Cities Index.
10. Adopt Reso Approving the List of Projects in the Prop FY 23-24 Capital Improvment Program to be Funded by SB1

Downey City Council
June 13, 2023

Document
10. Adopt Reso Approving the List of Projects in the Prop FY 23-24 Capital Improvment Program to be Funded by SB1
Meeting
June 13, 2023
Body
Downey City Council
Pages
6
Original file
12 KB
Text extracted from the city's file for reading and search. Open the original on lf.downeyca.org. That file is the official record.

Item No.
1 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: OFFICE OF THE CITY MANAGER
BY: MATTHEW BAUMGARDNER, P.E., DIRECTOR OF PUBLIC WORKS/CITY

ENGINEER
DATE: JUNE 13, 2023
SUBJECT: RESOLUTION APPROVING THE LIST OF PROJECTS IN THE PROPOSED FISCAL YEAR 2023-2024 CAPITAL IMPROVEMENT PROGRAM TO BE FUNDED BY SENATE BILL 1 (SB1), THE ROAD REPAIR AND

ACCOUNTABILITY ACT

EXECUTIVE SUMMARY
The City Council will consider adopting a Resolution approving the list of projects in the proposed Fiscal Year (FY) 2023-2024 Capital Improvement Program to be funded by State Senate Bill 1: The Road Repair and Accountability Act of 2017. The City will receive $2,816,896 in SB1 revenues for FY 2023-2024 that will be used to fund street rehabilitation and other infrastructure-related projects.

RECOMMENDATION
That the City Council:

Adopt Resolution No. 23-8171, approving the list of projects in the proposed Fiscal Year 2023-2024 Capital Improvement Program to be funded by Senate Bill 1: The Road Repair and Accountability Act of 2017.

BACKGROUND
Senate Bill 1 (SB1), The Road Repair and Accountability Act of 2017, is a transportation funding bill passed by the State Legislature and signed into law by the Governor in April 2017, which provides approximately $52 billion in funding raised through gasoline, diesel fuel, and sales tax increases over the first 10 years of the law, in order to address significant multi-modal transportation funding shortfalls Statewide.

AN ALYSIS
In order to receive SB1 funding approval for FY 2023-2024, the City must adopt a resolution approving a list of projects proposed to be funded through SB1. The project list must include a description and location of each proposed project, a proposed schedule for the project’s completion, and estimated useful life of the proposed improvements. The City is required to submit a copy of the adopted resolution to the California Transportation Commission by July 1, 2023. The City’s SB1 funding allocation for FY 2023-2024 is estimated at $2,816,896.

APPROVED BY

CITY MANAGER

ADOPT RESOLUTION APPROVING THE LIST OF PROJECTS IN THE PROPOSED FY 2023/2024 CAPITAL IMPROVEMENT PROGRAM TO BE FUNDED BY SENATE BILL 1 (SB1), THE ROAD REPAIR

AND ACCOUNTABILITY ACT
JUNE 13, 2023
PAGE 2

2 The projects proposed to be funded with SB1 revenues are listed in Exhibit “A” and Exhibit “B” of the attached Resolution. Staff recommends adoption of the attached Resolution to secure SB1 funds for FY 2023-2024. CITY COUNCIL PRIORITIES Quality of Life, Safety and Infrastructure FISCAL IMPACT Approval of the recommended action will result in the City receiving SB 1 revenues in the amount of $2,816,896 within the SB1 Transportation Fund 32 under various accounts for FY 2023-2024. ATTACHMENT Attachment “A”- Resolution Attachment “B”- Project Location List

RESOLUTION NO. 23-8171

A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF DOWNEY

APPROVING THE LIST OF PROJECTS IN THE PROPOSED FISCAL YEAR 2023/2024 CAPITAL IMPROVEMENT PROGRAM TO BE FUNDED BY SENATE BILL 1: THE ROAD REPAIR AND ACCOUNTABILITY ACT OF 2017

WHEREAS, Senate Bill 1 (SB1), the Road Repair and Accountability Act of 2017 (Chapter 5, Statutes of 2017) was passed by the Legislature and signed into law by the Governor in April 2017 in order to address the significant multi-modal transportation funding shortfalls statewide; and

WHEREAS, SB1 includes accountability and transparency provisions that will ensure the residents of our City are aware of the projects proposed for funding in our community and which projects are in progress or have been completed each fiscal year; and

WHEREAS, the City must adopt by resolution a list of projects proposed to receive fiscal year funding from the Road Maintenance and Rehabilitation Account (RMRA), created by SB1, which must include a description and the location of each proposed project, a proposed schedule for the project’s completion, and the estimated useful life of the improvement; and

WHEREAS, the City, will receive an estimated $2,816,896 in RMRA funding in Fiscal Year 2023/2024 from SB1; and

WHEREAS, this is the sixth year in which the City is receiving SB 1 funding and will enable the City to continue essential road maintenance and rehabilitation projects, safety improvements, repairing and replacing aging bridges, and increasing access and mobility options for the traveling public that would not have otherwise been possible without SB 1; and

WHEREAS, the City has undergone a robust public process to ensure public input into our community’s transportation priorities; and

WHEREAS, the City used a Pavement Management System to develop the SB1 project list to ensure revenues are being used on the most high-priority and cost-effective projects that also meet the community’s priorities for transportation investment; and

WHEREAS, the funding from SB1 will help the City maintain and rehabilitate a number of streets and add active transportation infrastructure throughout the City this year and hundreds of similar projects into the future; and

WHEREAS, the 2018 California Statewide Local Streets and Roads needs assessment found that the City’s streets and roads are in an at-risk condition and this revenue will help us increase the overall quality of our road system and over the next decade will bring our streets and roads into a good condition; and

WHEREAS, the local street and road system is also critical for farm to market needs, interconnectivity, multimodal needs, and commerce; and

WHEREAS, police, fire, and emergency medical services all need safe reliable, roads to react quickly to emergency calls and a few minutes of delay can be a matter of life and death; and

WHEREAS, restoring roads before they fail also reduces construction time which results in less air pollution from heavy equipment and less water pollution from site run-off; and

RESOLUTION NO.

PAGE NO. 2

WHEREAS, the SB 1 project list, attached herein as Exhibit “A” and “B”, and overall investment in our local streets and roads infrastructure with a focus on basic maintenance and safety, investing in complete streets infrastructure, and using cutting -edge technology, materials and practices, will have significant positive co-benefits statewide.

NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF DOWNEY DOES HEREBY RESOLVE AS FOLLOWS:

SECTION 1. The City Council of the City of Downey is approving the list of newly proposed projects attached herein as Exhibit “A” to be funded in Fiscal Year 2023-2024 with RMRA revenues.

SECTION 2. The City Council of the City of Downey is approving the list of projects previously proposed and adopted from Fiscal Year 2022-2023 attached herein as Exhibit “B” and may also utilize Fiscal Year 2023-2024 RMRA revenues in their delivery. With the relisting of these projects in the adopted fiscal year resolution, the City is reaffirming to the public and the State our intent to fund these projects with RMRA revenues:

SECTION 3. The City Clerk shall certify to the adoption of this Resolution.

APPROVED AND ADOPTED this 13th day of June, 2023.

___________________________________
CLAUDIA FROMETA, Mayor
ATTEST:

_______________________________

MARIA ALICIA DUARTE, CMC
City Clerk

I HEREBY CERTIFY that the foregoing Resolution was adopted by the City Council of the City of Downey at a regular meeting held on the 13th day of June, 2023, by the following vote, to wit

AYES: Council Members:

NOES: Council Member:

ABSENT: Council Member:

ABSTAIN: Council Member:

___________________________________

MARIA ALICIA DUARTE, CMC
City Clerk

EXHIBIT “A”

List of Projects in the Proposed FY 2023/2024 Capital Improvement Program to be Funded by Senate Bill 1 (SB1): The Road Repair And Accountability Act Project Description Location Estimated
Useful Life
Proposed
Schedule of
Completion

1. Residential
Streets Pavement
Rehabilitation – Area
7 Rehabilitation of pavement on
various residential streets and
replacement of damaged
sidewalk and curb and gutter
and reconstruction of curb
access ramps to comply with
current ADA requirements.

Area 7 20 years 12/2024

2. FY 23/24
Miscellaneous
Concrete Repairs
and ADA
Improvements
Annual miscellaneous
concrete construction and
Repairs of concrete surfaces
in Council District 1 and
construction of ADA-compliant
curb access ramps, drive
approaches and sidewalks.

Council District 1 20 years 06/2024

3. Lakewood
Boulevard Parkway
Improvements

Rehabilitation of existing
asphalt pavement, repair of
existing miscellaneous
concrete surfaces,
replacement of existing
striping and pavement
markings.

Imperial Hwy. to
Gardendale St. 20 years 06/2024

4. Lakewood
Boulevard Pavement
Rehabilitation
Rehabilitation of existing
asphalt pavement, repair of
existing miscellaneous
concrete surfaces and
replacement of existing
striping and pavement
markings.

U.P.R.R. to
Imperial Hwy. 20 years 06/2025

5. Garfield Avenue
Complete Streets
Improvements
Rehabilitation of existing
asphalt pavement, repair of
existing miscellaneous
concrete surfaces and
replacement of existing
striping and pavement
markings.

Gardendale St.
to North City
Limit
20 years 06/2025

6. Manzanar
Avenue Street
Improvements
Rehabilitation of existing
asphalt pavement, repair of
existing miscellaneous
concrete surfaces and
replacement of existing
striping and pavement
markings.

Manzanar
Avenue 150 Feet
South of
Telegraph Road
20 years 06/2025

EXHIBIT “B”

List of Carryover Projects in the FY 2022/2023 Capital Improvement Program Funded by Senate Bill 1 (SB1): The Road Repair And Accountability Act

Project Description Location Estimated
Useful Life
Proposed
Schedule of
Completion

1. Woodruff
Avenue Pavement
Rehabilitation
Rehabilitation of existing
asphalt pavement, repair of
existing miscellaneous
concrete surfaces,
replacement of existing
striping and pavement
markings and installation of
bike lanes.

Firestone Blvd.
to Foster Rd. 20 years 6/2024

2. Bellflower
Boulevard
Pavement
Rehabilitation
Rehabilitation of existing
asphalt pavement, repair of
existing miscellaneous
concrete surfaces,
replacement of existing
striping and pavement
markings.

Foster Rd. to
Dalen St. and
900’ N/O
Imperial Hwy. to
Stewart and
Gray Rd.
20 years 03/2025

3. Downey Avenue
Pavement
Rehabilitation
Rehabilitation of existing
asphalt pavement, repair of
existing miscellaneous
concrete surfaces,
replacement of existing
striping and pavement
markings and installation of
bike lanes (PS&E only).
5th St. to
Alameda St. 20 years 12/2024

4. Pavement
Management Plan
Update Citywide Pavement
Management Plan to
prioritize the City’s street
paving needs.

Citywide 3 years 6/2024

5. South Downey
Safe Routes to
School Project
Construction of new sidewalk
and curb ramps, signage,
replacement of striping and
pavement markings,
installation of vehicle speed
feedback signs and safety
education program
Blodgett Ave.,
Adoree St.,
Airpoint Ave.,
Nada St., Julius
St., Brunache
St. & Laura St.
50 12/2023