Agenda Item No: K.8

AGENDA REPORT
DATE: November 18, 2025

TO: Mayor and Council

FROM: David Gassaway, City Manager

SUBJECT: Resolution 2025-224 PW Red Top Zone II Pump Station Acceptance

Accepting the Red Top Zone II Pump Station Improvements as Complete

Funding Source: N/A

Contact: Tom Martian, (707) 428-7478

RECOMMENDED ACTION
Adopt resolution.

STATEMENT OF ISSUE
Adoption of the resolution will formally accept the improvements for the Red Top Zone II Pump Station as complete.

DISCUSSION
Albert D. Seeno Construction Co. (Developer) has completed all the required improvements for the Red Top Zone II Pump Station (Zone II Pump Station) in accordance with the improvement agreement adopted by the City Council on May 17, 2022, by Res olution No. 2022 -92. The Developer designed and constructed a hydro pneumatic pump station to provide water service to the developments along Red Top Road.

Staff inspected the improvements and found them to be complete in accordance with City standards and the requirements of the improvement agreement. The final punch list was completed on September 26, 2025. The proposed resolution accepts the improvements as being complete, except for the obligation of the Developer to repair or reconstruct defective w ork for a period of one year after final acceptance.

FINANCIAL IMPACT
Acceptance of the public improvements by the council will obligate the City to maintain the Zone II Pump Station, related appurtenances, and facilities including o n-site storm infrastru cture,

masonry walls, automatic gate, and on -site lighting. Ongoing maintenance for the public improvements will be funded by the Water Utility Fund.

PUBLIC CONTACT/ADVISORY BODY RECOMMENDATION
N/A

ALTERNATIVE ACTION
If the council has any questions, acceptance may be delayed so that staff may provide the necessary additional information.

COORDINATED WITH
N/A

STAFF CONTACT
Tom Martian, Public Works Interim Construction Manager