AMENDMENT NO. 8 TO THE AGREEMENT FOR CONSULTING SERVICES (DESIGN) FOR THE
IMPLEMENTATION PLAN OF THE CENTRAL FAIRFIELD REVITALIZATION AND LINEAR PARK
IMRPOVEMENTS BETWEEN THE CITY OF FAIRFIELD AND CALLANDER ASSOCIATES On August 21, 2018, the City of Fairfield, a municipal corporation, hereinafter referred to as “CITY” and CALLANDER ASSOCIATES, hereinafter referred to as “CONSULTANT”, entered into an agreement for consulting services for Professional Consulting Services for the I mplementation Plan for the Central Fairfield Revitalization and Linear Park Improvement Project, also known as the 2030 North Texas Recreation Center and Robbieburr Berger Park, hereinafter referred to as the “PROJECT”.
Based upon the need for additional consulting work outside the scope of the agreement, the CITY and CONSULTANT do hereby agree to amend the existing AGREEMENT for CONSULTING SERRVICES as follows:
WITNESSETH:
WHEREAS, CITY desires to obtain additional design services during construction for PROJECT; and WHEREAS, CONSULTANT has provided design services during construction for the PROJECT; and WHEREAS, continued services are necessary to address requests for information, submittal reviews, design clarifications, field conditions, project closeout activities, and other design-related matters arising during construction of the PROJECT; and
WHEREAS, CITY has requested CONSULTANT provide these additional design services during construction, as more particularly described in the scope of services attached to Amendment No. 8; and
WHEREAS, C ONSULTANT
is w illing an d q ualified t o p rovide t he ad ditional d esign s ervices d uring construction for the PROJECT.
The AGREEMENT is amended as follows:
1. Section 1, SERVICES of the AGREEMENT, shall be amended to include Exhibit “AMENDMENT #8 - REV” to this Amendment.
2. Section 2, PAYMENT of the AGREEMENT, shall be amended as follows a) The total contract price for services rendered by the CONSULTANT shall be increased by TWO HUNDRED SIXTY-ONE THOUSAND SIX HUNDRED AND FORTY- SIXTY DOLLARS ($261,646) for a total contract amount not to exceed TWO
MILLION FIVE HUNDRED AND SEVENTY-SEVEN THOUSAND ONE HUNDRED AND FIFTY-TWO DOLLARS ( $2,577,152)
2 Revised September 2024
In Witness whereof, the parties, through their authorized representatives, have affixed their signature.
C
ITY OF FAIRFIELD
a municipal corporation (CITY)
B
y
David Gassaway, City Manager
C
ONSULTANT
B
y
CALLANDER ASSOCIATES
12150 TRIBUTARY POINT DRIVE, SUITE 140
GOLD RIVER, CA 95670
w
ww.callanderassociates.com
BURLINGAME GOLD RIVER RENO SAN JOSE
1633 Bayshore Highway,
Suite 133
12150 Tributary Point Drive,
Suite 140
275 Hill St,
Suite 260
2025 Gateway Place,
Suite 285
Burlingame, CA 94010 Gold River, CA 95670 Reno, NV 89501 San Jose, CA 95110 650.375.1313 916.985.4366 775.787.2828 408.275.0565
Recreate
Educate
Live+Work
Connect
Sustain Via Email
A
ugust 26, 2026
AMENDMENT #8-REV
TO: Ryan Panganiban
City of Fairfield
r [email protected]
RE
: LINEAR PARK- NODE 4A CSI 5-YEAR IMP. PLAN/ Construction Administration Services T
he following additional services will be provided on this project in accordance with our agreement dated August 30, 2018, and are considered an amendment thereto:
Scope
This amendment is for additional consultant fees for Callander Associates (CALA) and ou r subconsultant team to continue providing coordination and support for the duration of the project’s construction. This amendment describes what contributed to the depletion of the original construction support budget and includes time for continued c oordination and preparation of additional construction administration tasks for the duration of the project.
Anticipated completion of the project is Fall 2026, which is longer than the 240 working days anticipated for the project (March 2025 start date).
The project is now anticipated to continue through October 2026. The p roposal reflects the current construction and closeout schedule, including anticipated substantial completion, punch-list work, record documents, warranty documentation, and final completion.
Our team’s construction budget was depleted in November 2025 and in order to provide continued uninterrupted service to the City with the understanding that we would be reimbursed for our additional time . Below are some of the contributing factors that depleted the construction administration allowance and why the request is being made.
1. Additional Construction Review Onsite: The City Construction Management team requested additional on-site support from the consultant team. This was an increase in the number of site visits originally anticipated due to an extended construction schedule and the quality control issues encountered with construction. (ongoing)
2. Additional Meetings : Additional weekly OAC meetings by CALA and Group 4 Architecture (Group 4) due to the schedule extension. (Nov. 2025- ongoing)
3. Sewer Line: During the design phase, CALA coordinated with the City on their water main project in N. Texas Street to identify the location of a new sewer stub to the site.
The information coordinated was included in the construction documents and permitted plan set reviewed and approved by the City. During construction, the consultant team was made aware that the location of the stub installed was in a different location than coordinated. This led to a significant redesign of the site's Additional Services Authorization #8
RE: Linear Park -Node 4A/ Construction Administration
Feb. 23rd,2026 Aug 10th, 2026
18057_MEM_FeeAmendment8_CAServices-REV.doc
© copyrighted 2026 Callander Associates
Landscape Architecture, Inc.
sewer and storm drain system, which was rerouted to the new location. (April-May 2025)
a. Includes redesign of sewer inverts, storm drain lines, grading, etc. b. Coordination of lines connections and conflicts with building plans c. Architectural time spent on coordinating the point of connection change. (Does not include time addressing redundant sewer lines inside building and elimination of stubs no longer necessary)
4. Trail Connection Elimination: Included the c oordination and revision to the plans to disconnect the trail connection from the project. Value added change since the connection would have needed to be demolished due to new design direction of the adjacent linear park trail. (April 2025)
5. Unknown Utility Locations: Wall shift at the northern edge of the project based on location of storm drain line found in the field. Original City records did not have correct information on the location of the line. (May-June 2025)
6. Playground Surfacing: Research on sealant for playground surfacing as a result of issues found at other park site. (August)
Below is a summary of some construction administration items that required significantly more support from the design team than initially expected, and this support has been necessary for a longer duration than originally planned. This i ncludes additional requests by City to review resubmittals, along with Requests for Information (RFIs), Time Impact Analysis (TIAs) and review of change order items. Below is a list of some of those items.
1. Trash Enclosure: Not constructed per plans, resulting in a request by the contractor to review if it could remain. Required analysis by design team on grading, layout, structure and function resulting in a solution that allowed the contractor to keep some of the structure remaining. (August-September 2025)
7. Signage: Ongoing coordination of the site and building s ignage changes due to new building name (Robbieburr Berger) and additional signage for the First 5 tenant included coordination of the appropriate location of the sign, analysis of various options and revisions to the plans and details. Also included new set of submittal reviews related to this on both site and building plans. (ongoing)
8. Roof Reframing: Roof redesign due to contractor using a truss joist manufacturer different from basis of design manufacturer. The contractor-selected manufacturer could not provide a product that performed the same as the basis of design joists in a couple of key details, which was not discovered until after the roof had been partially framed and the contractor requested a redesign. The contractor's requested redesign approach would have created significant architectural ripple effects with the street elevation of the building that were unacceptable. A redesign to add structural steel to the roof by the structural engineer was required to maintain the original design. (May- Oct. 2025)
9. Substitution Requests:
a. Playground equipment substitution request, including additional meetings, recommendation emails, and additional submittal reviews. (April-Aug. 2025) Additional Services Authorization #8
RE: Linear Park -Node 4A/ Construction Administration
Feb. 23rd,2026 Aug 10th, 2026
18057_MEM_FeeAmendment8_CAServices-REV.doc
© copyrighted 2026 Callander Associates
Landscape Architecture, Inc.
TOTAL
1.0 188,414.00 $
2.0 73,232.00 $
TOTAL 261,646.00 $
6,545.00 $
AMENDMENT NO. 8 SUMMARY
CALA GROUP 4 BKF
Construction Support -Nov.2025-July2026 (lump sum) 55,869.00 $ 126,000.00 $ 29,982.00 $ 30,000.00 $ 13,250.00 $
19,795.00 $
Construction Support -3mo.(hrly allowance)
85,851.00 $ 156,000.00 $
b. Fitness equipment substitution request, including additional meetings, recommendation emails, and additional submittal reviews. (April-Sept. 2025) c. Shade shelter substitution requests, including additional meetings, recommendation emails, and multiple submittal reviews. (July 2025-Jan. 2026) d. Booster Pump: RFI to coordinate substituted Booster Pump with potential space constraints. (Oct. 2025- Jan. 2026)
e. Light Pole Standards: Help City research potential substitution for light poles as a result of delays occurring at other park site. (April-May 2025) f. Sectional Overhead Doors: Multiple potential substitutions discussed with separate meetings because the contractor wanted to use an alternate manufacturer. In the end, the alternate manufacturer could not meet the size and construction detail intent shown in the contract documents. (April - Nov. 2025)
10. TPO Roof (RFI 233): This includes review of contractor’s work, City’s requests for proposed solutions, additional coordination and site reviews to observe construction. (January - July 2026)
• For the remaining 3 months of work ( August through October 2026) the consultant team anticipates the following for project completion and closeout of the project:
o The CALA team anticipates approximately $9,994/mo.
o The Civil team (BKF) anticipates approximately $4,416/mo. o The Architect team (Group 4) anticipates approximately $10,000/mo.
COMPENSATION SUMMARY
Schedule
Callander Associates will continue with the above service upon receipt of a signed copy of this authorization.
Signatures
Callander Associates Landscape
Architecture, Inc.
Agreed and authorized to proceed for:
City of Fairfield
Melissa Ruth, PLA, ASLA, Principal
Signature date Name & Title
Attachment: Standard Schedule of Compensation dated 202 6GR BKF 2026 Rate Sheet
Group 4 2026 Rate Sheet
Notice: Landscape architects are licensed by the State of California. Terms and conditions are sub ject to change after ninety days.