Item No.
1 TO: HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM: OFFICE OF THE CITY MANAGER
BY: MATTHEW BAUMGARDNER, P.E., DIRECTOR OF
PUBLIC WORKS/CITY ENGINEER
D ATE: MAY 27, 2025
SUBJECT: ADOPTION OF A RESOLUTION APPROVING THE LIST OF PROJECTS IN THE PROPOSED FISCAL YEAR 2025-2026 CAPITAL
IMPROVEMENT PROGRAM TO BE FUNDED BY SENATE BILL 1
(SB1), THE ROAD REPAIR AND ACCOUNTABILITY ACT
EXECUTIVE SUMMARY
The City Council will consider adopting a Resolution approving the list of projects in the proposed Fiscal Year (FY) 2025-2026 Capital Improvement Program to be funded by State Senate Bill 1: The Road Repair and Accountability Act of 2017. The City will receive $2,988,842 in SB1 revenues for FY 2025-2026 that will be used to fund street rehabilitation and other infrastructure-related projects.
RECOMMENDATION
That the City Council:
Adopt Resolution No. 25-8300, approving the list of projects in the proposed Fiscal Year 2025-2026 Capital Improvement Program to be funded by Senate Bill 1: The Road Repair and Accountability Act of 2017.
BACKGROUND
Senate Bill 1 (SB1), The Road Repair and Accountability Act of 2017, is a transportation funding bill passed by the State Legislature and signed into law by the Governor in April 2017, which provides approximately $52 billion in funding raised through gasoline, diesel fuel, and sales tax increases over the first 10 years of the law, in order to address significant multi-modal transportation funding shortfalls Statewide. These funds are used each year to fund a variety of pavement and traffic safety projects in the City.
AN ALYSIS
In order to receive SB1 funding for FY 2025-2026, the City must adopt a resolution approving a list of projects proposed to be funded through SB1. The project list must include a description and location of each proposed project, a proposed schedule for the project’s completion, and estimated useful life of the proposed improvements. The City is required to submit a copy of the adopted resolution to the California
APPROVED BY
CITY MANAGER
ADOPT RESOLUTION APPROVING THE LIST OF PROJECTS IN THE PROPOSED FY 2025/2026 CAPITAL IMPROVEMENT PROGRAM TO BE FUNDED BY SENATE BILL 1 (SB1), THE ROAD REPAIR
AND ACCOUNTABILITY ACT
MAY 27, 2025
PAGE 2
2 Transportation Commission by July 1, 2025. The City’s SB1 funding allocation for FY 2025-2026 is estimated at $2,988,842.
The projects proposed to be funded with SB1 revenues are listed in Attachment “B” of the attached Resolution. Staff recommends adoption of the attached Resolution to secure SB1 funds for FY 2025-2026. The street improvement projects have been selected based on the results of the City’s Pavement Management Program and as they appear in the City’s approved Capital Improvement Program. CITY COUNCIL PRIORITIES Quality of Life, Safety and Infrastructure FISCAL IMPACT Approval of the recommended action will result in the City receiving SB 1 revenues in the amount of $2,988,842 within the SB1 Transportation Fund 32 under various accounts for FY 2025-2026. ATTACHMENT Attachment A- Resolution No. 25-8300
RESOLUTION NO. 25-8300
A RESOLUTION OF THE CITY COUNCIL OF THE CITY OF DOWNEY
APPROVING THE LIST OF PROJECTS IN THE PROPOSED FISCAL YEAR 2025/2026 CAPITAL IMPROVEMENT PROGRAM TO BE FUNDED BY SENATE BILL 1: THE ROAD REPAIR AND ACCOUNTABILITY ACT OF 2017
WHEREAS, Senate Bill 1 (SB1), the Road Repair and Accountability Act of 2017 was passed by the Legislature and signed into law by the Governor in April 2017 in order to address the significant multi-modal transportation funding shortfalls statewide; and
WHEREAS, SB1 includes accountability and transparency provisions that will ensure the residents of the City of Downey are aware of the projects proposed for funding in our community and which projects are in progress or have been completed each fiscal year; and
WHEREAS, the City must adopt by resolution a list of projects proposed to receive fiscal year funding from the Road Maintenance and Rehabilitation Account (RMRA), created by SB1, which must include a description and the location of each proposed project, a proposed schedule for the project’s completion, and the estimated useful life of the improvement; and
WHEREAS, the City, will receive an estimated $2,988,842 in RMRA funding in Fiscal Year 2025/2026 from SB1; and
WHEREAS, this is the eighth year in which the City is receiving SB 1 funding, which will enable the City to continue essential road maintenance and rehabilitation projects, safety improvements, repairing and replacing aging bridges, and increasing access and mobility options for the traveling public that would not have otherwise been possible without SB 1; and
WHEREAS, the City has undergone a robust public process to ensure public input into our community’s transportation priorities; and
WHEREAS, the City used a Pavement Management System to develop the SB1 project list to ensure revenues are being used on the most high-priority and cost-effective projects that also meet the community’s priorities for transportation investment; and
WHEREAS, the funding from SB1 will help the City maintain and rehabilitate a number of street pavement rehabilitation projects and add active transportation infrastructure throughout the City this year and hundreds of similar projects into the future; and
WHEREAS, the 2021 California Statewide Local Streets and Roads Needs Assessment found that the City’s streets and roads are in an at-risk condition, and this revenue will help the City increase the overall quality of its road system and over the next decade will bring the City’s streets and roads into an improved condition; and
WHEREAS, the local street and road system is also critical for farm to market needs, interconnectivity, multimodal needs, and commerce; and
WHEREAS, police, fire, and emergency medical services all need safe reliable, roads to react quickly to emergency calls, and a few minutes of delay can be a matter of life and death; and
WHEREAS, restoring roads before they fail also reduces construction time which results in less air pollution from heavy equipment and less water pollution from site run-off; and
RESOLUTION NO. 25-8300
PAGE 2
WHEREAS, the SB 1 project list, attached herein as Exhibit A, and overall investment in our local streets and roads infrastructure with a focus on basic maintenance and safety, investing in complete streets infrastructure, and using cutting-edge technology, materials and practices, will have significant positive co-benefits statewide.
NOW, THEREFORE, THE CITY COUNCIL OF THE CITY OF DOWNEY DOES HEREBY RESOLVE AS FOLLOWS:
SECTION 1. The City Council of the City of Downey hereby approves the list of newly proposed projects appearing on Exhibit A to be funded in Fiscal Year 2025/2026 with RMRA revenues.
SECTION 2. The City Council hereby approves the list of projects previously proposed and adopted from Fiscal Year 2024/2025 appearing on Exhibit A and may also utilize Fiscal Year 2025/2026 RMRA revenues in their delivery. With the relisting of these projects in the adopted fiscal year resolution, the City is reaffirming to the public and the State the City’s intent to fund these projects with RMRA revenues.
SECTION 3. This Resolution shall take effect immediately upon its adoption by the City Council, and the City Clerk shall attest to and certify the vote adopting this Resolution.
APPROVED AND ADOPTED this 27th day of May, 2025.
___________________________________
HECTOR SOSA, Mayor
ATTEST:
_______________________________
MARIA ALICIA DUARTE, CMC
City Clerk
APPROVED AS TO FORM:
_______________________________
JOHN M. FUNK
City Attorney
RESOLUTION NO. 25-8300
PAGE 3
I HEREBY CERTIFY that the foregoing Resolution was adopted by the City Council of the City of Downey at a regular meeting held on the 27th day of May, 2025, by the following vote, to wit
AYES: Council Members:
NOES: Council Member:
ABSENT: Council Member:
ABSTAIN: Council Member:
___________________________________
MARIA ALICIA DUARTE, CMC
City Clerk
List of Projects in the Proposed FY 2025/2026 Capital
Improvement Program to be Funded by Senate Bill 1 (SB1):
The Road Repair and Accountability Act
EXHIBIT A
Project Description Location
Estimated
Useful
Life
Proposed
Schedule of
Completion
1. Bellflower Boulevard
Pavement
Rehabilitation
Rehabilitation of existing
asphalt pavement, repair of
existing miscellaneous
concrete surfaces and
replacement of existing
striping and pavement
markings.
Foster Road
to Dalen
Street and
Lakewood
Blvd.
20 years 6/30/26
2. Guatemala Avenue
at Suva Street Traffic
Signal Improvements
Install new traffic signal,
safety lighting and curb
ramps.
Suva Street
at
Guatemala
Avenue.
30 years 12/31/25
3. Garfield Avenue
Complete Streets
Rehabilitation of existing
asphalt pavement,
pedestrian safety
improvements, stripping
pavement markings and
storm-water infiltration
improvements.
Garfield
Avenue
between
north and
south city
limits.
20 years 12/31/25
4. Firestone at
Pangborn Traffic Signal
Improvements
Install new traffic signal,
safety lighting, pedestrian
safety enhancements.
Firestone
Boulevard at
Pangborn
Avenue.
30 years 6/30/26
5. Woodruff Avenue
Pavement
Rehabilitation
Rehabilitation of existing
asphalt pavement, repair of
existing miscellaneous
concrete surfaces and
replacement of existing
striping and pavement
markings.
Foster Road
to Firestone
Boulevard. 20 years 6/30/26
6. FY 25-26 Alley
Rehabilitation Program
Rehabilitation of existing
asphalt pavement and
repair/replacement of
existing miscellaneous
concrete surfaces.
Various
alleys
Citywide
20 years 6/30/26
List of Carryover Projects from the FY 2024/2025 Capital Improvement Program Funded by Senate Bill 1 (SB1):
The Road Repair and Accountability Act
Project Description Location
Estimated
Useful
Life
Proposed
Schedule of
Completion
7. FY 24/25
Miscellaneous
Concrete Repairs and
ADA Improvements
Annual miscellaneous
concrete constructions and
a repairs of concrete
surface in Council District 2
and construction of ADA-
compliant curb access
ramps, drive approaches
and sidewalks.
Council
District 2 20 years 06/30/25
8. Residential Streets
Pavement
Rehabilitation – Area 6
Rehabilitation of pavement
on various residential
streets and replacement of
damaged sidewalk and
curb and gutter and
reconstruction of curb
access ramps to comply
with current ADA
requirements.
Area 6 20 yeas 06/30/25
9. Downey Avenue
Pavement
Rehabilitation
Rehabilitation of existing
asphalt pavement, repair of
existing miscellaneous
concrete surfaces,
replacement of existing
striping and pavement
markings and installation of
bike lanes (PS&E only).
Gardendale
to Gallatin
Road
20 years 12/31/25
10. Lakewood
Boulevard Pavement
Rehabilitation
Rehabilitation of existing
asphalt pavement, repair of
existing miscellaneous
concrete surfaces and
replacement of existing
striping and pavement
markings.
5th Street to
Meadow
Road
20 years 06/30/26