Date Action
April 1, 2025 Council directs staff to proceed with Prop 218 April - May 2025 RFQ development
May 21, 2025 Release RFQ
June 17, 2025 RFQs due to City
June 18, 2025 - June 24, 2025 RFQ review panel independently review and score submittals June 25, 2025 RFQ review panel meets
June 26, 2025 - July 11, 2025 Consultant interviews (if needed) July 17, 2025 LOC dicusses RFQ results
August 2025 Consultant contract negotiations and Council approval September 2025 - February 2026 Develop Engineer's Report (Min. 6 months; consideration for holidays) February 2026 - February 2027 Community engagement w/Engineer's Report March 3, 2027 Notice of Intent
March 4, 2027 Mail notice and ballot package (NLT 45 days before public hearing) April 21, 2027 Public Hearing; Begin ballot tabulation
May 5, 2027 Announce ballot results; Form new districts June 2, 2027 Notice of Intent for districts that did not pass June 16, 2027 Public Hearing for districts that did not pass July 1, 2027 New assessment rates effective for FY 2027-2028 August 10, 2027 Tax rolls due to county
ATTACHMENT 2
PROPOSED MODIFIED TIMELINE
2027 LLMD PROPOSITION 218 BALLOTING TIMELINE FOR NEW ASSESSMENTS EFFECTIVE FY 2027-2028