03. CIP 17-07 Award Construction Contract for Citywide Bus Signal Priority Project

Downey City Council
August 22, 2023

Document
03. CIP 17-07 Award Construction Contract for Citywide Bus Signal Priority Project
Meeting
August 22, 2023
Body
Downey City Council
Pages
21
Original file
57 KB
Text extracted from the city's file for reading and search. Open the original on lf.downeyca.org. That file is the official record.

TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: OFFICE OF THE CITY MANAGER
BY: MATTHEW BAUMGARDNER, P.E., DIRECTOR OF PUBLIC WORKS/CITY

ENGINEER
DATE: AUGUST 22, 2023
SUBJECT: CONSTRUCTION CONTRACT FOR THE CITYWIDE BUS SIGNAL PRIORITY PROJECT, CAPITAL IMPROVEMENT PROJECT NO. 17-07

EXECUTIVE SUMMARY
The City Council will consider awarding a construction contract to International Line Builders, Inc. dba ILB Electric for the installation of fiber-optic communications and bus signal priority equipment in the field and at City Hall. This project will implement a bus signal priority system within the City, which will decrease travel times experienced by public transit buses if they are running behind schedule by granting the buses an early or extended "green" signal at signalized intersections along the bus routes to help them to get back on schedule.

RECOMMENDATION
That the City Council:

Award the Citywide Bus Signal Priority Project, Capital Improvement Project No. 17-07, to International Line Builders, Inc. dba ILB Electric, the lowest responsive, responsible bidder, for the total bid amount of $1,793,252 and waive any and all minor irregularities in the bidding documents as submitted by said bidder; and

2. Authorize the City Manager, or his designee, to execute the Construction Contract with International Line Builders, Inc. dba ILB Electric in the amount of $1,793,252, including any non -substantive extensions, change orders, purchase orders, and amendments up to the authorized budget amount of $1,972,577; and

3. Approve the transfer of $350,000 and $400,000 in Proposition C Local Return funds from Account Nos. 54-16789 and 54-16790, respectively, to Account No. 54-17826 and the transfer of $150,000 and $100,000 in Measure R Local Return funds from Account Nos. 56-16789 and 56-16790, respectively, to Account No. 56-17826.

BACKGROUND

BUS SIGNAL PRIORITY PROJECT, CIP 17-07
AUGUST 22, 2023
PAGE 2
On December 8, 2022, the City Council approved plans (Attachment A) and specifications and authorized staff to advertise for bids for the Citywide Bus Signal Priority Project, Capital Improvement Project (CIP) No. 17-07. A copy of the project specifications is available at the Public Works Department for public review. This project will implement a priority system for public transit buses within the City, including the Downey LINK, Metro, and Long Beach Transit bus routes, which will decrease travel times for said bus vehicles by granting the buses an early or extended "green" signal at signalized intersections along bus routes if they are running behind schedule. The radios, which will be installed at signalized intersections as part of this project for purposes of receiving the "request for priority" signals from approaching buses, will also provide WiFi in the vicinity of said intersections. The bus routes and signalized intersections at which bus priority will be provided, as well as other elements to be implemented through this project, are shown on the attached Project Location Map (Attachment B).

Specifically, this project will involve the expansion of the City's traffic signal communication system to seven signalized intersections through the construction of fiber- optic conduits and cables on various streets and the installation of communications equipment in traffic signal controller cabinets, the installation of bus signal priority equipment at 74 signalized intersections along bus routes, the procurement and delivery of bus signal priority network equipment to City Hall, the integration of the bus signal priority and communications systems with the City's Traffic Management Center at City Hall and retrofitting the Downey LINK bus fleet with bus signal priority transmitter devices.

ANALYSIS
The project was advertised for bids in the Downey Patriot on July 20, 2023 and July 27, 2023, posted on Planet Bids on July 20, 2023 and published in various trade publications.

On August 10, 2023, the City Clerk received and publicly opened seven bids ranging from $1,793,2522 to $2,472,889 (Attachment C). The bid results were as follows:

CONTRACTOR

I LOCATION

BASE BID AMOUNT
International Line Builders, Inc. dba ILB Electric
Corona, CA
$1,793,252
Select Electric, Inc.

Anaheim, CA
$1,967,232
Baker Electric
Cypress, CA
$1,978,346
Belco Elecnor Group
Chino, CA
$2,086,888
Crosstown Electrical & Data, Inc.

Irwindale, CA
$2,266,948
HHS Construction LLC
Ontario, CA
$2,306,219
DBX, Inc.

Temecula, CA
$2,472,889
The lowest responsive and responsible bidder was International Line Builders, Inc., dba ILB Electric in the amount of $1,793,252 as shown on the attached Bid Summary (Attachment C). Staff reviewed the bid proposal and references provided by International

BUS SIGNAL PRIORITY PROJECT, CIP 17-07
AUGUST 22, 2023
PAGE 3
Line Builders, Inc., dba ILB Electric and found that said contractor has satisfactorily completed similar projects for the Cities of Los Angeles, Downey, Santa Ana, Fountain Valley, Whittier, Irvine, Newport Beach, Fontana, Orange, and La Mirada. In addition, International Line Builders, Inc., dba ILB Electric's State of California contractor's license is current and active. Finally, International Line Builders, Inc., dba ILB Electric and its subcontractors are registered with the California Department of Industrial Relations under the Public Works Contractor Registration Program for Labor Compliance.

Staff recommends that the City Council award a contract in the amount of $1,793,252 to International Line Builders, Inc., dba ILB Electric for the Citywide Bus Signal Priority Project, Capital Improvement Project No. 17-07. Construction is estimated to begin in October 2023 and be completed in April 2024.

CITY COUNCIL PRIORITIES
Efficiency & Adaptability
Quality of Life, Safety & Infrastructure

FISCAL IMPACT
The total estimated cost of the project is $2,799,799 as shown in the table below:

Item
Amount
Construction Contract
$1,793,252
Contingencies
$179,325
Subtotal Construction Cost
$1,972,577
Design Engineering
$272,000
Equip Buses with Priority Devices
$200,000
Traffic Signal Timing/Fine-Tuning
$59,000
Construction Inspection
$198,222
Construction Engineering and Grant/Contract Administration $98,000
Grand Total
$2,799,799
Approval of the recommended actions will result in an expenditure of $2,799,799 from the Metro Call for Projects Proposition C 25% grant and Proposition C and Measure R Local Return funds involving said Public Works Capital Improvement accounts previously approved in the Fiscal Year (FY) 2018-2019 through FY 2023-2024 Capital Improvement budgets as shown in the following table. With the transfer of funds from the other accounts, there is sufficient fund balance for the recommended actions as shown in the below table:

LAKEWOOD BOULEVARD TRAFFIC SIGNAL UPGRADES AT FOUR LOCATIONS, CIP 20-36A JULY 25, 2023
PAGE 4
Account No.

Funding Source
Amount
26-1-7826
Metro Call for Projects Proposition C 25% grant funds
(previouslyexpended in FY 2018-23
$173,282
56-1-7826
Measure R Local Return funds (previously expended in
FY 2018-23
$71,501
26-1-7826
Metro Call for Projects Proposition C 25% grant funds
ro rammed in FY 2023-24
$1,112,243
56-1-7826
24 Measure R Local Return funds (programmed in FY 2023- $442,773
54-1-6789
Proposition C Local Return (budgeted in FY 2023-24
$350,000
54-1-6790
Proposition C Local Return (budgeted in FY 2023-24
$400,000
56-1-6789
Measure R Local Return (budgeted in FY 2023-24
$150,000
56-1-6790
Measure R Local Return (budgeted in FY 2023-24
$100,000
Total Project Funding:
$2,799,799

ATTACHMENTS
Attachment A — Plans
Attachment B — Project Location Map
Attachment C — Bid Summary

GENERAL NOTES

1. ALL WORK SHALL CONFORM TO THE STANDARD PLANS AND SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION (S.S.P.W.C.), LATEST EDITION, THE STATE OF

CALIFORNIA DEPARTMENT OF TRANSPORTATION STANDARD PLANS AND SPECIFICATIONS, LATEST EDITION, THE SPECIAL CONDITIONS, AND THESE PLANS.

2. ALL UNDERGROUND UTILITIES SHALL BE INSTALLED PRIOR TO PERMANENT PAVEMENT RESTORATION OF THE STREETS.

3. ALL JOINS TO EXISTING ASPHALT PAVEMENT, WITH ASPHALT CONCRETE OVERLAY

OR NEW STRUCTURAL SECTIONS, SHALL BE TO THE SATISFACTION OF THE CITY ENGINEER.

4. SAFETY VESTS AND HARD HATS SHALL BE WORN AT ALL TIMES WHEN WORKING ON THIS PROJECT.

5. THE CONTRACTOR SHALL NOTIFY THE CITY OF DOWNEY INSPECTOR AT LEAST 48 HOURS PRIOR TO ANY CONSTRUCTION PHONE: 562-904-7110.

6. THE CONTRACTOR SHALL USE PROPER TRAFFIC CONTROL AS REQUIRED PER THE

CALIFORNIA MANUAL OF UNIFORM TRAFFIC CONTROL DEVICES (CAMUTCD), OR PER CALTRANS TRAFFIC MANUAL AND W.A.T.C.H. HANDBOOK, WHICHEVER IS MORE STRINGENT, AND AS REQUIRED BY THE TRAFFIC ENGINEER.

7. WHERE STANDARD PLANS ARE CALLED FOR, S.P.P.W.C. STATE OF CALIFORNIA OR CITY OF DOWNEY STANDARD DRAWING OF THE LATEST EDITION SHALL BE USED.

8. CONTRACTOR AGREES THAT HE SHALL ASSUME SOLE AND COMPLETE

RESPONSIBILITY FOR JOB SITE CONDITIONS DURING THE COURSE OF THE CONSTRUCTION OF THIS PROJECT. INCLUDING SAFETY OF ALL PERSONS AND

PROPERTY, THAT THIS REQUIREMENT SHALL APPLY CONTINUOUSLY AND NOT BE LIMITED TO NORMAL WORKING HOURS; AND THAT THE CONTRACTOR SHALL

DEFEND, INDEMNIFY AND HOLD THE CITY AND ITS EMPLOYEES HARMLESS FROM

ANY AND ALL LIABILITY, REAL OR ALLEGED, IN CONNECTION WITH THE

PERFORMANCE OF THE WORK ON THIS PROJECT, EXCEPTING FOR LIABILITY ARISING FROM SOLE NEGLIGENCE OF THE CITY OR ITS EMPLOYEES.

9. CONTRACTOR SHALL VERIFY ALL CONDITIONS AND DIMENSIONS AND SHALL

REPORT ALL DISCREPANCIES TO THE CITY ENGINEER PRIOR TO THE COMMENCEMENT OF WORK.

10. AT NO 11ME IS ANY BUSINESS OR RESIDENCE TO BE WITHOUT ACCESS UNLESS OTHERWISE APPROVED IN WRITING BY THE CITY.

11. STREETS IN THE CONSTRUCTION AREA SHALL BE KEPT CLEAN AT ALL TIMES. ALL

SWEEPING PERFORMED BY THE CITY CREWS WILL BE CHARGED TO THE CONTRACTOR AT OVERTIME RATES.

12. ALL EXISTING IMPROVEMENTS SHALL BE PROTECTED IN PLACE UNLESS OTHERWISE NOTED.

13. POTHOLE/HAND DIG AT UTILITY CROSSINGS/OBSTRUCTIONS, AND AREAS WHERE

LOCATION OF UTILITIES AND UNDERGROUND FACILITIES ARE IN QUESTION PRIOR TO STARTING WORK, WHETHER SHOWN OR NOT SHOWN ON THE PLANS.

14. COORDINATE WITH OWNER OF ANY UTILITY OR OBSTRUCTION PRIOR TO RELOCATING/ADJUSTING ANY SUCH ITEMS.

15. WORK LIMITED BETWEEN 8:00 A.M. AND 5:00 P.M., UNLESS OTHERWISE APPROVED BY THE CITY.

16. NO STORAGE OF MATERIALS/EQUIPMENT IN PUBLIC RIGHT-OF-WAY. PROVIDE OFFSITE STAGING/STORAGE AREA IF NECESSARY.

17. ALL TREES WITHIN CITY RIGHT OF WAY WILL BE REMOVED BY CITY.

18. CONTRACTOR SHALL REPLACE/REPAIR IN KIND ALL LANDSCAPING AND IRRIGATION IMPROVEMENTS IMPACTED BY CONSTRUCTION OF NEW IMPROVEMENTS.

19. IT SHALL BE THE RESPONSIBILITY OF THE CONTRACTOR TO VERIFY THE

EXISTENCE AND LOCATION OF ALL UNDERGROUND FACILITIES AND TO PROTECT THEM FROM DAMAGE. THE CONTRACTOR SHALL BEAR THE TOTAL EXPENSE OF

REPAIR OR REPLACEMENT OF ANY UNDERGROUND FACILITIES DAMAGED DURING CONSTRUCTION.

UNDERGROUND STRUCTURES
CJIr J Y or�lrh ID) �Ww NilE�Y
�. . .8] IBC-' `_/'O 1ma0EA?Z'�.;1 rWr�

CONSTRUCTION PLANS FOR
C I -ILD N 0. t
ID -1 NAL
CITYWIDE '�)US Sl�_x

PROJECT SITE

PROJECTI I
VIl,IIVl 1 Y IVI/A1`

ALL UNDERGROUND UTILITIES OR STRUCTURES REPORTED BY

THE OWNER OR OTHERS AND THOSE SHOWN ON THE

UTILITY
AND
AGENCY
INDEX

RECORDS EXAMINED ARE INDICATED WITH THEIR
APPROXIMATE LOCATION AND EXTENT. THE OWNER BY

ACCEPTING THESE PLANS OR PROCEEDING WITH

SOUTHERN CALIFORNIA EDISON - DISTRIBUTION

JENNA BEAVER
562) 305-1566

IMPROVEMENTS PURSUANT THERETO AGREES TO ASSUME

SOUTHERN CALIFORNIA EDISON - TRANSMISSION

JAMES RUTHER
310) 608-5087

LIABILITY AND TO HOLD UNDERSIGNED HARMLESS FOR ANY

XO/VERIZON

CALISTRO ROSALES
714 656-7112

DAMAGES RESULTING FROM THE EXISTENCE OF

SOUTHERN CALIFORNIA GAS COMPANY

CHRIS KEEVERN
213 231-0456

UNDERGROUND UTILITIES OR STRUCTURES NOT REPORTED

TIME WARNER/CHARTER COMMUNICATIONS

ERNEST CHANG
310 212-1761
1724)

TO THE UNDERSIGNED, NOT INDICATED ON THE PUBLIC

CROWN CASTLE

KELLY KLINEFELTER
743-6085

RECORDS EXAMINED, LOCATED AT VARIANCE WITH THAT

CRIMSON PIPELINE

APRIL HARVEY
(562) 458-3109
REPORTED OR SHOWN ON RECORDS EXAMINED.

CITY OF DOWNEY - WATER & SEWER (UTILITIES)

DAN MUELLER
562) 699-7411
LA COUNTY DEPT. OF PUBLIC WORKS - CONST. DIVISION

JOHN NG
626) 458-7813

THE CONTRACTOR IS REQUIRED TO TAKE DUE
TORRANCE PIPELINE CO., LLC

ELEANOR MARX
310) 221-2914
1323)

PRECAUTIONARY MEASURES TO PROTECT THE UTILITIES OR

CENTRAL BASIN MWD

ISABELLE GUIDO
201-5541

STRUCTURES SHOWN AND ANY OTHER UTILITIES OR

MWD OF SOUTHERN CALIFORNIA

MELISSA CHOI
(213) 217-7516
STRUCTURES FOUND AT THE SITE. IT SHALL BE THE

LA COUNTY SANITATION DISTRICT

ANTHONY HOWARD
(562) 908-4288 [EXT 1602]

CONTRACTOR'S RESPONSIBILITY TO NOTIFY THE OWNERS OF

AT & T CALIFORNIA

MARCO MACIAS
626) 318-9039

THE UTILITIES OR STRUCTURES CONCERNED BEFORE

OSP ENGINEERING & CONS -WEST (SPRINT/T-MOBILE)

TIBOR LAKY
714) 617-9598
STARTING WORK.

TESORO PIPELINE

RITA HAGERTY
714) 880-1653

UNDERGROUND SERVICE ALERT (USA)
----
(800) 422-4133

UNAUTHORIZED CHANGES & USES
CAUTION: THE ENGINEER PREPARING THESE PLANS WILL

NOT BE RESPONSIBLE FOR, OR LIABLE FOR, UNAUTHORIZED
CHANGES TO OR USES OF THESE PLANS. ALL CHANGES

TO THE PLANS MUST BE IN WRITING AND MUST BE
APPROVED BY THE PREPARER OF THESE PLANS.
7-07
P'IZIO]E�,ITX

INDEX TO PROJECT DRAWINGS
SHEET NO. DESCRIPTION
1 TITLE SHEET
2 FIBER COMMUNICATION PLANS - GARDENDALE ST / PARAMOUNT BLVD TO DOWNEY AVE 3 FIBER COMMUNICATION PLANS - GARDENDALE ST / BROOKSHIRE AVE TO BARLIN AVE 4 FIBER COMMUNICATION PLANS - GARDENDALE ST / LAKEWOOD BLVD 5 FIBER COMMUNICATION PLANS - FOSTER RD / COLUMBIA WAY-CLARK AVE 6 FIBER COMMUNICATION PLANS - FOSTER RD / BELLFLOWER BLVD 7 FIBER COMMUNICATION PLANS - LAKEWOOD BLVD / ROSECRANS BLVD 8 FIBER COMMUNICATION PLANS - FIRESTONE BLVD / ANDREWS LN TO RYERSON AVE 9 COMMUNICATION BLOCK DIAGRAM
10 FIBER ASSIGNMENT TABLE I
11 FIBER ASSIGNMENT TABLE II
12 EQUIPMENT INSTALLATION DETAILS - PULL BOX DETAILS
13 EQUIPMENT INSTALLATION DETAILS - FIBER OPTIC SPLICING DETAILS 14 EQUIPMENT INSTALLATION DETAILS - CONDUIT AND PULL BOX DETAILS 15 EQUIPMENT INSTALLATION DETAILS - BSP WIRELESS RADIO DETAILS

SYMBOL/LEGEND

CENTERLINE

CITY BOUNDARY
(E) CURB EDGE
(E) R/W
(E) TRAFFIC SIGNAL CONDUIT
(P) TRAFFIC SIGNAL CONDUIT
(E) CAN
(E) ELECTRIC LINE
(E) FIBER OPTIC COMMUNICATION
(E) GAS LINE
(E) OVERHEAD TRANSMISSION
(E) RECLAIMED WATER LINE
(E) SEWER LINE
(E) STORM DRAIN
(E) TELEPHONE COMMUNICATION
(E) WATER LINE

BSP EQUIPMENT INSTALLATION LOCATIONS
NO.

INTERSECTION

EQUIPMENT

LOCATION
2 BELLFLOWER BLVD/CONG. STEVE HORN WAY
2-ACCESS POINTS

SWMA & NEMA
3 BELLFLOWER BLVD/FOSTER RD
2-ACCESS POINTS

SWMA & SEMA
4 BELLFLOWER BLVD/IMPERIAL HWY
2-ACCESS POINTS

NEMA & NWMA
5 BELLFLOWER BLVD/STEWART AND GRAY
2-ACCESS POINTS

NEMA & SWMA
6 BELLFLOWER BLVD/WASHBURN
2-ACCESS POINTS

NEMA & SWMA
9 BROOKSHIRE/GAR DEN DALE

ACCESS POINT
SEMA
11 COLUMBIA/FOSTER RD

ACCESS POINT
NWMA
12 COLUMBIA/IMPERIAL HWY
2-ACCESS POINTS

SEMA & NWMA
14 DOWNEY/GARDENDALE

ACCESS POINT
SEMA
15 FIRESTONE BLVD/ANDREWS LN
2-ACCESS POINTS

SWMA & NEMA
16 FIRESTONE BLVD/ARNETT

ACCESS POINT
SEMA
17 FIRESTONE BLVD/BROOKSHIRE
2-ACCESS POINTS

SEMA & NWMA
19 FIRESTONE BLVD/DOWNEY
2-ACCESS POINTS

SEMA & NWMA
21 FIRESTONE BLVD/PARAMOUNT BLVD
2-ACCESS POINTS

SEMA & NEMA
22 FIRESTONE BLVD/OLD RIVER SCHOOL RD

ACCESS POINT
NEMA
24 FIRESTONE BLVD/RIVES
2-ACCESS POINTS

SEMA & NWMA
25 FIRESTONE BLVD/RYERSON
2-ACCESS POINTS

SWMA & NEMA
26 FIRESTONE BLVD/STEWART AND GRAY

ACCESS POINT
NWMA
27 FIRESTONE BLVD/STONEWOOD

ACCESS POINT
NWMA
28 FIRESTONE BLVD/WOODRUFF

ACCESS POINT
NWMA
29 FLORENCE AVE/BROOKSHIRE

ACCESS POINT
SEMA
30 FLORENCE AVE/DOWNEY

ACCESS POINT
SEMA
31 FLORENCE AVE/NEWVILLE-MATTOCK

ACCESS POINT
SEMA
32 FLORENCE AVE/OLD RIVER SCHOOL RD

ACCESS POINT
SEMA
33 FLORENCE AVE/RIVES
2-ACCESS POINTS

SWMA & NEMA
34 FLORENCE AVE/STUDEBAKER

ACCESS POINT
SEMA
37 FLORENCE AVE/WOODRUFF

ACCESS POINT
SEMA
39 IMPERIAL HWY/ARDIS
2-ACCESS POINTS

SEMA & NWMA
40 IMPERIAL HWY/BARLIN
2-ACCESS POINTS

SEMA & NWMA
41 IMPERIAL HWY/BROOKSHIRE
2-ACCESS POINTS

SEMA & NWMA
42 IMPERIAL HWY/DOWNEY
2-ACCESS POINTS

SEMA & NWMA
43 IMPERIAL HWY/DUNROBIN
2-ACCESS POINTS

SEMA & NEMA
45 IMPERIAL HWY/OLD RIVER SCHOOL RD

ACCESS POINT
NWMA
46 IMPERIAL HWY/SMALLWOOD
2-ACCESS POINTS

SEMA & NWMA
47 IMPERIAL HWY/WOODRUFF
2-ACCESS POINTS

SEMA & NEMA
48 LAKEWOOD BLVD/ALAMEDA
2-ACCESS POINTS

SWMA & NEMA
49 LAKEWOOD BLVD/BELLFLOWER BLVD
2-ACCESS POINTS

NWMA & NEMA
50 LAKEWOOD BLVD/CECILIA-FIFTH
2-ACCESS POINTS

SWMA & NEMA
51 LAKEWOOD BLVD/CHEROKEE
2-ACCESS POINTS

SEMA & SWMA
53 LAKEWOOD BLVD/DONOVAN-ROSE
2-ACCESS POINTS

NEMA & SWMA
54 LAKEWOOD BLVD/DOWNEY LANDING DWY

ACCESS POINT
NEMA
56 LAKEWOOD BLVD/FIRESTONE BLVD
2-ACCESS POINTS

NWMA & NEMA
57 LAKEWOOD BLVD/FLORENCE AVE
3-ACCESS POINTS

SWMA/NWMA/NEMA
58 LAKEWOOD BLVD/GALLATIN
2-ACCESS POINTS

SWMA & NEMA
59 LAKEWOOD BLVD/GARDENDALE
2-ACCESS POINTS

SEMA & SWMA
60 LAKEWOOD BLVD/IMPERIAL HWY
3-ACCESS POINTS

SWMA/SEMA/NEMA
61 LAKEWOOD BLVD/ROSECRANS
2-ACCESS POINTS

NWMA & NEMA
62 LAKEWOOD-ROSEMEAD BLVD/TELEGRAPH RD
2-ACCESS POINTS

NWMA & NEMA
63 LAKEWOOD BLVD/STEWART-GRAY
2-ACCESS POINTS

NWMA & NEMA
65 OLD RIVER SCHOOL RD/ADWEN

ACCESS POINT
NEMA
66 PARAMOUNT BLVD/ALAMEDA

ACCESS POINT
NEMA
67 PARAMOUNT BLVD/BROOKMILL

ACCESS POINT
SWMA
69 PARAMOUNT BLVD/FIFTH

ACCESS POINT
NEMA
70 PARAMOUNT BLVD/FLORENCE AVE
2-ACCESS POINTS

SEMA & SWMA
71 PARAMOUNT BLVD/GALLATIN
2-ACCESS POINTS

SWMA & NEMA
72 PARAMOUNT BLVD/GARDENDALE
2-ACCESS POINTS

SEMA & NEMA
73 PARAMOUNT BLVD/IMPERIAL HWY
4-ACCESS POINTS

SEMA/SWMA/NEMA/NWM
74 PARAMOUNT BLVD/LUBEC

ACCESS POINT
NEMA
75 PARAMOUNT BLVD/QUILL-QUOIT

ACCESS POINT
NEMA
76 PARAMOUNT BLVD/SEVENTH
2-ACCESS POINTS

SWMA & NEMA
77 PARAMOUNT BLVD/STEWART AND GRAY
2-ACCESS POINTS

NWMA & NEMA
78 PARAMOUNT BLVD/SUVA
2-ACCESS POINTS

SWMA & NEMA
79 PARAMOUNT BLVD/TELEGRAPH
2-ACCESS POINTS

NWMA & NEMA
80 PARAMOUNT BLVD/THIRD

ACCESS POINT
NEMA
81 PARAMOUNT BLVD/VISTA DEL ROSA

ACCESS POINT
SWMA
82 STEWART AND GRAY/BROOKSHIRE

ACCESS POINT
SEMA
83 STEWART AND GRAY/OLD RIVER SCHOOL RD
2-ACCESS POINTS

SEMA & NWMA
84 STEWART AND GRAY/PATTON

ACCESS POINT
NWMA
85 STEWART AND GRAY/RIVES

ACCESS POINT
NWMA
88 TELEGRAPH RD/PASSONS
2-ACCESS POINTS

SEMA & NWMA
89 TELEGRAPH RD/SERAPIS
2-ACCESS POINTS

SEMA & NWMA
90 TELEGRAPH RD/TRUE
2-ACCESS POINTS

SEMA & NWMA
91 WOODRUFF/STEWART AND GRAY
2-ACCESS POINTS

SEMA & NEMA
92 WOODRUFF/WASHBURN

ACCESS POINT
NEMA
100% SUBMITTAL
k
m
x
0 i
U
z
U
w
W
m
ru
F-
U
O
w
IL
0 Ix
a
J
Z
O
N
H
Z
x
co -

EXISTING SMFO TO HUB

PARAMOUNT & IMPERIAL
A
F-
0 ry
0 m
Q
Ld
LIJ
V)
CITY OF DOWNEY — —

CITY OF SOUTH GATE
. ::N- -

GARDENDALE ST
IXI LXI ._�
BIZ
Flo
�0:
voi a
00 1
CONSTRUCTION NOTES: (THIS SHEET ONLY):
11 FURNISH AND INSTALL NEW SINGLE MODE FIBER OPTICAL (SMFO) CABLE IN CONDUIT PER CONDUCTOR SCHEDULE.
❑2 FURNISH AND INSTALL NEW #6E PULL BOX WITH EXTENSION. PULL BOX COVER SHALL HAVE "COMMUNICATION" INSCRIBED ON LID.
❑3 COIL TWENTY FIVE (25) FEET OF SLACK SMFO IN TRAFFIC SIGNAL CABINET. COIL FIFTY (50) FEET OF SLACK SMFO CABLE IN EACH PULL BOX. COIL ONE HUNDRED (100) FEET OF SLACK CABLE IN EACH PULL BOX CONTAINING A SPLICE ENCLOSURE.

R4 FURNISH AND INSTALL NEW #6E PULL BOX. PULL BOX COVER SHALL HAVE "COMMUNICATION" INSCRIBED ON LID. FURNISH AND INSTALL NEW SPLICE ENCLOSURE IN PULL BOX. FUSION SPLICE NEW 12-STRAND SMFO DROP CABLE TO MAINLINE FIBER OPTIC CABLE. SEE FIBER ASSIGNMENT ON SHEETS 9-11 FOR DETAILS.
a5 FUSION SPLICE MAINLINE FIBER OPTIC CABLES IN SPLICE ENCLOSURE. SEE FIBER ASSIGNMENT ON SHEETS 9-11 FOR DETAILS.
61 FUSION SPLICE NEW 12-STRAND SMFO DROP CABLE TO MAINLINE FIBER OPTIC CABLE IN EXISTING SPLICE ENCLOSURE. SEE FIBER ASSIGNMENT ON SHEETS 9-11 FOR DETAILS.

R7 FURNISH AND INSTALL NEW 12-PORT FIBER PATCH PANEL WITH SC CONNECTORS IN EXISTING TRAFFIC SIGNAL CABINET. TERMINATE ALL STRANDS AND TEST.

F8 REMOVE AND SALVAGE EXISTING CONTROLLER. FURNISH AND INSTALL NEW McCAIN 2070 CONTROLLER WITH TSP COMPATIBLE OMNI-X FIRMWARE. FURNISH AND INSTALL NEW BLACK BOX MODEL 4E1082A FIBER CAPABLE ETHERNET SWITCH. SEE THE SPECIAL CONDITIONS.

R9 FURNISH & INSTALL LC TYPE SFP DUPLEX TRANSCEIVERS. INSTALL SC TO LC JUMPER CABLES FROM FIBER PATCH PANEL TO SWITCH.

CB INSTALL CONDUIT INTO EXISTING PULL BOX.

RLLI
Q
Lv
z
o I
R T GA DENDALE S _410
1 Q
U
0 Of
w
©L
1 1
-4 1� -

CITY OF DOWNEY

CITY OF PARAMOUNT
0 DO

CONDUCTOR SCHEDULE
CONDUCTOR/CABLE A IA2 IA3IA I A
FIBER OPTIC DISTRIBUTION (48 SMFO)
1 1(N)
N
1 N
-
-
-
-
-
-
-
FIBER OPTIC TRANSMISSION (24 SMFO)
1 -
1(E)
1(E)
-
-
-
-
-
-
-
FIBER OPTIC DROP (12 SMFO)
-
-
-
1(N)
1(N)
1(N)
1(N)
1(N)
1(N)
1(N)
1(N)
FIBER OPTIC DROP (6 SMFO)
-
I -I
-
1(R)
1(R)
1(R)
1(R)
1(R)
-
I -
I -
#10 TRACER WIRE
-
1(N)
1(N)
1(N)
1(N)
1(N)
1(N)
1(N)
1(N)
1(N)
1(N)
ti.YA mmmmmmmulmmNAN
" ' AWG SERVICE0000000©OOOI'
0 A
00©0©©©OOOOI
000000000©0'
0000000000�
PERCENT FILL (7.)
3 2
19 9
22 22
38 20
2 25
13 CONDUIT SIZE (INCH)
4 4N)*
3 3
3 3
3 2-3
3(N)
3 2-4
ALL CONDUITS, CONDUCTORS AND CABLES ARE EXISTING EXCEPT AS NOTED:
(N) = NEW
*INSTALL FOUR 1" HDPE CONDUITS.
1 213
1 NI
Ld
W
V)
Ld
W
—
(n
100% SUBMITTAL
Ll-
W
J
0 J
uj
m
uj
07 GRAPHIC SCALE
40 40 60 80 120
1 INCH = 40 FEET

I
v;
1--
Ld
w
w
U)
c�
w
0 am
Q
w
w
r)
�
GARDENDALE ST 8 8
—�— - - - -

CONDUCTOR SCHEDULE

CONDUCTOR/CABLE
iziooaoaaoo
10 FIBER OPTIC DISTRIBUTION (48 SMFO)
1(N)
-
-
-
-
-
-
-
-
-
FIBER OPTIC DROP (12 SMFO)
-
1(N)
1(N)
1(N)
1(N)
1(N)
1(N)
-
-
1(N)
#10 TRACERWIRE
11 (N)
1(N)
1(N)
11(N)
1(N)
1(N)
1(N)
-
-
1(N)
#14 TRAFFIC SIGNAL POWER - - 16 116 1 19 140 147 1 16 35 #6 AWG SERVICE
-
-
-
-
-
-
-
-
-
2 #10 AWG LUMINAIRES
-
-
3 3
3 4
1 -
3 -

TYPE B DLC
-
-
2 3
3 3
9 2
4 8
k

SIGNAL INTERCONNECT (SIC)
PERCENT FILL (7.)
2 X
1 10
11 12
9 12
X
4 11

CONDUIT SIZE (INCH)
4-1
3(N)
3 3
3 2-3
2-3

1.5 2-3
2-3
ALL CONDUITS, CONDUCTORS AND CABLES ARE EXISTING EXCEPT AS NOTED:
(N) = NEW (R) = REMOVE
*INSTALL FOUR 1" HDPE CONDUITS.
z
0 nW
ry>

GARDENDALE ST
I
0 /1
W
W
Q
Q
n
W
CONSTRUCTION NOTES: (THIS SHEET ONLY)
❑1 FURNISH AND INSTALL NEW SINGLE MODE FIBER OPTICAL (SMFO) CABLE IN CONDUIT PER CONDUCTOR SCHEDULE.

Q2 FURNISH AND INSTALL NEW #6E PULL BOX WITH EXTENSION. PULL BOX COVER SHALL HAVE "COMMUNICATION" INSCRIBED ON LID.
❑3 COIL TWENTY FIVE (25) FEET OF SLACK SMFO IN TRAFFIC SIGNAL CABINET. COIL FIFTY (50) FEET OF SLACK SMFO CABLE IN EACH PULL BOX. COIL ONE HUNDRED (100) FEET OF SLACK CABLE IN EACH PULL BOX CONTAINING A SPLICE ENCLOSURE.
❑4 FURNISH AND INSTALL NEW #6E PULL BOX. PULL BOX COVER SHALL HAVE "COMMUNICATION" INSCRIBED ON LID. FURNISH AND INSTALL NEW SPLICE ENCLOSURE IN PULL BOX. FUSION SPLICE NEW 12-STRAND SMFO DROP CABLE TO MAINLINE FIBER OPTIC CABLE. SEE FIBER ASSIGNMENT ON SHEETS 9-11 FOR DETAILS.

R7 FURNISH AND INSTALL NEW 12-PORT FIBER PATCH PANEL WITH SC CONNECTORS IN EXISTING TRAFFIC SIGNAL CABINET. TERMINATE ALL STRANDS AND TEST. ❑8 REMOVE AND SALVAGE EXISTING CONTROLLER. FURNISH AND INSTALL NEW McCAIN 2070 CONTROLLER WITH TSP COMPATIBLE OMNI-X FIRMWARE. FURNISH AND INSTALL NEW BLACK BOX MODEL 4E1082A FIBER CAPABLE ETHERNET SWITCH. SEE THE SPECIAL CONDITIONS. a9 FURNISH & INSTALL LC TYPE SFP DUPLEX TRANSCEIVERS. INSTALL SC TO LC JUMPER CABLES FROM FIBER PATCH PANEL TO SWITCH.

CB INSTALL CONDUIT INTO EXISTING PULL BOX.
100% SUBMITTAL
::

W
w
V)
w
w
V)
w
_I
3-1
J
w
m
W
w
V)

GRAPHIC SCALE
40 40 60 80 120
1 INCH = 40 FEET
a
m
x
0 0
F
U
Z
U
w
W
m
1 U
0 m
a
a
cr
a
J
a
z
0 N
W
0 EXISTING SMFO TO HUB

LAKEWOOD & IMPERIAL
r� I
>. 3
Do I

CITY OF PARAMOUNT
I
I
\ O
1 1
4 1
1 \ 3 5 10 1

TO LAKEWOOD BLVD & ROSECRANS AVE
0 GARDENDALE ST
-----------------------
FIBER OPTIC DISTRIBUTION (48 SMFO)
1 1(N)
2(N)
FIBER OPTIC TRANSMISSION (24 SMFO
1 -
-
FIBER OPTIC DROP (12 SMFO)
-
-
-
%(N)l
#10 TRACERWIRE
-
1(N)
1(N)
PERCENT FILL (7.)
3 2
4 18
5 CONDUIT SIZE (INCH)
4 -1
(N)*
2 2

ALL CONDUITS, CONDUCTORS AND CABLES ARE EXISTING
EXCEPT AS NOTED:
(N) = NEW
*INSTALL FOUR 1" HDPE CONDUITS.
\ 7�
/2\f 1
�qb

FOSTER R
D
2 3
J
CITY OF DOWNEY _

CITY OF BELLFLOWER
CONSTRUCTION NOTES: (THIS SHEET ONLY)
Fil FURNISH AND INSTAU_ NEW SINGLE MODE FIBER OPTICAL (SMFO) CABLE IN CONDUIT PER CONDUCTOR SCHEDULE.
n FURNISH AND INSTALL NEW #6E PULL BOX WITH EXTENSION. PULL BOX COVER SHALL HAVE "COMMUNICATION" INSCRIBED ON LID.
n COIL TWENTY FIVE (25) FEET OF SLACK SMFO IN TRAFFIC SIGNAL CABINET. COIL FIFTY (50) FEET OF SLACK SMFO CABLE IN EACH PULL BOX. COIL ONE HUNDRED (100) FEET OF SLACK CABLE IN EACH PULL BOX CONTAINING A SPLICE ENCLOSURE.

FUSION SPUCE MAINLINE FIBER OPTIC CABLES IN SPUCE ENCLOSURE. SEE FIBER ASSIGNMENT ON SHEETS 9-11 FOR DETAILS.

F7 FURNISH AND INSTALL NEW 12-PORT FIBER PATCH PANEL WITH SC CONNECTORS IN EXISTING TRAFFIC SIGNAL CABINET. TERMINATE ALL STRANDS AND TEST. a8 REMOVE AND SALVAGE EXISTING CONTROLLER. FURNISH AND INSTALL NEW McCAIN 2070 CONTROLLER WITH TSP COMPATIBLE OMNI-X FIRMWARE. FURNISH AND INSTALL NEW BLACK BOX MODEL 4E1082A FIBER CAPABLE ETHERNET SWITCH. SEE THE SPECIAL CONDITIONS.

D9 FURNISH & INSTALL LC TYPE SFP DUPLEX TRANSCEIVERS. INSTALL SC TO LC JUMPER CABLES FROM FIBER PATCH PANEL TO SWITCH.
10 FURNISH AND INSTALL NEW SPLICE CLOSURE. FUSION SPLICE NEW 12-STRAND SMFO DROP CABLE TO MAINLINE FIBER OPTIC CABLE. SEE FIBER ASSIGNMENT ON SHEET NO. 9 FOR DETAILS.

CB INSTALL CONDUIT INTO EXISTING PULL BOX.
bi
Q
w
0 Of
0 LI
m
2 _ CITY OF DOWNEY _

CITY OF BELLFLOWER
100% SUBMITTAL
213
1 I-
Ld
Lit
U)
Ld
L�d
/�
V/

GRAPHIC SCALE
40 40 60 80 120
1 INCH = 40 FEET
x
W
C

w
Q
w
ry
w
ry
-
0 fy-
0 m
Q
W
W
0 CITY OF DOWNEY —

CITY OF BELLFLOWER
W
Q
rn
13171819
TI
n KA
1 FOSTER RD
d o o d es 7 9
CONSTRUCTION NOTES: (THIS SHEET ONLY)
a FURNISH AND INSTALL NEW SINGLE MODE FIBER OPTICAL (SMFO) CABLE IN CONDUIT PER CONDUCTOR SCHEDULE.
a FURNISH AND INSTALL NEW #6E PULL BOX WITH EXTENSION. PULL BOX COVER SHALL HAVE "COMMUNICATION" INSCRIBED ON LID.
�3 COIL TWENTY FIVE (25) FEET OF SLACK SMFO IN TRAFFIC SIGNAL CABINET. COIL FIFTY (50) FEET OF SLACK SMFO CABLE IN EACH PULL BOX. COIL ONE HUNDRED (100) FEET OF SLACK CABLE IN EACH PULL BOX CONTAINING SPLICE A ENCLOSURE.
❑4 FURNISH AND INSTALL NEW #6E PULL BOX. PULL BOX COVER SHALL HAVE "COMMUNICATION" INSCRIBED ON LID. FURNISH AND INSTALL NEW SPLICE ENCLOSURE IN PULL BOX. FUSION SPLICE NEW 12-STRAND SMFO DROP CABLE TO MAINLINE FIBER OPTIC CABLE. SEE FIBER ASSIGNMENT ON SHEETS 9-11 FOR DETAILS.
❑7 FURNISH AND INSTALL NEW 12-PORT FIBER PATCH PANEL WITH SC CONNECTORS IN EXISTING TRAFFIC SIGNAL CABINET. TERMINATE ALL STRANDS AND TEST. ❑8 REMOVE AND SALVAGE EXISTING CONTROLLER. FURNISH AND INSTALL NEW McCAIN 2070 CONTROLLER WITH TSP COMPATIBLE OMNI-X FIRMWARE. FURNISH AND INSTALL NEW BLACK BOX MODEL 4E1082A FIBER CAPABLE ETHERNET SWITCH. SEE THE SPECIAL CONDITIONS. ❑9 FURNISH & INSTALL LC TYPE SFP DUPLEX TRANSCEIVERS. INSTALL SC TO LC JUMPER CABLES FROM FIBER PATCH PANEL TO SWITCH.

CB INSTALL CONDUIT INTO EXISTING PULL BOX.

CITY OF DOWNEY

CITY OF BELLFLOWER
W
Q
V)
cy
W
O
0-t

FOSTER RD
W
Q
W
0 m
Z
Q
F-
W
Q
W
0 L-
Q11IN

CONDUCTOR SCHEDULE

CONDUCTOR/CABLE A Q Q
FIBER OPTIC DISTRIBUTION (48 SMFO)
1(N)
—
—
FIBER OPTIC DROP (12 SMFO)
—
1(N)
1(N)
#10 TRACERWIRE
1(N)
1(N)
1(N)
#14 TRAFFIC SIGNAL POWER I — I — 119
#6 AWG SERVICE
—
—
2 #10 AWG LUMINAIRES
—
—
2 #16 AWG VIDEO CAMERA CABLE
—
—
2 COAX CABLES — I — 1
PERCENT FILL (%)
X
X
X

CONDUIT SIZE (INCH)
(N)*
3(N)
2-3

ALL CONDUITS, CONDUCTORS AND CABLES ARE EXISTING
EXCEPT AS NOTED:
(N) = NEW
*INSTALL FOUR 1" HDPE CONDUITS.
100% SUBMITTAL
1 W
W
W
W
to
W
J
0 W
m
W
W
U)

GRAPHIC SCALE
40 40 60 80 120
1 INCH = 40 FEET

CONDUCTOR SCHEDULE
CONDUCTOR/CABLE JZ 1 JZ2 .

FIBER OPTIC DISTRIBUTION (48 SMFO)
1(N)
-
-
-
FIBER OPTIC DROP (12 SMFO)
-
1(N)
1(N)
1(N)
#10 TRACERWIRE
1(N)
1(N)
1(N)
1(N)
#6
AWG

SERVICE
-
-
-
2 #10
AWG

LUMINAIRES
-
-
2 -
#16
AWG

VIDEO CAMERA CABLE
-
-
4 4
EVPE CABLES - I - 1 4 4
PERCENT FILL (7.)
2 2
22 38

CONDUIT SIZE (INCH)
(N)*
3(N)
2-4
2-3

ALL CONDUITS, CONDUCTORS AND CABLES ARE EXISTING EXCEPT AS NOTED:
(N) = NEW
*INSTALL FOUR 1" HDPE CONDUITS.

W
Q
Z
Q
C�
ry
ry
0 U
u )
Ld
V)
W
W
V)
—

FOSTER RD
I
CITY OF DO*

CITY OF BELLFL
CONSTRUCTION NOTES:
(THIS SHEET ONLY)
F1 FURNISH AND INSTALL NEW SINGLE MODE FIBER OPTICAL (SMFO) CABLE IN CONDUIT PER CONDUCTOR SCHEDULE.
a2 FURNISH AND INSTALL NEW #6E PULL BOX WITH EXTENSION. PULL BOX COVER SHALL HAVE "COMMUNICATION" INSCRIBED ON LID.

F3 COIL TWENTY FIVE (25) FEET OF SLACK SMFO IN TRAFFIC SIGNAL CABINET. COIL FIFTY (50) FEET OF SLACK SMFO CABLE IN EACH PULL BOX. COIL ONE HUNDRED (100) FEET OF SLACK CABLE IN EACH PULL BOX CONTAINING A SPLICE ENCLOSURE.

FURNISH AND INSTALL NEW #6E PULL BOX. PULL BOX COVER SHALL HAVE "COMMUNICATION" INSCRIBED ON LID. FURNISH AND INSTALL NEW SPLICE ENCLOSURE IN PULL BOX. FUSION SPLICE NEW 12-STRAND SMFO DROP CABLE TO MAINLINE FIBER OPTIC CABLE. SEE FIBER ASSIGNMENT ON SHEETS 9-11 FOR DETAILS.
[7 FURNISH AND INSTALL NEW 12-PORT FIBER PATCH PANEL WITH SC CONNECTORS IN EXISTING TRAFFIC SIGNAL CABINET. TERMINATE ALL STRANDS AND TEST.

D8 REMOVE AND SALVAGE EXISTING CONTROLLER. FURNISH AND INSTALL NEW McCAIN 2070 CONTROLLER WITH TSP COMPATIBLE OMNI-X FIRMWARE. FURNISH AND INSTALL NEW BLACK BOX MODEL 4E1082A FIBER CAPABLE ETHERNET SWITCH. SEE THE SPECIAL CONDITIONS. ❑9 FURNISH & INSTALL LC TYPE SFP DUPLEX TRANSCEIVERS. INSTALL SC TO LC JUMPER CABLES FROM FIBER PATCH PANEL TO SWITCH.

CB INSTALL CONDUIT INTO EXISTING PULL BOX.
100% SUBMITTAL

GRAPHIC SCALE
40 40 60 80 120
1 INCH = 40 FEET
J
1-
m
R
K
O
O
Z1
O
F
a
U
Z
4'
W
m
C.

H
0 m
a
0 gr
a
z
2 in
0 z
W
G

CONSTRUCTION NOTES: (THIS SHEET ONLY)
F1 FURNISH AND INSTALL NEW SINGLE MODE FIBER OPTICAL (SMFO) CABLE IN CONDUIT PER CONDUCTOR SCHEDULE.
❑3 COIL TWENTY FIVE (25) FEET OF SLACK SMFO IN TRAFFIC SIGNAL CABINET. COIL FIFTY (50) FEET OF SLACK SMFO CABLE IN EACH PULL BOX. COIL ONE HUNDRED (100) FEET OF SLACK CABLE IN EACH PULL BOX CONTAINING A SPLICE ENCLOSURE.
77 FURNISH AND INSTALL NEW 12-PORT FIBER PATCH PANEL WITH SC CONNECTORS IN EXISTING TRAFFIC SIGNAL CABINET. TERMINATE ALL STRANDS AND TEST.

FURNISH AND INSTALL NEW BLACK BOX MODEL 4E1082A FIBER CAPABLE ETHERNET SWITCH. SEE THE SPECIAL CONDITIONS.
❑9 FURNISH & INSTALL LC TYPE SFP DUPLEX TRANSCEIVERS. INSTALL SC TO LC JUMPER CABLES FROM FIBER PATCH PANEL TO SWITCH.
10 FURNISH AND INSTALL NEW SPLICE CLOSURE. FUSION SPLICE NEW 12-STRAND SMFO DROP CABLE TO MAINLINE FIBER OPTIC CABLE. SEE FIBER ASSIGNMENT ON SHEET NO. 9 FOR DETAILS.

TO LAKEWOOD BLVD & GARDENDALE ST

PROJECT LIMIT
VE

CONDUCTOR SCHEDULE
CONDUCTOR/CABLE 3 Q Q
FIBER OPTIC DISTRIBUTION (48 SMFO)
1 -
-
FIBER OPTIC TRANSMISSION (24 SMFO)
1 -
-
FIBER OPTIC DROP (12 SMFO)
-
1(N)
1(N)
FIBER OPTIC DROP (6 SMFO)
-
1(R)
11(R)
#10 TRACERWIRE
-
il(N)11(N)
#14 TRAFFIC SIGNAL POWER I - I - 145
#6 AWG SERVICE
-
-
3 #10 AWG LUMINAIRES
-
-
3 TYPE B DLC
-
-
10 SIGNAL INTERCONNECT (12/19SIC) - - 2
PERCENT FILL (7.)
3 2
21 CONDUIT SIZE (INCH)
4 3
2-3

ALL CONDUITS, CONDUCTORS AND CABLES ARE
EXISTING EXCEPT AS NOTED:
(N) = NEW (R) = REMOVE
100% SUBMITTAL

GRAPHIC SCALE
40 40 60 80 120
1 INCH = 40 FEET
m
x
0 0
F
Q
v
z
U
W
m
U
0 ix
a
0 a
J
Q
Z
0 N
IF
as
Z
Q
P5
W
0 �r

CONSTRUCTION NOTES: (THIS SHEET ONLY)
m FURNISH AND INSTALL NEW SINGLE MODE FIBER OPTICAL (SMFO) CABLE IN CONDUIT PER CONDUCTOR SCHEDULE.

Q COIL TWENTY FIVE (25) FEET OF SLACK SMFO IN TRAFFIC SIGNAL CABINET. COIL FIFTY (50) FEET OF SLACK SMFO CABLE IN EACH PULL BOX. COIL ONE HUNDRED (100) FEET OF SLACK CABLE IN EACH PULL BOX CONTAINING A SPLICE ENCLOSURE.

R5 FUSION SPLICE MAINLINE FIBER OPTIC CABLES IN SPLICE ENCLOSURE. SEE FIBER ASSIGNMENT ON SHEETS 9-11 FOR DETAILS.

F9 FURNISH & INSTALL LC TYPE SFP DUPLEX TRANSCEIVERS. INSTALL SC TO LC JUMPER CABLES FROM FIBER PATCH PANEL TO SWITCH.
10 FURNISH AND INSTALL NEW SPLICE CLOSURE. FUSION SPLICE NEW 12-STRAND SMFO DROP CABLE TO MAINLINE FIBER OPTIC CABLE. SEE FIBER ASSIGNMENT ON SHEET NO. 9 FOR DETAILS.

FIRESTONE BLS
� 3 1
3 1
1 4 3
3 3 1
�i
2 1
3 CONDUCTOR SCHEDULE
CONDUCTOR/CABLE QQ 3 QQ
FIBER OPTIC DISTRIBUTION (48 SMFO)
1 1(N)
-
-
-
FIBER OPTIC TRANSMISSION (24 SMFO)
1 1(N)
-
-
-
FIBER OPTIC DROP (12 SMFO)
-
-
1(N)
1(N)
1(N)
#10 TRACERWIRE
-
1(N)
1(N)
1(N)
1(N)
#6 AWG SERVICE
-
-
-
-
2 #10 AWG LUMINAIRES
-
-
-
-
2 VDS CABLES I - I - I - I - 4
PERCENT FILL (%)
3 3
5 1
21 CONDUIT SIZE (INCH)
4 4
2 4
2-4

ALL CONDUITS, CONDUCTORS AND CABLES ARE EXISTING
EXCEPT AS NOTED:
(N) = NEW
W
Q
2 - 12 STRAND SMFO DROP
J'
100% SUBMITTAL

GRAPHIC SCALE
40 40 60 80 120
1 INCH = 40 FEET

TO HUB

PARAMOUNT BLVD/

IMPERIAL BLVD
` � PNITN
�0 02
N N N a
W N W -*
11 �
I I
I I
I
IIII

GARDENDALE ST

PARAMOUNT BLVD

TRAFFIC CABINET DETAIL

EXISTING
2 F CABLE

CONTROLLER

EXISTING
N

NETWORK

I SWITCH
12—PORT FIBER

PATCH PANEL EXISTING
t SFPs
• --- Ll
• — I OEXISTING
``SPLICE ALL 87RANDS 10

EXISTING SPLICE ENCLOSURE

EXISTING FIBER VAULT
r
48 GARDENDALE ST/

DOWNEY AVE

TRAFFIC CABINET DETAIL
PROP.

CAM
NEI

CONTROLLER
W�
PILOPOBEI►
tS 1*-PORT FBOt
I PAICH�PANEL A
t P,fe r—n--�
AL
PROPOSED PROPOSEa�FBER VVAHLLTT�

FIRESTONE BLVD

FIRESTONE BLVD/

ANDREWS LN

TRAFFIC CABINET DETAIL
EX.
x CABLE
EXISTING 2070LX

CONTROLLER EXISTING
04 NE

TWORK BTTCH
?S 12-POILf FIBERmo

PATCH P
t -I
I13 fl
s PROPOM
• PAIOI CABLES
a
I
PROPOSED � MAX
a
a

PROPOSED

PATH CABLES

GARDENDALE STREET
BROOKSHIREGAVEESOMMERSET RANCH RD GABARUN A ET/ LAKEWOOD BLVD COLUMBIA WAY—CLARK AVE BELLFLOWER DBLVD

TRAFFIC CABINET DETAIL TRAFFIC CABINET DETAIL TRAFFIC CABINET DETAIL TRAFFIC CABINET DETAIL TRAFFIC CABINET DETAIL PROP. PROP. PROP. PROP. PROP.
c B� __ CAKE _� � CABLES Z � � cCAAeBLEE Z � CABLE
f
t I I I • PROPOSED SPLICE

EXISTING SPLICE
x-- - 6

EXISTING
48 SMFO
� I
I

EXISTING
oR 24 SMFO
pmpom
DOSING FM V�IWLLTT �
100% SUBMITTAL
m
N
0 o_
I
a
U
Z
U
O:

W
m
F�
U
a
0 Ir
a
J
Z
C9
N
F
N
Z
IY
W
G
U

48-STRAND SMFO DISTRIBUTION CABLE

LAKEWOOD BLVD FROM ROSECRANS AVE TO LAKEWOOD

HUB CABINET
CABLE DIRECTION: NORTH

CONNECT TO LAKEWOOD BLVD/IMPERIAL HWY HUB
CABLE
NO.

BUNDLE
NO.

FIBER NO.

COLOR

FUNCTION

DESCRIPTION
16A
1 1
BLUE
TX/RX

LAKEWOOD BLVD/ROSECRANS BLVD
2 ORANGE
TX/RX

LAKEWOOD BLVD/GARDENDALE BLVD
3 GREEN
TX/RX

GARDENDALE ST/BARLIN AVE
4 BROWN
TX/RX

FOSTER RD/COLUMBIA WAY-CLARK AVE
5 SLATE
TX/RX

FOSTER RD/BELLFLOWER BLVD
6 WHITE
SPARE
7 RED
SPARE
-
g
BLACK
SPARE
g
YELLOW
SPARE
10 VIOLET
SPARE
11 ROSE
SPARE
12 AQUA
SPARE
2 1
BLUE
SPARE
_
2 ORANGE
SPARE
3 GREEN
SPARE
4 BROWN
SPARE
5 SLATE
SPARE
6 WHITE
SPARE
7 RED
SPARE
-
g
BLACK
SPARE
g
YELLOW
SPARE
10 VIOLET
SPARE
11 ROSE
SPARE
12 AQUA
SPARE
3 1
BLUE
SPARE
_
2 ORANGE
SPARE
3 GREEN
SPARE
4 BROWN
SPARE
5 SLATE
SPARE
6 WHITE
SPARE
7 RED
SPARE
g
BLACK
SPARE
g
YELLOW
SPARE
10 VIOLET
SPARE
11 ROSE
SPARE
12 AQUA
SPARE
4 1
BLUE
SPARE
2 ORANGE
SPARE
3 GREEN
SPARE
4 BROWN
SPARE
5 SLATE
SPARE
6 WHITE
SPARE
7 RED
SPARE
g
BLACK
SPARE
g
YELLOW
SPARE
10 VIOLET
SPARE
11 ROSE
SPARE
12 AQUA
SPARE
48-STRAND SMFO DISTRIBUTION CABLE

GARDENDALE ST FROM BARLIN AVE TO LAKEWOOD BLVD
CABLE DIRECTION: EAST

CONNECT TO LAKEWOOD BLVD/IMPERIAL HWY HUB
CABLE
NO.

BUNDLE
NO.

FIBER NO.

COLOR

FUNCTION

DESCRIPTION
16B
1 1
BLUE
SPARE
2 ORANGE
SPARE
3 GREEN
SPARE
4 BROWN
SPARE
5 SLATE
TX/RX

GARDENDALE ST/BARLIN AVE
6 WHITE
SPARE
7 RED
SPARE
-
g
BLACK
SPARE
g
YELLOW
SPARE
10 VIOLET
SPARE
11 ROSE
SPARE
12 AQUA
SPARE
2 1
BLUE
SPARE
2 ORANGE
SPARE
3 GREEN
SPARE
4 BROWN
SPARE
5 SLATE
SPARE
6 WHITE
SPARE
7 RED
SPARE
g
BLACK
SPARE
g
YELLOW
SPARE
10 VIOLET
SPARE
11 ROSE
SPARE
12 AQUA
SPARE
3 1
BLUE
SPARE
2 ORANGE
SPARE
3 GREEN
SPARE
4 BROWN
SPARE
5 SLATE
SPARE
6 WHITE
SPARE
7 RED
SPARE
g
BLACK
SPARE
g
YELLOW
SPARE
10 VIOLET
SPARE
11 ROSE
SPARE
12 AQUA
SPARE
4 1
BLUE
SPARE
2 ORANGE
SPARE
3 GREEN
SPARE
4 BROWN
SPARE
5 SLATE
SPARE
6 WHITE
SPARE
7 RED
SPARE
g
BLACK
SPARE
g
YELLOW
SPARE
10 VIOLET
SPARE
11 ROSE
SPARE
12 AQUA
SPARE
48-STRAND SMFO DISTRIBUTION CABLE

GARDENDALE ST/FOSTER RD FROM BELLFLOWER BLVD TO LAKEWOOD BLVD CABLE DIRECTION: WEST

CONNECT TO LAKEWOOD BLVD/IMPERIAL HWY HUB
CABLE
NO.

BUNDLE
NO.

FIBER NO.

COLOR

FUNCTION

DESCRIPTION
1 1
BLUE
SPARE
2 ORANGE
SPARE
3 GREEN
SPARE
_
4 BROWN
SPARE
5 SLATE
SPARE
_
6 WHITE
SPARE
7 RED
TX/RX

FOSTER RD/COLUMBIA WAY-CLARK AVE
g
BLACK
TX/RX

FOSTER RD/BELLFLOWER BLVD
g
YELLOW
SPARE
10 VIOLET
SPARE
11 ROSE
SPARE
12 AQUA
SPARE
2 1
BLUE
SPARE
2 ORANGE
SPARE
3 GREEN
SPARE
4 BROWN
SPARE
5 SLATE
SPARE
6 WHITE
SPARE
7 RED
SPARE
g
BLACK
SPARE
g
YELLOW
SPARE
10 VIOLET
SPARE
11 ROSE
SPARE
12 AQUA
SPARE
16C
3 1
BLUE
SPARE
_
2 ORANGE
SPARE
3 GREEN
SPARE
4 BROWN
SPARE
5 SLATE
SPARE
6 WHITE
SPARE
7 RED
SPARE
g
BLACK
SPARE
g
YELLOW
SPARE
_
10 VIOLET
SPARE
11 ROSE
SPARE
12 AQUA
SPARE
4 1
BLUE
SPARE
2 ORANGE
SPARE
3 GREEN
SPARE
-
4 BROWN
SPARE
5 SLATE
SPARE
6 WHITE
SPARE
7 RED
SPARE
g
BLACK
SPARE
g
YELLOW
SPARE
10 VIOLET
SPARE
11 ROSE
SPARE
12 AQUA
SPARE
J
_F
m
m
x
0 0
I
Z
O
F
a
U
Z
m
U
W
m
i
F-
U
O
Ix
a
0 W
a
J
Q
Z
O
N
H
Z
fE
W
0 U

48-STRAND SMFO DISTRIBUTION CABLE

PARAMOUNT BLVD FROM GARDENDALE ST TO PARAMOUNT BLVD HUB CABINET CABLE DIRECTION: NORTH

CONNECT TO PARAMOUNT BLVD/IMPERIAL HWY HUB
CABLE
NO.

BUNDLE
NO.

FIBER NO.

COLOR

FUNCTION

DESCRIPTION
15 1
1 BLUE
TX/RX

PARAMOUNT BLVD/GARDENDALE ST
2 ORANGE
TX/RX

PARAMOUNT BLVD/IMPERIAL HWY
3 GREEN
TX/RX

GARDENDALE ST/DOWNEY AVE
4 BROWN
TX/RX

GARDENDALE ST/BROOKSHIRE AVE-SOMMERSET RANCH RD
5 SLATE
SPARE
6 WHITE
SPARE
7 RED
SPARE
g
BLACK
SPARE
g
YELLOW
SPARE
10 VIOLET
SPARE
11 ROSE
SPARE
12 AQUA
SPARE
2 1
BLUE
SPARE
_
2 ORANGE
SPARE
3 GREEN
SPARE
4 BROWN
SPARE
5 SLATE
SPARE
6 WHITE
SPARE
7 RED
SPARE
g
BLACK
SPARE
g
YELLOW
SPARE
-
10 VIOLET
SPARE
11 ROSE
SPARE
12 AQUA
SPARE
3 1
BLUE
SPARE
_
2 ORANGE
SPARE
3 GREEN
SPARE
4 BROWN
SPARE
5 SLATE
SPARE
6 WHITE
SPARE
7 RED
SPARE
-
g
BLACK
SPARE
g
YELLOW
SPARE
_
10 VIOLET
SPARE
11 ROSE
SPARE
12 AQUA
SPARE
4 1
BLUE
SPARE
_
2 ORANGE
SPARE
3 GREEN
SPARE
4 BROWN
SPARE
5 SLATE
SPARE
6 WHITE
SPARE
7 RED
SPARE
g
BLACK
SPARE
g
YELLOW
SPARE
10 VIOLET
SPARE
11 ROSE
SPARE
12 AQUA
SPARE
48-STRAND SMFO DISTRIBUTION CABLE

GARDENDALE ST FROM BROOKSHIRE AVE TO PARAMOUNT BLVD CABLE DIRECTION: WEST

CONNECT TO PARAMOUNT BLVD/IMPERIAL HWY HUB
CABLE
NO.

BUNDLE
NO.

FIBER NO.

COLOR

FUNCTION

DESCRIPTION
16B
1 1
BLUE
SPARE
2 ORANGE
SPARE
3 GREEN
TX/RX

GARDENDALE ST/DOWNEY AVE
4 BROWN
TX/RX

GARDENDALE ST/BROOKSHIRE AVE-SOMMERSET RANCH RD
5 SLATE
SPARE
6 WHITE
SPARE
7 RED
SPARE
g
BLACK
SPARE
g
YELLOW
SPARE
10 VIOLET
SPARE
11 ROSE
SPARE
12 AQUA
SPARE
2 1
BLUE
SPARE
2 ORANGE
SPARE
3 GREEN
SPARE
4 BROWN
SPARE
5 SLATE
SPARE
6 WHITE
SPARE
7 RED
SPARE
g
BLACK
SPARE
g
YELLOW
SPARE
10 VIOLET
SPARE
11 ROSE
SPARE
12 AQUA
SPARE
3 1
BLUE
SPARE
2 ORANGE
SPARE
3 GREEN
SPARE
4 BROWN
SPARE
5 SLATE
SPARE
6 WHITE
SPARE
7 RED
SPARE
g
BLACK
SPARE
g
YELLOW
SPARE
10 VIOLET
SPARE
11 ROSE
SPARE
12 AQUA
SPARE
4 1
BLUE
SPARE
2 ORANGE
SPARE
3 GREEN
SPARE
4 BROWN
SPARE
5 SLATE
SPARE
6 WHITE
SPARE
7 RED
SPARE
g
BLACK
SPARE
g
YELLOW
SPARE
-
10 VIOLET
SPARE
11 ROSE
SPARE
12 AQUA
SPARE
100% SUBMITTAL
J
Q
m
a
O
O
1 z
O
F
4c
V
z
2 U
Ld
W
m
A
H
U
O
a
0 ir
a
4 z
0 U)
0 z
a
Ex
W
0 'u'

DETAIL A

NO SCALE
INSTALLATION NOTES:

STUD BOLTS, NUTS AND WASHERS,

1. CONCRETE RING SHALL BE MINOR CONCRETE.

2. CONCRETE ENCASEMENT RING DIMENSION, D,
BOLTDOWN (4X)
TO BE EQUAL TO DESIGN PAVEMENT DEPTH.

DIVISION ID 3. PAVEMENT AND SUBGRADE TO BE AS DIRECTED
(AS SHOWN ON PLANS: B
TRAFFIC — FIBER) Y THE ENGINEER.

PULL BOX COVER
PULL BOX NOTE:

NON—SKID SURFACE ALL NEW PULL BOXES SHALL BE NO. 6 UNLESS NOTED OTHERWISE ON THE PLANS. NEW PULL BOXES,
LIFT(2X)) PIN EXTENSIONS, AND PULL BOX LIDS SHALL BE CHRISTY CONCRETE PRODUCTS, INC. (FL36X18 FOR BOX, FL36X8
TYPICAL NO. 6 /
FOR EXTENSION, AND FL36D FOR LID) OR CITY APPROVED
6E PULL BOX COVER
' EQUAL.

Nlk
N0. 6E

PULL BOX

DETAIL B

PUOLL BOX IL LIFTING BOLT INSTALLATION
�
2 EACH SIDE NO SCALE

OPEN BASE

WALL ASPHALT PAVEMENT
LIFTING BOLT TYPICAL NO. 6E PULL BOX CONCRETE RING AROUND VAULT OPEN BASE 2 EACH SIDE L30 1.,,/277 X 17 1 2 X 24 N OM I 35" _ WALL ° d
4 TYPICAL NO. 6 PULL BOX o d d a
(30 1 2 X 17 1 2 77 X 12 77N OM I N ALA SEE DETAIL a
4 °
°° d d
=III=III=III ° ° °
_ d
I M 11=1II=1 11— d d
22/� III=1 I I=1 I ICI i I-
71 SEE DETAIL B o a ;III=III=III=1 I I— d
;1 1IEEE III=1 11=1 1I—
=III=III=III=III— d _
=III= III=III=1I1=
2 4 // `=111-1 I I=1 I I-111=
TYPICAL NO. 6 & 6E PULL BOX

PLAN VIEW
0 0

INSTALLATION IN ASPHALT PAVEMENT

NO SCALE
12"
NO. 6E PULL BOX SIDE VIEW COMMUNICATION , .._ —, ,—, , , ° d ® 20K _ —III—I I 1—I °
N0. 6 PULL BOX SIDE VIEW 7 1 }
III=III=III
o I 1=1 I I —I 11
p O �; —III—III—I °
,. °
° y y� =1 �1=1 ° d a°
30 112
" i ;III —III —III —III— �, °
=III-III-III=III— ° °
III—II1—III—III = ° — — 0
TYPICAL NO. 6 8 6E PULL B O X COVER I I(-1 =IIIz
III—i I MI 11—III—III—III _-- M
U
N 0. 6 PULL BOX END VIEW
W
m

INSTALLATION I N COMPACTED EARTH
N 0 SCALE
N0. 6E PULL BOX END VIEW 0
0 a
100% SUBMITTAL
0 PLANS a

PREPARED BY
•. •o • • • DESIGNED BY. DCS No REVISION DATE BY APP VERT SCALE: N Underground Service Alert uf`�y 11/30/2022 CITY OF DOWNEY CITY OF DOWNEY o SCALE p� iteri5
,7Up C9rt�eA-"WveMm, Suite,pp APPROVEDEPT. OF PUBLIC WORKS ENGINEERING DIVISION HORIZ SCALE: No i' Sara. AM, CA W7053551
Call: TOLL FREE P� ,M) 7o �-/+�� SCALE N
ra Fax �'270�481 DRAWN BY: DCS 6/26/2023 r 50368 s ~
► * '� v31-23 4;j

ECTOR OF PUBLIC WORKS RCE DATE CAPITALIIDE IMPROVEMENT

PROJECT
PRIORITY O. 17-07 <
(800)227-2600 ,,y `� UNDER THE SUPERVISION of SHEET � 2 OF � 5 SHEETS � ' CHECKED BY: PMF
TWO WORIQNG DAYS BEFORE You DIG � �-� � 28 June 2023 6/27/2023 7l15Z ?--le ?7 o PAUL M. FRISUE RCE 2982 DATE DIRECTOR OF PUBLIC WORKS/CITY ENGINEER RCE DATE EQUIPMENT INSTALLATION DETAILS — PULL BOX DETAILS DWG. N0. 3-48-29 0 U

DROP SMFO CABLE
CONDO

MAINLINE SIB
CABLE
A IAil IAI(- C^A Ar/"\ !-% A M1 r C`I_ACK

CONDUIT
\AAINLINE SMFO
CABLE

PULL BOX WITH NO SPLICE

NO SCALE
15 FEET SLACK
TO SPLICE CLOSUR\"",,FOR EACH CABLE

OUTSIDE PULL BOX
STEP 1
CLOSURE SHALL BE SCALE]

AND ENCAPSULATED USING
RE —ENTERABLE COMPOUND

INCOMING
CABLE

INSTALL SMFO CAB
STEP 3

OUTGOING
CABLE
SPLICE

CLOSURE

OUTGOING

CABLE IN

SPLICE PROCEDURE

NO SCALE

SPLICE CLOSURE

SEE SPLICE PROCEDUR

FOR DETAIL

CONDUIT

MAINLINE SMF
CABLE
15 FEET SLACK

FOR EACH CABL

OUTSIDE PULL E

PIGTAILS TO EN

SPLICE CLOSURE

INCOMING

CABLE IN
SPLICE CLOSURE Al

EXCESS CABLE ARE

BE COILED AND PL,
INSIDE GROUND B0;

CONDUIT
FIGURE 8 COIL OF

CABLE NOT SHOWN

FOR CLARITY

PULL BOX WITH SPLICE

NO SCALE
STEP 2
DROP CABLE STEP 4
COIL 25' OF DISTRIBUTION
CABLE & 15' OF DROP CABLE
IN PULL BOX AS SLACK. SEE

CONDUCTOR SCHEDULE ON PLANS

FOR CABLES INSTALLED IN
PULL BOX.

CONDUIT

MAINLINE SMFO CABLE

CABLES NOTING DIRECTION AND FIBER COUNT

SECURE WITH CABLE STRAPS

OUTGOING
CABLE

OUTGOING
CABLE
100% SUBMITTAL
J
m
M
N
K
O
O
Zi
O
F
a
U
z
V
W
m
i
F-
U
O
W
a
0 w
a
4 z
O
U)
H
us
z
Q
W
0 1,
■

DETAIL A

CONDUIT AND PULL BOX INSTALLATION

NO SCALE

ROADWAY -

EDGE OF CURB

SIDEWALK
w , •
rl A\/ (- A A f' K 1 -r

STANDARD DEPTH

AS PER SPECIAL PROVISIONS

PAVEMENT

MAINLINE SMFO CABLE

IN MICRODUCT
o
- - •
•
NO. 6 PULL BOX

TYPICAL ORIENTATION (PLAN VIEW

SIDEWALK
• - • .
• . , • . • .

NUMBER AND 1

SIZE OF CONDUIT

AS NOTED ON PLANS
I MAX 45°

STANDARD DEPTH

AS PER SPECIAL PROVISIONS

TOP FLUSH WITH SURROUNDING GRADE

MAINLINE SMFO CABLE SLACK

WITHIN MICRODUCT COUPLER

SECTION A- A
PULL BOX NO. 6

NUMBER AND

SIZE OF CONDUIT

AS NOTED ON PLANS
MIN R=3'
MAX 450

MAINLINE SMFO CABLE

IN MICRODUCT

TOP FLUSH WITH SURROUNDING GRADE

MAINLINE SMFO CABLE SLACK

WITHIN MICRODUCT COUPLER
..
. .

I
II I I"I (I NUMBER AND

SIZE OF CONDUIT

AS NOTED ON PLANS
- 12" 1211-11 " -_
i + i III

SECTION A -A
PULL BOX NO. 6E
MIN R=3'
MAX 45°

MAINLINE SMFO CABLE

IN MICRODUCT

DETAIL B

TYPICAL' TRENCH CROSS SECTION

NO SCALE
rw1
v
2 'B'
O
12' MIN. 1' N
SAWCUT
EXIST. AC
EXIST. BASE

BACKFILL
PER STDS.
------
---

UTTER OR

CURB EDGE

DETAIL C

TYPICAL DIRECTIONAL DRILL UNDER

PAVEMENTZSIDEWALK

NO SCALE
z
N
3" HDPE CC

OR AS NOTED ON
kv
TOP OF
TUNNEL

DIAMETER TO BE
'ED BY ENGINEER

DETAIL D

PULL BOX REMOVAL & CONDUIT CONNECTION

NO SCALE
r-EXISTING PAVEMENT

REMOVE EXISTING

PULL BOX

CONNECT INTO

EXISTING CONDUIT
-PROPOSED

CONDUIT

EXISTING EXISTING

CONDUIT CONNECT INTO CONDUIT

EXISTING

CONDUIT
NOTES:
(i BASE A.C. TRENCH IN FLUSH WITH ADJACENT SURFACE PRIOR TO COLD PLANING AND FINISH PAVING. COLD PLANE A MINIMUM OF 4' WIDE (CENTERED ON TRENCH) AND REPLACE A.C.

Q REMOVE AND REPLACE A.C. TO EDGE OF GUTTER (TO CURB FACE IF NO GUTTER EXISTS) OR TO ADJACENT TRENCH EDGE LINE WHERE 'B' IS LESS THAN 36".

Q TYPE 1 SLURRY SEAL SHALL BE APPLIED TO ALL FINISH TRENCH SURFACES (MIN. 6" BEYOND A.C. JOIN LINE).

Q IF TRENCHING BY CITY APPROVAL IS WITHIN A STREET COVERED BY A PAVEMENT CUT MORATORIUM PER HBMC CHAPTER 12.13, A TYPE 1 SLURRY SEAL SHALL BE APPLIED TO THE LIMITS REQUIRED BY THE CITY ENGINEER.
100% SUBMITTAL
J
I-
m
a
x
0 ASSEP
M)

DETAIL A

TYPICAL TSP EQUIPMENT INSTALLATION

NO SCALE

DETAIL C

PANEL ANTENNA ASSEMBLY ON SIGNAL MAST ARM

NO SCALE

TYPICAL ORIENTATION (PLAN VIEW

PELCO BRACKET

ON SIGNAL

MAST ARM
( NOTE 3 )
C-1
'A
204/508 GHz

PANEL ANTENNA
(NOTE 4)
-LMR 400 COAX
BLE TO RADIO If

ENCLOSURE
(NOTES 4,5,6)
PELCO
SECTION C— C
( NOTE 3 )
1Y" DIA.

GALVANIZED

MAXIMUM
M
EMT

DETAIL B

RADIO ENCLOSURE ON SIGNAL MAST ARM
Nf1 ' CrAI F
'PICAL ORIENTATION (PLAN VIEW)
5 0 8GHz
NTENNA
SIGNAL
ST ARM
ABLE
IBLY
,5,6)
ITDOOR CAT6 TO
►E IN TRAFFIC
'NAL CABINET
OTE 1)
r B

PRE-ASSEMBLED

ENCLOSURE ON

MAST ARM
(NOTE 25657)
CAT6 TO POE IN

TRAFFIC SIGNAL

CABINET
g (NOTES 1,6,7)
OU TD

ENCLOSURI
SIGN
SECTION B— B

PRE -ASSEMBLED
5 0 8GHz

OMNIDIRECTIONAL

ANTENNA

TRAFFIC SIGNAL

MAST ARM
4- LM R 400

COAX CABLE

TO ANTENNA

ASSEMBLY
(NOTES 4,5,6)

PRE -ASSEMBLED
LMR400 COAX TO

OMNIDIRECTIONAL

ANTENNA
OTES (THIS SHEET ONLY):

Q CONTRACTOR SHALL FURNISH AND INSTALL OUTDOOR -RATED CAT6 CABLE BETWEEN MAST ARM MOUNTED TSP EQUIPMENT AND TRAFFIC SIGNAL CONTROLLER CABINET.

Q CONTRACTOR SHALL INSTALL

CITY -PROVIDED
(PRE -ASSEMBLED)

ENCLOSURE USING
"39-POLE MOUNT -BRACKET"

AND HARDWARE

ON SIGNAL MAST

ARM PER MANUFACTURER
SPECIFICATIONS.

Q CONTRACTOR SHALL INSTALL CITY -PROVIDED "PELCO ASTRO-BRACKET AB-0506" MOUNTING

ON MAST ARM AND INSTALL CITY -PROVIDED PANEL ANTENNA ASSEMBLY IN BRACKET PER MANUFACTURER'S SPECIFICATION.

Q CONTRACTOR SHALL INSTALL CITY -PROVIDED COAX CABLES BETWEEN ENCLOSURE AND ANTENNA ASSEMBLY ON MAST ARM.

Q CONTRACTOR SHALL CONNECT COAX CABLES TO THE ANTENNA PANELS AND ENCLOSURE AS SPECIFIED BY CITY. SEAL ALL COAX CONNECTORS WITH CITY -PROVIDED OUTDOOR -RATED SELF -FUSING SILICONE RUBBER TAPE. SECURE COAX CABLES USING OUTDOOR -RATED TIE WRAPS.

Q CONTRACTOR SHALL SEAL ALL OPENINGS TO PREVENT WATER INTRUSION. SECURE CABLES WITH OUTDOOR -RATED TIE WRAPS.

Q CONTRACTOR SHALL CONNECT OUTDOOR CAT6 CABLE TO ENCLOSURE USING CITY -PROVIDED WATERPROOF BOOT TO PREVENT WATER INTRUSION.
s0 CONTRACTOR SHALL INSTALL POE INJECTOR IN CABINET. CONNECT OUTDOOR CAT6 TO POE AND CONNECT POE POWER PLUG TO EQUIPMENT RECEPTACLE. CONNECT CAT6A PATCH CHORD FROM POE TO CITY DESIGNATED PORT ON EXISTING NETWORK SWITCH. SECURE CABLES WITH TIE WRAPS. COORDINATE WITH CITY TO VERIFY CONNECTIVITY TO RADIO.

DETAIL D

POE INJECTOR IN TRAFFIC SIGNAL CABINET

NO SCALE
100% SUBMITTAL

OFF FOR FINAL
DOOR CAT6 CABLE
ER + DATA OUT

SIGNAL POLE

POE INJECTOR
( NOTE 8 )
.R TO

DMENT OUTLET

BELL GARDENS
tl
IN
aLIJ
kEi
Emmm
mm
El

CITY OF DOWNEY

DEPARTMENT OF PUBLIC WORKS
.................. 111- ------
CAPITAL IMPROVEMENT PROJECT NO. 17-07
Im

CITYWIDE TRANSIT PRIORITY PROJECT
sm"m

NORWALK
mom=
LEGEND
'OGNALIzo MTERSECTiONS
DOWNEY UNK NORTH WEST ROIfl'E

DOWNEY UNK NORTH EAST ROUTE

DOWNEY LINK SOUTH WEST ROUTE

DOWNEY UNK SOUTH EAST ROUTE

METRO ROUTES

STREETS

CITY BOUNDARY
EXRERNG FIE COMMUNtCATIONS

FUTURE TO COMMUMCAPONS

ENGINEERING DIVISION

ATTACHMENT B

LOCATION MAP

Capital Improvement Project No. 17.07
Citywide Bus Signal Priority Project

BID SUMMARY
August 10, 2023
Item
No.

Description
Qty.

Unit
International Line Builders, Inc.

Select Electric, Inc.

Baker Electric & Renewables LLC
Unit Price
Amount
Unit Price
Amount
Unit Price
Amount
BASE

BID ITEMS
1 Furnish and Install 4 - 1" HDPE Sch. 40 or 80 Conduits for Fiber -Optic Cables by Open Trenching or Jacking and Boring Method
9,705
LF
$ 55`.80
$ 541,539.00
$ 75.00
$ 727,875.00
$ 73.00
$ 708,465.00
2 Furnish and Install One 3" PVC Sch. 40 or 80 Drop Conduit for Fiber- Optic ables by Open Trenching or Jacking and Boring Method 95 LF
$ 155.00
$ 14,725.00
$ 126,00
$ 11,970.00
$ 216.00
$ 20,520.00
3 Furnish and Install Fiber -Optic Cable - 48 Fibers (Distribution Cable) Single Mode Fiber Optic (SMFO)
13,635
LF
$ 2.00
$ 27,270.00
$ 2,00
$ 27,270.00
$ 2.40
$ 32,724.00
4 Furnish and Install Fiber -Optic Cable - 24 Fibers (Transmission Cable) Single Mode Fiber Optic (SMFO)
1,205
LS
;$ 1i.80
$ 2,169.00
$ 4.00
$ 4,820.00
$ 7.00
$ 8,435.00
5 Furnish and Install Fiber -Optic Cable -12 Fibers (drop Cable) Single Mode Fiber Optic (SMFO)
2,265
LF
$ 1.70
$ 3,850.50 'i
$ 3.00
$ 6,795.00
$ 7.00
$ 15,855.00
6 Furnish and Install #10 Tracer Wire
10,097
LF
;$ 1':65
$ 16,660.05
$ 1.00
$ 10,097.00
$ 1.00
$ 10,097.00
7 Furnish and Install #6E Pull Box with Extension
20 EA
$ 2,209.00
$ 44,180.00 `,
$ 2,306.00
$ 46,120.00
$ 3,875.00
$ 77,500.00
8 Furnish and Install Splice Enclosure
8 EA
$ 1,196.00
$ 9,568,00
$ 1,829.00
$ 14,632.00
$ 2,333.00
$ 18,664.00
9 Furnish and Install 12-Port Fiber Patch Panel
9 EA
$ 551!00
$ 4,959.00
$ 788.00
$ 7,092.00
$ 2,235.00
$ 20,115.00
10 Remove Existing Twisted Pair cable
2,655
LF
'$ 1.00
$ 2,655.00
$ 1.00
$ 2,655.00
$ 1.00
$ 2,655.00
11 Furnish and Install 2070 Controller with McCain Omni -ex Firmware 9 EA
$ 8,844.00
$ 79,596,00 =
$ 8,285.00
$ 74,565.00
$ 7,862.00
$ 70,758.00
12 Furnish and Install Gigabit Ethernet Switch
8 EA
''.$ 2,795.00
$ 22,360.00
$ 2,824.00
$ 22,592.00
$ 2,679.00
$ 21,432.00
13 Furnish and Install BSP Equipment
1 LS
$ 733,217.00
$ 733,217.00
$ 741,074.00
$ 741,074.00
$ 703,120.00
$ 703,120.00
14 Procre and Deliver BSP Network Equipment
1 LS
$ 142,115.00
$ t 142,115.00
$ 143,638.00
$ 143,638.00
$ 136,285.00
$ 136,285.00
15 Testing, System, Integration and Documentation
1 LS
$ 148,388.00
$ 148,388.00
$ 126,037.00
$ 126,037.00
$ 131,721.00
$ 131,721.00
Total Base Bid - (Items 1 to 9)
$ 1,793,251.55
$ 1,967,232.00
$ 1,978,346.00
ADDITIONAL BIDS RECEIVED:

CONTRACTOR
Belco Electric, Inc.

Crosstown Electrical & Data, Inc.

HHS Construction LLC
DBX, Inc.

TOTAL BASE BID
$ 2,086,888.00
$ 2,266,948.00
$ 2,306,219.05
$ 2,472,889.00

ATTACHMENT C