Status of Fairfax’s Federally
Funded Bridge Projects
July 17, 2024
Presented by:

Loren Umbertis, Public Works Director, Town of
Fairfax
and
Nader Tamannaie, MGE Engineering, Inc
The Town’s Four Bridge
Projects
Meadow Way Bridge, Structurally
Deficient (SD) – Replace
Bridge Preventative Maintenance
Project (BPMP) for Bridges on Canyon
Rd. Spruce Rd. & Marin Rd.
Creek Road Bridge, Seismically
Vulnerable – Retrofit
Azalea Avenue Bridge, SD - Replace
General Phases of Federal
Projects
Preliminary Engineering (PE): Preliminary
design and environmental studies
Right-of-Way (ROW): ROW engineering
and acquisitions, Utilities and Final Design
Construction (CON)
Funds for each phase applied for
separately
CEQA required but not funded by
Caltrans but instead locally
Meadow Way Bridge
PE funds applied for in 2010
PE started in 2013, 88.57% federally funded
ROW (current phase) & CON Phases 100%
funded
NEPA cleared in October 2019
CEQA adopted by the Town in June 2020
Eminent Domain for 2 properties, begin in
Q4, 2024
Temporary and Permanent Easements for 5
properties to begin in Q4, 2024
Meadow Way Bridge -
Continued
Agreements for five utility owners in Q1,
2025
Last neighborhood meeting before
CON in Q2, 2025
Regulatory Permits Applications in Q1
2025
CON projected for FFY 25/26 (Begin
spring 2026)
BPMP (Bridge Preventative
Maintenance Program)
 PE funds applied for in 2010, project started 2013
 All phases are 88.53% federally funded
 NOAA required Fish Ladder repairs at Canyon, 2019
 FHWA & NOAA at odds, FHWA conceding late 2021
 New requirement for Extended Phase I (XPI) Report
(new archeological excavations at Marin Rd.)
 Met with Tribal Representatives in late January 2023
 Cultural Resource Investigation completed in July
2023
 Submitted Historic Property Survey Report (HPSR) to
Caltrans 8/24
BPMP – Continued
Certify NEPA in 9/2024
Draft CEQA submitted for Fairfax review in
06/2024
Begin 30-day community review in late August,
2024
Anticipate CEQA Town Council hearing
Sep/Oct 2024
Begin ROW, Utilities & Final Design in Q4, 2024
ROW or utilities issues not anticipated;
easements needed, however
Begin Regulatory Permits Applications in Q1,
2025
CON targeted for FFY 2026 (late spring)
Creek Road Bridge
Funds applied for in 2010, project started in 2013
All phases are 100% federally funded
Project in tandem with BPMP due to common
San Anselmo Creek environmental issues & XPI
XPI meetings & studies same timeframe as BPMP
Historical Resources Evaluation Report (HRER)
and HPSR required. Submit both to Caltrans 8/24
Certify NEPA 09/2024
Draft CEQA submitted for Fairfax for review in
06/2024
Creek Road Bridge -
Continued
30-day community review to begin
August 2024
Expect CEQA Town Council hearing
Sep/Oct 2024
Begin ROW, Utilities & Final Design Q4,
2024
ROW negotiations needed with 2
homeowners for acquisition and
temporary easement
CON targeted for FFY 2026 (late spring)
Azalea Avenue Bridge
 Started in 2016, all phases 100% federally funded
 NEPA, CEQA and preliminary design proceeding
 County Flood Control Program requires elevation of
street level by 3 feet
 Town and MGE Consultant met with neighbors in
2021 for preliminary discussion
 Schedule follow up meeting with residents and
impacted property owners in Q1 2025
 ROW easements (not acquisitions) needed
 Host 1st workshop and general meeting, Q2 2025
Azalea Avenue Bridge -
Continued
Certify NEPA and CEQA in late 2025
CON currently envisioned in 2028
(begin late spring)
Questions