Project Description From To
Pavement
Area
(SF)
Pavement
Treatment
Anticipated
Start
(MM/YY)
Anticipated
Completion
(MM/YY)
Estimated
Useful Life
(Years)
Woolner Ave. Pennsylvania Ave.West End of Street345,330 Cape Seal Gregory St. Woolner Ave. W. Texas 58,440 Cape Seal
Park Ln. Gregory Ln. Cul-De-Sac 15,675 Multilayer Sealing Gateway Blvd. Travis Blvd. Alaska Ave. 242,560 Cape Seal Pennsylvania Ave.HWY 12 Illinois St. 547,156 Cape Seal
Brighton Dr. Pennsylvania Ave.Brighton Ct. 9,900 Cape Seal Alaska Ave. Pennsylvania Ave.End 54,000 Cape Seal
Webster St. Travis Blvd. Illinois St. 514,656 Cape Seal Auto Mall Pkwy Ledgewood CreekChadbourne Rd. 206,335 Cape Seal E. Tabor Ave. Clay Bank Rd. Olive Rd. 75,000 Slurry Seal Tolenas Rd. E. Tabor Ave. Tolenas Elementary
School N/A N/A
Dickson Hill Rd. Clay Bank Rd. 150,000 2.5" Asphalt Grind and Overlay 4/26 12/26 12-16
Clay Bank Rd. Portland Ave. 150,000 New Road
Construction 4/26 12/26 15-20
West Texas Street Complete Streets Project:

Pavement rehabilitation throughout the project corridor, widened sidewalks and a landscape buffers, bike boxes and curb extensions at twelve intersections, raised concrete medians and traffic signal modifications and new traffic signals, new street lighting and fiber optic communication along the project corridor. (Re-listed Project)
West Texas St. Pennsylvania
Avenue Beck Ave. 282,000 2.5" Asphalt Grind
and Overlay 05/25 06/26 25-30
Lopes Road Reconstruction:

Full pavement reconstruction due to landslide from heavy winter rains. (Re-listed Project)
Lopes Rd. 2,500' South of
Gold Hill Rd.
3,000' South of Gold
Hill Rd. 15,000 Reconstruction 07/25 06/26 15-20
City of Fairfield
FY 25/26 RMRA Project List June 2025 Street Name
04/26 12/26 25-30
East Tabor Avenue/Tolenas Road Safe Routes to School Gap Closure Project:

Improve pedestrian access by installing sidewalk over an at-grade railroad crossing at East Tabor Avenue and Railroad Avenue. The project will also widen the sidewalk along Tolenas Avenue between East Tabor Avenue and the Tolenas Elementary School. Constructing the sidewalk and bicycle lane on the north side of East Tabor Avenue will close the gap that currently exists across the railroad tracks. 2026 Pavement Maintenance Project:

Pavement resurfacing of approximately 2,059,000 square feet and ADA curb ramp replacements.
7-108/2604/26
Manual Campos Parkway Widening:

Widening Manual Campos Parkway from 2 to 4 lanes, and grind and overlay the existing pavement.

Manual Campos
Pkwy.

Attachment 3
NOTE: Included with each proposed project is the preparatory work to be completed in advance of the actual overlays and/or surface seals.

This work includes crack sealing and asphalt digouts. Work not related to pavement maintenance are not funded by RMRA.