FAIRFAX TOWN COUNCIL MEETING

STAFF REPORT
AGENDA ITEM #4.h
MEETING DATE May 6, 2026
PREPARED FOR Mayor and Town Council
PREPARED BY Kristin Arnold, P.E. Director of Public Works SUBJECT Adopt a Resolution Approving the List of Projects for Fiscal Year 2026– 2027 Funded by SB 1: The Road Repair and Accountability Act of 2017

RECOMMENDATION
Adopt a resolution approving the list of projects for Fiscal Year 2026–2027 funded by SB 1: The Road Repair and Accountability Act of 2017.

DISCUSSION
Senate Bill 1 (SB 1), known as the Road Repair and Accountability Act of 2017 was created to address the need for more transportation funding in California. Each year, the California Transportation Commission (CTC) requires towns to submit an annual list of projects by July 1st to receive funding from SB 1. The project list must be adopted by resolution separate from the budget. The list needs to describe each project, its location, the proposed schedule for completion, and the expected lifespan of the improvements. CTC allows some flexibility to modify the list during the fiscal year.

The attached resolution includes the required project list. There is flexibility to change the project list if there is a change in priorities for the projects after we submit. If the funds are not enough to cover project costs in one fiscal year, the CTC allows jurisdictions to advance funds for projects and be reimbursed from future SB1 funds.

This project list was incorporated into the Town’s proposed FY26-27 budget.

The list is as follows:

Project Name Description
Approximate
Locations
Estimated
Useful Life
(Years)
Year of
Construction
General
Maintenance
General maintenance to include, but not limited to,
pothole patching, crack sealing, street signs, street
striping, and street sweeping. This project will
include Public Works staffing, public works
equipment, road maintenance and rehab materials,
procurement of public works safety materials and
gear.

Townwide 1-5 Start 07/2026
Complete
06/2027

FISCAL IMPACT
The Town will receive an estimated $213,105 from the Road Maintenance and Rehabilitation Account (RMRA) for fiscal year 2026-2027.

ATTACHMENTS
Resolution
Town of Fairfax
Resolution No.

Page 1 of 2 ends

RESOLUTION

A RESOLUTION OF THE TOWN COUNCIL OF THE TOWN OF FAIRFAX APPROVING THE LIST OF PROJECTS FOR FISCAL YEAR 2026-2027 FUNDED BY SB 1: THE ROAD REPAIR AND ACCOUNTABILITY ACT OF 2017
WHEREAS, Senate Bill 1 (SB 1), the Road Repair and Accountability Act of 2017 (Chapter 5, Statutes of 2017) was enacted to address transportation funding shortfalls in California; and WHEREAS, SB 1 includes provisions for accountability and transparency, ensuring that residents are informed about the projects funded and completed each fiscal year; and WHEREAS, this is the tenth year that the Town is receiving SB 1 funds, enabling essential road maintenance and safety improvements; and
WHEREAS, the Town must approve by resolution a list of all projects to receive funding from the Road Maintenance and Rehabilitation Account (RMRA) by July 1, 2026, to remain eligible for SB 1 funds; and WHEREAS, the Town will receive an estimated $213,105 in RMRA funding in Fiscal Year 2026-27 from SB 1; and
WHEREAS, the Town Council has discussed and prioritized these projects in various Council meetings; and
WHEREAS, SB 1 funding will help improve pedestrian accessibility, safety, and road rehabilitation, reducing vehicle emissions and enhancing the overall transportation infrastructure.

NOW, THEREFORE IT IS HEREBY RESOLVED, ORDERED AND FOUND by the Town Council of the Town of Fairfax, State of California, as follows:

1. The foregoing recitals are true and correct.

2. The following list of projects planned to be funded with Road Maintenance and Rehabilitation Account revenues is approved:

Project NameDescription
Approximat
e Locations
Estimated
Useful Life
(Years)
Year of
Construction
General
Maintenance
General maintenance to include, but not limited to,
pothole patching, crack sealing, street signs, street
striping, and street sweeping. This project will
include Public Works Staffing, public works
equipment, road maintenance and rehab materials,
procurement of public works safety materials and
gear.

Town wide 1-5 Start 07/2026
Complete
06/2027

3. The Town Manager is authorized to do everything necessary and appropriate to prepare and Town of Fairfax
Resolution No.

Page 2 of 2 ends

submit the required documentation to the California Transportation Commission (CTC) for the Town's SB 1 project list and expenditures reports for FY 2026-27.

The foregoing Resolution was duly introduced and adopted at a meeting of the Town Council of the Town of Fairfax held in said Town on the 6th day of May 2026 by the following vote:

AYES:

NOES:

ABSENT:

ABSTAIN:
__________________________________

STEPHANIE HELLMAN
MAYOR
ATTEST
__________________________________

CHRISTINE FOSTER

DEPUTY TOWN CLERK