2023/2024 Sustainable Streetscapes Project
Project Description
This project generally includes, but is not limited to, the reconstruction and preservation of asphalt pavement (primarily via slurry seal); replacement of traffic striping and markings; and installation of signs.
Project Locations
Street Name
From
To
48TH STREET
SAN PABLO AVENUE
CITY LIMITS
SALEM STREET
48TH STREET
47TH STREET
47TH STREET
SAN PABLO AVENUE
ADELINE STREET
45TH STREET
SAN PABLO AVENUE
ADELINE STREET
SALEM STREET
45TH STREET
43RD STREET
ESSEX STREET
45TH STREET
43RD STREET
43RD STREET
SAN PABLO AVENUE
ADELINE STREET
DOYLE STREET
47TH STREET
45TH STREET
45TH STREET
HOLLIS STREET
SAN PABLO AVENUE
53RD STREET
HOLLIS STREET
SAN PABLO AVENUE
MARINA PARKING LOT
PT EMERY PARKING LOT
CITY HALL PARKING LOT
STATION 35 PARKING LOT
Proposed Schedule for Completion
December 31, 2024
Estimated Useful Life
10 Years
Technology, Climate Change, and Complete Streets Considerations The City will add in project elements that follow SHC Section 2030(c)-(f) to the extent possible (where cost effective and feasible).
Other Statutory Consideration for Project Lists
Where applicable, the Project will follow SHC Sections 2034(a)(1), 2030(b), and 2037.
Exhibit A – City of Emeryville 2023/2024 SB 1 Project List