RESOLUTION NO. 23-106
Resolution Of The City Council Of The City Of Emeryville Approving Addition Of New Scope Of Work (Exhibit A-1) Related To Additional Design Work For Unsignalized Intersections On The North Side Of 40th Street As Part Of The 40th Street Multimodal Project For The Professional Services Contract With Diablo Engineering Group
WHEREAS, on March 3, 2020, the City Council approved the conceptual design of the 40th Street Multimodal Project and found it to be exempt from the California Environmental Quality Act; and
WHEREAS, as part of the resolution, City Council instructed Staff to conduct a traffic feasibility study for full and partial closures of the unsignalized streets that connect to 40th Street from the north (Watts, Haven, Holden, and Hubbard); and WHEREAS, in August 2022, the Public Works Department issued a Request for Proposals for "Professional Design Services for the 40th Street Transit-Only Lanes And Multimodal Enhancements Project" and after careful evaluation, City staff identified Diablo Engineering Group (“Diablo Engineering”) as the most suitable consultant, considering their approach, experience, and understanding of the City's requirements; and
WHEREAS, in early 2023, Fehr & Peers (a subconsultant to the Diablo Engineering team) completed a traffic feasibility analysis as one of the first items of work for the design phase of the Project and the results of the analysis were shared with the Emeryville Transportation Committee on May 9, 2023; and
WHEREAS, there is need for additional work related to the unsignalized intersections, Staff recommends extending the design contract with Diablo Engineering to include Exhibit A-1 for a total cost of $120,232.00; and
WHEREAS, Tasks described in Exhibit A-1 include the preparation of final traffic analyses, environmental studies, and civil designs for the additional design work needed for the unsignalized intersections on the north side of 40th Street; and WHEREAS, the 40th Street Multimodal Project including Exhibit A-1 is fully funded through various grant programs for Design and Construction Phases, and there is adequate budget in CIP Project No. 22242002; now, therefore, be it RESOLVED, by the City Council of the City of Emeryville that the City Council approves the addition of new scope of work (Exhibit A-1) related to additional design work for unsignalized intersections on the north side of 40th Street as part of The 40th Street Multimodal Project for the Professional Services Contract With Diablo Engineering Group.
DocuSign Envelope ID: 0B76E2D1-4829-4E2C-A765-8889DC7B2137 Resolution No. 23-106
40th Street Multimodal Project – Addition of Exhibit A-1 to 40th Street Multimodal Project City Council Meeting | July 18, 2023
ADOPTED, by the City Council of the City of Emeryville at a regular meeting held Tuesday, July 18, 2023, by the following vote:
AYES: 4
Mayor Bauters, Vice Mayor Welch and Council Members Kaur and Mourra
NOES: 1 Council Member Priforce
ABSTAIN: 0
ABSENT: 0
MAYOR
ATTEST: APPROVED AS TO FORM:
CITY CLERK CITY ATTORNEY
ATTACHMENTS
Exhibit A-1 – Design Work for Unsignalized Intersections on 40th Street (Task 8) DocuSign Envelope ID: 0B76E2D1-4829-4E2C-A765-8889DC7B2137 Proposal - 40th Street Multimodal Project Amendment Request 1 SCOPE OF WORK – PHASE 1
The Diablo Team will collaborate with the City Team to implement the following design and coordination items for the Project.
Project Tasks
8. 40th Street Phase 1 Added Scope of Work
8.1. Video Data Collection: For Hubbard Street, Horton Street, Holden Street, and Watts Street (between 40th Street and Park Avenue, IDAX to obtain 24-hour video for 4 weeks and then processing 12 hours per day for the first 14 days, given that the nighttime will likely have little activity. All videos will be collected using strategically placed wide angle timelapse cameras to cover the curb space. Full video will be provided in addition to a summary of Delivery Truck, Single Unit Truck and Truck w/Trailer per road and by date.
8.2. Added Traffic Analysis for Horton Diverter and Chick-Fil-A: For Hubbard Street, Holden Street, Haven Street and Watts Street, the traffic analysis includes all of these streets either opened or fully closed. In the original Alternative 2, the Horton Diverter was added to the analysis as requested by the City. After further coordination, the decision on if the Horton Diverter will be installed has been postponed until after this project. The City has also brought up concerns about the heavy traffic caused by the new Chick-Fil-A restaurant. Therefore, the following tasks will be added to the traffic analysis:
- Collect traffic data for Chick-Fil-A.
- Update Alternative 1 (all streets open) with Chick-Fil-A data. - Add New Alternative 3 (unsignalized streets closed, no Horton Diverter) with Chick-Fil-A data. - Prepare the final operations report with updated analysis. - Exclude Alternative 2 from any further analysis and exclude it from the final report.
8.3 Added Field Topography for Hubbard Street: For Hubbard Street sidewalk on the West side, topography will be collected to be used for designing new sidewalk to close the gap between 40th Street and Park Boulevard.
8.4 Added Design for Hubbard St and Path Connection to Halleck St: For Hubbard Street sidewalk on the West side, design of new sidewalk (approximately 320 linear feet) to close the gap between 40th Street and Park Boulevard will be added to the 40th Street plan submittals.
In addition, a new Class I path (approximately 280 linear feet) will be added to connect Halleck Street to the new cycle track on 40th Street in the area of Hubbard Street. This design will involve tight grading and potentially retaining walls given the constraints between 40th Street and the Pottery & Beyond lot. This will also be added to the 40th Street plan submittals.
8.5 Additional Outreach Efforts: Unsignalized Intersection Outreach: Effort for the preparation and mailing of the mailer to these stakeholders has gone through additional rounds of review which has increased labor cost. The area the mailer is being sent to has increased the number of mailings, currently estimated to be 550.
Exhibit A-1 Page 1 of 3
DocuSign Envelope ID: 0B76E2D1-4829-4E2C-A765-8889DC7B2137 Proposal - 40th Street Multimodal Project Amendment Request 2 Postcard to Broader Area around 40th Street project: This is a new task requiring content development and layout for the postcard to inform a broader area of stakeholders about the project moving forward and the Council Meeting where the 35% design will be approved.
Printing and mailing costs of the postcard is based on an estimated 750 addresses.
Exhibit A-1 Page 2 of 3
DocuSign Envelope ID: 0B76E2D1-4829-4E2C-A765-8889DC7B2137
TASK BREAKDOWN INVOICE SUMMARY
Diablo Engineering Group Team Invoicing
40th Street Transit-Only Lanes and Multimodal Enhancements Project Budget
TASK 1.0 Project Management and Grant Management
1.1 Regularly Scheduled Project Team Meetings $72,107.15
1.2 City/Project Manager Communications and Consultations $11,632.67
1.3 Partner Agency (Staff) Coordination and/or Meetings $15,645.01
1.4 Develop and Update Project Schedule $3,192.00
1.5 Manage SB1 ATP Cycle 5 Grant Funding Agreement Tasks $5,468.00
1.6 Manage ACTC Forms and Reports Deliverables $5,468.00
1.7 Perform Project Administration Tasks $72,077.21
Subtotal - TASK 1.0 $185,590.05
TASK 2.0 Environmental Review
2.1 Review Existing Project Environmental Approvals $3,232.40
2.2 Prepare Memo of NEPA Environmental Recommendations $4,033.26
2.3 Pavement Investigation and Design $13,109.93
2.4 Optional NEPA Clearance Assuming Caltrans Federal Funding $8,401.37
2.5 FEMA Floodplain Maps $887.65
2.6 Biological Technical Memo $6,628.28
2.7 Visual Impact Assessment Questionnaire $2,137.86
2.8 Equipment Staging Technical Memo $2,775.51
2.9 Cultural Resources APE and Memo - Section 106 compliance $16,049.14
2.10 Water Quality Technical Memo $6,389.22
2.11 Hazardous Materials Technical Memo $3,155.13
2.12 Hydrology $3,508.89
2.13 ROW Information Technical Memo (Diablo) $45,233.12
2.14 Traffic Technical Memo (F&P) $16,748.72
Subtotal - TASK 2.0 $132,290.48
TASK 3.0 Traffic Impact Assessment
3.1 Expand Existing VISSIM Model (AM and PM models) $6,383.35
3.2 Execute Existing VISSIM Model (AM and PM models) $13,104.67
3.3 Traffic Diversion Study (AM and PM) $13,556.39
3.4 Execute Project VISSIM Model (AM and PM models) $19,751.24
3.5 Multimodal Traffic Operations Documentation $12,948.11 Subtotal - TASK 3.0 $65,743.77
TASK 4.0 Public Outreach
4.1 Facilitate Community Engagement Meetings $67,563.65
4.2 Agency Engagement $36,835.59
4.3 City Committees and Council Meetings $18,874.43
Subtotal - TASK 4.0 $123,273.68
TASK 5.0 PS&E Design Services
5.1 Develop Corridor Planimetric and Topographic Surveys $39,384.25
5.2 Develop Right of Way and Existing Utility Base Mapping $28,680.23
5.3 Facilitate Conceptual Geometric Design Development $52,798.31
5.4 Develop and Finalize Geometric Approval Drawings (35% Milestone) $214,574.89
5.5 Develop Final Construction Drawings (65% Milestone) $272,250.80
5.6 Develop Final Construction Drawings (95% Milestone) $294,197.85
5.7 Develop Final Construction Drawings (100% Milestone) $198,714.07
5.8 Develop Final Construction Drawings (Final PS&E Milestone) $101,329.59
5.9 Prepare Updated Construction Cost Estimate (35%, 65%, 95%, 100%, Final) $101,809.44
5.10 Prepare Project Specifications (65%, 95%, 100% and Final) $55,304.52
5.11 Utility Coordination $29,799.94
5.12 Photometric Study $10,164.32
5.13 Easement Support $33,861.12
5.14 Monument Preservation $15,802.66
Subtotal - TASK 5.0 $1,448,672.00
TASK 6.0 Project Approvals
6.1 Coordinate and Manage PS&E Reviews and Approvals (City of Emeryville) $17,421.01
6.2 Coordinate and Manage PS&E Reviews and Approvals (City of Oakland) $11,228.34
6.3 Coordinate and Manage PS&E Reviews and Approvals (Caltrans) $16,330.84
6.4 Caltrans LAPM Forms $11,768.00
Subtotal - TASK 6.0 $56,748.19
TASK 7.0 Project Funding Outlook and Grant Support
7.1 Evaluate Grant Opportunities $3,608.00
7.2 Support the City with Grant Writing (Narrative, Mapping, Exhibits, and Forms) $12,043.72 Subtotal - TASK 7.0 $15,651.72
TASK 8.0 Added Scope of Work*
8.1 Video Data Collection $47,400.00
8.2 Added Traffic Analysis for Horton Diverter and Chick-Fil-A $18,000.00
8.3 Added Field Topography for Hubbard St $5,000.00
8.4 Added Design for Hubbard St and Path Connection to Halleck St $35,332.00
8.5 Additional Outreach Efforts $14,500.00
Subtotal - TASK 8.0 $120,232.00
$2,027,969.88
Other Direct Costs (Reimbursables):
Reprographics, Expenses, Mileage and Title Reports $19,778.87 Topographic Surveys/Aerial Mapping/Field Surveys/ Potholing $37,000.00 Prepare Irrigation Plans (subcontracted expense) $45,000.00 Supplimental Weekday Traffic Counts $3,000.00
Traffic Control, Coring and Soils Lab Testing $17,200.00 Total Other Direct Costs (Reimbursables): $121,978.87
Diablo Engineering Group Labor (Hours and Fee) $823,719.60 CD+A (Hours and Fee) $335,291.40
Fehr & Peers (Hours and Fee) $431,501.22
NCE (Hours and Fee) $80,834.59
MNS (Hours and Fee) $525,713.16
Total Hours and Labor $2,197,059.97
Total Other Direct Costs (Reimbursables): $121,978.87
Total Time and Materials Cost Approved $2,198,806.84
Total Time and Materials Cost with Task 8 Amendment $2,319,038.84 Total Hours/Fee Task 1 Through Task 7