EXECUTIVE SUMMARY
The City Council will consider approving a construction contract with Sequel Contractors Incorporated for the construction of the Woodruff Avenue Street Improvement Project, Phase 2, between Washburn Road and Foster Road in order to complete street improvements within said portion of Woodruff Avenue including pavement rehabilitation given that its condition has deteriorated and has outlived its useful life as well as the construction of new raised landscaped median islands and active transportation improvements.
RECOMMENDATION
That the City Council:
1. Award Capital Improvement Project No. 14-14B to Sequel Contractors, Inc., the lowest responsive, responsible bidder for the total bid amount of $5,052,110 and waive any and all minor irregularities in the bidding documents as submitted by said bidder;
2. Authorize the City Manager, or his designee, to execute the construction contract with Sequel Contractors, Inc. in the amount of $5,052,110, including any non- substantive extensions, change orders and amendments up to the authorized budget amount of $6,231,321, and
3. Approve an appropriation in the amount of $4,179,081 from Account No. 15-1- 6711-0520.
BACKGROUND
The City's Pavement Management Program (PMP) is the primary tool used to prioritize street pavement rehabilitation projects throughout the City. The City's PMP evaluates,
APPROVAL OF A CONSTRUCTION CONTRACT FOR THE WOODRUFF AVENUE STREET IMPROVEMENT PROJECT, PHASE 2, CAPITAL IMPROVEMENT PROJECT (CIP) NO. 14-14B DECEMBER 10, 2024
PAGE 2
ranks, and prioritizes each City street segment based on surface conditions (cracking, surface failures, etc.), pavement structural strength, ride quality and other field observations. Street segments earmarked for improvements are identified as priorities based on the condition of the pavement for the given street segment relative to the pavement condition of other street segments throughout the City.
The arterial and residential street segments in each area identified as priorities for improvements are either in a state of minor deterioration and can be inexpensively repaired with minor maintenance methods such as slurry seal, cape seal, or overlay, while, other arterial and residential street segments identified have deteriorated to a state of disrepair beyond what ordinarily could be handled through routine street maintenance practices and, therefore, must be reconstructed. Ultimately, the pavement rehabilitation on these street segments will raise the condition of the pavement to an acceptable standard and will extend the infrastructure's life by 20 years.
In addition, the City desires to implement aesthetic enhancements along the Woodruff Avenue corridor between Imperial Highway and Foster Road to create a more aesthetically pleasing gateway into the City as well as promote active transportation along the corridor. The project limits are shown on the attached location map (see Attachment A).
ANALYSIS
On September 24, 2024, the City Council approved plans and specifications and granted authority to advertise the subject project for bids (Attachment B). A copy of the project specifications is available for review in the Public Works Department. The proposed street improvements include pavement rehabilitation and reconstruction, the construction of raised center median islands with landscaping, irrigation, the installation of a City entry monument sign immediately north of Foster Road, the replacement of the hardscape material within the frontage road islands on the west side of Woodruff Avenue with landscaping and irrigation, the repair of existing concrete sidewalks, curb and gutter, driveway approaches and ADA compliant curb access ramps; and the replacement of striping and pavement markings (with bike lanes) and signage.
The project was posted on Planet Bids on October 10, 2024, advertised in the Downey Patriot on October 17, 2024 and October 24, 2024 and published in various trade publications. On November 7, 2024, the City received seven bids electronically through Planet Bids ranging from $5,052,110 to $6,369,000. This range is in excess of the original engineer's estimate on the project of $3.1 million. Over the last year, pavement rehabilitation projects on arterial roads that require full removal and reconstruction of the pavement have seen significant increases as a result of asphalt and concrete materials, excavation and disposal costs, and sharp increases in labor prices. As a result, staff is requesting use of available American Rescue Plan Act (ARPA) funds to complete the project. These funds were previously allocated to the Water Fund as one of the four
APPROVAL OF A CONSTRUCTION CONTRACT FOR THE WOODRUFF AVENUE STREET IMPROVEMENT PROJECT, PHASE 2, CAPITAL IMPROVEMENT PROJECT (CIP) NO. 14-14B DECEMBER 10, 2024
PAGE 3
approved uses; however, staff has recently worked with the federal granting authority to convert them so that they are now eligible for General Fund purposes. The bid results were as follows:
CONTRACTOR LOCATION BID AMOUNT
Sequel Contractors, Inc. Santa Fe Springs $5,052,110
All American Asphalt Corona $5,113,063
Toro Enterprises, Inc. Oxnard $5,299,850
Hardy & Harper, Inc. Lake Forest $5,550,000
Access Pacific, Inc. Pasadena $6,165,919
Gentry Brothers, Inc. Irwindale $6,266,950
Onyx Paving Company, Inc. Anaheim $6,369,000
The lowest responsive and responsible bidder is Sequel Contractors Incorporated in the amount of $5,052,110 (Attachment C). Staff reviewed the bid proposal and references provided by Sequel Contractors, Incorporated and found that said contractor has satisfactorily completed similar projects for the Cities of South Gate, Seal Beach, Inglewood, and Downey. In addition, Sequel Contractor’s State contractor’s license is “current and active,” is registered with the California Department of Industrial Relations (DIR) for Labor Compliance, and its Disadvantage Business Enterprise (DBE) Good Faith Effort was found to be acceptable. Therefore, staff recommends that the City Council award a contract to Sequel Contractors, Incorporated for the construction of the Woodruff Avenue Street Improvement Project, Phase 2, CIP No. 14-14B.
Construction for Phase 2 is anticipated to begin in January 2025 and be completed by June 2025. This closely follows Phase 1 construction, which is currently underway on Woodruff Avenue between Firestone Boulevard and Washburn Avenue.
This project is categorically exempt from the provisions of the California Environmental Quality Act (CEQA) under Section 15301(c), Existing Facilities and is categorically excluded from the provisions of the National Environmental Policy Act (NEPA) under section 23 USC 326.
CITY COUNCIL PRIORITIES
Quality of Life, Safety & Infrastructure
FISCAL IMPACT
Approval of the recommended actions will result in an estimated expenditure of $6,731,231, from the various accounts listed in the following table:
APPROVAL OF A CONSTRUCTION CONTRACT FOR THE WOODRUFF AVENUE STREET IMPROVEMENT PROJECT, PHASE 2, CAPITAL IMPROVEMENT PROJECT (CIP) NO. 14-14B DECEMBER 10, 2024
PAGE 4
Description Amount
Construction Contract $5,052,110
Construction Contract Contingencies (10%) $505,211 Total Construction Cost $5,557,321
Design and Preliminary Engineering (Expended) $174,000 Construction Management and Inspection $300,000
Soils and Materials Testing $100,000
Project Management and Contract Administration $100,000 Total Estimated Project Cost: $6,231,321
Approval of the recommended action(s) will result in $4,179,081 in available funds for the project from Account No. 15-1-6711-0520.
There will be sufficient fund balance for the recommended actions. The budgeted CIP funds for this project are Federal STPL Grant, Account 26-16711, Proposition C Local Return funds, Account No. 54-16711; Metro Proposition C Grant, Account No. 26-16765, Measure R Local Return funds, Account No. 56-16765 and $4,179,081, Account No. 15- 1-6711-0520, as shown in the table below:
Account No. Funding Source Amount
26-1-6711 Federal STPL Grant $350,930
54-1-6711 Proposition C Local Return $1,353,903
54-1-6711 Proposition C Local Return (Expended) $174,000 26-1-6765 Metro Proposition C Grant $138,726
56-1-6765 Measure R Local Return $34,681
15-1-6711 Special Projects Fund $4,179,081
Total Project Funding: $6,231,321
ATTACHMENTS
Attachment A: Project Location Map
Attachment B: Project Plans
Attachment C: Bid Summary
Project Location
Item Description Qty.Unit Unit Price Amount Unit Price Amount Unit Price Amount Unit Price 1 Construction Staking and Surveying 1 LS 50,000.00$ 50,000.00$ 40,000.00$ 40,000.00$ 100,000.00$ 100,000.00$ 2 Traffic Control, Public Convenience & Safety (Not
to Exceed 5% of the Total Bid)1 LS 250,000.00$ 250,000.00$ 228,450.00$ 228,450.00$ 260,000.00$ 260,000.00$ 3 Stormwater Management & Compliance 1 LS 19,000.00$ 19,000.00$ 15,000.00$ 15,000.00$ 100,000.00$ 100,000.00$ 4 Roadway Excavation 3,400 CY 182.00$ 618,800.00$ 110.00$ 374,000.00$ 113.00$ 384,200.00$ 5 Remove and Disposed of Parkway Drain System
and Access Hatches, and Cap and Plug
Remaining Portion of Parkway Drain
400 SF 60.00$ 24,000.00$ 70.00$ 28,000.00$ 22.00$ 8,800.00$ 6 Grade and Compact Existing Roadway Base
Material 52,000 SF 1.00$ 52,000.00$ 0.75$ 39,000.00$ 0.20$ 10,400.00$ 7 Cold Mill Existing AC Pavement (5-inch, Adjacent
Tapers, and Variable Cold Mill at Imperial
Highway Intersection)
248,000 SF 1.25$ 310,000.00$ 1.60$ 396,800.00$ 1.00$ 248,000.00$ 8 Cold Mill Existing AC Pavement (4-inch and
Adjacent Tapers)81,000 SF 1.10$ 89,100.00$ 1.25$ 101,250.00$ 1.00$ 81,000.00$ 9 Cold Mill Existing AC Pavement (1.5-inch)3,670 SF 3.00$ 11,010.00$ 0.50$ 1,835.00$ 1.60$ 5,872.00$ 10 Construct Asphalt Rubber Hot Mix (ARHM)
Pavement with Fibers 3,650 TON 162.00$ 591,300.00$ 155.00$ 565,750.00$ 185.00$ 675,250.00$ 11 Construct Hot Mix Asphalt (HMA) Pavement With
Fibers 9,000 TON 130.00$ 1,170,000.00$ 175.00$ 1,575,000.00$ 148.00$ 1,332,000.00$ 12 Remove Existing and Construct 10-Inch PCC
Curb and Gutter (Type A2-10, 24-Inch Gutter
Pan)
45 LF 100.00$ 4,500.00$ 130.00$ 5,850.00$ 195.00$ 8,775.00$ 13 Remove Existing and Construct 8-Inch PCC Curb
and Gutter (Type A2-8, 24-Inch Gutter Pan)1,630 LF 85.00$ 138,550.00$ 120.00$ 195,600.00$ 140.00$ 228,200.00$ 14 Remove Existing and Construct 6-Inch PCC Curb
and Gutter (Type A2-6, 24-Inch Gutter Pan)115 LF 85.00$ 9,775.00$ 115.00$ 13,225.00$ 150.00$ 17,250.00$ 15 Remove Existing and Construct 6-Inch PCC Curb
and Gutter (Type A2-6, 18-Inch Gutter Pan)50 LF 83.00$ 4,150.00$ 112.00$ 5,600.00$ 150.00$ 7,500.00$ 16 Remove Existing and Construct 8-Inch or 9-Inch
Curb and Gutter (Type A2-8 or A2-9, 12-Inch
Gutter Pan)
125 LF 85.00$ 10,625.00$ 120.00$ 15,000.00$ 150.00$ 18,750.00$ 17 Construct 8-Inch PCC Median Curb (Type A1)3,970 LF 33.00$ 131,010.00$ 26.00$ 103,220.00$ 45.00$ 178,650.00$ 18 Remove Existing and Construct 8-Inch Curb
(Type A1) Within Existing Cross Gutter 36 LF 90.00$ 3,240.00$ 70.00$ 2,520.00$ 125.00$ 4,500.00$ 19 Remove Existing and Construct Variable Height
PCC Curb (Type A1) in Private Property 60 LF 90.00$ 5,400.00$ 60.00$ 3,600.00$ 150.00$ 9,000.00$ 20 Construct Solid Median Nose 6 EA 1,000.00$ 6,000.00$ 3,000.00$ 18,000.00$ 850.00$ 5,100.00$ 21 Remove Existing and Construct 8-inch Thick PCC
Longitudinal Gutter 85 SF 30.00$ 2,550.00$ 45.00$ 3,825.00$ 51.00$ 4,335.00$ 22 Remove Existing and Construct 6-Inch Thick PCC
Commercial Driveway 10,550 SF 18.00$ 189,900.00$ 25.00$ 263,750.00$ 30.00$ 316,500.00$ Sequel Contractors, Inc.
Capital Improvement Project No. 14-14B
Woodruff Avenue Street Improvement Project, Phase 2 (Foster Road - Washburn Road)
BID SUMMARY
November 7, 2024
Part A - General Items
Part B - Roadway Items
Base Bid:
All American Asphalt Toro Enterprises, Inc.
H:\Pubworks\CAPIMP\CIP 14-14b Woodruff Ave. Street Imprvmts Phs 2\Bid Solicitation\CIP 14-14B Bid Sum
Item Description Qty.Unit Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Sequel Contractors, Inc.
Capital Improvement Project No. 14-14B
Woodruff Avenue Street Improvement Project, Phase 2 (Foster Road - Washburn Road)
BID SUMMARY
November 7, 2024
Base Bid:
All American Asphalt Toro Enterprises, Inc.
23 Remove Existing and Construct 6-Inch Thick PCC
Alley Intersection 310 SF 25.00$ 7,750.00$ 25.00$ 7,750.00$ 28.00$ 8,680.00$ 24 Remove Existing and Construct 4-Inch Thick PCC
Sidewalk 6,000 SF 16.00$ 96,000.00$ 18.00$ 108,000.00$ 25.00$ 150,000.00$ 25 Construct 4-Inch Colored Concrete Median
Hardscape 570 SF 25.00$ 14,250.00$ 45.00$ 25,650.00$ 25.00$ 14,250.00$ 26 Construct Decorative Cobble Median (with 6-Inch
Thick PCC Pavement)5,720 SF 20.00$ 114,400.00$ 20.00$ 114,400.00$ 24.00$ 137,280.00$ 27 Remove Existing and Construct Private Property
PCC Pavement 260 SF 25.00$ 6,500.00$ 20.00$ 5,200.00$ 35.00$ 9,100.00$ 28 Remove Existing and Construct 4-Inch Thick PCC
Ramp and Truncated Domes 5 EA 9,000.00$ 45,000.00$ 9,500.00$ 47,500.00$ 6,650.00$ 33,250.00$ 29 Remove Existing and Reconstruct Portion of
Local Depression 3 EA 2,500.00$ 7,500.00$ 5,500.00$ 16,500.00$ 1,500.00$ 4,500.00$ 30 Grind Existing Sidewalk Lip Flush 45 LF 60.00$ 2,700.00$ 30.00$ 1,350.00$ 48.00$ 2,160.00$ 31 Remove Existing and Reconstruct Single Chain
Fence With End Posts 2 EA 2,000.00$ 4,000.00$ 3,200.00$ 6,400.00$ 7,500.00$ 15,000.00$ 32 Remove and Reinstall Bus Stop Bench and Trash
Can 1 LS 4,000.00$ 4,000.00$ 1,200.00$ 1,200.00$ 2,200.00$ 2,200.00$ 33 Remove Existing and Install New Traffic Signal /
Street Light Pull Box to Grade 7 EA 400.00$ 2,800.00$ 1,200.00$ 8,400.00$ 1,280.00$ 8,960.00$ 34 Remove Existing and Install New Curb Drain 2 EA 1,500.00$ 3,000.00$ 1,700.00$ 3,400.00$ 1,400.00$ 2,800.00$ 35 Remove Existing and Install New Parkway Drain 1 EA 6,000.00$ 6,000.00$ 12,000.00$ 12,000.00$ 9,600.00$ 9,600.00$ 36 Adjust Parkway Drain Cleanout Cover to Grade 1 EA 1,200.00$ 1,200.00$ 3,600.00$ 3,600.00$ 600.00$ 600.00$ 37 Adjust City Storm Drain Manhole Frame and
Cover to Grade 6 EA 1,800.00$ 10,800.00$ 1,600.00$ 9,600.00$ 1,450.00$ 8,700.00$ 38 Adjust LACFCD Storm Drain Manhole Ring/Lid to
Grade 4 EA 2,000.00$ 8,000.00$ 1,600.00$ 6,400.00$ 1,500.00$ 6,000.00$ 39 Adjust City Sewer Manhole Frame and Cover to
Grade 5 EA 1,800.00$ 9,000.00$ 1,600.00$ 8,000.00$ 1,500.00$ 7,500.00$ 40 Adjust LACSD Sewer Manhole Ring/Lid to Grade 20 EA 2,000.00$ 40,000.00$ 1,600.00$ 32,000.00$ 1,560.00$ 31,200.00$ 41 Adjust MWD Water Manhole Ring/Lid to Grade 7 EA 2,400.00$ 16,800.00$ 1,600.00$ 11,200.00$ 2,400.00$ 16,800.00$ 42 Furnish and Install New 2-Inch Irrigation Water
Service and 1-1/2-Inch Meter and Box 2 EA 16,000.00$ 32,000.00$ 25,000.00$ 50,000.00$ 29,000.00$ 58,000.00$ 43 Install New Water Valve Box Lid 1 EA 1,500.00$ 1,500.00$ 800.00$ 800.00$ 500.00$ 500.00$ 44 Adjust City Water Meter Box to Grade 1 EA 1,000.00$ 1,000.00$ 600.00$ 600.00$ 500.00$ 500.00$ 45 Adjust City Water Valve Cover to Grade 45 EA 1,500.00$ 67,500.00$ 1,300.00$ 58,500.00$ 1,400.00$ 63,000.00$ 46 Adjust MWD Water Valve Cover to Grade 2 EA 1,500.00$ 3,000.00$ 1,300.00$ 2,600.00$ 2,000.00$ 4,000.00$ 47 Adjust City CP Test Station Box and Cover to
Grade 1 EA 2,000.00$ 2,000.00$ 1,300.00$ 1,300.00$ 3,000.00$ 3,000.00$ 48 Adjust City Monitoring Well Box and Cover to
Grade 2 EA 1,500.00$ 3,000.00$ 1,300.00$ 2,600.00$ 2,000.00$ 4,000.00$ 49 Furnish and Install City Monument Sign 1 LS 55,000.00$ 55,000.00$ 42,000.00$ 42,000.00$ 45,000.00$ 45,000.00$ 50 Traffic Signage 1 LS 60,000.00$ 60,000.00$ 16,000.00$ 16,000.00$ 18,000.00$ 18,000.00$ 51 Furnish and Apply Thermoplastic Traffic Striping
and Raised Pavement Markers 46,000 LF 1.50$ 69,000.00$ 0.80$ 36,800.00$ 2.30$ 105,800.00$ 52 Furnish and Apply Theroplastic Pavement
Markings 3,850 SF 4.00$ 15,400.00$ 5.00$ 19,250.00$ 7.20$ 27,720.00$ Part C - Traffic Signage and Striping Improvements
H:\Pubworks\CAPIMP\CIP 14-14b Woodruff Ave. Street Imprvmts Phs 2\Bid Solicitation\CIP 14-14B Bid Sum
Item Description Qty.Unit Unit Price Amount Unit Price Amount Unit Price Amount Unit Price Sequel Contractors, Inc.
Capital Improvement Project No. 14-14B
Woodruff Avenue Street Improvement Project, Phase 2 (Foster Road - Washburn Road)
BID SUMMARY
November 7, 2024
Base Bid:
All American Asphalt Toro Enterprises, Inc.
53 Paint Curb Red 130 LF 10.00$ 1,300.00$ 2.10$ 273.00$ 3.35$ 435.50$ 54 Paint Median Nose Yellow 6 EA 100.00$ 600.00$ 115.00$ 690.00$ 3.35$ 20.10$ 55 Remove Pedestrian Push Button Assembly, Post
and Foundation Complete. Construct New
Foundation and Install New Pedestrian Push
Button Assembly and Post
1 EA 10,000.00$ 10,000.00$ 7,800.00$ 7,800.00$ 3,750.00$ 3,750.00$ 56 Construct Additional Mortar Cap between
Finished Surface and Traffic Signal Pole Base
Plate
4 EA 1,000.00$ 4,000.00$ 825.00$ 3,300.00$ 715.00$ 2,860.00$ 57 Import and Place Class "A" Topsoil 975 CY 100.00$ 97,500.00$ 90.00$ 87,750.00$ 116.00$ 113,100.00$ 58 Furnish and Install Moisture Barriers (30' Deep)4,760 LF 6.00$ 28,560.00$ 3.25$ 15,470.00$ 3.40$ 16,184.00$ 59 Soil Preparation, Amendment & Fine Grading 18,000 SF 1.00$ 18,000.00$ 0.30$ 5,400.00$ 0.32$ 5,760.00$ 60 Planting 18,000 SF 4.00$ 72,000.00$ 3.05$ 54,900.00$ 3.20$ 57,600.00$ 61 Root Barrier 320 LF 12.00$ 3,840.00$ 9.00$ 2,880.00$ 9.30$ 2,976.00$ 62 Tree - 24 Inch Box 13 EA 800.00$ 10,400.00$ 585.00$ 7,605.00$ 610.00$ 7,930.00$ 63 Bark Mulch 170 CY 125.00$ 21,250.00$ 93.00$ 15,810.00$ 97.00$ 16,490.00$ 64 180-Day Landscape Maintenance/Establishment
Period 18,000 SF 2.00$ 36,000.00$ 0.70$ 12,600.00$ 0.75$ 13,500.00$ 65 Furnish and Install Complete Automatic Irrigation
Systems for Roadway and Frontage Road
Medians
18,000 SF 12.00$ 216,000.00$ 7.20$ 129,600.00$ 7.50$ 135,000.00$ 66 Furnish and Install 6-Inch PVC Irrigation Sleeve
(Schedule 80) for Mainline under Asphalt
Pavement
235 LF 100.00$ 23,500.00$ 120.00$ 28,200.00$ 68.00$ 15,980.00$ 67 Furnish and Install 1-1/2 Inch PVC (Schedule 40)
Conduit 965 LF 34.00$ 32,810.00$ 28.00$ 27,020.00$ 43.00$ 41,495.00$ 68 Furnish and Install 2 Inch PVC (Schedule 80)
Conduit 290 LF 80.00$ 23,200.00$ 69.00$ 20,010.00$ 90.00$ 26,100.00$ 69 Furnish and Install No. 5 Electrical Irrgiation Pull Box 8 EA 2,000.00$ 16,000.00$ 1,800.00$ 14,400.00$ 960.00$ 7,680.00$ 70 Furnish and Install #2 Conductors 730 LF 8.00$ 5,840.00$ 6.00$ 4,380.00$ 12.80$ 9,344.00$ 71 Furnish and Install #8 Conductors 4,950 LF 6.00$ 29,700.00$ 4.00$ 19,800.00$ 4.25$ 21,037.50$ 72 Furnish and Install 120 Volt, 20 Amp, Single Pole
Circuit Breaker 2 EA 800.00$ 1,600.00$ 450.00$ 900.00$ 213.00$ 426.00$
CONTRACTOR TOTAL BASE BID
Sequel Contractors, Inc.
All American Asphalt
Toro Enterprises, Inc.
Hardy & Harper, Inc.
Access Pacific, Inc.
Gentry Brothers, Inc.
Onyx Paving Company, Inc.
Part F - Electrical
Part D - Traffic Signal Improvements
Part E - Landscaping and Irrigation
Total - Bid Items 1 to 72 5,052,110.00$ 5,113,063.00$ 5,299,850.10$ 6,165,919.50$
6,266,950.00$
6,369,000.00$
ALL BIDS RECEIVED:
5,052,110.00$
5,113,063.00$
5,299,850.10$
5,550,000.00$
H:\Pubworks\CAPIMP\CIP 14-14b Woodruff Ave. Street Imprvmts Phs 2\Bid Solicitation\CIP 14-14B Bid Sum