Cities Index.
Presentation-to-Fairfax-Town-Council-Creek-BPMP-Azalea

Fairfax City Council
June 4, 2025

Document
Presentation-to-Fairfax-Town-Council-Creek-BPMP-Azalea
Meeting
June 4, 2025
Body
Fairfax City Council
Original file
150 KB
Text extracted from the city's file for reading and search. Open the original on storage.googleapis.com. That file is the official record.

Status of Fairfax’s Three Other
Federally Funded Bridge Projects
June 4, 2025
Presented by:

Nader Tamannaie, MGE Engineering, Inc.

The Town’s Other 3 Bridge Projects
 Bridge Preventative Maintenance Program
(BPMP) for Bridges on Canyon Road, Spruce
Road and Marin Road
 Creek Road Bridge, Seismically Vulnerable –
Retrofit
 Azalea Avenue Bridge, SD – Replace
 Local share varies from 0% to 11.5%
 In contract with Caltrans, if local agency
walks away from a project, all funds would
have to be refunded to fed
General Phases of Federal Projects
 Preliminary Engineering (PE): Preliminary
design and environmental studies
 Right-of-Way (ROW): ROW engineering
and acquisitions, Utilities and Final Design
 Construction (CON)
 Funds for each phase applied for
separately
 CEQA is required also but funded locally
(Fairfax)
Bridge Preventative Maintenance
Program (BPMP )
 PE (88.53% federally funded) applied for in
2010, project started in 2013
 Canyon Rd. Fish Ladder repairs required by
NOAA, FHWA approved funds late 2021
 Extended Phase 1 (XPI- new requirement for
archeological excavations at Marin Rd.
 Met with Tribal Representatives early 2023
 XPI investigation completed in July 2023
 Awaiting Historic Property Survey Report
(HPSR) approval by Caltrans
BPMP – Continued
 Caltrans certifying NEPA shortly
 2nd Draft CEQA in review by Fairfax, followed
by 30-day community review period
 Anticipate CEQA Town Council hearing in Q3,
2025
 Begin ROW, Utilities & Final Design in Q3, 2025
 ROW or utilities issues not anticipated;
temporary easements needed, however
 Begin regulatory permit applications late 2025
 CON targeted for FFY 2026 (late spring)
Creek Rr. Bridge Seismic Retrofit and
BPMP
 Funds applied for in 2010, project started 2013
 All phases are 100% federally funded
 XPI meetings & studies same schedule as BPMP
 Historical Resources Evaluation Report (HRER) &
HPSR required, to be submit to Caltrans shortly
 Certify NEPA in a couple of months
 2nd round of Draft CEQA comments received
from Fairfax & being addressed
Creek Road Bridge, Continued
 30-day community review to begin after
addressing comments on Draft CEQA
 Process followed by Council CEQA adoption
 Begin ROW, Utilities & Final Design Q4, 2025
 ROW negotiations needed with one
homeowners to formalize small acquisition
 Another agreement for temporary easement
 CON anticipated in FFY 2027 (late spring)
Azalea Ave. Bridge Replacement
 Started in 2016, 100% federal funds all phases
 Flood Zone 9 Program requires raising
elevation of bridge & street by 3 feet
 NEPA, CEQA & preliminary design continuing
 Need significant easements (not acquisitions)
 Town and Nader met with 2 neighbors in 2021
 Need to schedule follow up meetings with
other impacted property owners
 Host 1st workshop and meeting, Q3 2025
Azalea Avenue Bridge, Continued
 Certify NEPA and CEQA in first half of 2026
 CON currently envisioned in 2028 (begin late
spring)
Questions

← All documents from this meeting