City of East Palo Alto Public Works Department
On-Call Construction Management, Inspection, and Materials Testing 1 Cost Proposal for City of East Palo Alto, Public Works Dept.

On-Call Construction Management,
Inspection, and Materials Testing for Capital
Improvement Projects and Other Projects,
Including Route 101/University Ave. Pedestrian
Overcrossing
Proposed For: City of East Palo Alto - Public
Works Department
Attention: Glen March, Senior Engineer
1960 Tate Street
East Palo Alto, CA 94303
Proposed By: Ghirardelli Associates, Inc.
2055 Gateway Place, Suite 470
San Jose, CA 95110
Revised On:
5/26/2022
Section E: Scope of Services and Cost Proposal
for the Route 101 / University Avenue
Pedestrian Overcrossing Project
Project Description
The Project includes the following: (a) a pedestrian overcrossing over Route 101; (b) Class I Bicycle Facilities on each side of the pedestrian overcrossing;(c) an additional right turn lane and repaving at the southbound 101 off-ramp; (2) reconstruction of curb and gutters, curb ramps, and the center median on University Avenue; (3) reconstruction of the northbound 101 off ramp; (4) modify three traffic signals at the intersections on University Avenue.

All improvements will be constructed within the existing Caltrans right of way, City right of way, or an existing easement (ROW).

Scope of Services
The City’s Project Manager is responsible for oversight of the Construction Management Consultant and Design Consultant. The Design Consultant will provide construction design support services during construction for the project. The Design Consultant will be available to review and respond to all design related issues. The City Engineer is responsible for the overall direction and execution of this project.

Ghirardelli’s Resident Engineer (RE) will manage the construction contract management, inspection, and materials testing on behalf of the City. As such, the RE functions as the primary contact with the contractor in all matters of the contract. The RE will also ensure the community has been properly informed of the construction activities that would be taking place and that their concerns have been addressed.

Our Key Personnel for the Construction Management work will include a Resident Engineer, Structure Representative/Falsework Checker, Office Engineer, Inspectors and Scheduler.

Construction management, inspection, and materials testing tasks associated with the Project include the following:
i. Construction Management
A. Pre-Construction Work includes the following activities:

1. Constructability review of construction contract documents.

2. Assemble Caltrans Awards Package.

3. Participate in a major community meeting prior to start of construction to explain the project, construction events and schedules, and the Public Outreach program.

4. Develop list of anticipated Contractor submittals with milestones by which the submittal will be made and the timeframe allowed for review.

5. Develop a construction management plan that will describe all deliverables and timing for periodic reports to be received by the City. The plan shall describe the level of effort anticipated to be maintained by the Resident Engineer and project inspectors for the various activities during the construction period and project closeout; and

6. As part of the construction management plan, create an electronic filing system for review and approval by City.

B. Construction Project Meetings include the following activities:

1. Schedule and conduct project meetings, which includes preparing agendas and meeting minutes for all meeting. Types of meetings may include the following:
a) Pre-construction meeting with the Contractor and all the third parties. b) Weekly project meeting to discuss safety, coordination, schedule and other issues with contractor.
c) Monthly meeting with City staff to provide update of project status, including cost and schedule status.
d) Preconstruction Scheduling Conference.
e) Other project meetings as needed, e.g., schedule review meetings, contract change order meetings.

2. Organize partnering workshop.

C. Project Controls and Contract Administration include the following activities:

1. Prepare a Resident Engineer Daily report. The RE report should document daily construction activities, conversations with Contractor or others, issues, and concerns.

2. Document control for all construction correspondences, documents, contractor’s submittals, etc.

3. Review and monitor the contractor’s safety programs and requirements. Inform contractor when its staff does not comply with their programs and project requirements

4. Comply with Cal-OSHA regulations regarding safety equipment and procedures, and safety instructions issued by the state.

5. Take daily photographs to illustrate construction progress, construction problems and solutions to form a record of critical activities that could support City’s position in potential claims.

6. Review work done by contractors prior to recommending contractor’s invoices for payment. Submit completed contract costs with each invoice certification.

7. Prepare and process backup calculations for each pay item and maintain all records required for paying contractor’s invoices.

8. Review of all contractor’s submittals (with assistance from design consultant on designrelated submittals) and maintain a record of all the submittals. Check for compliance with Buy America requirements.

9. Submittals to be reviewed by the construction management team include but are not limited to:
a) Trenching/Shoring.
b) Falsework.
c) Traffic Control Plans.
d) Base Material; Asphalt concrete and other construction materials e) Other Construction submittals related to temporary conditions f) Public Notification Flyers

10. Review, respond and maintain a record of all contractor’s RFIs. Provide field recommendations for those RFIs that need to be responded by the City or Designer of Record.

11. Consult with the Design Engineer and the City prior to interpreting contract documents for the Contractor and assist in the resolution of questions which may arise.

12. Act as liaison with Caltrans, public agencies, utilities, and other entities during construction

13. Monitor project for compliance with Environmental requirements

14. Ensure Contractor maintains Storm Water Pollution and Protection Plan and Best Management Practices.

15. Monitor contractor for labor compliance including posting of posters, conducting Employee Interviews, and checking Certified Payrolls and Statement of Compliance

16. Check contractor compliance with Federal Trainee requirements

17. Prepare tri-monthly invoice package for Caltrans Reimbursement

18. Maintain a record set of conformed contract documents continually updated with all revisions and change orders

19. Monitor contractor’s records of “as-builts” conditions on the contract drawings and specifications
D. Change Management includes the following activities:

1. Maintain logs/lists of change notices, change directives, change orders, potential change orders, and potential claims. Lists shall include a description of each item and actual or potential cost associated with each item.

2. Review and respond to contractor’s claims

3. Prepare and process all construction Change Notices

4. Process Design Change Notices

5. Prepare Change Directives

6. Prepare all Change Orders documentation including Change Order and required support documentation and Change Order memorandums.

7. Negotiate Change Orders as directed by the City Engineer.

8. Establish an agreed upon scope of work for any changes and perform an independent cost estimate and schedule impact analyses, if required, for all contractor’s Change Orders prior to Change Order negotiations

9. Make appropriate recommendations to City as to the value of all changes, additive or deductive and any impact on schedule
E. Schedule Management includes the following activities:

1. Review contractor’s baseline schedule submittal for accuracy and reasonableness.

Provide comments to the schedule, as appropriate. Once satisfied that contractor has formulated a plausible plan, recommend approval of the contractor’s schedule to the City.

2. Monitor the contractor’s progress against their base-line schedule.

3. Review and provide comments, as necessary, to contractor’s monthly schedule update.

4. Prepare Weekly Statement of Working Days and provide to Contractor within 5 days after end of period.

5. Perform Time Impact Analysis in advance of negotiating contract change orders, as required. After execution of contract change order with time impact, ensure change order activities and time impact is appropriately incorporated into the project schedule.

F. Monthly Reports shall be submitted with the Consultant Invoice and include the following information:

1. Summary of Contractor’s construction progress to date, as well as, during the month with supporting progress photographs.

2. Summary of issues and potential issues that may impact project cost or schedule.

3. Approved total working days, working days worked to date, percentage of working days completed.

4. Forecast remaining working days and estimated date construction will be completed.

5. Current contract amount, amount spent to date, percentage of contract complete.

6. Forecast of Final Construction Contract Cost - costs spent to date and the projected completion cost including:
a) Base contract amount
b) Approved Contract Change Orders
c) Contract Change Order Log
d) Construction Directive Log
e) Construction Notice Log
f) Potential Contract Change Order Log, including Contractor’s Change Requests g) Projected overruns and underruns of bid items
h) Potential Claims, including denied Contractor’s Change Requests

7. Summary of liquidated damages assessed to Contractor due to failure to re-open lanes on the roadway on time and other items.

8. Estimate Construction Management Costs at the end of work, describing amount spent to date and forecasted cost at the end of work.

9. Submittals Logs

10. RFIs Log
G. Utility Relocations includes the following activities:

1. Establish contact with all the utility companies prior to start of construction to begin coordination of utility company activities; and

2. Coordinate all utility work with utility companies.

H. Community Outreach include the following activities:

1. Provide construction notices to affected businesses, residents, the City, and/or the City of Palo Alto announcing major traffic, noise, or other impacts.

2. Prepare quarterly newsletters about the project.

3. Participate in quarterly presentations to the City Council, if requested.

4. Assist City with responses to media contacts. All media contacts will be done by the City staff.
ii. Project Close-out

1. Transmit Contractor’s approved Record Drawings (As-Builts) to the City and Caltrans.

2. Finalize Change Orders, including finalizing bid items.

3. Assist with resolution of claims.

4. Finalize and resolve all punch list items.

5. Prepare all final reports including report of completion for acceptance of the Project.

6. Prepare closeout package to Caltrans.

7. Finalize and deliver all construction files to the City. iii. Construction Inspection
A. Inspect work done by contractor for contract compliance on a continuous basis B. Prepare daily inspection reports that describe labor, equipment and material provided by the contractor for each construction activity. When practicable, include name of activity from contractor’s construction schedule.

C. Photographs construction activities daily.

D. Provide a weekly summary of all construction activities.

E. Inspect material and equipment upon delivery for compliance to construction contract documents. Collect delivery records and certificates of compliance F. Recommend acceptance of the work when it is satisfactorily completed. Track noncompliant work separately until work is satisfactorily completed and accepted.

G. Conduct substantial completion and final inspections, preparing punch lists and monitoring their completion.

H. Keep accurate and precise records regarding when road and lane closures are put in place and removed.

I. Perform verification surveys to ensure the line, grade, and dimension for compliance with the construction contract documents. Monitor settlements and deformation at critical locations.
vi. Materials Testing and Inspection
A. Provide for material testing and inspection as required and necessary for quality project, include testing described in the construction contract, Quality Management Plan, Source Inspection Quality Control Management Plan, and/or City of East Palo Alto’s Quality Assurance Program by a qualified testing laboratory.

Cost Proposal (Revised on 5/26/2022)
Section F: Billing Rates

PW BILL RATE NPW BILL RATE
First Shift Second Shift First Shift Second Shift

NAME ST OT DT ST OT DT ST OT DT ST OT DT
Aaron Prchlik $227.39 $227.39 $281.04 $227.39 $241.63 $312.54 $227.39 $227.39 $227.39 $227.39 $227.39 $227.39 Bonnie Holt $174.08 $237.11 $300.14 $189.83 $260.74 $331.64 $140.01 $210.02 $280.02 $140.01 $210.02 $280.02 Carolyn Adkins $201.23 $264.26 $342.69 $216.98 $287.89 $358.79 $171.34 $257.02 $342.69 $171.34 $257.02 $342.69 Cesar Lara $163.06 $240.99 $321.31 $178.81 $249.72 $321.31 $160.65 $240.99 $321.31 $160.65 $240.99 $321.31 Chris Morris $193.37 $290.06 $386.74 $193.37 $290.06 $386.74 $193.37 $290.06 $386.74 $193.37 $290.06 $386.74 David Eldridge $258.02 $258.02 $280.07 $258.02 $258.02 $311.58 $258.02 $258.02 $258.02 $258.02 $258.02 $258.02 Donna James $163.26 $242.84 $323.79 $179.01 $249.92 $323.79 $161.89 $242.84 $323.79 $161.89 $242.84 $323.79 Jaime Heredia $222.32 $242.31 $305.34 $222.32 $265.94 $336.84 $222.32 $222.33 $222.33 $222.32 $222.33 $222.33 Jaimie Azvedo $176.89 $265.34 $353.79 $184.60 $265.34 $353.79 $176.89 $265.34 $353.79 $176.89 $265.34 $353.79 Jay Ryan $190.94 $286.42 $381.89 $190.94 $286.42 $381.89 $190.94 $286.42 $381.89 $190.94 $286.42 $381.89 Keith Baty $179.70 $269.56 $359.41 $181.07 $269.56 $359.41 $179.70 $269.56 $359.41 $179.70 $269.56 $359.41 Kenneth Wong $173.23 $259.85 $346.47 $178.90 $259.85 $346.47 $173.23 $259.85 $346.47 $173.23 $259.85 $346.47 Lesha Kubacki $162.35 $243.53 $324.71 $171.63 $243.53 $324.71 $162.35 $243.53 $324.71 $162.35 $243.53 $324.71 Matthew McKeon $221.45 $332.18 $442.91 $221.45 $332.18 $442.91 $221.45 $332.18 $442.91 $221.45 $332.18 $442.91 Michael Peters $208.39 $219.45 $282.48 $208.39 $243.07 $313.98 $208.39 $208.39 $208.39 $208.39 $208.39 $208.39 Michael Williams $164.72 $247.09 $329.46 $171.30 $247.09 $329.46 $164.72 $247.09 $329.46 $164.72 $247.09 $329.46 Neil Hannan $180.43 $233.87 $296.90 $186.59 $257.50 $328.40 $180.43 $180.43 $180.43 $180.43 $180.43 $180.43 Patrick Myers $181.71 $272.57 $363.43 $184.29 $272.57 $363.43 $181.71 $272.57 $363.43 $181.71 $272.57 $363.43 Paul Cabral $216.39 $324.59 $432.78 $216.39 $324.59 $432.78 $216.39 $324.59 $432.78 $216.39 $324.59 $432.78 Richard Kaufman $261.70 $261.70 $276.73 $261.70 $261.70 $308.23 $261.70 $261.70 $261.70 $261.70 $261.70 $261.70 Scott Buckley $234.80 $234.81 $272.78 $234.80 $234.81 $304.28 $234.80 $234.81 $234.81 $234.80 $234.81 $234.81 Teck Low $167.73 $251.60 $335.47 $182.11 $253.02 $335.47 $167.73 $251.60 $335.47 $167.73 $251.60 $335.47 Additional Comments

1. Hourly rates include vehicle, mobile phone, laptop, and camera.

2. Any extensive reproduction or delivery service charges shall be billed at actual.

3. Rates valid until 12/31/2022. Annual rate escalation is 5%.

4. Construction inspection activities are subject to prevailing wage requirements.

5. Per prevailing wage requirements, a shift differential is for any covered work shift beginning after 2PM. 399 Lindbergh Avenue
Livermore CA 94551
P 925.315.3151
www.bskassociates.com
Environmental, Geotechnical, Construction Services, Analytical Testing - An Employee-Owned Company BSK Proposal No. C00000144
May 25, 2022

COST ESTIMATE SUMMARY
City of East Palo Alto
US 101/University Avenue Interchange Improvement Project Quality Assurance (QA) Construction Materials Testing

HOURS RATE EXTENSION
Group 1 Special Inspector (NDT Testing) $155.00 $0.00
Group 2 Special Inspector (Source Inspections / Welding Inspections) 164 $149.00 $24,436.00 Group 3 Engineering Technician (Soils / HMA Sampling and Testing) 132 $135.00 $17,820.00 Group 4 Technician (Concrete Sampling) 100 $118.00 $11,800.00 Sample Courier (Pickup / Transportation) 40 $108.00 $4,320.00 Senior Professional (Senior Materials Engineer) 15 $230.00 $3,450.00 Senior Professional (Project Manager) 15 $230.00 $3,450.00 Staff Professional II (Assistant Project Manager) 5 $215.00 $1,075.00 Administrative Assistant (Reporting / Scheduling) 15 $90.00 $1,350.00 FIELD SERVICES ESTIMATE $67,701.00

QUANTITY UNIT COST TOTAL
Mobilization / Travel
Trip Charge (Mileage, Bridge Toll, Parking Fees) 77 $70.00 $5,390.00 Equipment Charges
Nuclear Gauge Equipment Fee 28 $64.00 $1,792.00
DIR Project Administration
DIR Prescribed Reporting 12 $150.00 $1,800.00

QUANTITY UNIT COST TOTAL
Soils Testing
Modified Proctor, 6" Curve 5 $286.00 $1,430.00
R-Value of Soils (CT 301) - Aggregate Base/Import Borrow 4 $454.00 $1,816.00 Sieve Analysis of Soils (CT 202) 14 $195.00 $2,730.00
Sand Equivalent (CT 217) 14 $144.00 $2,016.00
Durability Index (AASHTO T210) 1 $286.00 $286.00
HMA Testing
Sieve Analysis - 3 Bin Samples (AASHTO T27) 3 $285.00 $855.00 Sand Equivalent (AASHTO T27) 3 $144.00 $432.00
Aggregate Moisture Content (AASHTO T255) 3 $49.00 $147.00 Percent Crushed Particles (AASHTO T335) 2 $189.00 $378.00 LA Rattler (AASHTO T96) 2 $327.00 $654.00
Flat and Elongated Particles (ASTM D47915) 2 $144.00 $288.00 Fine Aggregate Angularity (CTM 234) 2 $92.00 $184.00
Asphalt Binder Content (AASHTO T308, Method A) 3 $256.00 $768.00 Ignition Oven Correction Factor 1 $595.00 $595.00
HMA Moisture Content (AASHTO T329) 3 $75.00 $225.00
Gyraratory Compaction / Sample Preparation 1 $382.00 $382.00 Air Void Content (AASHTO T269) 1 $167.00 $167.00
Voids in Mineral Aggregate 2 $64.00 $128.00
Dust Proportion 2 $64.00 $128.00
Theoretical Maximum Density (CTM 309) 3 $286.00 $858.00 Hamburg Wheel Track (AASHTO T324 $3,005.00 if required
Moisture Susceptibility (AASHTO T283) $1,253.00 if required HMA Core Unit Weight/ Bulk Specific Gravity (CTM 308) 8 $167.00 $1,336.00 Concrete Testing
Concrete Compressive Strength Test (Set of 4) 15 $155.00 $2,325.00 Aggregate Gradation - Coarse and Fine (CTM 202) 15 $190.00 $2,850.00 Cleanness Value (CTM 227) 15 $206.00 $3,090.00
Sand Equivalent (CTM 217) 15 $144.00 $2,160.00
Source Inspection Testing
Couplers, Sealant, Steel, HS Bolts, Anchor Rods TBD TBD $5,000.00 LABORATORY TESTING ESTIMATE $40,210.00
TOTAL BUDGET ESTIMATE $107,911.00
1 per day
1 per day
1 per day
as required
1 per 4,000 tons
2 per project
2 per project
if required
1 set / day
1 per 250 Tons
if required
1 per 750 tons
1 per 750 tons
1 per 750 tons
2 per project
2 per project
2 per project
2 per project
1 per mix
1 per 750 tons
1 per day
1 per mix

DIRECT LABOR

DESCRIPTION OF ITEM FREQUENCY
1 per Trip
1 per 750 tons
1 per Day
1 per Month

DESCRIPTION OF ITEM FREQUENCY
as required
1 per 2000 CY
1 per 500 CY
1 per 500 CY
1 per project
BSK Associates - September 1, 2021 to June 30, 2022 Schedule of Fees (North Determination) PROFESSIONAL STAFF TECHNICAL STAFF (North Prevailing Wage) Principal $ 260.00 Group 1 - Special Inspector $ 155.00 Senior Professional $ 230.00 Group 2 - Special Inspector $ 149.00 Project Professional II $ 215.00 Group 3 - Engineering Technician $ 135.00 Project Professional I $ 180.00 Group 4 - Technician $ 118.00 Staff Professional II $ 160.00 Ground Penetrating Radar Scanning Technician $ 300.00 Staff Professional I $ 145.00 Core Drilling Technician $ 220.00 Seismic GIS $ 200.00 Floor Flatness Testing Technician $ 200.00 GIS Specialist $ 145.00 Courier $ 108.00
Information Specialist II $ 160.00 Laboratory Technician $ 120.00 Information Specialist I $ 145.00 Administrative Assistant / Clerical $ 90.00 CAD $ 105.00 Litigation support 1.5x standard rate
Project Administrator $ 100.00

BASIS OF CHARGES FOR FIELD TECHNICIAN SERVICES
REIMBURSABLES Field Work from 0 to 4 hours Bill 4 hours Mileage (Portal to Portal) $ 0.88 Field Work from 4 to 8 hours Bill 8 hours Per Diem (as required) $ 200.00 Field Work over 8 hours / Saturdays Bill time and a half Bridge Toll Cost + 15% Sundays, holidays and over 12 hours Bill double time Parking Fees Cost + 15% Second/Special/Multi-Shift
Subconsultant Services Cost + 15% Show-up time (no work performed) Bill 2 hours Project Administration Fees 7% of Invoice Sampling or cylinder pickup, minimum charge Bill 2 hours DIR Administration Fees 3% of Invoice
Project Setup (Project) $500.00 EQUIPMENT
Nuclear Gauge (Day) $ 64.00
ANALYSIS SOFTWARE USAGE FEES Ultrasonic Weld Equipment (Day) $ 64.00 gINT (Project) $ 59.00 Torque Wrench (Day) $ 64.00
LPile (Project) $ 59.00 Proof Load Equipment (Day) $ 64.00 APile (Project) $ 59.00 Rebar Locator / Pachometer $ 116.00 SHAFT (Project) $ 59.00 Hand Auger (Day) $ 232.00
GROUP (Project) $ 115.00 Water Meter (Day) $ 59.00
Cliq (Project) $ 59.00 Drilling Kit - Paint, stakes and lath - (Project) $ 30.00 LiquefyPro (Project) $ 59.00 Drilling Supplies - Reuse of tubes/caps (Project) $ 290.00 LiqIT (Project) $ 50.00 Manometer (Day) $ 224.00
NovoLIQ (Project) $ 59.00 Double Ring Infiltrometer (Day) $ 579.00 Slide (Project) $ 115.00
Settle3D (Project) $ 115.00 DIR/PREVAILING WAGE ADMINISTRATION FEES (MONTHLY) ArcGIS (Project) $ 59.00 Certified Payroll / DIR Upload $ 300.00 EZ-FRISK (Per Project Site / Site Class) $ 550.00 Non-Performance Certified Payroll / DIR Upload $ 100.00 Subcontractor Management / Compliance Forms $ 100.00
Additional LCP Tracker or Other Compliance Software $ 200.00 Additional Special Forms, as required $ 150.00
Moisture Density Curves California Bearing Ratio (CBR)
Standard Proctor, 4" (ASTM/AASHTO) $ 269.00 CBR at 100% (ASTM D1883 or AASHTO T-180) $ 585.00 Modified Proctor, 4" Mold (ASTM/AASHTO) $ 269.00 CBR at 95% (ASTM D1883 or AASHTO T-180) $ 1,133.00 Modified Proctor, 6" mold (ASTM D1557) $ 286.00
Caltrans Maximum Wet Density (CT 216) $ 245.00 Permeability Tests Check Point $ 155.00 Rigid Wall Permeability (ASTM D2434) $ 322.00 Flexible Wall Permeability (ASTM D5084) $ 502.00
Particle Size Analysis Remolded Flexwall Perm (ASTM D5084) $ 638.00 Sieve Analysis w/ Wash (ASTM D422) $ 195.00
Minus #200 Wash, Soil (ASTM D1140) $ 95.00 Soil Corrosivity Tests Hydrometer Analysis (ASTM D422) $ 256.00 Minimum Resistivity of Soils (CT 643) $ 161.00 Double Hydrometer (ASTM D4221) $ 357.00 pH $ 75.00
Specific Gravity of Soil (ASTM D854) $ 183.00 Soluble Sulfate, Chloride and Sulfide $ 149.00 Visual Classification (ASTM D2488) $ 49.00
Sand Equivalent (ASTM D2419) $ 144.00 Soil Cement Tests % Organics in Soil (ASTM D2974) $ 156.00 Freeze Thaw Abrasion (ASTM D560) $ 715.00 Wetting-Drying Abrasion (ASTM D559) $ 679.00
Atterberg Limits / Swell Tests Preparation of Freeze-Thaw or Wetting-Drying Tests $ 859.00 Plasticity Index (ASTM D4318) $ 250.00 Soil Cement Compression (ASTM D1633) $ 275.00 Shrinkage Limits of Soils (ASTM D427) $ 233.00
Other
Moisture Density Test Sand Density Calibration (ASTM D1566) $ 107.00 Tube Density $ 57.00
Moisture Content of Soils (ASTM D2216) $ 49.00 Unconfined Compression Unconfined Compression (ASTM D2166) $ 144.00
"R" Value Determination
R-Value of Soils (CT 301) $ 454.00 Shear Tests
R-Value of Treated Materials (CT 301)) $ 502.00 Direct Shear, Undisturbed (ASTM D3080) $ 250.00 Direct Shear, Remolded (ASTM D3080) $ 299.00
Consolidation Tests Triaxial Compression Testing QUOTE
Consolidation (ASTM D2435) $ 478.00
Consolidation , Extra Points (ASTM D2435) $ 64.00
Collapse Potential of Soils (ASTM D2435) $ 233.00
Remolded Consolidation (ASTM D2435) $ 405.00
One-Dimen Swell of Soil (ASTM D4546) $ 149.00

PERSONNEL RATES
SOILS
Base Rate x 12.5%

MATERIALS LABORATORY TESTS

Page 1 of 2 ends

BSK Associates - September 1, 2021 to June 30, 2022 Schedule of Fees (North Determination) Sieve Analysis Coarse or Fine (ASTM C136) $ 95.00 Cement Content Concrete (ASTM C1084) $ 431.00 Sieve Analysis w/ Fineness Modulus $ 102.00 Chemical Test (ASTM C150) QUOTE Minus 200 Wash, Aggregates (ASTM C117) $ 95.00 Set Times Cement-Vicat Needle (ASTM C191) $ 357.00 Specific Gravity/Absorption (ASTM C127) $ 183.00 Specific Gravity of Hydraulic Cement (ASTM C191) $ 172.00 Specific Gravity/Absorption (ASTM C128) $ 183.00 Lineal Shrinkage Set of 3 (ASTM C157) $ 454.00 Organic Impurities (ASTM C40) $ 95.00 Compression Test of Concrete - 1 (ASTM C39) $ 39.00 % Lumps/Friable Particles (ASTM C142) $ 92.00 Compression Test of Concrete - 4 (ASTM C39) $ 155.00 % Flat and Elongated (ASTM D4791) $ 144.00 Compression Test of Core (ASTM C42) $ 69.00 Fine Aggregate Angularity (AASHTO 304) $ 92.00 Preparation of Specimens, Sawing $ 78.00 Moisture Content (ASTM D2216) $ 49.00 Compressive Strength of Shotcrete Panel $ 364.00 Aggregate Wt., pcf Compacted (ASTM C29) $ 101.00 Proportion of Cement in Concrete (ASTM C85) $ 399.00 Aggregate Wt., pcf Loose (ASTM C29) $ 75.00 Flexural Test Per Beam (ASTM C78) $ 102.00 Abrasion by LA Rattler, Small Size (ASTM C131) $ 269.00 Splitting Tensile Strength of Concrete (ASTM C496) $ 102.00 Abrasion by LA Rattler, Large Size (ASTM C131) $ 327.00 Unit Weight Lt Wt Concrete (ASTM C567) $ 64.00 Sodium Sulfate Soundness, Per Sieve (ASTM C88) $ 125.00 "AZ" Test-Reinforced Concrete Pipe "Life Factor" $ 89.00 Sodium Sulfate Soundness, Min. Charge (ASTM C88) $ 399.00 9 Pt Core Measurements, Each (ASTM C174) $ 39.00 Sand Equivalent (ASTM D2419 OR CT 217-I) $ 144.00 Concrete Trial Batches QUOTE Durability Index (CT 229) $ 286.00 Unit Weight & Abs Concrete (ASTM D642) $ 144.00 Potential Reactivity of Aggregates QUOTE Accelerated Curing of Concrete (ASTM C684) $ 286.00 Cleanness Value of Aggregate (CT 227) $ 206.00 Cylinder Molds (each) $ 8.00 Hydrometer (ASTM D422 OR CT 205-E) $ 256.00 Storage of Concrete Cylinders for more than 45 Days $ 66.00 % Crushed particles (CT 205) $ 189.00 RH Probe $ 66.00
Lightweight Pieces (ASTM 123) $ 250.00 Calcium Chloride Kit $ 44.00 Mixing Water (pH, elec. conductance, chloride, sulfate) $ 113.00 Contact Soil (pH, elec. conductance, chloride, sulfate) $ 136.00

HOT MIX ASPHALT
JMF Mix Design, HVEEM $ 3,542.00 MASONRY
JMF Mix Design, Marshall $ 4,197.00 Concrete Masonry Units Testing (ASTM C90) JMF Mix Design, Superpave / Caltrans $ 10,226.00 Compression Test Pavers, Single $ 88.00 JMF Verification - HMA - Superpave / Caltrans $ 5,926.00 Compression Test Composit CMU Prism $ 189.00 JMF Production Startup - Superpave / Caltrans $ 5,513.00 Specific Gravity and Unit Weight $ 131.00 RAP Material Testing - Additional Fee $ 717.00 Moisture Content $ 61.00 Rubberized RHMA Material - Additional Fee $ 1,654.00 Compression Test, Masonry Units (ASTM C140) $ 119.00 Hamburg Wheel Track (AASHTO T324) $ 3,005.00 Absorption / Moisture Content (ASTM C140) $ 119.00 Gyratory Compaction (AASHTO T312) $ 382.00 Linear Shrinkage (ASTM C426) $ 460.00 AC Content by Centrifuge (ASTM D2172) $ 328.00 Masonry Core Shear Test (Title 24) $ 214.00 AC Content-Ignition (ASTM D6307 / CT382 / AASHTO T308) $ 256.00 Masonry Core Compression/Shear Test (Title 24) $ 214.00 Superpave Ignition Oven Correction (AASHTO T308) $ 595.00 Compression Test Brick, Each (ASTM C67) $ 85.00 Moisture Content of Asphalt (CT 370) $ 75.00 Absorption/ Unit Wt. of Brick (ASTM C67) $ 89.00 Gradation/Extraction Aggregate (ASTM D5444) $ 155.00 Compression Test Grout (Set of 3 or 4) $ 137.00 Film Stripping $ 102.00 Compression Test Mortar (Set of 3 or 4) $ 125.00 Compaction/Preparation of HMA Briquette (CT 304) $ 250.00 Stabilometer Value (CT 366 / AASHTO T246) $ 201.00 WELDING AND STRUCTURAL STEEL AC Core Specific Gravity (ASTM D2726) $ 64.00 Welder Qualification Testing AC Core Specific Gravity - Paraffin Coated (AASHTO T275) $ 167.00 Welder / Procedure Welder Qualification Testing QUOTE AC Max Density Rice Method (ASTM D2041) $ 286.00 Face Bend of Steel $ 69.00 CIR/FDR Compressive Strength Testing (pre-compacted $ 275.00 Root Bend of Weld Coupon $ 69.00 specimen, includes conditioning) – CTM 371 Side Bend of Weld Coupon $ 69.00 Tensile Strength Ratio (AASHTO T283) $ 1,253.00 Tensile Test of Steel Coupon $ 95.00 Moisture Vapor Susceptibility (CT 307) $ 233.00 Bend Test of Steel Coupon $ 82.00 AC Surface Abrasion (CT 360) $ 572.00 Machining Charges (Per Coupon) QUOTE Index Retained Strength (ASTM D1074-D1075) $ 512.00 Brinell Hardness of Steel (ASTM E10) $ 113.00 AC Hveem Maximum Density (CT 375) $ 512.00 Rockwell Hardness of Steel (ASTM E18) $ 113.00 Marshall Stability and Flow (ASTM D6927) $ 286.00 Bolt Ultimate Load $ 151.00 Calculated AC Maximum Density (CT 367) $ 113.00 Bolt Hardness (set of 3) $ 113.00 Marshall Maximum Density, 50 Blows (ASTM D6926) $ 333.00 Nut Hardness (set of 3) $ 113.00 Examination of AC Cores $ 39.00 Washer Hardness (set of 3) $ 113.00 Thickness Determination of AC Cores $ 25.00 Proof Loading, bolt or nut $ 161.00 AC Tensile-Strength Premixed ASTM D4867 $ 740.00
AC Tensile-Strength Lab Mixed ASTM D4867 $ 1,253.00

REINFORCING STEEL FIREPROOFING
Tensile & Bend of Rebar, #3 - #8 $ 169.00 Cohesion/Adhesion Fireproofing Materials $ 144.00 Tensile & Bend of Rebar, #9 - #11 $ 169.00 Dry Density Fireproofing (ASTM E605) $ 108.00 Bend Test of Rebar $ 69.00
Slip and Tensile Rebar Couplers (CT 670) $ 246.00
Tension Test of Welded Wire Fabric QUOTE
Bend Test of Welded Wire Fabric QUOTE
Weld Shear Test, Welded Wire Fabric QUOTE
PT Cable Tensile and Elongation (ASTM A416 or A421) $ 310.00 PT Cable Preparation QUOTE
Escalation: The prices noted above are subject to an increase of 3-5% annual, effective January 1 of each year following the initiation of a services agreement.

AGGREGATES CONCRETE

MATERIALS LABORATORY TESTS

Page 2 of 2 ends

Our Offices
Local Office Information
San Jose
2055 Gateway Place, Ste. 470
San Jose, CA 95110
Tel. (408) 435-5503
Fax (408) 435-5505
Richmond
125 Park Place, Ste. 122
Richmond, CA 94801
Tel. (510) 232-6260
Fax (510) 232-6290
Humboldt County
1225 Central Ave., Ste. 10
McKinleyville, CA 95519
Tel. (707) 273-1004
Fax (707) 273-1002
Oakland
1970 Broadway, Suite 1220
Oakland, CA 94612
Tel. (510) 451-4180
Fax (510) 451
Roseville
2990 Lava Ridge Ct., Suite 120
Roseville, CA 95661
Tel. (916) 757-6006
Fax (916) 789-0105
Additional California Offices
Commerce
5800 S. Eastern Ave, Ste. 370
Commerce, CA 90040
Tel. (323) 447-2177
Fax (323) 477-2555
Irvine
9241 Irvine Blvd., Suite 150
Irvine, CA 92518
Tel. (949) 305-2980
Fax (949) 305-2440
Folsom
110 Blue Ravine Rd., Suite 150
Folsom, CA 95630

← All documents from this meeting