RESOLUTION NO. 25-37
Resolution Of The City Council Of The City Of Emeryville Approving The Proposed SB 1 Project List And Appropriation For Fiscal Year 2025/2026 WHEREAS, Senate Bill 1 (SB 1), Road Repair and Accountability Act (RRAA) of 2017 (Chapter 5, Statutes of 2017) was passed by the State Legislature and signed into law by the Governor in April of 2017 to address the significant multi-modal transportation funding shortfalls statewide; and
WHEREAS, SB 1 includes accountability and transparency provisions that will ensure the residents of Emeryville are aware of the projects proposed for funding in the community and which projects have been completed each fiscal year; and WHEREAS, the City must include a list of all projects proposed to receive funding from the Road Maintenance and Rehabilitation Account (RMRA), created by SB 1, in the City budget, which must include a description and the location of each proposed project, a proposed schedule for the project’s completion, and the estimated useful life of the improvement; and
WHEREAS, the City will receive an estimated $349,317 in RMRA funding for Fiscal Year 2025/2026; and
WHEREAS, this is the eighth year in which the City is receiving SB 1 funding, and this funding will enable the City to continue essential road maintenance and rehabilitation projects, safety improvements, repairing and replacing aging bridges, and increasing access and mobility options for the traveling public that would not have otherwise been possible without SB 1; and
WHEREAS, the City has undergone a robust public process to ensure public input into our community’s transportation priorities and project list; and WHEREAS, the funding from SB 1 will help the City maintain and rehabilitate streets, roads and pedestrian infrastructure, and it will also add active transportation infrastructure throughout the City this year and many similar projects into the future; and WHEREAS, the 2023 report of Emeryville’s Pavement Management Program showed that the average overall network Pavement Condition Index (PCI) of the City’s street network is 81, which indicates that the street network is in ‘Good’ condition, and this SB 1 funding will help the City to increase the overall quality of our road system over the next decade into an “excellent” condition; and
WHEREAS, the SB 1 Project List and overall investment in our local streets and roads infrastructure with a focus on basic maintenance and safety, investing in complete streets infrastructure, and using cutting-edge technology, materials, and practices, will have significant positive co-benefits statewide; and
Docusign Envelope ID: EB590F0D-0537-4947-8FE1-6DA1B1F6F07F Resolution No. 25-37
SB1 Project List For Fiscal Year 2025/2026
City Council Meeting | May 20, 2025
WHEREAS, the City of Emeryville is committed to ensuring that the RMRA funds received will be used and reported on as required by statute and the California Transportation Commission's (CTC) adopted program guidelines; and
WHEREAS, in addition to submitting an SB 1 Project List to the CTC, the SB 1 guidelines require that all proposed projects be included within an agency’s budget, and the Capital Improvement Program budget includes this funding within the Sustainable Streetscapes Project (CIP No. 24221005); now, therefore, be it
RESOLVED, by the City Council of the City of Emeryville that it hereby approves the following list of proposed projects (the “SB 1 Project List”, attached hereto as Exhibit A) to be funded in Fiscal Year 2025/2026 with Road Maintenance and Rehabilitation Account revenues:
a. “2025 Sustainable Streetscapes Paving Project”; Various Locations; 10-year estimated useful life; Anticipated to be constructed in FY2025/2026; and, be it, further
RESOLVED, by the City Council of the City of Emeryville that it hereby approves the SB 1 Project List.
ADOPTED, by the City Council of the City of Emeryville at a regular meeting held Tuesday, May 20, 2025, by the following vote:
AYES: 5
Mayor Mourra, Vice Mayor Kaur and Council Members Priforce, Solomon and Welch
NOES: 0
ABSTAIN: 0
ABSENT: 0
MAYOR
ATTEST: APPROVED AS TO FORM:
CITY CLERK CITY ATTORNEY
ATTACHMENTS
Exhibit A – FY2025/2026 SB 1 Project List
Docusign Envelope ID: EB590F0D-0537-4947-8FE1-6DA1B1F6F07F Exhibit A – City of Emeryville 2025/2026 SB 1 Project List
1. 2025/2026 Sustainable Streetscapes Project
a. Project Description
i. This project generally includes, but is not limited to, the reconstruction and preservation of asphalt pavement (primarily via slurry seal); replacement of traffic striping and markings; and installation of signs. b. Project Locations
Street Name From To
ADELINE STREET 41STSTREET 36TH STREET
45TH STREET ADELINE STREET CITY LIMITS
44TH STREET ADELINE STREET CITY LIMITS
43RD STREET ADELINE STREET CITY LIMITS
FRONTAGE ROAD ACCESS ROAD POWELL STREET
EMERY STREET 40TH STREET MACARTHUR BLVD
PERALTA STREET MACARTHUR BLVD 36TH STREET
WATTS STREET MACARTHUR BLVD 36TH STREET
53RD STREET HOLLIS STREET SAN PABLO AVENUE
54TH STREET WESTERLY END BOYER STREET
67TH STREET SHELLMOUND STREET CITY LIMITS
CHRISTIE AVENUE 65TH STREET SHELLMOUND WAY
65TH STREET CHRISTIE AVENUE SHELLMOUND STREET
c. Proposed Schedule for Completion
i. June 30, 2026
d. Estimated Useful Life
i. 10 Years
e. Technology, Climate Change, and Complete Streets Considerations i. The City will add in project elements that follow SHC Section 2030(c)-(f) to the extent possible (where cost effective and feasible).
f. Other Statutory Consideration for Project Lists
i. Where applicable, the Project will follow SHC Sections 2034(a)(1), 2030(b), and 2037.
Docusign Envelope ID: EB590F0D-0537-4947-8FE1-6DA1B1F6F07F