Text extracted from the city's file for reading and search. Open the original on pub-fairfield.escribemeetings.com. That file is the official record.

Agenda Item No: K.5

AGENDA REPORT
DATE: December 2, 2025

TO: Mayor and Council

FROM: David Gassaway, City Manager

SUBJECT: Resolution 2025-238 PW Canon Station – Planning Area 4 Lake Park Landscape – Phase 2 Acceptance

Accepting the Improvement Agreement for the Canon Extension – Planning Area 4 Lake Park Landscape – Phase 2 as Complete

Funding Source: N/A

Contact: Tom Martian, (707) 428-7478

RECOMMENDED ACTION
Adopt resolution.

STATEMENT OF ISSUE
Adoption of the resolution will formally accept the improvements for the Canon Station – Planning Area 4 Lake Park Landscape – Phase 2 as complete.

DISCUSSION
One Lake Holding, LLC (Developer) has completed all the required improvements in accordance with the improvement agreement adopted by the City council on November 16, 202 1, by Resolution No. 202 1-278. The improvements around the lake consist of various amenities, including but not limited to landscaping, irrigation, benches, slides, and playground equipment.

The shade structures have been differed and to be completed by December 31, 2026, per the completion of Planning Area 5 Neighborhood H.

FINANCIAL IMPACT
Upon council acceptance, the ongoing maintenance of the landscaping and irrigation around the lake and various amenities, including but not limited to, benches, slides, playground and equipment will be funded by the Community Facilities District (CFD) 2018-1 and the Homeowners Association (HOA).

PUBLIC CONTACT/ADVISORY BODY RECOMMENDATION
N/A

ALTERNATIVE ACTION
If the council has any questions regarding the request, approval may be postponed until the questions are addressed.

COORDINATED WITH
N/A

STAFF CONTACT
Tom Martian, Public Works Interim Construction Manager