Cities Index.
Exhibit A - FY25-26 SB1 Project List

Emeryville City Council
May 20, 2025

Document
Exhibit A - FY25-26 SB1 Project List
Meeting
May 20, 2025
Body
Emeryville City Council
Original file
47 KB
Text extracted from the city's file for reading and search. Open the original on emeryville.legistar1.com. That file is the official record.

Exhibit A – City of Emeryville 2025/2026 SB 1 Project List

1. 2025/2026 Sustainable Streetscapes Project
a. Project Description
i. This project generally includes, but is not limited to, the reconstruction and preservation of asphalt pavement (primarily via slurry seal); replacement of traffic striping and markings; and installation of signs. b. Project Locations
Street Name From To
ADELINE STREET 41STSTREET 36TH STREET
45TH STREET ADELINE STREET CITY LIMITS
44TH STREET ADELINE STREET CITY LIMITS
43RD STREET ADELINE STREET CITY LIMITS

FRONTAGE ROAD ACCESS ROAD POWELL STREET
EMERY STREET 40TH STREET MACARTHUR BLVD
PERALTA STREET MACARTHUR BLVD 36TH STREET
WATTS STREET MACARTHUR BLVD 36TH STREET
53RD STREET HOLLIS STREET SAN PABLO AVENUE
54TH STREET WESTERLY END BOYER STREET
67TH STREET SHELLMOUND STREET CITY LIMITS
CHRISTIE AVENUE 65TH STREET SHELLMOUND WAY
65TH STREET CHRISTIE AVENUE SHELLMOUND STREET
c. Proposed Schedule for Completion
i. June 30, 2026
d. Estimated Useful Life
i. 10 Years
e. Technology, Climate Change, and Complete Streets Considerations i. The City will add in project elements that follow SHC Section 2030(c)-(f) to the extent possible (where cost effective and feasible).
f. Other Statutory Consideration for Project Lists
i. Where applicable, the Project will follow SHC Sections 2034(a)(1), 2030(b), and 2037.