Del Mar City Council
Special Meeting Agenda
City of Del Mar Town Hall
1050 Camino del Mar, Del Mar, California 92014
1050 Camino del Mar, Del Mar, CA 92014 www.delmar.ca.us Civility Works: The Del Mar Code of Civil Discourse: Together we will promote inclusion; listen to understand; show respect; be clear and fair; and focus on the issue.
NOTICE AND CALL OF
SPECIAL MEETING OF THE DEL MAR
CITY COUNCIL GOALS & PRIORITIES SETTING
WORKSHOP
Wednesday, March 11, 2026, 2:00 p.m.
City of Del Mar Town Hall
1050 Camino del Mar, Del Mar, California
*********************************************
NOTICE IS HEREBY GIVEN that the Mayor of the City of Del Mar has called a Special Meeting at the time and place listed above to consider the following: Please refer to the attached agenda.
CERTIFICATION
I, Sarah Krietor, Administrative Services Manager/City Clerk of the City of Del Mar, hereby certify that a copy of this notice was posted at City Hall and distributed to the City Council on March 6, 2026, at approximately 4:30 p.m.
Sarah Krietor, Administrative Services
Manager/City Clerk
Assistance for Persons with Disabilities: In compliance with the Americans with Disabilities Act, if you need special assistance to participate in this meeting, please contact the Administrative Services Department at 1050 Camino del Mar or by calling (858) 755-9313.
Notification of at least 48 hours prior to the meeting will enable the City to make reasonable arrangements to ensure accessibility to this meeting.
Tracy Martinez
Mayor
John W. Spelich
Deputy Mayor
Terry Gaasterland
Council Member
Dan Quirk
Council Member
Ashley Jones
City Manager
Christina Cameron
City Attorney
Sarah Krietor
Administrative
Services
Manager/City Clerk
Del Mar City Council Goals and Priorities Setting Workshop March 11, 2026 Agenda Page 2
1050 Camino del Mar, Del Mar, CA 92014 www.delmar.ca.us I. CALL TO ORDER/ROLL CALL
II. PUBLIC COMMUNICATIONS
Public comment is restricted to only items listed on the Special Meeting Agenda.
Members of the public can participate in City Council meetings in-person or by submitting written comments. Anyone may address the City Council for up to three minutes, at the Mayor’s discretion, on agenda items. When addressing the Council, please state your name for the record. Any electronic presentations must be received before 12 p.m. on the date of the Council meeting. No PowerPoint presentations can be loaded during the meeting.
In-Person Participation: Please submit a completed “Speaker Slip”, including the item number you wish to speak on, to the City Clerk prior to the Mayor announcing the agenda item. The forms are located near the door at the rear of the Meeting Room. When called to speak, please approach the podium and state your name for the record.
Written Comments: Members of the public can participate in the meeting by submitting a written red dot comment via email to [email protected]. The deadline to submit written comments is 12 p.m. on the day of the meeting and the subject line of your email should clearly state the agenda item you are commenting on.
III. CITY COUNCIL BUSINESS
1. 2026 City Council Goals & Priorities Setting Workshop Recommended Action: Staff recommends that the City Council: 1) Receive an update on the Work Plan items to be completed during Fiscal Year (FY) 2025-26 (Attachment A); 2) Review the FY 2026-27 Work Plan including new items proposed by staff (Attachment B); 3) Review the list of Council Identified Proposed Work Plan Items (Attachment C); and provide direction to staff as needed.
Clerk’s File No. 401-1
IV. ADJOURNMENT
City of Del Mar
Agenda Report
________________________________________________________________________________________________________ City Council Action:
TO: Honorable Mayor and City Councilmembers
FROM: Ashley Jones, City Manager
Sarah Krietor, Administrative Services Manager
Kseniia Izgarskaia, Senior Management Analyst
DATE: March 11, 2026
SUBJECT: 2026 City Council Goals & Priorities Setting Workshop REQUESTED ACTION/RECOMMENDATION:
Staff recommends that the City Council: 1) Receive an update on the Work Plan items to be completed during Fiscal Year (FY) 2025-26 (Attachment A); 2) Review the FY 2026-27 Work Plan including new items proposed by staff (Attachment B); 3) Review the list of Council Identified Proposed Work Plan Items (Attachment C); and provide direction to staff as needed.
BACKGROUND:
At the beginning of each calendar year, the City Council holds a public workshop to review and establish Council goals and priorities, which is the basis for the City’s annual work plan and aids staff in identifying the necessary budgetary and staffing resources to accomplish the Council established goals. On March 5, 2025, City Council held a Goals & Priorities Setting Workshop and approved a two-year City Work Plan for FY 2025-26 and 2026-27 (Work Plan).
The Work Plan informed the FY 2025-26 and 2026-27 Operating and Capital Budget approved by City Council on June 16, 2025.
On February 3, 2026, the City Council provided direction to staff on the format for the 2026 Workshop, which they directed to be the standard moving forward unless changes are recommended by staff or Council in the future. Consistent with past practice, the Workshop will provide the City Council with an opportunity to receive an update on the FY 2025-26 Work Plan items that have been or will be completed during the current fiscal year; reaffirm/finetune the previously approved FY 2026-27 Work Plan, including reviewing any new items proposed by staff and the City Council; and provide the Council with the opportunity to discuss any policy level concerns. Feedback from the Workshop will be used for the FY 2026-27 Budget Update planned for presentation to the City Council in June 2026.
City Financial Position
On March 3, 2026, the City Council received the FY 2024-25 Final Financial Report and FY 2025-26 Mid-Year Financial Report. The report reflected positive financial results for FY 2024- 25 and for FY 2025-26 year-end projections. The agenda report is available here:
https://www.delmar.ca.us/DocumentCenter/View/11941/Item-12---FY25-Final-Report-andFY26-MY-Report City Council Agenda Report
2026 City Council Goals & Priorities Workshop
March 11, 2026
The FY 2024-25 Final Financial Report shows General Fund revenues came in $1.25 million (5.4%) higher than final budget projections, and General Fund expenditures came in approximately $91,000 (0.5%) lower than final budget projections. This resulted in a 34.8% General Fund Contingency (GFC) at June 30, 2025, which is approximately 4.7% higher than the 30.08% GFC projected in the FY 2024-25 Mid-Year Financial Report that was presented to the City Council on April 7, 2025.
The report also presented a positive year-end outlook for FY 2025-26. General Fund revenues are projected to come in $936,180 over budget while expenditures are projected to come in $23,000 underbudget. The City Council’s action to amend the FY 2025-26 Operating and Capital Budget also included approval to transfer an additional $425,000 to the Housing Reserve and $850,000 to the Capital Reserve. These approved adjustments result in a revised GFC estimated at 27.18%, or 99 days of operations, on June 30, 2026.
City Operations/Staffing Capacity
The City benefits greatly from a small team of dedicated and well-qualified employees who work diligently to provide the community with a high level of service through daily operations, while completing complex special and CIP projects to move Del Mar forward and timely achieve City Council goals.
A large majority of the City’s 66 full-time, regular staff spend 100% of their time on City operations. There are approximately 20 employees (30% of workforce) whose work in some capacity directly supports the Council-approved special and capital projects, and of those only the City’s Principal Engineers and Principal and Associate Long-Range Planners (7.5% of workforce) are primarily dedicated to special and/or CIP projects.
Staff capacity is closely aligned with the work items identified in Attachments A and B. Any substantive expansion of the current Work Plan may require either the re-prioritization or deferral of existing projects, or the addition of staffing resources.
To provide context on how the City spends the majority of its staff resources on day-to-day operations, Attachment D includes a summary of the operational duties and responsibilities for each department. All City departments have heavy operational responsibilities and provide critical services to the community. It is important to note that some operational items, such as administering elections or negotiating labor contracts and leases for use of public property, require significant staff time but are not included in the Goals & Priorities Work Plan because they are cyclical and non-discretionary.
DISCUSSION/ANALYSIS:
To facilitate the Workshop and help guide the City Council’s establishment of its Goals and Priorities for FY 2026-27, staff prepared the following resources:
1. Status update for the items on the current FY 2025-26 Work Plan that have or will be completed by the end of the fiscal year (Attachment A);
2. Identified Work Plan items for FY 2026-27, including new proposed items from staff (Attachment B);
3. City Council Identified Proposed Work Plan items (Attachment C); and City Council Agenda Report
2026 City Council Goals & Priorities Workshop
March 11, 2026
4. Overview/Summary of City operations by department (Attachment D).
List and Status Update for Current FY 2025-26 Work Plan Items Given the City is nearing the end of the current fiscal year, staff prepared a summary table (Attachment A) showing the FY 2025-26 Work Plan items that have or will be completed prior to June 30, 2026. Multi-year projects will be carried over to the proposed Work Plan for FY 2026-27. In total, staff completed, or are on track to complete, 30 significant work items by the end of the current fiscal year.
In addition to completed Work Plan items, staff made significant progress on a large number of multi-year, priority Work Plan items during FY 2025-26, notably the City’s Utility Undergrounding Program, Camino Del Mar Bridge design and environmental work, implementation of the City’s Housing Element and Short-Term Rental Ordinance, Shores Park Master Plan re-engagement, and several others.
Identified Work Plan Items FY 2026-27
Identified Work Plan items for FY 2026-27 are included as Attachment B, and are organized by the City’s established tiered priority system as follows:
Tier 1 (essential/non-discretionary services);
Tier 2 (important items that support City operations/values); and Tier 3 (discretionary/non-essential work items that could be deferred or eliminated).
There are several Work Plan items that the City Council has prioritized in recent years that will continue to be a significant focus for the City in the coming years including implementation of the City’s Housing Element, ongoing coordination and work with the San Diego Association of Governments (SANDAG) on their multiple rail-related CIP projects in the City, undergrounding of power lines throughout the City, replacement of the Camino Del Mar Bridge, and increased pavement improvements citywide to name a few. These projects alone will require significant time and attention from staff and the City’s elected leaders.
Construction of the Camino del Mar Bridge Replacement project is anticipated to begin in early 2027, with bidding to occur in 2026. To assist to Council with understanding the current project timeline and costs, a Construction Delivery Schedule and funding update is included as Attachment E.
Annual roadway paving remains a Tier 1 Council priority with the City Council previously committing a minimum of $750,000 annually towards paving. Based on the City’s positive financial results and favorable construction market conditions an expanded pavement management program totaling $3,000,000 is being proposed by staff for City Council consideration. Paving project funding sources, targeted streets, and a related work map for the proposed updated Pavement Management Program are presented in Attachment F.
Additionally, a summary of the funding sources and discussion about timing for completion of the Riverpath Phase 3 project are presented in Attachment G.
While staff works diligently to identify all Work Plan items for City Council consideration during the goal setting and budget development process, new important projects arise throughout City Council Agenda Report
2026 City Council Goals & Priorities Workshop
March 11, 2026
the year for various reasons such as City Council direction, legislative changes, or unforeseen challenges and/or emergencies. Accordingly, the FY 2026-27 City Work Plan includes the proposed new Work Plan items, which are denoted as “new” in the title.
Council Identified Potential Work Plan Items
As part of the annual Goal & Priorities Workshop, Councilmembers proposed new items for the City Council to consider adding to existing or future work plans, which are included as Attachment C.
Next Steps
Staff will use the feedback and direction provided by the City Council during the Workshop to solidify the City Council’s Goals and Priorities and update the FY 2026-27 Work Plan, which will be used to update the FY 2026-27 Operating and Capital Budget planned for presentation to the Council in June 2026. This information will also be used to evaluate the proposed FY 2026-27 City advisory committees’ annual work plans in preparation for the City Council’s consideration of the committee work plans for the coming fiscal year in the spring of 2026.
ATTACHMENTS:
Attachment A – FY 2025-26 Work Plan Items to be completed by June 30, 2026 Attachment B – Proposed Work Plan for Fiscal Year 2026-27 Attachment C – City Council Identified Proposed Work Plan Items Attachment D – Summary of City of Del Mar Department Operations Attachment E – Camino del Mar Bridge Replacement Update Attachment F – Pavement Management Program Update
Exhibit 1 to Attachment F - Pavement Management Program Update Streets Exhibit 2 to Attachment F - Map
Attachment G – Riverpath Phase 3 Update
Reference
No. Item Name Description Status Tier Department(s)
1 General Plan Update:
Safety Element Update
(6th Cycle Housing
Element Program 6H)
Preparation and processing of update to the Safety
Element in Del Mar Community Plan to comply with
Housing Element and State law. City Council
adopted Fire Hazard Severity Zone Maps in May
2025 and adopted updated California Building and
Fire Codes in September 2025, which are related
actions. Planning Commission recommended
approval January 13, 2026.
In Process. Estimated Completion in April 2026 Tier 1 Planning 2 General Plan Update: New
Environmental Justice
Element (6th Cycle
Housing Element Program
6E)
Preparation and processing of new Environmental
Justice Element in Del Mar Community Plan per
Housing Element. Project correlates with update to
the Safety Element in process. Planning
Commission recommended approval February 10,
2026.
In Process. Estimated Completion in May 2026 Tier 1 Planning 3 Mid Cycle ADU Production
Evaluation (6th Cycle
Housing Element Program
2E)
The Mid Cycle ADU Production Evaluation was
presented to City Council September 8, 2025. Completed in September 2025 Tier 1 Planning 4 Senate Bill 9 (SB 9)
Implementing
Ordinance/LCPA
Ordinance/LCPA to implement State law provisions
consistent with CCC guidance to harmonize
housing law with the Coastal Act. City Council
adopted June 19, 2023. City processed
modifications to address conditional certification
from Coastal Commission and obtained final
certification in June 2025.
Completed ahead of schedule in June 2025 Tier 1 Planning 5 ADU Ordinance/LCPA for
Consistency with State
Law
Ordinance/LCPA to implement State law provisions
in a manner that harmonizes State housing law and
the Coastal Act. City Council adopted December
2023. City processed modifications to address
conditional certification from Coastal Commission
and obtained final certification in May 2025.
Completed ahead of schedule in May 2025 Tier 1 Planning 6 Tiny House Regulations
(6th Cycle Housing
Element Program 2F)
Ordinance/LCPA to clarify within the updated ADU
regulations that tiny houses are to be implemented
consistent with the ADU regulations. City Council
adopted December 2023. City processed
modifications to address conditional certification
from Coastal Commission and obtained final
certification in May 2025.
Completed ahead of schedule in May 2025 Tier 1 Planning FY 2025-2026 Work Plan Items to be Completed
Reference
No. Item Name Description Status Tier Department(s)
FY 2025-2026 Work Plan Items to be Completed
7 Amend Central
Commercial (CC) Zone
(6th Cycle Housing
Element Program 1C)
Ordinance/LCPA to allow 20 du/ac density to create
adequate sites and facilitate affordable housing per
Housing Element. City Council timely adopted April
15, 2024, to meet State law. City processed
modifications to address conditional certification
from Coastal Commission and obtained final
certification in April 2025.
Completed ahead of schedule in April 2025 Tier 1 Planning 8 Update to Building and
Fire Codes
Prepare and Process Ordinance to adopt the latest
California Building and Fire Codes and incorporate
local modifications as desired. Routine update
processed every three years. New Codes will be
effective January 1, 2026.
Completed in September 2025 Tier 1 Planning and City Attorney 9 STR Permit Fee
Resolution
Prepare analysis to identify the associated cost for
implementation of STR permit issuance,
monitoring, and enforcement. Process Resolution
for City Council approval to establish fees for
implementation of the new STR regulations that
took effect February 6, 2026.
Completed in February 2026 Tier 1
Planning
Administrative Services
City Attorney
10 Short Term Rental
Regulations/Preservation
of Existing Housing Stock
(6th Cycle Housing
Element Program 5C)
Ordinance/LCPA to regulate short term rentals was
adopted by the City Council September 23, 2024,
and certified by the Coastal Commission February
5, 2026.
Completed in February 2026 Tier 1 Planning
City Attorney
11 Water System Priority
Improvements Scoping Water System repairs and improvements.
Completed scoping improvements for the next
construction project. Tier 1 Public Works
12 Grant Application for
Annual Wastewater
System Priority
Improvements
Wastewater System repairs and improvements.
Completed grant application, federal environmental
reviews, and prepared work plan for the USEPAfunded wastewater and storm drain improvements project (FY24 Community Grants).
Tier 1 Public Works
13 Grant Application for
Annual Storm Drain
System Priority
Improvement
Replace storm drain facilities that have surpassed
their useful life.
Completed grant application, federal environmental
reviews, and prepared work plan for USEPA-funded
wastewater and storm drain improvements project.
Tier 1 Public Works
Reference
No. Item Name Description Status Tier Department(s)
FY 2025-2026 Work Plan Items to be Completed
14 Annual Bike Route
Repairs
Repair bike lanes on major arterials; CDM, JDB,
Via de la Valle, Carmel Valley Road.
In-Process. Work will be completed as part of
Annual Pavement Management Program's repair of
Jimmy Durante Boulevard between Via de la Valle
and the roundabout, including bike lane
improvements.
Tier 1 Public Works
15 Annual Pavement
Management Program
Annual Roadway Repairs to Major Arterials and
Residential Streets.
In-Process. Project (Jimmy Durante Boulevard) will
be completed by June 2026. Tier 1 Public Works
16 Annual Water Valve
Replacement Project
Replace broken water valves as identified in
maintenance program.
In-Process. Annual valve exercising will be
completed by June 2026 and Public Works developed
a prioritized list of valves to be replaced in next Water System CIP project.
Tier 1 Public Works
17 Major Facility Repairs
Essential building (City Hall, Library, Public Works,
Community Services, etc.) repairs including
exterior, doors/windows, electrical, plumbing,
HVAC, fire and security systems.
Completed plumbing repairs to numerous public
restrooms, AC repairs to Council Chambers, Civic
Center Water Heater replacement, Civic Center
roof/gutter repairs, Civic Center Parking Garage
Grease Trap replacement, Civic Center Fire/Security
Alarm repairs, and AC repairs to the server room.
Tier 1 Public Works
18 Jimmy Durante Boulevard
Bike Lane Modification
Project
Safety enhancements to modify five curb inlets
along northbound Jimmy Durante Boulevard
between Luzon Avenue and San Dieguito Drive.
In-Process. Bidding phase completed as part of the
Jimmy Durante Boulevard Bluff Stabilization Project in
FY2025-2026. Council awarded the construction
contract in November 17, 2025, notice to proceed
issued for January 2026 with construction completion
anticipated May 2026.
Tier 1 Public Works
19 Annual Small Area
Pavement Repair Contract Citywide small area asphalt paving/repairs.
In Process. First phase of repairs completed in
December 2025, with second phase to be completed
before July 1, 2026.
Tier 1 Public Works
20 Utility Undergrounding
District 1A (Stratford
South)
Undergrounding of above ground dry utilities into
joint trench and underground service laterals.
In-process/Substantially Complete. City
construction was substantially completed by April
2025. Homeowner service laterals were mostly
completed by May 2025. Utility companies estimate
completion, including pole removals, by March 2026.
Final paving will be completed following utility
companies construction, with overall project
completion anticipated by April 2026.
Tier 1 Public Works
City Manager's Office
21 Jimmy Durante Boulevard
Bluff Stabilization Project
Design and construct improvements to permanently
protect bluff in City right of way along Jimmy
Durante Boulevard.
In-Process. Bidding phase completed in FY2025-
2026. Council awarded the construction contract in
November 17, 2025, notice to proceed issued for
January 2026 with construction completion anticipated
May 2026.
Tier 1 Public Works
Planning
Reference
No. Item Name Description Status Tier Department(s)
FY 2025-2026 Work Plan Items to be Completed
22 Amendment to City of San
Diego Wastewater
Transportation and
Disposal Agreements
Identify options to amend Metropolitan Wastewater
Commission Treatment and City of San Diego
Wastewater Transportation Agreements for Council
consideration. The City currently transports majority
of its wastewater to the San Elijo Joint Powers
Authority water reclamation facility in Encinitas via
Solana Beach's system.
Completed. The City Council approved the Second
Amended and Restated Regional Wastewater
Disposal Agreement between the City of San Diego
and the Participating Agencies in the Metropolitan
Sewerage System on January 20, 2026. The
Amendment has been approved by five of the twelve
Participating Agencies.
Tier 1 Public Works
City Manager's Office
23 Legislative Changes
Compliance
Implementation (New)
Evaluate City's existing procedures and ensure
compliance with several recent legislative changes,
including:
SB 827 – Local Agencies Officials Fiscal Training
Requirements; SB 707 - Brown Act Amendments;
AB 339 - Local Public Employee Organizations:
Notice Requirement; SB 513 - Personnel Records
Training Filing Requirement; SB 294 - Know Your
Rights Act; SB42, AB 953, 1286 – Campaign
finance regulations; and multiple bills amending
election regulations.
In-Process. City Clerk's Office and Finance
Department have begun implementation on several
listed bills, most of which is expected to be completed by July 2026. In regard to SB 707 (Brown Act
revisions), staff is currently analyzing options to
ensure compliance and will bring an updated public
participation policy to City Council for consideration
and approval in April/May 2026, for implementation
by July 1, 2026.
Tier 1 Administrative Services
24 Short-Term Rentals (STR)
Regulation Administration
Complete implementation of an STR administration
platform including registration and permitting,
maintaining an STR database, monitoring STR
activity, compliance and code enforcement support,
community outreach, and TOT remittance and
auditing.
In-Process. Staff completed an Request for
Proposals (RFP) solicitation process to hire a
consultant to manage short-term rental (STR)
administration with the City. Council approved the
contract with Deckard on October 20, 2025. The STR
Permit Application period is March 2, 2026, to May 1,
2026.
Tier 1 Administrative Services
Planning
25 Citywide Curbside
Management Inventory
Complete a comprehensive curbside management
inventory of all existing red curbs and "no parking"
areas along public streets. Working with the City's
traffic Engineer, MBI, staff will coordinate with the
Fire Department to review intersections for
accessibility and validate the City's existing red
curbs. Finally, the data will be used to calculate the
City's available parking supply to assist with
compliance reporting requirements of the City's
Coastal Development Permit.
In Process. Estimated completion by June 2026 Tier 2
City Manager's Office
Planning
Public Works
Community Services
Fire Department
26 Tree, Scenic Views, and
Sunlight Ordinance
(TSVS) Update
Prepare and process and amendment to the TSVS
Ordinance. Completed in November 2025 Tier 2 Planning
Reference
No. Item Name Description Status Tier Department(s)
FY 2025-2026 Work Plan Items to be Completed
27 Reconsider Advisory
Committee Structure
Council-initiated item. Subcommittee
(Martinez/Gaasterland) brought recommendation to
Council May 19, 2025. Council approved changes
have been implemented by staff.
Completed. Council approved changes to the
committee structure in May 2025. Future updates
could be considered by the City Council as needed.
Tier 3 Administrative Service
28 Smoke Free City Signs to
Enforcement Ordinance
Council-initiated item to evaluate opportunities to
place additional "No Smoking" signage in
accordance with the Municipal Code relating to
smoking.
Completed. Additional signage at key locations has
been posted. Tier 3 Community Services
29 Pedestrian Light Pole
Wood Refinishing Project
The Project sanded and refinished 62 wooden
pedestrian light poles along Camino del Mar from
9th Street to Plaza.
Completed in November 2025. Tier 3 Public Works
30 California Municipal
Treasurers Association
(CMTA) Investment Policy
Certification Program
Pursue CMTA Investment Policy Certification.
CMTA program provides professional guidance and
assistance in developing and/or improving
investment policies that meet industry best
practices for California's public sector agencies.
Completed. Certification of the City's Investment
Policy for FY 2025-26 was issued by the California
Municipal Treasurers Association on September 9,
2025.
Tier 3 Administrative Services
Reference
No. Item Name Description Status Department(s)
1 City Website ADA
Compliance
Evaluate City Website ADA compliance and implement solutions to maintain compliance and meet the newly released DOJ mandate by April 2027 as required by law.
Staff is working with its website hosting vendor to analyze current state of compliance and evaluate solutions.
Administrative Services
Information Systems
2 Enterprise Resource
Planning (ERP) System
Implementation Process
Timely selection and implementation of a new ERP system prior to the current system sunset in March 2027. Work on this item began in mid2024.
Council approved an agreement with Tyler Inc. for ERP Pro 10 on December 15, 2025. Project implementation began in January 2026, and will be completed in phases. Core
modules are targeted for implementation by March 2027,
and peripheral modules are targeted for implementation by December 2027.
Administrative Services
3 Participation in Multiple
SANDAG Major Projects:
- San Diego LOSSAN Rail
Realignment
- DM Bluff Stabilization 5
- DM Bluffs Access
Improvements
- San Dieguito Double
Track & Special Events
Platform
On-going coordination and work with SANDAG and the public on significant CIP projects happening in parallel, including the San Diego LOSSAN Rail Realignment Project; Del Mar Bluff Stabilization Project 5; Del Mar Bluffs Access Improvements Project (informed by the Coastal Connections Conceptual Planning Study); and the San Dieguito Double Track and Special Events Platform project, which involves relocation of City water/wastewater utility lines, a pedestrian undercrossing, license agreements, and an encroachment permit.
Coordination and participation with SANDAG on various
SANDAG projects affecting Del Mar is ongoing and
involves a substantial amount of City staff time from
multiple departments. For the San Diego LOSSAN Rail
Realignment project this includes working with SANDAG on a Memorandum of Understanding (MOU) between the two
agencies that would allow City staff and its consultants to participate in the environmental review process;
commenting on a joint Notice of Preparation/Notice of
Intent (NOP/NOI) in Fall 2026; and exploring potential
lobbying oppertunities at the apporiate time.
City Manager's Office
Planning
Public Works
City Attorney
4 LAFCO Municipal Service
Review (New)
Non-discretionary participation in a LAFCO Municipal Service Review of the Del Mar and Solana Beach to evaluate the availability and adequacy of local governmental services and governance
responsiveness relative to community needs and is required on a fiveyear rolling basis by the Commission.
Not started.
City Manager's Office
Planning
Public Works
Administrative Services
City Attorney
5 Fire Management Services
Transition (New)
In partnership with the City of Solana Beach, prepare for Encinitas to exit the current agreement for shared Fire Management Services effective March 31, 2026, and establish a new shared fire management command structure and cost sharing arrangement with the City of Solana Beach. To be followed by a joint
evaluation/analysis of long-term service options, such as through a JPA.
Transition is currently underway. Next steps include:
completion of recruitment processes to hire a permeant
Fire Chief and Fire Marshal; RFQ to retain a consultant to evaluate long term options; completing the transition of training, station inventory and other administrative
processes; and Council consideration of a cost sharing
agreement with the City of Solana Beach.
City Manager
Administrative Service
Fire
TIER 1: Essential Services (State Mandated/Legally or Contractually Required) Reference
No. Item Name Description Status Department(s)
TIER 1: Essential Services (State Mandated/Legally or Contractually Required) 6 Process Ordinances to
create incentives and an
Affordable Housing
Overlay Zone - (6th Cycle
Housing Element Program
1D and 1I)
Utilize data from Phase II studies completed January 2023 to prepare Ordinance/LCPA creating an overlay zone to apply objective design standards and provide site-specific incentives for affordable housing projects on sites relied upon for the 6th Cycle Housing Element. Will involve preparation of visual concepts and discussion of options related to potential scale and compatibility of development that could occur. Action is required per Housing Element Program 1D due to production of less than 30 lower income units by April 2025.
Estimated completion of Visual Concepts for Council review by June 2026 and new Overlay Zone to City Council by
December 2026
Planning
7 Prepare Fair Housing
Materials (6th Cycle
Housing Program 6B)
Prepare and publish Fair Housing Materials in English and Spanish in order to implement a component of Program 6B, Affirmatively Furthering Fair Housing. Materials will be made available on the City's website and local non-profits.
Estimated Completion in September 2026 Planning
8 Fairgrounds Housing
Strategy (6th Cycle
Housing Element Program
3A)
Secured Exclusive Negotiating Rights Agreement (ENRA) with 22nd District Agricultural Association (DAA) in March 2024. ENRA expires April 15, 2027. City is reviewing task orders prepared by DAA's consultant Harris Associates and processing additional task orders with City consultants SDA and KMA to complete due diligence analysis to facilitate site selection per the ENRA and negotiation of a lease agreement that aligns with the Fairgrounds master planning. process.
In-process. Continue to implement terms of ENRA
including: completion of due diligence studies through
March 2026, completion of conceptual designs for three
sites in Del Mar by September 2026, Council and District to discuss and select housing site March through October
2026. Target is ground lease agreement by November 2026 and RFP for solicitation of affordable housing developer to follow.
Planning
City Manager's Office
9 Affordable Housing on CityOwned Properties at 10th
Street (6th Cycle Housing
Element Program 3B)
Pursue declaration as exempt per Surplus Lands Act and process accordingly including noticing, RFP for developer solicitation, and ground lease agreement. As first priority, facilitate development project on City-owned vacant lot on 10th Street (i.e., CEQA and entitlements to develop 4-8 units for lower income households and building permit by 2027. City Council allocated $500,000 to program for FY 2026-2027.
In-process. City Council Resolution February 17, 2025 to declare 10th Street SLA exempt. City is implementing
additional steps in consultation with HCD per SLA and
pursuing project financing opportunities.
Planning
10 Affordable Housing on CityOwned Properties at 28th
Street (6th Cycle Housing
Element Program 3B)
Pursue declaration as exempt per Surplus Lands Act and process accordingly including noticing, RFP for developer solicitation, and ground lease agreement. Facilitate development project on Cityowned vacant lot on 28th Street (i.e., CEQA and entitlements to develop 3-4 units for lower income households and building permit by 2027. City Council allocated $500,000 to program for FY 2026-2027.
In-process. City Council Resolution to declare 28th Street SLA exempt. City is implementing additional steps in
consultation with HCD per SLA and pursuing project
financing opportunities. Targeting Spring 2026
Planning
11 General Plan Update: Open
Space Element Update (SB
1425)
State law requires the City update its Open Space Element by January 1, 2026, to address specified climate resilience and rewilding criteria to provide coordinated mitigation of impacts to new development.
Anticipated to start in April 2026 Planning
Reference
No. Item Name Description Status Department(s)
TIER 1: Essential Services (State Mandated/Legally or Contractually Required) 12 Residential Care Facilities
(6th Cycle Housing
Element Program 4A)
Prepare and process Ordinance/LCPA to clarify this land use type and bring the regulations into compliance with State law. City is using HAP Grant funds with target of City Council by September 2026.
In process. Anticipated to complete September 2026 Planning and City Attorney 13 Emergency Shelters,
Transitional Housing,
Supportive Housing, and
Low Barrier Navigation
Centers (6th Cycle
Housing Element Program
4B)
Prepare and process Ordinance/LCPA for compliance with State law.
Develop procedures and informational handouts to connect people to resources. City is using HAP grant funds with target of City Council by September 2026.
In process. Anticipated to complete September 2026 Planning and City Attorney 14 Additional Incentives to
Facilitate Affordable
Housing
City Council will provide direction on potential amendments to existing ADU incentive programs adopted in December 2023 and address homesharing opportunities (i.e. seniors, students). This relates to HE Programs 1I, 4C, 7G, and 7H.
In process. Anticipate City Council consideration by June 2026; then processing of Ordinance by June 2027 Planning 15 Reasonable
Accommodations
Regulation Zone Code
Amendment
Prepare and process an Ordinance to create a new Del Mar Municipal Code Chapter that will update regulations for reasonable accommodations requests consistent with applicable State and Federal Fair Housing regulations. Relates to HE Programs 7C and 7F. Timing correlates to 4A/4B amendments in process.
In process. Anticipated to complete September 2026 Planning and City Attorney 16 Update to ADU Sample
Floor Plans (New)
AB 1332 went into effect on January 1, 2025, and requires local agencies to establish a process for the preapproval of architectural and design plans for ADUs. This requires jurisdictions to create a process for reviewing and approving preapproved ADU plans submitted by applicants. While the City does have preapproved ADU plans available, these plans need to be revised to incorporate city development standards.
Anticipated to start in FY2027 Planning
17 Camino del Mar Bridge
Replacement Project
Replace Camino del Mar Bridge over San Dieguito River in accordance within Federal Highway Bridge Program requirements.
Design and permitting documents complete; working
through Caltrans/FHWA review and approval. Hiring
Construction Management & Inspection firm. Bid phase
anticipated to begin July 2026, construction award in
December 2026.
Public Works
Planning
18 Riverpath Del Mar Phase 3 Extend Riverpath Del Mar from Grand Avenue Bridge to Crest Canyon.
The City has received preliminary approval for a $1.3M
pass-through grant from the Wildlife Conservation
Board/National Parks Service. Construction mostly likely needs to occur in 2027 to accomodate next steps in grant process. These grant funds will significantly reduce project funding gap to enable project to proceed with certainty next calendar year.
Public Works
Planning
Reference
No. Item Name Description Status Department(s)
TIER 1: Essential Services (State Mandated/Legally or Contractually Required) 19 Utility Undergrounding
District X1A (Crest
Canyon)
Undergrounding of above ground dry utilities into joint trench and underground service laterals.
Council awarded the City construction contract and the
SDG&E cost agreement in September 2025. The City
construction notice to proceed was issued in October 2025, with completion anticipated by October 2026. Staff
estimates the utility companies completion, including pole removals, by Spring 2027.
Public Works
City Manager's Office
20 Utility Undergrounding
District 1B (Stratford
North)
Undergrounding of above ground dry utilities into joint trench and underground service laterals.
SDG&E 60% design completed in February 2026, and
under review by City. Final design and bidding anticipated in CY 2026. Construction start anticipated the second half of FY2026-27.
Public Works
City Manager's Office
21 Utility Undergrounding
District 25th Street (20A)
Undergrounding of above ground dry utilities into joint trench and underground service laterals. Funding included as part of Rule 20A.
Design to start in FY 2025-26, as part of District 2 design.
Construction needs to be completed by December 2030 to
use 20A funds.
Public Works
City Manager's Office
22 Utility Undergrounding
District 2 (Beach Colony)
Undergrounding of above ground dry utilities into joint trench and underground service laterals.
Design of entire District to begin in FY2025-26, with
construction to occur in two phases (2A & 2B), with the potential to construct entire District by 2030 pending
funding availablity.
Public Works
City Manager's Office
23 Undergrounding Financing
Analysis
Update the Finance-As-You-Go cash flow modeling to identify potential opportunites for strategic and fiscally responsible financing to improve timing for Undergrounding Program completion and reduce overall costs.
Staff to work with the Undergrounding and Finance
Committees to propose financing guidelines for Council
consideration and complete financing modeling. Work will occur in FY 2025-26 and FY 2026-27.
Public Works
Administrative Services
Reference
No. Item Name Description Status Department(s)
1 Cost Allocation Plan
Update
The last update to the City's cost allocation plan was
completed internally in 2016, and needs to be updated.
Industry best practice is to complete an update every
three years. This is a multi-year process that is expected to begin in July 2025 and involves issuing a Request for Proposal (RFP) to hire a consultant to assist with this effort.
Completed an RFP solicitation process and a contract
negotiation. Council approved the contract with
Clearsource Financial Consulting on January 20, 2026,
with the goal of completing an updated Cost Allocation
Plan by end of FY 2026-27.
Administrative Services
2 User Fee Study
The City plans to conduct a Comprehensive User Fee
Study to evaluate and update its fee structure and rates, account for total service costs and desired cost recovery, and to maintain equity and legal compliance. The City's last fee study was completed in 2019. Industry best
practices recommend comprehensive updates every five
years.
Completed an RFP solicitation process and a contract
negotiation. Council approved the contract with
Clearsource Financial Consulting on January 20, 2026,
with the goal of completing an updated Cost Allocation
Plan by end of FY 2026-27.
Administrative Services
3 Civic Center Operations
Guide
Comprehensive update to the City’s facility use policies, including proposed updates to the list of eligible nonprofits.
Staff will work with the Council Subcommittee
(Spelich/Gaasterland) to prepare policy recommendations for Council consideration by end of 2026.
Administrative Services
Community Services
4 Climate Action Plan
Update
With support from a consultant, staff will update the City's 2016 Climate Action Plan, Greenhouse Gas (GHG)
Inventories, and mitigation strategies to align with other CAPs in the region and industry best practices.
Staff issued RFQ in February 2026 to hire a technical
consultant to assist the City developing new GHG
inventories, updating the CAP, associated mitigation
strategies, and monitoring. In FY2024-2025, staff applied for Cycle 6 SGIP grant funds to complete the update,
funds were awarded in January 2026. The CAP Update will begin in FY2025-2026, with the bulk of work occuring in FY2026-2027.
City Manager's Office
5 Solar Energy Partnership
(6th Cycle Housing
Element Program 6D)
Partner with programs like CEA or the Center for
Sustainable Energy to install solar on multi-unit, lower income housing to meet renewable energy goals in
Climate Action Plan.
Staff is analyzing available programs, but has not yet
entered into a partnership.
City Manager's Office
Planning
6 Public Right of Way (ROW)
Vegetation Maintenance
Regulations
Development of an Ordinance regulating the maintenance
of private property vegetation and trees by private property owners, if the vegetation encroaches on the City's right-ofway.
Research started. Anticipated completion by Fall 2026.
City Manager's Office:
Public Works:
Planning: and
City Attorney's Office
7 Shores Park Master Plan
Coordinate with a consultant to develop three master plan alternatives for Shores Park. The three draft designs will then be refined to a final park Master Plan, which will include cost estimates for the future construction of the park and community building.
Estimated completion by Fall 2026. City Manager's Office TIER 2: Important Items that Support City Operations/Values (Not Mandated/Legally Required) Reference
No. Item Name Description Status Department(s)
TIER 2: Important Items that Support City Operations/Values (Not Mandated/Legally Required) 8 Housing Acceleration
Program (HAP) Grant
Funding - Cycle 2
SANDAG awarded Cycle 2 HAP grant funding (October
2023) for implementation of the City's Housing Element
including $1.5 million capital funds for Fairgrounds
Housing project and $181,000 planning funds for
Objective Design Standards and 4A/4B Supportive
Housing Ordinance. Funding applies to work starting
January 1, 2024. Timing to expend HAP grant funds was
extended from March 2026 to August 2026.
In-process through September 2026 to complete quarterly reporting. Planning
9 Tree, Scenic Views, and
Sunlight (TSVS) Hedge
Regulations
Prepare and process Ordinance. Hedge regulations were
"decoupled" from the TSVS Ordinance and will be
processed separately.
Anticipated to start in FY2027. Planning
10 Comprehensive Tree
Policy and Regulatory
Standards Update
Revise existing City tree policies for both public and
private trees, with an overall goal of protecting and
enhancing the City’s urban forest tree canopy while
managing the City’s wildfire risk.
This project will be deferred to align with the State's future implementation of "Zone Zero" defensible space
regulations, anticipated in mid 2026.
Planning
11 Amend Sand Compatibility
Opportunistic Use
Program (SCOUP) Permits
with Resource Agencies to
Account for Change in San
Dieguito Lagoon
Conditions
Prepare and process permit applications with United
States Army Corps of Engineers (USACE) and Regional
Water Quality Control Board (RWQCB) to amend the
existing SCOUP permits to allow the City to accept beach quality sand for beach nourishment when available. The
permit issued by USACE in July 2024 impacted the
feasibility of City implementation due to the restrictive limits on sediment quantities imposed and USACE's large volume sand placement in Encinitas and Solana Beach in
2024.
In process and will be further evaluated for feasibility due to USACE project Planning
12 San Dieguito Lagoon
Shoreline Protection
Planning Project
(Levee/Trails) and
Implementation of State
Parks Grant Funding
City and San Dieguito River Park JPA are coordinating on a joint project to develop living levees and trails along the north and south banks of the San Dieguito River. State
Parks awarded $500,000 grant funding to City and $1.3
million to the SDRP JPA. The City executed task orders
with Dudek ($500,000) and kicked off work in January
2025 to complete environmental, engineering, and
permitting task orders. A MOU with SDRP JPA will be
executed to facilitate completion of additional task orders using grant funds through June 2027. This effort
correlates to new City CIP project.
In-process through June 2027. Planning
Public Works
13 Review and Update the
Carmel Valley Precise Plan
(CVPP)
Comprehensive review and potential updates to the
CVPP, through the appropriate process (entitlements,
environmental review, public participation, etc.), as may be recommended by staff/City Attorney's office.
The City Attorney initiated the review of the CVPP. Should the CVPP need to be updated, a completion date of Fall
2026 is anticipated.
Planning
City Attorney
Reference
No. Item Name Description Status Department(s)
TIER 2: Important Items that Support City Operations/Values (Not Mandated/Legally Required) 14 Evaluate updating Del Mar
Municipal Code Chapter
24.70 (lot line adjustments)
Evaluate updating lot line adjustment/lot consolidation regulations, with consideration of requiring a lot line adjustment parcel map for any lot line adjustments or lot consolidation. Update would require processing a Zone
Code Amendment and preparing an Ordinance; Planning
Commission recommendation and City Council
introduction and adoption of Ordinance.
Estimated Completion in December 2026 Planning and
Engineering
15 General Plan Amendment,
Zoning Code Amendment,
Local Coastal Program
Amendment, and Rezone
of Vacant Land (6th Cycle
Housing Element Program
1E) (New)
Prepare and process amendments and rezone of vacant
land on Bluff and South Stratford Properties to 20-25
du/ac by right via overlay zone to create capacity for at least 54 lower income units. Will require Council and
Coastal Commission approval actions.
Anticipated to start in FY2027 Planning
16 Update to CEQA
Guidelines (New)
Staff initiated item based on legislative change requiring an update to the California Environmental Quality Act
(CEQA) Guidelines to identify the standard mitigation,
monitoring, and reporting protocols that the City applies to development projects that are required to be processed
through a ministerial permit decision process. Prepare and process a Resolution.
Anticipated to start in FY2027 Planning
17 San Dieguito Drive
Improvements
Construction of San Dieguito Drive between Racetrack
View Drive and Oribia Road as part of an approved
assessment district.
Construction anticipated after Work Zone 1 of UUD X1A
(Crest Canyon) in FY 2026-2027, with a likely start of
Summer 2026.
Public Works
City Manager's Office
Planning
18 29th Street Seawall and
Beach Access
Design and permit the northern half of the sea wall and beach access.
Conceptual design and cost estimate completed FY 2025-
2026. Design and permitting is targeted to begin CY 2026 and construction start in FY2026-2027.
Public Works
19 Minor Bridge Repairs
Critical bridge infrastructure repairs recommended by
Caltrans as a result of annual inspection; concrete repairs at 3 of the City's bridges (Via de la Valle, San Dieguito River at Jimmy Durante Blvd, and Camino del Mar at
Jimmy Durante Blvd).
Project will need to be designed and put out for public bid.
NCTD permit required for two railroad overhead bridges. Public Works Reference
No. Item Name Description Status Department(s)
TIER 2: Important Items that Support City Operations/Values (Not Mandated/Legally Required) 20 Stratford Court South
Pavement Improvements
Paving improvements for the Stratford Court South area
following the undergrounding project. Grind & overlay
improvements for low PCI (Pavement Condition Index)
streets of Stratford Court from 4th St to 12th St, Little Orphan Alley, and Melanie Way. Pavement sealing
application for other streets within the Stratford Court South UUD 1A District with trench lines.
Construction targeted after UUD 1A (Stratford Ct South) in FY 2026-2027. Public Works
21 Crest Canyon Pavement
Improvements
Paving Improvements for the Crest Canyon area following the undergrounding project. Grind & overlay
improvements for portions of low PCI (Pavement
Condition Index) streets of Zuni Dr, Avenida Primavera, and Serpentine Dr. Pavement sealing application for Crest Road and adjacent streets with trench lines.
Construction targeted after UUD X1A (Crest Canyon) end
in FY 2027-2028. Public Works
22 Stratford Court North
Pavement Improvements
(New)
Paving improvements for the Stratford Court North area
following the undergrounding project. Grind & overlay
improvements for low PCI (Pavement Condition Index)
streets and pavement sealing application for other streets within the Stratford Court North UUD 1B District with
trench lines.
Construction targeted after UUD 1B (Stratford Ct North) in FY 2027-2028. Public Works
23 City Hall IPE Wood
Refinishing Project (New)
The project requires power washing, sanding, cleaning,
staining, and sealing of all the IPE wood at the Del Mar Civic Center located at 1050 Camino del Mar.
Project to be bid and completed in FY 2026-27. Public Works 24 Coast Boulevard
Stormwater Analysis and
Infrastructure Alternatives
Study (New)
Historically, the Coast Boulevard area from 17th Street to 22nd Street has been subject to heavy flooding. A
technical study with conceptual cost estimates would be completed that analyzes existing hydrologic/hydraulic
conditions, summarizes environmental impacts, and
develops alternatives to mitigate stormwater drainage
issues.
Study to be completed during first half of FY 2026-27. Public Works 25 Speed Survey Segements
In FY25-26, Council directed staff to work with the Traffic and Parking Advisory Committee (TPAC) to identify
roadway segements for speed surveys.
On December 2, 2025, TPAC identified the following
speed survey segements: Jimmy Durante Blvd. from Via
de La Valle to the San Dieguito Bridge; Jimmy Durante
Blvd. between the San Dieguito Bridge and Camino del
Mar; and Camino del Mar from 4th Street to Carmel Valley Road. The speed survey results will be presented to
TPAC for recommendation and then to Council for
considerattion.
Public Works
Reference
No. Item Name Description Status Department(s)
1 Amend City Appeals
Procedure Consider
Modifications to DMMC
Evaluate options to amend the City's appeals
procedure and provide recommendations and
options to the City Council for consideration to be
started in FY 25-26 or thereafter as practical
without delaying of deferring other items.
Appeals procedures used by other agencies in the County are currently being researched. Staff will work with the Attorney's Office and Planning Department to review and develop potential modifications and will bring a recommendation to the City Council for consideration. Adoption of revised appeal procedures will require a public hearing and ordinance amending the Del Mar Municipal Code.
Administrative Services
2 Citywide Plaque Policy
Development of a City plaque policy that is
consistent with the City's branding guide for
consideration by the City Council.
Work will begin in Spring 2026. The item is on the proposed Parks & Recreation Committee Work Plan for FY2026-27. Staff will draft the policy and present the item for Parks & Recreation Committee review and feedback prior to City Council consideration.
City Manager's Office
Planning
Public Works
3 Solar Capacity on City
Owned property
Evaluate the possibility of increasing the City’s
solar capacity on City owned property.
Work was initiated in FY2025-26. Staff have identified specific City facilities that have the capacity for solar. The Sustainability Advisory Committee (SAC) is supporting staff in researching funding prospects to support City electrification and the expansion of solar on City facilities. Staff is monitoring opportunities for funding through the Clean Energy Alliance and the Caifornia Energy Commission Equitable Decarbonization Program. Staff is also working with Public Works to understand the type of solar systems that are needed.
City Manager's Office
4 Adopt-a-Spot Program
Update (New)
Complete important updates to the City's Adopt-aSpot Program to create a formalized program policy, application, and agreement process.
This item is on the proposed Parks & Recreation Committee Work Plan for FY2026-27. City Manager's Office
5 Leafblower Prohibition
Ordinance Update
(New)
Adopt an ordinance amending the City’s Municipal
Code to expressly include battery-operated leaf
blowers within the existing leaf blower prohibition.
Not started. Estimated by the end of 2026.
City Manager's Office
Planning
City Attorney's Office
6 Turn the Design
Review Guidelines into
Design Review
Ordinances
Development of an Ordinance to codify the City's
Design Review Guidelines in the Del Mar
Municipal Code. As part of the 2025 Goal setting
process, Council directed to add this item to Tier 2
to be started in FY 25-26 or thereafter as practical
without delaying or deferring other items.
Project is on-hold due to lack of Planning staff capacity to work on this program. Staff recommendation would be to move to FY2027- 2028.
Planning
TIER 3: Non-Essential Work Plan Items That Could be Deferred or Eliminated (Not Required) Reference
No. Item Name Description Status Department(s)
TIER 3: Non-Essential Work Plan Items That Could be Deferred or Eliminated (Not Required) 7 Major Arterial Median
Improvements
Design of drought tolerant landscaping and
irrigation efficiency enhancements along major
arterial median segments, currently planned for
four locations as Phase I of project.
CDM 15th Street to San Dieguito River Bridge;
Jimmy Durante Blvd/Via De La Valle Triangle;
Jimmy Durante Roundabout to CDM Merge; and
CDM 4th to 9th Street.
Conceptual design completed in FY 2025-2026. Final design is anticipated to start CY 2026 with first phase of construction FY2027- 2028. Work will continue on this project as time permits based on CIP project management staff capacity.
Public Works
8 City Facilities Gas
Appliances Inventory
Development of a policy that prioritizes the
purchase of electric appliances when possible for
recommendation by Sustainability Advisory
Committee and consideration by the City Council.
Work was intiated in FY2025-26. Staff has identified the appliances for the inventory.
Public Works
City Manager's Office
10 Public Works Facility
Improvements (New)
Replace antiquated facilities with new office
modular building, Locker Building, Warehouse,
Workshop, Wash Rack, and Equipment
Enclosure.
Schedule Coincides with San Dieguito Lagoon Shoreline Protection Project which will require partial demolition of Del Mar Public Works Facility.
Public Works
City Manager's Office
Reference No. Item Name Description Status Department(s) 1 Annual Wastewater System
Priority Improvements
Wastewater System repairs and
improvements.
In FY 2025-2026, grant application,
federal environmental reviews, and work
plan were prepared for the USEPAfunded wastewater and storm drain improvements project (FY24 Community
Grants). In FY 2026-2027, design to be
completed.
Public Works
2 Annual Storm Drain System
Priority Improvement
Replace storm drain facilities that have
surpassed their useful life.
In FY 2025-2026, grant application,
federal environmental reviews, and work
plan were prepared for the USEPAfunded wastewater and storm drain improvements project. In FY 2026-2027,
design to be completed.
Public Works
3 Annual Bike Route Repairs
Repair bike lanes on major arterials;
CDM, JDB, Via de la Valle, Carmel
Valley Road.
In FY 2026-2027, work will be completed
under the scheduled Pavement
Management Program.
Public Works
4 Annual Pavement
Management Program
Expanded annual pavement program to
perform roadway repairs to major
arterials and residential streets.
In FY 2026-2027, proposed pavement
improvements to be completed in various
areas around the City, as described in
Pavement Management Program Update
(Attachment F).
Public Works
5 Annual Small Area
Pavement Repairs
Citywide small area asphalt
paving/repairs.
Occurs once or twice per year depending
on repair needs. Public Works
6 Major Facility Repairs
Essential building (City Hall, Library,
Public Works, Community Services,
etc.) repairs including exterior,
doors/windows, electrical, plumbing,
HVAC, fire and security systems.
In FY 2026-2027 staff will complete
repairs as may be needed to essential
facilities, such as public restrooms,
Council Chambers, Civic Center,
Powerhouse, etc.
Public Works
Significant Annual Public Works Maintence/Repair Projects FY 2026-27 City Council Goals & Priorities Workshop
List of Council-Identified Proposed Work Plan Items
1) Council Health Insurance. Discuss City-sponsored health insurance coverage for Councilmembers on a go-forward basis.
2) Additional Maintenance Projects. Discuss repainting or refurbishing metal railings on Camino del Mar near dog beach bridge and Powerhouse Park lawn maintenance. 3) Standardization of Encroachment Permit Review. Discuss options for a standardized review of encroachments that would be based on a holistic approach (Exhibit 1).
Council initiated item: Holistic treatment of encroachments RATIONALE:
• Spreads message about permits needed for new construction/frontage improvements
• Recognizes reality of city’s present-day streets
• Saves staff time effort and money to work up EPs
• Moves city away from neighbors complaining anonymously on neighbors. • Removes arbitrary and capricious handling of EPs - consistency • Encourages people to properly keep up their property
CATEGORY 1. Preexisting encroachment
CATEGORY 2. New encroachments
CATEGORY 3. Safety issues
• Some more impactful than others.
• Some create dangerous conditions
System would need to take acct of all of those.
REGIME:
• Set up standard protocol.
• Here are preapproval processes but exclude safety risk or spike fence. • Determine all possibilities.
• People will game loopholes
• Free pass protocol.
Street survey will identify encroachments and put them into one of the three above buckets.
Focus on EPs on frontage.
Exclude side yard or rear yards. Designed for road ROWs Standard rule of thumb. 60 ft Row
• E.g. Crest road is probably 60 feet but 20 25 feet of pavement
SUMMARY OF CITY OF DEL MAR DEPARTMENT OPERATIONS
CITY MANAGER’S OFFICE
• Manage all City departments, operations, and City Council work plan • Provide City Council support
• Manage the City Council Goals and Priorities, including the goal setting process and progress toward completion
• Provide Citywide budget review and monitoring
• Manage the City’s public information function, including citywide communications, communications consultant contract, social media, weekly electronic newsletter, and City response to media requests
• Manage legislative advocacy, including coordination with legislative affairs consultant, meeting with elected representatives, preparation of state and federal funding requests, preparation of advocacy letters, and development of the City Council Legislative Policy Guidelines
• Customer service for sensitive and complex issues
• Public safety management and oversight
o Manage Sheriff’s contract
o Manage Fire Department and issues related to CSA-17
o Emergency management coordination
• Lead City’s emergency preparedness efforts (e.g., Emergency Operations Center, Fuel Reduction Program, Multijurisdictional Hazard Mitigation Plan update, Emergency Operations Plan, etc.)
• Oversee legal requests and City’s legal services contract • Serve as a liaison to Del Mar Fairgrounds (traffic/noise issues, peak activities, policy matters)
• Intergovernmental coordination with other jurisdictions and agencies, such as SANDAG, NCTD, San Dieguito River Park JPA, California Coastal Commission, the City of San Diego, County of San Diego, and League of California Cities • Coordination of efforts related to homelessness
• Provide project support to departments on an as-needed basis • Manage City’s real estate, telecommunication, and cable franchise leases • Coordination efforts for major special events, such as Breeders’ Cup, opening day at the Del Mar Racetrack, and peak summer activities
• Provide staff support to:
o Sustainability Advisory Committee
o Lagoon Committee
o Parks and Recreation Committee
o Del Mar Village Association
o Del Mar Non-Profits
o Finance Committee
o Measure Q Citizen Oversight Committee
o Undergrounding Program Advisory Committee
o Shores Park Master Plan Ad-Hoc Advisory Committee
• Implement the City’s Climate Action Plan and sustainability initiatives • Maintain “Go Green Del Mar” and other project webpages • Manage the City’s solid waste franchise agreement and compliance with organics recycling requirements (SB 1383)
• Staff support for the Regional Solid Waste Association • Administer the City’s Public Furniture Donation Program • Final review and approval of all Encroachment Permits Pg. 2 of 7
• Review and finalize all City Council agenda reports
• Provide management oversight of City policy and procedures manuals • Provide organizational training and coaching to staff • Oversee and manage various City grants and donations
• Manage and administer the Community Funding program
ADMINISTRATIVE SERVICES DEPARTMENT
Finance
• Water Utility Billing (new accounts/shut offs, bi-monthly billing, customer service) • Business License/Permitting Programs (issue new licenses, process annual renewals; taxicab permits, nuisance alarm violations; massage permits) • Operating and Capital Budget Development and Administration (Two-year budget process; Mid-Year budget process; second year Budget Update) • Capital Improvements Program and Special Projects financial management • Accounting and Control Functions (General Ledger management, asset management, accounts payable; accounts receivable; journal entries, payroll administration) • Year-End Audit and Annual Comprehensive Financial Report (single audits; Transnet audit)
• Financial and Compliance Reporting (annual compliance reporting, annual street report, local government compensation reporting, other required annual tax compliance reports) • Financial records management
• Master fee schedule maintenance and updates
• Treasury Function (quarterly reporting of cash and investments; cash management; investment coordination)
• Revenue Collection and Monitoring (collection, recording, and reporting of taxes, fines, fees, and penalties)
• Purchasing and Procurement (purchasing policy compliance, Purchase Order approvals) • Grant Accounting (tracking grant revenues and expenses for reimbursement) • Debt Management (debt analysis and issuance coordination; tracking and reporting of debt service obligations)
• Financial Policies and Planning
• Financial studies and special projects (user fees, cost allocation plan, forecasting, ERP implementation)
City Clerk
• Processing of Public Record Act (PRA) requests (Approximately 350 annually) • Agenda/Minutes production for City Council and City Committees (annual Council meeting schedule; Agenda packet production, posting, distribution; production of meeting minutes)
• Legal Advertisements/Public Noticing
• City Committee/Board/Commissions (conduct committee recruitments annually; onboarding of new members; committee roster and webpage management; facilitate Council local appointment process; maintain and update policies) • Form 700 Conflict of Interest Filing and ethics training compliance • Records Management (hardcopy and electronic files)
• Process Recorded Documents
• Process Municipal Code Amendments
• Contract Administration (maintain standard templates; contract review; routing; and maintain contract tracking database)
• Processing and maintaining vendors’ certificates of insurance required by contracts Pg. 3 of 7
• Municipal Election Activities (coordination with County Registrar of Voters (ROV); preparation of necessary election resolutions; ballot measure processing; candidate filings and campaign reporting; website updates/public information; swearing in of new Councilmembers)
• Management of hybrid public meetings for City Council and advisory committees in partnership with IT
• Biannual review and update of the City’s Conflict of Interest Code • Maintain Public Records Act request, City Council, agenda, committee, and public meeting calendar webpages.
Human Resources
• Employee Recruitments/New Hire Processing and onboarding: Full-Time and Part-Time, Seasonal (it should be noted that the seasonal hiring process is a significant annual undertaking due to the large number of seasonal staff)
• Personnel Matters (investigate complaints; discipline; counseling, etc.) • Negotiation of Labor Agreements
• Employee Benefits (Coordinate annual open enrollment process in June; provide yearround assistance to new hires and existing employees) • Processing Workers Compensation; Short-Term Disability; Family Medical Leave; Pregnancy Disability; Unemployment claims
• Administration of City Worker’s Compensation Program (claims processing and tracking; supervisor training; coordination with W/C insurance provider) • Employment and Salary Verifications as requested by third parties • Oversee City’s Department of Transportation (DOT) Class B Drivers Program • Coordinate and Track Employee trainings, including bi-annual harassment training • Wellness and Illness/Injury Prevention for Employees
• Administer the City’s Public Agency Retirement Services (PARS) program for part-time employees
• Process Public Employee Retirement System (PERS) and 457(b) Plan enrollments and employee changes
• Ongoing review and processing of necessary updates to job descriptions and compensation research
• Process payroll changes in coordination with Finance
• Tracking/Processing of Evaluations (prepare evaluation templates; track evaluations; work with departments on timely completion)
• Ensure personnel practices are compliant with state/federal law and review and update policies and procedures as needed
• Maintain Human Resources webpage and job postings, and internal SharePoint page for employees
• Annual review and update of personnel and hew hire forms to ensure compliance with federal and state requirements
Risk Management
• Claims Tracking & Processing (Claim review; coordination with City Third Party Administrator (TPA); issue letters; track status; notification to self-insurance provider, etc.) • Personal injury/property damages claims/lawsuits research, responses, depositions, litigation support
• Track all City related litigation; coordinate with the City Attorney’s office; compile litigation discovery; and represent the City at mediation.
• Coordinate insurance coverage through the City’s self-insurance Joint Powers Authority provider PRISM Excess Insurance Authority (EIA)
• Facilitate risk management training and implement best practices Pg. 4 of 7
• Annual and quarterly reporting in partnership with TPA Information Technology
• Provide end-user technical assistance and support for issues related to computer systems, software, and hardware
• Administer City software systems (TRAKIT permitting system; EDMS document management system; Eden financial system; e electronic timecard system; utility billing system; etc.)
• Provide support for City-wide Voice-over-IP phone system including troubleshooting and configuration of phones and voicemail accounts
• Install, modify, and repair computer hardware and software • Administer and support City’s email system and Office 365 environment (monitor and manage email security and spam filtering; create user accounts; reset passwords; and configure email accounts)
• Support and maintain SharePoint City Intranet
• Resolve technical problems with Local Area Networks (LAN), Wide Area Networks (WAN) including internet and point-to-point fiber connectivity. • Configure, manage, and install network printers and other network devices such as wireless access points and security cameras; administer the door access control system • Maintain the City’s GIS system and parcel database
• Provide support and administration for the City website • Conduct technology research and participate in professional organizations to stay current with technology trends and best practices
• Monitor, administer, maintain, and improve the cyber-security infrastructure • System administration, patches, and upgrades to servers, desktops, and software. • Administer data backups and offsite tape storage
• IT Project management and collaboration with other departments for special project work. • Develop and implement IT best practices, policies and procedures • Maintain inventory of hardware and software; manage maintenance contracts and software licensing as needed.
• A/V systems and meeting support; load presentations, assist end users and the public using conference rooms and Town Hall A/V
• Provide administration for SQL Server and database availability and backups • Assist with administration of Public Works Scada infrastructure (monitor of water and sewer system)
• IT Training (Online training for Microsoft technologies, cyber-security, and other relevant topics as time. Provide in-house training on software systems • Administration of Del Mar Television (DMTV) contract
COMMUNITY SERVICES DEPARTMENT
• Manage Lifeguard, Parking, Beach and Community Patrol, and Powerhouse/Open Space divisions
• Perform ocean, cliff, SCUBA, and swiftwater rescues throughout the City and via mutual aid throughout the County
• Provide emergency care and first aid in City parks, beach, and assist Fire Department in residential and commercial zones as needed
• Lifeguard Academy – Coordinate and train new lifeguard staff for over 100 hours of training each May
• Operate the City’s Junior Lifeguard Program that serves 230 children ages 9-15 annually • Perform wildlife rescue services in coordination with Sea World, Wildlife Assist, and San Diego Humane Society
Pg. 5 of 7
• Manage 800 MHz radio communications purchasing and oversight • Provide staff with training and certification in CPR, first aid, cliff rescue, and swiftwater rescue
• Provide quarterly beach and bluff overhead drone photo and video documentation, and as needed for other City departments or efforts
• Enforce municipal code on beach, parks, and throughout the City • Manage parking program throughout the City
• Enforce City, County, and State parking laws
• Install, maintain, service, and perform collections from City’s paid parking meters • Oversee planning, permitting and staff for special events at the City’s public beach, parks, Powerhouse Community Center, and Civic Center
• Provide supplemental public enforcement patrol services throughout the City • Manage surf and volleyball camp operators
• Co-manage operation of City loader and beach cleaner to maintain public beach access and protect public property
• Clean and maintain public restrooms at the Beach Safety Center and Powerhouse Community Center
• Maintain signage on public beach and parks
• City Committees – Quarterly staff representation on Traffic and Parking Advisory Committee and Parks and Recreation Committee
• Represent City in regional lifeguard and enforcement efforts – Lifeguard staff contribute to regional efforts through membership and coordination with various agencies and organizations
PLANNING & COMMUNITY DEVELOPMENT DEPARTMENT
• Process discretionary permits for conformance with the Design Review Ordinance, Zoning, Local Coastal Program, Community Plan, and CEQA • Provide customer service at the public counter, emails, phone, and website • Staff public meetings including the Design Review Board, Planning Commission, City Council and support to several committees and outside agencies • Administer the Citizens’ Participation Program (CPP) – part of Design Review • Provide Code Enforcement services
• Process Encroachment permits for proposed uses in public rights-of-way • Administer permitting for development in the floodplain • Provide processing and environmental support for City Capital Improvement Projects • Manage the City’s Building Services contract – plan check, permits, and inspections • Manage the City’s Clean Water program – compliance, education, noticing, reporting • Manage the City’s permit database and Department website content • Continue to implement digital application submittal and digital archiving of public records • Continue purging records in accordance with the City’s record retention policy • Prepare Community Plan Amendments/Municipal Code Amendments to ensure compliance with federal and state laws
• Provide research and retrieval support for development-related Public Records Act (PRA) requests
• Support Citywide fee schedule updates for Planning-related fees • Prepare updates to Council on Planning Dept status and projects • Manage permits/amendments of Specific Plans including Hotel SP and Plaza SP • Complete parking management implementation follow up/monitoring reports at 1201 CDM building and Del Mar Plaza
Pg. 6 of 7
• Prepare Housing Element Annual Progress Reports and ongoing actions related to housing resources and housing assistance
• Prepare public info materials (i.e. web updates and FAQs) for Accessory Dwelling Units • Manage and provide support to the City’s Short-Term Rental Program • Develop annual/bi-annual reporting to external agencies on various items • Attend monthly coordination meetings with California Coastal Commission, SANDAG, NCTD
• Work in partnership with Public Works to provide ongoing support of Capital Improvement Projects, including processing entitlements and coordinating environmental review
PUBLIC WORKS & ENGINEERING DEPARTMENT
• Emergency critical infrastructure response preparations, including potable water storage, back-up generators, and emergency response contractors
• Wastewater system State Water Resource Control Board permit compliance, including management plan, capital improvements, maintenance, reporting, and emergency responses
• Water system Regional Water Quality Control Board / Department of Environmental Health Water System Drinking Water Operational permit compliance, including analytical sampling, capital improvements, maintenance, reporting, and emergency responses • Storm drain system compliance with the City’s San Diego Regional Water Quality Control Board Municipal Stormwater Permit, including analytical sampling, capital improvements, maintenance, reporting, and emergency responses
• Water/Wastewater treatment/transportation contract administration, invoicing, and operations coordination with San Diego Regional Wastewater Commission, City of San Diego, San Diego County Water Authority, City of Solana Beach, Del Mar Fairgrounds, and the San Elijo JPA
• Developmental Permit review, including Encroachment Permits, Design Review Board, and Administrative Design Reviews.
• City representation in assigned regional organizations, including SDCWA General manager’s meeting and Metro Wastewater JPA Committee
• Oversight and administration of approximately 35 specialty maintenance contracts, including water testing, street sweeping, asphalt repairs, solar systems, landscape maintenance, elevators, security systems, and pipeline cleaning • Oversight and administration of approximately 20 as-needed professional services contracts, including municipal/traffic/design/geotechnical engineering, construction management, architectural, and telemetry services
• Submittal of approximately 50 annual / quarterly / monthly regulatory / compliance / certification reports, including Environmental Protection Agency (drinking water), CALTRANS (Federal Highway Bridge Program), California Water Boards, County Department of Environmental Health, and the San Diego Air Pollution Control District • Capital Improvement Program Management (CIP, wastewater, water, storm drain, undergrounding, paving, developmental projects); planning, design, construction, expenditure rate setting, budgeting and budget adjustments • CALTRANS / Federal Highway Bridge Program compliance
• Annual Bridge Cathodic Protection System Monitoring
• Work order management for streets, parks, beaches, sidewalks, landscaping, and tree repairs
• Citywide and Beach maintenance operations for trash/recycle receptacle emptying, abandoned property disposal, doggy bag dispenser replenishment Pg. 7 of 7
• Facility Maintenance and Repairs for all City Buildings including Community Connections Building and Del Mar Library. Administer Building Maintenance Contracts (approximately 20) for fire alarms, elevators, HVAC, Solar, etc.
• Janitorial services oversight and coverage at all city parks, beaches, and buildings • Public right-of-way permits review and approval and review of City permits and conditions for public and private development projects
• Review and approval of private property discretionary applications and final building permits for conformance with engineering conditions and infrastructure upgrades with proposed improvements
• Annual Storm Drain System cleaning
• Storm Water preparation activities including sandbags and inlet clearing • Storm Water response activities including street sweeping and tree removals • Storm Drain Inlet Trash Capture Devise Program
• Water meter upgrades and replacements, monthly billing readings, and turn on and turn off requests, construction water meter billing
• Water Valve exercising and replacement program
• Annual Sewer System Cleaning and quarterly “Hot Spot” cleaning • Daily sewer pump station monitoring, operation, and maintenance • Annual sewer pump station wet well cleaning
• Administer Fats Oil and Grease Program with local restaurants • Tree Maintenance Program Administration (approximately 1,500 City trees) • Citywide Landscape Maintenance contract oversight at City parks, street plantings, open space, and beaches.
• Recreational repairs and maintenance at City basketball and tennis courts. • Periodic bike lane and road edge, public pathways, and public easements vegetation clearing
• Minor and major roadway surface repairs
• Sidewalk Safety Program including Trip Hazard Prevention Plan • Citywide Sidewalk sand and debris cleaning
• Graffiti and sticker abatement
• Traffic signal equipment repairs and maintenance; monthly streetlight checks • Traffic signs and delineator repairs/replacements; traffic striping repairs • Street Sign Retroreflectivity Replacement Program (safety signs complete, street signs ongoing)
• Providing staff support to Traffic Parking Advisory Committee (TPAC), Undergrounding Program Advisory Committee (UPAC), and Parks & Recreation Committee as staff liaisons
• Traffic Engineering oversight including Speed Surveys and Posted Speed Limits establishment
• Administer Dead Animal Removal Contract
• San Dieguito River Valley Conservancy liaison and mitigation areas workshops • Bark Beetle Reduction Program implementation
• Sand Grading Operations for Beach Access and Powerhouse Park protection • Beach Raking/Cleaning Operations
• City Facilities Cyclic Maintenance Program development • Providing information to Administrative Services related to Public Records Act responses • Fleet Inventory, SMOG certifications, and vehicle maintenance • Equipment Maintenance and Repair/Replacement Program Budgeting • Manage Supervisory Control and Data Acquisition (SCADA) equipment and software to electronically monitor water and wastewater systems
Pg. 8 of 7
• Full time phone coverage and email inquiries / resident responses • Grant research and applications for public works related projects • City of Del Mar’s Public Tree Policy Manual update with City Arborist • Public Works Fees Study and updates
• Operational and capital expenses invoicing
• Dig Alert mark-out requests
• Bench donation and replacement program installations and replacements • Playground maintenance/repairs including annual Tot Lot inspection and playground certification
• Monitor and comply with changing infrastructure regulatory regulations • Stormwater/Wastewater/Water system master planning
• Preliminary Capital Improvement Project planning feasibility studies • Sanitary Sewer Management Plan (SSMP) Audits and Updates • Expanded State Issued California Drought Response Requirements Attachment E
Camino del Mar Bridge Replacement – Construction Delivery Schedule Update During the City Council meeting on November 17, 2025, staff shared that the anticipated construction duration would be extending from an anticipated 36 months at the 10% design phase to 50 months at the 90% design phase, which was an increase of 14 months. The updated project timing was determined when the constructability review was completed and more details of the specific activities became available. However, for the purpose of an apples-to-apples comparison, non-construction administrative activities that occur prior to and after construction have been removed. Therefore, the difference in anticipated timing for construction activities is actually 6 months, not the 14 months previously reported. Details on the original assumptions and justifications for the extension is summarized herein.
The 36-month construction duration was estimated during the environmental documentation preparation period in 2022 based on available information at the time. The project was at 10% design, before resource agency permitting, utility coordination, or final design was initiated. The original estimate and the current anticipated construction duration are summarized in the table below.
Activity
2022
Construction
Duration
Estimate
(Calendar
Months)
2025
Update
(Calendar
Months)
Change
NOTICE TO PROCEED
Stage 1 - Site Prep 3 1 -2 mos
Stage 2 - East Side Demo and Reconstruction 14 22 +8 mos Stage 3 - West side Demo and Reconstruction 14 17 +3 mos Stage 4 - Bridge Median Improvements 3 1 -2 mos
Stage 5 - Final Improvements and Demobilization 2 1 -1 mos Totals 36 42 6 mos
In late 2025, the project’s anticipated construction duration was adjusted since the environmental review, resource agency permitting, final design, and independent constructability review were all completed. The revised schedule reflects more detailed activity durations for fully defined design components, permitting requirements, temporary utility relocating, staging, sequencing, and construction requirements that were not detailed in pre-design phase.
Key changes based on constructability review:
Stage 2 - constructability review resulted in 8-month adjustment (longer) in east side bridge reconstruction due to detailed assessment of temporary trestle installation and Attachment E
utility staging/installations, including more recent input from SoCalGas and sewer forcemain active bypass, relocation, and reinstallation. Stage 3 - constructability review resulted in 3-month adjustment (longer) in west side bridge construction due to detailed assessment of temporary trestle installation and utility staging/installations, including more recent input from SDG&E.
Anticipated Project Delivery Dates
The current overall project schedule of activities from bidding through project close out is summarized in the table below. Please note that the construction impacts to the public will occur between April 2027 and September 2030 (42 months).
Description of Project Activities Start End
Duration
(months)
Bid/Award Phase July 2026 December 2026
Notice to Proceed January 2027
Admin (no construction) February 2027 March 2027 2
Stage 1 – Site Prep/Median Removal April 2027 April 2027 1 Stage 2 – East Side Demo and Reconstruction May 2027 February 2029 22 Stage 3 – West Side Demo and Reconstruction March 2029 July 2030 17 Stage 4 – Bridge Median Improvements
(closure of the median to unite the bridge) August 2030 August 2030 1 Stage 5 – Final Improvements and Demobilization September 2030 September 2030 1 Closeout (no construction) October 2030 March 2031 6
Total 50
PAVEMENT MANAGEMENT PROGRAM
FUNDING SUMMARY
Adopted
FY26
Adopted
FY27 FY28 FY29
General Fund 660,592 $ 627,750 $ 463,750 $ 460,750 $
SB1 (RMRA) 307,150 $ 100,000 $ 100,000 $ 100,000 $
SLFRF (Federal COVID-19 Response) 162,310 $ - $ - $ - $ Measure Q 136,500 $ 47,250 $ 47,250 $ 47,250 $
TransNet (RTIP) 649,000 $ 135,000 $ 139,000 $ 142,000 $ RTCIP (JDB/VDLV) 36,000 $ - $ - $ - $
ANNUAL TOTAL 1,951,552 $ 910,000 $ 750,000 $ 750,000 $
Anticipated Carryover 250,660 $
Returned to Capital Reserve during Mid-Year Budget Adjustment 1,750,000 $ Budget Available 2,910,660 $
PROJECTS FY26 FY27 FY28 FY29
Jimmy Durante Blvd 1,700,892 $ - $ - $ - $
Stratford Court South (areas within UUD 1A) - $ 700,000 $ - $ - $ CDM from 4th to 9th (both directions) - $ 850,000 $ - $ - $ PMP Identified Roads with lowest PCIs - $ 985,660 $ - $ - $ Crest Canyon (areas within UUD X1A) + low PCI streets - $ - $ 750,000 $ - $ Stratford Court North (areas within UUD 1B) + low PCI streets - $ - $ - $ 750,000 $ Supplemental Funding - San Dieguito Drive Replacement - $ 300,000 $ - $ - $ Second small area pavement project - $ 75,000 $ - $ - $ $ 2,910,660 1,700,892 $ 750,000 $ 750,000 $
Pavement Management Program List of Projects
Updated March 2026
Name From To PCI CIP PROJECT
COMPLETED
CAMINO DEL MAR COURT ST JIMMY DURANTE BLVD 54 FY24 Completed (2023 W-WW-P-SD Project) OCEAN VIEW AVE HIDDEN PINES RD PINE NEEDLES DR 56 FY24 Completed (2023 W-WW-P-SD Project) CAMINO DEL MAR JIMMY DURANTE BLVD COURT ST 77 FY24 Completed (2023 W-WW-P-SD Project) ALLEY N/O BELLAIRE ST BELLAIRE ST CDS 60 FY24 Completed (2023 W-WW-P-SD Project) - SLURRY SEAL BELLAIRE ST SEA VIEW AVE ZAPO ST 78 FY24 Completed (2023 W-WW-P-SD Project) - SLURRY SEAL HOSKA ALLEY HOSKA DR END OF ALLEY NEAR CAMINO DEL MAR - FY25 Completed Hoska Alley Storm Drain Improvements JIMMY DURANTE BLVD FAIR GROUNDS SOUTH ENTRANCE FAIR GROUNDS MAIN ENTRANCE 49 FY26 JDB Pavement JIMMY DURANTE BLVD VIA DE LA VALLE FAIR GROUNDS MAIN ENTRANCE 50 FY26 JDB Pavement JIMMY DURANTE BLVD FAIR GROUNDS MAIN ENTRANCE VIA DE LA VALLE 50 FY26 JDB Pavement JIMMY DURANTE BLVD FAIR GROUNDS MAIN ENTRANCE FAIR GROUNDS SOUTH ENTRANCE 62 FY26 JDB Pavement PLANNED FOR FY27
CAMINO DEL MAR 9TH ST 4TH ST 70 FY27 - CDM from 4th to 9th CAMINO DEL MAR 4TH ST 9TH ST 78 FY27 - CDM from 4th to 9th ORCHID LN HIGHLAND AVE KLISH WAY 53 FY27 recommended
GATUN ST BALBOA AVE CDS 53 FY27 recommended
MAIDEN LN 12TH ST ALLEY N/O 13TH ST 56 FY27 recommended ALLEY N/O 13TH ST MAIDEN LN LUNETA DR 56 FY27 recommended UMATILLA RD RIMINI RD VAN DYKE AVE 57 FY27 recommended
KLISH WAY KLISH WAY AMPHITHEATRE DR 57 FY27 recommended ALLEY N/O 13TH ST VAN DYKE AVE LUNETA DR 60 FY27 recommended CUCHARA DR 11TH ST RIMINI RD 61 FY27 recommended
KLISH WAY HOSKA DR TEWA ST 62 FY27 recommended
LUNETA DR 13TH ST 15TH ST 62 FY27 recommended
MAIDEN LN 15TH ST ALLEY N/O 13TH ST 63 FY27 recommended CUCHARA DR LUNETA DR RIMINI RD 66 FY27 recommended
STRATFORD CT 12TH ST 9TH ST 42 FY27 Stratford Ct S
LITTLE ORPHAN ALY STRATFORD CT CDS 52 FY27 Stratford Ct S MELANIE WAY STRATFORD CT CDS 53 FY27 Stratford Ct S
STRATFORD CT 9TH ST SEA FOREST CT 69 FY27 Stratford Ct S SEA ORBIT LN CDS CDS 78 FY27 Stratford Ct S - SLURRY
SHERRIE LN STRATFORD CT CDS 85 FY27 Stratford Ct S - SLURRY PENNY LN CDS CDS 93 FY27 Stratford Ct S - SLURRY
10TH ST CAMINO DEL MAR CDS 86 FY27 Stratford Ct S - SLURRY 9TH ST CAMINO DEL MAR CDS 94 FY27 Stratford Ct S - SLURRY 4TH ST CAMINO DEL MAR CDS 74 FY27 Stratford Ct S - SLURRY PARTIAL TARGETED FOR FY28
ZUNI DR AVENIDA PRIMAVERA CDS 56 FY28 Crest Canyon
HOSKA DR HIGHLAND AVE CREST RD 61 FY28 Crest Canyon
SERPENTINE DR FOREST WAY AVENIDA PRIMAVERA 65 FY28 Crest Canyon AVENIDA PRIMAVERA LUNETA DR SERPENTINE DR 67 FY28 Crest Canyon SERPENTINE DR AVENIDA PRIMAVERA CDS 69 FY28 Crest Canyon CREST RD HOSKA DR KLISH WAY 79 FY28 Crest Canyon SLURRY CREST RD HOSKA DR CITY BOUNDARY 83 FY28 Crest Canyon SLURRY CREST RD KLISH WAY 15TH ST 87 FY28 Crest Canyon SLURRY
Pavement Management Program List of Projects
Updated March 2026
Name From To PCI CIP PROJECT
15TH ST CREST RD CAROLINA RD 76 FY28 Crest Canyon SLURRY - partial ORIBIA RD CITY BOUNDARY CDS 90 FY28 Crest Canyon SLURRY - partial TARGETED FOR FY29
DEL MAR LANE (ALLEY E/O STRATFORD) ALL S/O 15T ST 12TH ST 53 FY29 Stratford Ct N 13TH ST CAMINO DEL MAR CDS 63 FY29 Stratford Ct N
PACIFIC LN 12TH ST ALLEY S/O 15TH ST 66 FY29 Stratford Ct N ALLEY S/O 15TH ST OCEAN AVE CAMINO DEL MAR 84 FY29 Stratford Ct N SLURRY OCEAN AVE 13TH ST 15TH ST 86 FY29 Stratford Ct N SLURRY - partial FY30 OR LATER
CAMINO DEL MAR NORTH END OF CDM BRIDGE 29TH ST 81 FY30 CDM Bridge CAMINO DEL MAR 29TH ST NORTH END OF CDM BRIDGE 89 FY30 CDM Bridge CAMINO DEL MAR VIA DE LA VALLE NORTH END OF CDM BRIDGE 91 FY30 CDM Bridge CAMINO DEL MAR NORTH END OF CDM BRIDGE VIA DE LA VALLE 93 FY30 CDM Bridge VIA DE LA VALLE DEL MAR DOWNS DR CITY BOUNDARY 60 HOLD UNTIL AFTER BRIDGE PROJECTS VIA DE LA VALLE CITY BOUNDARY DEL MAR DOWNS DR 71 HOLD UNTIL AFTER BRIDGE PROJECTS VIA DE LA VALLE CAMINO DEL MAR DEL MAR DOWNS DR 74 HOLD UNTIL AFTER BRIDGE PROJECTS VIA DE LA VALLE DEL MAR DOWNS DR CAMINO DEL MAR 74 HOLD UNTIL AFTER BRIDGE PROJECTS COAST BLVD 20TH ST 365' S OF 18TH ST 59 HOLD UNTIL UUD 2 IS DESIGNED OCEAN FRONT 27TH ST 24TH ST 62 HOLD UNTIL UUD 2 IS DESIGNED 26TH ST CAMINO DEL MAR CDS 62 HOLD UNTIL UUD 2 IS DESIGNED ALLEY E/O CAMINO DEL MAR 25TH ST 28TH ST 64 HOLD UNTIL UUD 2 IS DESIGNED 24TH ST CAMINO DEL MAR CDS 69 HOLD UNTIL UUD 2 IS DESIGNED 18TH ST OCEAN FRONT SANTA FE AVE 72 HOLD UNTIL UUD 2 IS DESIGNED 19TH ST OCEAN FRONT CDS 76 HOLD UNTIL UUD 2 IS DESIGNED 28TH ST CAMINO DEL MAR CDS 77 HOLD UNTIL UUD 2 IS DESIGNED 29TH ST CAMINO DEL MAR OCEAN FRONT 77 HOLD UNTIL UUD 2 IS DESIGNED OCEAN FRONT 21ST ST CDS 77 HOLD UNTIL UUD 2 IS DESIGNED 20TH ST OCEAN FRONT CDS 78 HOLD UNTIL UUD 2 IS DESIGNED 27TH ST CAMINO DEL MAR CDS 80 HOLD UNTIL UUD 2 IS DESIGNED SANTA FE AVE 18TH ST CDS 81 HOLD UNTIL UUD 2 IS DESIGNED 27TH ST CAMINO DEL MAR OCEAN FRONT 83 HOLD UNTIL UUD 2 IS DESIGNED 23RD ST CAMINO DEL MAR CDS 84 HOLD UNTIL UUD 2 IS DESIGNED OCEAN FRONT 24TH ST 21ST ST 85 HOLD UNTIL UUD 2 IS DESIGNED 21ST ST COURT ST CDS 85 HOLD UNTIL UUD 2 IS DESIGNED
22ND ST COURT ST CDS 90 HOLD UNTIL UUD 2 IS DESIGNED
21ST ST OCEAN FRONT COAST BLVD 91 HOLD UNTIL UUD 2 IS DESIGNED CAMINO DEL MAR COURT ST 29TH ST 91 HOLD UNTIL UUD 2 IS DESIGNED 25TH ST CAMINO DEL MAR CDS 91 HOLD UNTIL UUD 2 IS DESIGNED 25TH ST CAMINO DEL MAR OCEAN FRONT 92 HOLD UNTIL UUD 2 IS DESIGNED CAMINO DEL MAR 29TH ST COURT ST 93 HOLD UNTIL UUD 2 IS DESIGNED COAST BLVD 20TH ST CDS 93 HOLD UNTIL UUD 2 IS DESIGNED
COURT ST COAST BLVD 21ST ST 94 HOLD UNTIL UUD 2 IS DESIGNED 22ND ST OCEAN FRONT COAST BLVD 94 HOLD UNTIL UUD 2 IS DESIGNED 26TH ST CAMINO DEL MAR OCEAN FRONT 94 HOLD UNTIL UUD 2 IS DESIGNED ALLEY E/O CAMINO DEL MAR COURT ST 25TH ST 94 HOLD UNTIL UUD 2 IS DESIGNED Pavement Management Program List of Projects
Updated March 2026
Name From To PCI CIP PROJECT
23RD ST OCEAN FRONT COAST BLVD 95 HOLD UNTIL UUD 2 IS DESIGNED 24TH ST CAMINO DEL MAR OCEAN FRONT 100 HOLD UNTIL UUD 2 IS DESIGNED
TO BE SCHEDULED
CULEBRA ST SEA VIEW AVE ZAPO ST 59
ZUNI DR LUNETA DR CAROLINA RD 59
ALLEY S/O 10TH ST HIGHLAND AVE CDS 62
CARMEL VALLEY RD TORREY PINES RD N CITY BOUNDARY 65
7TH ST CDS CITY BOUNDARY 66
SEA VIEW AVE CULEBRA ST CDS 67
8TH ST HOSKA DR CITY BOUNDARY 68
FOREST WAY ZUNI DR SERPENTINE DR 68
HIGHLAND AVE HOSKA DR 10TH ST 69
HOSKA LN HOSKA DR CDS 69
OCEAN VIEW AVE TORREY PINES TER HIDDEN PINES RD 70
STRATFORD CT 12TH 15TH 70
BALBOA AVE CDS ZAPO ST 70
ZAPO ST SERPENTINE DR CULEBRA ST 70
VAN DYKE AVE LUNETA DR VIA ALTA 71
PINE NEEDLES DR OCEAN VIEW AVE OCEAN VIEW AVE 71
SEA VIEW AVE CAMINO DEL MAR CULEBRA ST 72
11TH ST CAMINO DEL MAR 10TH ST 72
SAN DIEGUITO DR JIMMY DURANTE BLVD GRAND AVENUE OVERLOOK 72 KALAMATH DR CREST RD AMPHITHEATRE DR 72
KLISH WAY AMPHITHEATRE DR CREST RD 73
OCEAN FRONT 29TH ST 27TH ST 73
BORDER AVE CAMINO DEL MAR CITY BOUNDARY 73
GRAND AVE CAMINO DEL MAR ON RAMP CDS 73
JIMMY DURANTE BLVD RR MAINTENANCE BLDG SAN DIEGUITO DR 73 WESLEY WAY CAMINO DEL MAR NOB AVE 73
LUZON AVE SEA VIEW AVE BALBOA AVE 73
CAMINO DEL MAR JIMMY DURANTE BLVD SEA VIEW AVE 74
JIMMY DURANTE BLVD FAIR GROUNDS SOUTH ENTRANCE SAN DIEGUITO DR 75 LUZON AVE JIMMY DURANTE BLVD CDS 75
SERPENTINE DR ZAPO ST FOREST WAY 75
PARISH LN MAIDEN LN LUNETA DR 75
NOB AVE 8TH ST CITY BOUNDARY 76
14TH ST CAMINO DEL MAR LUNETA DR 76
CAMINO DEL MAR SEA VIEW AVE JIMMY DURANTE BLVD 76
AVENIDA PRIMAVERA CREST RD SERPENTINE DR 76
LUNETA DR 15TH ST STRATFORD WAY 76
STRATFORD WAY LUNETA DR LUNETA DR 76
HIDDEN PINES LN PINE NEEDLES DR CDS 77
JIMMY DURANTE BLVD CAMINO DEL MAR RR MAINTENANCE BLDG 77 DAVID WAY JIMMY DURANTE BLVD CDS 78
COAST BLVD 365' S OF 18TH ST 15TH ST 79
Pavement Management Program List of Projects
Updated March 2026
Name From To PCI CIP PROJECT
CAMINO DEL MAR ON RAMP JIMMY DURANTE BLVD CAMINO DEL MAR 79 TEWA ST HIGHLAND AVE KLISH WAY 79
12TH ST CAMINO DEL MAR CDS 80
DEL MAR HEIGHTS RD CAMINO DEL MAR CITY BOUNDARY 80
ZAPO ST CULEBRA ST BALBOA AVE 80
15TH ST CAMINO DEL MAR LUNETA DR 80
15TH ST LUNETA DR CAROLINA RD 81
JIMMY DURANTE BLVD SAN DIEGUITO DR RR MAINTENANCE BLDG 81 NOB AVE OCEAN VIEW AVE CITY BOUNDARY 82
8TH ST STRATFORD CT CDS 82
RACETRACK VIEW DR SAN DIEGUITO DR CITY BOUNDARY 82
CAROLINA RD LUNETA DR ZUNI DR 83
SHIPPEY LN STRATFORD CT CDS 83
6TH ST STRATFORD CT CDS 83
13TH ST CAMINO DEL MAR LUNETA DR 83
ALLEY S/O 7TH ST NOB AVE CDS 83
15TH ST COAST BLVD CAMINO DEL MAR 84
JIMMY DURANTE BLVD RR MAINTENANCE BLDG CAMINO DEL MAR 84 LUNETA DR 11TH ST 13TH ST 85
ZUNI DR CAROLINA RD CDS 85
RIMINI RD UMATILLA DR VAN DYKE AVE 85
8TH ST CAMINO DEL MAR CITY BOUNDARY 86
10TH ST CAMINO DEL MAR 11TH ST 86
12TH ST CAMINO DEL MAR LUNETA DR 87
SAN DIEGUITO DR GRAND AVENUE OVERLOOK RACTRACK VIEW DR 88 AMPHITHEATRE DR CREST RD CUCHARA DR 89
CAMINO DEL MAR CARMEL VALLEY RD 1090' N OF CARMEL VALLEY RD 89 LOIS LN PACIFIC LN CDS 89
VIA ALTA VAN DYKE AVE CREST RD 90
CAMINO DEL MAR 1090' N OF CARMEL VALLEY RD 4TH ST 90
SERPENTINE DR AVENIDA PRIMAVERA ZAPO ST 91
11TH ST CAMINO DEL MAR CDS 91
PRIMAVERA LN AVENIDA PRIMAVERA CDS 91
CAMINO DEL MAR SEA VIEW AVE 13TH ST 91
7TH ST STRATFORD CT CDS 92
TORREY PINES TER OCEAN VIEW AVE W CDS 92
RIMINI RD CUCHARA DR UMATULLA DR 92
9TH ST CAMINO DEL MAR HIGHLAND AVE 92
OCEAN VIEW AVE W TORREY PINES TER CDS 92
BALBOA AVE ZAPO ST SEA VIEW AVE 93
LA AMATISTA RD CAMINO DEL MAR NOB AVE 93
CAMINO DEL MAR 13TH ST SEA VIEW AVE 93
HIDDEN PINES RD OCEAN VIEW AVE HIDDEN PINES LN 94
CAMINO DEL MAR 4TH ST 1090' N OF CARMEL VALLEY RD 94
NORTH TORREY PINES RD CITY BOUNDARY CARMEL VALLEY RD 94 Pavement Management Program List of Projects
Updated March 2026
Name From To PCI CIP PROJECT
CAMINO DEL MAR 1090' N OF CARMEL VALLEY RD CARMEL VALLEY RD 95 SEA CLIFF WAY STRATFORD CT CDS 95
NORTH TORREY PINES RD CARMEL VALLEY RD CITY BOUNDARY 96 CAMINO DEL MAR 13TH ST 9TH ST 97
CAMINO DEL MAR 9TH ST 13TH ST 98
EL AMIGO RD CAMINO DEL MAR CITY BOUNDARY 98
DEL MAR LN 12TH ST ALLEY S/O 15TH ST 100
15TH
C
O
A
S
T
CAM
D
EL MAR
J MI M
Y
DUR
ANTE
ORIBIA
VIA DE LA VALLE
ZUNI
LUNETA
SAN DIEGUITO
CREST
SEA VIEW
ZAPO
14TH
19TH
20TH
GRAND
RIMINI
SERPENTINE
ALLE
Y
BALBOA
VAN DYKE
24TH
27TH
28TH
25TH
26TH
18TH
COURT
LUZON
23RD
AVNDA PRIMAVERA
FOREST
VIA ALTA
GATUN
22ND
BELLAIRE
OCEAN
21ST
DAVID
CULEBRA
13TH
29TH
PARISH
BORDER
STRATFORD
O
C
E
A
N FR
O
N
T
UMATILLA
RACETRACK VIEW
OC
EAN
F
RO
NT
ALLEY
ALLEY
ALLEY
ZUNI
ALLEY
LUZON
27TH
ALLEY
ALLE
Y
23RD
Pavement Management Program
Completed Since 2024 PMP
FY27 Recommended G/O
FY27 Recommended Slurry Seal
Del Mar Boundary
0 375 750 1,500 Feet
CAM
DEL
MAR
15TH
CREST
11TH
10TH
09TH
13TH
12TH LUNETA
HOSKA
04TH
MAIDEN
08TH
ALLEY
PACIFIC
07TH
14TH
OCEAN VIEW
OCEAN
KLIS
H
PENN
ORCHID Y
C
OAS
T
STRATFORD
VAN DYKE
RIMINI
ORIBIA
LOIS
KALAMATH
PINE NEEDLES
TEWA
AMPHITHEATRE
CAROLINA
VIA ALTA
CUCHARA
NOB
06TH
CARMEL VALLEY
MELANIE
HIGHLAND
HIDDEN PINES
SEA ORBIT
SHIPPEY
TORREY PINES
EL AMIGO
PARISH
SHERRY
SEA CLIFF
LA AMATISTA
N
O
RT
H
T
O
R
REY
PINES
LITTLE ORPHAN
ALLEY
KLISH
08TH
NOB
ALLEY
ALLEY
ALLEY
07TH
ALLEY
ALLEY
STRATFORD
STRATFORD
Pavement Management Program
Completed Since 2024 PMP
FY27 Recommended G/O
FY27 Recommended Slurry Seal
Del Mar Boundary
0 375 750 1,500 Feet
Attachment G
Riverpath Phase 3
Estimated Project Cost
In September 18, 2023, the estimated project cost for the Riverpath Phase 3 project was $2,850,000, with an identified funding gap of $1,400,000. As such, the City Council put proceeding with construction of the project on hold and directed staff to pursue outside grant funding to help offset out of pocket project costs for the City. Since that time, the City has been able to secure additional project funding sources, which are identified in the table below.
In February 2026, contract engineering firm Michael Baker International (MBI) reviewed and updated the project Engineer’s Estimate based on recent bids for similar projects in the region.
The resulting new estimated project construction cost, including contingency, is $3,060,000.
Funding Sources
The City has secured funding from several sources as summarized in the table below:
Grant Funding Source Amount Terms
San Dieguito River Valley
Conservancy (SDRVC)
$725,000 Secured. Funding from
private donor is being held by
SDRVC
Fed FY23 Housing and Urban
Development (HUD)
Community Project Funding
$680,000 Agreement signed.
Funding requires construction
completion by August 31,
2031
Land and Water Conservation
Fund (LWCF)
$1,300,000 Funding requires 50% local
match
*Preliminarily awarded, Staff
actively processing postselection requirements.
TOTAL GRANT FUNDING $2,705,000
Estimated Funding Gap $100,000 - $355,000
(Depending on
bidding/use of project
contingency)
Based on estimated total
construction cost $3,060,000
Staff has been preliminarily awarded $1.3 million in pass-through federal funding through the Land and Water Conservation Fund (LWCF). LWCF is a federal, state, and local partnership through the National Park Service. Staff is processing post-selection requirements, which includes completion of required documentation, additional federal resource agency permitting reviews, and confirmation of land use eligibility. Staff anticipates that the post-selection be completed before the end of 2026, which would facilitate project construction in 2027. If the City were to bid and Attachment G
award the project prior to being notified of LWCF’s satisfaction of post-selection requirements, the project would no longer be eligible for the $1.3 million in funding.
Project Timing/Schedule
Due to the location of the project in the sensitive habitat of San Dieguito Lagoon and the protection of sensitive migratory birds, several overlapping biological mitigation measures are included in the permitting for the project restricting certain construction activities between February and August. Staff recommends that the project is bid in April 2027 to award the construction contract with adequate time to start construction in September of 2027. Construction would be completed by January 2028, within the ideal construction window.