CAPITAL PROJECT FACT SHEET PN: 1445000
The Alameda County Transportation Commission
(Alameda CTC), in cooperation with the California
Department of Transportation (Caltrans) and the cities
of Berkeley and Emeryville, proposes to reconstruct the I-80/ Ashby Avenue interchange to improve accessibility, safety, traffic flow, and bicycle and pedestrian facilities.

These improvements are intended to provide traffic
congestion relief and enhanced mobility at this critical access point and important intersection of regional
transportation routes. The project will also provide
multimodal transport options, while improving community connectedness, including connectivity to the existing Bay Trail. This project was approved by Alameda County
voters in 2014 under Measure BB and represents a direct investment in regional infrastructure and economic
development. It will provide a direct connection between westbound Interstate 80 (I-80) and Emeryville
by way of Shellmound Street. Improvements will include:
• A new bridge to replace existing bridges
• A new interchange form with connections to
Shellmound Street and Frontage Road
• Provision of bicycle and pedestrian access over
the I-80 freeway at the Ashby Avenue interchange
Interstate 80/Ashby Avenue (SR-13)
Interchange Improvements

PROJECT OVERVIEW
DECEMBER 2021

PROJECT NEED
• The existing I-80/Ashby interchange provides no
access to Shellmound Street to/from westbound I-80
nor from Shellmound Street to Frontage Road.
• All westbound traffic to access Emeryville must use
the Powell Street interchange.
• There is no direct pedestrian and bicyclist access to the Bay Trail from Shellmound Street.

PROJECT BENEFITS
• Improves mobility and reduces congestion on Ashby
Avenue at the I-80/Powell Street interchange and at
the intersection of Ashby Avenue and 7th Street
• Provides safe access for pedestrians and bicyclists to connect across I-80, linking the San Francisco Bay Trail to the City of Emeryville and Berkeley’s Aquatic Park
(For illustrative purposes only.)
Alameda County Transportation Commission 1111 Broadway, Suite 800 Oakland, CA 94607 510.208.7400 www.AlamedaCTC. org Caltrans, Alameda CTC and the cities of Berkeley and Emeryville Note: Information on this fact sheet is subject to periodic updates.

INTERSTATE 80/ASHBY AVENUE (SR-13) INTERCHANGE IMPROVEMENTS

PARTNERS AND STAKEHOLDERS
STATUS
Implementing Agency: Alameda CTC
Current Phase: Project Approval/Environmental Document
(PA&ED) – Initial Study/Environmental Assessment (IS/EA) • A public scoping meeting was held on May 22, 2019.
• Draft Environmental Document (DED) is circulated for 45-day public review beginning December 15, 2021 through
January 31, 2022. Download the DED at www.I80Ashby.com. • A virtual Public Open House will be held on January 11, 2022, 5:30-7:00 p.m. Visit www.I80ashby.com or dial in at
888-344-3561 (English), 888-348-0479 (Spanish) or
888-386-0764 (Cantonese).
• Project Approval and Final Environmental Document
(PA&ED) is anticipated in spring 2022.

Aerial view of I-80/Ashby Avenue (SR-13) interchange.

COST ESTIMATE BY PHASE ($ X 1,000)
PE/Environmental $4,500
Final Design (PS&E) $10,550
Right-of-Way/Utility $4,400
Construction $137,600
Total Expenditures $157,050

SCHEDULE BY PHASE
Measure BB $52,000
Federal TBD
State $50
Local TBD
Total Revenues $157,050
FUNDING SOURCES ($ X 1,000)
Note: Schedule subject to funding availability.

Begin End
Preliminary Engineering/
Environmental
Fall 2017 Early 2022
Final Design Early 2022 Fall 2023
Right-of-Way Early 2022 Fall 2023
Construction Spring 2024 Fall 2026
I-80 freeway looking south approaching
the Ashby Avenue exit.

I-80 eastbound Eastshore Freeway
approach at the Ashby Avenue exit.