will include new conduit, wirin g, traffic signal boxes, two new signal heads, and a split phase signal operation for vehicles entering onto Stevens Creek Blvd. Note:

SCB Bikeway Phase 2B and Bandley Drive Signal Upgrade projects are combined in design and construction to increase efficiency. Funding is noted separately because the Bandley intersection project is funded with DIL fees.

Project Justification
The Bandley Drive Signal Upgrades will significantly enhance pedestrian safety and pedestrian connectivity across Stevens Creek Blvd within the Crossroads district by reducing pedestrian-vehicle conflicts. Vehicle safety will also be increased for vehicles exiting the Crossroads driveway and Bandley Drive. Improving vehicular, pedestria n and bicyclist safety is a primary concern. This project will significantly enhance pedestrian and vehicular safety.

Prioritization Total Points: 245

Health & Safety 3 This project promotes safer pedestrian, bicyclist and vehicular crossings at the intersection.

Regulatory / Legal Mandate 1 Traffic/Roadway regulations will be respected.

Asset Condition & Infrastructure
Risk
1 The signals are in need of improvements

Climate Resilience & Sustainability 1 Promoting pedestrian and bicycle transportation encourages climate resilience and sustainability.

Strategic Alignment 3 Work to improve SCB is the number one priority of the 2016 Bicycle and Pedestrian Transportation Plans.

Community Benefit & Equity 3 A safer intersection will benefit the multitude of visitors to the retail outlets in that area.

Financial Leverage & Cost
Effectiveness
4 Developer In-Lieu funding is in place.

Project Readiness 3 Design documentation is 95% complete.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
Bandley Drive Signal Upgrades page 2 Operating Budget Impacts Annual Estimated Impact: $ 0
Negligible anticipated impact to the operating budget.

Funding Information
External grant funding has been secured for Phase 2A. Additional external funding may be available for Phase 2B. The remainder of the City funds allocated for Phase 2 will be applied to Phase 2B once Phase 2A is complete. The scope of work for the Bandley intersection will be included in the Phase 2B scope of work for efficiency.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 0
Other External Sources $ 25,658

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
420-99-036, ST 053, ST 059 $ 7,880 TBD TBD

Projected Schedule/5-year Plan Information
Design and Documentation of Phase 2B and the Bandley project is 95% complete. The project will be permitted, bid, and constructed once Phase 2A is complete.

Item/Phase Timeline for Completion Notes
Project Initiation, Consultant Procurement Completed
Design and Documentation 95% complete
Bid, Contract Award and Execution TBD 3 – 6 months in duration Construction TBD
Post-Construction/Close-out TBD

Project
Location

Bandley Drive and SCB

Project
Contact

Susan Michael, CIP
Manager
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
School Walk Audit Implementation page 1 Tier 3 Improvements
Total Funding $ 1,472,517

City Funding $ 250,654
External Funding $ 1,221,863 (Apple)
Remaining Funds (Feb 2026) $ 1,016,823
Funding Source Dev., General Fund
Approved [Master] Plan BTP, PTP
Project Category Transportation
Project Type Design & Construction
FY Initiated FY 18-19

Project Description
This project will construct infrastructure-related improvements around schools that were identified as pa rt of the comprehensive School Walk Audit study. Traffic improvements will improve walkability and safety around 14 Cupertino schools: Lincoln ES, Monta Vista HS, Lawson MS, Sedgwick ES, Hyde MS, Garden Gate ES, Homestead HS, Collins ES, Faria ES, Stevens Creek ES, Regnart ES, Cupertino HS, Kennedy MS, Eaton E S.

Project Justification
A walk audit is an assessment of travel behaviors for drivers, bicyclists, pedestrians (both pa rents and students), developed by observing a school pick up or drop-off period on and around school grounds. Walk audits provide insight into the specific barriers to walking and biking at each school. The assessment team included Alta Planning + Design staff; City of Cupertino staff, nearby residents, and concerned parents. Af ter the audit period completed, audit participants returned to discuss and document their findings on a large -scale school area map. Based on observations and input provided by school staff, audit participants, and others, the project team developed walk audit reports. The walk audit items identify barriers to walking and biking to school and recommend ways to i mprove safety and traffic conditions around local schools. Health and safety are the first priority.

Prioritization Total Points: 395

Health & Safety 5 The report identifies barriers to walking and biking to school and recommends ways to improve safety and traffic conditions.

Regulatory / Legal Mandate 3 This project creates regulated traffic conditions, abiding by mandated traffic codes to improve safety at schools.

Asset Condition & Infrastructure
Risk
3 The report identifies many road and sidewalk conditions that can be improved.

Climate Resilience & Sustainability 1 Increasing student safety is the sustainable approach to traffic conditions.

Strategic Alignment 3 The improvements align with the Bike and Pedestrian Transportation Plans.

Community Benefit & Equity 5 Safer walking routes directly benefits many aspects of the community.

Financial Leverage & Cost
Effectiveness
5 The project is funded primarily through external sources.

Project Readiness 4 The report identifies the scope of work for the project.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
School Walk Audit Implementation page 2 Operating Budget Impacts Annual Estimated Impact: $ 0
No anticipated impact to the operating budget.

Funding Information
In 2019, Apple, Inc. granted funds for the cost of implementing all the walk audit improvements in the City's ROW.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 0
Other External Sources $ 1,221,863

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
420-99-069, ST 034 $ 455,694 $ 400,000

Projected Schedule/5-year Plan Information
Tier 1 and 2 items are almost complete, and three Tier 3 items are being initiated: Hyannisport Drive at Fort Baker Drive intersection reconstruction and Tantau Ave/Barnhart Ave sidewalk widening. It’s estimated that design and construction of the project will have a 3-year duration.

Item/Phase Timeline for Completion Notes
Project Initiation, Consultant Procurement Completed
Design and Documentation Completed
Environmental/Regulatory Permitting N.A.

Bid, Contract Award and Execution July - Nov 2026
Construction December 2026
Post-Construction/Close-out January 2027

Project Location

Various.

Project Contact
Susan Michael, CIP Manager
[email protected]

FY25-26 CIP proposal and 5-year Plan Council Meetin g 4/02/2025 Page 30 of 34

INSERT SECTION PAGE (GRAPHICS!)

City of Cupertino

SUSTAINABILITY AND ENERGY PROJECTS
CIP FY26-27  5-YEAR PLAN

PROJECT NARRATIVES
PAGE 1
CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
EVCS expansion - Service Center page 1

Total Funding $ 785,230

City Funding $ 560,000
External Funding $ 225,230 (SVCE)
Remaining Funds (Feb 2026) $ 775,585
Funding Source CR/GF, Grant
Approved [Master] Plan General Plan
Project Category Sustainability & Energy
Project Type Design and Construction
FY Initiated FY 24-25

Project Description
The construction of electric vehicle charging station (EVCS) infrastructure at the Service Center is n eeded for the electrification of the City’s fleet in order to meet the Advanced Clean Fleet (ACF) regulation by Ca lifornia Air Resources Board (CARB). The scope of work follows the Silicon Valley Clean Energy (SVCE) report which identified the charging infrastructure needs to meet ACF regulation.

Project Justification
The SVCE systematic assessment of City fleet vehicles had the primary goals of identifying vehicle electrificat ion opportunities, establishing an electrification timeline based on vehicle replacements and the City’s climate action goals and regulatory compliance, and determining the costs and emissions benefits of fleet electrification. State regulations require the conversion of City fleet vehicles to electric vehicles, and the EVCS infrastructure is needed to address operations in response to those requirements.

Prioritization Total Points: 300

Health & Safety 1 The project improves operational safety by providing properly designed and code-compliant electric vehicle charging
infrastructure for the City’s fleet operations.

Regulatory / Legal Mandate 5 The project is necessary for compliance with the CA Air Resources Board (CARB) Advanced Clean Fleets (ACF) regs.

Asset Condition & Infrastructure
Risk
1 Without infrastructure upgrades, the City faces operational limitations, increased risk of inadequate charging capacity, and potential service disruptions as additional electric fleet vehicles are deployed

Climate Resilience & Sustainability 4 The project supports the City’s sustainability and CAP goals by enabling the transition from gasoline-powered to zero-emission electric vehicles.

Strategic Alignment 5 The project aligns with the City’s strategic priorities related to sustainability, operational efficiency, and regulatory compliance.

Community Benefit & Equity 2 Transitioning the City fleet to electric vehicles contributes to improved local air quality and reduced greenhouse gas emissions, providing environmental and public health benefits to the community.

Financial Leverage & Cost
Effectiveness
5 Planning efforts were completed through the SVCE assessment report to identify the most efficient and cost-effective charging infrastructure improvements.

Project Readiness 5 Infrastructure needs and charging requirements have been established for the project, construction is ready to begin.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
EVCS expansion - Service Center page 2

Operating Budget Impacts Annual Estimated Impact: $0
When this improvement is completed, and ongoing maintenance efforts are added to operations, operating costs will increase for the Facilities Division. While minor maintenance and supplies costs are anticipated, it is believed that these costs will be offset by the savings of transitioning from Gas to Electric. Ongoing evaluation of impacts to operations will be evaluated. This project is a response to state mandates regarding fleet vehicles. Th e maintenance of a Level 2 charger is estimated at $500 per station annually, and $3000 per station annually for Level 3 EVCS.

Funding Information
Funding for construction of the infrastructure required for operation of the EVCS. Procurement and installation of units, ongoing operation of the facilities, as well as potential upgrades to electrical service, may req uire additional funding.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 225,230
Other External Sources $ 0

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
420-99-272, ST 069 $ 9,645 $650,000

Projected Schedule/5-year Plan Information
It is currently anticipated that the project can begin construction in the latter half of 2026 .

Item/Phase Timeline for Completion Notes
Project Initiation to Contract Award and
Execution
Completed
Construction Fall 2026 - Spring 2027
Post-Construction/Close-out Spring 2027

Project Location

10555 Mary Avenue
Project Contact
Jimmy Tan, Asst Director of
Public Works
[email protected]

CIP FY26-27 • 5-YEAR PLAN PAGE 1 PROJECT NARRATIVE
Photovoltaic Systems Design & Installation page 1 PV at Sports Center, Community Hall and Quinlan
Total Funding $ 6,300,000
City Funding $ 6,300,000
External Funding $ 0
Remaining Funds (Feb 2026) $ 5,513,958
Funding Source CR/GF
Approved [Master] Plan CAP
Project Category Sustainability & Energy
Project Type Design & Construction
FY Initiated FY 24-25

Project Description
In 2023 PG&E announced a rate decrease for electricity generated by photovoltaic (PV) systems (NEM 3) but provided a window to allow grandfathering the more economically-attractive NEM 2.0 rates if in terconnection applications were successfully submitted and corresponding systems operational by 2026. NEM 2.0 Interconnection Applications were successfully submitted to PG&E for five Cupertino facilities: Blackberry Farm, Civic Center, Library, Quinlan Community Center & Senior Center, and Sports Center. This project aims to design and buil d PV systems at three locations. Council reviewed and approved the conceptual designs for Community Hall, Quinlan Community Center and Sports Center in December 2024 before awarding the Design Build contract in February 2025.

Project Justification
The City must connect the proposed photovoltaic systems to the grid by 4/15/2026 to take advan tage of the NEM 2.0 applications for Community Hall and Sports Center, which provides 75 – 80% greater compensation than NEM 3 rates for electricity that is fed back into the electrical system. The savings in utility costs are projected to be $290K annually, and $13.4M over a 30yr lifespan. Installation of the PV systems is projected to provide substantial savings on utility costs, going forward. The use of cleaner energy sources is a CAP goal.

Prioritization Total Points: 325

Health & Safety 3 Passive energy generation is a safe asset for the City.

Regulatory / Legal Mandate 3 Some accessibility requirements, EVCS, and other building codes apply to these projects.

Asset Condition & Infrastructure
Risk
0 The project was not generated by deficiencies in infrastructure.

Climate Resilience & Sustainability 5 Green energy generation is aligned with the CAP goals.

Strategic Alignment 5 Green energy generation is aligned with the CAP goals

Community Benefit & Equity 3 Cost savings on energy costs will benefit the community.

Financial Leverage & Cost
Effectiveness
5 The ROI of this project is less than ten years.

Project Readiness 5 Two of the three sites are completed. The third site is under construction.

CIP FY26-27 • 5-YEAR PLAN PAGE 2 PROJECT NARRATIVE
Photovoltaic Systems Design & Installation page 2 Operating Budget Impacts Annual Estimated Impact: -$ 300,000 When this improvement is completed, and ongoing maintenance efforts are added to operations, operating costs will increase for the Facilities Division. While minor maintenance and supplies costs are anticipated, these costs will be offset by the savings electric savings. Anticipate operations and maintenance costs are estima ted at $15,000 annually, while electricity savings are anticipated at approximately $315,000 annually.

Funding Information
The proposed budget will enable design and construction of the systems. Inflation Reduction Act credits projected for this project are approximately $1.4M. Staff will also pursue other grant funding opportun ities.

External Funding
2026-27 2027-28 2028-29 2029-30 2030-31
Grants $ 0
Rebates ~$ 1,400,000

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) 2025-26
Actual
2026-27
Projected
2027-28
Projected
2028-29
Projected
2029-30
Projected
2030-31
Projected
420-99-274, FVAR 004 $ 786,042 $4,500,000

Projected Schedule/5-year Plan Information
Conceptual Design development and cost analysis completed in 2024. Design-Build: March 2025 to October 2026.

Item/Phase Timeline for Completion Notes
Project Initiation to, Contract Award &
Execution
Completed
Construction October 2026 Sports Center & Community Hall Complete.

Quinlan/Alves Parking area is underway.

Post-Construction/Close-out Nov – Dec 2026

Project
Location

Sports Center,
Community Hall and
Quinlan Community
Center
Project
Contact

Susan Michael, CIP
Manager
[email protected]

FY25-26 CIP proposal and 5-year Plan Council Meetin g 4/02/2025 Page 30 of 34

INSERT SECTION PAGE (GRAPHICS!)

C. COMPLETED PROJECTS
City of Cupertino
CIP FY26-27  5-YEAR PLAN

PROJECT NARRATIVES
PAGE 1
CIP FY26-27 • 5-YEAR PLAN PROJECT NARRATIVES
All Inclusive Playground – Jollyman
And Adult-Assistive Bathroom facility
Total Funding $ 4,891,347
City Funding $ 2,080,652
External Funding (SCC AIPG) $ 1,448,201
External Funding (CA P&R) $ 1,000,000
External Funding (donation) $ 25,000
External Funding (Art In-Lieu) $ 338,146
Remaining Funds (Feb 2025) $ 381,035
Funding Source, Approved Plan GF, Grant, PRSMP, DIL
Project Category Parks, Facilities
Project Type Design and Construction
Location Jollyman Park
Origin of Request Public Works, Parks
Budget Unit 420-99-051, PVAR 007
Initiated FY18-19

Project Description

Project Justification

Projected Schedule/5-year Plan information

Funding Information

Operating Budget Impacts

Design and construct an all-inclusive playground at Jollyman Park, and a new adult-assistive bathroom facility adjacent to the All-Inclusive Play Area.

Community input secured during the Parks and Recreation System Master Plan process favors having an All-Inclusive play area in Cupertino. The new "All-Inclusive Playground" (AIPG) project is intended to serve the broad needs of the [inclusive] community The added bathroom facility can serve all ages who require mo bility assistance and will vastly improve the usability of the new play area.

Anticipated construction completion date is June 2025.

Anticipated to be a slight impact to the Operating Budget due to the specialized nature of the play equipment and the addition of a bathroom facility. By accepting the grant, the City agreed to construct a nd maintain the playground for 20 years.

Santa Clara County All-inclusive Playground funding grant was secured in 2019 for $ 1,448,201. This requires $2,201,799 in matching funds and required fund-raising of $1M. CA Parks and Recreation department awarded a second grant in the amount of $1,000,000 as a Specified Grant program, which met the fund-raising requirement.

PG&E also donated $25,000. Art In-Lieu fees were used to design, procure, and install the “kaleidoscope” art feature, with a budget of $338,146. The Adult-Assistive Bathroom Facility scope was fun ded by Council in FY22-23 ($850K) and added to this project funding.

CIP FY26-27 • 5-YEAR PLAN PROJECT NARRATIVES
City Bridge Maintenance Repairs
Completed – FY 25-26
Total Funding $ 2,186,173
City Funding $ 2,186,173
External Funding $ 1,893,195
Remaining Funds (Feb 2026) $ 213,559
Funding Source, Approved Plan TF, GP
Project Category Streets and Infrastructure
Project Type Design and Construction
Location Homestead/ McClellan @ Stevens
Ck., Stevens Creek/ Vallco/ Miller/
Tantau @ Calabazas Ck.

Origin of Request Public Works
Budget Unit 270-90-960, ST 002
Initiated FY15-16

Project Description

Project Justification

Projected Schedule/5-year Plan information

Funding Information

Operating Budget Impacts

Design and construct 6 bridges' repairs as recommended in the FHWA’s Bridge Preventive Maintenance Program reports along with additional improvements to prolong the useful life of the bridges.

The City of Cupertino owns and maintains a total of eight vehicular bridges. Caltrans inspects these bridges a nd prepares a biennial report detailing the recommended repairs. Six of the eight bridges require rehabili tation; SCB over Stevens Creek has issues not covered by maintenance. The rehabilitation includes the required repairs as recommended in the Caltrans Bridge Report as well as additional work to prolong the life and use of the bridges.

Approximately 88% of the project costs are eligible for Federal reimbursement through FHWA’s Bridge Preventive Maintenance Program (BPMP), which is administered by Caltrans.

Construction is anticipated to be complete in April 2025.

There are no anticipated impacts to the Operating Budget.

The Federal Highway Administration (FHWA) grant funding begun as $571,151 and was increased since FY15-16 to be a total of $1,893,195. This grant will be a reimbursement and requires $245,28 4 in matching funds.

CIP FY26-27 • 5-YEAR PLAN PROJECT NARRATIVES

City Lighting LED Improvements
Updates to meet Dark Sky requirements (Completed)
Total Funding $ 1,350,000

City Funding $ 1,350,000
External Funding $ 125,790
Remaining Funds (Feb 2026) $ 403,087
Funding Source, Approved Plan GF, GP
Project Category Streets and Infrastructure
Project Type Feasibility
Location Various
Origin of Request Public Works
Budget Unit 420-99-258, ST 052
Initiated FY21-22
Project Description

Project Justification

Prioritization

Projected Schedule

Operating Budget Impacts

Develop a strategy to transition the City's streetlight infrastructure, and other City operated lights, from induction to LED fixtures to meet the “Dark Sky” requirements and reduce light pollution. Assess the costs, benefits, and opportunities of the proposed improvements.

In March 2021 the City ratified the "Dark Sky" night lighting requirements for private development. As City street lighting and other facility lighting may create unintended light pollution, and in some cases is nearing the end of its useful life, this study will evaluate lighting needs and compliance with dark sky requirements for the City' s nearly 3000 streetlights, various path lighting and exterior facility lighting.

Procurement is underway. The construction schedule is listed to be completed by December 2025.

There are no anticipated additional impacts to the Operating Budget by this work.

This project brings the City streetlights into compliance with the Dary Sky codes and reduces energy costs. It is a highly prioritized project for these reasons and because it is nearing completion.

Capital Improvement Programs Fiscal Year 2026 – 2027
and 5-Year Plan

Glossary

ADA (Americans with Disabilities Act): Federal legislation requiring public facilities and programs to be accessible to individuals with disabilities.

Appropriation : An authorized allocation of funds for a specific purpose or project.

CEQA (California Environmental Quality Act): State law requiring environmental review of projects that may impact the environment.

Capital Improvement Fund: A fund used for the acquisition, construction, or renovation of major capital assets.

Capital Improvement Program (CIP): A multi-year plan that identifies, prioritizes, and funds capital projects such as infrastructure, facilities, and park improvements.

Capital Reserve : A designated reserve within the General Fund used to fund capital projects and reduce reliance on debt.

Completed Project : A project that has been substantially completed and financially closed.

Contingency : Budgeted funds set aside to cover unforeseen costs or changes in project scope.

Debt Financing : Borrowing used to fund capital projects when pay-as-you-go funding is not practical.

Defunded Project : A project that has been removed from the CIP and no longer receives funding.

Enterprise Fund : A fund used to account for activities financed primarily through user fees.

Facilities Condition Assessment (FCA): A report evaluating the condition of City facilities and identifying needed repairs and upgrades.

Fiscal Year (FY): The City’s twelve-month financial period, running from July 1 through June 30.

FY 26–27 CIP Book Page 2
Five-Year Plan : A planning horizon that includes the current fiscal year plus four additional years.

Fund Balance : The difference between assets and liabilities in a governmental fund.

Funding Source : The origin of funds used to pay for a project, such as grants, reserves, or special revenues.

GAAP (Generally Accepted Accounting Principles): Standard accounting principles used in preparing governmental financial documents.

GIS (Geographic Information System) : Software used to map and analyze spatial information, including project locations.

General Fund : The City’s primary operating fund used to account for most governmental activities.

Grant Funding : Financial assistance from federal, state, regional, or private sources.

Infrastructure : Physical assets such as roads, bridges, storm drains, buildings, and utilities.

Life-Cycle Cost : The total cost of owning, operating, maintaining, and eventually replacing an asset.

Operating and Maintenance (O&M) Costs : Ongoing expenses required to operate and maintain completed projects.

Pay-As-You-Go Financing : Funding capital projects using current revenues and available fund balances rather than debt.

Project Budget : The total estimated cost required to complete a project.

Project Manager : The department or individual responsible for delivering a project.

Project Narrative : A summary describing the purpose, scope, status, schedule, and funding of a project.

Restricted Funds : Resources that may only be used for legally specified purposes.

Soft Costs : Project costs other than direct construction, such as design, permitting, and project management.

Special Revenue Fund : A fund used to account for revenues legally restricted to specific purposes.

FY 26–27 CIP Book Page 3

Sustainability : Practices and projects that support environmental stewardship and long- term resilience.

Transportation Impact Fee : A development fee used to fund transportation improvements needed to serve growth.

Unfunded Project : A proposed project that has not yet received funding.

Useful Life : The expected period during which an asset provides service.

FY 26–27 CIP Book Page 4

Capital Improvement Programs Fiscal Year 2026 – 2027
and 5-Year Plan

Index

ADA Improvements ................................................ 61, 71 Appropriations ................................................ 20–21 Background Information ................................................ 5 Capital Improvement Fund ................................................ 10 Capital Improvement Program (CIP) ................................................ 4–11, 53–91 Capital Reserve ................................................ 4–5, 10, 15 Completed Projects ................................................ 51, 92–95 Council Priorities ................................................ 6 Defunded Projects ................................................ 96–98 Enterprise Funds ................................................ 10–11 Facilities Condition Assessment (FCA) ................................................ 20–22 Facilities Projects ................................................ 19–27, 60–65 Fiscal Policies ................................................ 12–17 Five-Year Plan ................................................ 8–9, 56 Funding Sources ................................................ 10–11 General Fund ................................................ 4, 10 Glossary ................................................ To be inserted Grant Funding ................................................ 8, 10, 20–21 Health and Safety Priorities ................................................ 5–7 Index ................................................ To be inserted Infrastructure Projects ................................................ 35–40, 72–79 Introduction ................................................ 4–11 Master Plan Priorities ................................................ 6 Operating and Maintenance Costs ................................................ 12 Parks Projects ................................................ 28–34, 66–71 Project Narratives ................................................ 59–91 Project Prioritization ................................................ 5–7 Special Revenue Funds ................................................ 10 Status Report ................................................ 18–50 Streets and Infrastructure ................................................ 35–40, 72–79 Sustainability Projects ................................................ 47–50, 89–91 Table of Contents ................................................ 2–3 Transportation Projects ................................................ 41–46, 80–88 Unfunded Projects ................................................ 22–25 Notes for Future Updates
• Update all page references after the final docume nt is paginated.

FY 26–27 CIP Book Page 5
• Add or remove glossary terms based on changes to project categories, funding sources, and terminology.
• Review the index to ensure all major sections and recurring project references are included.
• Consider adding cross-references for commonly use d acronyms and alternate terms.

Appendix A – Fiscal Policies Page 3 of 6
Appendix A – Fiscal Policies

Capital Improvement Programs Policy

PURPOSE
To establish a Capital Improvement Programs (CIP) Policy to assist in future budget projections.

SCOPE
All anticipated CIP projects for the current fiscal year plus four additional fiscal years.

POLICY
The City will prepare an annual CIP for the current fiscal year that includes a projection of anticipated programming and funding for a total of five fiscal years.

Projects included in the CIP will have information on the need for the project (project justification), description and scope of work, total cost estimates, future operating and maintenance impacts, and funding sources.

The project justification will incorporate information on the factors that a ffect the prioritization of the project. The factors to be considered include (but are not limited to) the Health & Safety of the community, continuation of ongoing work, Community requests, General Plan and Master Plans' directives, sta ffing and operational demands, sustainability and resiliency, and internal and external funding viability.

Changes to the CIP such as the addition of new projects, significant changes in scope and costs of a project or reprioritization of projects will require City Manager and City Council approval.

The City will maintain its physical assets at a level adequate to protect the City’s capital investment and to minimize future operating maintenance and replacement costs. The City recognizes that deferred maintenance increases future capital costs, thus placing a burden on future residents.

Therefore, the budget will provide for adequate maintenance and the orderly replacement of capital facilities from current revenues when possible.

The City will determine the least costly funding method for its capital projects and will obtain grants, contributions and low cost state or federal loans whenever possible.

The City will utilize “pay-as-you-go” funding for capital improvement expenditures considered recurring, operating or maintenance in nature. The City may also utilize “pay-as-you-go” funding

Appendix A – Fiscal Policies Page 4 of 6
for capital improvements when current revenues and adequate fund balances are available or when issuing debt would adversely affect the City’s credit rating.

The City will consider the use of debt financing for capital projects under the following circumstances:
• When the project’s useful life will exceed the terms of the financing • When resources are deemed sufficient and reliable to service the long-term debt • When market conditions present favorable interest rates for City financing • When the issuance of debt will not adversely affect the City’s credit rating and debt coverage ratios.

Revised April 2023

Appendix A – Fiscal Policies Page 5 of 6
Committed, Unassigned Fund Balance, and Use of One-Time Funds Policy

PURPOSE
To establish assigned and unassigned fund balance and one-time use policies.

SCOPE
The General Fund and Capital Funds.

POLICY
To maintain sufficient committed and unassigned fund balance (General Fund only) in each fund for the ability to meet the following economic uncertainties:

Economic Uncertainty – $21,329,593 and represents two months of General Fund (GF) expenditures excluding transfers out plus a two year drop in total general fund revenue of 13% or approximately

1.5 months, excluding the use of reserves. Transfers out are primarily used to fund Capital Projects and do not represent on-going expenditures. This assignment will change from year to year based on budgeted general fund expenditures and revenues.
• Mitigate short-term economic downturns and volatility in revenues (2 years or less) • Sustain city services in the event of an emergency
• Meet requirements for debt reserves
• Meet operating cash flow requirements as a result of delay in the receipt of taxes, grant proceeds and other operating revenues

Sales Tax Repayment Reserve – $77,554,500 and represents the funds committed for potential sales tax repayments. The result of the California Department of Tax and Fee Administration (CDTFA) audit of a City taxpayer is expected to have significant financial implications for the City’s operations. To prepare for a potential adverse CDTFA decision and the uncertain outcome of the anticipated legal challenge, the City established a General Fund Sales Tax Repayment Reserve. The purpose of this reserve is to set aside funds for potential sales tax repayments to the CDTFA. An initial allocation of $56.5 million corresponds to sales tax revenue received between April 2021 and June 2023 that the City may need to repay to the CDTFA. All or part of the funds will be transferred to General Fund Unassigned if the City’s efforts to contest CDTFA’s decision are ultimately successful, in whole or in part.

This reserve can be augmented when additional disputed sales tax revenue is received.

PERS – $19,088,859 and represents the funds restricted for the City's pension obligations. In response to the increasing retirement costs based on actuarial forecasts, the City created a secondary pension trust to help stabilize the impact of pension cost volatility on the City's operating budget. To fund this secondary trust, the City made an initial contribution. After that, the annual contributions are determined based on the difference between CalPERS' current discount rate and a more conservative rate determined by the City. This difference will then be transferred to the pension trust and used exclusively for the benefit of members in the plan.

Appendix A – Fiscal Policies Page 6 of 6

The primary goal of establishing this secondary trust is to ensure that the City can continue to provide its employees with the retirement benefits they have earned while maintaining fiscal responsibility. By using a more conservative rate for calculating contributions, the City can better anticipate and manage pension costs and mitigate potential negative impacts on the City's budget.

Funds in this trust are technically “restricted” under Governmental Accounting Standards Board (GASB) Statement No. 54 in that the funds are legally restricted to be used for retirement costs; however, the timing for which these funds may be used is only at the discretion of City Council.

Sustainability Reserve – Cupertino’s Sustainability Division oversees the City’s Climate Action Plan (CAP), which defines strategies to reduce greenhouse gas emissions, and provides residents, businesses and schools with programs and services focused on energy efficiency, renewable energy, water conservation, alternative transportation and other sustainable actions. The City receives rebates for projects that successfully meet the eligibility requirements such as energy or water efficiency. If the rebates were not initially budgeted, they are categorized as committed fund balance in the General Fund. The purpose of this reserve is to help support future sustainability projects/programs.

Unassigned – $500,000 and represents 1% of the total general fund operating budget. This assignment may change from year to year based on budgeted general fund expenditures. • Absorb unanticipated operating needs that arise during the fiscal year that were not anticipated during the budget process
• Absorb unexpected claims or litigation settlements

Capital Improvement – $5,000,000 and represents average dollars spent for capital projects in the last three fiscal years. This assignment may change from year to year based on actuals dollars spent on capital projects and anticipated future capital project needs. • Meet future capital project needs so as to minimize future debt obligations

The City shall not use fund balances/reserves in lieu of revenues to pay for ongoing expenses except as specifically provided in the City’s reserve policy.

The chart below summarizes reserve policy levels as described above:

Appendix A – Fiscal Policies Page 7 of 6

1 As of June 30, 2023
2 Rounded to the nearest hundred thousand
3 Excludes Transfers Out
4 Excludes the use of reserves

Changes to Committed Fund Balance – All reserves listed in this policy, with the exception of the PERS restricted reserve, are classified as Committed Fund Balance under GASB Statement No. 54.

Committed fund balance is comprised of amounts that can be used only for the specific purposes determined by a formal action of the government’s highest level of decision-making authority.

Changes to committed fund balances must be approved by City Council. This policy will be reviewed annually as part of the budget process.

Replenishment process – Should the City need to utilize any of the committed fund balances listed in this policy, a recommendation will be brought to City Council for approval and a plan to replenish the committed balance will be developed in conjunction with its use.

Appendix A – Fiscal Policies Page 8 of 6
Excess – Funding of these reserves will come generally from one-time revenues, annual net income, and transfers from other reserves that exceed policy levels. They will be funded in the following priority order with any remaining funds to be placed in the Capital Reserve:
1) Economic Uncertainty Reserve
2) Sales Tax Repayment Reserve
3) PERS
4) Sustainability Reserve
5) Unassigned

Revised May 1, 2024

Appendix B - Fund Types for CIP Page 1 of 3

Appendix B – Fund Types for CIP

Tax Supported Funds
Capital Improvement Fund (General Fund) - 420
The General Fund is the primary operating fund for governmental services. Within the General Fund, the Capital Improvement Fund is utilized for the acquisition or construction of major capital facilities. Funds in this account are previously approved by Council and dedicated to CIP projects.

Typically, these funds roll-over until the project[s] are completed or defunded. A copy of the Capital Improvement Policy is attached at the end of this letter.

Capital Reserve (General Fund) - 429
The City’s Capital Reserve is intended to be used for capital improvement projects in the City.

Funding for this reserve is governed by the City’s Assigned and Unassigned Fund Balance and Use of One Time Funds Policy that can be found in the Financial Policies and Schedules section of the City’s proposed and final budget documents. Per that policy, any unassigned fund balance in the General Fund at year-end over $500,000 will be transferred to the Capital Reserve.

Stevens Creek Corridor Park Capital Projects - 427
This fund pays for the design and construction of the Stevens Creek Corridor Park projects.

Special Revenue Funds
Storm Drain Improvement Fund - 210
This fund pays for the construction and maintenance of storm drain facilities. Revenues are collected as a line item on the city’s behalf via the County property tax billing.

Park Dedication Fund - 280
This fund pays for the activity granted by the business and professions code of the State of California in accordance with the open space and conservation element of the City’s General Plan.

Revenues are collected as a development “in-lieu” fee with new residential development, excluding exempted ADU’s per state regulation and designated Below Market Rate Housing (BMR).

Transportation Fund - 270
This fund pays for expenditures related to the maintenance and construction of City streets.

Revenues are collected from Vehicle License Fees, Gas Tax, Cal Recycle State Grant funding (for rubberized pavement) as well as SB1 dollars.

Transportation Impact Fee - 271
This fund pays for the cost of transportation improvements required to serve new development.

Impact fees are one-time charges on new development, additions to existing structures, change in use, or similar construction activity that requires a building permit and results in additional peak

Appendix B - Fund Types for CIP Page 2 of 3

hour vehicle trips, and is collected and used by the City to cover the cost of capital facilities and infrastructure that are required to serve new growth.

Housing & Community Development -260
This fund pays for the Federal Housing and Community Development Grant Program activities administered by the City. This fund also pays for activities related to the Below Market Rate Housing Program. Revenues are collected as a development “in-lieu” fee with new residential development, excluding exempted ADU’s per state regulation and designated Below Market Rate Housing (BMR).

Enterprise Funds
Blackberry Farm Golf Course Fund - 560
This fund pays for operating costs related to the Blackberry Farm Golf Course. Revenues are collected as fees from users of the golf course.

Sports Center Fund - 570
This fund pays for operating costs related to the Sports Center. Revenues are collected as fees from users of the Sports Center.

Recreation Programs Fund - 580
This fund pays for operating costs related to the City’s community centers and park facilities.

Revenues are collected as fees for recreation programs at the City’s community centers and park facilities.

Table: CIP Funding Sources and Organizational Priorities Funding
Source Typical Eligible Uses Restrictions /
Considerations
Organizational Priorities
Best Supported
General Fund
(100, 420)
Core infrastructure
repairs, urgent facility
needs, safety-related
capital work, and
projects without an
alternative dedicated
funding source.

Most flexible source,
but also subject to
competing operating
demands and overall
fiscal conditions.

Public health and safety,
essential services,
emergency preparedness,
and fiscal resilience.

Capital Reserve
(429)

Major rehabilitation,
replacement of aging
assets, large civic facility
projects, and high-
priority one-time capital
needs.

Should be used
strategically for non-
recurring needs and
preserved to support
long-term
infrastructure
obligations.

Asset preservation,
infrastructure reliability,
civic facility stewardship,
and long-range capital
planning.

Appendix B - Fund Types for CIP Page 3 of 3

Developer Fees
/ In-Lieu
Contributions

Growth-related
transportation, park,
and infrastructure
improvements that
offset development
impacts.

Use is limited by legal
nexus requirements,
fee program rules, and
availability of
collected revenue.

Growth management,
infrastructure capacity,
transportation
improvements, and parks
asset support.

Transportation
Special
Revenues (270,
271)

Pavement rehabilitation,
roadway maintenance,
traffic safety projects,
bicycle and pedestrian
improvements, and
related mobility
investments.

Restricted to
transportation
purposes and may
depend on formula
allocations, program
rules, and
reimbursement
timing.

Mobility, traffic safety,
multimodal access, and
preservation of
transportation assets.

Grant Funding
Eligible transportation,
sustainability, safety,
resilience, and facility
projects that meet
outside program
requirements.

Competitive and often
time-limited; may
require matching
funds, reporting, and
delivery schedules.

Cost effectiveness,
acceleration of priority
projects, sustainability,
resilience, and external
funding leverage.

Dedicated /
Restricted
Funds (210,
260, 280, 427,
560, 570, 580)

Special-purpose capital
improvements tied to
the specific purpose of
the fund or revenue
source.

Must be used strictly
in accordance with
legal, policy, or voter-
imposed restrictions.

Stewardship of restricted
resources, compliance, and
targeted delivery of eligible
infrastructure
improvements.

Future Use
Fund (Long-
Range
Planning)

Potential future
investment in major
strategic civic facility
needs or other Council-
directed long-term
capital priorities.

Typically reserved for
significant one-time
priorities and subject
to future policy
direction and fund
availability.

Long-term civic
infrastructure, strategic
investment, and future
facility replacement or
modernization needs.

Note: Actual funding assignments vary by project scope, legal eligibility, available fund balance, grant timing, and City Council authorization as part of the annual CIP and budget adoption process.

Appendix C - CIP Prioritization process Page 1 of 9
Appendix C

CIP Prioritization
Process
Attachments:

Appendix A - Scoring Descriptions
Appendix B – Project Information and Scoring
Worksheet
Appendix C – Prioritization Matrix Template
Effective Date : March 3, 2026 Responsible Department: Public Works Related Policies & Notes: CIP Policy Revised: 3/01/26

Purpose
This Capital Improvement Program (CIP) prioritizati on process is designed to help the City of Cupertino transparently, consistently, and defensibly rank capital projects across departments. The framework balances safety, regulatory compliance, fiscal responsibility, community benefit, and City Council strategic priorities, while remaining flexible enough to adapt to changing conditions.

Guiding Principles
All CIP prioritization should be:
• Transparent – Clear criteria and scoring that can be explained to decision makers and the public
• Equitable – Considers community-wide benefit and underserved populations • Data Driven – Based on measurable impacts where possible • Strategically Aligned – Supports adopted plans, policies, and Council goals • Financially Responsible – Accounts for lifecycle cost and funding availability

Step-by-Step Prioritization Process
Step 1: Project Intake & Eligibility Screening
Departments submit proposed CIP projects using a standardized form. Projects must:
• Be a capital asset or extend the useful life of an existing asset • Meet minimum cost and useful-life thresholds
• Be consistent with adopted plans (General Plan, Master Plans, Climate Action Plan, etc.) Projects that are strictly operational, duplicative, or infeasible are screened out.

Step 2: Baseline Classification – Information gathering (Non-Scored) Each project is tagged for reporting and tie-breaking purposes:
• Asset/Project Type (Transportation, Parks, Facilities, etc.) • Project Category (New, Rehabilitation, Replacement, Expansion) • Mandated vs. Discretionary
• Geographic Location / Service Area

Appendix C - CIP Prioritization process Page 2 of 9
Step 3: Scoring Using the CIP Prioritization Matrix
Projects are scored using the matrix below and the Worksheet in Appendix B. Each criterion is scored on a 0–5 scale and multiplied by its assigned weight.

Step 4: Scoring Review & Calibration
• Scores are initially assigned by staff subject-matter experts • Cross-departmental review ensures consistency
• Outliers or tied scores are reviewed and adjusted if justified

Step 5: Draft CIP Ranking & Financial Constraint
Projects are ranked by total score and then evaluated against:
• Available funding by fund type
• Debt capacity and cash flow
• Staffing and delivery capacity
Lower-ranked projects may advance if they are fully grant-funded or time-sensitive.

Step 6: Policy Review & Council Consideration
City Council may:
• Adjust rankings based on policy direction
• Group projects into tiers (Tier 1: Fund Now, Tier 2: Fund if Available, Tier 3: Unfunded) • Direct staff to return with alternatives or phasing options Any deviations from the scoring results should be documented for transparency.

Step 7: Annual Update & Continuous Improvement
• Scores are refreshed annually as conditions, costs, or regulations change • Completed or cancelled projects are removed
• Criteria and weights are reviewed every 2–3 years. Projects scoring under 250 will be removed in the following year from active consideration.

CIP Prioritization Matrix
This adjusted weighting reflects Cupertino priorities including climate resilience, safety, and fiscal responsibility, while preserving core safety and compliance requirements.

Table 1: CIP Prioritization Matrix Scoring Guidance
Category Weight Description Scoring Guidance
(0–5)

1. Health & Safety 30%
Improves public safety,
emergency response, and safety
for all transportation users
0 = No safety impact;
5 = Critical safety risk
if not addressed

2. Regulatory / Legal
Mandate 15%
Required to meet federal, state,
or local regulations, permits, or
legal agreements
0 = Not required; 5 =
Legally mandated
with deadlines or
penalties
Appendix C - CIP Prioritization process Page 3 of 9

3. Asset Condition &
Infrastructure Risk 15%
Addresses failing or near-end-
of-life physical or digital
infrastructure
0 = Good condition; 5
= Failure imminent or
service disruption
likely

4. Climate Resilience
& Sustainability 5%
Reduces greenhouse gas
emissions, improves energy
efficiency, or enhances resilience
to heat, drought, flooding, or
power outages
0 = No climate
benefit; 5 =
Significant emissions
reduction and
resilience benefit

5. Strategic Alignment 10%
Advances City Council goals,
General Plan, Climate Action
Plan, or adopted Master Plans
0 = No alignment; 5 =
Explicitly identified
priority project

6. Community Benefit
& Equity 5%
Improves access, quality of life,
or services, including benefits to
underserved populations
0 = Minimal benefit; 5
= Broad and
equitable community
benefit

7. Financial Leverage
& Cost Effectiveness 15%
Maximizes grants, partnerships,
lifecycle savings, or operational
efficiencies
0 = No leverage; 5 =
Majority funded
externally or major
long-term savings

8. Project Readiness &
Deliverability 5%
Level of design, environmental
clearance, and ability to deliver
within the CIP window
0 = Concept only; 5 =
Shovel-ready

Appendix C - CIP Prioritization process Page 4 of 9
Attachment A - Scoring Descriptions

Refer to the descriptions below to ensure consistent scoring. Scores should be evidence-based and documented in the worksheet notes.

1. Health and Safety (Weight: 30)
Focus: Risk to public or staff if the project is delayed. • 0 – No identifiable safety benefit
• 1 – Minor safety improvement; low risk
• 2 – Addresses isolated or infrequent safety concerns
• 3 – Reduces known safety issues; moderate risk exposure • 4 – Addresses serious safety hazards or near-miss history • 5 – Critical safety risk; high likelihood of injury or emergency response failure if not addressed

2. Regulatory / Legal Mandate (Weight: 15)
Focus: Compliance with laws, permits, or binding agreements. • 0 – No regulatory or legal requirement
• 1 – Indirectly supports compliance
• 2 – Anticipated future regulation
• 3 – Required to maintain compliance; no immediate deadline • 4 – Required with a defined deadline or enforcement risk • 5 – Legally mandated with penalties, consent decree, or active enforcement

3. Asset Condition & Infrastructure Risk (Weight: 15)
Focus: Current condition and likelihood of failure.
• 0 – Asset in good condition; no issues
• 1 – Minor wear; routine maintenance sufficient
• 2 – Moderate deterioration
• 3 – Poor condition; increasing maintenance or service impacts • 4 – Near end-of-life; high risk of failure
• 5 – Failure imminent or already occurring

4. Climate Resilience & Sustainability (Weight: 5)
Focus: Climate action, resilience, and long-term environmental performance. • 0 – No climate or sustainability benefit
• 1 – Minor efficiency improvement
• 2 – Small emissions reduction or resilience improvement • 3 – Meaningful sustainability benefit aligned with Climate Action Plan • 4 – Significant emissions reduction and/or resilience improvement • 5 – Transformational climate or resilience benefit; flagship sustainability project

Appendix C - CIP Prioritization process Page 5 of 9

5. Strategic Alignment (Weight: 10)
Focus: Consistency with adopted City priorities and policy direction. • 0 – No alignment with adopted plans or Council goals
• 1 – Indirect or minimal alignment
• 2 – Supports one minor objective or policy
• 3 – Directly advances one major Council goal or adopted plan • 4 – Advances multiple adopted goals, plans, or initiatives • 5 – Explicitly identified or prioritized in adopted plans or formal Council direction

6. Community Benefit & Equity (Weight: 5)
Focus: Breadth and fairness of benefits.
• 0 – Minimal or internal benefit only
• 1 – Limited benefit to a small group
• 2 – Localized benefit to one neighborhood or user group • 3 – Noticeable benefit to a significant portion of the community • 4 – Broad community benefit with improved access or quality of life • 5 – Citywide benefit and/or directly addresses equity or underserved populations

7. Financial Leverage & Cost Effectiveness (Weight: 15) Focus: Maximizing value of City funds.
• 0 – No cost savings or outside funding
• 1 – Minor operational efficiencies
• 2 – Some lifecycle cost avoidance
• 3 – Moderate cost savings or partial grant funding
• 4 – Significant outside funding or strong lifecycle savings • 5 – Majority funded by grants/partners or substantial long-term savings

8. Project Readiness & Deliverability (Weight: 5)
Focus: Ability to deliver within the CIP timeframe.
• 0 – Concept only; no scope definition
• 1 – Preliminary idea; major unknowns
• 2 – Scope defined; early feasibility work
• 3 – Preliminary design or environmental review underway • 4 – Design substantially complete; permits in progress • 5 – Shovel-ready; environmental clearance and design complete

Appendix C - CIP Prioritization process Page 6 of 9
Attachment B – Project Information and Scoring Worksheet

Red text signifies areas that require information from the applicant[s].

PROJECT TITLE page 1

Proposed FY26-27 City Funding $ 110,000
Total Funding $ 970,000
City Funding FY26-27 $ 110,000
External Funding $ 0
Remaining Funds (Feb 202 6) $ 191,990
Funding Source Capital Reserve/GF
Approved [Master] Plan 2015 ADA Transition Plan
Project Category Facilities, Parks, Streets
and Infrastructure,
Transportation, OR
Sustainability
Project Type Design and Construction
Origin of Request Public Works
FY Initiated FY 2015-16

Project Description
Insert project description here (75 words or less).

Project Justification
Insert project justification here. (Include references to Master Plan, General Plan, or other Strategic Plans).

Prioritization (score 1 to 5 in each section below. See prioritization matrix notes for additional information.)

Health & Safety 1 Provide substantiation notes for each category

Regulatory / Legal Mandate 0

Asset Condition & Infrastructure Risk 3

Climate Resilience & Sustainability 1

Strategic Alignment 4

Community Benefit & Equity 3

Financial Leverage & Cost
Effectiveness
3 Project Readiness 3

Appendix C - CIP Prioritization process Page 7 of 9
PROJECT TITLE page 2

Operating Budget Impacts
Describe how this project impacts operational costs including maintenance contracts, processes, materials, and staffing requirements. Provide any one -time and/or annual costs that may be available.

Funding Information
Note any external funding available. If external fu nding is a good possibility in the future, that can also be noted.

External Funding
FY 26-27 FY 27-28 FY 28-29 FY 29-30 FY 30 -31
Grants $ 0
Other External Sources $ 0

Expenditure Schedule/5-year Plan Information
Annual Expenditures (GL#) FY 25-26
Actual
FY 26-27
Projected
FY 27-28
Projected
FY 28-29
Projected
FY 29-30
Projected
FY 30-31
Projected
T.B.D. N.A. $ 100,000 $ 110,000 $ 115,000 $ 120,000 $ 125,000

Projected Schedule/5-year Plan Information
This is an ongoing program, funded annually, to imp rove accessibility at all public facilities throughout the City.

Item/Phase Timeline for Completion Notes
Project Initiation July 2026
Consultant Procurement Ongoing
Planning/Pre -Design Ongoing
Design Ongoing
Permitting & Environmental Clearance Ongoing
Construction Bid Ongoing
Contract Award and Contracting Ongoing
Construction Ongoing
Post -Construction/Close -out Ongoing

Project Location
Address
(Add any information or graphic that you can share )
Project Contact
CIP project manager name

Appendix C - CIP Prioritization process Page 8 of 9

ATTACHMENT C
PRIORITIZATION MATRIX TEMPLATE - FY 26-27 CIP PROJECTS

Appendix C - CIP Prioritization process Page 9 of 9

ATTACHMENT C
PRIORITIZATION MATRIX TEMPLATE - FY 26-27 CIP PROJECTS
(Page 2)

APPENDIX D
FY 26-27 PRIORITIZATION MATRIX - CIP PROJECTS
1 2 3 4 5 6 7 8 Totals
LEGEND :

Facilities
Parks & Rec
Streets & Infrastructure
Transportation
Sustainability & Energy
Health & Safety Regulatory /
Legal Mandate
Asset
Condition &
Infrastructure
Risk
Climate
Resilience &
Sustainability
Strategic
Alignment
Community
Benefit &
Equity
Financial
Leverage &
Cost
Effectiveness
Project
Readiness
Points
Range: 0
to 500
30 15 15 5 10 5 15 5

ACTIVE PROJECTS
City Hall Improvements 5 3 5 4 5 3 3 2 410
City Hall Annex 5 3 3 3 5 5 3 5 400
ADA Improvements 4 5 3 1 5 5 3 3 380
McClellan Road Bridge
Replacement
5 3 4 1 2 3 5 2 380
Stevens Creek Bridge Repair 5 3 4 1 2 3 5 2 380
Citywide Building Condition
Assessment Implementation
4 3 4 4 3 2 4 2 355
PV Systems Design & Installation 3 3 0 5 5 3 5 5 325
Outfalls Repairs [Storm Drains] 4 3 4 1 2 3 2 2 305
Vai Avenue Outfall 4 3 4 1 2 3 2 2 305
EVCS expansion - Service Center 1 5 1 4 5 2 5 5 300
Tamien Innu - East Segment 3 1 1 4 5 2 5 5 300
MRP West Parking Lot
Improvements
0 5 1 5 5 5 5 5 290
Roadway Safety Improvements -
HSIP
4 1 1 2 2 2 5 5 290
Lawrence-Mitty Park and Trail
Plan
2 1 2 5 5 5 4 4 285
QUEUED
Annual Playground Replacement 4 3 5 5 5 5 3 2 395
School Walk Audit 5 3 3 1 3 5 5 4 395
Library Expansion Project
(landscaping and other
improvements)
2 1 3 5 5 5 5 5 320
Tamien Innu - Central Segment 3 1 1 4 5 2 5 5 300
Tamien Innu - West Segment 3 1 1 4 5 2 5 5 300
Stevens Creek Blvd CL IV
Bikeway - Design & Phase 2A
Construction
3 1 2 3 5 3 3 5 285
Stevens Creek Blvd CL IV
Bikeway - Phase 2B construction
3 1 2 1 5 3 3 5 275
Park Amenity Improvements 1 1 3 5 5 5 3 2 245
Stevens Creek Blvd CL IV
Bikeway - Bandley Dr. Signal
3 1 1 1 3 3 4 3 245
Street Light Installation - Annual
Infill
3 1 1 2 3 2 2 4 220
NEW PROJECTS FY 26-27
Blesch Property Improvements 5 1 5 5 5 3 1 0 345
Sports Center Courts Resurfacing 4 3 5 0 0 4 2 2 300 BBF Golf Course Pro Shop
Renovation
4 3 5 0 0 3 1 2 280
SCB/SR 85 NB ramp Intersection
improvements
3 0 2 1 4 3 5 4 275
Memorial Park Pickleball Sound
Attenuation
4 3 3 0 0 4 1 2 255
CIP Prioritization process - FY 26 - 27 Prioritizat ion Matrix Page 1 of 3

APPENDIX D
FY 26-27 PRIORITIZATION MATRIX - CIP PROJECTS
1 2 3 4 5 6 7 8 Totals
LEGEND :

Facilities
Parks & Rec
Streets & Infrastructure
Transportation
Sustainability & Energy
Health & Safety Regulatory /
Legal Mandate
Asset
Condition &
Infrastructure
Risk
Climate
Resilience &
Sustainability
Strategic
Alignment
Community
Benefit &
Equity
Financial
Leverage &
Cost
Effectiveness
Project
Readiness
Points
Range: 0
to 500
30 15 15 5 10 5 15 5

UNFUNDED PROJECTS
Stocklmeir and properties 5 0 5 2 3 3 1 0 295
McClellan Ranch Preserve Barn
Renovation
3 2 5 2 3 3 2 1 285
BBF Golf Course Irrigation 3 1 5 3 2 2 3 2 280
Bollinger Road Corridor Constrn 5 0 1 1 3 4 3 3 280
Bollinger Road Corridor Design 5 0 1 1 3 4 3 3 280
BBF Golf Course Pond Restoration 3 1 5 3 2 2 3 1 275
Blackberry Farm Play Area
Improvements
3 2 4 2 5 3 1 1 275
Memorial Park projects: All-
Inclusive Playground (Phase 1A)
3 2 4 2 5 3 1 1 275
Building Electrification Analysis 2 1 4 5 5 1 3 3 275
Memorial Park projects: Softball
Field Lighting
3 2 4 3 1 2 3 2 270
Quinlan Community Center
Electrification
2 1 4 5 5 1 3 1 265
Blackberry Farm Golf Course
Restroom Renovation
3 3 3 2 1 3 3 1 265
Electrification of other City 2 1 3 5 5 2 3 2 260
Library Electrification &
Resiliency upgrades
2 1 3 5 5 2 3 2 260
CIP Prioritization process - FY 26 - 27 Prioritizat ion Matrix Page 2 of 3

APPENDIX D
FY 26-27 PRIORITIZATION MATRIX - CIP PROJECTS
1 2 3 4 5 6 7 8 Totals
LEGEND :

Facilities
Parks & Rec
Streets & Infrastructure
Transportation
Sustainability & Energy
Health & Safety Regulatory /
Legal Mandate
Asset
Condition &
Infrastructure
Risk
Climate
Resilience &
Sustainability
Strategic
Alignment
Community
Benefit &
Equity
Financial
Leverage &
Cost
Effectiveness
Project
Readiness
Points
Range: 0
to 500
30 15 15 5 10 5 15 5

UNFUNDED PROJECTS (CON'T)
Regnart Road Improvements,
(Phase 2)
3 2 3 1 4 2 1 2 245
Blackberry Farm Pools Water
Heating Upgrades
2 1 2 5 5 2 3 2 245
Storm Drain Improvements -
Bubb Road, Phases 1-3
3 2 3 1 4 2 1 1 240
Memorial Park projects:

Amphitheater renovation (Phase
2A)
2 1 2 2 5 4 1 2 210
Memorial Park projects: Central
Picnic Area, Alves entrance and
plaza, Softball field, tennis courts
and basketball courts (Phase 2B)
2 1 2 2 5 4 1 2 210
Memorial Park projects: Fields
and Alves parking lot renovation
(Phase 2C)
2 1 2 2 5 4 1 2 210
Memorial Park projects: Pickleball
Courts, Bocce, Event Lawns and
Restrooms (Phase 1B)
2 1 2 2 5 4 1 2 210
Memorial Park projects: Senior
Center and Quinlan parking lot
renovations (Phase 3)
2 1 2 2 5 4 1 2 210
Linda Vista Park Improvements:
picnic area, path and field
improvements
3 1 2 2 2 3 1 1 200
Pumpkin and Fiesta Storm Drain
Project (Phase 2)
2 1 3 1 4 2 1 1 195
Park Pathways Paving 2 1 2 2 3 3 1 1 180
Portal Park Improvements: picnic
area, rec bldg.
2 1 2 2 2 3 1 1 170
Blackberry Farm Entrance
Improvements
2 1 2 1 2 2 1 1 160
Carmen Road Bike/Ped Bridge 3 0 0 1 3 2 1 2 160
Stevens Creek Blvd Separated
Class IV Bikeway, Phase 3
3 0 0 1 3 2 1 2 160
Replace Non-Functional Turf &
Improve water efficiency
2 0 1 5 2 2 1 1 150
Blackberry Farm Family Restroom
Conversion
0 2 3 3 1 2 2 1 145
SV Hopper EV Parking 0 0 0 5 3 3 4 2 140
Park Shade Structures 2 0 0 2 3 5 0 1 130
Merriman Road Storm Drain 2 1 3 1 0 1 0 0 130
Fiber Expansion 0 0 0 0 5 2 1 1 80
Little Rancho picnic area 1 0 0 2 2 2 0 0 70
New Neighborhood Parks 0 0 0 3 3 3 0 0 60
CIP Prioritization process - FY 26 - 27 Prioritizat ion Matrix Page 3 of 3 FY 26–27 CIP Book Page 43

Capital Improvement Programs Fiscal Year 2026 – 2027
and 5-Year Plan

CIP Project Narratives