Cities Index.
04. CIP No. 25-03 - Apprv Plans & Specs, Solicit Const Bids for Florence Ave Access Walkway Imprvs

Downey City Council
September 8, 2026

Document
04. CIP No. 25-03 - Apprv Plans & Specs, Solicit Const Bids for Florence Ave Access Walkway Imprvs
Meeting
September 8, 2026
Body
Downey City Council
Pages
9
Original file
16 KB
Text extracted from the city's file for reading and search. Open the original on lf.downeyca.org. That file is the official record.

Item No. 4.

TO:HONORABLE MAYOR AND MEMBERS OF THE CITY COUNCIL
FROM:OFFICE OF THE CITY MANAGER
BY:MATTHEW BAUMGARDNER, DIRECTOR OF PUBLIC WORKS/CITY ENGINEER DATE:SEPTEMBER 8, 2026
SUBJECT:

APPROVAL OF PLANS AND SPECIFICATIONS AND AUTHORIZATION TO SOLICIT CONSTRUCTION BIDS FOR FLORENCE AVE. ACCESS WALKWAY IMPROVEMENTS, CAPITAL IMPROVEMENT PROJECT (CIP) NO. 25-03, AND FIND THE PROJECT

EXEMPT FROM THE CALIFORNIA ENVIRONMENTAL QUALITY ACT (CEQA) PURSUANT TO SECTION 15301(C), EXISTING FACILITIES

EXECUTIVE SUMMARY

The City Council will consider approving the plans and specifications and authorizing the solicitation of construction bids for the Florence Ave. Access Walkway Improvements, CIP No. 25-03, to improve accessibility for pedestrians between Florence Ave. and the Florence Ave. frontage road between Mattock Ave. and Pico Vista Rd.

RECOMMENDATION

That the City Council:

Approve plans and specifications and authorize the solicitation of construction bids for the Florence Ave.

Access Walkway Improvements, CIP No. 25-03, and find the project exempt from the California Environmental Quality Act (CEQA) pursuant to Section 15301(c), existing facilities.

BACKGROUND

The main portion of Florence Ave. on the north side between the San Gabriel River and Mattock Ave. is separated from the Florence Ave. frontage road by a landscaped island. Beginning at Lesterford Ave., Florence Ave. increases in elevation relative to the frontage road as you proceed east towards the San Gabriel River bridge. A pedestrian access walkway/ramp is currently in-place within the landscaped island between Newville Ave. and Lestorford Ave. to provide access for pedestrians between main Florence Ave. and the frontage road. The walkway/ramp does not meet current Americans with Disabilities Act (ADA) standards per the City's ADA Transition Plan and, therefore, requires an upgrade to meet current accessibility standards. In addition, a request was received from a resident through the City's ADA Coordinator to upgrade the pedestrian access walkway in order for it to be accessible. The location of the pedestrian access walkway is shown in Attachment A and existing photos of the walkway are shown in Attachment B.

ANALYSIS

The plans (Attachment C) and specifications for the improvement of the pedestrian access walkway are complete, and the City is ready to solicit construction bids for this project. The project will include the construction of a new ADA-compliant walkway within the island separating Florence Ave. from the Florence Ave. frontage road between Lesterford Ave. and Pico Vista Rd., which will line up with the easterly side of Lesterford Ave. where it meets the frontage road. The existing walkway will be removed and reconstructed as a stairway. Construction is anticipated to begin in October 2026 and be completed in December 2026. This project is exempt from the California Environmental Quality Act (CEQA) under Section 15301(c), Existing Facilities.

CITY COUNCIL PRIORITIES

Quality of Life, Safety and Infrastructure

FISCAL IMPACT

Approval of the recommended action will result in the estimated expenditure of $200,000 of budgeted CIP funds consisting of Transportation Development Act (TDA) Article III funds to cover the total estimated project costs, as listed in the table below.

Description Amount
Design and preliminary engineering $30,000
Construction contract (estimated)$118,000
Contingencies (10%)$12,000
Construction Inspection & materials testing $30,000
Construction engineering and contract administration $10,000 Total estimated project cost:$200,000

There are sufficient fund balances in the approved Fiscal Year 2026-2027 CIP budget for the recommended action.

Account
No.Funding Source Amount
25-1-
6923 Transportation Development Act (TDA) Article III funds (Fund 25)$200,000 Total Estimated Project Cost:$200,000

Depending on actual bids received, a detailed project cost summary will be provided at the time of the construction contract award for this project.

Attachments
Attachment A: Project Location Map
Attachment B: Existing walkway photos
Attachment C: Final Plans

ATTACHMENT B

On Florence Ave. frontage road, looking east

On Florence Ave. frontage road, looking west

CITY OF DOWNEY

PUBLIC WORKS DEPARTMENT

ALL UNDERGROUND UTILITIES OR STRUCTURES REPORTED BY THE OWNER

OR OTHERS AND THOSE SHOWN ON THE RECORDS EXAMINED ARE INDICATED WITH THEIR APPROXIMATE LOCATION AND EXTENT. THE OWNER BY

ACCEPTING THESE PLANS OR PROCEEDING WITH IMPROVEMENTS PURSUANT

THERETO AGREES TO ASSUME LIABILITY AND TO HOLD UNDERSIGNED

HARMLESS FOR ANY DAMAGES RESULTING FROM THE EXISTENCE OF

UNDERGROUND UTILITIES OR STRUCTURES NOT REPORTED TO THE

UNDERSIGNED, NOT INDICATED ON THE PUBLIC RECORDS EXAMINED,

LOCATED AT VARIANCE WITH THAT REPORTED OR SHOWN ON RECORDS EXAMINED.

THE CONTRACTOR IS REQUIRED TO TAKE DUE PRECAUTIONARY MEASURES

TO PROTECT THE UTILITIES OR STRUCTURES SHOWN AND ANY OTHER UTILITIES OR STRUCTURES FOUND AT THE SITE. IT SHALL BE THE

CONTRACTOR'S RESPONSIBILITY TO NOTIFY THE OWNERS OF THE UTILITIES OR STRUCTURES CONCERNED BEFORE STARTING WORK.

CITY OF DOWNEY

PUBLIC WORKS DEPARTMENT

FLORENCE AVENUE ACCESS WALKWAY

IMPROVEMENTS
CAPITAL IMPROVEMENT PROJECT NO. 25-03

TITLE SHEET

ALL WORK CALLED FOR ON THE PLANS SHALL COMPLY WITH THE CITY OF DOWNEY STANDARD PLANS AND SPECIFICATIONS; THE LATEST EDITIONS OF THE

STANDARD PLANS AND SPECIFICATIONS FOR PUBLIC WORKS CONSTRUCTION, "GREENBOOK"; AND THE CALTRANS STANDARD PLANS AND SPECIFICATIONS.

LOCATIONS OF EXISTING UTILITIES AND/OR UNDERGROUND FACILITIES, IF

SHOWN, ARE IN THEIR APPROXIMATE LOCATIONS BASED ON BEST AVAILABLE INFORMATION AT TIME OF PREPARING PLANS. ACTUAL LOCATION, SIZE, TYPE,

AND NUMBER OF UTILITIES AND/OR UNDERGROUND FACILITIES MAY DIFFER

FROM THAT SHOWN AND SUCH UTILITIES OR FACILITIES MAY BE PRESENT THAT ARE NOT SHOWN. IT IS THE CONTRACTOR'S RESPONSIBILITY TO HAVE SITE

INSPECTED BY USA PRIOR TO COMMENCING WORK AND TO VERIFY LOCATIONS

OF ALL UTILITIES WITH RESPECTIVE OWNERS PRIOR TO STARTING WORK AND THROUGHOUT CONTRACT. THE PLANS ONLY SHOW KNOWN UNDERGROUND UTILITIES WITHIN THE PROJECT LIMITS.

THE CONTRACTOR SHALL NOTIFY THE CITY OF DOWNEY INSPECTOR AT LEAST 48 HOURS PRIOR TO ANY CONSTRUCTION (PHONE: 562-904-7110).

INSPECTION BY THE CITY OR ITS REPRESENTATIVE OF THE WORK CALLED FOR

ON THE PLANS DOES NOT, IN ANY WAY, RELIEVE THE CONTRACTOR OF THEIR

OBLIGATION TO PERFORM WORK IN COMPLIANCE WITH THE PLANS AND SPECIFICATIONS.

THE CONTRACTOR SHALL USE PROPER SAFETY SIGNING AND BARRICADING AS

REQUIRED PER CALIFORNIA MANUAL OF UNIFORM TRAFFIC CONTROL DEVICES (CAMUTCD), LATEST EDITION.

REQUESTS FOR DEVIATIONS FROM THE APPROVED PLANS (EXCEPT MINOR

ADJUSTMENTS IN THE FIELD TO MEET EXISTING CONDITIONS), SHALL BE MADE IN

WRITING AND ARE NOT TO BE INITIATED UNLESS, OR UNTIL, THEY ARE APPROVED

BY THE PUBLIC WORKS DIRECTOR/CITY ENGINEER OR A REPRESENTATIVE ACTING SPECIFICALLY UPON HIS INSTRUCTIONS.

QUANTITIES, AS SHOWN ON THE PLANS ARE ESTIMATED, AND THE CONTRACTOR

IS ADVISED THAT FINAL QUANTITIES OF MATERIAL AND WORK IN PLACE MAY BE MORE OR LESS THAN THOSE INDICATED ON THE PLANS.

CONTRACTOR SHALL VERIFY ALL CONDITIONS AND DIMENSIONS AND SHALL

REPORT ALL DISCREPANCIES TO THE CITY PRIOR TO THE COMMENCEMENT OF WORK.

AT NO TIME IS ANY BUSINESS OR RESIDENCE TO BE WITHOUT ACCESS UNLESS OTHERWISE APPROVED IN WRITING BY THE CITY.

WORK SHALL BE LIMITED BETWEEN 8:00 A.M. AND 5:00 P.M., UNLESS OTHERWISE APPROVED BY THE CITY.

NO STORAGE OF MATERIALS/EQUIPMENT WILL BE ALLOWED IN PUBLIC RIGHT-OF-WAY. PROVIDE OFFSITE/ONSITE STAGING/STORAGE AREA IF NECESSARY.

TRAFFIC CONTROL SHALL BE PER CAMUTCD OR WORK AREA TRAFFIC CONTROL HANDBOOK (WATCH).

PEDESTRIAN ACCESS ALONG PARKWAY MUST BE MAINTAINED AT ALL TIMES.

THE CONTRACTOR SHALL OPERATE IN A MANNER COMPLIANT WITH ALL

APPLICABLE SECTIONS OF THE DOWNEY MUNICIPAL CODE AND COMPLIANT WITH ALL APPLICABLE CITY COUNCIL RESOLUTIONS.

HARD HATS AND SAFETY VESTS SHALL BE WORN AT ALL TIMES WHEN WORKING ON THIS PROJECT.

CONTRACTOR AGREES THAT HE SHALL ASSUME SOLE AND COMPLETE

RESPONSIBILITY FOR JOB SITE CONDITIONS DURING THE COURSE OF THE

CONSTRUCTION OF THIS PROJECT, INCLUDING SAFETY OF ALL PERSONS AND PROPERTY; THAT THIS REQUIREMENT SHALL APPLY AND NOT BE LIMITED TO NORMAL WORKING HOURS; AND THAT THE CONTRACTOR SHALL DEFEND,

CONTINUOUSLY INDEMNIFY AND HOLD THE CITY AND ITS EMPLOYEES HARMLESS

FROM ANY AND ALL LIABILITY, REAL OR ALLEGED, IN CONNECTION WITH THE

PERFORMANCE OF THE WORK ON THIS PROJECT, EXCEPTING FOR LIABILITY ARISING FROM SOLE NEGLIGENCE OF THE CITY OR ITS EMPLOYEES.

1. 2.

3. 4.

5. 6.

7. 8.

9. 10.

11. 12.

13. 14.

15. 16.

GENERAL NOTES

UNDERGROUND STRUCTURES

BENCHMARKS

TITLE SHEET

REMOVAL PLAN

CONSTRUCTION PLAN

CONSTRUCTION DETAILS
1 2
3 4

SOUTHERN CALIFORNIA EDISON

FRONTIER COMMUNICATIONS

SOUTHERN CALIFORNIA GAS COMPANY

TIME WARNER CABLE

TIME WARNER TELECOM

EXXON MOBIL PIPELINE COMPANY

PARAMOUNT PETROLEUM

ERNESTO CHAVEZ

ARIEL FATALLA

ERIC ROMERD

ERIK LEMUS

BART VANWEY

MELODY SEBRING
(562) 903-3183
(714) 375-6717
(714) 231-0456
(562) 383-9960
(909) 456-3693
(310) 212-4141
(562) 531-2060 x2751STEVE PEYTON
CITY OF DOWNEY - WATER & SEWER (562) 904-7202DAN MUELLER LA COUNTY DEPT. OF PUBLIC WORKS - CONST. DIVISION (626) 458-7169MANUEL ALARCON CENTRAL BASIN MWD (323) 201-5528JEREMY MELENDEZ
MWD OF SOUTHERN CALIFORNIA (213) 217-7670KEN CHUNG
CROWN CASTLE JEFF ROGERS (951) 232-5268
SOUTHERN CALIFORNIA EDISON - TELEOM NOLAN LAM (714) 815-2683 LA COUNTY SANITATION DISTRICT (562) 699-7411 x1205TOM SUNG UNDERGROUND SERVICE ALERT (USA)8-1-1----
AT&T
AT

ASPHALT CONCRETE

ANGLE POINT

ASPHALT RUBBERIZED HOT MIX
AVENUE

BACK OF WALK

BEGN CURVE

BEGIN CURVE RETURN
BEGIN

BUILDING

BOLLARD

CURB & GUTTER

CENTER LINE

CABINET,

CRUSHED AGGREGATE BASE

CATCH BASIN
CLF

COMMMERICAL DRIVEWAY

COMMUNICATIONS

CONCRETE

CONSTRUCTION

CEMENT TREATED SUBGRADE

DIAMETER

DRAWING

DRIVEWAY

EASTBOUND

END CURVE

END CURVE RETURN

EDGE OF GUTTER

ELECTRICAL

ELECTRICAL PULLBOX

EASTERLY

EDGE OF PAVEMENT

EXISTING

FIRE HYDRANT

FIBER OPTIC
@
AC
ANG
ARHM
AVE
B/W
BC
BCR
BEG
BLDG
BOL
C&G
C/L
CAB
CB
CLF
COM
COMM
CONC
CONST
CST
DIA
DWG
DWY
EB
EC
ECR
EG
ELEC
EL.PB
E'LY
EP
(E), EXIST
FH,
FO
FEET

GRADE BREAK

GAS METER

GUARD POST
GUTTER

GAS VALVE

GUYWIRE ANCHOR

HOT MIX ASPHALT

INCH(ES)
INVERT

IRRIGATION
LENGTH

LAYOUT LINE
LEFT

MAXIMUM

MANHOLE

MINIMUM

MONUMENT

MOW STRIP

MONITORING WELL
NUMBER

NORTHERLY

NEW STAND

NOT TO SCALE

ON CENTER

PULL BOX

PORTLAND CEMENT CONCRETE

PRIVATE LIGHT

PROPERTY LINE

POWER POLE

PROPOSED
POINT

PAVEMENT

RIGHT OF WAY
RADIUS
FT, '
GB
GM

GP, GPOST
GTR
GV
GYA
HMA
IN, "
INV
IRR
L
LOL
LT
MAX
MH,
MIN
MON
MOW
MW
No
N'LY
NS
NTS
OC
PB
PCC
PL
P/L
PP
(P), PROP
PT
PVMT
R/W
RAD

REINFORCED CONCRETE PIPE
ROAD
RIGHT

RECLAIMED WATER

RESIDENTIAL DRIVEWAY

STORM DRAIN

STORM DRAIN MANHOLE
SHEET

SURVEY MONUMENT

STREET LIGHT

SANITARY SEWER

STANDARD PLANS AND SPECIFICATIONS

FOR PUBLIC WORKS CONSTRUCTION
STREET

STANDARD

SIDEWALK

TOP OF CURB

TELEPHONE

TRAFFIC SIGNAL

TRAFFIC SIGNAL CABINET

TRAFFIC SIGNAL POLE

TRAFFIC SIGNAL PULL BOX

TREE WELL

TYPICAL

VARIABLE

WEST BOUND

WESTERLY

WATER METER

WHEEL STOP

WATER VALVE

CROSS GUTTER
RCP
RD
RT
RW
RES
SD
SDMH
SHT
SM
SL
SS
SSPWC
ST
STD
SW
TC
TELE
TS
TSC
TSP
TSPB
TW
TYP
VAR
WB
W'LY
WM,
WS
WV
XG
(310) 515 - 2461MARCO MACIAS
CIP NO. 25-03
4FLORENCE AVENUE ACCESS WALKWAY IMPROVEMENTS
18872 MacArthur Blvd, Suite 210
Irvine, CA. 92612
714-656-0160

KREUZER CONSULTING GROUP

BASIS OF BEARING

THE BASIS OF BEARING FOR THIS SURVEY IS THE CALIFORNIA
COORDINATE SYSTEM, ZONE 5, NAD 83 EPOCH 2017.50.

BENCHMARK
LOS ANGELES COUNTY PUBLIC WORKS LY10712
L&T IN W CB 17FT S/O BCR @ SW COR TELEGRAPH RD & HASTY AVE ELEV = 142.530 NAVD 1988

LEGEND & ABBREVIATIONS

PROPOSED CONCRETE

RETAINING CURB

PROPOSED METAL HAND

RAILING

PROPOSED CONTOUR

EXISTING CONTOUR

PROPOSED ELEVATION

EXISTING ELEVATION

FINISH SURFACEFS
(100.0)
100.0

FINISH GRADEFG

TOP OF CURBTC

BACK OF WALKBW

PROPOSED CONCRETE

EARTHEN SWALE

GRADING LIMITS

CONCRETE REMOVALAVENUEPICO VISTARDFLORENCE AVE

FRONTAGE R
O
A

DLESTERFORD

TS
(125.0)
(126.0)(127.0)
(125.5)
(126.5
)(127.
5)
(125.0)
(126.0)
(127.0)
(128.0)
(124.5)
(125.5)
(126.5)
(127.5)
POLE/
CONC. PAD

PULL BOX
SIGN
TREE
TREE

GRADING LIMIT

GRADING LIMIT

GRADING LIMIT GRADING LIMIT
A
A
A
D
D
B
C
C
A
A

FLORENCE AVENUE

FRONTAGE ROAD

REMOVAL PLAN
CIP NO. 25-03
4FLORENCE AVENUE ACCESS WALKWAY IMPROVEMENTS
18872 MacArthur Blvd, Suite 210
Irvine, CA. 92612
714-656-0160

KREUZER CONSULTING GROUP

LEGEND & ABBREVIATIONSREMOVAL NOTES

GRADING LIMITS

CONCRETE REMOVALA
B
C
PROTECT IN PLACE.

SAWCUT, REMOVE, AND DISPOSE OF EXISTING
CONCRETE SIDEWALK AND RAMP.

SAWCUT AND DISPOSE EXISTING HAND RAIL.

CLEAR AND GRUB.D

4" CF4.0" CF0" CF16" CF16" CF3.8" CF3.8" CFTS

GRADING LIMIT

GRADING LIMIT

GRADING LIMIT

GRADING LIMIT
(125.0)
(126.0)(127.0)
(125.5)
(126.5
)(127.
5)
(125.0)
(126.0)
(127.0)
(128.0)
(124.5)
(125.5)
(126.5)
(127.5)
1 1
1 1
2 2
1 1
2 2
2 2
1 1 1

4.50%
11 .
5 '

@

4 .
5 0
%123.96 FS124.29 TC124.22 FG4" CF126.85 FS127.18 TC125.70 FG127.38 FS127.38 TC127.38 FG0" CF126.93 FS127.26 TC127.23 FG127.45 TC127.45 FS(124.51 TC)(124.15 FS)5.0'

63.8 LF

64.3 LF
A
A
125.02 FS
125.42 FS
125.83 FS
126.25 FS
127.18 FS
127.50 FS
126.66 FS

2.00%12
.
0 '

@

4 .
4 2
%
124.60 FS
127.91 FS

2.00%1.10%128.06 FS
(128.
4 2
B
W)1.5%1.50%1.40%1.50%(128.
5 0
T
C)(128.
1 0
T
C)(127.
7 8
T
C)
125
125.5
126
126.5
127.
0 127.
5 125125.5126
126.
5 1
2 7
1 2
7 .
5 (128.
1 0
T
C)
127.84 F
S

4.50%

5.0'

5.0'(127.
0 9
F
L)

11.5 LF

12.0 LF
(123.90 AC)(124.22 TC)124.06 FS125.56 TC125.05 FG124.05 FS125.55 TC125.00 FG5.0 LF (123.91 AC)(124.23 TC)6.0 LF

2.00%5.0'
(TYP.)

6.0'

6.0'

6.2'

5.7'

7.0'

20.0 LF 6.0 LF 14.0 LF
JOIN
JOIN

7.5 LF
(124.
6 4
T
C)(125.
9 4
F
L)1.50%SCORELINE
(TYP.)
4 3
2 6.7 LF
5 5.0'
2"
2"
12"VAR16"TC PER
PLAN
FS PER
PLAN
FG PER
PLAN
#4 CONT
(TYP)
#4 @ 24" OC
RAMP
VARIES (2.2' - 7.3')

GRADING LIMIT
1 GRADING LIMIT
2 2

EX C/G

EX CURB

5.0'6.7'

FG PER PLAN

FG PER PLAN

FLORENCE AVE

FRONTAGE ROAD

2.00%

FLORENCE AVENUE

FRONTAGE ROAD
NTS

RETAINING CURB DETAIL A
--

CONSTRUCTION PLAN
CIP NO. 25-03
4FLORENCE AVENUE ACCESS WALKWAY IMPROVEMENTS
18872 MacArthur Blvd, Suite 210
Irvine, CA. 92612
714-656-0160

KREUZER CONSULTING GROUP

LEGEND & ABBREVIATIONS

PROPOSED CONCRETE

RETAINING CURB

PROPOSED METAL HAND

RAILING

CONSTRUCTION NOTES
CONSTRUCT 4" CONCRETE SIDEWALK PER SPPWC STD.

PLAN NO. 112-2 AND DETAIL B ON SHEET 4.

CONSTRUCT CONCRETE RETAINING CURB PER DETAIL
A HEREON. TOP OF CURB (TC) AND FINISH SURFACE
(FS) ELEVATIONS PER PLAN.

CONSTRUCT REINFORCED CONCRETE STAIRWAY, TYPE
A, PER SPPWC STD. PLAN NO. 640-4 AND DETAIL C ON
SHEET 4. T=12"; R=5"; S=7'; C=12'. FINISH SURFACE (FS)
ELEVATIONS PER PLAN.

CONSTRUCT METAL HAND RAILING, TYPE A, PER
SPPWC STD. PLAN NO. 606-5 AND DETAIL D ON SHEET 4.

FURNISH AND PLACE 3' X 5' DETECTABLE WARNING
DEVICE PER SPPWC STD. PLAN NO. 111-5 AND DETAIL E
ON SHEET 4.

PROPOSED CONTOUR

EXISTING CONTOUR

PROPOSED ELEVATION

EXISTING ELEVATION

FINISH SURFACEFS
(100.0)
100.0

FINISH GRADEFG

TOP OF CURBTC

BACK OF WALKBW

PROPOSED CONCRETE
NTS

SECTION A-A

EARTHEN SWALE

GRADING LIMITS

CIP NO. 25-03
4FLORENCE AVENUE ACCESS WALKWAY IMPROVEMENTS
18872 MacArthur Blvd, Suite 210
Irvine, CA. 92612
714-656-0160

KREUZER CONSULTING GROUP

CONSTRUCTION DETAILS
NTS

CONCRETE SIDEWALK B
--NTS

CONCRETE STAIRWAY C
--
NTS

DETECTABLE WARNING DEVICE E
--NTS

METAL HAND RAILING D
--

← All documents from this meeting