Status of Fairfax’s Meadow Way
Bridge Replacement Project
June 4, 2025
Presented by:

Nader Tamannaie, PE, MGE Engineering, Inc.

Fairfax’s Four Federally Funded
Bridge Projects
 Meadow Way Bridge, Structurally Deficient
(SD) – Replace
 Bridge Preventative Maintenance Program
(BPMP) for Bridges on Canyon Road,
Spruce Road and Marin Road
 Creek Road Bridge, Seismically Vulnerable
– Retrofit
 Azalea Avenue Bridge, SD - Replace
The First of Town’s 4 Bridge Projects
 Presenting Meadow Way Bridge
 Will present the other three projects
separately tonight
General Phases of Federal Projects
 Preliminary Engineering (PE): Preliminary
design and environmental studies
 Right-of-Way (ROW): ROW engineering
and acquisitions, Utilities and Final Design
 Construction (CON)
 Funds for each phase applied for
separately
 CEQA is required also but funded locally
(Fairfax)
Meadow Way Bridge
 PE funds applied for in 2010, 88.57% federal
funding. Project started in 2013
 In contract with Caltrans, if local agency walks
away from a project, all funds would have to
be refunded to fed
 NEPA cleared in 2019, CEQA in 2020
 ROW (current phase) & CON 100% funded
 Current Federal Amendment of $1,061,666
 $218,840 Fairfax match
Meadow Way Bridge - Continued
 Eminent Domain for 2 properties, temporary &
permanent easements, 5 properties
 Five utility entities run 6 utilities through the site  Agreements with five utility owners in Q3, 2025
 Last neighborhood meeting before CON in
Q4, 2025
 Regulatory Permits Applications in Q3 2025
 CON projected for FFY 26/27 (Begin Spring of
2026)
Questions