Cities Index.
04. Approval of Water System Repairs at Lakewood Blvd and 5th St

Downey City Council
May 14, 2024

Document
04. Approval of Water System Repairs at Lakewood Blvd and 5th St
Meeting
May 14, 2024
Body
Downey City Council
Pages
2
Original file
3 KB
Text extracted from the city's file for reading and search. Open the original on lf.downeyca.org. That file is the official record.

Item No.

TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL

FROM: OFFICE OF THE CITY MANAGER
BY: MATTHEW BAUMGARDNER, P.E., DIRECTOR OF PUBLIC WORKS/

CITY ENGINEER

DATE: MAY 14, 2024

SUBJECT: APPROV AL OF WATER SYSTEM REPAIRS AT LAKEWOOD BOULEVARD AND 5TH STREET

EXECUTIVE SUMMARY

The City Council will consider approving water system repairs conducted by Williams Pipeline Contractors, Inc. in an amount of $85,769. The water improvements, which occurred at the intersection of Lakewood Boulevard and 5th Street, were necessary to restore water service, subgrade materials, and pavement in the area in response to an emergency water leak which was undermining soil and other subgrade materials in the vicinity of the leak due to the force of the water.

RECOMMENDATION

That the City Council:

Ratify the emergency purchase order with Williams Pipeline Contractors, Inc. for water system repairs at Lakewood Boulevard and 5th Street in the amount of $85,769.

BACKGROUND

The City’s recycled water system at Lakewood Boulevard and Fifth Street recently developed a water leak that undermined subgrade materials and street paving in the area. During such emergency water leak events, when the extent of repairs is large and/or there is a lack of staff to adequately respond to the site in a timely manner, contractors with past experience working in the City are contacted to determine their availability of crews to perform the work and their proximity to the site. Due to the scope of the work required to restore recycled water service, displaced subgrade, and damaged pavement, the City requested the assistance of Williams Pipeline Contractors, Inc., considering their past experience performing water improvements for the City and their quick response time, to conduct the time-sensitive emergency repair work. The repair work commenced on March 11, 2024 and was completed on March 19, 2024.

APPROVE WATER SYSTEM REPAIRS AT LAKEWOOD BOULEVARD AND 5TH STREET MAY 14, 2024
PAGE 2

ANALYSIS

The emergency repairs of the City’s recycled water system at Lakewood Boulevard and Fifth Street included: dewatering and hauling away of saturated subgrade and damaged asphalt paving; recycled water system repairs; placement and compaction of new subgrade materials; replacement of damaged asphalt pavement; traffic control; overtime work; and all other labor, materials, equipment, and subcontracting necessary to properly conduct the repair work.

The water system repairs at Lakewood Boulevard and 5th Street have been completed in accordance with City standards and staff recommends that the City Council approve a purchase order with Williams Pipeline Contractors, Inc. for the repairs.

CITY COUNCIL PRIORITIES

Quality of Life, Safety & Infrastructure

FISCAL IMPACT

The final cost of the repair work is $85,769, broken down as follow:

Item Amount
Emergency Repairs $85,769
Total Cost: $85,769

Sufficient water CIP funds are available to cover the total repair cost, as shown in the following table.

Account
No. Funding Source Amount
51-1-8674 FY 2023-24 Water System Improvements CIP $220,000 Total Funding: $220,000

ATTACHMENTS

None.

← All documents from this meeting